Next Article in Journal
Cycling Impact Assessment of Renewable Energy Generation in the Costs of Conventional Generators
Previous Article in Journal
Short-Term Wind Speed Forecasting Based on Low Redundancy Feature Selection
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Transient Stability Enhancement Using a Wide-Area Controlled SVC: An HIL Validation Approach

1
Facultad de Ingeniería, Universidad Autonóma de San Luis Potosí, Dr. Manuel Nava No. 8, San Luis Potosí S.L.P., México 78290, Mexico
2
Centro Universitario de Ciencias Exactas e Ingenierías, Universidad de Guadalajara, Av. Revolución 1500, Guadalajara 44430, Mexico
3
Independent Researcher, Morelia 58120, Mexico
*
Author to whom correspondence should be addressed.
Energies 2018, 11(7), 1639; https://doi.org/10.3390/en11071639
Submission received: 31 May 2018 / Revised: 17 June 2018 / Accepted: 19 June 2018 / Published: 22 June 2018
(This article belongs to the Section F: Electrical Engineering)

Abstract

:
This paper presents a control scheme of a wide-area controlled static VAr compensator (WAC-SVC) and its real-time implementation in a hardware-in-the-loop (HIL) simulation scheme with three control objectives: (1) to increase the critical clearing time, (2) to damp the power oscillations, and (3) to minimize the maximum line current. The proposed control scheme considers a correction strategy to compensate the delays up to 200 ms. In addition to this, a generator tripping scheme based on synchrophasor measurements to determine the proximity to the loss of synchronism is proposed. A delay compensation algorithm based on polynomial approximations is also developed. The proposed WAC-SVC is experimentally validated using a Real-Time Digital Simulator platform (RTDS), industrial communication protocols, a commercial device for PMU-based control implementations, and digital relays with PMU capability. The real-time simulation results confirm its effectiveness and feasibility in real industrial applications. Furthermore, practical guidelines to implement this kind of control schemes are provided.

1. Introduction

Due to the historical occurrence of several blackouts [1,2,3], significant research efforts have been motivated to investigate their causes to prevent future events [4,5,6]. That research suggests that monitoring systems have to be improved [7]. An essential factor to achieve this goal is the wide-area measurement system (WAMS), and, more specifically, the use of phasor measurement units (PMUs). Although many PMUs have been installed in power systems around the world for monitoring purposes and protection schemes, recently they are being incorporated in automatic control systems [6,8,9,10,11]. Due to the high sampling rate and accuracy, compared with Supervisory Control and Data Acquisition (SCADA) systems, it has been possible to close the control loop not only locally, but in a wide-area—introducing in this way the wide-area control systems (WACS) [12,13].
The use of flexible AC transmission systems (FACTS) as actuators in WACS, leads to robust real-time control systems able to swiftly mitigate perturbations on the network. The most common FACTS device in literature and in the industry used for WACS applications is the static VAr compensator (SVC). The SVC has been commonly used for VAR regulation using local measurements, allowing for increasing the power transfer capabilities, controlling the voltage at a specific node, and enhancing stability margins, among others [14,15,16]. With WAMS, it is possible to improve these common uses, and develop new SVC applications, such as the proposed in the contribution. Previous works present wide-area controls for power systems with embedded SVCs [17,18,19,20,21,22,23,24]. Ref. [17] presents the design of a nonlinear control for damping oscillations, while [18] concludes that wide-area control is better for damping inter-area oscillation than local control. Then, Ref. [20] proposes a resilient control to communication failures and delays, and Ref. [19] proposes a robust coordination control for multiple high voltage direct current and FACTS wide-area controls. Ref. [21] presents a coordinated FACTS control to improve the small-signal stability [25]. More recently, Ref. [22] introduces a strategy for the improvement of the transient stability in [25]. Second to last, Ref. [23] proposes a resilient wide-area damping controller against input and output delays and package drop. Lastly, Ref. [24] develops a WAC-SVC based on estimated signals from a dynamic state estimator and a robust supplementary controller, which allows it to work even when the synchrophasor signals are lost.
According to the emerging industrial requirements for testing custom tailored solutions, this paper presents a hardware-in-the-loop (HIL) implementation of a WAC-SVC in a five-bus two-machine power system with the following three control objectives: to reduce the overloading along of the transmission line, to damp the power oscillations and to increase the critical clearing time (CCT). The primary aim of the HIL-based WAC-SVC is to validate the feasibility of the proposed WAC-SVC in industrial applications using the most modern commercially available synchrophasor technology.
The industrial devices used to test the proposed WAC-SVC are two digital SEL-421 relays and two digital SEL-351 relays, a SEL-2404 satellite clock, a real-time digital simulator (RTDS), and the SEL-3530 real-time automation controller (RTAC).
The paper is organized as follows: Section 2 describes the central problem regarding this contribution and describes the proposed wide-area control. Section 3 presents the details of the hardware-in-the-loop implementation of the test system revealing the central issues using commercial devices for PMU-based control applications and PMUs. Section 4 presents the obtained results with the proposed WAC-SVC. Section 5 draws out the discussion derived from the obtained results. Finally, the conclusion is given in Section 6.

2. Description of the Problem and Its Proposed Control

When a power system experiences a large momentary disturbance (e.g., short circuit, transmission line tripping, loss of generation, among others), the machines’ speeds and angles increase during and after the disturbance. The power systems controllers such as Automatic Voltage Regulator (AVR), Power System Stabilizer (PSS), governor, and FACTS help the system to reach a new steady state. However, if the stability is not recovered, the speeds and angles keep increasing, and the system loses synchronism. In this regard, this paper proposes a generator tripping scheme to complement the proposed WAC-SVC and avoid machine damage in case the system could not reach a stable condition. This tripping scheme tracks the machine angle difference and the acceleration power in actual time to establish the closeness to the loss of synchronism and shut down the generator before it loses synchronism. This tripping logic disconnects the generator if and only if the system were to lose synchronism.
In addition to this, an efficient and straightforward strategy to compensate the communication delay is proposed so as to implement the WAC-SVC and the generator tripping scheme. These proposals are detailed, implemented and evaluated in offline and HIL simulations in the following sections.
Firstly, the test system is introduced for the explanatory purposes. Later on, the generator tripping scheme is explained methodically and validated against critical three-phase faults. After that, the development of the control strategy for the minimization of the line current along the SVC-compensated transmission line is presented. Then, the wide-area control for damping power oscillations is introduced. Finally, the delay compensation is thoroughly explained. Even though the generator tripping scheme is enabled the entire time in the proposed WAC-SVC, this is validated before the results section to focus that section on the current minimization and the damping oscillation control actions.

2.1. Test System

To explain the implementation and test the proposed WAC-SVC, the five-bus two-machine power system is used (shown in Figure 1). The capacity of machine A is 1150 MVA, and its active power reference is 1100 MW. The size of machine B is 5000 MVA. Each generator is a synchronous machine with its hydraulic turbine and controllers: AVR (IEEE ST1), PSS (IEEE PSS1A) and governor. The reference voltage at bus 1 and bus 5 is 13.8 kV.
Transmission lines are modeled using a distributed parameter transmission line model. An SVC is connected at bus 4 and its capacity is ±230 MVAr at 500 kV. The convention used indicates that negative power corresponds to the inductive zone of the SVC. A 5000 MVA load is connected at bus 3; this load is represented by a constant power model. Appendix A gives all the parameters used.

2.2. Generator Tripping Scheme

Figure 2 is used to explain the proposed tripping scheme. P e ( t ) represents the active electric power delivered by the synchronous machine, P m is the mechanical power supplied to the generator by the prime mover, and δ ( t ) is the angular displacement of the rotor machine in electrical values. The three different P δ curves represent the prefault, fault and postfault scenarios. The equal-area criterion (EAC) states that the machine will be stable if deceleration area ( A 2 ) is equal or bigger than the acceleration area ( A 1 ) [26]. However, since the P δ curves are time-varying due to the control and compensation actions, it is challenging to establish a priori fulfillment of the EAC just after the fault clearing time in industrial applications.
Figure 2a shows typical dynamic behavior of a stable case against a large disturbance. Originally, the system is operating at the equilibrium point a, where P e ( t ) = P m and δ ( t ) = δ 0 . When the fault strikes at t = t f , P e ( t ) suddenly changes from point a to point b and P e ( t ) becomes smaller than P m . Therefore, the rotor starts to accelerate, and the machine speed commences to exceed the synchronous speed (Figure 2a, bottom, red waveform), and thus the δ ( t ) starts to increase (Figure 2a, bottom, green waveform). Then, the fault is cleared at point c and suddenly the operating point d is reached in the postfault condition. At this operating point, d, P e ( t ) > P m and the rotor machine starts to slow down and reaches the synchronous speed at point e. However, even at this point, the machine is not in the final equilibrium point yet due to P e ( t ) > P m . Therefore, the machine continues reducing its speed to values below the synchronous speed. This oscillation process continues until the transient dies out and the machine settles down in the final steady-state.
Figure 2b shows the unstable case. Here, the machine does not reach the synchronous speed before reaching the critical point. Consequently, the machine starts to accelerate from δ ( t ) > δ u n since P e ( t ) < P m [26].
As a conclusion, it is said that the machine is stable against a large disturbance if the machine reaches synchronous speed for the first time—after the fault clearance—before its angle reaches the critical point. A close-up of the critical and tripping points are shown in Figure 2c. Notice that, if the critical point exists, this is always between π / 2 rad and π rad in the P δ curve.
The basic idea to detect the unstable behavior after the fault clearance is to determine if the angle δ ( t ) keeps increasing just before it reaches the critical point δ u n , as shown in Figure 2. To do this, we have to be able to measure or estimate in real time δ ( t ) , P e ( t ) , and P m . It is clear as per Figure 2 that, in the first swing, the system is in the deceleration area A 2 if δ ( t ) > π / 2 rad and P e ( t ) > P m ( P a < 0 ) . The closeness between P e ( t ) and P m for δ ( t ) > π / 2 rad gives the proximity to the critical point, and consequently to the instability. Figure 3 shows the proposed generator tripping scheme based on the previous explanations. Due to the simplicity of the equal-area criterion based on the classical model of transient stability, two conservative thresholds are added to establish the closeness to the tripping point before the machine starts to speed up again (Figure 2b,c).
Figure 4 and Figure 5 show the performance of this tripping scheme against a three-phase bolted fault cleared by opening the faulted line after 11 and 12 cycles, respectively. The bottom of Figure 4 and Figure 5 shows the tripping conditions in real time. In Figure 4, the tripping condition is not reached. On the other hand, the tripping condition is actually reached as shown in Figure 5; the angle difference evolution when the machine is not disconnected is the one in red, and the one in blue is the response when the machine is disconnected just after the tripping condition is detected. The proposed generator tripping logic demonstrates its effectiveness as it disconnects the machine just when it is necessary and not before. Notice that, after the disconnection, the remaining system reaches a new steady-state. Be aware that the system loses synchronism if the machine A is not disconnected.
This logic allows the machines to remain connected to the power system to give time to their controllers and the proposed WAC-SVC to act and to stabilize the power oscillations. In addition, it prevents the generator from remaining connected under unsafe conditions.
The next subsection describes the proposed control to increment the critical clearing time (CCT) and damp the power oscillations.

2.3. Control Strategy for the Minimization of the Line Current

The proposed control strategy for the minimization of the current magnitude along the SVC-compensated transmission line while maintaining the active power flow is described here. As by-products, the power losses decrease, and the transferred active power along the line can increase since the reactive current component decreases.
On transmission lines, the Root Mean Squared (RMS) current varies along the line and its maximum value depends on the voltages at the ends of the line and the surge impedance load (SIL) [26,27]. For explanation purposes, consider the SVC-compensated transmission line section shown in Figure 6.
The following equation gives the current profile along the line regarding its parameters and end voltages from the lossless long transmission line model [26]:
I 24 ( x ) = V 2 V 4 e γ Z c ( e γ e γ ) e γ x V 4 e γ V 2 Z c ( e γ e γ ) e γ x ,
where I 24 ( x ) , V 2 , and V 4 are phasor quantities. x represents the distance to the sending end. I 24 ( x ) is the current at x, V 2 and V 4 are the voltage at sending and receiving ends, respectively, and is the transmission line length. γ is the propagation constant defined as Z Y ; for a lossless line Y = j ω C and Z = j ω L , therefore
γ = Y Z = j ω L C = j β .
The objective is to supply the required active power at the sending end with the minimum value of the maximum RMS current along the line. Bear in mind that I 24 ( x ) is a complex variable, and its magnitude is:
| I 24 ( x ) | = ( I 24 ( x ) ) 2 + ( I 24 ( x ) ) 2 .
( I 24 ( x ) ) and ( I 24 ( x ) ) are detailed in Appendix B. The position x I m a x at which the current reaches its maximum RMS value is found by solving d | I 24 ( x ) | d x = 0 for x. This assumption is true for lines transferring active power above its SIL; below the SIL, the maximum current is at one of the two ends. The maximum RMS current magnitude is found by substituting x I m a x in Equation (3), i.e., | I 24 m a x | . Since an SVC is connected at the receiving end of the line, the voltage magnitude at this node can be regulated to minimize I 24 m a x . Therefore, the SVC voltage reference that minimizes the maximum current along the line is found by solving d | I 24 m a x | d | V 4 | = 0 for | V 4 | , yielding the following result:
| V 4 | = cos ( β ) | V 2 | 2 { V 2 } .
Only the measurement of the sending end voltage is required to calculate the SVC voltage reference that minimizes the maximum current along the transmission line which can be observed in this equation. PMUs along with a delay compensation algorithm are used to implement Equation (4) in WAC-SVC.

2.4. Wide-Area Control for Damping Power Oscillations

Synchrophasor measurements can also be used for damping power system oscillations that consequently affect generator angular speeds. The power oscillations between two groups of machines or areas interconnected by a transmission link can be counteracted by adding the term k ( f 1 f 5 ) to Equation (4). The current control and damping oscillations strategies for the control reference calculation are synthesized in Equation (5):
| V 4 | = cos ( l β ) | V 2 | 2 { V 2 } + k ( f 1 f 5 ) ,
where f 1 and f 5 are the voltage oscillation frequencies of buses 1 and 5, respectively; and k is a proportional gain that weighs the damping oscillation term. An SVC is used in this work to follow the voltage reference given by Equation (5); however, a static compensator (STATCOM) can also be used instead [28,29].

2.5. Delay Compensation

The delay compromises the control performance, so it is necessary to implement an additional action to compensate it. This adverse effect can be worse than not having the SVC since delay increases the system oscillations, reduces the damping and the CCT. Figure 7 shows the typical time delays regarding the different stages involved in the WAC-SVC implementation. The total delay goes from 60 ms to 200 ms, approximately. However, this delay can be up to 400 ms or more, depending on the control application. The delay is time-varying since the phasor data concentrators (PDCs), in practical implementations, are configured to time-align and transmit simultaneously several synchrophasor data streams so as to be used for monitoring or control application. In the HIL implementation presented in this paper, the PDC function is executed by the RTAC.
In real-life networks, the buses could be up to hundreds of kilometers apart. Therefore, the communication delays are not negligible. For this reason, an estimation process based on a polynomial fitting method is proposed to efficiently compensate the delays and allow the implementation of the proposed generator tripping scheme and the WAC-SVC. Refer to Appendix C for details.

3. HIL Implementation

HIL tests are now being increasingly used to assess and analyze the behavior of proposed controls, protections or algorithms because it is possible to detect some poor functioning or properties that are not considered or known in typical factory acceptance testing stages. Specifically, in the field of electrical power systems, it is uncommon to perform testing tasks in real-world systems; nonetheless, when the devices under test do not require power interchange, HIL tests are the best real-world approach in digital simulation.
The HIL implementation of the proposed generator tripping and WAC-SVC schemes consists of their programming in an industrial controller, and in the use of different communication protocols to send and receive information between the commercial devices. Commonly, commercially available controllers do not have sophisticated built-in functions, which makes it difficult to program complex control actions in these kind of devices. The following subsections present the HIL implementation details and guidelines.

3.1. Real-Time Test System Implementation

The real-time simulation platform used in this implementation is an RTDS. To reproduce the test power system, the RTDS must have at least two PB5 processor cards, a Giga Transceiver Analogue Output (GTAO) card for analog outputs, and a Giga Transceiver Network Interface (GTNET) card with enabled Generic Stream Encapsulation (GSE) protocol. In addition, four relays are necessary. In this case, we use two SEL-351S and two SEL-421. The relays must have an enabled PMU function. A GPS clock is required to timestamp the estimated phasors. Finally, the SEL-3530 RTAC (real-time automation controller) is used for programming the WACS, the time delay compensation method, and the generator tripping scheme [30].
Figure 8 shows the schematic representation of the HIL implementation. The power system is modeled and simulated in RTDS. The three-phase voltages of the buses 1, 2, 4 and 5 are sent to the relays using the analog output card. The four relays use the IEEE protocol C37.118 [31,32] to send the synchrophasors to the SEL-3530 RTAC via Ethernet. All the devices receive a GPS signal from the satellite clock SEL-2404 to timestamp the phasors calculated by the SEL relays.
The RTAC receives and aligns the phasors according to their timestamp. Then, it executes the control strategy given by Equation (5) which is programmed in IEC 61131 language [33]. The resulting voltage reference signal for the SVC is sent back to the RTDS via Ethernet in the IEC 61850 GOOSE communication protocol [34,35]. GOOSE protocol is widely used in communications between protection devices and monitoring of electrical power systems [36]. The control signal is received by the RTDS and is assigned as the reference voltage to the internal control of the SVC. This follows the reference signal set by Equation (5) to complete the control action.

3.2. Device Configuration for Implementation

To reproduce this work, the following next steps are suggested:
  • Model the test system in RSCAD and perform dynamic simulation tests for assessing its correct behavior.
  • Connect external devices as shown in Figure 1. The GTAO card output voltage is ±10 V and the relays have a rated voltage input of up to 300 V (LN). Since a power amplifier is not considered in this implementation, a special cable is necessary to connect the RTDS with the relays. The special cable links the GTAO card with the low voltage card of each relay as shown in the relay manual [37,38].
  • Configure each relay with 60 messages per second and select P as the PMU application. The user defines the IP address, the PMU ID, and the communication port. The user must also indicate the IP of the controller device, in this case, the RTAC. It is essential to ensure that the voltage measured by each relay corresponds to the voltage value in the respective bus of the power system implemented in the RTDS software.
  • Use the RTAC to perform the following three tasks: synchrophasors reception, algorithm programming, and sending of the control signal through GOOSE protocol.
  • Finally, configure the RTDS to receive GOOSE signals. It is necessary to have the GOOSE protocol in RTDS.
It is important to test each step separately beforehand to reduce error uncertainties and possible malfunctioning.

4. Results

This section presents the HIL results of the WACS implemented on the test system shown in Figure 1. Firstly, the system is used to evaluate the control strategy for the minimization of the maximum current along the line. Lastly, the proposed damping term is added and assessed against a three-phase bolted fault.

4.1. Assessment of the Control Strategy for the Line Current Minimization

Equation (4) gives the maximum current when the line is overloaded. Figure 9a shows the current along the SVC-compensated transmission line, i.e., the line between buses 2 and 4. The blue waveform corresponds to the current leaving bus 2, the pink one corresponds to the current entering bus 4, and the other waveforms correspond to intermediate currents along line 2–4. The system is initially in steady state with the SVC disconnected. At t = 1 s, the SVC starts the compensation using the voltage reference computed with Equation (4) to reduce the maximum current along the line. Notice how the maximum current is at the receiving end node (bus 4) and how it starts reducing as soon as the SVC is connected. Figure 9b,c shows the injected reactive power by the SVC and its voltage reference, respectively. Since the load is over the transmission line SIL and the reactive power is dominantly inductive, the reactive current component is inductive. This explains why the SVC is injecting its total capacitive reactive power.
As per Figure 9c, the voltage reference is dynamically changing about 1 pu according to Equation (4), but the voltage can only be taken to 0.95 pu due to the size of the SVC. A smaller maximum current along the line can be obtained using a larger SVC. With the actual SVC size, the maximum current is barely reduced a 4.3%.
To evaluate the effect of the SVC size, a steady-state analysis is performed. Figure 10 shows the maximum current along the line against the SVC reactive power and voltage. According to Figure 10a, it is possible to reduce the maximum current even more by injecting more reactive power.
On the other hand, Figure 10b shows the voltage on the SVC bus depending on the maximum current. For this no-SVC case, the bus voltage is 0.905 pu. As the injected reactive power increases, the SVC bus voltage increases and the maximum current decreases. The bus voltage is 0.95 pu when the SVC injects 200 MVAr. Figure 10a,b show that the voltage reference to minimize the maximum current is 1.069 pu. However, this reference implies injecting 800 MVAr, which exceeds the SVC capability. Figure 9 and Figure 10 are obtained under overloaded conditions and the uncompensated line open.

4.2. Power Oscillations Damping Control

The purpose of this section is to evaluate the proposed WAC-SVC against power oscillations due to a 10-cycle three-phase bolted fault in the middle of the uncompensated transmission line. The short-circuit is cleared by simultaneously opening the breakers at the ends of this transmission line. A constant load model of 5000 MVA with a lagging power factor of 0.85 is used for representing the load at bus 3. The machine A supplies 1100 MW, and therefore the remaining line is over SIL after tripping the faulted line.
Figure 11 shows the system response for the three different scenarios: the yellow waveform for the case without SVC, red for the proposed WAC-SVC implemented in the RTDS simulation software (RTDS-based WAC-SVC), and the blue one for the proposed delay-compensated HIL-based WAC-SVC. Notice that the second oscillation is the main problem for the case without SVC. For the other two cases, the responses almost overlap each other, demonstrating the effective implementation of the proposed WACS in the HIL environment.
During the fault and the first swing after the fault clearing, the SVC injects its total capacitive reactive power and therefore, the delay compensation at the beginning of the fault is not needed. An extra logic is programmed to ensure the injection of the total capacitive reactive power after the fault is detected and during the first sliding window of the delay compensation method, i.e., 200 ms for this case.
Figure 12 shows the SVC voltage reference through the prefault, fault, and postfault conditions. On the other hand, Figure 13 shows the reactive power injected by the SVC. Notice that, at the fault condition, the SVC is only capable of injecting around 90 MVAr due to the voltage sag. The SVC keeps injecting its full capacity during an additional 200 ms and then tracks the voltage reference given by Equation (5) after the fault is cleared. Notice that the SVC automatically behaves as described in [39] when using the proposed WACS. Due to the electromagnetic transients after the fault clearance, the SVC injects an oscillating reactive power as shown in Figure 13. Figure 11, Figure 12 and Figure 13 demonstrate how the response of the delay-compensated HIL-based WAC-SVC match with the response only obtained through digital simulation without communication delays. These results show that the proposed delay compensation method and its implementation in an industrial real-time automatic controller work efficiently. By using industrial PMU and communication protocols as well as a satellite clock, a behavior as good as that obtained in ideal conditions without time delays is also achieved.
Figure 14 shows the P- δ phase portrait of the RTDS-based WAC-SVC. It can be seen here that the dynamic of the P- δ plot matches the theoretical plot described in Section 3 [26,39]. During the fault, machine A accelerates and can only supply around 500 MW. Machine A active power oscillates from a maximum of 1786 MW to a minimum of 493 MW after the fault is cleared. Two oscillations afterwards, the system practically reaches a steady state.
For further comparison, the critical clearing time (CCT) is computed for these operating scenarios. The case without SVC has a CCT of 180 ms, the case with SVC in local control mode has a CCT of 186 ms, the proposed RTDS-based WAC-SVC has a CCT of 225 ms, and, finally, the proposed delay-compensated HIL-based WAC-SVC gives a CCT of 218 ms. Notice that the SVC case with local control mode increments the CCT by 6 ms in comparison to the system without SVC; this barely represents an improvement of 3.22%. On the other hand, using the proposed control fully implemented in the RTDS software, the CCT increases 45 ms or 25%. The HIL implementation has a CCT increment of 38 ms (21.1%) due to the use of real industrial devices, different communication protocols, and an online delay compensation. The increase of the CCT also represents an increment of the power transfer capability. Ref. [40] indicates an increment of up to 15 MW for every increased millisecond.

4.3. Alternative Case Studies

This section presents some extra studies for a deeper assessment of the WAC-SVC. This case consists of the same test system presented in the previous section but with the SVC-compensated line operating under the SIL. Machine A now supplies 950 MW with a rated capacity of 1000 MVA. In addition, the lagging load power factor changes from 0.85 to 0.95.
Figure 15 shows the system response for the three different scenarios: the yellow waveform for the case without SVC, red for the proposed RTDS-based WAC-SVC, and the blue one for the proposed delay-compensated HIL-based WAC-SVC. In this case, the second oscillation problem is present for the no-SVC scenario. For this scenario, the damping is lower than in the previous case study. For the other two scenarios, the second angle swings are smaller than their respective first swings, and the damping is as good as in the over-SIL case. A negligible difference between the RTDS and the HIL implementations of the proposed WAC-SVC is also observed.
Figure 16 shows the machine A angle response against a larger clearing time of 181.67 ms for further validation of the proposed WAC-SVC. In the case without SVC, machine A loses synchronism after three oscillations. In the case with the SVC, the machine can maintain synchronism although with poor damping; after six swings, the system still oscillates. Finally, the systems with the RTDS-based WAC-SVC and delay-compensated HIL-based WAC-SVC reach the steady state after only two oscillations.
Figure 17 and Figure 18 show the P- δ curves from Figure 16. Figure 17 compares the no-SVC (in orange) and delay-compensated HIL-based WAC-SVC (in blue) responses. Point A indicates the steady state of the system before the fault starts. The fault is cleared by opening the faulted line at point B. Note that, from A to B, in both cases, the behavior is similar; however, the WAC-SVC slightly reduces the acceleration area. Points C1 and C2 indicate the maximum angle for the first swing without SVC and with the WAC-SVC, respectively. These points (C1 and C2) show that the power transfer with the WAC-SVC is higher during the deceleration area within the first swing. Notice that the WAC-SVC reduces and increases the acceleration and deceleration areas by injecting reactive power when the machine angle is increasing, but it absorbs reactive power when the angle is decreasing. This process is repeated until the power oscillations dampen out. These important phenomena are spotlighted in zones Z1 and Z2 of Figure 17. Figure 18 compares the SVC with local control (green) and the delay-compensated HIL WAC-SVC (blue) responses. These cases have similar behavior from Point A to point C. After point C, the improvement of the proposed control can be pinpointed within Z1 and Z2. According to Z1, the WAC-SVC reduces the acceleration area more than the local controlled SVC. This is achieved as the former absorbs reactive power while the latter continues injecting reactive power, whereas, in Z2, the WAC-SVC increases the deceleration area by injecting reactive power. The local control also injects reactive power in this part, but it is not enough to dampen the oscillations quickly.

5. Discussion

The wide-area controlled SVC showed satisfactory results regarding the proposed objectives, increasing loadability and minimizing the maximum current flow through the SVC-compensated transmission line. In addition, CCT increased up to 25% and 21.1% with the proposed WAC-SVC in simulation and HIL implementation, respectively. The maximum current along the SVC-compensated line can be minimized to up to 119 A; due to the capacity of the SVC used, this was reduced to 67 A, which corresponds to a reduction of 8.2% in conduction losses along the line. On the other hand, the WAC-SVC swiftly dampens out the power oscillations as compared with the SVC in local control mode. Furthermore, the proposed machine tripping logic demonstrated that it can detect disconnection instantly, just before the machine loses synchronism.
One of the principal benefits of the proposed WAC-SVC is that its implementation does not depend on a mathematical model. Another significant contribution is that the control was implemented with synchrophasors and control devices, which, in fact, are used for industrial applications.

6. Conclusions

This paper has presented a wide-area controlled static VAr compensator (WAC-SVC) and its Hardware-in-the-loop implementation with both industrial PMUs and areal-time automatic controller. The obtained results have demonstrated the feasibility of this type of control systems using the latest technology.
The proposed control allowed to increase the critical clearing time up to 21.1% (38 ms) and 17.2% (32 ms) concerning the cases without SVC and with the local controlled SVC. In addition to this, a generator tripping scheme and a delay compensation algorithm to complement the WAC-SVC were proposed.

Author Contributions

This paper is the result of the effort of all the authors. A.E., J.S., C.N., and E.B. conceived the seminal idea. N.V. and H.G. evaluated the control performance. H.G. assisted in the HIL implementation by providing support and equipment. A.E. did the case studies design as well as their programming in the offline and HIL simulations. The results were evaluated and analyzed by all the authors. The writing, review, and editing were carried out by all the authors.

Acknowledgments

This research was supported by CONACYT, Mexico (Grant: 369611). We would like to thank the project FORDECYT 190966 for the facilities granted to carry out this research. We thank Schweitzer Engineering Laboratories (SEL) for providing the RTAC device to develop the HIL tests.

Conflicts of Interest

SEL and CONACYT had no role in the design of the study; in the collection, analyses, or interpretation of data; in the writing of the manuscript, and in the decision to publish the results.

Abbreviations

The following abbreviations are used in this manuscript:
AVRAutomatic Voltage Regulator
CCTCritical Clearing Time
FACTSFlexible AC Transmission System
PMUPhasor Measurement Unit
PSSPower System Stabilizer
RTACReal-Time Automation Controller
RTDSReal-Time Digital Simulator
STATCOMStatic Synchronous Compensator
SVCStatic VAr Compensator
WACSWide-Area Control System
WAC-SVCWide-Area Controlled SVC
WAMSWide-Area Monitoring System
SELSchweitzer Engineering Laboratories

Appendix A. Model Parameters

Table A1. Machine parameters.
Table A1. Machine parameters.
MachineNominal
Voltage (kV)
Inertia
H
X a
(pu)
X d
(pu)
X d
(pu)
X d
(pu)
X q
(pu)
X q
(pu)
R a
(pu)
M i 13.83.70.181.3050.2960.2520.4740.2430.00285
Table A2. AVR parameters (type IEEE ST1).
Table A2. AVR parameters (type IEEE ST1).
T r V imx
(pu)
V imn
(pu)
T c
(pu)
T b
(s)
K a T a
(s)
V rmx
(pu)
V rmn
(pu)
K c K f T f
(pu)
0.0210.0−10.00.00.02000.00120.00.00.00.0010.1
Table A3. PSS parameters (type IEEE PSS1A).
Table A3. PSS parameters (type IEEE PSS1A).
A 1 A 2 T 1
(s)
T 2
(s)
T 3
(s)
T 4
(s)
T 5
(s)
T 6
(s)
K S
(pu)
V rmax
(pu)
V rmin
(pu)
V cu
(pu)
V cl
(pu)
0.00.00.060.50.00.00.70.01520.15−0.1520.31
Table A4. Governor parameters (type PIDGOV).
Table A4. Governor parameters (type PIDGOV).
R perm
(pu)
T perm
(s)
K p
(pu/s)
K i
(pu/s)
K d
(s)
T a
(s)
T b
(pu)
D turb
(pu)
G 0
(pu)
G 1
(pu)
0.050.01.1630.1050.00.000010.30.00.00.25
P 1
(pu)
G 2
(pu)
P 2
(pu)
P 3
(pu)
G max
(pu)
G min
(pu)
A tw
(pu)
T w
(s)
Vel max
(pu/s)
Vel min
(pu/s)
0.250.50.51.01.20.011.03.00.1−0.1
Table A5. Transmission line parameters.
Table A5. Transmission line parameters.
Line R 1
( Ω / Km )
Xl 1
( Ω / Km )
Xc 1
( M Ω / Km )
R 0
( Ω / Km )
Xl 0
( Ω / Km )
Xc 0
( M Ω / Km )
L i j 0.017550.32937710.19899340.27581.2139110.3197038
Table A6. Transformers parameters.
Table A6. Transformers parameters.
TransformerVoltage (kV)
Winding 1
Voltage (kV)
Winding 2
Connection
Winding 1
Connection
Winding 2
x l
(pu)
R
(pu)
T i 13.8500YY0.120.002

Appendix B

Remembering that:
| I 24 ( x ) | = ( I 24 ( x ) ) 2 + ( I 24 ( x ) ) 2 ,
( I 24 ( x ) ) and ( I 24 ( x ) ) are:
( I ( x ) ) = R 1 + R 2 + R 3 + R 4 R 5 ,
where
R 1 = ( ( V s r V r e l α cos ( l β ) ) e x α cos ( x β ) ( V s i + V r e l α sin ( l β ) ) e x α sin ( x β ) ) ( e l α cos ( l β ) e l α cos ( l β ) ) , R 2 = ( ( V s i + V r e l α sin ( l β ) ) e x α cos ( x β ) + ( V s r V r e l α cos ( l β ) ) e x α sin ( x β ) ) ( e l α sin ( l β ) + e l α sin ( l β ) ) , R 3 = ( ( V r e l α cos ( l β ) + V s r ) e x α cos ( x β ) + ( V r e l α sin ( l β ) + V s i ) e x α sin ( x β ) ) ( e l α cos ( l β ) e l α cos ( l β ) ) , R 4 = ( ( V r e l α sin ( l β ) + V s i ) e x α cos ( x β ) ( V r e l α cos ( l β ) + V s r ) e x α sin ( x β ) ) ( e l α sin ( l β ) + e l α sin ( l β ) ) , R 5 = Z c ( ( e l α cos ( l β ) e l α cos ( l β ) ) 2 + ( e l α sin ( l β ) + e l a l p h a sin ( l β ) ) 2 ) ,
and
( I ( x ) ) = I m 1 + I m 2 + I m 3 + I m 4 I m 5 ,
where
I m 1 = ( ( V s i + V r e l α sin ( l β ) ) e x α cos ( x β ) + ( V s r V r e l α cos ( l β ) ) e x α sin ( x β ) ) ( e l α cos ( l β ) e l α cos ( l β ) ) , I m 2 = ( ( V s r V r e l α cos ( l β ) ) e x α cos ( x β ) ( V s i + V r e l α sin ( l β ) ) e x α sin ( x β ) ) ( e l α sin ( l β ) + e l α sin ( l β ) ) , I m 3 = ( ( V r e l α sin ( l β ) + V s i ) e x α cos ( x β ) ( V r e l α cos ( l β ) + V s r ) e x α sin ( x β ) ) ( e l α cos ( l β ) e l α cos ( l β ) ) , I m 4 = ( ( V r e l α cos ( l β ) + V s r ) e x α cos ( x β ) + ( V r e l α sin ( l β ) + V s i ) e x α sin ( x β ) ) ( e l α sin ( l β ) + e l α sin ( l β ) ) , I m 5 = Z c ( ( e l α cos ( l β ) e l α cos ( l β ) ) 2 + ( e l α sin ( l β ) + e l α sin ( l β ) ) 2 ) .
Solving
d | I 24 ( x ) | d x = 0
for x, it is found the position x I m a x at which the current reaches its maximum RMS value. This value is:
x I m a x = 1 β arctan ( X m n 1 X m n 2 + X m n 3 + X m n 4 + X m n 5 + X m n 6 2 sin ( l β ) V r ( sin ( l β ) 2 V r + cos ( l β ) 2 V s r V r ) ) ,
where
X m n 1 = 2 cos ( l β ) 3 V r 2 2 cos ( l β ) 2 V r V s r cos ( l β ) V r 2 + cos ( l β ) V s i 2 + cos ( l β ) V s r 2 , X m n 2 = 4 cos ( l β ) 6 V r 4 + 4 sin ( l β ) 6 V r 4 8 cos ( l β ) 5 V r 3 V s r + 4 sin ( l β ) 2 V r 4 X m n 3 = 8 cos ( l β ) sin ( l β ) 4 V r 3 V s r 8 sin ( l β ) 4 V r 4 + 4 cos ( l β ) 3 V r 3 V s r , X m n 4 = 4 cos ( l β ) 4 V r 2 V s i 2 + 8 cos ( l β ) 4 V r 2 V s r 2 + 4 cos ( l β ) 2 sin ( l β ) 2 V r 2 V s r 2 4 cos ( l β ) 4 V r 4 , X m n 5 = 4 cos ( l β ) 3 V r V s i V s r 2 4 cos ( l β ) 3 V r V s r 3 8 cos ( l β ) sin ( l β ) 2 V r 3 V s r 2 cos ( l β ) 2 V r 2 V s i 2 , X m n 6 = cos ( l β ) 2 V r 4 2 cos ( l β ) 2 V r 2 V s r 2 + cos ( l β ) 2 V s i 4 + 2 cos ( l β ) 2 V s i 2 V s r 2 + cos ( l β ) 2 V s r 4 .
Substituting x I m a x in Equation (A1), the maximum RMS current magnitude is found, i.e., | I 24 m a x | . Since an SVC is connected at the receiving end of the line, the voltage magnitude at this node can be regulated to minimize I 24 m a x . Therefore, solving
d | I 24 m a x | d | V 4 | = 0
for | V 4 | , the SVC voltage reference that minimize the maximum current along the line is found, yielding the following result:
| V 4 | = cos ( β ) | V 2 | 2 { V 2 } .

Appendix C

To perform the estimation, a window of N samples (synchrophasors) is used to fit the following polynomial function:
y ( t ) = α 1 + α 2 t + α 3 t 2 + α 4 t 3 + α 5 t 5 ,
where α 1 , α 2 , α 3 , α 4 and α 5 are parameters estimated using the least squares method. The function to be minimized is the error between the measurements and the function y ( t ) :
E = i = 1 N ( Y i y i ) 2 ,
where Y i and y i are the measurement and function y ( t ) evaluated in the i-th window sample, respectively. E is the sum of the squares of the error of each sample. This creates the system of algebraic equations given by Equation (A10):
N i = 1 N t i = 1 N t 2 i = 1 N t 3 i = 1 N t 5 i = 1 N t i = 1 N t 2 i = 1 N t 3 i = 1 N t 4 i = 1 N t 6 i = 1 N t 2 i = 1 N t 3 i = 1 N t 4 i = 1 N t 5 i = 1 N t 7 i = 1 N t 3 i = 1 N t 4 i = 1 N t 5 i = 1 N t 6 i = 1 N t 8 i = 1 N t 5 i = 1 N t 6 i = 1 N t 7 i = 1 N t 8 i = 1 N t 10 α 1 α 2 α 3 α 4 α 5 = i = 1 N Y i i = 1 N t Y i i = 1 N t 2 Y i i = 1 N t 3 Y i i = 1 N t 5 Y i .
This system of equations is solved for α 1 , α 2 , α 3 , α 4 and α 5 within the RTAC with the Gaussian elimination method. After obtaining the values for each α i , the function y ( t ) is evaluated at the desired time instant. In this case, at the time of the end of the window, it is added the communication time delay to estimate and compensate forward. Figure A1 graphically shows how this estimation is performed. First, a window of N phasors is taken. With them, the parameters α i are calculated and the value of the control signal is calculated one time forward. In the next time step, a new phasor is obtained and the oldest phasor is discarded. With this new window, the process is repeated, and a new estimated value of the control signal is obtained, and so on with the next samples.
Figure A1. Estimation of reference signal.
Figure A1. Estimation of reference signal.
Energies 11 01639 g0a1

References

  1. Adibi, M.; Martins, N. Impact of power system blackouts. In Proceedings of the 2015 IEEE Power & Energy Society General Meeting, Denver, CO, USA, 26–30 July 2015; pp. 1–15. [Google Scholar]
  2. Liang, G.; Weller, S.R.; Zhao, J.; Luo, F.; Dong, Z.Y. The 2015 ukraine blackout: Implications for false data injection attacks. IEEE Trans. Power Syst. 2017, 32, 3317–3318. [Google Scholar] [CrossRef]
  3. Xue, Y.; Xiao, S. Generalized congestion of power systems: Insights from the massive blackouts in India. J. Mod. Power Syst. Clean Energy 2013, 1, 91–100. [Google Scholar] [CrossRef]
  4. Andersson, G.; Donalek, P.; Farmer, R.; Hatziargyriou, N.; Kamwa, I.; Kundur, P.; Martins, N.; Paserba, J.; Pourbeik, P.; Sanchez-Gasca, J.; et al. Causes of the 2003 major grid blackouts in North America and Europe, and recommended means to improve system dynamic performance. IEEE Trans. Power Syst. 2005, 20, 1922–1928. [Google Scholar] [CrossRef]
  5. Heydt, G.; Liu, C.; Phadke, A.; Vittal, V. Solution for the crisis in electric power supply. IEEE Comput. Appl. Power 2001, 14, 22–30. [Google Scholar] [CrossRef]
  6. Lalou, M.; Loosli, A.; Sauvain, H.; Zima, M.; Andersson, G. Improvement of power transmission capacity in power networks equipped with FACTS devices and Wide Area Control Systems: A case study. In Proceedings of the International Symposium Modern Electric Power Systems (MEPS), Wroclaw, Poland, 20–22 September 2010; pp. 1–5. [Google Scholar]
  7. Soonee, S.K.; Agrawal, V.K.; Agarwal, P.K.; Narasimhan, S.R.; Thomas, M.S. The View from the Wide Side: Wide-Area Monitoring Systems in India. IEEE Power Energy Mag. 2015, 13, 49–59. [Google Scholar] [CrossRef]
  8. Xue, Y. Some viewpoints and experiences on wide area measurement systems and wide area control systems. In Proceedings of the IEEE Power and Energy Society General Meeting—Conversion and Delivery of Electrical Energy in the 21st Century, Pittsburgh, PA, USA, 20–24 July 2008; pp. 1–6. [Google Scholar]
  9. Xiaoyang, T.; Guodong, L.; Xiaoru, W.; Shan, Z. The analysis of communication architecture and control mode of wide area power systems control. In Proceedings of the Autonomous Decentralized Systems, ISADS, Chengdu, China, 4–8 April 2005; pp. 59–65. [Google Scholar]
  10. Taylor, C.; Erickson, D.C.; Martin, K.; Wilson, R.; Venkatasubramanian, V. WACS-Wide-Area Stability and Voltage Control System: R D and Online Demonstration. Proc. IEEE 2005, 93, 892–906. [Google Scholar] [CrossRef]
  11. Martinez, E. SIMEFAS: A phasor measurement system for the security and integrity of Mexico’s electric power system. In Proceedings of the IEEE Power and Energy Society General Meeting—Conversion and Delivery of Electrical Energy in the 21st Century, Pittsburgh, PA, USA, 20–24 July 2008; pp. 1–7. [Google Scholar]
  12. Ferrer, H.J.A.; Schweitzer, E.O. Modern Solutions for Protection, Control, and Monitoring of Electric Power Systems; Schweitzer Engineering Laboratories: Pullman, WA, USA, 2010. [Google Scholar]
  13. Phadke, A.G.; Thorp, J.S. Synchronized Phasor Measurements and Their Applications; Springer: Berlin/Heidelberg, Germany, 2008; Volume 1. [Google Scholar]
  14. Gyugyi, L. Power electronics in electric utilities: Static VAR compensators. Proc. IEEE 1988, 76, 483–494. [Google Scholar] [CrossRef]
  15. Fairley, P. Flexible AC Transmission: The FACTS Machine. 2011. Available online: https://spectrum.ieee.org/energy/the-smarter-grid/flexible-ac-transmission-the-facts-machine (accessed on 30 May 2018).
  16. Janke, A.; Mouatt, J.; Sharp, R.; Bilodeau, H.; Nilsson, B.; Halonen, M.; Bostrom, A. SVC operation & reliability experiences. In Proceedings of the 2010 IEEE Power and Energy Society General Meeting, Providence, RI, USA, 25–29 July 2010; pp. 1–8. [Google Scholar]
  17. Venayagamoorthy, G.K.; Jetti, S.R. Dual-Function Neuron-Based External Controller for a Static Var Compensator. IEEE Trans. Power Deliv. 2008, 23, 997–1006. [Google Scholar] [CrossRef]
  18. Heniche, A.; Kamwa, I. Assessment of two methods to select wide-area signals for power system damping control. IEEE Trans. Power Syst. 2008, 23, 572–581. [Google Scholar] [CrossRef]
  19. Li, Y.; Rehtanz, C.; Ruberg, S.; Luo, L.; Cao, Y. Wide-Area Robust Coordination Approach of HVDC and FACTS Controllers for Damping Multiple Interarea Oscillations. IEEE Trans. Power Deliv. 2012, 27, 1096–1105. [Google Scholar] [CrossRef]
  20. Zhang, S.; Vittal, V. Design of wide-area power system damping controllers resilient to communication failures. IEEE Trans. Power Syst. 2013, 28, 4292–4300. [Google Scholar] [CrossRef]
  21. Deng, J.; Li, C.; Zhang, X.P. Coordinated design of multiple robust FACTS damping controllers: A BMI-based sequential approach with multi-model systems. IEEE Trans. Power Syst. 2015, 30, 3150–3159. [Google Scholar] [CrossRef]
  22. Vahidnia, A.; Ledwich, G.; Palmer, E.W. Transient stability improvement through wide-area controlled SVCs. IEEE Trans. Power Syst. 2016, 31, 3082–3089. [Google Scholar] [CrossRef]
  23. Padhy, B.P.; Srivastava, S.C.; Verma, N.K. A Wide-Area Damping Controller Considering Network Input and Output Delays and Packet Drop. IEEE Trans. Power Syst. 2017, 32, 166–176. [Google Scholar] [CrossRef]
  24. Ortega-rivera, I.L.; Vittal, V.; Heydt, G.T.; Fuerte-Esquivel, C.R.; Angeles-Camacho, C. A Dynamic State Estimator Based Control for Power System Damping. IEEE Trans. Power Syst. 2018. [Google Scholar] [CrossRef]
  25. Kundur, P.; Paserba, J.; Ajjarapu, V.; Andersson, G.; Bose, A.; Canizares, C.; Hatziargyriou, N.; Hill, D.; Stankovic, A.; Taylor, C.; et al. Definition and classification of power system stability IEEE/CIGRE joint task force on stability terms and definitions. IEEE Trans. Power Syst. 2004, 19, 1387–1401. [Google Scholar]
  26. Kundur, P.; Balu, N.J.; Lauby, M.G. Power System Stability and Control; McGraw-Hill: New York, NY, USA, 1994; Volume 7. [Google Scholar]
  27. Grainger, J.J.; Stevenson, W.D. Power System Analysis; McGraw-Hill: New York, NY, USA, 1994; Volume 621. [Google Scholar]
  28. Singh, B.; Sharma, N.; Tiwari, A.; Verma, K.; Singh, S. Applications of phasor measurement units (PMUs) in electric power system networks incorporated with FACTS controllers. Int. J. Eng. Sci. Technol. 2011, 3, 64–82. [Google Scholar] [CrossRef]
  29. Paserba, J. How FACTS controllers benefit AC transmission systems—Phases of power system studies. In Proceedings of the IEEE/PES Power Systems Conference and Exposition (PSCE ’09), New Orleans, LA, USA, 19–22 April 2009; pp. 1–4. [Google Scholar]
  30. RTAC SEL-3530 Instruction Manual. Available online: https://www.selinc.com (accessed on 21 March 2018).
  31. IEEE Std C37.118.1-2011 (Revision of IEEE Std C37.118-2005). In IEEE Standard for Synchrophasor Measurements for Power Systems; IEEE: Piscataway, NJ, USA, 2011; pp. 1–61.
  32. IEEE Std C37.118.2-2011 (Revision of IEEE Std C37.118-2005). In IEEE Standard for Synchrophasor Data Transfer for Power Systems; IEEE: Piscataway, NJ, USA, 2011; pp. 1–53.
  33. SELINC. ACSELERATOR RTAC SEL-5033 Software Instruction Manual. Available online: https://www.selinc.com (accessed on 10 April 2018).
  34. Sidhu, T.; Gangadharan, P.K. Control and automation of power system substation using IEC61850 communication. In Proceedings of the 2005 IEEE Conference on Control Applications (CCA 2005), Toronto, ON, Canada, 28–31 August 2005; pp. 1331–1336. [Google Scholar]
  35. Mackiewicz, R. Overview of IEC 61850 and Benefits. In Proceedings of the 2006 IEEE PES Power Systems Conference and Exposition (PSCE’06), Atlanta, GA, USA, 29 October–1 November 2006; pp. 623–630. [Google Scholar]
  36. Seeley, N.C. Automation at Protection Speeds: IEC 61850 GOOSE Messaging as a Reliable, High-Speed Alternative to Serial Communications. In Proceedings of the 10th Annual Western Power Delivery Automation Conference, Spokane, WA, USA, 1–6 April 2008. [Google Scholar]
  37. SELINC. SEL-421 Instruction Manual. Available online: https://www.selinc.com (accessed on 10 March 2018).
  38. SEL-351 Instruction Manual. Available online: https://www.selinc.com (accessed on 11 March 2018).
  39. Haque, M. Improvement of first swing stability limit by utilizing full benefit of shunt FACTS devices. IEEE Trans. Power Syst. 2004, 19, 1894–1902. [Google Scholar] [CrossRef]
  40. Eastvedt, R.B. The Need for Ultra-Fast Fault Clearing. In Proceedings of the Third Annual Western Protective Relay Conference, Spokane, WA, USA, 19–21 October 1976. [Google Scholar]
Figure 1. Test case.
Figure 1. Test case.
Energies 11 01639 g001
Figure 2. P δ and δ t curves: (a) stable case; (b) unstable case; (c) critical point of the unstable case.
Figure 2. P δ and δ t curves: (a) stable case; (b) unstable case; (c) critical point of the unstable case.
Energies 11 01639 g002
Figure 3. Generator tripping scheme.
Figure 3. Generator tripping scheme.
Energies 11 01639 g003
Figure 4. Stable case against an 11-cycle fault: the voltage angle difference between bus 1 and bus 5, the evolution of the power condition in green, the angle condition in blue, and the tripping signal in red.
Figure 4. Stable case against an 11-cycle fault: the voltage angle difference between bus 1 and bus 5, the evolution of the power condition in green, the angle condition in blue, and the tripping signal in red.
Energies 11 01639 g004
Figure 5. Unstable case against a 12-cycle fault: the angle difference between bus 1 and bus 5 when the machine A is not disconnected (red) and when the machine A is disconnected according the proposed tripping logic (blue), the evolution of the power condition is in green, the angle condition is in blue, and the tripping signal is in red.
Figure 5. Unstable case against a 12-cycle fault: the angle difference between bus 1 and bus 5 when the machine A is not disconnected (red) and when the machine A is disconnected according the proposed tripping logic (blue), the evolution of the power condition is in green, the angle condition is in blue, and the tripping signal is in red.
Energies 11 01639 g005
Figure 6. SVC-compensated transmission line section.
Figure 6. SVC-compensated transmission line section.
Energies 11 01639 g006
Figure 7. Implementation delays on the WAC-SVC and the generator tripping scheme.
Figure 7. Implementation delays on the WAC-SVC and the generator tripping scheme.
Energies 11 01639 g007
Figure 8. Schematic representation of the proposed HIL implementation.
Figure 8. Schematic representation of the proposed HIL implementation.
Energies 11 01639 g008
Figure 9. Transient response of SVC voltage reference given by Equation (4).
Figure 9. Transient response of SVC voltage reference given by Equation (4).
Energies 11 01639 g009aEnergies 11 01639 g009b
Figure 10. Steady-state relation among V s v c , I m a x , and Q s v c .
Figure 10. Steady-state relation among V s v c , I m a x , and Q s v c .
Energies 11 01639 g010aEnergies 11 01639 g010b
Figure 11. Machine A angle response of the over-SIL test system against a 10-cycle fault: without SVC (yellow), RTDS-based WAC-SVC (red), and delay-compensated HIL-based WAC-SVC (blue).
Figure 11. Machine A angle response of the over-SIL test system against a 10-cycle fault: without SVC (yellow), RTDS-based WAC-SVC (red), and delay-compensated HIL-based WAC-SVC (blue).
Energies 11 01639 g011
Figure 12. SVC voltage reference due to a 10-cycle fault: RTDS-based WAC-SVC (red), and delay-compensated HIL-based WAC-SVC (blue).
Figure 12. SVC voltage reference due to a 10-cycle fault: RTDS-based WAC-SVC (red), and delay-compensated HIL-based WAC-SVC (blue).
Energies 11 01639 g012
Figure 13. Transient reactive power injected by the SVC due to a 10-cycle fault: RTDS-based WAC-SVC (red), and delay-compensated HIL-based WAC-SVC (blue).
Figure 13. Transient reactive power injected by the SVC due to a 10-cycle fault: RTDS-based WAC-SVC (red), and delay-compensated HIL-based WAC-SVC (blue).
Energies 11 01639 g013
Figure 14. P- δ curve of the RTDS-based WAC-SVC.
Figure 14. P- δ curve of the RTDS-based WAC-SVC.
Energies 11 01639 g014
Figure 15. Machine A angle response against a 10-cycle fault: no SVC (yellow), proposed RTDS-based WAC-SVC (red), and delay-compensated HIL-based WAC-SVC (blue).
Figure 15. Machine A angle response against a 10-cycle fault: no SVC (yellow), proposed RTDS-based WAC-SVC (red), and delay-compensated HIL-based WAC-SVC (blue).
Energies 11 01639 g015
Figure 16. Machine A angle against 10.9-cycle fault: no SVC (yellow), SVC in local control mode (green), proposed RTDS-based WAC-SVC (red), and delay-compensated HIL-based WAC-SVC (blue).
Figure 16. Machine A angle against 10.9-cycle fault: no SVC (yellow), SVC in local control mode (green), proposed RTDS-based WAC-SVC (red), and delay-compensated HIL-based WAC-SVC (blue).
Energies 11 01639 g016
Figure 17. P- δ plot: without SVC case in orange, and delay-compensated HIL-based WAC-SVC in blue.
Figure 17. P- δ plot: without SVC case in orange, and delay-compensated HIL-based WAC-SVC in blue.
Energies 11 01639 g017
Figure 18. P- δ plot: SVC with local control case in green, and delay-compensated HIL-based WAC-SVC in blue.
Figure 18. P- δ plot: SVC with local control case in green, and delay-compensated HIL-based WAC-SVC in blue.
Energies 11 01639 g018

Share and Cite

MDPI and ACS Style

Esparza, A.; Segundo, J.; Nuñez, C.; Visairo, N.; Barocio, E.; García, H. Transient Stability Enhancement Using a Wide-Area Controlled SVC: An HIL Validation Approach. Energies 2018, 11, 1639. https://doi.org/10.3390/en11071639

AMA Style

Esparza A, Segundo J, Nuñez C, Visairo N, Barocio E, García H. Transient Stability Enhancement Using a Wide-Area Controlled SVC: An HIL Validation Approach. Energies. 2018; 11(7):1639. https://doi.org/10.3390/en11071639

Chicago/Turabian Style

Esparza, Aaron, Juan Segundo, Ciro Nuñez, Nancy Visairo, Emilio Barocio, and Héctor García. 2018. "Transient Stability Enhancement Using a Wide-Area Controlled SVC: An HIL Validation Approach" Energies 11, no. 7: 1639. https://doi.org/10.3390/en11071639

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop