Next Article in Journal
Efficient Assessment of Reservoir Uncertainty Using Distance-Based Clustering: A Review
Next Article in Special Issue
A Chance-Constrained Multistage Planning Method for Active Distribution Networks
Previous Article in Journal
Sliding Mode Observer-Based Parameter Identification and Disturbance Compensation for Optimizing the Mode Predictive Control of PMSM
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Optimal Operational Scheduling of Reconfigurable Microgrids in Presence of Renewable Energy Sources

by
Fatma Yaprakdal
1,
Mustafa Baysal
1,* and
Amjad Anvari-Moghaddam
2
1
Faculty of Electrical and Electronics Engineering, Yildiz Technical University, Davutpasa Campus, 34220 Esenler, Istanbul
2
Department of Energy Technology, Aalborg University, 9220 Aalborg East, Denmark
*
Author to whom correspondence should be addressed.
Energies 2019, 12(10), 1858; https://doi.org/10.3390/en12101858
Submission received: 15 March 2019 / Revised: 1 May 2019 / Accepted: 10 May 2019 / Published: 15 May 2019

Abstract

:
Passive distribution networks are being converted into active ones by incorporating distributed means of energy generation, consumption, and storage, and the formation of so-called microgrids (MGs). As the next generation of MGs, reconfigurable microgrids (RMGs) are still in early phase studies, and require further research. RMGs facilitate the integration of distributed generators (DGs) into distribution systems and enable a reconfigurable network topology by the help of remote-controlled switches (RCSs). This paper proposes a day-ahead operational scheduling framework for RMGs by simultaneously making an optimal reconfiguration plan and dispatching controllable distributed generation units (DGUs) considering power loss minimization as an objective. A hybrid approach combining conventional particle swarm optimization (PSO) and selective PSO (SPSO) methods (PSO&SPSO) is suggested for solving this combinatorial, non-linear, and NP-hard complex optimization problem. PSO-based methods are primarily considered here for our optimization problem, since they are efficient for power system optimization problems, easy to code, have a faster convergence rate, and have a substructure that is suitable for parallel calculation rather than other optimization methods. In order to evaluate the suggested method’s performance, it is applied to an IEEE 33-bus radial distribution system that is considered as an RMG. One-hour resolution of the simultaneous network reconfiguration (NR) and the optimal dispatch (OD) of distributed DGs are carried out prior to this main study in order to validate the effectiveness and superiority of the proposed approach by comparing relevant recent studies in the literature.

1. Introduction

Distributed generations (DGs) and local loads can be considered as self-sustainable entities operating as a subsystem of the distribution system by way of the increased penetration of distributed energy resources (DERs) into distribution grids [1]. This subsystem is called a microgrid (MG), which is an aggregation of different types of local loads (controllable or fixed loads), a variety of DERs, and storage devices that can be operated in grid-connected as well as islanded modes [2,3]. Even though the current MGs are technically static, they are about to transform into dynamic systems called reconfigurable MGs (RMGs) thanks to the addition of reconfiguration capability to the MGs via smart switches [4]. Higher levels of cost-effectiveness, efficiency, reliability, and power quality can be indicated as advantages of RMGs for customers even though challenges remain. Primary goals can be achieved by controlling and changing MG topology via the use of remote-controlled switches (RCSs) to control and change the MG topology, which can be represented as the primary objective of using RMGs [5].
Reconfiguration is considered as one of the most critical solutions for active distribution networks (ADNs) facilitating optimal operation management. This plan of action changes the on/off status of the remotely controlled sectionalizing switches (normally closed switches) and RCSs (normally open switches) to improve the total efficiency of the power grid [6]. In addition to decreasing power losses by transferring electrical loads from overloaded feeders to feeders with less electrical load during normal operation of the ADN feeder, voltage profile is also improved. The faulty region is isolated in case of a fault, and electrical loads with the highest priority are restored according to their levels of importance with regard to certain switching operations. Moreover, network reconfiguration (NR) can be performed for a variety of goals such as increasing DG penetration and thus fueling consumption reduction [7], meeting the highest possible energy demand [8], minimizing active power losses [9,10], reducing cost of energy and switching operations [11,12], improving power quality and reliability indices (e.g., mitigating voltage sag) [13], and system restoration with minimum loss in case of failure [14].
Reducing the power loss is the common major objective in ADN reconfiguration studies. The maximum loadability of the ADN is also increased during the process for attaining this objective function, which improves the reliability of the system accordingly [15]. Two essential methods can be used for decreasing real power losses in ADN; the NR and optimal dispatch (OD) of DG units. The losses caused by the distribution systems can only be mitigated up to a certain level with the NR technique. The OD of DGs is a major contributor to obtain greater power loss reduction. The sizing of DGS and NR has been implemented either sequentially or simultaneously in various studies in the literature in order to attain further reductions in power loss [7,16,17]. It is necessary for sequential implementation to determine the sizing of DGs prior to NR, while NR and the sizing of DGs are executed at the same time in a simultaneous action plan. There is a large number of heuristics and artificial intelligence-based methods suggested in the literature for simultaneous application [18,19]. However, the sizing of DGs is considered in terms of distribution network planning in these studies. A combined evaluation of NR and OD of DGs with high wind penetration in the short-term period has been performed [20] as part of the network operation analysis, but the simultaneous application of these two techniques has not been taken into account. In [13], power dispatch is obtained after finding optimal topology within the operational scheduling of a reconfigurable smart microgrid (RSMG). In [21], investor-owned DGs are used, which are not allowed to schedule a generation model. Therefore, the simultaneous application of the two aforementioned techniques is not performed in the optimal day-ahead scheduling study of the smart distribution grid.
This study provides a comprehensive operational scheduling framework to the MG by simultaneously performing the OD of the DGs and NR for minimizing the active power loss and further improving the voltage profile of the power system. The procedure of the framework is realized for the normal operation mode. The operating costs of the distribution network are minimized in the normal operation mode by the optimal scheduling and dispatching of controllable DGs based on the model presented in [22]. In addition, the probabilistic and intermittent characteristics of renewable DG units, including an hourly variation of the demand and power market prices in the power system, have been considered within the scope of our optimal scheduling framework [23,24,25]. Thus, the optimal operational scheduling problem, which is already a non-linear, combinatorial, and NP-hard optimization problem, becomes a more complex problem [11]. A novel approach is suggested in that paper for solving this optimization problem by combining particle swarm optimization (PSO) and selective PSO (SPSO) methods (PSO&SPSO). These are the most frequently used PSO techniques [26,27,28] in power system optimization problems. Here, the proposed PSO–SPSO approach is used for solving the simultaneous application of the MG reconfiguration and the optimal dispatch of three diesel DG units with the objective of power loss minimization in the literature for the first time. The new approach benefits from combining the advantage of both PSO algorithms. Also, the proposed technique facilitates the combinatorial optimization problem, which has too many possible switch combinations. The opening and closing states of switches in the network are used for generating all possible trees via integrating the capabilities of SPSO methods for searching in a selective space. Branches (switches) that are normally closed or opened are used as the search space for that algorithm [29,30].
The remainder of the study has been arranged as such: Section 2 presents the operational scheduling problem of RMGs, where the objective and related constraints are expressed by mathematical explanation. The solution for the problem by using the proposed method (PSO&SPSO) is described in Section 3, while validation of the suggested method is analyzed and the results are given in detail in Section 4. The conclusion is provided in Section 5.

2. Problem Formulation

This part of the study focuses on the optimal operational scheduling problem of RMGs where the system operator has to determine the optimal radial topology of the balanced medium-voltage MG system as well as the optimum power generation level of DGs in order to minimize real power losses. The mathematical formulation given below represents the indicated non-linear combinatorial problem that can be considered as a single-objective optimization problem [31]:
x = [ x 1 ,   x 2 ,   , x d v   ]
min ( f 1 ( x ) ,   f 2 ( x ) ,   f N ( x ) )
s . t .   h i ( x ) = 0   ;   i = 1 ,   ,   p
  g i ( x ) 0   ;   i = 1 ,   ,   q
In this paper, the optimization problem is a minimization problem with its equality and inequality constraints given in the following sections.

2.1. Objective Function

The NR techniques and OD of DG units that eventually decide the direction of power flow in a MG have a significant impact on power loss reduction and voltage profile improvement for the whole system. Hence, minimizing the sum of active power losses in all branches as given in the following equation [16] is the primary goal of our specific problem:
min   { P L = i = 1 b | I i | 2 R i }

2.2. Operational Cost Calculation

The total operational cost is comprised of the purchasing power cost from the main grid (CostRMG) and production cost of DGs (CostDG).
Total   Cost =   Cos t RMG + Cost DG

2.2.1. Cost of Purchasing Power from the Main Grid

The RMG has to purchase power from the upstream grid when DGs are not able to meet total energy demand. The total active power purchase for this case is calculated as follows [13]:
Cost RMG = t = 1 24 v b ( t ) P b ( t )

2.2.2. The Operation Cost of Dispatchable DG Units

DG production cost on a daily basis, which consists of the fuel cost, is calculated by the following mathematical relation [21]:
Cost DG = t = 1 24 a + b × P DG ( t ) + c × ( P DG ( t ) ) 2

2.3. Constraints

Some of the equality and inequality constraints of the RMG have to be considered during the simultaneous application of reconfiguration and the OD of DGs in an RMG. The constraints considered for this study are given as follows [13,31].

2.3.1. Power Balance Constraint

The power balance constraint always must be met through the following equation:
P EP + j = 1 N DG P DGj i = 1 N MGL P MGLi P L = 0

2.3.2. Inequality Constraints

  • Maximum and minimum generation constraint:
There is a constraint for the maximum and minimum active power generation of dispatchable units, which can be stated as indicated below:
P DGi min ( t ) P DGi ( t ) P DGi max ( t )
  • Bus voltage limits:
V min V i V max
It is required that the bus voltage values, Vi, should range between minimum and maximum values after reconfiguration. In this study, these limits are set to Vmin = 0.90 p.u. and Vmax = 1.10 p.u., respectively.
  • Branch current limits:
| I i | I i max
The amount of the flowing current Ii at the ith branch should not be greater than its maximum thermal value Iimax.
  • DG capacity constraint:
The renewable energy policies in some of the countries have a great impact on DG penetration rates. For our study, the total injected active power from the renewable DGs is assumed to vary between 10–60% of the total active power load in the distribution network as in [31], namely:
0.1 × i = 1 n P MGLi i = 1 N DG P DGi 0.6 × i = 1 n P MGLi

2.3.3. Radiality Constraints

Throughout the NR process, all possible MG configurations should be in radial condition. Furthermore, there must not be any loops, and all loads must be connected to the main power supply in the MG’s topological structure. That can be expressed by the following formula [31]:
b N b β b = n N sub

3. Proposed Optimization Method

3.1. Overview of PSO and SPSO

PSO is a population-based metaheuristic optimization algorithm introduced by Kennedy and Eberhart in 1995. Although PSO was first developed for continuous and non-linear optimization problems, it was then enhanced to solve a variety of optimization problems in the fields of engineering and science. In these areas, PSO is preferred primarily with regard to faster convergence rate, accuracy, parallel calculation, and simple application in comparison with other optimization methods. In this part, the mathematical structure of the basic and selective PSO is explained in detail [26,27,32].
The PSO method is created according to the study of the behavior of clustered social animals such as the school of fish and a flock of birds. There is a population of n particles in D-dimensional space with each particle representing a possible solution for PSO which are defined by two parameters as position (pi) and velocity (vi), and are initially chosen randomly. They are updated in each iteration based on their own experience and experience from other ‘particles’ in the group pbest and gbest. The following model is taken as the basis for updating the parameters:
v iD k + 1 = ω × v iD k + c 1 × rand × ( p best i p i k ) + c 2 × rand × ( g best i p i k )
p i k + 1 = p i k × v i k + 1
ω is the inertia weight and is calculated by the following formula:
ω = ω max ( ω max ω min ) × ( k k max )
The velocities are confined in the range of [0,1] by way of applying sigmoid transformation on the velocity parameters in binary PSO, thereby ensuring that the particle position values are either 0 or 1:
sig ( v iD k + 1 ) = 1 1 + exp ( v iD k + 1 )
x iD k + 1 = { 1 ,   if   σ < sig ( v iD k + 1 ) 0 ,   if   σ sig ( v iD k + 1 )
A minor change has been proposed by Khalil and Gorpinich to binary PSO, SPSO by keeping the search in the selected search space. The search space in SPSO at each D dimension SD = [SD1, SD2, …, SDN] is comprised of a set of DN positions, with DN representing the number of selected positions in dimension D. As in the basic PSO, a fitness function is described; in SPSO, it maps at each D dimension from DN positions of the selective space SD, which leads to alter the position of each particle from being in real-valued space to be a point in the selective space, thereby changing the sigmoid transformation as per (20):
v iD k + 1 = { rand × v iD k + 1 ,     if   | v iD k + 1 | < | v iD k | v iD k + 1 ,     otherwise
The dimension of the reconfiguration problem is indicated by the number of tie switches in the MG states. Some loops are present in the network when all tie switches are closed, with the number of loops equal to the number of switches. The search space in a certain dimension is comprised of all branches in the loop that defines that dimension. The branches out of any loop are not considered in the optimization algorithm. If there is a common branch that belongs to more than one loop, it should be placed just in one loop in the dimension. SPSO can be applied for determining the optimum configuration as soon as the dimensions and search space for each dimension are determined.

3.2. Proposed Method

In this work, the discussed framework is NR in parallel with the OD of DGs aiming at minimize real power losses with some constraints on the MG. From the most basic point of view to the overall problem, the PSO algorithm is chosen due to its improved potential in solving discrete, non-linear, and complex optimization problems. The motivation of integrating PSO and SPSO algorithms is to combine the advantages of both PSO approaches [27,33,34].
In particular, OD is a non-linear optimization problem with many equality and inequality constraints that states the optimal power output of DGs to meet the forecasted electrical loads from an economic perspective. Conventional optimization methods may not be efficient for these types of problems because of local optimum solution convergence, while metaheuristic optimization techniques, especially PSO, have achieved amazing success by solving such type of OD problems in the last decades.
MG reconfiguration constitutes the combinational part of the whole optimization problem. Distribution system planners work with a large number of switches for ensuring that the proper regulation of power and radial configuration is attained for each load. It is possible to maintain radiality by setting the sectionalizing switches (normally closed) and the tie switches (normally open). Various switch combinations can be obtained using an accurate switching operation plan. This combinatorial nature of the constrained optimization problem can be easily dealt with by embedding selective operators into the standard PSO.
The optimization problem becomes more complex when the time sequence variation in load, power market price, and output power of DGs are taken into consideration. The problem with the majority of the metaheuristic methods is the high computation time for larger systems, which may hinder real-time operation. Therefore, PSO is preferred to overcome the complexity of the optimization problem due to its faster convergence rate, accuracy, parallel calculation, and easy application.
It is very important how MG parameters are associated with optimization parameters for the simultaneous MG reconfiguration and ED problem. The OD for the DG units is carried out by the basic PSO using the proposed PSO&SPSO method, while the switch positions are determined by the SPSO method simultaneously at every iteration. The dimension of search space is equal to the number of diesel DGs, while it is equal to the tie switch numbers in the MG. In the next section, the PSO&SPSO procedure is presented for the test MG system and given the case results.

4. Test and Results

4.1. Test System Features

In this study, the standard IEEE 33-bus test system, a balanced and radial distribution network with a voltage level of 12.66 kV and 100 MVA base apparent power, is handled as an RMG. The voltage at the reference bus (PCC), as well as the upper and the lower limits of voltage for other buses are 1.0 p.u, 1.1 p.u., and 0.9 p.u., respectively. There is a total of 32 sectionalizing switches (S1–S32) and five tie-switches (S33–S37) in the system, which are indicated by solid and dotted lines in Figure 1, respectively.
The total real and reactive power demand of the test system is 3715 kW and 2300 kVAr, respectively. The load data and line data can be found in [35]. Three diesel DGs with 4 MW total real power capacity operated at a unity power factor are installed in different buses, as stated in Table 1.
Regarding RMG operational scheduling, it is considered that a wind turbine (WT) is integrated into bus number 6 on the RMG [36]. The estimated power output of the WT as given in Table 2, including the electricity demand and power price values for a 24-h time period for that scheduling framework of RMG are the same as those in [25].
Figure 2 has been presented in the form of a graph in order to see the daily load distribution comparable with power pricing. Furthermore, the main assumptions made in the test cases in [21] have been taken into account for this study.

4.2. PSO&SPSO Procedure for the Optimization Problem

In the proposed PSO&SPSO algorithm, the particles are comprised of two decision variables sets, namely possible switch configurations (SD), and the DG power output values (PDG), as shown in (24):
x = [ S 1 ,   S 2 ,   ,   Sk ,   PDG 1 ,   PDG 2 ,   ,   PDG n ]
Here, k is the tie switches number, and n represents the total DG number. The switch positions in this approach are determined by the SPSO algorithm, while the OD of the diesel DG units is done with the basic PSO algorithm at each iteration. Both algorithms have a common objective function for minimizing the active power loss of the whole system. Table 3 shows the parameters used in PSO&SPSO.
Figure 1 shows the test RMG system with all the specified sectionalizing switches and tie switches. The dimension of the SPSO algorithm is equal to the number of loops that are formed by closing all the tie switches in the RMG. Each dimension corresponds to a search space consisting of all the branches of the loop indicated with that dimension. Regarding our particular optimization problem, there are five loops in this RMG test system once the tie switches (S33, S34, S35, S36, S37) are closed. Therefore, the dimension is equal to five, and the search space in the SPSO algorithm is also represented by this dimension as five. Table 4 shows the loops comprised of the respective branches (switches) on the RMG test system, which also represents each search space. In this case, the connection to the feeder must be maintained continuously, and the switches that are common in the loops should appear only in one loop at a time. The switches of the test system that are not in any loop do not belong to any of the search spaces and thus are not taken into consideration in the optimization algorithm [27]. Once the switches are selected and the connection conditions are met, it should be investigated whether the test system is radial or not. The optimal solution can be assigned once radiality condition is obtained.

4.3. PSO&SPSO Procedure for the Optimization Problem

Here, RMG operational scheduling study is treated as a continuation of two parts. First of all, the effectiveness and validity of the suggested method are tested on the 33-bus IEEE radial test system with three diesel DGs of 4-MW maximum real power capacity for a one-hour period. The proposed method is performed on the RMG test system with integrated WT for a 24-h time period after having an effective hourly solution, as presented in Table 5. The implementation details are given in the following sections.
  • Benchmarking against existing methods
Five different cases have been performed in this section in order to show the applicability and effectiveness of the proposed approach in comparison with similar related studies in the literature with the results given in Table 5. The initial IEEE 33-bus test system is utilized in cases I and II, while the same test system but considered as an MG with the addition of three diesel DGs with 4-MW maximum real power capacity placed, as shown in [7], is used in the remaining cases. The studied cases are expressed as follows:
Case I: In this case, the AC power flow algorithm (Newton’s method) by using Matpower 4.1, which is an open-source simulation tool for Matlab, is utilized on the initial MG test system where the DGs are not integrated into the system yet.
Case II: Unlike case I, the distributed diesel DG units are integrated into the MG test system in case II. The diesel DGs are placed as in [7] at buses 14, 18, and 32, since the same IEEE 33-bus test system has been used; also, the optimal placement of DGs has already been studied in the scope of that reference paper. After all these arrangements on the system, the OD of the three diesel DGs is mainly performed here in this case by using the basic PSO algorithm.
Case III: NR is utilized to the basic MG test system which is the same as in case I by using the SPSO algorithm.
Case IV: Here, NR is applied by using the SPSO technique just after optimally dispatching the DG units on the MG test system, which is the same as in case II by using the basic PSO technique.
Case V: Simultaneous application of NR and OD of the DG units on the MG test system; the same as in case II is performed by using the joint approach of the basic PSO and the SPSO algorithms.
Total power losses, minimum voltage, and total operational costs have been calculated in case I by applying the power flow algorithm on the initial MG test system. The numerical values obtained here are just the results of load flow for the basic test system and are used as a means of comparison with other case studies.
DG units are optimally dispatched in the second case by way of a basic PSO algorithm without performing network reconfiguration. As a result of this study, it is realized that the active power loss is reduced by 76.63% in addition to improving the voltage level (as can be seen, the minimum voltage level throughout the network is 0.9941 p.u.). It should be noted that the results acquired via the basic PSO method in the present study are better in terms of reduction in active power loss value and voltage level improvement in comparison with the results obtained using other methods in the literature.
The NR is applied via the SPSO algorithm to the basic test system without DG units in case III. Considering the active power loss assessment, a decrease of 33.34% is observed compared to the base case while the minimum voltage level throughout the network is improved. However, it has been put forth in another relevant study in the literature [16], [4] that the rate of reduction in active power loss by the EP method is slightly higher, whereas the rate of improvement on the voltage level in this study has not been emphasized.
The OD of the DG units is performed in the fourth case study first by using the basic PSO algorithm and after that, the network is reconfigured by applying the SPSO algorithm on the MG test system. The best active power loss reduction is obtained at a rate of 77.71% in comparison with all previous studies. Furthermore, the minimum voltage level on the system is very close to the nominal value (around 0.99 p.u.). The total capacity of dispatched DG units is around 2.6 MW, and the total operating cost is calculated as 393.97 Euro. It can be seen from the table that better results are obtained for active power loss minimization and voltage level improvement in comparison with those of other studies in the literature.
Finally, the network reconfiguration and the optimal OD of the DG units are applied simultaneously to the MG test system. Whereas the generation capacity of DG units is around 2 MW (50%) in total in this study, the total operating cost is reduced to 306.52 Euros. The rate of active power loss reduction is much better compared to the aforementioned case studies and the studies surveyed in the literature so far by approximately 80%, as can be seen in Table 5. The obtained minimum voltage level is closest to the unit value (1 p.u.) among the relevant studies in the literature, and the voltage profile improvement can be seen in Figure 3. Also, the convergence profile of PSO&SPSO in this case is shown in Figure 4.
  • Day-ahead scheduling in the presence of renewable resources
Five different cases have been studied in this section with the results given in Table 6. An initial IEEE 33-bus test system is used in cases I and II, while the same test system is considered as an RMG with three diesel DGs by 2-MW maximum real power capacity, which was already installed at the same buses as in the previous cases of a benchmarking study, and a WT that was already installed at the bus 6 is used in other cases. In all the optimization case studies here, the proposed single-objective problem is optimized at every time sequence by considering hourly load demand and non-dispatchable DG unit (WT) output power profiles. The cases that are performed for a 24-hr period are briefly as follows:
Case I: For this case, AC power flow analysis is executed for the initial IEEE 33-bus test system without any distributed DG units.
Case II: Reconfiguration of the MG test system which is the same as in case I is performed by using the SPSO algorithm in this case.
Case III: Unlike case 2, NR is performed here by using the SPSO algorithm for a distributed DGs (diesel DGs and WT) integrated MG test system to monitor the effects of the integration of diesel DGs and WT, which has intermittent characteristic into the system during the day.
Case IV: Optimal dispatching study for dispatchable DGs on the MG test system, which is the same as in case III, is realized by using the basic PSO algorithm to monitor the effects of the DGs in the system during the day.
Case V: The NR and OD are studied separately in case 3 and case 4, respectively, and after analyzing their effects on the MG test system, these two studies are performed simultaneously in this case by using the joint approach of basic PSO and SPSO algorithms.
In the first case, the basic power flow algorithm is run for the MG test system without any DG units. The total daily real power loss is about 3.4 MW, while the total demand is 73.6 MW, as tabulated in Table 6. The loss value is very high, and is almost 5% of the total demand. The minimum voltage level on the MG is 0.9108 p.u., which is very close to the lower limit. The cost of the purchasing power from the main grid is calculated for that case, and it is about 4688.26 Euros.
NR is studied for the MG without any DG units in the second case, and the total daily real power loss here is about 2.7 MW. However, the total losses are approximately 55% by adding distributed DG units at the pre-installed buses, as seen in the third case study and calculated from Table 6. Furthermore, as it is expected by adding DGs, the voltage level is improved within the scope of the NR study. Hence, the minimum voltage level rises up to 0.9689 p.u. while it is 0.90 with just the NR study. The cost of the purchasing power from the main grid is 4633.38 Euro, while it is 1072.124 Euro with added DGs into the MG system in Case III. However, there is also the operation cost of dispatchable units consisting of the generation cost, which is about 4608.6 Euros for case III.
Regarding case IV, the OD on the RMG decreases the total loss value to 2.4 MW as calculated from Table 7, and it is less than the NR study without any DGs on the system in case II, but it is much more than the obtained total loss value in case III, which is about 1.5 MW. The latest invention combines both techniques of DG dispatching and NR together for further improving the system performance, and they perform simultaneously, as indicated in case V. It is an indication that both variables (switches and dispatch of DG) are set at the same time, while both techniques run separately during the period of the common functioning. As a result of the compromise solution approach, the total daily power loss value decreases to 1.18 MW from Table 7, taking the lowest value among all the case studies. Here, in this case, the lowest voltage level is measured as 0.9690, and that value is quite good (near to unity). Thus, the proposed solution ensures the most significant benefits for the whole power system by giving more global optimal results, as seen in case V.

5. Conclusions

The purpose of this study was to present an optimal operation scheduling framework for RMGs by way of a combined approach comprised of PSO and SPSO algorithms. In this respect, the NR and OD of the DGs in the RMG were studied simultaneously. Although the methods and application approaches to the distribution NR problem differ in most studies in the literature, the same main objective function (i.e., minimizing the active power loss) as in other studies was used here. The study was primarily performed for one-hour resolution, and the results were compared with the recent related studies in literature. According to the results of the benchmarking, while the maximum active power loss reduction rate was obtained in [37] by approximately 70% compared to the other references in Table 5, our study approximately achieved an active power loss reduction rate of up to 80%. The result of this study put forth the efficiency of the joint approach of PSO and SPSO algorithms for the simultaneous solution of NR and OD of the DGs in the RMG, which motivated us to go further with the operational scheduling framework of RMGs in the presence of renewable energy sources. To this end, five different cases were studied. A total daily power loss reduction of 0.7 MW was observed when the first basic system in case I was reconfigured in case II; however, at least two of the switches’ position changes were required, as was indicated in the simulations. As soon as the distributed DGs including WT were integrated into the basic test system in case III, the total daily active power loss in the previous case was reduced by more than half with a noticeable improvement in the hourly voltage levels ranging between 0.95–1 p.u. When the OD of diesel DGs was applied to the basic system in case IV where the distributed DGs were integrated instead of NR in case III, the total active power loss was 2.4 MW, which is 1.5 times greater than that of the third case. However, the voltage levels at each hour were greater than 0.99 p.u. in this case. Finally, in case V, the target study, the application of simultaneous NR and the OD of diesel DGs’ study for the operational scheduling of the test RMG system was carried out, and the daily active power loss value, which was 2.7 MW in the first case, was reduced to 1.18 MW. Here, the voltage levels were around 0.97 p.u. throughout a 24-hr time period. It is noteworthy that the switching was done approximately every two hours with only one switch position changing. Although the number of switching was not taken into consideration in this paper, this situation could result in additional cost in practice. It could also be observed from the case studies performed for the operational scheduling framework of RMGs that although both techniques (i.e., the OD of the DGs and NR) may help improve the operation of the system, the simultaneous application of these techniques during the analysis could make great improvements; namely the voltage profile improvement and the reduced energy production cost in the entire system. Furthermore, the proposed joint approach of the PSO and SPSO methods demonstrated superior performance in power loss reduction in comparison with the other methods in the literature.

Author Contributions

F.Y. and A.A.-M. designed the model. F.Y. gathered the input data, executed the simulations, and accomplished writing of the paper. A.A.-M. and M.B. supervised the entire work and edited the language.

Funding

This research received no external funding.

Conflicts of Interest

The authors declare no conflict of interest.

Nomenclature

xdecision vector
dvnumber of decision variables
f(x)optimization problem’s objective function
hi(x)equality constraint that should be satisfied
gi(x)inequality constraints that should be satisfied
p number of equality constraint
qnumber of inequality constraints
PLtotal active power losses of the network
Iireal component of the current at branch i
Ribranch resistance
bsets of branches
CostRMGpurchasing power cost from the main grid
CostDGproduction cost of DGs
vbforecasted price of the purchasing power
Pbvalue of purchased power
PDGoutput power of a DG unit
a, b, and ccost function coefficients of a DG
PEPexchanged power between MG and the main grid
PMGLpower consumption of each load of MG
NMGLnumber of MG loads
NDGnumber of DGs
Vivoltage level of each bus
Vminminimum voltage level of each bus
Vmaxmaximum voltage level of each bus
Iiamount of the flowing current in the ith branch
Iimaxthermal rating of the ith branch
βba binary variable that defines a branch status (0—open, 1–closed)
Nbset of branches (b)
nnumber of network buses
Nsubnumber of substations
pieach particle’s position in the swarm
vieach particle’s velocity in the swarm
kcurrent iteration number
kmaxmaximum number of iterations
viDkcomponent of velocity at iteration k in dimension i
randa randomized number between 0–1
pimcurrent position in the ith dimension
c1, c2coefficients of acceleration
pbest-ibest local position in the ith dimension
gbest-ibest overall position in the ith dimension
ωinertia weight
ωmaxinitial weight value
ωminfinal weight value
Ddimension of SPSO
DN number of selected positions in dimension D
SDselective search space at each dimension D
vminminimum velocity of each particle
vmaxmaximum velocity of each particle

References

  1. Shariatzadeh, F.; Member, S.; Vellaithurai, C.B. Real-Time Implementation of Intelligent Reconfiguration Algorithm for Microgrid. IEEE Trans. Sustain. Energy 2014, 5, 598–607. [Google Scholar] [CrossRef]
  2. Shahir, A.; Hasan, K.; Chowdhury, D.; Ziaur, M.; Khan, R. Scalable DC Microgrid Architecture with a One-Way Communication Based Control Interface. In Proceedings of the 2018 10th International Conference on Electrical and Computer Engineering (ICECE), Dhaka, Bangladesh, 20–22 December 2018; pp. 265–268. [Google Scholar]
  3. Dabbaghjamanesh, M.; Kavousi-Fard, A.; Mehraeen, S. Effective Scheduling of Reconfigurable Microgrids With Dynamic Thermal Line Rating. IEEE Trans. Ind. Electron. 2019, 66, 1552–1564. [Google Scholar] [CrossRef]
  4. Chowdhury, D.; Shahir, A.; Hasan, K.; Khan, Z.R. Scalable DC Microgrid Architecture with Phase Shifted Full Bridge Converter Based Power Management Unit. In Proceedings of the 10th International Conference on Electrical and Computer Engineering (ICECE), Dhaka, Bangladesh, 20–22 December 2018; pp. 22–25. [Google Scholar]
  5. Kavousi-Fard, A.; Khodaei, A.; Bahramirad, S. Improved efficiency, enhanced reliability and reduced cost: The transition from static microgrids to reconfigurable microgrids. Electr. J. 2016, 29, 22–27. [Google Scholar] [CrossRef]
  6. Najafi, J.; Peiravi, A.; Anvari-Moghaddam, A.; Guerrero, J.M. Resilience Improvement Planning of Power-Water Distribution Systems with Multiple Microgrids Against Hurricanes Using Clean Strategies. J. Clean Prod. 2019, 223, 109–126. [Google Scholar] [CrossRef]
  7. Rao, R.S.; Ravindra, K.; Satish, K.; Narasimham, S.V.L. Power loss minimization in distribution system using network reconfiguration in the presence of distributed generation. IEEE Trans. Power Syst. 2013, 28, 317–325. [Google Scholar] [CrossRef]
  8. Hemmatpour, M.H.; Mohammadian, M.; Gharaveisi, A.A. Electrical Power and Energy Systems Optimum islanded microgrid reconfiguration based on maximization of system loadability and minimization of power losses. Int. J. Electr. Power Energy Syst. 2016, 78, 343–355. [Google Scholar] [CrossRef]
  9. Na, H.; Farahani, V.; Abyaneh, H.A.; Abedi, M. Optimal daily scheduling of reconfiguration based on minimisation of the cost of energy losses and switching operations in microgrids. IET Gener. Transm. Distrib. 2015, 6, 513–522. [Google Scholar]
  10. Esmaeili, S.; Anvari-Moghaddam, A.; Jadid, S.; Guerrero, J.M. A stochastic model predictive control approach for joint operational scheduling and hourly reconfiguration of distribution systems. Energies 2018, 11, 2628. [Google Scholar] [CrossRef]
  11. Asrari, A.; Lotfifard, S.; Ansari, M. Reconfiguration of Smart Distribution Systems with Time Varying Loads Using Parallel Computing. IEEE Trans. Smart Grid. 2016, 7, 2713–2723. [Google Scholar] [CrossRef]
  12. Esmaeili, S.; Jadid, S.; Anvari-Moghaddam, A.; Guerrero, J.M. Optimal Operational Scheduling of Smart Microgrids Considering Hourly Reconfiguration. In Proceedings of the 4th IEEE Southern Power Electronics Conference (SPEC 2018), Singapore, 10–13 December 2018; pp. 1–6. [Google Scholar]
  13. Hemmati, M.; Mohammadi-ivatloo, B.; Ghasemzadeh, S.; Reihani, E. Electrical Power and Energy Systems Risk-based optimal scheduling of reconfigurable smart renewable energy based microgrids. Electr. Power Energy Syst. 2018, 101, 415–428. [Google Scholar] [CrossRef]
  14. Butler, K.L.; Sarma, N.D.R.; Prasad, V.R. A new method of network reconfiguration for service restoration in shipboard power systems. In Proceedings of the IEEE Transmission and Distribution Conference, New Orleans, LA, USA, 11–16 April 1999; pp. 658–662. [Google Scholar]
  15. Kavousi-Fard, A.; Niknam, T. Optimal distribution feeder reconfiguration for reliability improvement considering uncertainty. IEEE Trans. Power Deliv. 2014, 29, 1344–1353. [Google Scholar] [CrossRef]
  16. Dahalan, W.M.; Mokhlis, H.; Ahmad, R.; Abu Bakar, A.H.; Musirin, I. Simultaneous Network Reconfiguration and DG Sizing Using Evolutionary Programming and Genetic Algorithm to Minimize Power Losses. Arab. J. Sci. Eng. 2014, 39, 6327–6338. [Google Scholar] [CrossRef]
  17. Mohamed Imran, A.; Kowsalya, M.; Kothari, D.P. A novel integration technique for optimal network reconfiguration and distributed generation placement in power distribution networks. Int. J. Electr. Power Energy Syst. 2014, 63, 461–472. [Google Scholar] [CrossRef]
  18. Badran, O.; Mekhilef, S.; Mokhlis, H.; Dahalan, W. Optimal reconfiguration of distribution system connected with distributed generations: A review of different methodologies. Renew. Sustain. Energy Rev. 2017, 73, 854–867. [Google Scholar] [CrossRef]
  19. Bayat, A.; Bagheri, A.; Noroozian, R. Optimal siting and sizing of distributed generation accompanied by reconfiguration of distribution networks for maximum loss reduction by using a new UVDA-based heuristic method. Int. J. Electr. Power Energy Syst. 2016, 77, 360–371. [Google Scholar] [CrossRef]
  20. Bizuayehu, A.W.; Sanchez De La Nieta, A.A.; Catalao, J.P.S.; Meneses De Quevedo, P.; Contreras, J. Distribution system reconfiguration in economic dispatch with high wind penetration. In Proceedings of the IEEE Power & Energy Society General Meeting, Denver, CO, USA, 26–30 July 2015; pp. 1–5. [Google Scholar]
  21. Golshannavaz, S.; Afsharnia, S.; Aminifar, F. Smart Distribution Grid: Optimal Day-Ahead Scheduling with Reconfigurable Topology. IEEE Trans. Smart Grid 2014, 5, 2402–2411. [Google Scholar] [CrossRef]
  22. Hosseinnezhad, V.; Rafiee, M.; Ahmadian, M.; Siano, P. Optimal day-ahead operational planning of microgrids. Energy Convers. Manag. 2016, 126, 142–157. [Google Scholar]
  23. Ameli, A.; Ahmadifar, A.; Shariatkhah, M.H.; Vakilian, M.; Haghifam, M.R. A dynamic method for feeder reconfiguration and capacitor switching in smart distribution systems. Int. J. Electr. Power Energy Syst. 2017, 85, 200–211. [Google Scholar] [CrossRef]
  24. López, E.; Opazo, H.; García, L.; Bastard, P. Online reconfiguration considering variability demand: Applications to real networks. IEEE Trans. Power Syst. 2004, 19, 549–553. [Google Scholar] [CrossRef]
  25. Hosseinnezhad, V.; Rafiee, M.; Ahmadian, M.; Siano, P. A comprehensive framework for optimal day-ahead operational planning of self-healing smart distribution systems. Int. J. Electr. Power Energy Syst. 2018, 99, 28–44. [Google Scholar] [CrossRef]
  26. Lumpur, K. The Simultaneous Application of Optimum Network Reconfiguration and Distributed Generation Sizing Using PSO for Power Loss Reduction. Przegląd Elektrotechniczny 2013, 89, 137–141. [Google Scholar]
  27. Tandon, A.; Saxena, D. A comparative analysis of SPSO and BPSO for power loss minimization in distribution system using network reconfiguration. In Proceedings of the Innovative Applications of Computational Intelligence on Power, Energy and Controls with their impact on Humanity (CIPECH), Ghaziabad, India, 28–29 November 2014; pp. 226–232. [Google Scholar]
  28. Esmaeili, S.; Anvari-Moghaddam, A.; Jadid, S.; Guerrero, J.M. Optimal simultaneous day-ahead scheduling and hourly reconfiguration of distribution systems considering responsive loads. Int. J. Electr. Power Energy Syst. 2019, 104, 537–548. [Google Scholar] [CrossRef]
  29. Selim, T.M.K.; Gorpinich, A.V.; Wasiak, I. A selective particle swarm optimization for large scale practical distribution system reconfiguration. In Proceedings of the 23rd International Conference on Electricity Distribution Paper, Lyon, France, 15–18 June 2015; pp. 1–4. [Google Scholar]
  30. Zhu, J. Optimization of Power System Operation, 2nd ed.; Wiley-IEEE Press: Piscataway, NJ, USA, 2015; pp. 483–528. [Google Scholar]
  31. Ben Hamida, I.; Salah, S.B.; Msahli, F.; Mimouni, M.F. Optimal network reconfiguration and renewable DG integration considering time sequence variation in load and DGs. Renew. Energy 2018, 121, 66–80. [Google Scholar] [CrossRef]
  32. Kumar, D.; Singh, A.; Mishra, S.K.; Jha, R.C.; Samantaray, S.R. A coordinated planning framework of electric power distribution system: Intelligent reconfiguration. Int. Trans. Electr. Energy Syst. 2018, 28, e2543. [Google Scholar] [CrossRef]
  33. Mahor, A.; Prasad, V.; Rangnekar, S. Economic dispatch using particle swarm optimization: A review. Renew. Sustain. Energy Rev. 2009, 13, 2134–2141. [Google Scholar] [CrossRef]
  34. Mohammadian, M.; Lorestani, A.; Ardehali, M.M. Optimization of single and multi-areas economic dispatch problems based on evolutionary particle swarm optimization algorithm. Energy 2018, 161, 710–724. [Google Scholar] [CrossRef]
  35. Baran, M.E.; Wu, F.F. Network reconfiguration in distribution systems for loss reduction and load balancing. IEEE Trans. Power Deliv. 1989, 4, 1401–1407. [Google Scholar] [CrossRef]
  36. Nayak, M.R. Optimal Feeder Reconfiguration of Distribution System with Distributed Generation Units using HC-ACO. Int. J. Electr. Eng. Inform. 2015, 6, 107–128. [Google Scholar] [CrossRef]
  37. Nguyen, T.T.; Truong, A.V.; Phung, T.A. A novel method based on adaptive cuckoo search for optimal network reconfiguration and distributed generation allocation in distribution network. Int. J. Electr. Power Energy Syst. 2016, 78, 801–815. [Google Scholar] [CrossRef]
Figure 1. The standard IEEE 33-bus test system considered as a reconfigurable microgrid (RMG).
Figure 1. The standard IEEE 33-bus test system considered as a reconfigurable microgrid (RMG).
Energies 12 01858 g001
Figure 2. Daily load and price profiles of the 33-bus test RMG system and power price curve, comparatively.
Figure 2. Daily load and price profiles of the 33-bus test RMG system and power price curve, comparatively.
Energies 12 01858 g002
Figure 3. Voltage profile improvement in case V.
Figure 3. Voltage profile improvement in case V.
Energies 12 01858 g003
Figure 4. The convergence characteristics of the proposed method in case V.
Figure 4. The convergence characteristics of the proposed method in case V.
Energies 12 01858 g004
Table 1. The characteristics of dispatchable units.
Table 1. The characteristics of dispatchable units.
Dispatchable UnitsBusa (£)b (£/kW)c (£/kW2)
DG-11425870.0045
DG-21828920.0045
DG-33226810.0035
Table 2. Generation of non-dispatchable units (MW)/installed (MW). WT: wind turbine.
Table 2. Generation of non-dispatchable units (MW)/installed (MW). WT: wind turbine.
Time123456
WT0.350.270.230.290.380.29
Time789101112
WT0.570.460.470.460.520.34
Time131415161718
WT0.290.380.400.350.460.12
Time192021222324
WT0.460.570.630.680.610.69
Table 3. The parameters used in the combined particle swarm optimization and selective PSO (PSO&SPSO) algorithm.
Table 3. The parameters used in the combined particle swarm optimization and selective PSO (PSO&SPSO) algorithm.
The Common Parameters of the Combined PSO&SPSO AlgorithmValue
Swarm population (n)50
Maximum iteration number200
wmax0.9
wmin0.4
Accelaration coefficients (c1, c2)2
Table 4. The loops of the RMG test system in the SPSO algorithm.
Table 4. The loops of the RMG test system in the SPSO algorithm.
Loop (Dimension)Search Space for Each Dimension (Loop)Switches on Each Loop
ISD1S8, S9, S10, S11, S21, S33, S35
IISD2S2, S3, S4, S5, S6, S7, S18, S19, S20
IIISD3S12, S13, S14, S34
IVSD4S15, S16, S17, S29, S30, S31, S32, S36
VSD5S22, S23, S24, S25, S26, S27, S28
Table 5. A comparative study of a microgrid (MG) operation management problem.
Table 5. A comparative study of a microgrid (MG) operation management problem.
CasesItemPSO&SPSOACSA [37]HSA [17]FWA [7]EP [16]
Case ISwitches opened33, 34, 35, 36, 3733, 34, 35, 36, 3733, 34, 35, 36, 3733, 34, 35, 36, 3733, 34, 35, 36, 37
PL (kW)208.46202.68202.67202.67202.3
Vmin (p.u.)0.91080.91080.91310.9131-
Total cost (Euro)339,3281----
Case IISwitches opened33, 34, 35, 36, 3733, 34, 35, 36, 3733, 34, 35, 36, 3733, 34, 35, 36, 3733, 34, 35, 36, 37
Dispatch of DGs in MW (Bus number)1.1182 (14)0.7798 (14)0.5897 (14)0.1070 (18)0.731 (6)
0.840 (18)
0.7256 (18)1.1251 (24)0.1895 (18)0.5724 (17)1.827 (22)
0.8891 (32)1.3496 (30)1.0146 (32)1.0462 (33)2.335 (29)
PL (kW)48.717974.2688.6896.76106
Vmin (p.u.)0.99410.97780.96800.9670-
% Loss reduction76.629563.2656.2452.2647.6
Total cost (Euro)393.97---
Case IIISwitches opened7, 9, 14, 32, 377, 14, 9, 32, 287, 14, 9, 32, 287, 14, 9, 32, 3716, 5, 10, 25, 13
PL (kW)138.9275139.98139.98138.06121
Vmin (p.u.)0.94230.94130.94130.9342-
% Loss reduction33.33530.9330.9331.8840.2
Total cost (Euro)339,3281----
Case IVSwitches opened8, 17, 20, 24, 3433, 9, 8, 36, 277, 34, 9, 32, 28-36, 34, 9, 7, 37
Dispatch of DGs in MW (Bus number)1.1182 (14)0.7798 (14)0.5897 (14)-0.729 (6)
0.800 (18)
0.7256 (18)1.1251 (24)0.1895 (18)1.827 (22)
0.8891 (32)1.3496 (30)1.0146 (32) 2.250 (29)
PL (kW)46.462162.9868.28-99.5
Vmin (p.u.)0.99070.98260.9712--
% Loss reduction77.711768.9366.31-50.8
Total cost (Euro)393.97----
Case VSwitches opened5, 10, 12, 36, 377, 10, 13, 32, 277, 14, 11, 32, 287, 14, 10, 32, 2828, 16, 12, 10, 7
Dispatch of DGs in MW (Bus number)0.6888(14)0.4263 (32)0.5367 (32)0.5258 (32)0.720 (6)
0.2860 (18)1.2024 (29)0.6158 (29)0.5586 (31)0.741 (18)
1.0579 (32)0.7127 (18)0.5315 (18)0.5840 (33)1.733 (22)
2.235 (29)
PL (kW)41.786363.6967.1173.0594.1
Vmin (p.u.)0.98070.97860.97130.9700-
% Loss reduction79.954668.5866.8963.9553.5
Total cost (Euro)306.5282----
ACSA: Adaptive cuckoo search algorithm, FWA: Fireworks algorithm, HAS: Harmony search algorithm, EP: Evolutionary programming.
Table 6. 24-h period resolution in the presence of WT (cases I, II, and III). DG: distributed generator, NR: network reconfiguration, WT: wind turbine.
Table 6. 24-h period resolution in the presence of WT (cases I, II, and III). DG: distributed generator, NR: network reconfiguration, WT: wind turbine.
Case I (Only Power Flow)Case II (Only NR without DGs)Case III (Only NR with all DGs)
HrDemand (MW)PL (kW)Vmin (p.u.)PL (kW)Vmin (p.u.)Switches OpenedPL (kW)Vmin (p.u.)Switches Opened
13.72208.450.9108159.110.935611, 6, 34, 36, 26103.630.971511, 6, 13, 29, 26
23.53186.720.9156159.680.93088, 6, 34, 32, 2488.880.968911, 6, 13, 29, 25
33.34166.340.9204123.520.93548, 7, 34, 32, 2675.560.968911, 6, 13, 29, 25
43.16147.290.9251107.520.938310, 7, 34, 32, 2661.270.971511, 6, 13, 29, 26
52.97129.530.9298100.150.93569, 6, 34, 36, 2650.440.971511, 6, 13, 29, 26
62.79113.030.934584.910.93478, 7, 34, 36, 2642.610.968911, 6, 13, 29, 25
72.6097.770.939172.150.934811, 7, 34, 36, 2633.590.971511, 6, 13, 29, 26
82.4283.720.943662.740.93548, 7, 34, 32, 2628.560.968911, 6, 13, 29, 25
93.72208.460.9108184.060.900111, 6, 14, 30, 26103.510.971511, 6, 13, 29, 26
103.53186.720.9156159.710.90008, 7, 34, 30, 2689.700.968911, 6, 13, 29, 25
113.34166.340.9204127.460.935611, 6, 34, 36, 2675.310.968911, 6, 13, 29, 25
123.16147.290.9251109.590.93548, 7, 34, 32, 2661.220.971511, 6, 13, 29, 26
132.97129.530.929891.870.939811, 7, 34, 32, 2750.510.971511, 6, 13, 29, 26
142.79113.030.934594.940.90019, 7, 34, 30, 2642.550.968911, 6, 13, 29, 25
152.6097.770.939173.150.93548, 7, 34, 32, 2634.800.968911, 6, 13, 29, 25
162.4283.720.943664.740.936035, 7, 14, 32, 2628.620.968911, 6, 13, 29, 25
173.72208.460.9108160.570.93078, 6, 14, 32, 26103.520.971511, 6, 13, 29, 26
183.53186.720.9156142.900.935611, 6, 14, 32, 3499.220.971611, 6, 13, 29, 26
193.34166.340.9204119.370.938311, 7, 14, 32, 2675.360.968911, 6, 13, 29, 25
203.16147.290.9251117.440.902711, 7, 14, 30, 2672.260.969011, 6, 13, 29, 25
212.97129.530.9298119.680.900221, 6, 14, 31, 2650.240.971511, 6, 13, 29, 26
222.79113.030.934596.520.90008, 7, 34, 30, 2648.620.971611, 6, 13, 29, 26
232.6097.770.939175.860.93569, 6, 34, 36, 2634.660.968911, 6, 13, 29, 25
242.4283.720.943697.180.90008, 19, 34, 32, 2728.430.968911, 6, 13, 29, 25
Table 7. 24-h period resolution in the presence of WT (cases IV–V). OD: optimal dispatch.
Table 7. 24-h period resolution in the presence of WT (cases IV–V). OD: optimal dispatch.
Case IV (Only OD)Case V (OD&NR)
HrPL (kW)Vmin (p.u.)DGs (MW)PL (kW)Vmin (p.u.)Switches OpenedDispatch of DGs (MW)
1176.400.99210.5481, 0.3038, 0.308574.270.969011, 6, 13, 29, 250.5961, 0.3904, 0.2668
2130.160.99330.5412, 0.3544, 0.477749.790.970711, 6, 13, 29, 250.4465, 0.6016, 0.4574
3108.000.99420.4637, 0.5293, 0.451854.350.974511, 6, 13, 29, 260.2735, 0.3889, 0.5387
469.350.99540.6200, 0.5332, 0.606039.620.976311, 6, 14, 29, 260.5900, 0.5473, 0.6723
5115.090.99530.3743, 0.2936, 0.446434.390.975611, 6, 13, 29, 250.6482, 0.2686, 0.5437
682.370.99650.1938, 0.5403, 0.602039.980.977211, 6, 14, 29, 250.2277, 0.2823, 0.7086
774.660.99710.6697, 0.3865, 0.258663.070.980721, 6, 13, 29, 260.6167, 0.5578, 0.6800
882.370.99760.5632, 0.1246, 0.399837.950.980511, 6, 14, 29, 250.3419, 0.5362, 0.6618
9162.840.99240.2578, 0.6461, 0.330654.590.971011, 7, 14, 29, 260.3564, 0.4735, 0.7133
1096.650.99380.5084, 0.4928, 0.675962.400.970911, 6, 13, 29, 250.5154, 0.6872, 0.7013
1183.360.99450.6877, 0.5158, 0.508448.220.974611, 6, 13, 29, 260.3642, 0.5808, 0.3469
1292.610.99500.4800, 0.3603, 0.620164.310.976111, 6, 14, 29, 250.4165, 0.4903, 0.2240
1387.200.99570.5085, 0.3844, 0.505256.620.975411, 6, 13, 29, 250.2709, 0.4333, 0.2424
1464.950.99670.6713, 0.6236, 0.285541.460.979111, 6, 13, 29, 260.4236, 0.4801, 0.6655
1559.440.99750.2580, 0.6710, 0.599347.350.978711, 6, 14, 29, 250.5016, 0.3848, 0.1748
1661.520.99810.2026, 0.5231, 0.628550.660.979811, 7, 13, 29, 250.2016, 0.6149, 0.6551
17227.990.99170.2074, 0.3665, 0.239252.950.971911, 6, 14, 29, 260.5036, 0.6319, 0.5507
18119.530.99350.1654, 0.5740, 0.737161.270.973011, 6, 13, 29, 260.4395, 0.2968, 0.4903
19113.750.99410.6269, 0.5150, 0.265044.030.974611, 6, 13, 29, 260.5480, 0.5590, 0.2619
20115.550.99480.1503, 0.6150, 0.474150.450.974111, 6, 13, 29, 250.5857, 0.5750, 0.6041
21120.560.99530.3733, 0.1463, 0.536940.870.975711, 6, 14, 29, 250.6906, 0.2830, 0.5535
2267.370.99670.5427, 0.3050, 0.645452.430.977311, 6, 13, 29, 250.4713, 0.6354, 0.5992
2340.860.99780.6889, 0.5510, 0.613136.790.978711, 6, 13, 29, 250.1608, 0.3895, 0.4283
2448.220.99830.4637, 0.4626, 0.610824.110.982011, 6, 13, 29, 260.6919, 0.3019, 0.3080

Share and Cite

MDPI and ACS Style

Yaprakdal, F.; Baysal, M.; Anvari-Moghaddam, A. Optimal Operational Scheduling of Reconfigurable Microgrids in Presence of Renewable Energy Sources. Energies 2019, 12, 1858. https://doi.org/10.3390/en12101858

AMA Style

Yaprakdal F, Baysal M, Anvari-Moghaddam A. Optimal Operational Scheduling of Reconfigurable Microgrids in Presence of Renewable Energy Sources. Energies. 2019; 12(10):1858. https://doi.org/10.3390/en12101858

Chicago/Turabian Style

Yaprakdal, Fatma, Mustafa Baysal, and Amjad Anvari-Moghaddam. 2019. "Optimal Operational Scheduling of Reconfigurable Microgrids in Presence of Renewable Energy Sources" Energies 12, no. 10: 1858. https://doi.org/10.3390/en12101858

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop