Next Article in Journal
Nonlinear Model Predictive Control of an Autonomous Power System Based on Hydrocarbon Reforming and High Temperature Fuel Cell
Next Article in Special Issue
Open Source Modelling and Simulation of the Nordic Hydro Power System
Previous Article in Journal
Reduced-Order Modelling with Domain Decomposition Applied to Multi-Group Neutron Transport
Previous Article in Special Issue
Design Space Optimization of a Three-Phase LCL Filter for Electric Vehicle Ultra-Fast Battery Charging
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Combined Framework with Heuristic Programming and Rule-Based Strategies for Scheduling and Real Time Operation in Electric Vehicle Charging Stations

by
Héricles Eduardo Oliveira Farias
1,*,
Camilo Alberto Sepulveda Rangel
1,*,
Leonardo Weber Stringini
1,
Luciane Neves Canha
1,
Daniel Pegoraro Bertineti
1,
Wagner da Silva Brignol
1 and
Zeno Iensen Nadal
2
1
Department of Electrical Engineering , Federal University of Santa Maria—UFSM, Santa Maria 97105-900, Brazil
2
Electric Energy Paranaense Company—COPEL-DIS, Curitiba 81200-240, Brazil
*
Authors to whom correspondence should be addressed.
Energies 2021, 14(5), 1370; https://doi.org/10.3390/en14051370
Submission received: 31 January 2021 / Revised: 24 February 2021 / Accepted: 24 February 2021 / Published: 3 March 2021

Abstract

:
This paper proposes a flexible framework for scheduling and real time operation of electric vehicle charging stations (EVCS). The methodology applies a multi-objective evolutionary particle swarm optimization algorithm (EPSO) for electric vehicles (EVs) scheduling based on a day-ahead scenario. Then, real time operation is managed based on a rule-based (RB) approach. Two types of consumer were considered: EV owners with a day-ahead request for charging (scheduled consumers, SCh) and non-scheduling users (NSCh). EPSO has two main objectives: cost reduction and reduce overloading for high demand in grid. The EVCS has support by photovoltaic generation (PV), battery energy storage systems (BESS), and the distribution grid. The method allows the selection between three types of charging, distributing it according to EV demand. The model estimates SC remaining state of charge (SoC) for arriving to EVCS and then adjusts the actual difference by the RB. The results showed a profit for EVCS by the proposed technique. The proposed EPSO and RB have a fast solution to the problem that allows practical implementation.

1. Introduction

Through the years, the number of electric vehicles (EV) has significantly increased all over the world. There is a growth projection of 250 million EVs by 2030 [1,2,3]. Alongside the EV growth, the number of electric vehicles charging stations (EVCS) hand increased by 44% from 2018 to 2019 [3]. Most of EVCS are based on private investments [1]. Although the growth of EV, and furthermore EVCS, could present environmental benefits, an uncoordinated penetration may present problems to power grid performance. These problems are related to the following: peak demands higher than the distribution system operator (DSO), voltage distortions, overloading of lines, and another energy quality problem [4,5,6]. Knowing these problems, the EVCS management relates to carefully select the charging time and quantity for EV use. This management could maximize economic benefits and reduce grid impact.
Related to EVCS management, a common approach is focused on demand shifting, applying controls over the EV charging and discharging [7,8,9,10,11]. The work of Reference [12] focuses on maximizing the number of EV charges at the station, respecting the grid limits of the DSO. Furthermore, metaheuristic (MH) techniques are presented as valid solutions, as they offer flexibility and simplicity of implementation. An example of MH is presented in Reference [9], where a genetic algorithm (GA) is used to flatten daily loading curves. The authors of Reference [7] showed that the particle swarm optimization (PSO) technique performed better than the GA method when scheduling consumer charging. In addition, Reference [13,14] applies a PSO algorithm for solution based on planning strategies. In Reference [15], a framework solution for EVCS planning is developed, considering interactions between EV and EVCS. The framework is based on long term evaluation and rules to check charging demands and EV growth towards rejections indices and locations.
In addition to load management methods, the use of distributed energy resources (DERs) could support the EVCS by reducing dependence on grid power. Normally, DERs are composed of renewable energy sources, such as wind or solar photovoltaic (PV) generation and/or battery energy storage systems (BESS). Adding these factors makes the EVCS management more challenging and brings complexity for the operation. In Reference [10], DERs are considered in energy management control (EMC) system, using BESS lifetime as a factor to minimize total operational costs. The work of Reference [16] also considers PV generation but focuses on residential EV use. In Reference [16], the BESS stores PV energy surplus to be injected into the grid or residence. In Reference [17], an EV scheduling approach based on a Markov Decision Process (MDP) is proposed. In Reference [17], the main objective is to minimize the average waiting time of EVs and considers charging stations having renewable energy generators and storage devices at disposal. In Reference [18], a solution for BESS support on EVCS is developed, considering wind farm as renewable resource. A genetic algorithm is applied for optimization but disregards EV scheduling and EV chargers availability and types.
It should be noted that EVCS operation problem depends on different objectives, as there is participation of several agents. As mentioned, there is a necessity to balance both the EVCS interest on increasing the EV chargings without compromising the DSO interest on reducing the stress on the grid caused by possible overloadings. Moreover, it is also important to consider the user comfort in terms of waiting times and charging speed. Regarding this, some scheduling models are based on selection of time periods for charging by the users. In Reference [19], an application was developed allowing the EV owner to pick an EVCS location, based on its necessities. A machine learning approach [8] was applied to select chargers options for the users.
As EVCS investment is gaining interest, some applications further expand to long distance travel, in contrast to the short and common EV trips inside cities [20]. As an example, the EV Charging Station installed at the COPEL-Distribution Electric Power Company in the Curitiba City—Paraná—Brazil will further extend a larger electrovia that communicates several cities [21]. Large distance travel gives more challenges as the EV requires an adequate availability for charging. In addition, times for charging should be short in order to optimize EV travel. The use of scheduled methods is important for EVCS for adequately manage the chargers to attend demand based on previous information.
Considering EV stochastic behavior, predictive analysis could be useful for charging planning [17,22]. Nevertheless, the need for information to construct forecast data could be a limitation for new infrastructure investment. An alternative to gain information is previous scheduling based on request for EV users, interested in charging for future use. For this approach, the previous cited heuristic techniques and frameworks [7,17,19,23,24,25,26], are useful to schedule the charging operation. However, real time operation gets limited if there is a lack of information for new users. In addition, difference in distance from arriving to the station could impact the charging time. Therefore, rule-based (RB) strategies are presented as an alternative solution. RB strategies [7,10,25,27] are based on decision-making choices considered set of conditions and depending on present information. Thus, a combination of schedule planning, with real time operation, could give a more robust operation for EVCS focus on EV user comfort, DSO objectives, and EVCS profit.
This paper proposed an MH technique combined with RB framework for EVCS operation, considering PV and BESS support. The heuristic chosen was an evolutionary particle swarm optimization algorithm (EPSO), in which the present rapid convergence is less sensitive to parameters changes as PSO [28]. The proposed work is denoted as EPSO-RB, to combine the two techniques. As intended for application in long distance travel, EVCS are located on highways. The charger’s characteristics are based on fast charging (30 min to 1:30 min), with 3 type of chargers. A comparison of EPSO-RB features against previous work is presented in Table 1.
As shown by Table 1, only EPSO-RB considered the key features presented. Thus, the main contributions of this work are:
  • A combined MH and RB technique for EVCS management considering scheduled and real time demands.
  • A method for EVCS management applied for long distance travel, considering short time of charging and BESS and PV support.
  • Multi-objective load shifting of EV applying an EPSO approach. Objectives set to economic profit and reduction on grids impact.
  • Real time-based framework for BESS support of EVCS considering degradation cost and PV injection.
  • RB strategy to handle difference on charging schedule and state of charge (SoC) variation for user arrival.
The work is divided as follows. First, a description of the methodology is explained. Second, a study case is made based on stochastic scenarios for representation of user’s demand. Finally, conclusions, about EPSO-RB impact are presented.

2. Proposed Methodology

The proposed EPSO-RB framework is based on two parts:
  • first, a day-ahead planning of EV users chargings is made based on the EPSO algorithm and the scheduling requests; and,
  • second, the RB strategy is used to manage the EVCS operation in real time. RB supports the EPSO planed load and the random load that may arrive during the day.
The model considers three types of charging modes. The first one is the Normal Charging (NC) that fully recharges the EV in 1 h and 30 min. The second type is the Fast Charging (FC) that takes 1 h to complete an EV charge. Finally, the Ultra-Fast Charging (UFC), that fully recharges an EV in 30 min. For each charging type, it is considered that the lower the time to complete the recharge the higher the price for sell. Taking FC chargers as reference, NC will be 10% cheaper, and UFC will be 10% more expensive. The model works in a time step (TS) of 30 min for each day, and the simulations are performed in Python programming language [33]. It should be noted that the proposed approach was tested in only one EVCS, as the intention was for private and long distance applications. Nevertheless, the model could be adapted to consider more EVCS by establishing a communication and set of rules to attend multiple agents objectives.

2.1. Demand Model

The EVCS serves two different consumer types: The scheduled consumer (SCh) and the non-scheduled consumer (NSCh). For simplification purposes, all EV fleets have the same EV model, with a 40-kWh battery.

2.1.1. SCh Model

The SCh requests its own recharge by contacting the EVCS in the day before the recharge. Then, the consumer must provide to the EVCS the desired charging mode and the expected traveled distance before the arrival. The model associates this expected distance with the EV SoC to have a more accurate estimate of the required energy by the EV at the arrival.
Although the user cannot provide a specific time for the connection, they can still choose to request a recharge according with the cluster time that better suits his needs. These clusters are presented in Table 2.
Table 2 shows 7 options for chargers vacancies, starting at time T i and finishing at time T f . As an example, if an EV owner wants to recharge his car at night, he should select, for instance, the cluster C6 (21:00 to 0:00) and then contact the EVCS on the day before. The range of time for the contact must be the same of the cluster, i.e., 21:00 to 0:00.
By the end of the selected cluster, the EVCS informs the EV owner about his scheduled time (or availability) for connection. It should be noted that the user will not be scheduled outside the chosen cluster time range for the studied case.
The clusters division is important to ensure user comfort. If the range for schedule is too long, this could provide long waiting times and uncertainty for the user request. Thus, the clusterization provides:
  • a more suitable option for the users recharges around a specific time of the day of their interest; and
  • the possibility to the EVCS for optimization of DERs dispatch and scheduled load.
Due the lack of practical data on EV demand profile, a random distribution of EV users and profiles are generated. Figure 1 shows the distribution of data for the EV users adapted from Reference [34].
The histograms of Figure 1 are used to generate the amount of EV users to be scheduled in each cluster by the EPSO algorithm. The green part in Figure 1a represents the Commercial Period (CP) where the EVCS can supply both NSCh and SCh consumers. Outside the time window marked in green, only the SCh consumer can be supplied. The vertical lines denote the area of each cluster presented in Table 2.
The SCh import of data by the ECVS is divided in two parts. First, each EV consumer selects his charging mode. Second, each EV consumer estimates the remaining movement capacity (km related to SoC use) upon arrival to EVCS. Figure 2 presents the process of the first step. Note that, in Figure 1b, the idea of having a larger number of EVs at a high SoC during the request time is to represent the consumers that, in the day before the recharge, will use the EV for traveling long distances, arriving at the EVCS with a lower SoC to then fully complete the recharge and to continue their trips.
In Figure 2, for every EV evaluated at the current time step (TS), there is an associated SoC and probability to select a specific charging mode, depending in the SoC value. The set of rules created were defined by the authors to handle several scenarios, and the main idea of this set of probabilities is to bias the user to select a fast charging type if the required energy is low, a slow charging type if he needs a higher amount of energy, and the normal charging if its SoC is medium. The second process is represented in Figure 3.
Figure 3 presents the determination process of the remaining SoC at arrival for the EV. This process depends on whether or not the consumer will use the EV before going to the EVCS. The estimation of this value is used on the EPSO algorithm. Then, the real SoC is handled on the RB strategy. The EV estimation is based on two factors:
  • first, the distance between the EV and the EVCS; and,
  • second, the expected usage of the EV before arrival at the EVCS.
For instance, if the EV owner has, at the time of the request, 40% of SoC, then the required amount of energy is 60% of the capacity. Nevertheless, if the user intends to use the EV before the recharge, he also must estimate the number of kilometers he will travel. The estimated value—based on the average consumption per kilometer of the EV—provides a more accurate estimated value for the SoC at arrival.
These estimates help the EVCS to better supply the EV and to dispatch its own DERs. In addition, the EV user is not penalized when the error between the estimate and the real energy is below 15%. If the error is above 15%, a penalization of 5% in the final EV consumer bill is applied. As the SCh user is responsible to give a realistic estimate on the expected EV usage before the recharge happens, this penalization is set to avoid losing performance at the EPSO scheduling because a very bad estimate could invalid the whole scheduled for a given cluster TS. Moreover, this penalization is only applied to the SCh consumer, as this consumer is the user who also does not need to request a schedule, and he canalso arrive at the EVCS as an NSCh consumer in order to recharge; however, if there is no available chargers, he would also have to wait until one of them is, and he cannot select its connection time in the day before.
Due to the limited number of chargers in the EVCS, for each cluster, there is also a limited number of reserves that can be made for each type of charging mode. For instance, the total number of UFC requests that can be scheduled in one single charger is eight if the selected cluster has 4 h of range because the UFC can completely recharge an EV in just 30 min. Table 3 presents the total amount of schedules for each charging mode for each cluster.

2.1.2. NSCh Consumer

The NSCh consumer can only recharge their own vehicle if there is an available charger. However, this type of consumer can only arrive in the EVCS during the Commercial Period (CP), i.e., by 7:00 to 9:00. Outside this range, the EVCS will serve only the SCh consumer. The reason for this is to give some advantage to the SCh consumer, which in turn allows a better control for the EVCS dispatch.
For the study case, the NSCh consumers are randomly settled based on the histograms of Figure 4. As NSCh works in real time, the EVCS has complete knowledge of the EV SoC at arrival, so there is no need for estimation.
Although the NSCh consumer depends on an available charger at arrival, he also can use the remaining chargers from the Scheduled process that have not been reserved. This approach maximizes the Scheduled chargers usage and extend availability for NSCh consumers to recharge.

2.2. EPSO Approach

The scheduled framework is based on the Evolutionary Particle Swarm Optimization (EPSO) method. This method relies on a self-adaptative technique analog to evolutionary behaviors. The EPSO defines a set of particles that represent a possible solution for the scheduling of the EV users. A random population is defined initially for the set of solution. In the search space, each particle presents a movement and to avoid unfeasible solutions a population ranking approach is used to select valid candidates. This algorithm is defined as follows [28,35]:

2.2.1. EPSO Contextualization

The EPSO approach share most parts of the PSO method [26,36,37]. The particle movement follows rules based on inertia, memory, and cooperation; however, it can be said that it represents a self-adaptive algorithm because it uses concepts of mutation and selection of parameters.
The particle movement is presented in Equation (1), where X k is a particle, X k n e w is the new, and v e l k n e w is the particle velocity. Equation (2) presents the velocity equation [28].
X k n e w = X k + v e l k n e w ,
v e l k n e w = w e k 0 * × v e l k + w e k 1 * × ( b k X k ) + w e k 2 * × ( b G * X k ) ,
w e k * = w e k * + σ N ( 0 , 1 ) ,
where, in Equation (2), the weights w e are mutated based on a Gaussian distribution with mean 0 and variance 1, as presented in Equation (3). The variable b represents the best point found by the particle, and b G is the global best point. The EPSO approach also replicates each particle r times and mutates b G in order to produce some disturbance [28].

2.2.2. Population Ranking Process

Each individual must satisfy the constraint of maximum allowed EV connections for each TS. For instance, if the total amount of chargers is ten, then the total number of EV being recharged simultaneously is ten.
A feasible solution is based on a Mixed Integer Linear Programming (MILP) model, described as follows:
min i = 0 N U F C i + F C i + N C i ,
subject to
i = 0 N ( U F C i + 2 × F C i + 3 × N C i C t s ) ,
i = 0 N N C = T o t a l N C N C = 0 , , max n Z : n C t s 3 ,
i = 0 N F C = T o t a l F C F C = 0 , , max n Z : n C t s 2 ,
i = 0 N U F C = T o t a l U F C U F C = 0 , , C t s ,
where, in Equation (4), U F C , F C , and N C are the number of charging mode types scheduled for a specific charger i. The Objective Function (OF) of Equation (4) is defined to find a viable solution that satisfies the restrictions from Equations (5) to (8). The sum of all charging mode types in each charger must be equal to T o t a l N C , T o t a l F C , and T o t a l U F C , which represents the total amount of schedules for N C , F C , and U F C , respectively.
In Equation (5), the constants multiplying the variables U F C , F C , and N C refer to the number of TSs required by each charging type, considering the TS length of 30 min of this study.
In other words, the MILP problem is to find a setup where all the demanded charging types are assigned to some chargers without violating the total amount of available chargers. The  C t s variable is the total amount of TSs in the cluster, which can be either eight (4 h) or six (3 h), as presented in Table 2.
The MILP solution then provides a matrix that correlates charging types to chargers, and the final step is to randomly fill these chargers with the appropriated EVs. The final solution is then sent to the EPSO algorithm as a valid individual in the initial population. It should be noted that, for each generation, this solution could be improved by another individual; moreover, this approach avoids non-feasible solutions at the end of the algorithm.

2.2.3. EPSO Fitness Function Evaluation

In this study, the EVCS scheduling problem is approached by using the load shifting technique, and it is based on Reference [35]. It is also considered that the operating day is discretized in M TSs. The total number of EVs are N, and they can be connected to the EVCS only once throughout the day. Moreover, the EV then must be charged during L i consecutive TSs from its initial operation moment n 1 , ( i ) . To assess the performance of each particle, a Fitness Function is applied and defined as:
F O b j = w × f 1 + ( 1 w ) × f 2 + P e n a l ,
where Equation (9) represents the multi objective function for the EV scheduling. w is the weight of the function f 1 that represents the cost of supplying the load defined by:
f 1 = i = 0 N m = 0 M 1 P i × U i , m × C m ,
where, P R N : is a vector of dimension 1 × N that represents all the demanded power of the EVs (in kW) and is expressed as: P = [ P 1 P N ] 1 × N ; C R M : is a vector of dimension M × 1 in which the values represent the energy cost for each interval of time (in USD/kWh) and is expressed as: C = [ C 0 C M 1 ] M × 1 T ; U R N × M : is a binary matrix in which entries are the intervals where each EV remains connected or not. The inputs of U n , m can have the value of 1 to indicate the EV n is charging during the time m, or the value of 0 if the EV is not charging in that moment.
Each EV have its own characteristics and stays connected to a charger by a specific and continuous interval sequence, according to the type of charging mode selected. The number of intervals that the charger will be at use is represented by L i , while m 1 , ( n ) represents the initial instant of operation of each charger, as shown below:
U = 0 1 m = m 1 , ( 1 ) × L 1 2 1 m = m 1 , ( 1 ) + L 1 0 0 1 m = m 1 , ( N ) × L N 2 1 m = m 1 , ( N ) + L N 0 N × M .
The second part of Equation (9) is f 2 , which represents the peak to average to peak to ratio (PAPR) metric. This metric seeks to secure better control and load reduction at the grid; lower values of PAPR means the system have a more plain load curve, which in turn limits the peaks and possible high grid purchases. In addition, with a lower peak, it is possible to control better the dispatch. Regarding the system performance variability, the RB strategy helps to handle in time events. Whenever the system needs, the RB relies on the grid support. The PAPR metric is defined as:
f 2 = P m a x P a v g ,
where P m a x is the peak power over the M scheduling TSs, and P a v g is the mean value of the power among all the TSs. The variable P m a x and P a v g are presented, respectively, in Equations (12)–(13).
P max = max m i = 1 N P i × U i , m ,
P avg = 1 M m = 0 M 1 i = 1 N P i × U i , m .
As presented in Equation (9) both f 1 and f 2 are linearly combined through the weighted sum of them. When w is unitary, the modeling will only consider the f 1 metrics that are related to the costs for the EVCS. And, when w = 0 , only f 2 is considered, giving more importance in the grid exchanges of power. Any other valor w between 0 an 1 will consider both functions.
Finally, the  P e n a l variable in Equation (9) represents the penalization applied to the OF whenever the individual at evaluation exceeds the number of maximum simultaneously EV connections, i.e., whenever there are more EVs being recharged than there are chargers.
The main objective is to find the binary matrix U that minimizes the EPSO fitness function for a given weight w. The optimization problem is defined as:
min F o b j ( U ) ,
subject to
P i > 0 i ,
C m > 0 m ,
U i , m 0 , 1 ,
0 i = 0 N P i × U i , m P m a x m ,
0 m 1 , ( i ) m i n m 1 , ( i ) m 1 , ( i ) m a x M L i i ,
where the OF from Equation (9) must be minimized in (14). The constraints (15) and (16) means that both the load to be scheduled and the cost of energy considered must be greater than zero. Constraint (17) presents the possible values of the binary matrix U . Constraint (18) means that the peak of the considered setup must be between zero and the possible maximum peak for the system. Finally, constraint (19) represents that the scheduled time of connection for each EV must respect the cluster time range.

2.2.4. OF Normalization

In Equation (9), two different functions are linearly combined; however, f 1 has a higher magnitude than f 2 , and it is measured in USD, while f 2 is an a-dimensional parameter. To combine both sides, in this study, both functions are normalized with regard to their maximum and minimum possible values. EPSO approach is then used to find these limits. By maximizing or minimizing the system with only one function ( f 1 or f 2 ), it is possible to scan the search space to find the maximums and minimums for each cluster. The next step is to apply the normalization of each metric by Equation (20) [38,39].
X N o r m = X X m i n X m a x X m i n ,
where, in Equation (20), X N o r m is the normalized value, X m a x is the global maximum, X m i n is the global minimum, and X is the value real value of the considered metric.

2.2.5. Binary Matrix Shifting

In this study, the particle is represented by the vector containing the shifting exponents which main function is to change the initial setup of the binary matrix U, for instance, considering the position vector v = [ 110000 ] , with the columns representing TSs. The value 1 means there is an EV connected in that TS slot, and 0 means there is not. By converting the binary positional code to decimal, we have the value 48; based on this, it is possible to apply Equation (21).
E p o s n e w = E p o s × 2 s h f .
Considering, for instance, a shifting of 1 ( s h f = 1 ), the new vector is v = [ 011000 ] , or 24 in decimal. This logic is then applied in each EV of matrix U to change the load configuration.

2.3. Rule-Based (RB) Algorithms

The RB algorithms are defined in this study as a data-driven methodology to handle events in real time; it is essentially a set of conditionals that rule the operation of a given system. The following components of the modeling have RB components. The main motivation to use RB algorithm is due the lack of practical data on EV charging behaviors; therefore, in time decision-making is needed.

Rule-Based (RB) Random EV Connection

As previously stated, the NSCh EV connection depends both on the available chargers dedicated to them and the free chargers from the scheduled. These remaining chargers are presented by the empty spots in the final solution of the matrix calculated by the EPSO approach. Figure 5 presents the flowchart for the RB algorithm that rules the NSCh EV connection.
In Figure 5, RCH means the chargers dedicated to the NSCh consumer, and CH is the charger dedicated to the SCh consumers. There are four types of scenarios that could happen.
  • there are both RCH and free CH chargers ready to be used, in which case the NSCh EV is preferably connected to a CH charger if possible, to maximize the usage of the CH chargers; if the NSCh EV cannot be connected to it, then the consumer will be connected to a RCH charger if possible;
  • there are no RCH chargers, and there are free CH chargers, so the only option is to connect the NSCh consumer in a free CH charger if possible;
  • there are no free CH chargers; however, there are RCH chargers, in which case, the NSCh EV will be connected to a RCH charger if possible; and
  • there are no chargers available, in which case the EV user will not charge in the EVCS and must find another EVCS or try another time.

2.4. Rule-Based (RB) Dispatch

The dispatch of the system DERs also is controlled by an RB algorithm; among the DERs, there is a photovoltaic solar system (PVSS) of 150 kWp and a BESS of 250 kWh/150 kW.

2.4.1. BESS Module

The flowchart of the BESS operation and control is presented in Figure 6.
The flowchart of Figure 6 represents the logic behind the operation of the BESS. The BESS can operate at three different states: charging, discharging, and idling. At charging state, the BESS receives energy from the system. At this condition, the Analyze In module verifies if it is possible to absorb a given amount of energy or not.
When the BESS is at discharging state, the Analyze Out module verifies if it is possible to remove energy from the BESS. In idling state, the BESS remains inactive. Figure 7 presents the inside operation of the BESS.
In Figure 7, whenever the system sends energy to be absorbed by the BESS, and the Analyze In module allows it, the module Energy In performs the injection operation and, at the same time, updates the BESS metrics, such as SoC, BESS average price, and the degradation cost of the operation. The BESS average price is a metric that reflects the average price of the operations of removal or injection of energy in the BESS, and it is defined as follows:
B E S S a v g p r i c e = C u m u l a t i v e p r i c e C u m u l a t i v e e n e r g y .
In Equation (22), the C u m u l a t i v e p r i c e is the metric that measures the price balance of the energy injected or absorbed by the BESS, and it is updated in every operation performed by the BESS. The  C u m u l a t i v e e n e r g y is the metric that measures the energy balance inside the BESS, and it is also updated in every operation.
The B E S S a v g p r i c e will be the combination of both, for instance, if the BESS receives 1 kWh of energy, and the base price of this amount of energy is 1 USD/kWh, then the cost of the operation will be 1 USD plus the degradation cost of the BESS.
This value is then added to the cumulative price of the BESS, and the cumulative energy is updated by the energy coming in.
In other words, if the energy being sent to the BESS is cheap, then the B E S S a v g p r i c e will decrease, and, if the energy is expensive, it will increase B E S S a v g p r i c e .
This operation is also computed when discharging energy, where the B E S S a v g p r i c e will also vary according to the amount discharged and the average price of the operation.
In this step, the Energy Out is used. Finally, the BESS degradation model is based on Reference [40]. In addition, as this study focuses on the EVCS planning, for simplification purposes, only the degradation of the battery connected to the charging station is considered.

2.4.2. Economic Model of the EVCS

The economic model is the set of metrics used to create a simple Cash Flow (CF) system for the EVCS. And the CF is defined as:
C F = i = 0 T S ( E V B i l l E V C S S e l l + A v a i l C o s t ) ( E V B c o s t + E V C S B u y ) ,
where, in Equation (23), E V B i l l is the total invoice value of all EVs at TS i; this variable has taken into account the revenue by delivering energy to the consumers. The  E V C S S e l l is the remuneration of the total amount of energy sold to the grid by exporting the PV excess or BESS energy. A v a i l C o s t is the availability cost of the chargers, and it changes according with the time an EV stays connected to it. In this study, 10 dollar cents is considered every 30 min of connection time for the SCh consumer, and 20 dollars cents for the NSCh.
Note that, for instance, the  A v a i l C o s t under UFC charging mode is cheaper than the one under NC; this is because the EV stays less time connected under UFC. In contrast, the UFC energy price is more expensive than the NC energy.
The E V B c o s t is the base cost of supplying the EV load with the use of the DERs dispatch and the grid energy. The  E V C S B u y is the total value paid to the grid when purchasing energy from it.
A positive value for Cash Flow (CF) means a profit for the EVCS, and a negative value of FC means a deficit for the EVCS. Another economic incentive for reducing the total load concentrated at the higher periods of the tariff is a bonus for the EVCS whenever it must buy energy from the grid, and this happens at a low cost of the tariff.
Is important to point out that the framework is intended for operation purposes, checking the daily behavior, the response to the system, and consumers demand. Therefore, the simple CF only considers the operational revenues and expenses that incur over the day; initial investments and Net Present Costs (NPC) for larger time horizons are not considered.
It is considered a variable percentage of profit for the EVCS that is inversely proportional to the tariff price, i.e., the EVCS receives more profit selling energy bought from the grid to the EV consumer if the current price of the tariff is low.
This approach is justified because, in our study, the Grid Utility owns the EVCS; therefore, reducing the base cost of supplying the EV load is also interesting to the Grid Utility.
Finally, the battery degradation costs are considered both by the EVCS and the EV consumer; however, the consumer also pays a percentage more whenever the energy it requires is coming from the BESS.

2.4.3. RB DER’s Dispatch

The DER’s dispatch is also RB according with the Algorithm 1.
Algorithm 1: Rule-based (RB) dispatch.
Energies 14 01370 i001
In Algorithm 1, for each TS, the system verifies if there is EV load to be supplied. The system will always use PV energy to serve the load if there is generation.
When PV generation is in surplus, the excess energy will go to the BESS. When the BESS is full, the excess from PV is sent to the grid. The whole operation will always prioritize the lowest economical dispatch to better serve the load.

3. Study Case

For the study cases, it is considered an EVCS composed of:
  • 10 chargers for scheduling;
  • 5 chargers for the NSCh EVs;
  • 150 kWp Photovoltaic (PV) Solar System and a 250 kWh/150 kW BESS; and
  • a modified Static Time of Use Tariff (White Tariff) [41].
The simulations were performed in a desktop computer with 64-bits Windows operational system, processor Intel i5 2.90 GHz, and 16 GB of RAM.
In all scenarios, it is considered that the BESS will operate in arbitrage mode. This means that BESS is only available to serve the load in the more expensive periods of the tariff.
The WT is modified to reflect the PV availability. For more PV output, there is a lower price for the WT in each instant. The original WT, the WT with variability, and the modified variable WT are presented in Figure 8.
In Figure 8a, Gaussian noise is added to the WT in order to produce more variability in the WT prices, similar to Real Time Pricing tariffs [42].
Regarding the EPSO parameters, in all cases, 1000 generations are considered as the stop criteria, and 50 particles per generation. Figure 9 presents the PV curve utilized and the PV forecast for the next day in per unity (PU) values. The PU curve for the real PV production is based on the PVSS installed at the Federal University of Santa Maria [43].
The forecast PV output of Figure 9 is used in the EPSO approach, and the real values are used in the RB strategy.

3.1. EPSO Results

To better visualize the impact of the EPSO approach, for each cluster, the impact of varying the weight w is evaluated, as follows:
  • comparison of the scheduled demand for w = 1 and w = 0;
  • Pareto point for the two main parts of the EPSO OF; and
  • main comparison between the cases with w = 1,w = 0 and the Pareto set.
Table 4 presents the number of requests generated for each cluster. The total number of EVs to be scheduled are 126 for the day-ahead operation; in the E s t L o a d row of the table, the amount of energy in each cluster that has to be supplied is presented. And the T o t a l C m o d e s presents the number of all charging modes for each cluster.
Figure 10 presents the scheduled demands for the case with w = 1 and w = 0 for all the seven clusters.
In Figure 10, for the case with w = 1 , the load is more concentrated in the lower periods of the tariff; this behavior is due to the OF of the optimization considering only the cost function f 1 , which in turn reduces the final cost of supplying the load.
For the second case, with w = 0, the load is more distributed, thus filling all the valleys of the first case, which, in this case, ends lowering its PAPR metric, as expected, due to the OF only consider the PAPR part f 2 .
To search for a mean term between both functions, according with the modeling, it was defined that the interval for w is 0 w 1 ; thus, after running several simulations, in Table 5, the Pareto weight find for each cluster is presented.
The found weights for each cluster in the Pareto case are presented in Table 6.
In Table 5, when using w = 1 the cost function, or f 1 , is minimized, and the PAPR is not taken into consideration. When using w = 0 , only f 2 is minimized, and f 1 is now neglected. Finally, the Pareto set for all clusters presents the equilibrium between both metrics. Figure 11 shows the f 1 metric for all clusters considering w = 0 , w = 1 and the Pareto set of points.
The cluster with the highest value is C5 that represents the cluster with more EVs to be scheduled. Figure 12 presents the PAPR values for each cluster and for each case.
In Figure 12, although the cluster C0 is not the one with highest load demand, the PAPR metric is the one with the highest differences for each of the cases, and, for all clusters, the Pareto point was between w = 0.4 and w = 0.8 .
The Pareto set of points is found based on the values of f 1 and f 2 by changing the w parameter, and the balance point between them is then selected. As an example, in order to visualize this behavior, Figure 13 presents the results for the Cluster 5.
As Figure 13 shows, the Pareto point for EPSO solution was w = 0.6 for Cluster 5, which presents a low impact in PAPR and significant reduction in costs. With these criteria, it is possible to validate the EPSO methodology by comparing it to another MA for the weight found.

3.2. EPSO Validation

In order to validate the heuristic method, the EPSO strategy is here compared to the well known heuristics of Genetic Algorithm (GA) [7,9] and Particle Swarm Optimization (PSO) [37]. As the EPSO is performed in each cluster, the validation of the method is presented here in cluster C5. It should be noted that similar results of performance were found in the other clusters, but here the focus is made on the cluster with the higher number of EVs to be scheduled. It is also considered the weight w of 0.6 as the one in Table 6.
The three MA compared consider two stop criteria, the first based on the maximum generations and set to 1000, and the second related to output improvement, where the algorithm stops if there are 15 consecutive generations without improvement. In order to validate the model, all approaches are performed with different population sizes, ranging from 50 to 500. The GA parameters are described as follows [7,9].
  • selection of individuals by Roulette Wheel approach with β = 1.0 ;
  • mutation rate with μ = 0.05 and σ = 0.5 ;
  • crossover rate with γ = 0.5 .
The PSO parameters are described as follows [7,26,31].
  • Acceleration constants c1 = 1.5 and c2 = 2.0;
  • Inertia = 0.7; and
  • Damp factor = 0.995.
In Figure 14, the validation outputs are presented for the three metaheuristics approaches in Cluster 5 with w = 0.6 .
Figure 14a–c shows performance of the proposed EPSO compared with GA and PSO. The tests shows that most of the cases EPSO present the fastest results in comparison with GA and PSO. It can be seen that EPSO requires only 3.87 s to obtain a solution with 500 generations, being 80% faster than GA, and 45% faster than PSO. The number of generations to achieve result were less from EPSO methodology requiring only between 15 and 28, which directly impacts simulation time. As can be seen, only for 100 individuals does the EPSO require more generations in comparison with PSO and GA, but, in most of the cases, the EPSO presented a faster convergence.
Comparing OF performance, the EPSO presented better results with the minimal costs, for all of the number of individuals tested. These results prove that EPSO is useful for the proposed framework with a better performance than AG [18] and PSO [13,14] in terms of reduction of speed and improvement of objective function.

3.3. Rule-Based (RB) Impact

RB strategy supports EPSO optimized solution. The required simulation time for RB was 0.0118 s for the total of 48 TSs, which means an average time of 0.246 μ s for each TS. This very short time for determination of control signals for EVCS makes the RB suitable for application in real time operation, by reducing TSs formulation. The impact in the EVCS, considering w = 1 , w = 0 , and the Pareto set of points are summarized in Table 7.
In Table 7, the three cases are compared. With w = 1 , the system presents the best profit for the EVCS, and the EV owner also have a lowered bill price in relation to the other cases. This is mainly because, by using w = 1 , the EPSO tends to concentrate the EV load in the lowest periods of the tariff; thus, when the EVCS supplies it with the grid energy, its bill is also lowered.
Although using w = 1 showed a big difference in the EPSO step, compared to using w = 0 , in the RB algorithm, the factors, such as the NSCh EV load and the DER’s dispatch, affect the final balance of the system. Nevertheless, the EVCS still presents a better profit when considering only the cost function.
When using w = 0 , the PAPR is of the system always minimized, and, although this parameter is modified by the NSCh load that has stochastic characteristics, it is still he lower of the three cases.
The Pareto point, in almost all cases, presented a mid-term for every variable of Table 7. Figure 15 presents the Pareto demand load in comparison to the tariff.
Figure 16 presents the SCh and the NSCh chargers usage matrix.
Figure 16 presents the chargers usage for the entire day. Vertical values are related to clusters and horizontal values refer to chargers use. The black rectangles are related to the non-commercial hours; thus, is not possible for use by the NSCh users. In addition, the pink rectangles are the available chargers that remain not used because the demand of EV is low. The NSCh requests are being organized, both in the RCH chargers and in the CH chargers, because this type of consumer is advised to use the free SCh chargers whenever possible. It should be noted that, when the SCh chargers are not completely used by all SCh users, the remaining chargers could be used by the NCh users. This is presented in the Figure 16; for example, the red rectangles at the right side means there are NSCh EVs being recharged by SCh chargers. This behavior ends up creating a left to right movement of the NSC requests. To evaluate the technical impact of the Pareto system in the EVCS, Figure 17 presents the DERs dispatch for the day-ahead.
In Figure 17, the BESS is in arbitrage mode, i.e., it is only used in the higher periods of the tariff, providing load supply with a lower base cost, and lowering the grid purchases from the EVCS. The PV output remains serving the load in the generation periods and exports its excess to the BESS whenever is possible. Figure 18 presents the grid impact considering the EPSO-RB strategy.
In Figure 18, there is an increase of losses as the EVCS demands energy from the grid. Nevertheless, the losses value are low enough for a high impact to the network, as was set a limit for requirement of energy to the grid. In addition, there are times where the solar generation contributes to sell energy to the network with low losses at hours 15:00 to 17:00.
To evaluate the economic impact of the DERs dispatch in the EV managed load, by using the simple CF system, Figure 19 presents the relation between the total EV invoice prices and the grid tariff.
In Figure 19, it can be seen that the Cash Flow (CF) follows, most of the time, the EV invoice, increasing as the EV payments grows. Moreover, the EVCS also profits by selling energy to the grid, as shown in hours 10:00 to 11:00, where there is a low EV invoice but an excess in PV production. Figure 20 presents the comparison between the CF and the EVCS exchanges with the grid.
In Figure 20, it is shown that, even when is required energy from the grid, the EVCS presents a positive cash flow by selling energy to the client as presented in hours 3:00 to 7:00 and 19:00 to 21:00. Moreover, in most of the cases, it was not needed to demand high amount of energy from the grid because the DERs supported the EVCS operation.

4. Limitations and Challenges

Our proposed methodology is based on daily operation; thus, studies for planning based on middle time or long-time applications, are disregarded. The battery operates in responsive operation, based on rules, but could be developed also for application in the scheduling operation, applying predictions techniques for EV demand. Moreover, the scheduling process could also use EV owners historic charging behavior; however, this approach would require a higher level of data availability. Regarding this, the lack of practical data motivates the operation based on rules, as this methodology is intended for application in Brazilian electricity transportation. Nevertheless, this market is growing fast in the Brazilian market, as the COPEL application shows [21], giving the opportunity to gather data for future development of prediction techniques for set EV scheduling operation.
The proposed approach was tested with the purpose to be further used in some EVCS actually installed in the Brazilian electrovia. Regarding this, the model could be adapted to consider more EVCS by establishing a communication and set of rules to attend multiple agents. Thus, for future improvements in the proposed EPSO-RB model, it could be considered a multi-agent study considering more objectives in the fitness function. It could be also considered that the SCh consumers could use the NSCh remaining chargers to maximize the NSCh charger’s usage.

5. Conclusions

This paper presented a combined framework for day-ahead and real time operation of EVCS. The combined EPSO-RB approach presented fast and good results, and the EPSO algorithm found, for each cluster, the Pareto point of the system when scheduling the requests in less than 4 s for 500 individuals. The RB strategy proved to handle the NSCh consumers demand, thus providing more profit to the EVCS without overloading it. The RB simulation time were less than 0.3 μ s.
Although the best profitable scenario found was with only the cost function taken into account, as the EVCS belongs to the Grid Utility, it is also important to reduce the peak of the system to avoid overloading whenever using the grid for energy exchanges. Thus, the Pareto approach also presented an efficient method to find a mid-term between the economic and the technical metrics. Finally, the RB strategies presented high flexibility by handling the NSCh loads given the stochastic characteristics of both the EVs and the PV.
As this methodology presents a flexible option to handle real-time problems and provides more profit to the EVCS, this approach is considered to be implemented in large electric cars electrovias, as the one in Reference [21]. For this purpose, the methodology would require some changes, such as lower TSs, which can be easily implemented. In addition, the real-time RB strategy could be crucial to the EVCS given the lack of practical data on EVs charging behaviors. Moreover, the system is able to combine both optimized decision-making provided by the scheduling and also to handle real-time EV demand. Finally, as the scripts were developed in a open source language, it is easier to have interoperability with Raspberry micro controllers in practical applications.

Author Contributions

Conceptualization, L.W.S. and C.A.S.R.; methodology, H.E.O.F. and C.A.S.R.; software, H.E.O.F. and L.W.S. and D.P.B.; validation, H.E.O.F. and C.A.S.R.; formal analysis, C.A.S.R. and H.E.O.F.; investigation, C.A.S.R. and L.W.S.; resources, H.E.O.F.; data curation, H.E.O.F.; writing—original draft preparation, H.E.O.F.; writing—review and editing, C.A.S.R. and W.d.S.B. and H.E.O.F. and Z.I.N.; visualization, L.N.C.; supervision, L.N.C.; project administration, L.N.C. and W.S.B.; funding acquisition, L.N.C. and Z.I.N. All authors have read and agreed to the published version of the manuscript.

Funding

This study was also financed by the Coordination for the Improvement of Higher Education Personnel—CAPES Foundation (“Coordenação de Aperfeiçoamento de Pessoal de Nível Superior”)—Brazil (CAPES/PROEX)—Financial code 001.

Institutional Review Board Statement

Not applicable.

Informed Consent Statement

Not applicable.

Data Availability Statement

The data presented in this study are openly available at https://github.com/Hericles-Farias/Energies_2021_Datasets (accessed on 3/01/2021).

Acknowledgments

The authors acknowledge the technical and financial support of ANEEL Strategic R&D P022/2019, COPEL—distribution R&D de (PD 2866-0519/2019), Federal University of Santa Maria, Santa Maria—RS, Brazil, CNPq PQ 1-D 310761/2018-2, INCT-GD process CNPq 465640/2014-1, process CAPES no. 23038.000776/2017-54 and FAPERGS 17/2551-0000517-1.

Conflicts of Interest

The authors declare no conflict of interest.

Abbreviations

The following abbreviations are used in this manuscript:
EVCSElectric vehicle charging station
EPSOEvolutionary particle swarm optimization
EVElectric vehicle
RBRule-based
SChScheduled consumers
NSChNon-scheduling users
PVPhotovoltaic generation
BESSBattery energy storage system
SOCState of charge
DSODistribution system operator
MHMetaheuristic
GAGenetic algorithm
PSOParticle swarm optimization
DERsDistributed energy resources
EMCEnergy management control
MDPMarkov decision process
NCNormal charging
FCFast charging
UFCUltra-fast charging
CPCommercial period
TSTime step
MILPMixed integer linear programming
OFObjective function
PAPRPeak to average to peak to ratio
ESEvolution strategies
PVSSPhotovoltaic solar system
WTWhite tariff
PUPer unity

References

  1. IEA. Global EV Outlook 2019, IEA, Paris. 2019. Available online: https://www.iea.org/reports/global-ev-outlook-2019 (accessed on 3 January 2021).
  2. IRENA. Innovation Outlook: Smart Charging for Electric Vehicles, Abu Dhabi. 2019. Available online: https://www.irena.org/-/media/Files/IRENA/Agency/Publication/2019/May/IRENA_Innovation_Outlook_EV_smart_charging_2019.pdf (accessed on 25 January 2021).
  3. Global EV Outlook 2020; International Energy Agency (IEA): Paris, France, 2020. [CrossRef]
  4. Heydt, G.T. The impact of electric vehicle deployment on load management strategies. IEEE Trans. Power Appar. Syst. 1983, PAS-102, 1253–1259. [Google Scholar] [CrossRef]
  5. Deb, S.; Tammi, K.; Kalita, K.; Mahanta, P. Impact of electric vehicle charging station load on distribution network. Energies 2018, 11, 178. [Google Scholar] [CrossRef] [Green Version]
  6. Chung, H.M.; Li, W.T.; Yuen, C.; Wen, C.K.; Crespi, N. Electric Vehicle Charge Scheduling Mechanism to Maximize Cost Efficiency and User Convenience. IEEE Trans. Smart Grid 2019, 10, 3020–3030. [Google Scholar] [CrossRef] [Green Version]
  7. Milas, N.; Mourtzis, D.; Tatakis, E. A Decision-Making Framework for the Smart Charging of Electric Vehicles Considering the Priorities of the Driver. Energies 2020, 13, 6120. [Google Scholar] [CrossRef]
  8. Shibl, M.; Ismail, L.; Massoud, A. Machine learning-based management of electric vehicles charging: Towards highly-dispersed fast chargers. Energies 2020, 13, 5429. [Google Scholar] [CrossRef]
  9. Alonso, M.; Amaris, H.; Germain, J.G.; Galan, J.M. Optimal charging scheduling of electric vehicles in smart grids by heuristic algorithms. Energies 2014, 7, 2449–2475. [Google Scholar] [CrossRef]
  10. Abronzini, U.; Attaianese, C.; D’arpino, M.; Di Monaco, M.; Tomasso, G. Cost minimization energy control including battery aging for multi-source EV charging station. Electronics 2019, 8, 31. [Google Scholar] [CrossRef] [Green Version]
  11. Lee, J.; Lee, E.; Kim, J. Electric vehicle charging and discharging algorithm based on reinforcement learning with data-driven approach in dynamic pricing scheme. Energies 2020, 13, 1950. [Google Scholar] [CrossRef] [Green Version]
  12. Hafez, O.; Bhattacharya, K. Integrating EV charging stations as smart loads for demand response provisions in distribution systems. IEEE Trans. Smart Grid 2018, 9, 1096–1106. [Google Scholar] [CrossRef]
  13. Dharmakeerthi, C.H.; Mithulananthan, N.; Saha, T.K. A comprehensive planning framework for electric vehicle charging infrastructure deployment in the power grid with enhanced voltage stability. Int. Trans. Electr. Energy Syst. 2015, 25, 1022–1040. [Google Scholar] [CrossRef]
  14. Dharmakeerthi, C.H.; Mithulananthan, N.; Saha, T.K. Planning of electric vehicle charging infrastructure. In Proceedings of the 2013 IEEE Power & Energy Society General Meeting, Vancouver, BC, Canada, 21–25 July 2013. [Google Scholar] [CrossRef]
  15. Hayajneh, H.S.; Zhang, X. Evaluation of electric vehicle charging station network planning via a co-evolution approach. Energies 2019, 13, 25. [Google Scholar] [CrossRef] [Green Version]
  16. Kwon, Y.; Kim, T.; Baek, K.; Kim, J. Multi-objective optimization of home appliances and electric vehicle considering customer’s benefits and offsite shared photovoltaic curtailment. Energies 2020, 13, 2852. [Google Scholar] [CrossRef]
  17. Zhang, T.; Chen, W.; Han, Z.; Cao, Z. Charging scheduling of electric vehicles with local renewable energy under uncertain electric vehicle arrival and grid power price. IEEE Trans. Veh. Technol. 2014, 63, 2600–2612. [Google Scholar] [CrossRef] [Green Version]
  18. Hayajneh, H.S.; Lainfiesta, M.; Zhang, X. Three birds one stone: A solution to maximize renewable generation, incentivize battery deployment, and promote green transportation. In Proceedings of the 2020 IEEE Power and Energy Society Innovative Smart Grid Technologies Conference, ISGT 2020, Washington, DC, USA, 17–20 February 2020; pp. 4–8. [Google Scholar] [CrossRef]
  19. Bharatiraja, C.; Padmanaban, S.; Siano, P.; Krishnamoorthy, R.; Selvaraj, R. Real-time forecasting of EV charging station scheduling for smart energy systems. Energies 2017, 10, 377. [Google Scholar] [CrossRef] [Green Version]
  20. Yang, S.N.; Cheng, W.S.; Hsu, Y.C.; Gan, C.H.; Lin, Y.B. Charge scheduling of electric vehicles in highways. Math. Comput. Model. 2013, 57, 2873–2882. [Google Scholar] [CrossRef]
  21. COPEL. Copel Inaugura Maior Eletrovia Do Pais. 2019. Available online: https://www.copel.com/hpcopel/root/nivel2.jsp?endereco=%2Fhpcopel%2Froot%2Fpagcopel2.nsf%2Fdocs%2F66B766F31D7940A58325836200594384 (accessed on 15 January 2021).
  22. Shi, R.; Zhang, P.; Zhang, J.; Niu, L.; Han, X. Multidispatch for microgrid including renewable energy and electric vehicles with robust optimization algorithm. Energies 2020, 13, 2813. [Google Scholar] [CrossRef]
  23. Liu, W.L.; Gong, Y.J.; Chen, W.N.; Liu, Z.; Wang, H.; Zhang, J. Coordinated Charging Scheduling of Electric Vehicles: A Mixed-Variable Differential Evolution Approach. IEEE Trans. Intell. Transp. Syst. 2020, 21, 5094–5109. [Google Scholar] [CrossRef]
  24. Sassi, O.; Oulamara, A. Electric vehicle scheduling and optimal charging problem: Complexity, exact and heuristic approaches. Int. J. Prod. Res. 2017, 55, 519–535. [Google Scholar] [CrossRef]
  25. Xu, Y.; Pan, F.; Tong, L. Dynamic Scheduling for Charging Electric Vehicles: A Priority Rule. IEEE Trans. Autom. Control 2016, 61, 4094–4099. [Google Scholar] [CrossRef]
  26. Savari, G.F.; Krishnasamy, V.; Sugavanam, V.; Vakesan, K. Optimal Charging Scheduling of Electric Vehicles in Micro Grids Using Priority Algorithms and Particle Swarm Optimization. Mob. Netw. Appl. 2019, 24, 1835–1847. [Google Scholar] [CrossRef]
  27. Zima-Bockarjova, M.; Sauhats, A.; Petrichenko, L.; Petrichenko, R. Charging and discharging scheduling for electrical vehicles using a shapley-value approach †. Energies 2020, 13, 1160. [Google Scholar] [CrossRef] [Green Version]
  28. Miranda, V.; Keko, H.; Jaramillo, A. EPSO: Evolutionary Particle Swarms BT—Advances in Evolutionary Computing for System Design; Springer: Berlin/Heidelberg, Germany, 2007; pp. 139–167. [Google Scholar] [CrossRef] [Green Version]
  29. Kurniawan, T.; Baguley, C.A.; Madawala, U.K.; Suwarno; Hariyanto, N.; Adianto, Y. An electric vehicle charge scheduling approach suited to local and supplying distribution transformers. Energies 2020, 13, 3486. [Google Scholar] [CrossRef]
  30. Pflaum, P.; Alamir, M.; Lamoudi, M.Y. Probabilistic Energy Management Strategy for EV Charging Stations Using Randomized Algorithms. IEEE Trans. Control Syst. Technol. 2018, 26, 1099–1106. [Google Scholar] [CrossRef]
  31. Hadian, E.; Akbari, H.; Farzinfar, M.; Saeed, S. Optimal Allocation of Electric Vehicle Charging Stations With Adopted Smart Charging/Discharging Schedule. IEEE Access 2020, 8, 196908–196919. [Google Scholar] [CrossRef]
  32. Liu, Z.; Wu, Q.; Shahidehpour, M.; Li, C.; Huang, S.; Wei, W. Transactive real-time electric vehicle charging management for commercial buildings with PV on-site generation. IEEE Trans. Smart Grid 2019, 10, 4939–4950. [Google Scholar] [CrossRef] [Green Version]
  33. Van Rossum, G.; Drake, F.L., Jr. Python Reference Manual; Centrum voor Wiskunde en Informatica Amsterdam: Amsterdam, Netherlands, 1995. [Google Scholar]
  34. Cross, J.D.; Hartshorn, R. My Electric Avenue:Integrating Electric Vehicles into the Electrical Networks. 2021. Available online: http://myelectricavenue.info (accessed on 21 January 2021).
  35. Bertineti, D.P.; Canha, L.N.; Brignol, W.; Medeiros, A.P.; De Azevedo, R.M.; Nadal, Z.L. Flexible Energy Management Strategy for Electric Vehicles Charging Stations. In Proceedings of the UPEC 2020—2020 55th International Universities Power Engineering Conference, Proceedings, Torino, Italy, 1–4 September 2020. [Google Scholar] [CrossRef]
  36. Mirjalili, S. Genetic algorithm. Stud. Comput. Intell. 2019, 780, 43–55. [Google Scholar] [CrossRef]
  37. Poli, R.; Kennedy, J.; Blackwell, T. Particle swarm optimization: An overview. Swarm Intell. 2007, 1, 33–57. [Google Scholar] [CrossRef]
  38. Jain, Y.K.; Bhandare, S.K. Min Max Normalization Based Data Perturbation Method for Privacy Protection. Int. J. Comput. Commun. Technol. 2013, 4, 233–238. [Google Scholar] [CrossRef]
  39. Naidu, K.; Mokhlis, H.; Bakar, A.H. Multiobjective optimization using weighted sum Artificial Bee Colony algorithm for Load Frequency Control. Int. J. Electr. Power Energy Syst. 2014, 55, 657–667. [Google Scholar] [CrossRef]
  40. Ma, Z.; Zou, S.; Ran, L.; Shi, X.; Hiskens, I.A. Efficient decentralized coordination of large-scale plug-in electric vehicle charging. Automatica 2016, 69, 35–47. [Google Scholar] [CrossRef]
  41. ANEEL. Establishes the General Conditions of Electricity Supply from Updated and Consolidated Form. 2021. Available online: https://www.aneel.gov.br/documents/656877/ (accessed on 13 January 2021).
  42. IRENA. Time-of-Use Tariffs; International Renewable Energy Agency: Abu Dhabi, United Arab Emirates, 2019; pp. 1–18. [Google Scholar]
  43. UFSM. Photovoltaic Power Plant Starts to Work at UFSM. 2021. Available online: https://www.ufsm.br/2018/10/10/usina-de-geracao-de-energia-solar-comeca-a-funcionar-na-ufsm/ (accessed on 20 January 2021).
Figure 1. Histograms for the electric vehicle (EV) users who are scheduled consumers (SCh): (a) Histogram for the average number of requests. (b) Histogram for the EV state of charge (SoC) at request time.
Figure 1. Histograms for the electric vehicle (EV) users who are scheduled consumers (SCh): (a) Histogram for the average number of requests. (b) Histogram for the EV state of charge (SoC) at request time.
Energies 14 01370 g001
Figure 2. Flowchart for the EV user request.
Figure 2. Flowchart for the EV user request.
Energies 14 01370 g002
Figure 3. Flowchart for the EV user estimate and real SoC at arrival.
Figure 3. Flowchart for the EV user estimate and real SoC at arrival.
Energies 14 01370 g003
Figure 4. NSCh (non-scheduling users) consumers used data: (a) Histogram for the average number of EVs at arrival. (b) Histogram for the EV SOC at arrival.
Figure 4. NSCh (non-scheduling users) consumers used data: (a) Histogram for the average number of EVs at arrival. (b) Histogram for the EV SOC at arrival.
Energies 14 01370 g004
Figure 5. NSCh EV connection flowchart: (a) First part. (b) Second part.
Figure 5. NSCh EV connection flowchart: (a) First part. (b) Second part.
Energies 14 01370 g005
Figure 6. Battery energy storage systems (BESS) flowchart.
Figure 6. Battery energy storage systems (BESS) flowchart.
Energies 14 01370 g006
Figure 7. BESS modules.
Figure 7. BESS modules.
Energies 14 01370 g007
Figure 8. Tariff setup: (a) WT and WT with variability. (b) WT variable and the forecast photovoltaic (PV) output.
Figure 8. Tariff setup: (a) WT and WT with variability. (b) WT variable and the forecast photovoltaic (PV) output.
Energies 14 01370 g008
Figure 9. Real and forecast PV production.
Figure 9. Real and forecast PV production.
Energies 14 01370 g009
Figure 10. EV demand: (a) Demand with w = 1. (b) Demand with w = 0.
Figure 10. EV demand: (a) Demand with w = 1. (b) Demand with w = 0.
Energies 14 01370 g010
Figure 11. f 1 metric for each cluster.
Figure 11. f 1 metric for each cluster.
Energies 14 01370 g011
Figure 12. f 2 metric for each cluster.
Figure 12. f 2 metric for each cluster.
Energies 14 01370 g012
Figure 13. Pareto point for cluster 5.
Figure 13. Pareto point for cluster 5.
Energies 14 01370 g013
Figure 14. Validation for the Cluster 5 with w e i g h t = 0.6 : (a) Simulation time comparison. (b) Generation number comparison. (c) Objective Function (OF) comparison.
Figure 14. Validation for the Cluster 5 with w e i g h t = 0.6 : (a) Simulation time comparison. (b) Generation number comparison. (c) Objective Function (OF) comparison.
Energies 14 01370 g014aEnergies 14 01370 g014b
Figure 15. Pareto load demand.
Figure 15. Pareto load demand.
Energies 14 01370 g015
Figure 16. Charger usage for the Pareto case.
Figure 16. Charger usage for the Pareto case.
Energies 14 01370 g016
Figure 17. Distributed energy resources (DERs) and EV power dispatch.
Figure 17. Distributed energy resources (DERs) and EV power dispatch.
Energies 14 01370 g017
Figure 18. Grid power impact.
Figure 18. Grid power impact.
Energies 14 01370 g018
Figure 19. Comparison between Cash Flow (CF) and EV invoice.
Figure 19. Comparison between Cash Flow (CF) and EV invoice.
Energies 14 01370 g019
Figure 20. Comparison between cash flow and grid economic exchanges.
Figure 20. Comparison between cash flow and grid economic exchanges.
Energies 14 01370 g020
Table 1. Comparison of evolutionary particle swarm optimization-rule-based (EPSO-RB) features against alternative approaches.
Table 1. Comparison of evolutionary particle swarm optimization-rule-based (EPSO-RB) features against alternative approaches.
FeaturesReferencesEPSO-RB
Combine Schedule with Real time[7,10,11,15,19,23,29]X
Works on real time[7,9,10,11,15,18,19,29,30]X
Works on schedule[7,9,11,12,13,14,15,16,17,19,23,24,25,26,27,29,31]X
Consider users comfort decisions[7,13,15,19,27,29,30,31,32]X
Applied on long distance travel[19,20]X
Handle remaining SOC of EV during
arrival to EVCS
[11,12,15,19,23,26,30,31]X
Considers different charger operations[7,8,9,15,23]X
Handle grid impact[8,9,10,11,12,13,14,18,19,22,24,26,29,30,31]X
Considers BESS support[10,17,18,26]X
Consider PV support[10,11,13,16]X
Compute BESS degradation cost[10]X
Consider injection to Grid[16,18]X
Table 2. Clusters for scheduling.
Table 2. Clusters for scheduling.
ClusterC0C1C2C3C4C5C6
Hours4333443
Ti0:004:007:0010:0013:0017:0021:00
Tf4:007:0010:0013:0017:0021:000:00
Table 3. Maximum schedules per charging mode type, considering 10 chargers for scheduling.
Table 3. Maximum schedules per charging mode type, considering 10 chargers for scheduling.
Clusters/Ctypemax UFCmax FCmax NC
C0, C4, C5804027
C1, C2, C3, C6603020
Table 4. Users requests.
Table 4. Users requests.
Ch/ClusterC0C1C2C3C4C5C6
FC213779147
NC16771174
SC1521375
TotalCmodes4241615232816
EstLoad (kWh)62303204234329315245
Table 5. Metrics for each case.
Table 5. Metrics for each case.
CaseCost (USD)PAPR
w = 1 154.874.08
w = 0 197.251.50
Pareto167.882.24
Table 6. Pareto weights for each cluster.
Table 6. Pareto weights for each cluster.
Cluster0123456
w0.80.40.50.50.50.60.6
Table 7. EPSO-RB metrics for the operational day.
Table 7. EPSO-RB metrics for the operational day.
CaseProfit (USD)PAPRBESS Deg (USD)Grid Use (kWh)Invoice EV (USD)
w = 0 239.841.879.351103405.77
w = 1 247.302.9311.241364405.73
Pareto240.342.5610.761230387.90
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Share and Cite

MDPI and ACS Style

Oliveira Farias, H.E.; Sepulveda Rangel, C.A.; Weber Stringini, L.; Neves Canha, L.; Pegoraro Bertineti, D.; da Silva Brignol, W.; Iensen Nadal, Z. Combined Framework with Heuristic Programming and Rule-Based Strategies for Scheduling and Real Time Operation in Electric Vehicle Charging Stations. Energies 2021, 14, 1370. https://doi.org/10.3390/en14051370

AMA Style

Oliveira Farias HE, Sepulveda Rangel CA, Weber Stringini L, Neves Canha L, Pegoraro Bertineti D, da Silva Brignol W, Iensen Nadal Z. Combined Framework with Heuristic Programming and Rule-Based Strategies for Scheduling and Real Time Operation in Electric Vehicle Charging Stations. Energies. 2021; 14(5):1370. https://doi.org/10.3390/en14051370

Chicago/Turabian Style

Oliveira Farias, Héricles Eduardo, Camilo Alberto Sepulveda Rangel, Leonardo Weber Stringini, Luciane Neves Canha, Daniel Pegoraro Bertineti, Wagner da Silva Brignol, and Zeno Iensen Nadal. 2021. "Combined Framework with Heuristic Programming and Rule-Based Strategies for Scheduling and Real Time Operation in Electric Vehicle Charging Stations" Energies 14, no. 5: 1370. https://doi.org/10.3390/en14051370

APA Style

Oliveira Farias, H. E., Sepulveda Rangel, C. A., Weber Stringini, L., Neves Canha, L., Pegoraro Bertineti, D., da Silva Brignol, W., & Iensen Nadal, Z. (2021). Combined Framework with Heuristic Programming and Rule-Based Strategies for Scheduling and Real Time Operation in Electric Vehicle Charging Stations. Energies, 14(5), 1370. https://doi.org/10.3390/en14051370

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop