Next Article in Journal
Short-to-Medium-Term Wind Power Forecasting through Enhanced Transformer and Improved EMD Integration
Next Article in Special Issue
Analyzing Current Trends in Career Choices and Employer Branding from the Perspective of Millennials within the Indonesian Energy Sector
Previous Article in Journal
Effect of Biochar on Anaerobic Co-Digestion of Untreated Sewage Sludge with Municipal Organic Waste under Mesophilic Conditions
Previous Article in Special Issue
Towards Energy Transformation: A Case Study of EU Countries
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Methodology for Selecting a Location for a Photovoltaic Farm on the Example of Poland

1
Mineral and Energy Economy Research Institute of the Polish Academy of Sciences, Wybickiego 7A, 31-261 Krakow, Poland
2
Faculty of Electrical Engineering, Czestochowa University of Technology, Armii Krajowej 17, 42-200 Czestochowa, Poland
*
Author to whom correspondence should be addressed.
Energies 2024, 17(10), 2394; https://doi.org/10.3390/en17102394
Submission received: 28 March 2024 / Revised: 12 May 2024 / Accepted: 13 May 2024 / Published: 16 May 2024

Abstract

:
As the LCOE for photovoltaics has decreased several times, it is once again gaining popularity. The intensification of the development of PV installations is contributing to the duck curve phenomenon in an increasing number of countries and, consequently, affecting current electricity prices. Decisions on new investments in large-scale PV sources are driven by potential economic and environmental effects, and these, in turn, are subject to locational considerations, both as to the country and its region. In calculating the economic impact of locating a 1 MWp PV farm, it was assumed that the electricity generated by the farm would be fed into the national grid, and that the life of the PV farm would be 20 years. Poland was considered as an example country for the placement of a photovoltaic farm. The authors of this paper proposed that the main verification parameter is the availability of connection capacities to feed the produced electricity into the country’s electricity grid. The methodology proposed by the authors for the selection of the location of a PV farm consists of four steps: step (i) identification and selection of the administrative division of a given country; step (ii) verification of available connection capacities; step (iii) (two stages) verification of other factors related to the location of the PV farm (e.g., information on land availability and the distance of the land from the substation), and analysis of productivity at each potential location and electricity prices achieved on the power exchange; step (iv) economic analysis of the investment—analyses of PV farm energy productivity in monetary terms on an annual basis, cost analysis (CAPEX, OPEX) and evaluation of economic efficiency (DPP, NPV, IRR). The greatest impact on the economic efficiency of a PV project is shown by the value of land (as part of CAPEX), which is specific to a given location, and revenues from energy sales, which are pretty similar for all locations.

1. Introduction

In recent years, many countries have begun to intensify their decarbonisation targets under the Paris Agreement [1] (with its subsequent ratifications) for reducing greenhouse gas emissions. These changes particularly accelerated in the face of the 2022 energy crisis triggered by Russia’s aggression against Ukraine. At that time, many countries became independent of Russian raw materials [2].
In the case of the European Union, in order to become independent of Russian fossil fuels, the EU Commission presented the REPowerEU Plan [3] for the transformation of the European energy system, involving, among others, the accelerated introduction of renewable energy. This also coincided with the first upgrade of the National Energy and Climate Plans (NECPs), which were due in 2023. The NECPs are implemented by the European Union Member States, which are obliged to implement them by virtue of the regulation [4]. The regulation (Regulation EU, 2018) was agreed in the Clean Energy for All Europeans package [5], in line with the objectives of the European Green Deal [6]. At the beginning of December 2023, a draft of the first update had already been submitted by 22 EU Member States [7].
Analysing the drafts first update of the NECPs, it can be seen that some of the countries listed have set very ambitious emission reduction targets (relative to 1990) of 55% or more by 2030, among others: 78% Romania [8] 70% each Denmark [9] and Lithuania [10], 65% Germany [11], 63% Czechia [12], 60% Finland [13], and 55% each Italy [14], Luxemburg [15] (relative 2005), Malta [16], Slovakia [17] and Portugal [18]. Some of the EU countries set reduction targets at a slightly lower level than the October 2023 updated Fit to 55 climate package [19], at just above 50%. These were: Greece, emission reduction of 54% [20]; France [21] and Hungary [22], emission reductions of 50% each.
Some countries have also revised their national energy policies, introducing not only ambitious climate targets, but also including an energy security aspect. In Poland, the assumptions for the update of the current energy policy until 2040 were adopted on 29 March 2022 [23]. According to the assumptions presented in [23], by 2040, among other things, around half of the electricity generation is to come from renewable sources. In 2022, the US presented the National Security Strategy [24]. According to this strategy [24], a target was set for the regional electricity sector to reach a 70% share of installed renewable energy capacity in 2030. Still, in 2021, the country ratified the Paris Agreement and set a new target for greenhouse gas emission reductions in the 2030 horizon of 50–52% net [25]. In June 2022, China’s National Development and Reform Commission published its 14th Five-Year Renewable Energy Plan, consistent with existing targets and policies [26]. According to the assumptions presented, the share of renewable energy in electricity generation is expected to reach 33% in 2025.
Solar energy is one of the most important clean energy carriers. It has experienced significant growth in recent years. Between 2010 and 2022, solar power experienced the largest increase in generation capacity globally: according to data [27], it increased 29-fold to 1145 GW, and solar PV-based electricity generation increased 40-fold to 1291 TWh. According to the Net Zero Emissions scenario [27], solar PV is still expected to be one of the fastest-growing generation streams in the 2030 timeframe. Compared to 2022, its share of the global generation mix is expected to increase by as much as 17 percentage points, to 21%.
It should also be mentioned that solar energy is a sustainable, as well as relatively clean and relatively inexpensive, energy source [28,29]; however, it is unstable. A detailed description of the selection of a photovoltaic farm location in Poland is presented in [30]. This article also presents other formal legal procedures related to the construction of a photovoltaic farm; among others [30]: its design, the environmental permit, an individual planning permit, and the document that specifies the grid connection requirements.
The use of the AHP method for selecting a plot of land for the location of a PV farm in Poland is described by [31]. In [31], for the municipality of Czarnia (north-eastern Poland), the authors presented a ranking of land plots from the point of view of a potential PV farm location.
An analysis of the economic and social, as well as spatial, determinants of the location of a photovoltaic farm was carried out by [32]. In the analyses presented, ref. [32] focused on the regional division of Poland (at the level of provinces), using the scenario method as well as multiple regression analysis.
In the case of a photovoltaic farm, the selection of its location is an important issue; however, it is fraught with some risk. In order to determine this risk [28], the use of the Dempster–Shafer method was proposed. Geographical Information Systems (GIS) are often used to assess the optimal location of PV farms [28,33,34,35,36], combined with multi-criteria decision-making (MCDM) [28,33,34,35,37].
Due to such a significant development of solar PV generation, and based on a literature review, the authors of this article decided to analyse the site selection methodology for the location of a 1 MWp PV farm. The purpose of the study is to demonstrate how significantly the choices of different locations within the scale of one region or country can influence investment decisions. Poland was chosen as an example country for the location of a PV farm in this article. The innovation of the proposed scheme lies in its incorporation of the relationship between photovoltaic-specific yields for different regions of the country and actual energy prices (hour by hour). This enables the identification of locations where energy productivity may not be the highest, but the potential for additional revenue is greater. This aspect is often overlooked in the identified analyses, for example, by Demir et al. [38].
The main limitations of this study include the reliance on highly fluctuating electricity prices (2018–2022), as well as the scarcity of available locations for PV installations due to national grid capacity and regulations, and also land prices.

2. Materials and Methods

When considering the methodology for locating a PV farm anywhere in the world, it was assumed that a 1 MWp PV farm would be built. It was also assumed that the investor has sufficient funds available to build a PV farm installation on the scale of at least 1 MWp, which means funds of approximately EUR 500,000. The electricity generated by the farm will be fed into the national electricity grid. It was also assumed that the lifetime will be 20 years. In their analysis, the authors did not take into account any subsidies or certain facilities/investor incentives from the local government administration (in the case of Poland: municipality/county/province).
The site selection methodology algorithm proposed by the authors of this article for the location of a photovoltaic farm (Figure 1) consists of four steps.

2.1. Choice of Administrative Division

In the first step, the region was identified and selected, e.g., according to the administrative division of the country. In the case of Poland, there is a three-tier administrative division of the country [39]. The following administrative units are distinguished [39]: first level—16 provinces, second level—314 powiats and 66 cities with powiat (the second-level unit of local government and administration in Poland) status, third level—2489 municipalities (including 11 municipalities of the capital city of Warsaw). In this article, the authors propose to focus on the first degree of administrative division, which is the provinces.

2.2. Verification of Available Connection Capacities

In the second step, a proposal was made for available connection capacities within a given country/region to be verified. In the case of Poland, each voivodship was taken into account as the region under consideration. Then, information from Distribution Network Operators in Poland was used to analyse the available connection capacities. Pursuant to the Energy Law [40], they were obliged to publish values of the total available connection capacity for sources, as well as planned changes to those values within the next 5 years from the date of their publication. This applies for the entire network of the companies with rated voltage above 1 kV, with a division into substations or their groups included in the network with rated voltage of 110 kV and higher. The data obtained were estimates, but reflect the state of each network at the date of the study. The author team analysed the data made available by the operators that are part of the capital groups: Tauron [41], Polska Grupa Energetyczna [42], Enea [43] and Energa [44].
On the basis of the information obtained, it was found that 12 of the 16 provinces analysed had available connection capacities. For each of the 12 provinces, one main supply point was randomly selected. The locations of these selected points are presented in Figure 2. For each of these selected points, the geographical coordinates were determined (longitude and latitude) using a publicly available web portal showing the electricity grid map [45]. This information will be used to calculate the productivity at the selected points of the analysis.

2.3. PV Specific Yields Analyses for Each Region and Year

The third step of the proposed methodology for the verification of factors affecting the productivity of the farm is divided into two stages. In the first stage, other factors related to the location of the photovoltaic farm are verified. The following are analysed, among others: information on land availability and the distance of the land from the main feed-in point (feed-in station). In the case considered in this article, land availability within a ±5 km radius from the main feed point was taken into account.
The second stage in step three concerns the analysis of productivity at each potential location and the electricity prices achieved on the power exchange. For each of the 12 selected locations, productivity was calculated for an angle of inclination ranging from 30 to 50 degrees, in increments of 1 degree. This range was chosen based on [30,47]. Hourly energy values produced by the PV installation were calculated according to Formula (1). This formula has been validated under Polish conditions and is based on the work of [47,48,49,50]:
P P V ( τ , β , r e g . , y . ) = Y P V × F P V × G τ , β , r e g . , y G S T C × ( 1 + α p ( T C ( τ , r e g . , y . ) T S T C ) ) × 1 h
where
  • PPV—hourly energy output of photovoltaic panels, kWh/kWp;
  • YPV—rated capacity of the PV array, which implies that its output power under standard test conditions was used (1 MWp), MW/MWp;
  • FPV—PV derating factor, 0.90 based on [51];
  • G—available intensity of solar radiation incident on surface dependent on time and panel tilt angle, based on ERA5 data [52] and HDKR mode, W/m2;
  • GSTC—incident radiation at Standard Test Conditions, 1 kW/m2;
  • αp—temperature coefficient of power, based on Longhi PV Data (0.37) %/°C;
  • TC—PV cell temperature, based on the equation included in [53] and ERA5 data for each region, °C;
  • TSTC—PV cell temperature under standard test conditions (25 °C);
  • reg.—region;
  • y.—year.
The PPV values were then summed for each region and each panel angle considered. The graphs in Figure 3 show the results of the productivity thus calculated, expressed in [MWh/MWp], for the two extreme cases: the provinces with minimum (Podlaskie) and maximum (Malopolskie) productivity.
In the next step, an analysis of electricity prices on the exchange between 2018 and 2022 was carried out. In the case of Poland, hourly electricity prices formed in the Day-Ahead Market and published on the web portal of the Polish Power Exchange (Towarowa Gielda Energii—TGE) were used [54]. Hourly prices expressed in PLN/MWh for the period from 1 January 2018 to 31 December 2022 were taken into account for the calculations. These prices were converted using the fixed exchange rate EUR/PLN = 4.5, and are presented in Figure 4.
Considering the time aspect, the last five years were taken at the beginning of the analysis: 2018–2022. However, due to the fact that the share of solar power in the Polish energy mix only became relatively significant between 2020 and 2022, this time period was chosen for further financial analysis. As recently as 2020, Poland (according to [55]) produced 2.0 TWh based on solar energy, which accounted for 1.2% of the Polish energy mix. In 2021, solar-based generation in Poland increased to 3.9 TWh (data [56]), and the share in the national energy mix increased to 2.2%. The year 2022 saw a further increase in solar generation to 8.1 TWh (according to [56]), and its share in the Polish fuel mix increased to 4.6%. According to [57], analysing photovoltaic generation globally, Poland’s share increased annually by 0.2 percentage points from 0.2% to 0.6% between 2020 and 2022, respectively.

2.4. Economic Analysis of the Investment

The fourth step of the proposed methodology analyses the final effects of interest to the investor, related to the financial aspect. In the end, it tentatively answers the question: will the investment be economically viable in the analysed location?

2.4.1. Factors Affecting Capital Expenditure

Among the important factors influencing the capital expenditure is the price of the land. In order to minimise costs, it was assumed that the land for the future photovoltaic farm would be a maximum of ±5 km from the substation. According to the applicable Polish regulation [58], all land uses are shown in the land and building register, with an additional soil quality class shown for agricultural and forest land. In Poland, land classification is carried out in accordance with the Regulation [58].
When recognising land prices, prices from official national statistics [59] and price offers from the current market were considered (Figure 5). In the case of market prices, three land price offers were retrieved for each selected potential location, using a publicly available online property trading portal [60].

2.4.2. Productivity Analysis in Monetary Terms

Another research element in the proposed methodology is the analysis of productivity in monetary terms. For each hour of the year, productivity was calculated and multiplied by the energy price (from the TGE quotation) according to Formula (2):
I n p u t ( τ , β , r e g . , y . ) = P P V ( τ , β , r e g . , y . ) × D A M ( τ , y . )
where
  • Input—revenues from the energy exchange or equivalent revenues;
  • DAM—energy market price, Day-Ahead Market.
The results of the maximum monetary value analysis for all analysed potential locations are presented in Figure 6. The data of the results of the maximum monetary value of productivity obtained in 2022 are presented in descending order. An important element influencing the obtained monetary values of productivity was the electricity prices from 2018 to 2022. The highest electricity prices occurred in 2022 (see Figure 4). For most of the year, they were several times higher than the energy prices of earlier years and, therefore, had a strong impact on the result, as shown in Figure 6.

2.4.3. Project Cost (CAPEX, OPEX)

In performing the economic analysis of the investment, the authors made the following assumptions:
  • The funds allocated for the investment in a 1 MWp photovoltaic farm are approximately EUR 500,000;
  • Weighted average cost of capital (WACC)—10%;
  • Depreciation rate—10%;
  • Tax rate—12%;
  • The costs of purchasing and installing PV farm components in each province are assumed to be the same;
  • OPEX assumed that the annual operating costs of the farm would be 2% of the total capital expenditure [61], with half of this amount covering expenses related to materials, energy, fuel, etc., and this would be the same for all locations and the rest would be labour costs;
  • Labour cost of operating the farm—in this case official national statistics on wages were used [59] (Table 1), whereby these statistics referred to salaries obtained within the county (County—administrative unit of the second order in Poland) in which the potential location of the photovoltaic farm is situated;
  • Land cost—in this case, land price offers from the current market were used (Figure 4).

2.4.4. Measures of Economic Efficiency of the Investment (DPP, NPV, IRR)

Three commonly used indicators were used to assess the economic efficiency of a 1 MWp PV farm for the twelve sites analysed: Discounted Pay-Back Period (DPP), Net Present Value (NPV) and Internal Rate of Return (IRR).
Discounted Pay-Back Period
The Discounted Pay-Back Period determines the time over which the invested funds will be returned, taking into account a discounting factor (e.g., inflation or the assumed cost of capital) [62]. It is determined according to Formula (3):
D P P = T D C F C A P E X
where
  • DPP—Discounted Pay-Back Period [year];
  • TDCF—total discounted incoming cash flow [EUR];
  • CAPEX—capital expenditure [EUR].
Net Present Value
The NPV method is still one of the most popular and profitable valuation methods, and is also used in the appraisal of renewable energy installations such as photovoltaic farms [63]. NPV reflects the value of the project at the discount rate used and a number of other cash flow assumptions, such as revenue projection, depreciation, residual value, etc., when capital expenditure is incurred only in the initial year of the investment. According to Formula (4), the net present value is the sum of the present values of the future annual cash flows:
N P V = t = 0 n C F t 1 + d t
where
  • CFt—cash flow for the year [PLN];
  • d—discount rate [%];
  • n—the total number of years required to complete the licensed operation.
Where capital expenditure is incurred in the initial year of investment only, the above formula takes the form of Equation (5).
N P V = t = 1 n C F t 1 + d t I 0
where
  • I0—initial investment [PLN].
Internal Rate of Return (IRR)
IRR can be defined as the rate that aligns the size of the initial investment with the present value of future cash flows. The higher the Internal Rate of Return, the greater the return on invested capital. The internal rate of return is defined as the discount rate at which the NPV is zero. The relationship between NPV and IRR is represented by Equation (6),
N P V = 0 = t = 1 n C F t 1 + I R R t I 0
where
  • CFt—cash flow in year t [PLN];
  • I0—initial investment [PLN];
  • IRR—Internal Rate of Return [%];
  • n—the total number of years required to complete the licensed operation.
From the perspective of the decision-maker, an investment should be made if the IRR is greater than the so-called MARR (minimum acceptable rate of return) that the investor is willing to accept before starting the project, given its risks [64]. When the IRR is greater than or equal to the discount rate, then we assume that the project generates flows capable of covering inputs and operating costs over the life of the investment project.

3. Results and Discussion

An important issue facing the developer is the choice of location for a photovoltaic farm. In their study on the optimal location for a photovoltaic farm, ref. [28] focused on choosing a site characterised by a high number of sunshine hours per year; in this case, the south-east of Fars province in Iran. The authors of this paper proposed that the main parameter was the availability of connection capacity to feed the electricity produced back into the national grid.
Table 2 presents the economic results obtained for 12 potential 1 MWp photovoltaic farm locations in Poland. Economic results were obtained on the basis of calculated annual productivity, specific CAPEX values (resulting from the same installation cost and variable land price) and the diversified value of annual OPEX.
As a result of the analysis, it was found that out of 12 analysed cases, the investment would be unprofitable only in 1 province (Lodz Province). The land purchase price was the main factor influencing this investment’s unprofitability. The price offer of land, in addition to the valuation class and technical classification (e.g., agricultural, forestry, construction land), is also influenced by, among others: location (in the city, in the countryside, outside built-up areas, etc.), utilities in the area, accessibility to access roads. In the case of the Lodz Province, the plot was located within an urban area, significantly increasing the plot’s value. In the remaining 11 locations, regional differences in profits were noted. An Internal Rate of Return (IRR) above 20% was achieved in four provinces: Malopolskie, Wielkopolskie, Swietokrzyskie and Lubuskie. A relationship was found between a shorter investment payback time and a higher NPV value for two provinces: Malopolskie and Wielkopolskie. In these two cases, the NPV exceeded EUR 400,000.
Figure 7 presents the results of the NPV sensitivity analysis for 12 potential locations of a 1 MWp PV farm in Poland. In each of the analysed cases, a ±20% change in CAPEX, Income and OPEX compared to the base value was taken into account.
Analysing the results presented in Figure 7, it can be stated that the profitability of individual investment projects depends mainly on the change in revenues and investment outlays. In the 12 cases analysed, a change of ±20% in annual revenues resulted in a modification of the NPV ranging from 48 to 418% compared to the base value. In the case of total investment outlays, their change of ±20% compared to the initial value resulted in an update of the NPV value ranging from 25 to 369%. The change in annual operating costs (OPEX) has a much smaller impact on the profitability of projects expressed in NPV (from 3.1 to 28.7%). With the exception of two locations (Lodzkie and Pomorskie Provinces), the sensitivity analysis in the range of ±20% in the remaining cases always indicated the profitability of a 1 MWp photovoltaic farm. In the case of a PV farm in the Pomorskie Province, an increase in CAPEX by 10% or a reduction in revenues by the same value resulted in a situation where the project becomes economically ineffective (NPV < 0); for this location, due to balancing on the verge of profitability, the largest relative changes in NPV occurred depending on the base amount. High investment outlays in the case of the Lodzkie province, related to the high cost of purchasing real estate, cause the permanent ineffectiveness of the project in the subject area of the sensitivity analysis.

4. Conclusions

This article proposes a methodology for selecting a site for locating a 1 MWp photovoltaic farm in Poland. It takes into account the location (network connection capacity, weather conditions over the years, land prices), installation prices and electricity prices occurring in periods of electricity production (2020–2022), as well as the sensitivity analysis. The results calculated according to the method were the IRR values, Discounted Pay-Back Time, and NPV for selected locations (according to network connection possibilities). The highest NPV value was shown for the Malopolskie Province and the lowest for the Lodzkie Province (mainly due to the high CAPEX resulting from the land price).
The proposed scheme can also be used in other regions or countries because it is based on the assessment of a given location in terms of PV productivity, OPEX, land cost and, above all, the available connection resulting from the energy policy of a given region and its characteristics.
The greatest advantage of the proposed scheme is the comparison of only those locations that can realistically be created due to the availability of connection power for renewable energy installations and their evaluation using proven and commonly understood economic measures. One of the most important aspects is that our method involves searching for locations where the energy production values peak during hours when electricity prices are potentially higher than in other places (energy production values). While the differences in value may not be significant on their own, when considering additional profit, they can sometimes be substantial (as comparison), especially in the future (higher RES/photovoltaic impact in national grid).
Investments in renewable energy sources increase the energy security of a given country. In the case of Poland, they are included in energy policy until 2040 [23].
A financial challenge for photovoltaics will be the introduction of the CBAM carbon border tax (Carbon Border Adjustment Mechanism) [65]. This tax will be levied on goods imported into the EU customs territory whose production involves high CO2 emissions. Until 1 October 2023, it was in a transitional phase, and from 1 January 2026, it will be in permanent force. The introduction of this tax will burden the supply of PV components from Asia, which will translate into an increase in costs.
The topics of further research will include a comparison of different countries in Europe in terms of economic indicators assessing the investment in a photovoltaic farm (including tax aspects), taking into account the value of land after the life of the photovoltaic installation, including the costs of dismantling/disposal. An additional area for future research is to ascertain the prospective relationships between the productivity of photovoltaic farms and electricity prices. Presently, there is an inverse correlation, as the high value of energy from PV at national scale coincides with relatively low electricity prices.

Author Contributions

Conceptualization, P.O., K.S.-S. and J.K.; methodology, P.O., K.S.-S. and J.K.; validation, P.O., K.S.-S. and J.K.; formal analysis P.O., K.S.-S., J.K. and M.S.; resources, P.O., K.S.-S., J.K. and M.S.; data curation, P.O. and K.S.-S.; writing—original draft preparation, P.O., K.S.-S., J.K. and M.S.; writing—review and editing, P.O., K.S.-S., J.K. and M.S.; visualization, K.S.-S.; supervision, P.O. All authors have read and agreed to the published version of the manuscript.

Funding

This research received no external funding.

Data Availability Statement

Data are contained within the article.

Acknowledgments

This work was carried out as part of the statutory research activity of the Mineral and Energy Economy Research Institute of the Polish Academy of Sciences.

Conflicts of Interest

The authors declare no conflicts of interest.

References

  1. The Paris Agreement. Available online: https://unfccc.int/process-and-meetings/the-paris-agreement (accessed on 2 December 2023).
  2. IEA Renewables 2022. Analysis and Forecast to 2027; IEA: Paris, France, 2022. [Google Scholar]
  3. REPowerEU Plan. Available online: https://commission.europa.eu/strategy-and-policy/priorities-2019-2024/european-green-deal/repowereu-affordable-secure-and-sustainable-energy-europe_en (accessed on 3 March 2024).
  4. Regulation EU Regulation (EU) 2018/1999 of the European Parliament and of the Council of 11 December 2018 on the Governance of the Energy Union and Climate Action; EUR-Lex—European Union: Brussels, Belgium, 2018; pp. 1–77.
  5. Clean Energy for All Europeans Package. Available online: https://energy.ec.europa.eu/topics/energy-strategy/clean-energy-all-europeans-package_en (accessed on 3 March 2024).
  6. Green Deal Communication from The Commission to The European Parliament, The European Council, The Council, The European Economic and Social Committee and The Committee of The Regions The European Green Deal; EUR-Lex—European Commission: Brussels, Belgium, 2019.
  7. NECP_EU National Energy and Climate Plans for 2021–2030. Available online: https://www.iea.org/policies/16822-national-energy-and-climate-plan-2021-2030 (accessed on 3 March 2024).
  8. NECP_RO Integrated National Energy and Climate Plan of Romania 2021–2030 Update First Draft Version; European Commission: Brussels, Belgium, 2023.
  9. NECP_DK Denmark’s 2023 Draft Update of the 2019 Integrated National Energy and Climate Plan; European Commission: Brussels, Belgium, 2023.
  10. NECP_LT Draft Updated National Energy and Climate Plan of the Republic of Lithuania 2021–2030; European Commission: Brussels, Belgium, 2023.
  11. NECP_DE Update of the Integrated National Energy and Climate Plan Draft Germany—Draft Updated NECP 2021–2030; European Commission: Brussels, Belgium, 2023.
  12. NECP_CZ Update of the Czech National Plan of the Republics in the Field of Energy and Climate; European Commission: Brussels, Belgium, 2023.
  13. NECP_FI Finland’s Integrated National Energy and Climate Plan Draft Update; European Commission: Brussels, Belgium, 2023.
  14. NECP_IT National Plan Integrated for Energy and Climate; European Commission: Brussels, Belgium, 2023.
  15. NECP_LU Integrated National Plan Energy and Climate in Luxembourg for the Period 2021–2030 Draft Update; European Commission: Brussels, Belgium, 2023.
  16. NECP_MT Malta Draft National Energy and Climate Plan 2021–2030; European Commission: Brussels, Belgium, 2023.
  17. NECP_SK Draft Update of the Integrated National Energy and Climate Plan for 2021–2030; European Commission: Brussels, Belgium, 2023.
  18. NECP_PT Portugal National Energy Plan and Climate 2021–2030 (NECP 2030) Update/Revision Draft Version; European Commission: Brussels, Belgium, 2023.
  19. Fit55 Commission Welcomes Completion of Key “Fit for 55’’ Legislation, Putting EU on Track to Exceed 2030 Targets. Available online: https://ec.europa.eu/commission/presscorner/detail/en/IP_23_4754 (accessed on 3 March 2024).
  20. NECP_GR National Energy and Climate Plan—Preliminary Draft Revised Version October 2023; European Commission: Brussels, Belgium, 2023.
  21. NECP_FR National Energy Climate-Plan of France—Draft Update; European Commission: Brussels, Belgium, 2023.
  22. NECP_HU National Energy and Climate Plan Revised Version 2023; European Commission: Brussels, Belgium, 2023.
  23. Gov_PL Principles for the Update of the Energy Policy of Poland until 2040. Available online: https://www.gov.pl/web/climate/energy-policy-of-poland-until-2040-epp2040 (accessed on 1 April 2024).
  24. US. National Security Strategy; The White House: Washington, DC, USA, 2022. Available online: https://www.whitehouse.gov/wp-content/uploads/2022/10/Biden-Harris-Administrations-National-Security-Strategy-10.2022.pdf (accessed on 3 March 2024).
  25. United States Department of State and the United States Executive Office of the President. US The Long-Term Strategy of the United States: Pathways to Net-Zero Greenhouse Gas Emissions by 2050; United States Department of State and the United States Executive Office of the President: Washington, DC, USA, 2021. [Google Scholar]
  26. China Released its 14th Five-Year Plan for Renewable Energy with Quantitative Targets for 2025. Available online: https://climatecooperation.cn/climate/china-released-its-14th-five-year-plan-for-renewable-energy-with-quantitative-targets-for-2025/ (accessed on 3 March 2024).
  27. IEA. World Energy Outlook; IEA: Paris, France, 2023. [Google Scholar]
  28. Mokarram, M.; Mokarram, M.J.; Khosravi, M.R.; Saber, A.; Rahideh, A. Determination of the optimal location for constructing solar photovoltaic farms based on multi-criteria decision system and Dempster–Shafer theory. Sci. Rep. 2020, 10, 8200. [Google Scholar] [CrossRef] [PubMed]
  29. Li, B.; Liu, Z.; Wu, Y.; Wang, P.; Liu, R.; Zhang, L. Review on photovoltaic with battery energy storage system for power supply to buildings: Challenges and opportunities. J. Energy Storage 2023, 61, 106763. [Google Scholar] [CrossRef]
  30. Kurowska, K.; Kryszk, H.; Bielski, S. Location and Technical Requirements for Photovoltaic Power Stations in Poland. Energies 2022, 15, 2701. [Google Scholar] [CrossRef]
  31. Agugliaro, F.M.; Kowalczyk, A.M.; Czy Za, S. Optimising Photovoltaic Farm Location Using a Capabilities Matrix and GIS. Energies 2022, 15, 6693. [Google Scholar] [CrossRef]
  32. Kocur-Bera, K. Are Local Commune Governments Interested in the Development of Photovoltaics in Their Area? An Inside View of Poland. Energies 2024, 17, 1895. [Google Scholar] [CrossRef]
  33. Sun, L.; Jiang, Y.; Guo, Q.; Ji, L.; Xie, Y.; Qiao, Q.; Huang, G.; Xiao, K. A GIS-based multi-criteria decision making method for the potential assessment and suitable sites selection of PV and CSP plants. Resour. Conserv. Recycl. 2021, 168, 105306. [Google Scholar] [CrossRef]
  34. Villacreses, G.; Martínez-Gómez, J.; Jijón, D.; Cordovez, M. Geolocation of photovoltaic farms using Geographic Information Systems (GIS) with Multiple-criteria decision-making (MCDM) methods: Case of the Ecuadorian energy regulation. Energy Rep. 2022, 8, 3526–3548. [Google Scholar] [CrossRef]
  35. Hasti, F.; Mamkhezri, J.; McFerrin, R.; Pezhooli, N. Optimal solar photovoltaic site selection using geographic information system–based modeling techniques and assessing environmental and economic impacts: The case of Kurdistan. Sol. Energy 2023, 262, 111807. [Google Scholar] [CrossRef]
  36. Benalcazar, P.; Komorowska, A.; Kamiński, J. A GIS-based method for assessing the economics of utility-scale photovoltaic systems. Appl. Energy 2024, 353, 122044. [Google Scholar] [CrossRef]
  37. Sánchez-Lozano, J.M.; Teruel-Solano, J.; Soto-Elvira, P.L.; Socorro García-Cascales, M. Geographical Information Systems (GIS) and Multi-Criteria Decision Making (MCDM) methods for the evaluation of solar farms locations: Case study in south-eastern Spain. Renew. Sustain. Energy Rev. 2013, 24, 544–556. [Google Scholar] [CrossRef]
  38. Demir, A.; Dinçer, A.E.; Yılmaz, K. A novel method for the site selection of large-scale PV farms by using AHP and GIS: A case study in İzmir, Türkiye. Sol. Energy 2023, 259, 235–245. [Google Scholar] [CrossRef]
  39. SP Administrative Division of Poland. Available online: https://stat.gov.pl/en/regional-statistics/classification-of-territorial-units/administrative-division-of-poland/ (accessed on 3 March 2024).
  40. Energy_PL. Announcement by the Speaker of the Sejm of the Republic of Poland of 19 May 2022 on the Announcement of the Consolidated Text of the Act—Energy Law; Parliament of the Republic of Poland: Warsaw, Poland, 2022. [Google Scholar]
  41. Tauron Available Grid Connection Capacity. Available online: https://www.tauron-dystrybucja.pl/przylaczenie-do-sieci/dostepne-moce (accessed on 2 February 2023).
  42. PGE. Table of the Total Available Connection Capacity [MW] for Sources Connected to the Grid with a Rated Voltage Higher than 1kV on the Premises of PGE Dystrybucja SA. Available online: https://pgedystrybucja.pl/przylaczenia/informacje-o-dostepnych-mocach-przylaczeniowych (accessed on 2 February 2023).
  43. ENEA. Connection to the Network. Information about Connections. Available online: https://www.operator.enea.pl/przylaczeniedosieci/Informacje%20o%20przyłączeniach (accessed on 2 February 2023).
  44. Energa. Information about Connection Status. Available online: https://energa-operator.pl/przylaczenie-do-sieci/informacje-o-stanie-przylaczen (accessed on 2 February 2023).
  45. Ebin Map of the Power Grid in Europe. Available online: https://ebin.josm.pl/electricity/#5/51.44/20.15 (accessed on 15 March 2023).
  46. Bing Maps in Excel BingMaps Microsoft. Available online: https://www.microsoft.com/en-us/maps/bing-maps/product (accessed on 15 March 2023).
  47. Jacobson, M.Z.; Jadhav, V. World estimates of PV optimal tilt angles and ratios of sunlight incident upon tilted and tracked PV panels relative to horizontal panels. Sol. Energy 2018, 169, 55–66. [Google Scholar] [CrossRef]
  48. Jordan, D.C.; Deceglie, M.G.; Kurtz, S.R. PV Degradation Methodology Comparison—A Basis for a Standard. In Proceedings of the 2016 IEEE 43rd Photovoltaic Specialists Conference, Portland, OR, USA, 5–10 June 2016. [Google Scholar]
  49. Olczak, P.; Komorowska, A. An adjustable mounting rack or an additional PV panel? Cost and environmental analysis of a photovoltaic installation on a household: A case study in Poland. Sustain. Energy Technol. Assess. 2021, 47, 101496. [Google Scholar] [CrossRef]
  50. Olczak, P. Comparison of modeled and measured photovoltaic microinstallation energy productivity. Renew. Energy Focus 2022, 43, 246–254. [Google Scholar] [CrossRef]
  51. Al Garni, H.Z.; Awasthi, A.; Ramli, M.A.M. Optimal design and analysis of grid-connected photovoltaic under different tracking systems using HOMER. Energy Convers. Manag. 2018, 155, 42–57. [Google Scholar] [CrossRef]
  52. ERA5 Copernicus Climate Change Service Climate Data Store (CDS). Available online: https://cds.climate.copernicus.eu/#!/home (accessed on 4 August 2023).
  53. Olczak, P.; Zelazna, A.; Matuszewska, D.; Olek, M. The “My Electricity” Program as One of the Ways to Reduce CO2 Emissions in Poland. Energies 2021, 14, 7679. [Google Scholar] [CrossRef]
  54. TGE Day-Ahead Market. Available online: https://tge.pl/electricity-dam (accessed on 15 August 2023).
  55. Polish Power Industry Statistics 2021; ARE: Warsaw, Poland, 2022.
  56. Polish Power Industry Statistics 2022; ARE: Warsaw, Poland, 2023.
  57. IEA. Solar PV Power Generation in the Net Zero Scenario, 2015–2030. Available online: https://www.iea.org/data-and-statistics/charts/solar-pv-power-generation-in-the-net-zero-scenario-2015-2030 (accessed on 3 March 2024).
  58. Regulation PL Rozporządzenie Rady Ministrów z dnia 12 Września 2012 r. w Sprawie Gleboznawczej Klasyfikacji Gruntów; Rada Ministrów Rzeczypospolitej Polskiej: Warsaw, Poland, 2012.
  59. SP_BDL Local Data Bank (BDL—Bank Danych Lokalnych). Statistics Poland. Warsaw. Available online: https://bdl.stat.gov.pl/bdl/start (accessed on 3 January 2023).
  60. Domimporta Sale. Available online: https://www.domiporta.pl/dzialke/sprzedam (accessed on 15 March 2023).
  61. Vartiainen, E.; Masson, G.; Breyer, C.; Moser, D.; Román Medina, E. Impact of weighted average cost of capital, capital expenditure, and other parameters on future utility-scale PV levelised cost of electricity. Prog. Photovolt. Res. Appl. 2020, 28, 439–453. [Google Scholar] [CrossRef]
  62. Azar, S.A.; Noueihed, N. The Discounted Payback in Investment Appraisal: A Case Study. Int. J. Bus. Adm. 2014, 5, 58–64. [Google Scholar] [CrossRef]
  63. Doughan, Y.; Salam, D.A. Techno-economic feasibility of using solar energy in small-scale broiler production. Energy Sustain. Dev. 2023, 77, 101337. [Google Scholar] [CrossRef]
  64. Reniers, G.; Talarico, L.; Paltrinieri, N. Cost-Benefit Analysis of Safety Measures. Dyn. Risk Anal. Chem. Pet. Ind. Evol. Interact. Parallel Discip. Perspect. Ind. Appl. 2016, 195–205. [Google Scholar]
  65. CBAM Carbon Border Adjustment Mechanism. Available online: https://taxation-customs.ec.europa.eu/carbon-border-adjustment-mechanism_en (accessed on 17 August 2023).
Figure 1. Proposed algorithm as part of the site selection methodology for the location of the farm. (Source: own study).
Figure 1. Proposed algorithm as part of the site selection methodology for the location of the farm. (Source: own study).
Energies 17 02394 g001
Figure 2. Poland map with the location of research points (Source: map base [46]).
Figure 2. Poland map with the location of research points (Source: map base [46]).
Energies 17 02394 g002
Figure 3. Calculated productivity on the basis of maximum values achieved for provinces in Poland; example, province with maximum (a) and minimum productivity (b) (Source: own calculations).
Figure 3. Calculated productivity on the basis of maximum values achieved for provinces in Poland; example, province with maximum (a) and minimum productivity (b) (Source: own calculations).
Energies 17 02394 g003
Figure 4. The course of the volatility of hourly electricity prices based on the Day-Ahead Market on TGE, 2018–2022 (Source: own elaboration on the basis of data [54]).
Figure 4. The course of the volatility of hourly electricity prices based on the Day-Ahead Market on TGE, 2018–2022 (Source: own elaboration on the basis of data [54]).
Energies 17 02394 g004
Figure 5. Summary of land prices in the analysed survey points in Poland—logarithmic scale (Source: own elaboration on the basis of data [59,60]).
Figure 5. Summary of land prices in the analysed survey points in Poland—logarithmic scale (Source: own elaboration on the basis of data [59,60]).
Energies 17 02394 g005
Figure 6. Results of the analysis of the maximum energy productivity of a PV farm in monetary terms on an annual basis (Source: own calculations).
Figure 6. Results of the analysis of the maximum energy productivity of a PV farm in monetary terms on an annual basis (Source: own calculations).
Energies 17 02394 g006
Figure 7. NPV sensitivity analysis for 12 potential locations of a 1 MWp PV farm in Poland. CAPEX, Income and OPEX in the range of 80–120% in relation to the base value [EUR in 20 years] (Source: own study).
Figure 7. NPV sensitivity analysis for 12 potential locations of a 1 MWp PV farm in Poland. CAPEX, Income and OPEX in the range of 80–120% in relation to the base value [EUR in 20 years] (Source: own study).
Energies 17 02394 g007
Table 1. Table with data adopted for further calculations.
Table 1. Table with data adopted for further calculations.
SpecificationSalaryLand PriceMaximum Productivity
ProvinceCounty20212022202020212022
EUR/monthEUR/haMWh/MWpMWh/MWpMWh/MWp
DolnoslaskieLuban110797,667121911671254
LubelskieZamosc972171,911120412071203
LubuskieKrosno113917,778118011181212
Lodzkiecity Łodz1347666,511119911791223
MalopolskieMiechow10907733124412181251
MazowieckieWarsaw-
Western
1450149,822119311691201
PodlaskieWysokie
Mazowieckie
119955,556115311411147
PomorskieChojnice1068295,578110911231192
SlaskieZawiercie1291167,600122712071251
SwietokrzyskieOstrowiec Swietokrzyski109251,467121012031223
WielkopolskieKolo11888466119111731223
ZachodniopomorskieGryfino1177125,244116711151211
Discount Rate (WACC)10.0%
Deprecation Rate10.0%
Tax Rate12.0%
Table 2. Economic results calculated for 12 potential 1 MWp photovoltaic farm locations in Poland.
Table 2. Economic results calculated for 12 potential 1 MWp photovoltaic farm locations in Poland.
SpecificationRevenueCAPEXOPEXNPVIRRUndisc. Payback
Period
Partial Year Payback
Period
Discounted Payback PeriodPartial Year Payback Period
ProvinceEUR/MWp/YearEUREUREUR/20 Year%First Year PositiveActual Number of YearsFirst Year PositiveActual Number of Years
Dolnoslaskie139,249−597,6679150310,01318%54.676.5
Lubelskie141,562−671,9118645250,02316%65.187.4
Lubuskie133,502−517,7789270353,65120%54.265.7
Lodzkie139,315−1,166,51110,050−315,9365%109.02524.4
Malopolskie143,184−507,7339090437,53523%43.855.0
Mazowieckie138,266−649,82210,435236,29916%65.187.5
Podlaskie134,289−555,5569495316,63019%54.576.2
Pomorskie132,689−795,578900546,99111%76.41110.8
Slaskie142,346−667,6009840251,55916%65.087.4
Swietokrzyskie141,490−551,4679095377,32720%54.265.7
Wielkopolskie139,057−508,4669455403,48422%43.965.2
Zachodnio-pomorskie132,747−625,2449415229,90616%65.187.4
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Stala-Szlugaj, K.; Olczak, P.; Kulpa, J.; Soltysik, M. Methodology for Selecting a Location for a Photovoltaic Farm on the Example of Poland. Energies 2024, 17, 2394. https://doi.org/10.3390/en17102394

AMA Style

Stala-Szlugaj K, Olczak P, Kulpa J, Soltysik M. Methodology for Selecting a Location for a Photovoltaic Farm on the Example of Poland. Energies. 2024; 17(10):2394. https://doi.org/10.3390/en17102394

Chicago/Turabian Style

Stala-Szlugaj, Katarzyna, Piotr Olczak, Jaroslaw Kulpa, and Maciej Soltysik. 2024. "Methodology for Selecting a Location for a Photovoltaic Farm on the Example of Poland" Energies 17, no. 10: 2394. https://doi.org/10.3390/en17102394

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop