1. Introduction
The pile foundation, a slender structure often used for transferring the load from the upper structure to the soil [
1], can generally be categorized as a precast pile or a cast in situ pile according to the piling construction method used. Onsite piling is more suitable for high-rise buildings because it is easy to drill a deep hole for the cast. As for projects that do not need substantial compression capacity, a precast pile foundation is the optimum option. Further, prefabricated piles are more cost effective than bored piles [
2].
When a pile is cast in soil, the shaft and end resistance contribute to the pile capacity, and therefore, studies have designed numerous methods, such as grouting technology, to increase the shaft and the base area [
3,
4]. As for the precast pile, and, in particular, the steel precast pile, the effects of adding helixes up to the tip have been examined. One study demonstrated that the pile’s bearing capacity can be improved by adding the helix [
5]. Further studies have focused on determining the number of helixes to be used as well as the design with the optimum distance between helixes [
6,
7,
8,
9].
The helix pile can also be used as an uplift resisting structure, and its capacity can be determined through two methods: the individual and the cylindrical methods. In the individual method, it is assumed that each blade that contacts the soil will contribute to the ultimate uplift bearing capacity, whereas in the cylindrical method, it is assumed that the shaft resistance created by the soil from the extreme top and bottom blades (the cylinder volume) will contribute to this capacity [
10]. The authors of [
11,
12] investigated the use of the screw pile in sand, silt and clay. Recently, [
13] updated the cylindrical shear method equations. Further, [
14] focused on the proposed factor values, such as the bearing capacity factor Nc, in calculating the uplift capacity.
In addition to the helix pile showing better load capacity, these blade piles are easy to install because of the presence of the helix. Traditional solid precast piles have often been criticized because driving these into hard soil is difficult, and the process, which requires the use of a hammer drive, results in significant noise; however, this issue has been solved because small size precast piles are being used these days, for these are easy to install and the process is less noisy [
15].
Many researchers have also investigated the correlation between the installation torque and its designed capacity. An empirical study showed that there is a direct correlation between the axial ultimate load capacity and the installation torque [
16]. Furthermore, a later study investigated the relationship between the uplift bearing capacity and the installation torque and proposed an empirical torque factor, which is related to the diameter of the spiral and the friction angle of the sand [
17].
Resistance to lateral loads is also an important function of pile foundations in practical applications. According to [
18], pile foundations for structures often involve crane towers or offshore platforms, and these structures are used for resisting the lateral movement caused by the external environment. However, limited research has focused on the helix pile when using blades to resist the lateral load caused by wind action. Moreover, a suitable method is yet to be proposed to estimate the lateral bearing capacity when using screw piles. Further, onsite testing showed that the lateral bearing capacity of piles varies over a small range [
19]. In this context, this study considers the wind lateral load in examining the blade pile foundation embedded in clay soil.
2. FEM Simulation of Pile Foundation
2.1. Pile Geometry and Material Parameter
In civil engineering, the interaction between pile and soil is a complex process. They suggested that, due to the more complex nature of soil, it is not isotropic [
20]. Therefore, the interaction between the structure and the soil affects the expression of the structure. The finite element method (FEM) allows the analysis and processing of complex behaviors. Moreover, it is worth mentioning that numerical simulation methods have gained much popularity in recent years. Many researchers use finite element analysis in the study of pile–soil interactions [
21,
22,
23,
24,
25].
This study used Abaqus, a very popular finite element software, which allows researchers to simulate structure–soil interactions for examining the nonlinear behavior of soils. The finite element method (FEM) is commonly used to solve engineering problems by decomposing complex structures into multiple simple individual parts and then mathematically calculating different individual parts to obtain the desired values. The construction is meshed by the discretization of the spatial dimension. In detail, FEM is constructed by discretizing the spatial dimension for meshing, then using a system of algebraic equations for simulation and, last, minimizing the error by using the variational method.
In this research, the problem is solved statically. Based on piles set in the middle of the soil, the equilibrium of the ground stress is considered in the numerical simulation process, displacement constraints must be applied to the lateral sides of the soil in the calculation domain, and the specific constraints are that the two lateral sides in the X direction constrain their displacements in the X direction, and the two lateral sides in the Y direction constrain their displacements in the Y direction.
To examine the blade’s effect on traditional shaft piles, two models are considered, as shown in
Figure 1. The standard circular hollow section (CHS) tube available in the market is used for this investigation, which has an outside diameter (OD) of 76.1 mm and a wall thickness of 4 mm. As shown in
Figure 1, the only difference between these two models is that one of the CHS tubes does not have blades welded on it. In this study, the standard CHS pile and the CHS blade pile are labeled as CHSB
0P and CHSB
1P, respectively. Note that 0 represents that there are no blades, and 1 represents that there is one layer of it (i.e., two blades).
The pile geometry and the material parameter of these FEM models are summarized in
Table 1,
Table 2 and
Table 3. As shown in
Table 2, the blades of CHSB
1P have an area of 0.05375 m
2 (250 mm in length and 10 mm in thickness), which come into contact with soil from the pile end.
Based on previous numerical simulation studies, the material parameters of helical piles were referenced and set [
26,
27]. These two models do not vary in terms of material strength; that is, the modulus, Poisson’s ratio, density, yield and ultimate strength are identical, as depicted in
Table 3.
2.2. Soil Material Parameter and Model Geometry
For the FEM simulation, the Mohr–Coulomb constitutive relationship is selected, and the penalty formula is used for simulating the surface contact between the soil and the pile shaft. This study integrates and adjusts the soil parameters used in past studies on the soil [
28].
Table 4 provides the soil parameters of clay used in the FEM modeling.
To perform the parametrical study of these two models in various soil states, the cohesion used in the FEM simulation ranges from 10 to 80 kPa, representing the soil state being soft to hard. In this context, the modulus is assumed to be a constant. Furthermore, the Young’s modulus of the clay used varies from 10 to 120 MPa, which represents the soil state being in a very soft state to a stiff state. Note that cohesion is assumed to be a constant. To be more realistic, FEM models with two variables (different cohesion and modulus) are also simulated; the soil parameters are summarized in
Table 4.
In addition, based on previous studies, in the numerical simulation of helical piles, in order to reduce the influence of soil boundary conditions on the model, the soil size is chosen to be at least 20 times the pile diameter, and the soil depth in the lower part of the helical pile is at least 10 times the pile diameter [
29].
In this research, the model will take too much time or provide inaccurate results when the soil dimension is too big or too small, respectively. In this context, the soil width and the depth in all models are determined as 3 m and 3 m, respectively.
5. Conclusions and Recommendation
The study in relation to the mechanical behavior of the soil and tube/cylinder shaft pile under lateral load action has been investigated for a long time. However, when an enlarged head is added at the bottom of the pile foundation, which acts as anchor stabilization, the study of the mechanical properties between its pile and soil is very limited. In this study, a parametrical investigation was performed, and the ultimate bearing capacity of the normal CHSB pile and the blade pile in different types of soil was calculated and compared. Two soil parameters were considered, namely, Young’s modulus and the soil strength parameter of cohesion. The conclusions of this study are as follows:
The ultimate bearing capacity of the CHSB0 pile foundation as well as of the CHSB1 pile foundation will increase as the Young’s modulus increases.
The ultimate capacity improvement rate is related to cohesion: the greater the cohesion, the greater the capacity; however, the improvement rate will be changed.
The ultimate bearing capacity of the CHSB0 pile foundation as well as of the CHSB1 pile foundation will increase as the soil cohesion increases.
The ultimate capacity improvement rate is related to Young’s modulus: the greater the Young’s modulus, the greater the capacity improvement. Furthermore, the cohesion of 35 MPa is found to be a boundary. When the cohesion is less than 35 MPa, the capacity improvement rate is greater.
Numerical simulations of the CHSB0 pile and of the CHSB1 pile were also conducted for six states of soil: very soft, soft, firm, stiff, very stiff and hard. The ultimate bearing capacity of each pile was determined and compared. The conclusions are as follows.
When the soil state is ascertained, the ultimate bearing capacity of the blade pile foundation is greater than that of the CHSB0 pile.
When the soil state changes from very soft to hard, the lateral bearing capacity of both the CHSB0 pile and the CHSB1 pile will increase.
When the soil is very soft to firm, the CHSB1 pile has much greater capacity than the CHSB0 pile, but when the soil is stiff to hard, the blade pile capacity is just slightly greater than that of the CHSB0 pile. The reason is that when the soil is stiff to hard, the load-displacement curve shows no ‘drop’ point, which means the pile–soil system does not show the failure condition.
On replacing the CHSB0 pile by the CHSB1 pile, the maximum lateral capacity improvement can be 14.8% when the soil is very soft and 2.5% when the soil is hard.