Next Article in Journal
An Approach to Determine the Weibull Parameters for Wind Energy Analysis: The Case of Galicia (Spain)
Next Article in Special Issue
Fast Cut Back Thermal Power Plant Load Rejection and Black Start Field Test Analysis
Previous Article in Journal / Special Issue
A Wide-Area Measurement Systems-Based Adaptive Strategy for Controlled Islanding in Bulk Power Systems
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Fault Detection and Location by Static Switches in Microgrids Using Wavelet Transform and Adaptive Network-Based Fuzzy Inference System

1
Department of Electrical Engineering, Chung Yuan Christian University, 200 Chung Pei Road, Chung Li 320, Taiwan
2
Division of Smart Grid, Institute of Nuclear Energy Research, Longtan 32546, Taiwan
*
Author to whom correspondence should be addressed.
Energies 2014, 7(4), 2658-2675; https://doi.org/10.3390/en7042658
Submission received: 7 February 2014 / Revised: 4 April 2014 / Accepted: 9 April 2014 / Published: 23 April 2014
(This article belongs to the Special Issue Smart Grids: The Electrical Power Network and Communication System)

Abstract

: Microgrids are a highly efficient means of embedding distributed generation sources in a power system. However, if a fault occurs inside or outside the microgrid, the microgrid should be immediately disconnected from the main grid using a static switch installed at the secondary side of the main transformer near the point of common coupling (PCC). The static switch should have a reliable module implemented in a chip to detect/locate the fault and activate the breaker to open the circuit immediately. This paper proposes a novel approach to design this module in a static switch using the discrete wavelet transform (DWT) and adaptive network-based fuzzy inference system (ANFIS). The wavelet coefficient of the fault voltage and the inference results of ANFIS with the wavelet energy of the fault current at the secondary side of the main transformer determine the control action (open or close) of a static switch. The ANFIS identifies the faulty zones inside or outside the microgrid. The proposed method is applied to the first outdoor microgrid test bed in Taiwan, with a generation capacity of 360.5 kW. This microgrid test bed is studied using the real-time simulator eMegaSim developed by Opal-RT Technology Inc. (Montreal, QC, Canada). The proposed method based on DWT and ANFIS is implemented in a field programmable gate array (FPGA) by using the Xilinx System Generator. Simulation results reveal that the proposed method is efficient and applicable in the real-time control environment of a power system.

1. Introduction

The Kyoto Protocol mandates that industrialized countries reduce their collective greenhouse gas emissions in 2012 to 5.2% below the levels in 1990 [1]. Later, the Copenhagen Accord required the reduction of global emissions in order to limit the increase in global temperatures to a maximum of 2 °C [2]. Renewable energy plays a major role in providing distributed electricity resources in power systems to achieve a low carbon environment. However, the penetration of renewable energies in a distribution system causes many operational problems (such as protective coordination). To avoid this problem, the concept of the microgrid was developed to include these renewable energies [3,4]. Owing to the intermittence of the generation from renewable energies (such as wind-turbine and solar power), the reliability of the microgrid should be enhanced using other power sources (e.g., gas turbines and batteries).

Many works have developed methods to implement the microgrid test bed. The Consortium for Electric Reliability Technology Solutions (CERTS) microgrid testbed was developed in the early 1990s [3], and an assessment report for this testbed was published recently [4]. The important concepts developed by CERTS include peer-to-peer and plug-and-play devices embedded in the microgrid. Numerous new issues, which were not raised by the conventional large power systems, have emerged [5,6]. Ahn and Peng [5] presented a decentralized control architecture for microgrids along with a simulation environment appropriate for on-going investigations into real-time decision-making. Lim et al. [6] presented a distributed load-shedding system for agent-based autonomous operation of a microgrid. The total amount of load to be shed is calculated to maintain frequency above minimum permissible frequency for the maximum anticipated overload.

A new issue associated with static switches in microgrids has emerged recently. A static switch is a fast electronic switch located at the secondary side of the main transformer near the point of common coupling (PCC). When a fault occurs inside or outside a microgrid, the static switch should immediately disconnect the microgrid from the power system of the utility [3,4]. Klapp and Vollkommer [7] developed a silicon controlled rectifier (SCR)-based static switch, which incorporates a high level system control scheme to comply with IEEE Standard 1547. Nikkhajoei and Lasseter [8] suggested that a static switch should activate the breaker in 1/2–2 cycles. Kroposki et al. [9] developed the concept of the circuit-breaker-based (20–100 ms), SCR-based (1/2–1 cycle) and insulated-gate bipolar transistor (IGBT)-based (100 μs) switches. A digital signal processor (DSP) was designed to perform functions of relay, communication, monitoring and diagnosis [9]. Chan et al. [10] designed a static switch that has a 16-bit DSP chip-based controller and an SCR-based switch (JK3PTS-48850). Thresholds of overcurrent, high/low-voltage and high/low-frequency are specified in the DSP chip for detecting a fault in either the main grid or the microgrid. Once the fault is detected, the static switch is opened in 10 ms. A complex programmable logic device (CPLD)-based module circuit board with a communication circuit interface using RS-485/CAN2.0B/IEEE802.3 Ethernet was developed to transmit operating data [10].

This work presents a novel method for a static switch to detect/locate a fault in the first outdoor microgrid test bed in Taiwan. The generation capacity of this microgrid, including gas-turbine generators, wind-turbine generators (WTG), energy storage and high concentration photovoltaic (PV), is 360.5 kW. Numerous research projects have been undertaken to investigate key technologies, including power converters, wind turbines, PV modules, protection schemes, and monitoring systems. Preliminary studies of the operating mode, motor starting and voltage fluctuation have been published [11,12]. In contrast to [710], this work focuses mainly on the detection/location module of a static switch. Sensitive signal processing is necessary since the fault current originating from power converter-based distributed generation is very small and the fault voltage at the PCC is not significant [7]. Therefore, this work analyzes the fault voltage and current at the secondary side of the main transformer near the PCC by using multi-resolution analysis (MRA) of the discrete wavelet transform (DWT). Additionally, the faulty zone is identified using the adaptive network-based fuzzy inference system (ANFIS), based on the wavelet energy of the fault current. The proposed method that uses the voltage wavelet coefficient and the ANFIS output determines whether the electronic breaker should be opened or not. Moreover, this microgrid test bed is studied using the real-time simulator, eMegaSim, which was developed by Opal-RT Technology Inc. (Montreal, QC, Canada) [13]. The detection module is implemented in a field programmable gate array (FPGA) using the Xilinx System Generator.

The rest of this paper is organized as follows: Section 2 briefly introduces the microgrid and presents the assumptions in the studied problem; Section 3 introduces the proposed method based on DWT, ANFIS and Opal-RT; Section 4 summarizes the simulation results; and Section 5 draws conclusions and offers recommendations for future research.

2. Studied Microgrid and Assumptions

2.1. Microgrid Testbed

The studied microgrid has 11 AC buses. Figure 1 illustrates the one-line diagram of this microgrid with rectifiers, buck/boost converters, and inverters, which will be fully considered in the transient/dynamic simulation. The microgrid testbed (380 V) is planned to cover three zones:

  • 2011: Buses 1–6 are constructed in Zone 1, which includes a 60 kW load, 65 kW gas turbine, 100 kW (60 kW h) battery and 31.5 kW PV;

  • 2012: Buses 7–10 are located in Zone 2, which mainly consists of a 90 kW load, 25 and 4 kW wind turbines, and 10 kW PV;

  • 2013: Bus 11 is located in Zone 3, which comprises a 60 kW PV and a 65-kW gas turbine.

Detailed models of components used in the microgrid are given in the appendix [11,12,14].

2.2. Assumptions

In order to study the problem, the following assumptions are made:

(a)

The voltage and current at the secondary side of the main transformer near the PCC are available. PT and CT are generally installed at the secondary side of the main transformer. The levels of fault voltage and current are reduced for the further usage of FPGA chip.

(b)

The time delay in the electronic switch is ignored in the simulation. If an IGBT-based switch is used, opening the circuit takes about 100 μs [9]. The proposed method takes advantage of 1/4 of the cycle of the fault voltage and current for further signal processing. One-fourth of the cycle is used because the voltage/current is most likely to experience a large variation of the instantaneous values in a 1/4 of the cycle.

(c)

The latency of FPGA is ignored in the simulation. According to the results herein, the latency of FPGA is several nano seconds, which is significantly shorter than that of a DSP chip (a latency of the order of milli seconds).

(d)

The faulty zone is disconnected by the zonal isolating switch if a fault occurs in the microgrid.

(e)

The fault and the microgrid are balanced. Neither the single-phase grounded fault nor the phase-to-phase fault is discussed herein. Nine hundred and ninety-four balanced scenarios are studied herein using MATLAB/Simulink (see Section 4.1). Almost 3000 scenarios will be studied in case imbalance is concerned. The detection logic architecture is still the same in case of imbalance.

3. Proposed Method

3.1. Outline

Fault detection and location problems for both distribution and transmission systems have been extensively studied [1518]. The harmonic impedance [15], wavelet singular entropy [16], automated graph [17], and three different structures of neural networks incorporating with the negative current [18] were employed in these methods. However, since the inverter-based power converter in distributed generations is used, the fault current is not large and may not be easily detected if a fault occurs inside a microgrid. ANFIS, DWT and FPGA are used herein to cope with the above dilemma for the following reasons:

(1)

The small disturbance caused by faults inside a microgrid is detected using DWT because DWT is a transient-sensitive means of processing a signal. Both the wavelet coefficient of the transient voltage and the sum of squared wavelet coefficients (called wavelet energy herein) of the fault current are utilized to enhance the proposed method. The proposed method avoids negative sequence of components [18], which may be caused by unbalanced loads rather than balanced faults, and avoids the use of fault currents only [15], which may lead to a delay in the detection logic.

(2)

Fuzzy reasoning provides a high-level linguistic inference engine that can tolerate uncertainty but lacks learning capability. An artificial neural network, by contrast, is like a black box but it can learn and tolerate imprecision. ANFIS is an intelligent system that integrates fuzzy reasoning with a neural network by considering their advantages. ANFIS builds a hybrid intelligent system that is capable of reasoning and learning in an uncertain and imprecise environment. However, three different neural networks, which are not subject to uncertainty and lack reasoning capability, were developed in [18].

(3)

The use of double detection/location logics (wavelet coefficient of transient voltage and ANFIS plus wavelet energy of transient current) enhances the reliability of the proposed method. The proposed method, therefore, is able to use only the transient voltage and current near PCC to detect and locate a fault. This capability is essential in case the plug-and-play and peer-to-peer implementations are concerned and the decentralized control is applied. However, references [1518] used multiple sensors in the power systems.

(4)

The microgrid test bed is studied using the real-time simulator eMegaSim developed by Opal-RT Technology Inc. [13]. The detection/location module established by the DWT and ANFIS is implemented in an FPGA using the Xilinx System Generator. Other studies in [16,17] are not suitable for real-time applications.

3.2. DWT

A signal can be represented as a sum of wavelets and scale functions with coefficients at different time shifts and scales (frequencies) using DWT. DWT is able to extract the features of transient signals by decomposing signal components overlapping in both time and frequency [15].

According to DWT, a time-varying function (signal) f(t) ∈ L2(R) can be expressed in terms of ϕ(t) and φ(t) as follows:

f ( t ) = k c 0 ( k ) φ ( t k ) + k j = 1 d j ( k ) 2 j / 2 φ ( 2 j t k ) = k c j 0 ( k ) 2 j 0 / 2 φ ( 2 j 0 t k ) + k j = j 0 d j ( k ) 2 j / 2 φ ( 2 j t k )
Where ϕ(t), φ(t), c0 and dj represent the scaling function, wavelet function, scaling (coarse) coefficient at Scale 0, and wavelet (detailed) coefficient at scale j, respectively. The symbol k refers to the translation coefficient, which localizes (detects) a signal in time. The scales j = 1, 2, … denote the different (high to low) frequency bands. The symbol j0 could be any integer. The translated and scaled (dilated) version of the wavelet, φ(2j tk) constructs a time-frequency picture of the decomposed signal. Daubechies 4 is used as a mother wavelet herein.

The small scales represent high-frequency ranges of a transient signal. Thus, the wavelet coefficient (dj) of a fault voltage (i.e., if f(t) is the fault voltage) is used as a feature to detect the occurrence of a transient caused by a fault.

On the other hand, the Parseval's Theorem [19] asserts that:

| f ( t ) | 2 d t = k | c j 0 ( k ) | 2 + k j = 1 | d j ( k ) | 2

The second term of Equation (2) here denotes the “wavelet energy” of the fault current (i.e., if f(t) denotes the fault current). In particular, “wavelet energies”, at scales j = 1, 2 and 3, serve as the inputs (i.e., WI(1), WI(2), and WI(3)) of ANFIS to identify the faulty zone.

In summary, this work utilizes the wavelet coefficients of the fault voltage and the sum of the squared wavelet coefficients of the fault current to activate the electronic switch to open once a fault occurs inside or outside the microgrid. All wavelet coefficients are computed using 1/4 of a cycle of sampled points of both the voltage and current. Traditional effective (rms) values of the fault voltage and current are not suitable to be indicators for detecting the fault occurrence because the faults may occur at zero crossings. However, the DWT is able to detect changes of instantaneous voltage/current by using the detailed coefficients obtained at their corresponding scales (j = 1, 2, 3…) even though the fault occurs at zero crossings.

Some mother wavelets are available in the wavelet theory [19]: the Haar wavelet is defined in a finite bounded set but is discontinuous. The Shannon wavelet is smooth and decays at infinity very slowly; it is not compactly supported, either. The linear spline wavelet is continuous, but has infinite support. Thus, these mother wavelets are not suitable to study the power system transients. Compared with these wavelets, the Daubechies 4 belongs to a class of compactly supported, continuous, and orthonormal basis-generating wavelets. The Daubechies 4 was also used in [20,21].

3.3. ANFIS

This subsection describes the use of three inputs (i.e., WI(1), WI(2), and WI(3)) to demonstrate the feasibility of using ANFIS to identify the faulty zone, where WI(1), WI(2) and WI(3) denote the “wavelet energies” of the fault current at Scales 1, 2 and 3, respectively. A typical fuzzy rule of ANFIS can be expressed as follows:

If WI ( 1 ) is A 1 and WI ( 2 ) is B 1 and WI ( 3 ) is C 1 , then f i = k i 0 + k i 1 W I ( 1 ) + k i 2 W I ( 2 ) + k i 3 W I ( 3 )
where A1, B1 and C1 are the membership functions for the wavelet energies. The antecedent part of the fuzzy rules is related to inputs WI(1), WI(2), and WI(3). The consequent part of the fuzzy rules is a linear combination of WI(1), WI(2), and WI(3). fi is a real function. In this paper, A1–A5, B1–B5, and C1–C5 are considered as possible membership functions of WI(1), WI(2), and WI(3), respectively. For example, A1, A2, A3, A4, and A5 signify “very small”, “small”, “normal”, “large” and “very large” memberships of WI(1), respectively. Combining A1–A5, B1–B5, and C1–C5 yields 125 (i.e., 53) fuzzy rules. If A1–A5, B1–B5, and C1–C5 and fi are known, then the output can be determined. However, A1–A5, B1–B5, and C1–C5 and fi are unknowns, which must be determined by training the ANFIS using various scenario data. ANFIS is an effective approach to transforming the fuzzy rules (e.g., Equation (3)) into a neural network, including membership functions. Figure 2 shows the equivalent ANFIS for these 125 fuzzy rules.

The structure of ANFIS can be explained as follows: the first layer in Figure 2 is the input layer; the second layer includes the membership functions, which are the same as the activation functions in the neural network, of the fuzzy rules. Each membership (activation) function can be expressed as follows:

y i ( 2 ) = 1 1 + ( x i a i c i ) 2 b i
where ai, bi and ci represent the center, width and slope of input values, respectively. The superscript “(2)” in Equation (4) denotes the second layer. The third layer performs the rules and the ∏i operator applies the linguistic “and” in the antecedent part of the fuzzy rules. Normalization (denoted as “Ni”) is implemented in the fourth layer. The fifth layer deals with defuzzification as follows:
y i ( 5 ) = μ ¯ i × f i ( WI ( 1 ) , WI ( 2 ) , WI ( 3 ) )
Where μ̄i refers to the normalized value of the output (consequence) of the i-th fuzzy rule in the fourth layer. Finally, the value of each output neuron can be integrated from 125 fuzzy rules with proper values of μ̄i in the sixth layer:
i = 1 125 μ ¯ i × f i ( WI ( 1 ) , WI ( 2 ) , WI ( 3 ) )

In the training stage for developing the proposed ANFIS, the unknowns ai, bi and ci and the coefficients ki0, ki1, ki2 and ki3 of fi are determined by training the neural network using input/output pairs (WI(1), WI(2), WI(3); binary bit) where the binary bit denotes 1 (faulted) or 0 (unfaulted). In the testing stage for developing the proposed ANFIS, the output of the ANFIS is evaluated using Equation (6). If the value of Equation (6) exceeds 0.5, then a fault occurs; otherwise, no fault occurs. Like other supervised neural networks, the ANFIS needs to be trained again if the topology of the microgrid system is changed.

3.4. Module for Fault Detection and Location

The occurrence of a fault inside/outside the microgrid is detected and located using two logics:

First, the occurrence of a fault is detected using the MRA of DWT implemented by FPGA. Wavelet coefficients at Scale 2 are the most appropriate for this role (see Figure 3 below). In this work, a cycle includes 256 sampled points. 64 sampled points (1/4 of the cycle) were used for implementation (see Assumption (b) in Section 2.2).

Second, because the voltage transient may be related to other disturbance (e.g., capacitor switching), the wavelet energies that are calculated using wavelet coefficients of 1/4 cycle of the fault current at Scales 1, 2 and 3 are also used to identify faulty zone by ANFIS.

If the values of both logics are unities, then the electronic switch is activated to open the circuit. Figure 4 shows the overall architecture of these two logics. ANFIS1–ANFIS4 were trained individually with different data sets. For example, only the data sets related to the scenarios with faults occurring in Zone 1 were used to train ANFIS2. If identifying the fault locations is not needed, then only one ANFIS is required.

3.5. Real-Time Digital Simulation and FPGA Implementation

Real-time simulation was conducted in this work using Opal-RT eMegaSim. eMegaSim, which is composed of software (RT-Lab, Montreal, QC, Canada) and hardware (target computer; Intel i7 965 Extrem), can be integrated entirely with the MATLAB\Simulink software. Parallel computation is implemented in Opal-RT-Redhat OS. In a host PC, the user can perform preliminary design and integrate the above models constructed in the studied case in the Simulink environment (i.e., SimPowerSystem Blockset). The developed Simulink-based case can then be moved to the Opal-RT-Redhat OS to perform parallel computation in the target computer (eMegaSim).

In this work, the Xilinx FPGA chip and the Xilinx System Generator (XSG) are used to implement the proposed method. The XSG toolbox can build a system model to be a hardware circuit in a Matlab/Simulink environment. Figure 5 illustrates how wavelet coefficients d1, d2 and d3 are calculated by wavelet high-pass (G) and low pass (H) filters as well as down sampling 2 using the MRA of DWT in the XSG environment. The symbol “C0” denotes the original signal.

The proposed ANFIS was trained using the MATLAB ANFIS Editor GUI. Following convergence, ai, bi and ci and the coefficients ki0, ki1, ki2 and ki3 of fi can be determined and are used in the XSG environment to design the FPGA chip.

4. Test Results

The performance of the proposed method is evaluated using the microgrid described in Section 2. This microgrid test bed is described in detail in [11,12].

4.1. Performance of Proposed Method

This section uses various wind speeds (11, 10, 9, 8 and 0 m/s), irradiations (1000, 800, 600, 400 and 0 W/m2), load levels (150 kW multiplied by 100%, 85% and 70%) and short circuit capacities (1714.2 MV A multiplied by 100% and 70%) at PCC. The minimum generation of a gas-turbine generator is 37 kW. The power generation in the microgrid is not allowed to be injected into the main grid. Thus, there are a total of 142 base cases, which include normal and extreme meteorological limits as well as possible operating conditions. The faults are assumed to occur individually at Buses 1, 4–6, or 9–11. Considering these faults yields 994 scenarios: the results of simulating 663 and 331 scenarios are used for training and testing ANFIS, respectively. In order to enhance the proposed method, the 663 training scenarios are selected at random. The simulations are conducted using the MATLAB/Simulink SymPowerSystem.

Figure 3 shows the wavelet coefficients of voltages at PCC determined from the scenarios in which individual faults occur at Buses 1 and 5 (i.e., outside and inside the microgrid). Figure 3 does not consider the action of static switch because the effect of wavelet coefficients is addressed. Duration of the fault is 2 s in the simulation (t = 2–4 s); however, only 1/4 of the first cycle is used in the proposed method. Obviously, d2 is the most suitable wavelet coefficient for detecting the occurrence of a fault transient. Specifically, a sufficiently large d2 occurs at t = 2 s compared with other d2. However, the value of d1 at t = 2 s is not sufficiently large and values of d3 oscillate after t = 2 s. These imply d1 and d3 are inappropriate for the usage of detection. Any transient and noise may be included in the measured signals. However, the DWT can still identify the most appropriate scale (j = 2 herein) because different scales (j = 1, 2, 3) cover different frequency bands.

Unlike traditional methods in which multiple sensors are used in the power systems, the proposed method only uses the transient voltages and currents near the PCC. Figure 6 shows the obtained 15 corresponding membership functions.

The accuracy of the proposed ANFIS is still promising although only signals near the PCC are used, as shown in Table 1. Besides, this table also shows that the proposed method is able to locate the faults in different areas (main grid and Zones 1–3) even though the fault currents are small due to the current limits that are imposed by the inverters of the distributed generators.

In total, 452,172 slices, 812,007 FFs (flip-flops), 52 BRAMs (block RAM, kB) and 651,915 LUTs (look-up table, 16 × 1 RAM) are required in the FPGA for the proposed ANFIS. Moreover, DWT requires 920 slices, 80 FFs, 0 BRAMs and 1200 LUTs in the FPGA.

4.2. Scenario of Islanding Microgrid from Grid-Tied Mode

This subsection discusses a three-phase balanced fault occurring at Bus 4 at 2 s. Suppose that the wind speed, irradiation and system load are 8 m/s (corresponding to 11 and 1.5 kW from the two wind turbines at Bus 10), 600 W/m2 (corresponding to 17, 6 and 30 kW at Buses 6, 10 and 11) and 150 kW, respectively. After 1/4 of the cycle, the proposed method activates the static switch at PCC and the microgrid becomes islanded. Meanwhile, the following actions are carried out according to the assumptions described in Section 2:

(a)

Disconnect all loads, the gas-turbine generator, PV and the energy storage at Bus 4.

(b)

The gas-turbine generator at bus 11 becomes the master generation source with the V/f control. The other distributed generations are maintained in their P/Q mode.

Figure 7 illustrates the system responses including kW generations for different distributed generations, voltage and frequency. The real power generation of a gas-turbine generator at Bus 5 (P/Q mode) becomes zero after disconnection. Bus 11 increases its generation from 37 kW (P/Q mode) to 45 kW (V/f mode). This figure reveals that the lowest voltage is close to 325 V (0.86 p.u.) and the lowest frequency is 59.8 Hz during the fault. Additionally, each DG is operated individually with the same real power generation before and after the fault in the steady state due to their P/Q mode except for the gas-turbine generator at bus 11 (for which the P/Q mode is switched to V/f mode).

The time step is 1 μs in the above simulation. The simulation is run for 4 s. Table 2 lists different approaches to perform the simulations. The ATX motherboard of Opal-RT eMegaSim OP5600 has 12 processor cores in a single CPU. The studied microgrid is decomposed into 11 cores. One of the 12 cores is used to coordinate all computations in the other 11 cores. According to Table 2, 12 s are required to simulate 4 s using Opal-RT eMegaSim. This required time can be reduced by using more cores. The used PC in Table 2 has an Intel Xeon Processor (X3440 2.53 GHz) and 4.0 G RAM.

5. Conclusions

This work presents a novel method for designing the fault detection/location module of a static switch in a microgrid. The contributions of the proposed method are summarized as follows:

  • Both the wavelet coefficient of fault voltage and the “wavelet energy” of fault current incorporating with ANFIS are utilized. The small fault current from the inverter-based distributed generations can therefore be effectively and reliably detected and located.

  • Only the transient voltage and current near the PCC are utilized. No complicated communication system and other sensors at other buses inside the microgrid are required. This may enable peer-to-peer and plug-and-play to be realized in the microgrid.

  • The proposed ANFIS is capable of reasoning and learning to detect/locate a fault inside or outside the microgrid. Fifteen membership functions for three “wavelet energies” are evaluated by training a six-layered ANFIS.

  • Not only is the simulation performed, the detection/location module is also implemented using the Xilinx FPGA chip. The accuracy of the proposed method, applied to the studied problem, is favorable. The performance of the designed FPGA indicates that the proposed method is highly promising for applications in a real-time environment.

Future work will consider imbalanced faults and resynchronization between the main grid and the islanded microgrid.

Acknowledgments

The authors gratefully acknowledge the contributions of Robert H. Lasseter at University of Wisconsin at Madison and Dave Klapp, Dolan Technology Center, American Electric Power for their comments on designing/operating the microgrid test bed. The authors would like thank the financial support from the Institute of Nuclear Energy Research under the Grant NL1020402.

Conflicts of Interest

The authors declare no conflict of interest.

Appendix

This appendix provides the model of components used in the microgrid for studies.

A1. High Concentration PV (HCPV) Module

The characteristics of HCPV implemented with the III-V family (GaAs) are measured and tested according to IEC 62108. Each HCPV panel (1.5 kW or 5 kW) incorporates an inverter to perform maximum power point tracking (MPPT). Figure A1 shows the model of the HCPV panel with inputs 25 (temperature in °C) and 1000 (irradiation in W/m2). HCPV is modeled with a controlled current source. MPPT is applied to the DC/DC converter.

Figure A1. Model of high concentration PV (HCPV) panel and its power converters with maximum power point tracking (MPPT).
Figure A1. Model of high concentration PV (HCPV) panel and its power converters with maximum power point tracking (MPPT).
Energies 07 02658fa1 1024

A2. Wind Turbine

The specifications of WTG adhere to the IEC 61400-1 Class-1A. Its essential technologies comprise active turbine sliding control, pitch control of the blade, intelligent stalling control and MPPT-based power converter. Figure A2 illustrates the control structure of a 25 kW WTG. The generators are permanent magnetic synchronous machines (PMSM). MPPT is implemented in the “wind turbine” block with inputs of wind speed (m/s) and generator speed (rad/s or p.u.). The output of PMSM is connected to a rectifier (thyrister converter), which is controlled by a synchronized six-pulse generator and then cascaded to an inverter.

Figure A2. Control structure of 25-kW wind-turbine generators (WTG).
Figure A2. Control structure of 25-kW wind-turbine generators (WTG).
Energies 07 02658fa2 1024

A3. Energy Storage

The microgrid has one energy storage device, which is a Li-based battery system. This battery system is 100 kW, 60 kW h, and 696 Vdc. This battery system has two control modes: (a) master mode operates with both V and f controls once the microgrid is islanded; and (b) slave mode operates with the P/Q controls if the microgrid is grid-tied. Figure A3 illustrates the buck/boost DC/DC converter and inverter for the battery energy storage system.

Figure A3. Control of discharge from energy storage device.
Figure A3. Control of discharge from energy storage device.
Energies 07 02658fa3 1024

A4. Gas Turbine Generator

The Capstone 65 kW gas-turbine generator is adopted in the microgrid. It is a high-speed single-shaft design with the compressor and turbine mounted on the same shaft as the permanent magnet synchronous generator [22]. The generator produces an extremely high frequency signal ranging from 1500 Hz to 4000 Hz, which is first rectified and then inverted to a nominal 50/60 Hz signal. Thus, the generation of AC power from the micro-turbine generator is controlled by AC/DC and DC/AC converters. The DC bus voltages are 760 V and 750–785 V in the grid-tied and the standalone modes, respectively. When the microgrid is grid-connected, the gas-turbine generators can operate in either the P/Q control mode or the standby mode. The gas-turbine can be operated in the V/f control mode once the microgrid is islanded. Figure A4 illustrates the model of the gas turbine. The model includes governor control, fuel control and the dynamics of the gas-turbine engine [14].

Figure A4. Model of gas turbine.
Figure A4. Model of gas turbine.
Energies 07 02658fa4 1024

References

  1. Kyotol Protocol to the United Nations Framework Convention on Climate Change; Kyotol Protocol: Kyoto, Japan, 1997.
  2. The Copenhagen Accord. Proceedings of the United Nations Climate Change Conference, 7–18 December 2009; Copenhagen, Denmark.
  3. Lasseter, R.H.; Eto, J.H.; Schenkman, B.; Stevens, J.; Vollkommer, H.; Klapp, D.; Linton, E.; Hurtado, H.; Roy, J. CERTS microgrid laboratory test bed. IEEE Trans. Power Deliv. 2011, 26, 325–332. [Google Scholar]
  4. Lasseter, R.H.; Eto, J. Value and Technology Assessment to Enhance the Business Case for the CERTS Microgrid; DE-FC02-06CH11350; US Department of Energy: Washington, DC, USA, 2010. [Google Scholar]
  5. Ahn, C.S.; Peng, H. Decentralized and real-time power dispatch control for an islanded microgrid supported by distributed power sources. Energies 2013, 6, 6439–6454. [Google Scholar]
  6. Lim, Y.J.; Lim, H.M.; Kinoshita, T. Distributed load-shedding system for agent-based autonomous microgrid operations. Energies 2014, 7, 385–401. [Google Scholar]
  7. Klapp, D.; Vollkommer, H.T. Application of an Intelligent Static Switch to the Point of Common Coupling to Satisfy IEEE 1547 Compliance. Proceedings of the 2007 IEEE Power Engineering Society General Meeting, Tampa, FL, USA, 24–28 June 2007.
  8. Nikkhajoei, H.; Lasseter, R.H. Microgrid Protection. Proceedings of the 2007 IEEE Power Engineering Society General Meeting, Tampa, FL, USA, 24–28 June 2007.
  9. Kroposki, B.; Pink, C.; Lynch, J.; John, V.; Meor Daniel, S.; Benedict, E.; Vihinen, I. Development of a High-Speed Static Switch for Distributed Energy and Microgrid Applications. Proceedings of the Power Conversion Conference, Nagoya, Japan, 2–5 April 2007; pp. 1418–1423.
  10. Chan, C.M.; Lee, Y.D.; Chang, Y.R. A Novel Control System for Microgrid Operation and Protection. Proceedings of the 2011 SICE Annual Conference, Tokyo, Japan, 13–18 September 2011; pp. 722–726.
  11. Hong, Y.Y.; Su, D.S.; Hsiao, M.C.; Chang, Y.R.; Lee, Y.D.; Cheng, C.M. Preliminary Studies on First Outdoor Microgrid Test Bed in Taiwan. Proceedings of the 2011 IEEE Trondheim PowerTech, Trondheim, Norway, 19–23 June 2011; pp. 1–7.
  12. Hong, Y.Y.; Lai, Y.Z.; Hsiao, M.C.; Chang, Y.R.; Lee, Y.D.; Huang, H.C. Studies on Operation Modes for the First Outdoor Microgrid Test Bed in Taiwan. Proceedings of the 2012 IEEE Conference on Power System Technology (POWERCON), Auckland, New Zealand, 30 October–2 November 2012; pp. 1–6.
  13. OP5600 HILBOX USER GUIDE Real-Time Simulator; Opal-RT Technology Inc.: Montreal, QC, Canada, 2011.
  14. Gaonkar, D.N.; Patel, R.N.; Pillai, G.N. Dynamic Model of Microturbine Generation System for Grid Connected/Islanding Operation. Proceedings of the IEEE International Conference on Industrial Technology, ICIT 2006, Mumbai, India, 15–17 December 2006; pp. 305–310.
  15. Long, X.; Li, Y.W.; Xu, W.; Lerohl, C. A new technique to detect faults in de-energized distribution feeders—Parts I and II. IEEE Trans. Power Deliv. 2011, 26, 1893–1910. [Google Scholar]
  16. He, Z.Y.; Fu, L.; Lin, S.; Bo, Z.Q. Fault detection and classification in EHV transmission line based on wavelet singular entropy. IEEE Trans. Power Deliv. 2010, 25, 2156–2163. [Google Scholar]
  17. Dustegor, D.; Poroseva, S.V.; Hussaini, M.Y.; Woodruff, S. Automated graph-based methodology for fault detection and location in power systems. IEEE Trans. Power Deliv. 2010, 25, 638–646. [Google Scholar]
  18. Jiang, J.A.; Chuang, C.L.; Wang, Y.C.; Hung, C.H.; Wang, J.Y.; Lee, C.H.; Hsiao, Y.T. A hybrid framework for fault detection, classification, and location—Part I: Concept, structure, and methodology. IEEE Trans. Power Deliv. 2011, 26, 1988–1998. [Google Scholar]
  19. Burrus, C.S.; Gopinath, R.A.; Guo, H. Introduction to Wavelets and Wavelet Transforms; Prentice Hall Inc.: Englewood Cliffs, NJ, USA, 1998. [Google Scholar]
  20. Mokhtari, H.; Karimi-Ghartemani, M.; Iravani, M.R. Experimental performance evaluation of a wavelet-based on-line voltage detection method for power quality applications. IEEE Trans. Power Deliv. 2002, 17, 161–172. [Google Scholar]
  21. Hong, Y.Y.; Wang, C.W. Switching detection/classification using discrete wavelet transform and self-organizing mapping network. IEEE Trans. Power Deliv. 2005, 20, 1662–1668. [Google Scholar]
  22. Capstone MicroTurbine Model C65 User's Manual; Capstone Turbine Corporation: Chatsworth, CA, USA, 2007.
Figure 1. One-line diagram of studied microgrid with converters. PV: photovoltaic.
Figure 1. One-line diagram of studied microgrid with converters. PV: photovoltaic.
Energies 07 02658f1 1024
Figure 2. Proposed structure of ANFIS.
Figure 2. Proposed structure of ANFIS.
Energies 07 02658f2 1024
Figure 3. Wavelet coefficients d1–d3 of voltages at point of common coupling (PCC): (a1)–(c1) fault at Bus 1; and (a2)–(c2) fault at Bus 5.
Figure 3. Wavelet coefficients d1–d3 of voltages at point of common coupling (PCC): (a1)–(c1) fault at Bus 1; and (a2)–(c2) fault at Bus 5.
Energies 07 02658f3 1024
Figure 4. Overall architecture of the two logics. MRA: multi-resolution analysis; DWT: discrete wavelet transform; and ANFIS: adaptive network-based fuzzy inference system.
Figure 4. Overall architecture of the two logics. MRA: multi-resolution analysis; DWT: discrete wavelet transform; and ANFIS: adaptive network-based fuzzy inference system.
Energies 07 02658f4 1024
Figure 5. Calculation of wavelet coefficients d1, d2 and d3 in Xilinx System Generator (XSG).
Figure 5. Calculation of wavelet coefficients d1, d2 and d3 in Xilinx System Generator (XSG).
Energies 07 02658f5 1024
Figure 6. 15 membership functions (A1–A5, B1–B5, and C1–C5) of ANFIS used to identify faults in Zone 1.
Figure 6. 15 membership functions (A1–A5, B1–B5, and C1–C5) of ANFIS used to identify faults in Zone 1.
Energies 07 02658f6 1024
Figure 7. System responses caused by fault at Bus 4: (a) kW of gas-turbine at Bus 11; (b) kW of gas-turbine at Bus 5; (c) wind power generations; (d) PV generations; (e) voltage at Bus 3; and (f) frequency at Bus 3.
Figure 7. System responses caused by fault at Bus 4: (a) kW of gas-turbine at Bus 11; (b) kW of gas-turbine at Bus 5; (c) wind power generations; (d) PV generations; (e) voltage at Bus 3; and (f) frequency at Bus 3.
Energies 07 02658f7a 1024Energies 07 02658f7b 1024
Table 1. Accuracy of proposed ANFIS.
Table 1. Accuracy of proposed ANFIS.
Faulty gird/zoneTraining errorsAccuracy
Main grid0.012389100%
Zone 10.037720100%
Zone 20.07797196.37%
Zone 30.08730798.19%
Table 2. CPU times required using the three approaches.
Table 2. CPU times required using the three approaches.
Software environmentPlatformMin:Sec
Simulink (normal)PC36:36
Simulink (accelerator)PC4:13
Simulink (Opal-Lab)eMegaSim0:12

Share and Cite

MDPI and ACS Style

Hong, Y.-Y.; Wei, Y.-H.; Chang, Y.-R.; Lee, Y.-D.; Liu, P.-W. Fault Detection and Location by Static Switches in Microgrids Using Wavelet Transform and Adaptive Network-Based Fuzzy Inference System. Energies 2014, 7, 2658-2675. https://doi.org/10.3390/en7042658

AMA Style

Hong Y-Y, Wei Y-H, Chang Y-R, Lee Y-D, Liu P-W. Fault Detection and Location by Static Switches in Microgrids Using Wavelet Transform and Adaptive Network-Based Fuzzy Inference System. Energies. 2014; 7(4):2658-2675. https://doi.org/10.3390/en7042658

Chicago/Turabian Style

Hong, Ying-Yi, Yan-Hung Wei, Yung-Ruei Chang, Yih-Der Lee, and Pang-Wei Liu. 2014. "Fault Detection and Location by Static Switches in Microgrids Using Wavelet Transform and Adaptive Network-Based Fuzzy Inference System" Energies 7, no. 4: 2658-2675. https://doi.org/10.3390/en7042658

Article Metrics

Back to TopTop