1. Introduction
Renewable energy production has been increased rapidly over the last few years and wind energy production has made an important contribution to this development [
1]. Wind energy is produced by onshore or offshore wind farms (WFs) that are groups of wind turbines (WTs) located in the same place. Wind energy is deemed a mature and cost-competitive source of electricity production in Europe that contributes to the security and sustainability of the energy system [
2]. Europe installed 15.4 GW (13.2 GW in the EU) of new wind power capacity (mainly onshore WFs) in 2019 and reached 205 GW of wind energy cumulative capacity; wind energy accounted for 15% of the electricity consumption in the EU-28 in 2019. In Greece the new onshore installations in 2019 were about 0.7 GW, whereas the cumulative onshore installed capacity reached about 3.6 GW; the percentage of the electricity demand covered by wind energy in 2019 was 12%. According to data on fourteen countries the average power rating of onshore turbines in Europe is 3.1 MW, whereas in Greece the average power rating is 2.3 MW [
3].
A WT’s efficiency evaluation can be carried out using [
4]: (i) the annual energy output (AEP), (ii) the power curve, and (iii) the power coefficient. To measure a WT’s productive efficiency as the ratio of current performance to best performance, a benchmark is required that represents the best performance attainable. The use of AEP is inappropriate because wind conditions influence power production, and it is difficult to adjust these conditions to comparable levels in real applications. In addition, power curve and power coefficient are both average output metrics, and are thus not deemed suitable. The shortcomings of the above metrics have driven researchers to look for benchmarks in the field of production economics [
4]. The measurement of efficiency is focused on estimating a production function using input and output data for a set of production units which may be WTs or WFs in the context of wind energy.
The productive efficiency of wind energy facilities is dependent on wind conditions, i.e., wind speed and wind power density at the production site, and other factors such as implantation and generation costs, and turbine productivity. Except for the above factors, profitability is determined by also taking into account the energy prices. Investments in WFs may attain high returns on investments because, in many countries, producers can take advantage of the above market guaranteed wind energy price. It is evident that production inefficiency can reduce the profitability of WFs, thus the measurement of productive efficiency is essential [
1].
Competitive approaches are used to assess the performance of WF projects such as the parametric stochastic frontier analysis (SFA) [
5,
6] and the non-parametric data envelopment analysis (DEA) [
7]. SFA includes the selection of a functional type for production or cost frontier function, estimated econometrically, using two error term components, namely statistical noise and inefficiency. The normal and half-normal assumptions for noise and inefficiency are usually made for these terms, respectively.
In frontier efficiency analysis, given a group of
j (= 1, …,
n) observations on homogeneous entities that generate one output
y using a vector of
m inputs
xj = (
x1, …,
xm) Equations (1) and (2), respectively are assumed to provide frontier and observed production function [
8]:
where,
is the deterministic component and
is an error term.
Different distributional assumptions set on
that represent deviations from the frontier lead to different models [
8]: (i) If
such that
yf ≥
y for all observations, then the frontier is deterministic and DEA can be used. (ii) If
is a two-error term of noise and inefficiency then the frontier is stochastic and SFA should be used.
DEA, published by Charnes et al. [
9] in the literature, is a mathematical programming technique that is used to determine the efficiency of a group of decision-making units (DMUs), in this case WFs. Efficiency ratings based on DEA take values between zero and unity (i.e., perfect efficiency for units located on the border); units located off the frontier are considered inefficient. With regard to WFs, it is necessary to identify two phases related to performance evaluation: the phase of construction (i.e., investment) prior to start-up, and the phase of operation. These stages are related to the evaluation ex ante and ex post [
7], respectively.
The current study focuses on DEA which is more flexible than SFA and can be used to assess power facilities’ construction and operating phase [
10]. There is a lack of studies assessing the WF projects’ DEA-based efficiency with a focus on the investment and operational stage. In this context, the current research aims at improving a single black box DEA [
11] and evaluating the performance of a group of WF projects in Greece using a series two-stage DEA.
This research adds to the existing literature in several ways. Firstly, it provides new empirical evidence on the performance of investment and operational stages of WF projects. Second, it fills the gap produced by the single DEA black-box model for WF projects, using a DEA series two-stage model structure to assess both investment and operational efficiency. It determines for a group of Greek WFs to what extent the performance of projects could be improved in the construction phase by reducing selected inputs given the output and whether the WF operators could increase the produced electricity given the inputs. Moreover, WF performance and size are studied, and sensitivity analysis is conducted to provide more insight into the factors influencing WF performance.
Projects are seen as systems whose monitoring is based on the principles of the triangle of project management (i.e., schedule, cost, and quality). Using DEA, project efficiency is measured employing a results-oriented methodology based on the above principles [
10]. In the case of the DEA-based assessment of power plants, performance in the investment and operating process can be separately differentiated and modeled [
12].
The WF project assessment studies by DEA are divided into single-, two-stage and serial two-stage works. WFs are specified as DMUs in the works reviewed below. The classic single-stage DEA studies evaluate WFs within a black-box context in which the power facility is treated as a whole (i.e., black box) system without throwing light onto its structure [
11]. Sarıca and Or [
12] propose DEA models for the operational and investment performance of a group of Turkey’s thermal, hydro and wind power stations. In Greece, Champilomatis [
13] assesses the performance of a group of 13 WFs. Kim et al. [
14] evaluate the efficiency of the investment for renewable energy in Korea and Akbari et al. [
15] perform a cross-European DEA-based efficiency assessment of offshore wind farms. Rodríguez et al. [
16] provide an empirical DEA-based study of the evolution of total factor productivity among Spanish wind farms by deriving the Malmquist productivity index.
The two-stage studies measure the efficiency through DEA in the first stage, and then regress it in the second stage on explanatory variables [
17]. Two-stage studies typically incorporate DEA and Tobit regression, such as Iglesias et al. [
7] research on WF performance assessment in Spain, and Wu et al. [
18] and Sağlam’s [
19] works on WF performance assessment in China and Texas. Ederer [
20] evaluates the performance of offshore WFs by also employing the two-stage DEA.
In another research strand, model building is based on the series two-stage DEA. Unlike the single DEA black-box model, a two-series DEA series structure distinguishes sub-processes and aims to calculate their efficiency [
11]. In this strand lies the work of Niu et al. [
21] proposing a DEA approach with a two series structure to evaluate the performance of WTs. It is worth noting that a series two-stage DEA can also be combined with Tobit regression [
21]. With regard to explanatory variables, in a different modeling approach [
22], they can be considered as inputs but are not active in the optimization process for the definition of the efficiency metrics. Examples of these explanatory variables which are deemed exogenous are the solar irradiance and ambient air temperature for the case of photovoltaic systems [
23]. In a different setting, Sağlam [
24] evaluates the US states’ wind power performances for electricity generation by employing the two-stage DEA approach and treating individual states as DMUs. DEA can also be combined with other methods such as SFA [
7], life cycle assessment (LCA) [
25] and emergy analysis [
2].
Single- and two-stage DEA have been already employed for ex-post evaluation of WF projects. To the best of the author’s knowledge, a DEA-based assessment of the performance of WF projects in Greece by employing a series two-stage structure has not been implemented so far. The current study aims to fill this gap by adopting this structure to evaluate the efficiency of a group of WF projects ex-post and to open the black box by identifying the investment and operational stages in a DEA setting. Moreover, the current research is the first attempt to evaluate the performance of a group of WFs in Greece by distinguishing discretionary (i.e., controllable) and non-discretionary inputs.
The rest of the paper unfolds as follows. In
Section 2, the problem to be solved for the case of WF projects is stated.
Section 3 deals with methods and the data set for the analysis. In
Section 4, the results are presented and discussed. The final section concludes.
4. Results
In the light of the results produced by the BCC input-oriented Model (3), out of the 13 projects, 5 (38%) were found to be ex-post relatively efficient; mean investment performance efficiency: 0.76. The model satisfactorily discriminates the efficient and inefficient WFs. The median investment performance efficiency was about 0.78. The efficiency score of 0.76 means that, on average, a reduction of 24% (= 1 − 0.76) of the current discretionary (i.e., controllable) input level is possible while maintaining the same level of output (
Table 6). The results of the BCC output-oriented model (4) suggest that 7 (54%) of the 13 projects were found to be relatively efficient ex-post; mean operating efficiency: 0.89. The model’s discriminatory power is lower relative to stage 1, however that is a characteristic of the BCC model and, thus, the findings are deemed acceptable. Moreover, efficiency in operating phase can be improved by producing more electricity by about 12% (= (1/0.89) − 1) (
Table 6). It is evident from the above findings that the construction stage is more ineffective compared to the operating stage.
One of the major drawbacks of the DEA framework is that efficiency scores are solely dependent upon the model’s input and output variables. To address this constraint, a sensitivity analysis is performed to assess the effects of input removal on the DEA efficiency scores. The efficiency scores for the different multiple-input single-output scenarios are reported in
Table 7. In modified models (3′) and (3″) and models (4′) and (4″) one of the non-discretionary input and one of the input variables has been removed at a time, respectively. In all modified models at least one discretionary input and one output variable is necessary. However, the variable representing the number of turbines is not omitted because it is the variable that the two subprocesses have in common.
The average investment performance efficiency score of the original Model (3) including all the discretionary and non-discretionary inputs and the output variable is higher or equal compared to models (3′) and (3″), respectively. Removing the wind speed non-discretionary input variable results in the lowest average efficiency (0.54) in the initial Model (3). The original Model’s (4) average investment efficiency score including all the input and output variables is higher compared to models (4′) and (4″). Removing the input variable related to installed capacity in original Model (4) results in the lowest average efficiency (0.86). The results of the sensitivity analysis show that the wind power density has no effect on investment performance. The other input variables have an effect on efficiency. It is worth noticing that the installed capacity has the greater effect on operating efficiency.
The dual BCC output-oriented model can provide information on scale efficiency and RTS. The average scale efficiency score of the sample WFs is about 0.89. There are two WFs (15% of the total) that operate at their most productive scale under CRS; WF2 and WF12 are the only scale efficient projects. As for the scale inefficient farms, four WFs (31% of the total) exhibit IRS and they should increase their size to reach the optimum production scale. Notably, the rest of WFs (54% of the total) exhibit DRS and they should decrease their size (
Table 6).
Figure 2 illustrates the distribution of RTS in operating performance for the sampled WFs.
In
Figure 3, a so-called bubble diagram, the scale efficiency scores for operating performance and size (measured by installed capability of the WF) are plotted. Within this diagram, a circle reflects the size of a WF, with larger circles representing greater WFs. The three categories of scale (CRS, IRS, and DRS) are shown on the y-axis. From
Figure 3 it is evident that large-sized WFs tend to exhibit DRS compared with the small- and medium-sized WFs that exhibit CRS and IRS.
Results of the investment performance evaluation include the WF1, WF2, WF4, WF9, and WF11 as best-in-class projects. The operating performance results include the WF1, WF2, WF3, WF7, WF8, WF11 and WF12 as the best-in-class projects. The WF1, WF2, WF11 projects are the best-in-class in both investment and operating performance. The WT2 type turbine is used by WF2 (autonomous system) and WF11 (with down-rated capacity), while the WT1 type turbine is used by WF1. In addition, the construction of a voltage rise substation is required for WF1. In the light of the sensitivity analysis results, the benchmarks of investment performance assessment in all scenarios considered are: WF1, WF2, WF9, and WF11. In the operating performance efficiency evaluation, the benchmarks for all scenarios are: WF3, WF8, WF11 and WF12. The benchmark in both dimensions of performance for all scenarios is the project WF11.
5. Conclusions
The current study adopts a series two–stage structure for the ex-post DEA-based performance assessment of a sample of 13 WF projects taking into consideration the structure of the WF projects. The data on onshore WF projects in Greece are used to illustrate the applicability and empirical usefulness of the approach being proposed. The series two-stage structure is considered superior to the traditional single-stage DEA setting because, in the case of WFs, it seeks to open the project black-box. DEA-based efficiency scores from the BCC model of input minimization are produced in the first stage of the investment project analysis using data on project cost, wind speed, and wind power density as inputs and turbine number as output. In the second stage, the operating efficiency of the WF projects is evaluated using the BCC model of output maximization using the number of turbines, installed power, and annual O&M cost as inputs and the annual electricity generated as output. The modeling approach provides project DEA-based efficiency scores for each stage that take values between zero and unity and represents how well the project performs at each stage.
The findings suggest that only five and seven of the 13 sample WF projects in stages 1 and 2, respectively, are ex-post efficient in the context of the DEA; however, only two WFs operate at the optimum production scale. It is also evident that the investment stage has a lower level of performance than the operational stage. Although the results are sample-specific, WF size appears to be related to operating efficiency. Small- and medium-sized WFs operate under CRS and IRS, while large-sized WFs operate under DRS. Moreover, in the light of the sensitivity analysis results, wind speed and WF installation capacity appear to be the factors that affect the investment performance and operational efficiency, respectively.
The derived consolidated metrics in stages 1 and 2 can serve for project managers and facility operators as an indicator for the level of achievement of the projects in the investment and operational stage, respectively. In addition, they may also be viewed as performance metrics for the project’s design and operating team.
Throughout the current study, static DEA models were used to analyze a group of WF projects from the point of view of the contractor/operator. If a long time series on WF operating data will be made available, future research can be focused on dynamic analysis and DEA can provide a dynamic evaluation of WF performance. Since the distribution of wind speed is not taken into account in the current research this can be seen as a limitation of the study that can be addressed by using high-frequency data in future research.