Next Article in Journal
Wideband Low Phase-Noise Signal Generation Using Coaxial Resonator in Cascaded Phase Locked Loop
Previous Article in Journal
Coordinated Reconfiguration with Energy Storage System for Load Restoration in Integrated Electric and Heating Systems
Previous Article in Special Issue
Fixed (Trackside) Energy Storage System for DC Electric Railways Based on Full-SiC Isolated DC-DC Converters
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Reinforcement of DC Electrified Railways by a Modular Battery Energy Storage System

by
Erick Matheus da Silveira Brito
1,2,*,
Philippe Ladoux
1,
Joseph Fabre
3 and
Benoit Sonier
4
1
Laboratory of Plasma and Energy Conversion (LAPLACE), University of Toulouse, 31071 Toulouse, France
2
Institute of Exact and Technological Sciences, Federal University of Viçosa, Florestal 35690-000, Brazil
3
Société de Construction des Lignes Électriques-Systèmes pour Ferroviaire et Énergie (SCLE-SFE), 31204 Toulouse, France
4
Société Nationale des Chemins de Fer Français (SNCF-Réseau), 93574 Saint Denis, France
*
Author to whom correspondence should be addressed.
Electronics 2024, 13(10), 1933; https://doi.org/10.3390/electronics13101933
Submission received: 13 April 2024 / Revised: 3 May 2024 / Accepted: 11 May 2024 / Published: 15 May 2024
(This article belongs to the Special Issue Railway Traction Power Supply, 2nd Edition)

Abstract

:
DC railway electrification was deployed at the beginning of the 20th century in several countries in Europe. Today, this power system is no longer adapted to the demands of increased rail traffic. Due to the relatively low voltage level, the current consumed by the trains reaches several kAs. So, in the worst case, the locomotives cannot operate at their rated power due to the voltage drop along the contact line. Conventional solutions to reduce the voltage drop consist of increasing the cross-section of overhead lines or reducing the length of sectors by installing additional substations. Nevertheless, these solutions are expensive and not always feasible. The implementation of a Modular Battery Energy Storage System (MBESS) can be an alternative solution to reinforce the railway power supply. This paper first presents an MBESS based on elementary blocks associating Full-SiC Isolated DC-DC converter and battery racks. The electrical models of a railway sector and an elementary block are described, and simulations are performed considering real railroad traffic on two sectors of the French National Rail Network, electrified at 1.5 kV. The results show that the installation of an MBESS in the railway sector boosts the locomotive’s voltage while also increasing overall system efficiency.

1. Introduction

In the European Union (EU), four railway electrification systems are mainly used: DC, at 1.5 kV or 3 kV, Medium Voltage AC (MVAC) of 15 kV at the special frequency of 16.7 Hz and 25 kV at the standard line frequency of 50 Hz [1]. The first two systems were introduced at the beginning of the 20th century. The last one was developed after World War II. From that moment, the countries that had not yet electrified their railway lines chose the 25 kV/50 Hz system. The other electrification systems, already in place, were kept and even extended during the second half of the 20th century. Today, in the EU, 43% of electrified railway routes are powered by DC, 30% at 15 kV/16.7 Hz, and 27% at 25 kV/50 Hz [2].
Faced with the collective need to favor modes of transport that are more respectful of the environment, train traffic, for freight and passengers, is expected to increase in the years to come [3]. From the point of view of the railway network operator, an increase in traffic is only possible if a minimum contact-line voltage can be ensured to allow the locomotives to draw the power necessary to keep to their timetables [4]. Due to its relatively low voltage level, the DC electrification system is penalized by the level of current absorbed by the trains which can reach several kAs. Conventional solutions to reduce the voltage drop consist of increasing the cross-section of overhead lines or reducing the length of sectors by installing new substations [5]. Additionally, paralleling stations (PS) at the middle of the sector can be added to reduce the contact-line resistance. Previous studies have demonstrated that the middle of the sector between two substations is the critical point in terms of voltage drop. Excluding the paralleling stations (since the majority of the DC railway lines already have a PS installed), the other solutions are expensive and not always feasible. As of 2014, several papers proposing a Medium Voltage DC (MVDC) electrification system were published [6,7,8,9]. In [10], it was demonstrated that a nominal contact-line voltage of 9 kV made it possible to obtain performances similar to those of 25 kV/50 Hz electrification system in terms of railroad traffic, substation spacing, and contact-line cross-section. Figure 1 illustrates a DC-electrified railway system. When the line is electrified at 1.5 kV, the distance between substations, referred to as D, is in the order of 10–20 km. Nevertheless, for a line electrified at 9 kV, the substations could be spaced approximately 50 km apart.
However, changing the voltage level to MVDC is challenging cost-wise. On the one hand, new rectifier groups have to be installed in substations and MVDC circuit breakers have to be developed. On the other hand, updating all the rolling stock traction converters is not a simple task even considering advances in high blocking-voltage semiconductors [10]. Therefore, the MVDC electrification system is considered only as a long-term solution. In the short term, several reinforcement solutions can be deployed. The principle of a three-wire DC power supply is illustrated in Figure 2. This solution can be considered as an intermediate stage in converting a classical DC power supply, e.g., 1.5 kV or 3 kV, to MVDC. MVDC rectifier groups are installed in existing substations and an additional feed-wire is deployed on the support posts of the contact line. Then DC/DC converters are implemented at the PS to reinforce the power supply and boost the voltage on the contact lines [11].
Other reinforcement solutions, also shown in Figure 2, rely on energy storage systems and renewable energy sources, e.g., photovoltaic (PV) systems, integrated with the DC power electrification lines [12,13,14]. Solutions involving battery energy storage systems (BESS) have gained attention in the last few years. Due to the environmental pressure, the road transportation sector is shifting from fossil fuels to more sustainable electric power. This demand drives advances and developments in battery technologies, creating more reliable, efficient, and less expensive solutions [15,16].
Several works in the literature have proposed incorporating BESS in railway applications [17,18,19,20,21]. Japan railways are the pioneers in this field and have installed around 20 BESS rated at 100 kWh [22,23]. The authors in [24] propose a sizing and control strategy optimization of a hybrid energy storage system based on batteries and ultracapacitors in urban rail transit to reduce the substation energy cost and achieve the peak shaving function. Additionally, the authors in [25] propose a battery and ultracapacitor hybrid storage system for high-speed railway applications. In [26], the impact assessment of energy storage systems supporting DC railways on AC power grids is investigated, considering both wayside and on-board solutions. A techno-economic sizing of auxiliary-battery-based substations in 3 kV Italian DC railway systems is established in [27]. Also, recent research progress and applications of energy storage systems in China’s high-speed railways are developed in [28]. However, until now, no BESS has been implemented on the French rail network and there is still no dedicated industrial product.
Therefore, this paper focuses on the sizing of a Modular Battery Energy Storage System (MBESS) based on the association of 300 kW elementary converters, including an isolated DC-DC converter and battery racks. The case studies considered in this paper are for two critical sectors of the French Rail Network where, during peak hour traffic, the contact-line voltage drops below 1.3 kV, limiting the power that the locomotives can draw. Simulations are performed considering real railroad traffic to determine the number of elementary blocks of the MBESS.
This paper is structured as follows: Section 1 introduces the subject of study; Section 2 describes the topology of the MBESS and its control strategy; Section 3 models the railway sector as an equivalent electrical circuit and designs the MBESS for the proposed application. In Section 4, the sizing method is applied for two critical sectors of the French rail network electrified at 1.5 kV. Then, simulation results are presented and discussed. Finally, Section 5 presents the conclusions of the paper and perspectives for future works.

2. Description of the MBESS

2.1. Topology of the Elementary Converter

The topology of the elementary converter is presented in Figure 3. The converter is based on 3.3 kV SiC power modules in LV100 packaging. A Medium Frequency Transformer (MFT) provides galvanic isolation between the railway line and the battery. The Resonant Dual Bridge Converter (RDBC) consists of two H-bridges connected through a series-resonant circuit formed by the MFT’s leakage inductances L p in series with capacitors C r p and C r s . The sizing and the tests of RDBC were presented in papers [29,30]. The resonance frequency was slightly higher than the switching frequency to obtain a Discontinuous Conduction Mode (DCM) in the AC stage. As a result, the switching losses are very low, which makes it possible to achieve an efficiency of 99% over 80% of the operating range [31]. Conversely, in DCM, the RDBC operates with a constant voltage ratio close to one and therefore does not allow the battery current to be controlled. Thus, a Two-leg Interleaved Step-down Chopper (TISC) regulates the battery current. A coupled inductor (InterCell Transformer, ICT) is connected to the output of the two legs as a solution with reduced volume [32]. The parameters of converters RDBC and TISC as well as the MFT are given in Table 1 and Table 2, respectively.

2.2. Modularity of the BESS

The modularity of the BESS is illustrated in Figure 4. Thanks to the galvanic isolation, several combinations are possible: q is chosen regarding the contact-line voltage and N is determined according to the power or energy required to sustain the traffic on the railway line. The Input Series and Output Parallel (ISOP) association of q elementary converters guarantees a natural balancing of input voltages V i n and output currents I o u t . Additionally, p battery racks can be connected in parallel while respecting the battery’s maximum current capability.
In RDBC, the isolation of MFT was chosen so that MBESS could be implemented on a future 9 kV electrification system. Table 3 presents the values of q as a function of the nominal voltage level. The voltage ranges for 1.5 kV or 3 kV electrification systems are defined by European standard EN 50163/2005 [33]. The contact-line lowest and highest acceptable voltage V c l during permanent operation are denoted as V c l , m i n and V c l , m a x , respectively, in this paper. For future MVDC electrification systems, the voltage ranges are defined in [10] while maintaining the same rules of proportionality.
For the first implementation on the French Rail Network, a lithium iron phosphate (LiFePO4 or LFP) battery technology was selected due to safety exigencies. Despite having lower energy density than other battery technologies, the LPF has a longer lifetime and better current/voltage stability [34]. The characteristics of one battery rack are presented in Table 4. The rack is composed of 14 modules in series, thus offering a nominal voltage of 717 V.
In each BESS, the battery associates p racks in parallel based on the elementary converter nominal output current I o u t , according to:
I o u t , n = P n V b a t , r a c k ,
p = q I o u t , n I m a x , d .

2.3. Modelling and Control Strategy of the MBESS

For the sizing of the MBESS, it is necessary to model a railway sector taking into account the movement of trains. The switching period of the converters is negligible compared to the dynamic performances of the trains, thus only an averaged model of the elementary BESS is considered. In Figure 5a, the RDBC is assumed to have a unitary voltage ratio. Then, voltages V i n and V d c are supposed to be equal and the input equivalent capacitance C e q is the sum of C i n and C d c . The TISC is represented by a small signal model with controlled sources: the current I d c is a function of the output current I o u t and duty cycle α ; the output voltage V o u t depends on the input voltage V i n and also α . The equivalent output inductor L e q corresponds to the leakage inductance of the ICT’s windings.
The inputs of the elementary converters being connected in series and the outputs in parallel, the averaged model of the elementary BESS, presented in Figure 5b, is easily deduced. Moreover, the battery model is considered as an internal resistance R i n t in series with an electromotive force e b a t , i . The values of e b a t , i depend on the state of charge (SOC) that is obtained from the integration of the battery current divided by its capacity. A look-up table correlating SOC with battery voltage is provided by the manufacturer.
Figure 6a shows the control block diagram of the MBESS. The inner loops control the battery current whether in charge or discharge mode, for each elementary BESS. The outer loop regulates contact-line voltage V c l at the connection point whose reference value V r e f must be carefully determined to maintain the pantograph voltage of the locomotives above a certain level, ensuring correct operation of the trains [35]. The bandwidths of the inner and outer control loops were chosen as 1/10 and 1/100, respectively, of the TISC switching frequency f T I S C .
The voltage-current characteristic of MBESS is shown in Figure 6b. When trains are running on the sector and the PI controller of the outer control loop is not saturated, the MBESS is regulating the contact-line voltage at its connection point, which means that V c l = V r e f . When the trains pass near this point, the power delivered by the MBESS has to be limited according to the maximum value of the battery discharge current. Thus, the voltage-control loop is disabled (PI controller output saturated at − I m a x , d and the MBESS operates at negative constant power. Conversely, when the trains are in a regenerative braking phase or when there is no traffic in the sector, the voltage V c l increases and the power absorbed on the contact line by MBESS has to be limited according to the maximal allowed battery charge-current. The outer control loop is again disabled (PI controller output saturated at I m a x , c ) and the MBESS operates at positive constant power. The limits of the contact-line voltage, V c l , m a x and V c l , m i n , depending on the nominal voltage of the electrification system, are given in Table 3. Outside of this voltage range, the MBESS must be disconnected from the contact line by a circuit breaker, as is the case for rolling stock systems.

3. Implementation of MBESS on a Railway Sector

3.1. Modeling of a Railway Sector

The railway sector considered in this work consists of a double-track line with a length D and with a PS in the middle of the sector. The MBESS is connected to the already installed PS. The equivalent electrical circuit is presented in Figure 7. The time constants of the electrical circuit are much smaller than the travel time of a train on the sector. Thus, to calculate the voltage at the pantograph of the locomotives, a steady-state DC model is sufficient. Substations at both ends of the sector are modeled as voltage source E s s in series with an internal resistance R s s . The trains are represented as power-controlled current sources according to:
I l o c , i = P l o c , i V l o c , i ,
where P l o c , i is the power drawn by the locomotive i and V l o c , i and I l o c , i correspond to its pantograph voltage and current, respectively. Moreover, I e x t , i represents the current circulating outside of the modeled sector, which also has an impact on the pantograph voltage of the trains running on the sector. This information must be provided by the rail network operator.
According to the railroad traffic, this sector is divided into k subsectors with a maximum of one train circulating in each direction at any time. Concerning the numbering of variables, the odd index ( i = 2 k 1 ) corresponds to the trains running from left to right while the even index ( i = 2 k ) corresponds to the trains running in the opposite direction. If at a given moment, there is no train in circulation in a subsector, the corresponding current source I l o c , i is set to zero. Since the rails of the two tracks are electrically connected in parallel at regular intervals, they are considered as a single conductor. The resistances of the contact lines and rails depend on the position of the trains x 2 k and x 2 k 1 . As can be seen in Figure 8, there are two possible cases of the train’s position in each k t h subsector. The resistances in the equivalent circuit can be determined by the following equations:
R c l , 1 a = R a x 2 k 1 ,
R c l , 1 b = R a ( 1 x 2 k 1 ) ,
R c l , 2 a = R a x 2 k ,
R c l , 2 b = R a ( 1 x 2 k ) .
Considering the case of Figure 8a, when x 2 k 1 > x 2 k , then:
R r , 1 = R b x 2 k ,
R r , 3 = R b ( 1 x 2 k 1 ) .
Similarly, in the case of Figure 8b, when x 2 k > x 2 k 1 , then:
R r , 1 = R b x 2 k 1 ,
R r , 3 = R b ( 1 x 2 k ) .
For both cases, R r , 2 can be calculated as follows:
R r , 2 = R b | x 2 k x 2 k 1 | .
The resistances R a and R b are calculated according to:
R a = 18.8 S c L k ,
R b = 0.9 2 W t L k ,
where S c is the equivalent copper cross-section, expressed in mm², W t is the weight of the rail per unit length, expressed in kg/m, and L k is the length of the k t h subsector, in km.

3.2. Methodology for Sizing the MBESS

The methodology adopted to correctly size the MBESS is detailed in Figure 9. Three main steps are described regarding the topology of the MBESS that is connected to the PS in the equivalent circuit shown in Figure 7. The data of railroad traffic versus time, i.e., train position P k i ( t ) , the power drawn by the train P l o c , i ( t ) and sector external currents I e x t , i ( t ) are considered as inputs of the simulation. The following steps are made, consecutively:
  • Step 1: The first step consists of a railroad traffic preliminary verification. The simulation is performed without the MBESS connected to the PS. Then, over the simulation time horizon, the pantograph voltage V l o c , i is compared to a minimum value, V l o c , m i n , that avoids a power limitation for the locomotive. European Standard EN 50338/2022 [36] determines technical criteria for traction power supply systems and rolling stock to achieve interoperability following EN 50163/2005 [33]. Usually, this value is around 85% of the contact-line nominal voltage, but it can vary depending on the locomotive manufacturer. If none of the pantograph voltage points are below V l o c , m i n , this railroad traffic is considered not critical, thus, there is no need for installing an MBESS. Otherwise, MBESS parameters V r e f and N must be determined to maintain the pantograph voltage of the trains above V l o c , m i n .
  • Step 2: After establishing the existence of critical points in railroad traffic, the next step is to determine the reference voltage V r e f that the MBESS should impose on the contact line. For this, the electrical simulation is performed assuming that MBESS behaves as a voltage source whose value is fixed by the voltage control loop setpoint, V r e f , with an initial value of V r e f , i n i t = V l o c , m i n . Successive simulations are then performed by incrementing V r e f , with a Δ V until the following condition is satisfied over the simulation time horizon:
    V l o c , i V l o c , m i n .
    It should be noted that if the minimum value of V r e f that satisfies (15) is equal to or greater than E s s , there is no other solution than to increase the cross-section of the contact line.
  • Step 3: Once V r e f is determined, the initial value of N, named as N i n i t , is set according to Equation (16), and rounded to the highest integer value. P M B E S S , m a x is the maximum power supplied by the MBESS when modeled as a controlled voltage source connected at PS (determined in the previous step). P n is the nominal power of the elementary DC/DC converter given in Table 1 and q is the number of elementary DC/DC converters in ISOP configuration, given in Table 3.
    N i n i t = P M B E S S , m a x q P n .
    Then, the average model of N MBESS and their control loops are connected at the paralleling station in the equivalent circuit of the sector. The batteries are considered identical and initially fully charged (SOC = 100%). Afterward, successive simulations are performed and N is decremented to satisfy the Equation (15) even in the case of the power delivered by MBESS being limited by the maximum battery discharge current. Minimizing N reduces the installation cost of the MBESS which has to be compared to that of a new substation, which varies greatly with the location of the paralleling station and the need to realize a new AC transmission line to supply the substation.

4. Sizing of the MBESS—Examples of Sectors on the French Railways

4.1. Description of the Railway Sectors

This section applies the proposed methodology to size the MBESS for two different sectors on the French Rail Network. These sectors are electrified in 1.5 kV DC both consisting of a double-track line with trains circulating in each direction, as illustrated in Figure 10. The simulation of the equivalent circuit presented in Figure 7 is performed on PLECS software, version 4.8.1 (64 bits) [37], considering that the MBESS is installed at a PS.
The first railway sector is located on the Lyon-Dijon classical line between the substations of Crèches ( P k = 445 km) and Romanèche ( P k = 453 km), with a paralleling station at the sector midpoint ( P k = 449 km). The second sector is located on the Chartres-Le Mans regional line between the substations of Le Theil ( P k = 159 km) and Sceaux-Boëssé ( P k = 179 km), with a paralleling station also positioned in the middle of the sector ( P k = 169 km). From the point of view of the French Rail Network Operator (SNCF-Réseau), these sectors are considered problematic because significant contact-line voltage drops occur.
Table 5 specifies the parameters used in the simulations for both cases. Because of the paralleling station, there are always, at least two subsectors. Nevertheless, the number of subsectors in the equivalent circuit can be chosen according to the railroad traffic. Thus, with four subsectors it is possible to have simultaneously in the sector, a maximum of four trains circulating in each direction.
The information required for the simulations, P k i ( t ) , P l o c , i ( t ) , I e x t , 1 ( t ) and I e x t , 2 ( t ) , was provided by SNCF-Réseau. The time plots for the sectors Crèches-Romanèche and Le Theil-Sceaux-Boëssé are shown in Figure 11. The time interval considered corresponds to a traffic peak in the sector.
Table 6 presents a preliminary analysis of traffic in the considered sectors. The Crèches-Romanèche sector has the shortest length and the critical situation results from high power train circulations with a high traffic density. Regarding the Le Theil-Sceaux-Boëssé sector, the critical situation results from greater substation spacing and a low contact-line cross-section. Even though the trains draw less power than in the previous sector, the energy demand is increased because the travel time to cross the sector is longer.

4.2. Simulation Results of the MBESS Boosting the Locomotives Pantograph Voltage

Figure 12a,b and Figure 13a,b show the pantograph voltage of the locomotives over P k for both sectors before the installation of the MBESS. In the following analysis, V l o c , m i n = 1.3 kV will be considered as the threshold voltage for critical points. Therefore, operating points with a voltage below 1.3 kV are observed in both cases. In such a situation, the operation of locomotives at constant power can be constrained by the limitation of the current absorbed by the traction inverters, leading to delays and disturbances in the railroad traffic. Therefore, the MBESS is installed in this sector to reinforce the power supply and avoid pantograph voltage values lower than 1.3 kV. The MBESS sizing process, presented in Figure 9, was applied for both sectors, and Table 7 shows the corresponding values of N and V r e f . Since the railway sector is electrified in 1.5 kV DC, q and p are selected as 1 and 3, respectively, according to Table 3.
Figure 12c,d and Figure 13c,d show the pantograph voltage of the locomotives over P k for both sectors after the installation of the MBESS. As can be noticed, the critical points have been removed. Figure 14 shows a time-zoomed view of the action of the MBESS in the first case study, due to the passage of a freight train with two high-power peaks. During the first power peak, the MBESS regulates the voltage at PS to V r e f (Voltage Source Mode: VSM). During the second power peak, the discharge current of the batteries is limited. In this case, the MBESS behaves as a current source operating at constant power (Current Source Mode: CSM). Nevertheless, the contact-line voltage is still maintained above 1.3 kV. Figure 15a presents the contact-line characteristics of V c l  versus  I c l over the simulation time horizon of the Crèches-Romanèche case study, as an example. When comparing the contact-line operation points with Figure 6b, it is possible to identify the zone of VSM with V c l regulated at 1580 V and the zones of CSM, with battery charge and discharge saturation.
With N = 10 in the first case, the total storage energy capacity is 2.58 MWh, higher than the second case with N = 8, storing 2.06 MWh. In this study, the decision to only charge the MBESS in the off-peak traffic period was taken. Thus, during the time interval 16:00–21:00, the MBESS is only discharging. After 22:00 there are no trains in circulation and the substations charge the batteries. Figure 15b shows the state-of-charge (SOC) of the batteries for both analyzed sectors.
In the case study Crèches - Romanèche, the battery SOC is reduced from 100% to 88%. The energy storage is much higher than that needed. In fact, the MBESS mostly provides current to the sector to compensate for the high-power-demand trains, but only for a short period, due to the short length of the sector. After 22:00, the MBESS batteries are recharged to 100% at current I m a x , c in around 15 min. In the case of Le Theil-Sceaux-Boëssé, after the traffic peak, the SOC of the batteries decreases to 44%. Due to the higher sector length, the batteries must deliver power over a longer time. After 22:00, MBESS batteries are recharged to 100% at current I m a x , c in around 1 h 30 min.
In the two sectors studied, it is important to note that the total depth of discharge is never reached. In fact, as it was presented in Section 2, the number of battery racks depends on the current rating of the elementary power converter. Additionally, according to the sizing process shown in Figure 9, N is selected to provide the peak power required to ensure a pantograph voltage above V l o c , m i n = 1.3 kV. Therefore, due to the characteristics of the selected battery, the stored energy is always oversized.

4.3. Impact of the MBESS on the Global System Efficiency

The elimination of critically low values of locomotive pantograph voltage is not the only advantage of installing an MBESS. Along the sector, the locomotives operate with a higher contact-line voltage and consequently draw a lower current. Therefore, there is an improvement in the global electrical system efficiency because of the lower power losses in the contact line and the rails. Table 8 and Table 9 show the energy balance of the sector before and after the installation of an MBESS for each case of study. The energy absorbed by the trains does not change from one condition to another, as it depends exclusively on the traffic. However, the substations provide less current due to the reduced voltage drop along the contact lines. The energy provided by the batteries to the railway line takes into account the SOC reduction previously calculated and the losses in the internal resistor R i n t . However, the losses in the power converters are not considered. The energy efficiency of the railway sector is calculated over the simulation time according to Equation (17) where E l o c , i is the energy consumed by the trains running on the sector and E s u b , i is the energy provided by the substations, also allowing for the energy required to recharge the battery to 100% of capacity. As noticed, there is a gain of around 2% in efficiency with the installation of the MBESS for both cases, which is very relevant considering the power level of the railway application.
η g l o b a l = E l o c , 1 + E l o c , 2 E s u b , 1 + E s u b , 2 100 % .

5. Conclusions

This paper proposed a modular BESS solution to reinforce DC railway lines. By reducing the contact-line voltage drop, the MBESS prevents the onboard locomotive control system from limiting the traction power. Therefore, trains can respect their timetables. Furthermore, the power losses in the contact line and the rails are reduced and the energy efficiency of the electrification system is improved. Thanks to the galvanic isolation included in the DC/DC converters, the solution is suitable for different contact-line voltage levels, including for future 6 kV or 9 kV electrified lines still under consideration.
The sizing method of the MBESS was presented in Section 3. The number of elementary blocks depends on the electrical parameters of the sector considered and the rail traffic. To run the simulations, traffic information, and power consumed by trains must be provided by the rail infrastructure manager. The two case studies covered in this paper were provided by SNCF-Réseau, the French rail infrastructure manager. The first one concerns a sector of a main line where there is a high traffic density with high-power trains in circulation. The second one concerns a sector of a regional line with large substation spacing and a low contact-line cross-section. Respectively, the power ratings of the MBESS are 3 MW and 2.4 MW which represents about half of the nominal power of a substation used on lines electrified in 1.5 kV DC.
Taking into account the characteristics of the batteries initially selected, the stored energies are 2.58 MWh and 2.06 MWh. These values are oversized regarding the evolution of the battery SOC during the peaks of traffic. A way of optimizing the storage energy and the power capability of the MBESS could be simply increasing the battery’s nominal voltage. However, this is problematic given the battery management system currently available.
Finally, it is important to say that the work presented here is the design of a planned prototype to be installed on a line of the French rail network. Further studies are expected to achieve the integration of the MBESS in the railway line, design of input filters, different energy management strategies, lifetime evaluations and so on.

Author Contributions

Conceptualization, P.L. and J.F.; methodology, E.M.d.S.B. and P.L.; validation, E.M.d.S.B. and B.S.; writing and editing, E.M.d.S.B. and P.L.; review, J.F. and B.S. All authors have read and agreed to the published version of the manuscript.

Funding

This research was carried out as part of the INSTODRES project. INSTODRES is funded by the French Government as part of the Investment Program “France 2030”, and operated by French Agency for Ecological Transition (ADEME) (2105D0041).

Data Availability Statement

The data presented in this study are available on request from the corresponding author.

Conflicts of Interest

Author Joseph Fabre was employed by the company SCLE-SFE. Author Benoit Sonier was employed by the company French National Railway Company (SNCF) Réseau. The remaining authors declare that the research was conducted in the absence of any commercial or financial relationships that could be construed as a potential conflict of interest.

Abbreviations

The following abbreviations are used in this manuscript:
ACAlternating Current
BESSBattery Energy Storage System
CSMCurrent Source Mode
DCDirect Current
DCMDiscontinuous Conduction Mode
DoDDepth of Discharge
ENEuropean Standard
EUEuropean Union
ICTIntercell Transformer
ISOPInput Series and Output Parallel
LFPLithium Iron Phosphate
MBESSModular Battery Energy Storage System
MFTMedium Frequency Transformer
MVACMedium Voltage AC
MVDCMedium Voltage DC
PIProportional Integral controller
PLECSPiecewise Linear Electrical Circuit Simulation
PSParalleling Station
PVPhotovoltaic
RDBCResonant Dual Bridge Converter
SiCSilicon Carbide
SOCState of charge
SNCFSociété Nationale des Chemins de Fer Français
TISCTwo-leg Interleaved Step-down Chopper
VSMVoltage Source Mode

References

  1. IEC 60850; Railway Applications-Supply Voltages of Traction Systems. International Electrotechnical Commission: Geneva, Switzerland, 2014.
  2. Bueker. Maps and Facts on European Interoperability Issues. Available online: http://www.bueker.net/trainspotting/voltage_map_europe.php (accessed on 26 March 2018).
  3. CER. Railway to a Green Future. Available online: https://www.cer.be/cer-facts-figures/railway-to-a-green-future (accessed on 4 December 2023).
  4. Steimel, A. Under Europe’s incompatible catenary voltages a review of multi-system traction technology. In Proceedings of the 2012 Electrical Systems for Aircraft, Railway and Ship Propulsion, Bologna, Italy, 16–18 October 2012; pp. 1–8. [Google Scholar] [CrossRef]
  5. Mousavi Gazafrudi, S.M.; Tabakhpour Langerudy, A.; Fuchs, E.F.; Al-Haddad, K. Power Quality Issues in Railway Electrification: A Comprehensive Perspective. IEEE Trans. Ind. Electron. 2015, 62, 3081–3090. [Google Scholar] [CrossRef]
  6. He, X.; Peng, J.; Han, P.; Liu, Z.; Gao, S.; Wang, P. A Novel Advanced Traction Power Supply System Based on Modular Multilevel Converter. IEEE Access 2019, 7, 165018–165028. [Google Scholar] [CrossRef]
  7. Gómez-Expósito, A.; Mauricio, J.M.; Maza-Ortega, J.M. VSC-Based MVDC Railway Electrification System. IEEE Trans. Power Deliv. 2014, 29, 422–431. [Google Scholar] [CrossRef]
  8. Zhu, R.; Liang, T.; Dinavahi, V.; Liang, G. Wideband Modeling of Power SiC mosfet Module and Conducted EMI Prediction of MVDC Railway Electrification System. IEEE Trans. Electromagn. Compat. 2020, 62, 2621–2633. [Google Scholar] [CrossRef]
  9. Yang, X.; Hu, H.; Ge, Y.; Aatif, S.; He, Z.; Gao, S. An Improved Droop Control Strategy for VSC-Based MVDC Traction Power Supply System. IEEE Trans. Ind. Appl. 2018, 54, 5173–5186. [Google Scholar] [CrossRef]
  10. Verdicchio, A.; Ladoux, P.; Caron, H.; Courtois, C. New Medium-Voltage DC Railway Electrification System. IEEE Trans. Transp. Electrif. 2018, 4, 591–604. [Google Scholar] [CrossRef]
  11. Ladoux, P.; Blaquiere, J.M.; Caron, H.; Iannuzzi, D.; Coppola, M. New three-wire supply systems for DC electric railways. IET Electr. Syst. Transp. 2015, 5, 112–119. [Google Scholar] [CrossRef]
  12. Dong, H.; Tian, Z.; Spencer, J.W.; Fletcher, D.; Hajiabady, S. Coordinated Control Strategy of Railway Multisource Traction System With Energy Storage and Renewable Energy. IEEE Trans. Intell. Transp. Syst. 2023, 24, 15702–15713. [Google Scholar] [CrossRef]
  13. Aatif, S.; Yang, X.; Hu, H.; Maharjan, S.K.; He, Z. Integration of PV and Battery Storage for Catenary Voltage Regulation and Stray Current Mitigation in MVDC Railways. J. Mod. Power Syst. Clean Energy 2021, 9, 585–594. [Google Scholar] [CrossRef]
  14. Liu, X.; Li, K. Energy storage devices in electrified railway systems: A review. Transp. Saf. Environ. 2020, 2, 183–201. [Google Scholar] [CrossRef]
  15. Hu, X.; Deng, X.; Wang, F.; Deng, Z.; Lin, X.; Teodorescu, R.; Pecht, M.G. A Review of Second-Life Lithium-Ion Batteries for Stationary Energy Storage Applications. Proc. IEEE 2022, 110, 735–753. [Google Scholar] [CrossRef]
  16. Walvekar, H.; Beltran, H.; Sripad, S.; Pecht, M. Implications of the Electric Vehicle Manufacturers’ Decision to Mass Adopt Lithium-Iron Phosphate Batteries. IEEE Access 2022, 10, 63834–63843. [Google Scholar] [CrossRef]
  17. Lee, H.M. A study on development of ESS installed in DC railway system. In Proceedings of the ICCAS 2010, Goyang-si, Republic of Korea, 27–30 October 2010; pp. 804–806. [Google Scholar] [CrossRef]
  18. Ahmadi, M.; Jafari Kaleybar, H.; Brenna, M.; Castelli-Dezza, F.; Carmeli, M.S. Integration of Distributed Energy Resources and EV Fast-Charging Infrastructure in High-Speed Railway Systems. Electronics 2021, 10, 2555. [Google Scholar] [CrossRef]
  19. Ratniyomchai, T.; Kulworawanichpong, T. A Demonstration Project for Installation of Battery Energy Storage System in Mass Rapid Transit. Energy Procedia 2017, 138, 93–98. [Google Scholar] [CrossRef]
  20. Lamedica, R.; Ruvio, A.; Galdi, V.; Graber, G.; Sforza, P.; GuidiBuffarini, G.; Spalvieri, C. Application of battery auxiliary substations in 3kV railway systems. In Proceedings of the 2015 AEIT International Annual Conference (AEIT), Naples, Italy, 14–16 October 2015; pp. 1–6. [Google Scholar] [CrossRef]
  21. Calderaro, V.; Galdi, V.; Graber, G.; Piccolo, A.; Capasso, A.; Lamedica, R.; Ruvio, A. Energy management of Auxiliary Battery Substation supporting high-speed train on 3 kV DC systems. In Proceedings of the 2015 International Conference on Renewable Energy Research and Applications (ICRERA), Palermo, Italy, 22–25 November 2015; pp. 1224–1229. [Google Scholar] [CrossRef]
  22. Konishi, T.; Morimoto, H.; Aihara, T.; Tsutakawa, M. Fixed Energy Storage Technology Applied for DC Electrified Railway. IEEJ Trans. Electr. Electron. Eng. 2010, 5, 270–277. [Google Scholar] [CrossRef]
  23. Konishi, T.; Tobita, M. Fixed energy storage technology applied for DC electrified railway (traction power substation). In Proceedings of the 2012 Electrical Systems for Aircraft, Railway and Ship Propulsion, Bologna, Italy, 16–18 October 2012; pp. 1–6. [Google Scholar] [CrossRef]
  24. Dong, H.; Tian, Z.; Spencer, J.W.; Fletcher, D.; Hajiabady, S. Bi-level Optimization of Sizing and Control Strategy of Hybrid Energy Storage System in Urban Rail Transit Considering Substation Operation Stability. IEEE Trans. Transp. Electrif. 2024. [Google Scholar] [CrossRef]
  25. de la Torre, S.; Sánchez-Racero, A.J.; Aguado, J.A.; Reyes, M.; Martínez, O. Optimal Sizing of Energy Storage for Regenerative Braking in Electric Railway Systems. IEEE Trans. Power Syst. 2015, 30, 1492–1500. [Google Scholar] [CrossRef]
  26. Graber, G.; Calderaro, V.; Galdi, V.; Ippolito, L.; Massa, G. Impact Assessment of Energy Storage Systems Supporting DC Railways on AC Power Grids. IEEE Access 2022, 10, 10783–10798. [Google Scholar] [CrossRef]
  27. Graber, G.; Calderaro, V.; Galdi, V.; Piccolo, A.; Lamedica, R.; Ruvio, A. Techno-economic Sizing of Auxiliary-Battery-Based Substations in DC Railway Systems. IEEE Trans. Transp. Electrif. 2018, 4, 616–625. [Google Scholar] [CrossRef]
  28. Yuan, J.; Peng, L.; Zhou, H.; Gan, D.; Qu, K. Recent research progress and application of energy storage system in electrified railway. Electr. Power Syst. Res. 2024, 226, 109893. [Google Scholar] [CrossRef]
  29. Fabre, J.; Ladoux, P.; Caron, H.; Verdicchio, A.; Blaquière, J.M.; Flumian, D.; Sanchez, S. Characterization and Implementation of Resonant Isolated DC/DC Converters for Future MVdc Railway Electrification Systems. IEEE Trans. Transp. Electrif. 2021, 7, 854–869. [Google Scholar] [CrossRef]
  30. Fortes, G.; Ladoux, P.; Fabre, J.; Flumian, D. Characterization of a 300 kW Isolated DCDC Converter using 3.3 kV SiC-MOSFETs. In Proceedings of the PCIM Europe digital days 2021; International Exhibition and Conference for Power Electronics, Intelligent Motion, Renewable Energy and Energy Management, Online, 3–7 May 2021; pp. 1–8. [Google Scholar]
  31. Hannan, M.A.; Ker, P.J.; Lipu, M.S.H.; Choi, Z.H.; Rahman, M.S.A.; Muttaqi, K.M.; Blaabjerg, F. State of the Art of Solid-State Transformers: Advanced Topologies, Implementation Issues, Recent Progress and Improvements. IEEE Access 2020, 8, 19113–19132. [Google Scholar] [CrossRef]
  32. Laboure, E.; Cuniere, A.; Meynard, T.A.; Forest, F.; Sarraute, E. A Theoretical Approach to InterCell Transformers, Application to Interleaved Converters. IEEE Trans. Power Electron. 2008, 23, 464–474. [Google Scholar] [CrossRef]
  33. EU 50163/2005; Railway Applications-Supply Voltages of Traction Systems. European Standard: Geneva, Switzerland, 2005.
  34. Kim, H.J.; Krishna, T.; Zeb, K.; Rajangam, V.; Gopi, C.V.V.M.; Sambasivam, S.; Raghavendra, K.V.G.; Obaidat, I.M. A Comprehensive Review of Li-Ion Battery Materials and Their Recycling Techniques. Electronics 2020, 9, 1161. [Google Scholar] [CrossRef]
  35. Fabre, J.; Ladoux, P.; Caron, H. Fixed (Trackside) Energy Storage System for DC Electric Railways Based on Full-SiC Isolated DC-DC Converters. Electronics 2023, 12, 1675. [Google Scholar] [CrossRef]
  36. EU 50338/2022; Railway Applications-Fixed Installations and Rolling Stock-Technical Criteria for the Coordination between Electric Traction Power Supply Systems and Rolling Stock to Achieve Interoperability—Part 1: General. European Standard: Geneva, Switzerland, 2022.
  37. Plexim. PLECS The Simulation Platform for Power Electronic Systems; Technical Report; Plexim: Zurich, Switzerland, 2024. [Google Scholar]
Figure 1. Representation of a DC electrified double-track railway system.
Figure 1. Representation of a DC electrified double-track railway system.
Electronics 13 01933 g001
Figure 2. Alternative solutions for reinforcing the DC electrified railways include integrating three-wire DC power feeders, battery energy storage systems and renewable energy sources.
Figure 2. Alternative solutions for reinforcing the DC electrified railways include integrating three-wire DC power feeders, battery energy storage systems and renewable energy sources.
Electronics 13 01933 g002
Figure 3. Topology of the SiC-based Isolated DC/DC elementary converter.
Figure 3. Topology of the SiC-based Isolated DC/DC elementary converter.
Electronics 13 01933 g003
Figure 4. Modularity of the BESS: q elementary converters in series, N elementary BESS in parallel, and battery composed of p racks in parallel.
Figure 4. Modularity of the BESS: q elementary converters in series, N elementary BESS in parallel, and battery composed of p racks in parallel.
Electronics 13 01933 g004
Figure 5. Modeling of the MBESS: (a) averaged model of the elementary DC/DC converter; (b) averaged model of the MBESS with q elementary blocks connected in ISOP configuration.
Figure 5. Modeling of the MBESS: (a) averaged model of the elementary DC/DC converter; (b) averaged model of the MBESS with q elementary blocks connected in ISOP configuration.
Electronics 13 01933 g005
Figure 6. (a) Control block diagram of the MBESS and (b) MBESS input voltage-current characteristics.
Figure 6. (a) Control block diagram of the MBESS and (b) MBESS input voltage-current characteristics.
Electronics 13 01933 g006
Figure 7. Equivalent circuit of a double-track sector of length D with paralleling station PS at the middle.
Figure 7. Equivalent circuit of a double-track sector of length D with paralleling station PS at the middle.
Electronics 13 01933 g007
Figure 8. View of the k t h subsector of length L k , considering that in case (a) x 2 k 1 > x 2 k , and in case (b) x 2 k > x 2 k 1 .
Figure 8. View of the k t h subsector of length L k , considering that in case (a) x 2 k 1 > x 2 k , and in case (b) x 2 k > x 2 k 1 .
Electronics 13 01933 g008
Figure 9. Flowchart of MBESS sizing to find the minimum values of V r e f and N that ensures V l o c , i V l o c , m i n .
Figure 9. Flowchart of MBESS sizing to find the minimum values of V r e f and N that ensures V l o c , i V l o c , m i n .
Electronics 13 01933 g009
Figure 10. Representation of the railway sector provided by SNCF-Réseau. It consists of a double-track sector with trains circulating in each direction.
Figure 10. Representation of the railway sector provided by SNCF-Réseau. It consists of a double-track sector with trains circulating in each direction.
Electronics 13 01933 g010
Figure 11. Railroad traffic between the substations of Crèches-Romanèche (left side) and Le Theil-Sceaux-Boëssé (right side): (a,b) P k , (c,d) P l o c , (e,f) I e x t .
Figure 11. Railroad traffic between the substations of Crèches-Romanèche (left side) and Le Theil-Sceaux-Boëssé (right side): (a,b) P k , (c,d) P l o c , (e,f) I e x t .
Electronics 13 01933 g011
Figure 12. Pantograph voltage of the locomotives before (upside) and after (downside) the installation of the MBESS on the railway sector: (a,c) trains departing from Crèches; (b,d) trains departing from Romanèche.
Figure 12. Pantograph voltage of the locomotives before (upside) and after (downside) the installation of the MBESS on the railway sector: (a,c) trains departing from Crèches; (b,d) trains departing from Romanèche.
Electronics 13 01933 g012
Figure 13. Pantograph voltage of the locomotives before (upside) and after (downside) the installation of the MBESS on the railway sector: (a,c) trains departing from Le Theil; (b,d) trains departing from Sceaux-Boëssé.
Figure 13. Pantograph voltage of the locomotives before (upside) and after (downside) the installation of the MBESS on the railway sector: (a,c) trains departing from Le Theil; (b,d) trains departing from Sceaux-Boëssé.
Electronics 13 01933 g013
Figure 14. Time-zoomed view between 18:36 and 18:48 hours during a freight train passage with two high-power peaks departing from Crèches: (a) pantograph voltage of the locomotive V l o c ; (b) battery rack voltage V b a t , (c) contact-line voltage V c l at PS; and (d) contact-line current I c l at PS and battery current I b a t . Remark: q = 1 and p = 3.
Figure 14. Time-zoomed view between 18:36 and 18:48 hours during a freight train passage with two high-power peaks departing from Crèches: (a) pantograph voltage of the locomotive V l o c ; (b) battery rack voltage V b a t , (c) contact-line voltage V c l at PS; and (d) contact-line current I c l at PS and battery current I b a t . Remark: q = 1 and p = 3.
Electronics 13 01933 g014
Figure 15. (a) Simulated characteristic of contact-line voltage V c l  versus contact-line current I c l obtained from simulation over the time horizon of case study Crèches-Romanèche; (b) MBESS state-of-charge at the end of peak traffic. From 16:00 to 21:00, the batteries are discharged to supply the trains. After 22:00, the batteries are recharged to 100%.
Figure 15. (a) Simulated characteristic of contact-line voltage V c l  versus contact-line current I c l obtained from simulation over the time horizon of case study Crèches-Romanèche; (b) MBESS state-of-charge at the end of peak traffic. From 16:00 to 21:00, the batteries are discharged to supply the trains. After 22:00, the batteries are recharged to 100%.
Electronics 13 01933 g015
Table 1. RDBC and TISC parameters.
Table 1. RDBC and TISC parameters.
ParametersSymbolValue
Input voltage range V i n 1.3–1.8 kV
Output voltage range V o u t 0.56–1.1 kV
Nominal power P n 300 kW
RDBC switching frequency f R D B C 15 kHz
RDBC resonance frequency f 0 19.37 kHz
TISC switching frequency f T I S C 7.5 kHz
Input capacitor C i n 60 μ F
DC-link capacitor C d c 120 μ F
ICT self-inductance L 1 = L 2 1.35 mH
ICT mutual inductanceM1 mH
Table 2. MFT parameters.
Table 2. MFT parameters.
ParametersSymbolValue
Turns ration1:1
Input voltage range V 1 1.3–1.8 kV
Nominal power S n 400 kVA
Isolation level V i s o 20 kV
Total weight-160 kg
Total volume-45 L
Cooling system-Water (5 L/min)
Table 3. Number of elementary converters and battery racks in an MBESS in function of the DC electrification system.
Table 3. Number of elementary converters and battery racks in an MBESS in function of the DC electrification system.
Ref.Nominal
Voltage (kV)
Lowest *
Voltage (kV)
Highest *
Voltage (kV)
qp
[33]1.51.01.813
3.02.03.627
[10]6.04.07.2414
9.06.010.8621
* Permanent operation.
Table 4. Characteristics of one battery rack.
Table 4. Characteristics of one battery rack.
ParametersSymbolValue
Number of battery modules in series N b 14
Nominal voltage V b a t , r a c k 717 V
Nominal capacity C n , r a c k 120 Ah
Energy E b a t , r a c k 86 kWh
Max. discharge current (1.0 C n ) I m a x , d 120 A
Max. charge current (0.5 C n ) I m a x , c 60 A
Depth of DischargeDoD>90%
Table 5. Parameters of the two railway sectors investigated in the case study.
Table 5. Parameters of the two railway sectors investigated in the case study.
Crèches-Romanèche Sector
ParameterSymbolValue
Substation spacingD8 km
Number of subsectorsk2
Substation 1 no-load voltage E s s , 1 1750 V
Substation 1 internal resistance R s s , 1 28 m Ω
Substation 2 no-load voltage E s s , 2 1750 V
Substation 2 internal resistance R s s , 2 28 m Ω
Contact-line cross-section S c 432 mm²
Rail weight per unit length W t 50 kg/m²
Le Theil-Sceaux-Boëssé sector
ParameterSymbolValue
Substation spacingD19.4 km
Number of subsectorsk4
Substation 1 no load voltage E s s , 1 1750 V
Substation 1 internal resistance R s s , 1 21 m Ω
Substation 2 no load voltage E s s , 2 1750 V
Substation 2 internal resistance R s s , 2 70 m Ω
Contact-line cross-section S c 368 mm²
Rail weight per unit length W t 60 kg/m²
Table 6. Preliminary assessment of traffic in each sector from 16:00 to 21:00.
Table 6. Preliminary assessment of traffic in each sector from 16:00 to 21:00.
ParametersCrèches-RomanècheLe Theil-Sceaux-Boëssé
Number of trains running from left to right107
Number of trains running from right to left259
Average travel time from left to right4.27 min14.16 min
Average travel time from right to left5.29 min15.47 min
Mean of the averaged power drawn from trains running from left to right1.44 MW0.85 MW
Mean of the averaged power drawn from trains running from right to left1.90 MW1.23 MW
Average value of the energy absorbed by trains running from left to right94.86 kWh200.41 kWh
Average value of the energy absorbed by trains running from right to left171.06 kWh312.71 kWh
Table 7. Sizing parameters of the MBESS.
Table 7. Sizing parameters of the MBESS.
ParameterCrèches-RomanècheLe Theil-Sceaux-Boëssé
N108
V r e f 1580 V1630 V
Table 8. Crèches-Romanèche railway sector energy balancing before and after the installation of the MBESS.
Table 8. Crèches-Romanèche railway sector energy balancing before and after the installation of the MBESS.
ParametersSymbolInitial SituationAfter MBESS Installation
Sum of energies absorbed by trains running from Crèches to Romanèche E l o c , 1 0.95 MWh0.95 MWh
Sum of energies absorbed by trains running from Romanèche to Crèches E l o c , 2 4.28 MWh4.28 MWh
Total energy provided by the substation at Crèches E s u b , 1 2.60 MWh2.51 MWh
Total energy provided by the substation at Romanèche E s u b , 2 3.35 MWh3.30 MWh
Energy efficiency η g l o b a l 87.90%90.02%
Table 9. Le Theil-Sceaux-Boëssé railway sector energy balancing before and after the installation of the MBESS.
Table 9. Le Theil-Sceaux-Boëssé railway sector energy balancing before and after the installation of the MBESS.
ParametersSymbolInitial SituationAfter MBESS Installation
Sum of energies absorbed by trains running from Le Theil to Sceaux-Boëssé E l o c , 1 1.40 MWh1.40 MWh
Sum of energies absorbed by trains running from Sceaux-Boëssé to Le Theil E l o c , 2 2.82 MWh2.82 MWh
Total energy provided by the substation at Le Theil E s u b , 1 2.84 MWh2.75 MWh
Total energy provided by the substation at Sceaux-Boëssé E s u b , 2 2.21 MWh2.17 MWh
Energy efficiency η g l o b a l 83.56%85.77%
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

da Silveira Brito, E.M.; Ladoux, P.; Fabre, J.; Sonier, B. Reinforcement of DC Electrified Railways by a Modular Battery Energy Storage System. Electronics 2024, 13, 1933. https://doi.org/10.3390/electronics13101933

AMA Style

da Silveira Brito EM, Ladoux P, Fabre J, Sonier B. Reinforcement of DC Electrified Railways by a Modular Battery Energy Storage System. Electronics. 2024; 13(10):1933. https://doi.org/10.3390/electronics13101933

Chicago/Turabian Style

da Silveira Brito, Erick Matheus, Philippe Ladoux, Joseph Fabre, and Benoit Sonier. 2024. "Reinforcement of DC Electrified Railways by a Modular Battery Energy Storage System" Electronics 13, no. 10: 1933. https://doi.org/10.3390/electronics13101933

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop