5.1. DPV Limit Penetration Level Evaluation for LV Distribution Network
Firstly, the confidence level
βk of each LV court can be calculated according to Equation (7). To simplify calculation, the maximum value of all min(
βk) is used as the confidence level of all LV courts. The annual load data of each LV distribution network are evaluated at a confidence level of β = 95% based on kernel density estimation. Taking LV court 63 as an example for visualization, the rated transmission capacity of the transformer is 100 kVA. The probability density of the annual load data is shown in
Figure 3, where the width of each straight is 0.2 kVA.
As shown in
Figure 3, in LV court 63, min(
S63) = 6.09 kVA, S
95%,63 = 20.51 kVA. S
95%,63 is more than three times better than 3.6 times min(
S63), increasing by 14.42 kVA. Correspondingly,
Pvlow,95%(63) = 120.51 kW, increased by 13.59% over
Pvlow(63).
In the same way, the
S95%,k and min(
Sk) of other LV courts can be evaluated based on kernel density estimation and the minimum rule, respectively. The DPV limit penetration level
Pvlow(
k) and
Pvlow,95%(
k) of each LV court can be calculated respectively according to Equation (1) and Equation (5). Compared with the rated capacity of the distribution transformer of each LV court, the result is shown in
Figure 4.
As shown in
Figure 4, the DPV limit penetration level in every LV court based on kernel density estimation is significantly higher than that based on the minimum rule. In particular, both the DPV limit penetration level of court 71 and its increase were the largest, respectively, valuing 231.38 kVA and 18.69 kVA. The DPV limit penetration level of court 84 was the minimum, with the smallest increase of 3.65 kVA. In general, the total DPV limit penetration level of all the 12 LV courts based on kernel density estimation is 1033.49 kVA, which increased by 10.37% over that based on the minimum rule. It can be concluded that the DPV limit penetration level determined based on kernel density estimation evaluating load data can better reflect the DPV connection ability of an LV distribution network compared to the conventional minimum rule. If studying on a distribution network with higher load levels, the difference between
S95%,k and min(
Sk) can be more considerable.
Considering extreme conditions, each LV distribution network is connected to DPVs at the limit penetration level (with a total connection of 1033.49 kVA). On this basis, the limit penetration level of the MV distribution network continuously connected to DPVs is evaluated via a single-node and multi-node connect to DPVs respectively, as shown in
Section 5.2 and
Section 5.3, respectively.
5.2. Evaluation of DPV Limit Penetration Level for MV Distribution Networks with Single Node Connection
Take the 85th 10 kV node at the end of the line as an example. Considering calculation speed and accuracy, take the binary number as 15, the initial condition as
Pdown(85) = 0 and
Pup(85) = 10 MW. The daily DPV limit penetration level for the entire year is evaluated, as shown in
Figure 5.
Figure 5 shows that the overall DPV limit penetration level is lower in spring and summer than that in autumn and winter. The DPV limit penetration level in autumn and winter is more than 1000 kVA. On some days in the winter, the level can be more than 2000 kVA. The DPV limit penetration levels in spring and summer are mostly less than 1000 kVA, or even lower. It may be concluded from these results that the DPV limit penetration level is directly related to the actual output of DPVs (i.e., the irradiation intensity).
Specifically, the maximum DPV limit penetration level of the 85th node occurs on 9 December 2018, up to 4019.47 kVA. From June to July, there were three days that the limit was less than 200 kVA, which was significantly lower than other days. The minimum value appeared on June 2, and the ultimate DPV limit penetration level of node 85 is Pvmid(85) = 169.98 kVA. Results indicate that the final Pdown(85) = 169.97 kVA and Pup(85) = 169.99 kVA, with an accuracy of 0.01 kVA.
Relatively, the comparison of the DPV limit penetration level based on different methods of generation-load uncertainty analysis is shown in
Table 1. Here, the large sample data based method of this paper, the method of load prediction [
13], the method of DPV output prediction [
15] and the method of typical moment (with the maximum DPV permeability) [
17] are adopted.
As shown in
Table 1, the results calculated by the method based on the predicted photovoltaic output slightly deviate from the real value because of prediction errors. The results based on load forecasting have a larger deviation than those based on DPV output prediction; this is because actual load distribution (similar to
Figure 3) is not the adopted standard normal distribution. Additionally, the results obtained by the typical time method have the most serious deviation due to its large contingency. In this paper, the large sample data-based evaluation method ensured that the results are more reliable compared to the other three mentioned methods. At the same time, the moment of maximum DPV connecting restrictions can be obtained, and then, only the uncertainties of the location and number of connecting nodes need to be considered when evaluating the limit penetration level of DPV multi-node connection.
Further, by comparing and calculating the daily DPV limit penetration level in the entire year, the DPV limit penetration level of each node can be evaluated when a node connects to DPVs alone, as shown in
Figure 6. There, the red points are the load nodes and the blue points are the connecting nodes with no users.
As shown in
Figure 6, nodes of the MV distribution network can continue to connect to DPVs for a certain capacity after a large capacity of DPVs are connected to the LV courts. The limit penetration level of a single node connecting to DPVs ranges from 169.98 to 275.57 kVA. Among all nodes,
Pvmid(63) = 275.57 kVA, which is the maximum value of DPV for each node. Additionally, the DPV limit penetration level of the 63rd node is 105.59 kVA higher than that of the 85th node. It can be seen that the closer the node is to the end, the lower the limit penetration level.
Finally, the results show that the total time required for calculating the DPV limit penetration level for 23 nodes based on the dichotomy method is 5117.25 s, and the calculation time for a single node is approximately 222.49 s.
5.3. Evaluation of DPV Limit Penetration Level for MV Distribution Network with Multi-Node Connection
Sampling functions such as ① beta distribution β(2,5), ② gamma distribution γ(2,3), ③ pseudo-normal distribution [
17], and ④ uniform distribution [
18,
19] were selected as the optional functions according to sample M (the number of connection points) and nodes connected to DPVs.
First, the sampling method of two-phase sampling should be determined. Combined with this example, the total number of schemes corresponding to different values from 2 to 12 for M is 4083. Take 5000 as the number of sampling to compare different sampling methods, as shown in
Table 2. (to avoid randomness, each value of the ‘number of schemes sampled’ in the table is the minimum of 1000 repetitions).
As shown in
Table 1, it can be found that reasonable selection of the sampling method can effectively reduce the sampling repetition rate of the DPV connection location schemes while improving the efficiency of stochastic simulation. In 5000 times repetition of two-phase sampling, it is obvious that the two-phase sampling methods that contain ‘③’ are far less efficient than those that do not. Specially, the method ‘① + ④’ sampled the largest number of schemes, a total of 2756 schemes, which covered 26.65% more schemes than method ‘④ + ④’ [
18,
19] and nearly three times more than method ‘④ + ③’ [
17]. Up to 67.50% of all the schemes were covered based on method ‘① + ④’. Method ‘③ + ③’ only covered 10.51% of all the schemes, which was the lowest. All the mentioned methods take less than a minute to calculate so that the selection of sampling method mainly considers the sampling efficiency.
In general, two-phase sampling can sample more schemes than single-sampling. When uniform distribution is taken as the second sampling, the maximum number of schemes can be sampled. It means that the sampling probability of each node during the second sampling should be as equal as possible. When β(2,5) is taken as the first sampling, more schemes can be sampled than γ(2,3) and pseudo-normal sampling. It can be found that the closer the probability density distribution of the first sampling function is to the distribution characteristic of "big in the middle and small at both ends" of combinatorial function, the higher the scheme coverage.
After comparative analysis, method ‘① + ④’ is selected: β(2,5) was identified as the first sampling function, and uniform sampling as the second sampling function. Considering the repetition rate of sampling results, the number of stochastic simulations is 20,000. The two-phase sampling results are shown in
Table 3.
As shown in
Table 2, 4028 different DPV connection location schemes were extracted from 20,000 times two-phase sampling, which covered 98.65% of all the schemes. Compared to traditional stochastic simulation, this article optimizes the sampling method to cover more DPV connection schemes, which effectively improves the evaluation accuracy and reliability of the DPV limit penetration level.
When capacity simulation is carried out for the location scheme of DPV connection points determined by 20,000 two-phase sampling according to Equation (15), the value selection of the accumulation coefficient g affects the calculation accuracy of the power flow. When g ≥ 8, the matrix is close to the singular value, and when g ≤ 7, the convergence of the power flow calculation can be guaranteed.
The day of the year with the maximum DPV connection limit was June 2 according to the calculation results presented in
Section 5.2. To improve the calculation accuracy, let g = 0.2. Capacity simulations of 20,000 sample results were conducted based on the generation-load data on June 2. The minimum value in the day is taken as the limit penetration level of the distribution network when multiple nodes are connected to DPVs. The simulation results at the corresponding time are shown in
Figure 7. The running time is 1500.34 s, and the total time to calculate the DPV limit penetration level of this LV-MV distribution network is about 6617.59 s.
As shown in
Figure 7, the maximum value of system node voltage (pu) reached 1.046 after DPVs were connected in each LV court at the limit penetration level. Based on this, the limit penetration level of the MV distribution network when multiple nodes are connected to DPVs was calculated.
Pv.total = 165.87 kVA can be determined according to the minimum rule, however, connection capacity can be further improved by optimizing connection schemes because of the need for mass connection of users.
Pv.total = 275.79 kVA can be determined according to the maximum rule, but the voltage may exceed the limit if improper planning for the DPV connection location scheme.
Obviously, continuous connection of DPVs from 165.87 kVA to 275.79 kVA may cause potential safety hazards in the LV-MV network. In this paper, each scatter point in the figure represents a specific DPV connection scheme, and schemes that meet the requirements can be screened out. Therefore, the proposed stochastic simulation can solve the two mentioned problems by giving specific DPV connection schemes, which can not only guarantee the safety of the power grid, but also improve DPV connecting capacity to meet the needs of users.
Therefore, it can be calculated that the DPV limit penetration level under the premise of grid safety is 1309.28 kVA in total based on the comprehensive evaluation of the LV-MV distribution network. Pvlow = 1033.49 kVA is increased by more than 10% on the basis of the minimum rule. Pvmid = 275.79 kVA increased by 26.69% over the LV courts based on the improved stochastic simulation.
For the planning of DPVs with a certain capacity in this distribution network, all DPVs can be distributed to each LV distribution network when connecting capacity is less than 1033.49 kVA (mode = 1) based on the three-step rule of DPV connection. When DPV connecting capacity is larger than 1033.49 kVA but no more than 1309.28 kVA (mode = 0), the 275.79 kVA DPVs beyond the limit penetration level of the LV distribution network can be connected to the MV distribution network. When DPV connecting capacity is larger than 1309.28 kVA (mode = −1), it will not be allowed to connect to this distribution network due to network security issues.
Finally, compare the connection schemes of a certain DPV capacity: when the DPV capacity is larger than 1293.49 kVA but not more than 1309.28 kVA, DPVs exceeding 260 kVA shall be connected to the MV distribution network. It was found that the MV distribution network allows DPVs to connect to five single nodes (the 63rd, 65th, 69th, 70th, or 71th node), as well as many multi-node connection schemes through the 20,000 stochastic simulations. Due to space limitation. This paper only lists six schemes corresponding to 2~7 connection points, as shown in
Table 4.
The results show that the number of nodes that continue to connect to DPVs is less than seven when total connecting capacity exceeds 1293.49 kW. Especially, the 75th, 77th, 79th, and 85th nodes are not allowed to continuously connect to DPVs due to grid security constraints. As shown in
Table 3, there is only one connecting scheme when connecting to DPVs at the limit penetration level, including the 63th and 65th node. In general, the method proposed in this paper can provide a variety of connecting schemes for DPVs of a certain capacity. In terms of practical applications, power grid companies can provide corresponding connection schemes combined with specific reporting installation requirements based on strictly limited DPV penetration levels.