Next Article in Journal
The Role of Low Temperature Waste Heat Recovery in Achieving 2050 Goals: A Policy Positioning Paper
Next Article in Special Issue
An MPC-Sliding Mode Cascaded Control Architecture for PV Grid-Feeding Inverters
Previous Article in Journal
Dynamic Mechanical Compression Impulse of Lithium-Ion Pouch Cells
Previous Article in Special Issue
A Study on Neutral-Point Potential in Three-Level NPC Converters
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

A Nearly Zero-Energy Microgrid Testbed Laboratory: Centralized Control Strategy Based on SCADA System

1
Department of Computer, Modeling, Electronics, and Systems Engineering (DIMES), University of Calabria, 87036 Rende, Italy
2
Department of Astronautical, Electrical and Energy Engineering (DIAEE), Sapienza University of Rome, 00184 Rome, Italy
*
Author to whom correspondence should be addressed.
Energies 2020, 13(8), 2106; https://doi.org/10.3390/en13082106
Submission received: 4 March 2020 / Revised: 5 April 2020 / Accepted: 15 April 2020 / Published: 23 April 2020
(This article belongs to the Special Issue SCADA and Energy Management Applications in Electric Power Systems)

Abstract

:
Currently, despite the use of renewable energy sources (RESs), distribution networks are facing problems, such as complexity and low productivity. Emerging microgrids (MGs) with RESs based on supervisory control and data acquisition (SCADA) are an effective solution to control, manage, and finally deal with these challenges. The development and success of MGs is highly dependent on the use of power electronic interfaces. The use of these interfaces is directly related to the progress of SCADA systems and communication infrastructures. The use of SCADA systems for the control and operation of MGs and active distribution networks promotes productivity and efficiency. This paper presents a real MG case study called the LAMBDA MG testbed laboratory, which has been implemented in the electrical department of the Sapienza University of Rome with a centralized energy management system (CEMS). The real-time results of the SCADA system show that a CEMS can create proper energy balance in a LAMBDA MG testbed and, consequently, minimize the exchange power of the LAMBDA MG and main grid.

1. Introduction

There has been significant renovation of the electricity network in the last years. The increasing limitations in the expansion of the network have been solved via the installation of local power supply units, which allowed for distributed generation (DG) since they were not placed in centralized configurations as in traditional generation systems. In the meantime, climate change has become one of the most discussed themes affecting all aspects of society. Therefore, in order to lessen the dependence on fossil fuel in the energy sectors, DG has been combined with power systems [1,2] based on renewable energy sources. To integrate DG [3], in an effective and optimized way, into the electricity network [4], the concept of microgrids (MG) was born [5,6]. Via this method, DG works in synergy with energy storage devices [7] for moderate and low voltage electrical loads. In the near future, the role of MGs will be extremely relevant, and it will be possible to assist distribution networks consisting of internally interconnected MGs and MGs connected with each other [8]. The former means that a single MG will supply an aggregation of the user, e.g., all the users in the same building, while the latter means that several MGs will exchange energy with each other to increase the exploitation of the energy produced, which introduces new types of users, jointly-acting renewable self-consumers, and energy communities.
From the main grid point of view, an MG is a controllable set that can act as a load or power supply. In fact, MGs are able to operate in grid connection and island mode [9]. An exciting aspect of grid mode is the services that an MG could provide to the network if considered as a virtual power plant [10]. In this case, it can be seen as a source of ancillary services. Thus, it can help support the normal operation of the grid. However, factors such as interruptions in the main grid, grid loss, power quality, or maintenance issues can cause the MG to be disconnected from grid mode to island mode operation.
In order to satisfy customers’ needs, an MG needs to increase its interaction with the electricity grid while guaranteeing the safety, quality, and continuity of the supply. For this reason, power electronic devices play an essential role as interfaces between distributed generation sources and the MG system, where the voltage source inverters are the most essential equipment.
The presence of DG units in MGs has caused higher complexity in power control and voltage regulation. MG control is generally performed through a control structure that is very similar to the frequency control structure in traditional power grids, with the difference that, in addition to frequency control, other control topics such as voltage control, power-sharing, harmonic compensation, and energy management can be implemented [11]. In these controls, voltage source inverters are controlled in a centralized and decentralized manner [12]. The centralized control is based on communication links similar to the master–slave method in which the DG unit is responsible for the highest voltage power control capability. In the decentralized control method each DG unit is controlled by a local controller, which is based on frequency control. Although this method does not guarantee the voltage and frequency of the system, the simplicity and advantages of not using control based on telecommunication have determined it to be an appropriate solution for controlling MGs. The relationship between centralized and decentralized control is carried out by hierarchical control, which is formed by primary, secondary, and tertiary control levels as shown in Figure 1 [13,14].
In general, the initial points of power can be adjusted with the primary/inner control loops. In the secondary control, the frequency deviation and voltage range are restored. Finally, at the third level, the power distribution control between the main grid and the MG is set at the point of common coupling. Since energy management in an MG requires a large amount of data for long distances, this will increase the length of the communication channel and reduce the reliability of data transmission. For this reason, two centralized and decentralized control strategies are used in supervisory control and data acquisition (SCADA) systems to overcome this problem. The outline for this manuscript is as follows. In the next section, the LAMBDA MG LAB is described. The proposed SCADA system and centralized energy management system (CEMS) in the LAMBDA LAB are discussed in Section 3 and Section 4, respectively. Finally, the conclusion is discussed in Section 5.

2. LAMBDA MG Testbed LAB

Design, control, protection [16,17], security [18], operation status (grid-connected or/and island mode), and energy management [19] are the main areas of the MG field. The LAMBDA MG LAB consists of several sources: a 12 kW three phase PV system (PV1), a single-phase PV system (PV2) with 2 kW rated power, an emergency generator set (EGS) with 5.2 kW installed for island mode, a battery energy storage system (BESS) with 6.5 kWh of rated capacity (2.2 kW charge, 1.8 kW of AC discharge), and an uninterruptible power supply (UPS) to supply the electronic components [20].
The master–slave control structure in LAMBDA MG LAB is shown in Figure 2. Generally, when an MG operates in grid-connected mode, the voltage and frequency are dictated by the main grid, while in island mode a DG or an BESS of the master controller should operate in V/f mode to provide voltage and frequency references for other DGs and ESS in the MG, which work in active and reactive (PQ) control mode [21]. The controller with the V/f control method is named the master controller, while the other controllers are slave controllers. As a future plan in LAMBDA LAB, an emergency generator set EGS will be used as the master controller (V/f mode) in order to regulate the voltage and frequency so that the LAMBDA MG can operate in island mode.
In this paper, a CEMS based on a real-time SCADA system was used in a LAMBDA testbed to achieve a nearly zero-energy MG. All the processes for the implementation and SCADA programming were done by the LAMBDA MG group. The proposed control strategy based on SCADA operated in such a way to catch real-time data of devices equipped with smart meters. Then, energy management was evaluated to consider appropriate strategies for the future. Those strategies are meant to be carried out by the SCADA system by sending comfortable orders, by means of network server, to the smart switches installed next to each component to turn them on or off by used power electronic interfaces.

3. SCADA System in LAMBDA Laboratories

SCADA systems, after the latest developments, are the best choice to manage processes such as oil, gas, and distribution systems. The most critical applications of SCADA systems in MGs include data collection, communication [22], processing, remote control, and demand-side planning tools [23]. The remote terminal unit (RTU), programmable logic controller (PLC), human–machine interface (HMI), and telecommunications infrastructure are the main components of a SCADA system [24]. The combination of these components makes the execution of logical processes independent. The programming language (IEC61131-3) is used to write the commands and programs needed on RTU and PLC. Distribution network operators perform RTUs by connecting smart relays that lead to short time alerts, programmable pulse length digital outputs, and so on. Centralized and decentralized control are the main strategies in SCADA systems. One of the most important functions of centralized control in SCADA systems is demand-side management. A CEMS is used in SCADA systems for easy management, support, and dedicated monitoring. In addition to low-cost telecommunications infrastructure, fast response time is one of the most important benefits of this control strategy. The main screen of the SCADA system in the LAMBDA lab includes three main stages. The first represents the power system scheme, such as the electrical switchboard panel and single line diagram of the system. Lighting control, sensors, controllable plugs, weather stations, and air conditioning have been characterized in the KNX part as the second stage, in order to program and implement the smart home and building projects as zero-energy buildings [25,26,27,28,29,30]. The last part is for the energy meters in the switchboard with Modbus communication protocol.
In Figure 3, the LAMBDA communication scheme is shown. Two protocols are fundamentals in order to make all the devices communicate, i.e., Modbus and KNX. In other words, two gateways relate these two protocols with the LAN network. This allows every node to possess an IP address in order to easily and remotely manage the laboratory. For the same reason, a smart control strategy may be implemented to automate the room accurately. A UPS is used to assure the continuity of supply to the main lab components.
The SCADA network was based on a master station unit, RTU, and data link to send and receive inputs and outputs. The process was as follows: The RTUs withdraw all the necessary data by the sensors; then, this information is sent through the data link to the main workstation in order to be processed; finally, the needed operations are performed. In this way, the LAMBDA LAB system directly adjusts itself on the basis of what the server processed and established as the optimal configuration. The physical means by which the communication function, such as telephone, fiber optics, radio communication, and especially the PLC S7–1200 Siemens model, is present in the lab is a crucial part of the SCADA network. With the proper combination of the two, it was feasible to control the grid and island mode MG behavior to manage the system efficiency.
Figure 4 depicts the lab planimetry along with the physical disposition of the essential components that made the lab work properly. The core of the whole connection was the rack Lan (violet, on the left), which dispatched all the Ethernet cables that got into the relevant components, i.e., giving them a proper and unique IP address. Connected to this are the 3ph inverter of the PV system (located in the upper part of the building), BESS (blue box, on the right), security cameras, EGS (located by the exterior wall; brown, on the bottom center), KNX and Modbus gateways placed in the local switchboard, and the PC workstation where the SCADA software was installed (on the desk by the BESS).
The LAMBDA lab included different types of loads that had to be supplied based on the considered strategy. We categorized the load into the three main groups, namely critical, essential, and normal loads, according to necessity in the system operator’s point of view. The critical loads had to be supplied in any case, while essential and normal loads were supplied in case of existing extra power based on the battery energy management strategy. This strategy follows generated power by the PV array and consumes power by loads. If the PV power is more than the load power in the first step the essential loads will be turned on. In the case of existing extra power the normal loads will be imported to the grid in the second step. Finally, in the third step, extra power was transmitted to the BESS. However, if the load power was more than the PV generation then both the essential and normal loads had to be turned off and, in the case of insufficient power provided by the BESS, the critical load was satisfied by imported power from the main grid. Table 1 provides information regarding the rated power of different load categories and their subsets. According to Figure 4, the LAMBDA LAB is divided into eight different lighting zones. A required power of 40% was considered the essential load and the rest of the lighting system was classified as the normal load, which will be supplied if the system has extra power. The zone classification was based on the importance of the places. In this regard, the lighting of zones 2, 4, and 8, which are the main, had the highest value, 100%. This issue is clearly shown in Figure 5.
Modbus is a communication protocol responsible for communication with energy meters and the auxiliary’s contractors located in the switchboard. KNX is another communication protocol related to the distributed devices present in the lab, such as fingerprint door, A/C, commanded plugs, and presence sensors. Finally, there is the last gateway between KNX and other communication protocol, called digital addressable lighting interface (DALI), which is responsible for the regulation and dimming of the lighting system.
As shown in Figure 6, a SCADA system is usually presented through a client–server architecture. The core of the client side is the HMI, which acts as an interface between one or more operators and the server. The client side is responsible for the visualization and supervision of the process. Furthermore, remote client visualization is possible via the internet through smartphones, tablets, and notebooks located far from the geographical point of view. This is possible thanks to a part of the server called webserver. Therefore, the server is divided into the central control station, or master terminal unit (MTU) which is the core of the server and processes and collects all the information derived from slave units or field devices, the branches, which are the alarm server and manage the alarms and notifications, the historian server, which is a logic module responsible for the archaization and data logging, and the webserver for the remote connections. The server is supported by the virtual file system, which allocates the recorded data into three possible manners: cloud, file disk, or database. Finally, at the bottom level, there are field devices. The field data acquisition unit or slave unit is an interface between the server and the field data element, such as sensors and switches. This unit is composed of PLC or RTU, which are the interface between the sensors and the actuators. The communication between the slave control unit and the field data element is carried out by communication protocols such as Modbus and KNX.

4. SCADA System for CEMS in LAMBDA LAB

The SCADA system in the LAMBDA MG LAB communicated with the CEMS through both the Com’X 510 energy server and the BESS Element’s web application, directly. Com’X 510 is a compact plug and play gateway and data logger, and collects and stores consumption of water, air, gas, electricity, steam, and environmental parameters such as temperature, humidity, and CO2 levels in a building. It provided access to reports such as onboard device and circuit summary pages, as well as on-board data logging. Data could be securely accessed in real-time or transmitted as a report to an Internet database server. As in Figure 7, the Com’X 510 energy server receives data from five energy meters through the Modbus protocol, main grid, PV system, BESS, reverse and load.
As shown in Figure 8, the data are ready to be processed once it is received by the server and displayed as web pages through energy management services to support the optimization of energy performance and cost management. Com’X provides device views of real-time data and trends along with historical data log trends, such as voltage, current, active power, power factor, breaker status, exchange energy, and frequency. It is even possible to export each of the previously described measurements in comma-separated values. Moreover, the energy storage is a three phase BESS with an integrated inverter. It uses lithium-ion cell modules with a current sensor, which acts as an instrument to measure the current draw or feed into the public grid. It was installed directly behind the electricity meter inside the fuse box for measuring the current flow through the house connection line. Furthermore, a sensor unit mounted on the current sensor transmitted the measurement result to the energy storage system, and it was possible to integrate both programmable relays for the load control and a linear power control resistor. The system was fitted with an integrated web server which, through a network connection, allowed settings to be locally managed and the data monitored. Furthermore, VARTA also offers a remote monitoring website. These web services provided a view (charts and graphs) of real-time data and trends along with historical data log trends about battery SoC, energy stored, the energy transferred to the load, and the energy exchanged with the main grid. The SCADA system in the LAMBDA LAB communicated with both Com’X 510 and VARTA Element through the Ethernet connection via the rack LAN. It was possible to have the data collected from the two devices in order to analyze the results more accurately.
Figure 9 shows five minutes based on real data of the LAMBDA LAB, indicating that at the beginning the load consumption was about 750 W, which is related to critical loads, while the PV production was about 4.5 kW when the BESS was in charging mode with a rate around 2200 W. Consequently, the extra power had to supply essential and normal loads, but the system automatically applied a defined delay to ensure sufficient power in the upcoming periods. In this regard, even though we had extra power in the first minute, the system made sure that the power remained stable before adding essential and critical loads. By adding HVAC, the essential load was supplied from the second minute onwards, and, as a result, the amount of load rose to almost 2 kW, and the BESS remained in charging mode with the rate of 2200. Due to the extra power, the normal load had to be added to the system after a one-minute duration to ensure extra power can satisfy the normal loads in upcoming minutes. At the end of the second and third minutes, the normal load was added in two steps and the total power increased to almost 2.7 kW and 4.3 kW, respectively. The most outstanding point in this period was the 4:20 that the PV generation felt because of the environmental problem. The amount of load consumption was more than that of PV production. At this point, the BESS condition altered to discharging mode, while the normal load was eliminated, causing the battery to receive energy. Consequently, the PLC system rapidly eliminated the normal load to stop receiving energy from the main grid, and, after a period, the normal load was added to the system again. The overall trend of power exchanged with the grid was upward, which meant the power transmitted to the main grid decreased because of the added local loads.
Figure 10 provides a screenshot of the SCADA system that reveals the power flow of the system in a moment. The PV production was almost 4.1 kW, and the BESS was charging with 2.064 kW. Consequently, the system automatically added the essential and normal loads to reach almost 2 kW to minimize the amount of energy that the system transmitted to the main grid. Meanwhile, the power transmitted to the main grid was about 11 W, which can be neglected.
Figure 11 represents the behavior of the sources and loads exported from the Com’X 510 energy server in October 2019 in the LAMBDA LAB. According to the recorded data, the SCADA system, by collecting data from smart meters, was able to create an energy management system by load control to minimize the exchange power with the main grid. In this way, the PV system supplied the critical loads and the excess power went to charge the battery, with a top rate of 2200 W, and supply priority loads of the microgrid. Finally, if there was any residual power, it went to the main grid. On the other hand, in the case of lack of sufficient PV power, the BESS started to supply the critical loads and discharged at a top rate of 1800 W. However, if the required power was more than the BESS discharge rate, or if the BESS SoC was low, the system started to take power from the main grid, as shown by the black line in Figure 11. This rarely happened.
As shown in Figure 12, the amount of energy produced by the PV array varied month to month in 2019. In this regard, the peak was just under 2000 kWh in August due to higher irradiation and temperature compared to other months. It fell to almost 300 kWh in December, and the monthly average value of generated energy was about 1300 kWh.
Figure 13 provides information regarding the amount of consumed energy by different loads in 2019. It reached almost 400 kWh in January as a result of the highest heating system usage. However, in August, it decreased to about 120 kWh because of the closure of the LAMBDA LAB. The average loads’ energy consumption had an average value of 280 kWh in 2019.
Figure 14 shows the amount of energy received from the main grid in different months in 2019. As expected, in month 8, due to high irradiation and temperature and as a result of higher PV production, the amount of imported energy from the main grid was minimized. The amount of exchanged power with the main grid strongly depended on the synchronization of the BESS and the PV array. For example, although in January the produced energy by the PV system satisfied the loads, almost 140 kWh had to be imported from the main grid because in the night the PV array production was zero and when the BESS was empty energy had to be imported from the min grid to satisfy the loads.
Figure 15 shows the amount of charging and discharging power of the BESS, and the amount of transmitted and received powers from the main grid, which are in orange and red, respectively. It also provides the amount of stored energy in the BESS in a green line that is relative to its SoC.
The key points after a one-year investigation based on Figure 16 are summarized as follow:
  • In the period from March to October (Spring, Summer, and Fall), the quantity of energy taken from the main grid was nearly zero, with a very high value of self-consumption thanks to the management of the battery storage system.
  • In the winter period, from November to February, because of low irradiation, the quantity of energy from the main grid was more significant, but the monthly balance was positive (more energy produced than consumed).

5. Conclusions

The world MG testbed system can be useful for scientific research, and commercial and industrial applications. In this paper, a real MG system (LAMBDA MG) was installed at the University of Rome Sapienza, Italy, and investigated. Two kinds of controls for the LAMBDA MG testbed were designed and implemented: one for energy optimization of the local sources in normal operations based on HBES/SCADA and a second for emergency conditions in order to operate the MG in island mode operation based on a fast PLC. In this paper, the first approach, i.e., increasing the capacity of the BESS, was considered. The results of one year of investigation highlight that from March to October the quantity of energy taken from the grid was nearly zero, with a very high value of self-consumption thanks to the management of the storage system. In the winter period from November to February, because of low irradiation resulting in less PV production, the quantity of received energy from the main grid was more significant but the monthly balance remained positive (more energy produced than consumed).
The results of nearly zero-energy from the main gridhad a tremendous economic impact, considering the savings of energy bought from the grid. It is possible to conclude that by the operation of the MG with the PV and battery storage systems, LAMBDA MG is a “nearly zero-energy laboratory.” For future work, other approaches will be implemented. First, we plan to gather the installed 1.6 kW sigle-phase PV panel data into the SCADA system, which will satisfy the LAMBDA LAB single-phase loads, such as lightings. Second, emergency generators will be involved through a fast PLC controller to investigate island mode operation in the LAMBDA LAB.

Author Contributions

M.K. proposed the centralized energy management and wrote the paper; project administration D.L.C.; review and editing S.R.; real-time carried out by A.P. and F.M.; supervision, L.M. All authors have read and agreed to the published version of the manuscript.

Funding

This research received no external funding.

Conflicts of Interest

The authors declare no conflicts of interest.

Abbreviations

BESSBattery Energy Storage System
CEMSCentralized Energy Management System
DGDistributed Generation
EGSEmergency Generator Set
HMIHuman Machine Interface
MGMicrogrid
PLCProgrammable logic Controller
RESRenewable energy Resorces
RTURemote Terminal unit
SCADASupervisory Control and Data Acquisition
UPSUninterruptible Power Supply

References

  1. Barker, P.P.; De Mello, R.W. Determining the Impact of Distributed Generation on Power Systems: Part 1—Radial Distribution Systems. In Proceedings of the 2000 Power Engineering Society Summer Meeting (Cat. No.00CH37134), Seattle, WA, USA, 16–20 July 2000; pp. 1645–1656. [Google Scholar]
  2. Dugan, R.C.; Mcdermott, T.E. Operating conflicts for distributed generation interconnected with utility distribution systems. In Proceedings of the 2001 Rural Electric Power Conference. Papers Presented at the 45th Annual Conference (Cat. No.01CH37214), Little Rock, AR, USA, 29 April–1 May 2001. [Google Scholar]
  3. Pepermans, G.; Driesen, J.; Haeseldonckx, D.; Belmans, R.; D’haeseleer, W. Distributed generation: Definition, benefits and issues. Energy Policy 2005, 33, 787–798. [Google Scholar] [CrossRef]
  4. Alsokhiry, F.; Lo, K.L. Distributed generation based on renewable energy providing frequency response ancillary services. In Proceedings of the 4th International Conference on Power Engineering, Energy and Electrical Drives, Istanbul, Turkey, 13–17 May 2013; pp. 1200–1205. [Google Scholar]
  5. Lasseter, R.H. MicroGrids. In Proceedings of the 2002 IEEE Power Engineering Society Winter Meeting. Conference Proceedings (Cat. No.02CH37309), New York, NY, USA, 27–31 January 2002; Volume 1, pp. 305–308. [Google Scholar]
  6. Hatziargyriou, N.; Asano, H.; Iravani, R.; Marnay, C. Microgrids. IEEE Power Energy Mag. 2007, 5, 78–94. [Google Scholar] [CrossRef]
  7. Faisal, M.; Hannan, M.A.; Ker, P.J.; Hussain, A.; Mansor, M.B.; Blaabjerg, F. Review of energy storage system technologies in microgrid applications: Issues and challenges. IEEE Access 2018, 6, 35143–35164. [Google Scholar] [CrossRef]
  8. Ipakchi, A.; Albuyeh, F. Grid of the Future. IEEE Power Energy Mag. 2009, 500, 50–59. [Google Scholar] [CrossRef]
  9. Bidram, A.; Davoudi, A. Hierarchical structure of microgrids control system. IEEE Trans. Smart Grid 2012, 3, 1963–1976. [Google Scholar] [CrossRef]
  10. Asmus, P. Microgrids, Virtual Power Plants and Our Distributed Energy Future. Electr. J. 2010, 23, 72–82. [Google Scholar] [CrossRef]
  11. Katiraei, F.; Iravani, R.; Hatziargyriou, N.; Dimeas, A. Microgrids Management. IEEE Power Energy Mag. 2008, 6, 54–65. [Google Scholar] [CrossRef]
  12. Mehrizi-Sani, A. Distributed Control Techniques in Microgrids. Microgrid Adv. Control Methods Renew. Energy Syst. Integr. 2017, 5, 43–62. [Google Scholar]
  13. Guerrero, J.M.; VASQUEZ, J.C.; Miret, J.; Castilla, M.; Garci, L. Hierarchical Control of Intelligent Microgrids. IEEE Ind. Electron. Mag. 1932, 4, 23–29. [Google Scholar]
  14. Guerrero, J.M.; Vasquez, J.C.; Matas, J.; De Vicuña, L.G.; Castilla, M. Hierarchical control of droop-controlled AC and DC microgrids—A general approach toward standardization. IEEE Trans. Ind. Electron. 2011, 58, 158–172. [Google Scholar] [CrossRef]
  15. Alam, M.N.; Chakrabarti, S.; Ghosh, A. Networked Microgrids: State-of-the-Art and Future Perspectives. IEEE Trans. Ind. Inform. 2019, 15, 1238–1250. [Google Scholar] [CrossRef]
  16. Bayati, N.; Aghaee, F.; Sadeghi, S.H.H. The adaptive and robust power system protection schemes in the presence of DGs. Int. J. Renew. Energy Res. 2019, 9, 732–740. [Google Scholar]
  17. Aghaee, F.; Dehkordi, N.M.; Bayati, N.; Hajizadeh, A. Distributed control methods and impact of communication failure in AC microgrids: A comparative review. Electronics 2019, 8, 1265. [Google Scholar] [CrossRef] [Green Version]
  18. Teymouri, A.; Mehrizi-Sani, A.; Liu, C.C. Cyber security risk assessment of solar PV units with reactive power capability. In Proceedings of the IECON 2018—44th Annual Conference of the IEEE Industrial Electronics Society, Washington, DC, USA, 21–23 October 2018; Volume 1, pp. 2872–2877. [Google Scholar]
  19. Bagheri, M.; Nurmanova, V.; Abedinia, O.; Naderi, M.S.; Ghadimi, N.; Naderi, M.S. Renewable energy sources and battery forecasting effects in smart power system performance. Energies 2019, 12, 373. [Google Scholar] [CrossRef] [Green Version]
  20. Martirano, L.; Kermani, M.; Manzo, F.; Bayatmakoo, A.; Graselli, U. Implementation of SCADA systems for a real microgrid lab testbed. In Proceedings of the 2019 IEEE Milan PowerTech, Milan, Italy, 23–27 June 2019; pp. 1–6. [Google Scholar]
  21. Kermani, M. Transient Voltage and Frequency Stability of an Isolated Microgrid Based on Energy Storage Systems. In Proceedings of the 2016 IEEE 16th International Conference on Environment and Electrical Engineering (EEEIC), Florence, Italy, 7–10 June 2016; pp. 5–9. [Google Scholar]
  22. Bani-Ahmed, A.; Weber, L.; Nasiri, A.; Hosseini, H. Microgrid communications: State of the art and future trends. In Proceedings of the 3rd 2014 International Conference on Renewable Energy Research and Application (ICRERA), Milwaukee, WI, USA, 19–22 October 2014; pp. 780–785. [Google Scholar]
  23. Lazar, E.; Etz, R.; Petreus, D.; Patarau, T.; Ciocan, I. SCADA development for an islanded microgrid. In Proceedings of the 2015 IEEE 21st International Symposium for Design and Technology in Electronic Packaging (SIITME), Brasov, Romania, 22–25 October 2015; pp. 147–150. [Google Scholar]
  24. Rezai, A.; Keshavarzi, P.; Moravej, Z. Key management issue in SCADA networks: A review. Eng. Sci. Technol. Int. J. 2017, 20, 354–363. [Google Scholar] [CrossRef] [Green Version]
  25. Kermani, M.; Ghasemzadeh, E.; Vahidi, T.; Reza, M. Implementing BMS in household and commercial complexes using industrial PLCs as well as its impact on optimizing energy consumption. In Proceedings of the 9th International Energy Conference, At Tehran, Iran, 20–21 February 2013. [Google Scholar]
  26. Magro, M.C.; Giannettoni, M.; Pinceti, P.; Vanti, M. Real time simulator for microgrids. Electr. Power Syst. Res. 2018, 160, 381–396. [Google Scholar] [CrossRef]
  27. Paolillo, A.; Carni, D.L.; Kermani, M.; Martirano, L.; Aiello, A. An innovative Home and Building Automation design tool for Nanogrids Applications. In Proceedings of the 2019 IEEE International Conference on Environment and Electrical Engineering and 2019 IEEE Industrial and Commercial Power Systems Europe (EEEIC/I&CPS Europe), Genova, Italy, 11–14 June 2019. [Google Scholar]
  28. Alfieri, S.; Piccini, S.; Kermani, M. Feasibility study of Nearly Zero Energy Building in a real Microgrid case study. In Proceedings of the 2019 IEEE International Conference on Environment and Electrical Engineering and 2019 IEEE Industrial and Commercial Power Systems Europe (EEEIC/I&CPS Europe), Genova, Italy, 11–14 June 2019. [Google Scholar]
  29. Martirano, L.; Manganelli, M.; Sbordone, D.A.; Di Pietra, B.; Carni, D.L.; Parise, L.; Lamonaca, F. Classification of smart metering systems for zero-energy buildings. In Proceedings of the 2015 IEEE 8th International Conference on Intelligent Data Acquisition and Advanced Computing Systems: Technology and Applications (IDAACS), Warsaw, Poland, 24–26 September 2015; Volume 1, pp. 68–74. [Google Scholar]
  30. Martirano, L.; Habib, E.; Parise, G.; Greco, G.; Manganelli, M.; Massarella, F.; Parise, L. Demand Side Management in Microgrids for Load Control in Nearly Zero Energy Buildings. IEEE Trans. Ind. Appl. 2017, 53, 1769–1779. [Google Scholar] [CrossRef]
Figure 1. Microgrid control strategies [15].
Figure 1. Microgrid control strategies [15].
Energies 13 02106 g001
Figure 2. Master–slave control structure in LAMBDA MG.
Figure 2. Master–slave control structure in LAMBDA MG.
Energies 13 02106 g002
Figure 3. Communication layer for different parts of the LAMBDA MG.
Figure 3. Communication layer for different parts of the LAMBDA MG.
Energies 13 02106 g003
Figure 4. Physical disposition of the essential components in LAMBDA MG.
Figure 4. Physical disposition of the essential components in LAMBDA MG.
Energies 13 02106 g004
Figure 5. Lighting zone classification in LAMBDA lab.
Figure 5. Lighting zone classification in LAMBDA lab.
Energies 13 02106 g005
Figure 6. Client–server architecture of the SCADA system implemented in the LAMBDA MG LAB.
Figure 6. Client–server architecture of the SCADA system implemented in the LAMBDA MG LAB.
Energies 13 02106 g006
Figure 7. CEMS based on Com’X 510 in LAMBDA MG LAB.
Figure 7. CEMS based on Com’X 510 in LAMBDA MG LAB.
Energies 13 02106 g007
Figure 8. Total PV production per month in 2019.
Figure 8. Total PV production per month in 2019.
Energies 13 02106 g008
Figure 9. Real-time energy management in LAMBDA MG.
Figure 9. Real-time energy management in LAMBDA MG.
Energies 13 02106 g009
Figure 10. Electrical switchboard of the LAMBDA MG LAB.
Figure 10. Electrical switchboard of the LAMBDA MG LAB.
Energies 13 02106 g010
Figure 11. LAMBDA historical data by the Com’X 510 energy server in October 2019 (in Watts).
Figure 11. LAMBDA historical data by the Com’X 510 energy server in October 2019 (in Watts).
Energies 13 02106 g011
Figure 12. Total PV production per month in 2019 in kWh.
Figure 12. Total PV production per month in 2019 in kWh.
Energies 13 02106 g012
Figure 13. Total load demand per month in 2019 in kWh.
Figure 13. Total load demand per month in 2019 in kWh.
Energies 13 02106 g013
Figure 14. Total energy from the main grid per month in 2019.
Figure 14. Total energy from the main grid per month in 2019.
Energies 13 02106 g014
Figure 15. A screenshot of the real-time monitoring of the BESS.
Figure 15. A screenshot of the real-time monitoring of the BESS.
Energies 13 02106 g015
Figure 16. The summarized energy behavior in kWh for the LAMBDA MG testbed in 2019.
Figure 16. The summarized energy behavior in kWh for the LAMBDA MG testbed in 2019.
Energies 13 02106 g016
Table 1. Load categories with details.
Table 1. Load categories with details.
Load CategorySub-CategoryPower (W)
CriticalPC Server, rack box, and electronic components700
Essential loadBESS (In case of excess power during the day)2200
Other PCs and student’s laptops400
40% of lighting system2000
Normal loadHVAC800
Boiler1500
Kitchen appliances
60% of lighting system
1000

Share and Cite

MDPI and ACS Style

Kermani, M.; Carnì, D.L.; Rotondo, S.; Paolillo, A.; Manzo, F.; Martirano, L. A Nearly Zero-Energy Microgrid Testbed Laboratory: Centralized Control Strategy Based on SCADA System. Energies 2020, 13, 2106. https://doi.org/10.3390/en13082106

AMA Style

Kermani M, Carnì DL, Rotondo S, Paolillo A, Manzo F, Martirano L. A Nearly Zero-Energy Microgrid Testbed Laboratory: Centralized Control Strategy Based on SCADA System. Energies. 2020; 13(8):2106. https://doi.org/10.3390/en13082106

Chicago/Turabian Style

Kermani, Mostafa, Domenico Luca Carnì, Sara Rotondo, Aurelio Paolillo, Francesco Manzo, and Luigi Martirano. 2020. "A Nearly Zero-Energy Microgrid Testbed Laboratory: Centralized Control Strategy Based on SCADA System" Energies 13, no. 8: 2106. https://doi.org/10.3390/en13082106

APA Style

Kermani, M., Carnì, D. L., Rotondo, S., Paolillo, A., Manzo, F., & Martirano, L. (2020). A Nearly Zero-Energy Microgrid Testbed Laboratory: Centralized Control Strategy Based on SCADA System. Energies, 13(8), 2106. https://doi.org/10.3390/en13082106

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop