The Factors that Influence Human Resources on Affordable Housing Delivery within Restraint of Budget
Abstract
:1. Introduction
2. Literature Review
2.1. Human Resource Management towards Affordable Housing Delivery
2.2. Improve Human Resource Management Plan for Housing Production Process
2.3. Procurement of Affordable Housing Delivery Team
- A project manager is expected to acquire required human resources, such as skills, knowledge, experience, etc to participate in the attainment of affordable housing delivery [12]. If the process of engagement is not executed effectively, it will frustrate timely delivery, budgeted cost, client satisfaction, quality and increase the risks involved [19,29]. An additional effect of this factor is that the probability of success could be affected, which would result in inadequate housing delivery [28].
- Unavailability of skilled people, due to time constraints and economic reasons, could pressurise the project manager to seek elsewhere or, prefer to organise and train personnel for such sensitive positions [2,17]. For this reason, the protocol has to be executed in accordance with the regulatory and mandatory procedures established in the contract documents [27].
2.4. Creatings Affordable Housing Delivery Team
2.5. Efficient Utilisation of Labour
3. Methodology
4. Data Analysis Results and Discussion of Findings
4.1. Respondent’s Professional Affiliation
4.2. Analysis of Factors That Influence Human Resources Management on Cost in Affordable
4.3. Principal Component Analysis of Human Resources Management on Cost
4.4. Qualitative Analysis
4.4.1. G-Case Study 1
4.4.2. H-Case Study 2
4.4.3. K-Case Study 3
4.4.4. Q-Case Study 4
4.4.5. Qualitative Findings
4.5. Discussion of Findings
5. Conclusions and Recommendation
Author Contributions
Funding
Conflicts of Interest
References
- Langford, D.; Fellows, R.F.; Hancock, M.R.; Gale, A.W. Human Resources Management in Construction; Routledge: Abingdon, UK, 2014; pp. 1–207. [Google Scholar]
- Nübler, I. Human Resources Development and Utilization in Demobilization and Reintegration Programmes. In Demobilization in Sub-Saharan Africa; Palgrave Macmillan: London, UK, 2000; pp. 45–77. [Google Scholar]
- Morris, P.; Langdon, D. What does green really cost? PREA Q. 2007, Summer, 55–60. [Google Scholar]
- Odediran, S.J.; Windapo, A.O. Systematic Review of Factors Influencing the Cost Performance of Building Projects. In Proceedings of the Postgraduate Conference, Johannesburg, South Africa, 10–11 February 2014; pp. 501–520. [Google Scholar]
- Creswell, J.W.; Creswell, J.D. Research Design: Qualitative, Quantitative, and Mixed Methods Approaches; Sage Publications: Thousand Oaks, CA, USA, 2017; pp. 203–224. [Google Scholar]
- Abdul-Rahman, H.; Wang, C.; Wood, L.C.; Khoo, Y.M. Defects in affordable housing projects in Klang Valley, Malaysia. J. Perform. Constr. Facil. 2014, 28, 272–285. [Google Scholar] [CrossRef] [Green Version]
- Windapo, A.; Odediran, S.; Moghayedi, A.; Adediran, A.; Oliphant, D. Determinants of Building Construction Costs in South Africa. J. Constr. Bus. Manag. 2017, 1, 8–13. [Google Scholar]
- Attia, E.A.; Dumbrava, V.; Duquenne, P. Factors affecting the development of workforce versatility. IFAC Proc. Vol. 2012, 45, 1221–1226. [Google Scholar] [CrossRef] [Green Version]
- Chan, P.W.; Kaka, A. Productivity improvements: Understand the workforce perceptions of productivity first. Pers. Rev. 2007, 36, 564–584. [Google Scholar] [CrossRef] [Green Version]
- Wirojanagud, P.; Gel, E.S.; Fowler, J.W.; Cardy, R. Modelling inherent worker differences for workforce planning. Int. J. Prod. Res. 2007, 45, 525–553. [Google Scholar] [CrossRef]
- Basu, V.; Hartono, E.; Lederer, A.L.; Sethi, V. The impact of organizational commitment, senior management involvement, and team involvement on strategic information systems planning. Inf. Manag. 2002, 39, 513–524. [Google Scholar] [CrossRef]
- Edum-Fotwe, F.T.; McCaffer, R. Developing project management competency: Perspectives from the construction industry. Int. J. Proj. Manag. 2000, 18, 111–124. [Google Scholar] [CrossRef]
- Attia, E.A.; Duquenne, P.; Le-Lann, J.M. Considering skills evolutions in multi-skilled workforce allocation with flexible working hours. Int. J. Prod. Res. 2014, 52, 4548–4573. [Google Scholar] [CrossRef] [Green Version]
- Barker, T.; Frolick, M.N. ERP implementation failure: A case study. Inf. Syst. Manag. 2003, 20, 43–49. [Google Scholar] [CrossRef]
- Katzenbach, J.R.; Smith, D.K. The Wisdom of Teams: Creating the High-Performance Organization; Harvard Business Review Press: Boston, MA, USA, 2015; pp. 1–5. [Google Scholar]
- Foley, J.; Macmillan, S. Patterns of interaction in construction team meetings. CoDesign 2005, 1, 19–37. [Google Scholar] [CrossRef] [Green Version]
- Nalbantian, H.R.; Schotter, A. Productivity under group incentives: An experimental study. Am. Econ. Rev. 1997, 87, 314–341. [Google Scholar]
- Dziekoński, K. Project managers’ competencies model for construction industry in Poland. Procedia Eng. 2017, 182, 174–181. [Google Scholar] [CrossRef]
- Katz, R.L. Skills of an Effective Administrator; Harvard Business Review Press: Boston, MA, USA, 2009; pp. 1–28. [Google Scholar]
- Gurmu, A.T. Fuzzy synthetic evaluation of human resource management practices influencing construction labour productivity. Int. J. Prod. Perform. Manag. 2020. [Google Scholar] [CrossRef]
- Abdul-Rahman, H.; Kwan, C.L.; Woods, P.C. Quality function deployment in construction design: Application in low-cost housing design. Int. J. Q. Reliab. Manag. 1999, 16, 591–605. [Google Scholar] [CrossRef]
- Ugwu, O.O.; Haupt, T.C. Key performance indicators and assessment methods for infrastructure sustainability—A South African construction industry perspective. Build. Environ. 2007, 42, 665–680. [Google Scholar] [CrossRef]
- Burgoyne, M.L. Factors Affecting Housing Delivery in South Africa: A Case Study of the Fisantekraal Housing Development Project, Western Cape. Ph.D. Thesis, University of Stellenbosch, Stellenbosch, South African, 2008; pp. 1–110. [Google Scholar]
- Aiyetan, A.; Smallwood, J.; Shakantu, W. A systems thinking approach to eliminate delays on building construction projects in South Africa. Acta Structilia 2011, 18, 19–39. [Google Scholar]
- Meredith, J.R.; Mantel, S.J., Jr.; Shafer, S.M. Project Management: A Managerial Approach; John Wiley & Sons: Hoboken, NJ, USA, 2017; pp. 1–19. [Google Scholar]
- Papke-Shields, K.E.; Beise, C.; Quan, J. Do project managers practice what they preach, and does it matter to project success? Int. J. Proj. Manag. 2010, 28, 650–662. [Google Scholar] [CrossRef]
- Kerzner, H. Project Management: A Systems Approach to Planning, Scheduling, and Controlling; John Wiley & Sons: Hoboken, NJ, USA, 2017; pp. 1–825. [Google Scholar]
- Cooke-Davies, T. The “real” success factors on projects. Int. J. Proj. Manag. 2002, 20, 185–190. [Google Scholar] [CrossRef]
- Patel, K.V.; Vyas, C.M. Construction materials management on project sites. In Proceedings of the National Conference on Recent Trends in Engineering & Technology, Vallabh Vidyanagar, India, 13–14 May 2011; pp. 13–14. [Google Scholar]
- Rahman, I.A.; Memon, A.H.; Karim, A.T.A. Relationship between factors of construction resources affecting project cost. Mod. Appl. Sci. 2013, 7, 67–75. [Google Scholar]
- Akinmoladun, O.I.; Oluwoye, J. An assessment of why the problems of housing shortages persist in developing countries: A case of study of Lagos Metropolis, Nigeria. Pak. J. Soc. Sci. 2007, 4, 589–598. [Google Scholar]
- Long, H.; Tu, S.; Ge, D.; Li, T.; Liu, Y. The allocation and management of critical resources in rural China under restructuring: Problems and prospects. J. Rural Stud. 2016, 47, 392–412. [Google Scholar] [CrossRef] [Green Version]
- Atkinson, R. Project management: Cost, time and quality, two best guesses and a phenomenon, it is time to accept other success criteria. Int. J. Proj. Manag. 1999, 17, 337–342. [Google Scholar] [CrossRef]
- Cameron, R.; Molina-Azorin, J.F. The acceptance of mixed methods in business and management research. Int. J. Organ. Anal. 2011, 19, 256–271. [Google Scholar] [CrossRef]
- Trochim, W.M.; Donnelly, J.P. Research Methods Knowledge Base (Vol. 2); Atomic Dog Publishing: Cincinnati, OH, USA, 2001; pp. 1–344. [Google Scholar]
- Trochim, W.M. Qualitative measures. In Research Measures Knowledge Base; Atomic Dog Publishing: Cincinnati, OH, USA, 2006; Volume 361, pp. 2–16. [Google Scholar]
- Marshall, M.N. Sampling for qualitative research. Fam. Prac. 1996, 13, 522–526. [Google Scholar] [CrossRef]
- Fapohunda, J.A. Operational Framework for Optimal Utilisation of Construction Resources during the Production Process. Ph.D. Thesis, Sheffield Hallam University, Sheffield, UK, 2009. [Google Scholar]
- Pallant, J. SPSS Survival Manual; McGraw-Hill Education: London, UK, 2013; pp. 1–353. [Google Scholar]
- Olojede, O.A.; Agbola, S.B.; Samuel, K.J. Technological innovations and acceptance in public housing and service delivery in South Africa: Implications for the Fourth Industrial Revolution. J. Public Adm. 2019, 54, 162–183. [Google Scholar]
- Saidu, A.I.; Yeom, C. Success Criteria Evaluation for a Sustainable and Affordable Housing Model: A Case for Improving Household Welfare in Nigeria Cities. Sustainability 2020, 12, 656. [Google Scholar] [CrossRef] [Green Version]
- McGaffin, R.; Spiropoulous, J.; Boyle, L. Micro-developers in South Africa: A Case Study of Micro-property Developers in Delft South and Ilitha Park, Cape Town. In Urban Forum; Springer: Dordrecht, The Netherlands, 2019; Volume 30, pp. 153–169. [Google Scholar]
- Ubisi, S.V.; Khumalo, P.; Nealer, E.J. Provision of adequate housing through cooperative government and intergovernmental relations in the Bushbuckridge Local Municipality. Gend. Behav. 2019, 17, 13355–13369. [Google Scholar]
- Pullen, S.; Arman, M.; Zillante, G.; Zuo, J.; Chileshe, N.; Wilson, L. Developing an assessment framework for affordable and sustainable housing. Australias. J. Constr. Econ. Build. 2010, 10, 48–64. [Google Scholar]
Variable (Respondent Professional Affiliation) | Frequency | Percentage (%) |
---|---|---|
Architects | 12 | 10.5 |
Project managers | 33 | 28.9 |
Site engineers | 7 | 6.1 |
Contract managers | 6 | 5.3 |
Contractors | 6 | 5.3 |
Quantity surveyors | 50 | 43.9 |
G-Total | 114 | 100 |
Coding | How Human Resource Management Have an Effect on Cost in Delivery of Sustainable Housing | Mean | Std. Deviation | Variance | Rank |
---|---|---|---|---|---|
ICMCR23 | Workforce productivities affect cost | 4.1404 | 0.75113 | 0.564 | 1 |
ICMCR1 | Involvement of all team members in planning and implementation | 4.1316 | 0.79281 | 0.629 | 2 |
ICMCR4 | Regular meetings on-site for promoting efficient productivity | 4.1140 | 0.76145 | 0.580 | 3 |
ICMCR10 | Team-building strategies for production | 4.0877 | 0.90780 | 0.824 | 4 |
ICMCR21 | Prompt payment of wages by contractors will enhance productivity | 4.0789 | 0.85336 | 0.728 | 5 |
ICMCR2 | Develop staffing management plan | 4.0789 | 0.70579 | 0.498 | 6 |
ICMCR29 | Flexibility of construction operators in making timely management decisions on production | 4.0702 | 0.78390 | 0.615 | 7 |
ICMCR28 | Skill to define effective techniques for achieving objectives | 4.0702 | 0.73736 | 0.544 | 8 |
ICMCR24 | Skill to apply techniques for a reduction in the cost of construction during production | 4.0526 | 0.83974 | 0.705 | 9 |
ICMCR9 | A sound knowledge of quality design decisions and implementation | 4.0526 | 0.82914 | 0.687 | 10 |
ICMCR27 | Knowledge of good safety practices and awareness of personal safety during production | 4.0351 | 0.85113 | 0.724 | 11 |
ICMCR30 | Constant emphasis on making maximum usage of the local labour force to achieve housing production | 4.0263 | 0.86690 | 0.752 | 12 |
ICMCR3 | Document delivery roles and responsibilities among construction team members | 3.9912 | 0.73467 | 0.540 | 13 |
ICMCR26 | Ability of the workforce to develop willingness in sustainability practices | 3.9912 | 0.88743 | 0.788 | 14 |
ICMCR13 | Build trust among construction team members | 3.9912 | 0.92646 | 0.858 | 15 |
ICMCR15 | Ability to define a plan for effective use of resources available for production | 3.9649 | 0.86146 | 0.742 | 16 |
ICMCR25 | Wastage of workforce input during the production process | 3.9649 | 1.00380 | 1.008 | 17 |
ICMCR14 | Reduction in delivery time through proper job allocation to the workforce | 3.9649 | 0.87168 | 0.760 | 18 |
ICMCR20 | Aptitude to work under pressure to meet tight deadlines and adapt to changes affect the cost of construction | 3.9561 | 0.85590 | 0.733 | 19 |
ICMCR11 | Ability to carry out the effective implementation of techniques on housing production | 3.9474 | 0.81840 | 0.670 | 20 |
ICMCR22 | Ability to safeguard safety consciousness during housing production | 3.9298 | 0.93808 | 0.880 | 21 |
ICMCR12 | Emphasis on constant encouraging construction operators on skill advancement and development | 3.9211 | 0.81082 | 0.657 | 22 |
ICMCR16 | Steadfastness in carrying out commitments and obligations | 3.8947 | 0.88616 | 0.785 | 23 |
ICMCR18 | Skill in oral and written communication for keeping subordinates, associates, superiors and others adequately informed during production | 3.8860 | 0.92897 | 0.863 | 24 |
ICMCR8 | Constant training of workers for the use of techniques | 3.8772 | 0.97890 | 0.958 | 25 |
ICMCR5 | Define quality accomplishment for housing production | 3.8684 | 0.82562 | 0.682 | 26 |
ICMCR7 | Skill to establish requirements, methods and techniques for housing production | 3.8070 | 0.85058 | 0.682 | 27 |
ICMCR6 | Time wastage by workforce during production | 3.7105 | 1.02813 | 1.057 | 28 |
ICMCR19 | Improper planning of workforce activities on-site | 3.6754 | 1.02617 | 1.053 | 29 |
ICMCR17 | Shortage of experienced worker on-site | 3.5965 | 1.17284 | 1.376 | 30 |
Test | Value and Remark | |
---|---|---|
Kaiser-Meyer-Olkin measure of sampling adequacy (KMO) | 0.877 Significant and adequate for principal component analysis (PCA) | |
Bartlett’s Test of Sphericity | Approx. Chi-Square | 2474.668 |
df | 435 | |
Sig. | 0.000 Significant and adequate for PCA |
Coding | Variable Name | Pattern Matrix Coefficient | Structural Matrix Coefficient | Communalities | ||
---|---|---|---|---|---|---|
1 | 2 | 1 | 2 | |||
ICMCR1 | Involvement of all team members in planning and implementation | 0.675 | 0.507 | 0.641 | 0.482 | 0.414 |
ICMCR2 | Develop staffing management plan | 0.701 | - | 0.651 | - | 0.431 |
ICMCR3 | Document delivery roles and responsibilities among construction team members | 0.713 | - | 0.620 | - | 0.409 |
ICMCR4 | Regular meetings on-site for promoting efficient productivity | 0.790 | - | 0.708 | - | 0.520 |
ICMCR5 | Define quality accomplishment for housing production | 0.438 | 0.392 | 0.525 | 0.395 | 0.298 |
ICMCR6 | Time wastage by workforce during production | - | 0.553 | - | 0.522 | 0.275 |
ICMCR7 | Skill to establish requirements, methods and techniques for housing production | 0.669 | - | 0.719 | 0.438 | 0.524 |
ICMCR8 | Constant training of workers for the use of techniques | 0.674 | 0.768 | 0.528 | 0.615 | |
ICMCR9 | A sound knowledge on quality design decisions and implementation | 0.671 | - | 0.718 | 0.434 | 0.522 |
ICMCR10 | Team-building strategies for production | 0.629 | - | 0.716 | 0.491 | 0.534 |
ICMCR11 | Ability to carry out effective implementation of techniques on housing production | 0.671 | - | 0.766 | 0.529 | 0.613 |
ICMCR12 | Emphasis on constant encouraging construction operators on skill advancement and development | 0.704 | 0.697 | 0.713 | 0.376 | 0.509 |
ICMCR13 | Build trust among construction team members | 0.856 | 0.667 | 0.778 | - | 0.623 |
ICMCR14 | Reduction in delivery time through proper job allocation to workforce | 0.745 | 0.660 | 0.706 | 0.303 | 0.502 |
ICMCR15 | Ability to define plan for effective use of resources available for production | 0.603 | - | 0.679 | 0.457 | 0.478 |
ICMCR16 | Steadfastness in carrying out commitments and obligations | 0.336 | 0.430 | 0.555 | 0.601 | 0.445 |
ICMCR17 | Shortage of experienced workers on-site | - | 0.782 | - | 0.707 | 0.516 |
ICMCR18 | Skill in oral and written communication for keeping subordinates, associates, superiors and others adequately informed during production | - | 0.662 | 0.489 | 0.737 | 0.563 |
ICMCR19 | Improper planning of workforce activities on-site | - | 0.776 | 0.392 | 0.767 | 0.589 |
ICMCR20 | Aptitude to work under pressure to meet tight deadlines and adapt to changes affect cost of construction | 0.413 | 0.421 | 0.628 | 0.632 | 0.525 |
ICMCR21 | Prompt payment of wages by contractors will enhance productivity | 0.700 | - | 0.740 | 0.435 | 0.552 |
ICMCR22 | Ability to safeguard safety consciousness during housing production | 0.527 | 0.713 | 0.652 | 0.514 | 0.469 |
ICMCR23 | Workforce productivities affect cost | 0.332 | 0.515 | 0.595 | 0.684 | 0.550 |
ICMCR24 | Skill to apply techniques for reduction in cost of construction during production | 0.353 | 0.497 | 0.607 | 0.677 | 0.551 |
ICMCR25 | Wastage of workforce input during production process | - | 0.734 | 0.445 | 0.770 | 0.596 |
ICMCR26 | Ability of workforce to develop willingness in sustainability practices | - | 0.702 | 0.476 | 0.762 | 0.591 |
ICMCR27 | Knowledge of good safety practices and awareness of personal safety during production | 0.475 | 0.305 | 0.631 | 0.547 | 0.467 |
ICMCR28 | Skill to define effective techniques for achieving objectives | 0.679 | - | 0.740 | 0.473 | 0.560 |
ICMCR29 | Flexibility of construction operators in making timely management decisions on production | 0.700 | - | 0.743 | 0.442 | 0.558 |
ICMCR30 | Constant emphasis on making maximum usage of local labour force to achieve housing production | 0.441 | 0.415 | 0.652 | 0.639 | 0.552 |
Component | Initial Eigenvalue | Extraction Sums of Squared Loading | Rotations Sums of Squared Loadings a Total | ||||
---|---|---|---|---|---|---|---|
Total | % of Variance | Cumulative % | Total | % of Variance | Cumulative % | ||
1 | 13.123 | 43.745 | 43.745 | 13.123 | 43.745 | 43.745 | 12.038 |
2 | 2.227 | 7.423 | 51.168 | 2.227 | 7.423 | 51.168 | 8.442 |
3 | 1.641 | 5.470 | 56.638 | ||||
4 | 1.495 | 4.983 | 61.621 | ||||
5 | 1.229 | 4.098 | 65.719 | ||||
6 | 1.057 | 3.524 | 69.244 | ||||
7 | 0.970 | 3.233 | 72.477 | ||||
8 | 0.869 | 2.898 | 75.374 | ||||
9 | 0.713 | 2.376 | 77.751 | ||||
10 | 0.681 | 2.270 | 80.020 | ||||
11 | 0.621 | 2.070 | 82.090 | ||||
12 | 0.594 | 1.980 | 84.071 | ||||
13 | 0.562 | 1.875 | 85.945 | ||||
14 | 0.541 | 1.803 | 87.748 | ||||
15 | 0.472 | 1.574 | 89.322 | ||||
16 | 0.420 | 1.400 | 90.722 | ||||
17 | 0.362 | 1.206 | 91.927 | ||||
18 | 0.341 | 1.137 | 93.065 | ||||
19 | 0.306 | 1.020 | 94.085 | ||||
20 | 0.269 | 0.896 | 94.981 | ||||
21 | 0.231 | 0.771 | 95.752 | ||||
22 | 0.209 | 0.698 | 96.450 | ||||
23 | 0.190 | 0.632 | 97.082 | ||||
24 | 0.172 | 0.575 | 97.657 | ||||
25 | 0.157 | 0.524 | 98.181 | ||||
26 | 0.138 | 0.459 | 98.640 | ||||
27 | 0.124 | 0.415 | 99.055 | ||||
28 | 0.109 | 0.363 | 99.418 | ||||
29 | 0.096 | 0.320 | 99.738 | ||||
30 | 0.079 | 0.262 | 100.000 |
© 2020 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (http://creativecommons.org/licenses/by/4.0/).
Share and Cite
Akinyede, I.; Fapohunda, J.; Haldenwang, R. The Factors that Influence Human Resources on Affordable Housing Delivery within Restraint of Budget. J 2020, 3, 250-265. https://doi.org/10.3390/j3030019
Akinyede I, Fapohunda J, Haldenwang R. The Factors that Influence Human Resources on Affordable Housing Delivery within Restraint of Budget. J. 2020; 3(3):250-265. https://doi.org/10.3390/j3030019
Chicago/Turabian StyleAkinyede, Imisioluseyi, Julius Fapohunda, and Rainer Haldenwang. 2020. "The Factors that Influence Human Resources on Affordable Housing Delivery within Restraint of Budget" J 3, no. 3: 250-265. https://doi.org/10.3390/j3030019
APA StyleAkinyede, I., Fapohunda, J., & Haldenwang, R. (2020). The Factors that Influence Human Resources on Affordable Housing Delivery within Restraint of Budget. J, 3(3), 250-265. https://doi.org/10.3390/j3030019