1. Introduction
With the entry into force of the Paris Agreement in November 2016, many countries are accelerating their decarbonization efforts based on international agreements. On the other hand, the Intergovernmental Panel on Climate Change (IPCC) special report in 2018 pointed out that, in order to keep global warming below 1.5
C, CO
emissions need to be significantly lower than the original target and achieve carbon neutrality in 2050–2060 [
1], which has led to further efforts to decarbonize the power sector in many countries. For instance, the Glasgow Climate Pact at the 26th session of the Conference of the Parties (COP26) to the United Nations Framework Convention on Climate Change in November 2021 calls for all parties to work towards a transition to a low emission energy system, “including accelerating efforts towards the phasedown of unabated coal power” [
2].
The 2050 Net Zero Scenario released by the International Energy Agency (IEA) in 2021 states that, in addition to the elimination of inefficient coal-fired power generation by 2040, renewable energy sources must be expanded to 90% of the electricity generated (including 70% from solar and wind) for the achievement of the scenario [
3]. To realize sustainable development while reducing a carbon footprint, renewable energy moreover becomes important. In particular, Japan’s Sixth Strategic Energy Plan calls for PV capacity to play an important role as a low-carbon power source in the future power system, as PV capacity accounts for a large percentage of VRE in Japan’s power supply mix planned for 2030 [
4]. (PV accounts for 14–16% within 36–38% of renewable energy sources as shown in
Figure 1).
However, PV is an inverter-based resource (IBR), and there is a concern about the reduction of grid inertia (deterioration of frequency stability against contingency) with the increase of their installation rate [
6,
7,
8]. For example, in a system with a large number of synchronized inertia, the Rate of Frequency Change (RoCoF) is suppressed, which means that there is sufficient time before generators supply the governor response. On the other hand, in a power system with little inertia, the large RoCoF may cause the system to deviate from the allowed range of frequency change before the injection from generators, and in the worst case, IBRs and synchronous generators may dissociate one after another, resulting in a blackout.
In order to ensure the frequency stability of power systems with high IBR implementation rates, the following major approaches exist:
Adding inertia such as a synchronous condenser;
Increasing the allowable range of frequency fluctuation in the system;
Providing fast frequency control (FFC) ancillary service from IBRs.
Introducing additional inertia with a synchronous condenser is considered to be a simple and effective approach but has the disadvantage of high equipment cost. The second approach corresponds to the sophistication of the fault ride through (FRT) function of IBRs, but this approach alone has its limitations. To deal with significant frequency fluctuations with FRTs, the hardware must be designed to withstand overcurrents, which can be very costly. With regard to the third approach, operating IBRs as a regulating power source is considered to be one of the effective ways to offset their disadvantages, as IBRs are characterized by their ability to provide very fast output regulation compared to the governor’s conventional frequency response while reducing grid inertia. For example, Hoke et al. showed that the fast frequency compensation by the inverter systems with PV is effective in stabilizing the grid frequency in the low-inertia system on Oahu. [
9]. In addition, the IEA has also organized the grid interconnection requirements for distributed energy resources (DERs) with classifying four stages according to their penetration, and they assume that the technical requirement for DERs includes the low power operation for supplying reserve power and autonomous adjustment function for system frequency and voltage in a third-fourth stage with high penetration [
10].
As an FFC by IBRs, in addition to the frequency droop control, recent researchers have focused on the implementation of pseudo-inertia to suppress RoCoF. IBRs with this function, called Virtual Synchronous Machine (VSM) or Virtual Synchronous Generator (VSG), are expected to contribute to resolving the technical constraint of the inverter penetration (referred to as VSMs in this paper).
Some approaches have been proposed to implement the pseudo-inertia function of the VSM. One is to impose a first order lead–lag unit on the droop control [
11], and another is to emulate a synchronous generator with the controller of the IBR [
12]. The latter approach is unique in that a virtual rotor frequency is stored and used as an internal signal in the control system, where various topologies have been proposed, including KHI topology [
13], synchronverter topology [
14,
15], ISE Lab topology [
16,
17], VISMA topology [
18,
19,
20], universal VSM topology [
21], etc. (Refs. [
22,
23,
24] are detailed as recent reviews.) However, pseudo-inertia by VSM is a function reproduced in software, and in order for the emulated pseudo-inertia to trigger the actual output compensation (in particular, the operation of increasing output against frequency decrease), energy resources which correspond to the kinetic energy of the synchronous generator must be reserved by the IBR side.
Such alternative energy can be guaranteed by the following options:
Use of kinetic energy inside IBRs, such as turbine blades;
Use of fast-responding energy storage systems (ESSs) such as batteries and capacitor banks;
Reserve capacity from the IBR source’s headroom.
In the case of wind power, the turbine blades function as inertial bodies, making them a practical option as a virtual inertial energy resource with VSM. However, this approach cannot be adopted for PV, which is one of VRE’s main forms of power generation. The second approach of harnessing Energy Storage is one of the effective approaches, but it is burdened by additional costs. As for the third approach, particularly during peak times of PV output in low-load periods (e.g., consecutive holidays), it is necessary to curtail PV output due to the system’s inertial constraints; setting reserve power in the curtailment (headroom) could translate the opportunity loss of PV generation into system value.
The provision of reserve power through PV headroom was examined by CAISO, First Solar, and the National Renewable Energy Laboratory in 2016 at a mega solar facility in California, and its effectiveness is demonstrated [
25]. When utilizing headroom, two points are important: the design of the control system and determination of reserve capacity. As a review, Dreidy et al. [
26] gave a comprehensive review of frequency control of the PV system utilizing headroom. Most of them are achieved by operating PV at a voltage higher than the voltage of maximum power point (MPP) and adjusting the PV operating voltage according to the frequency deviation. (This approach is sometimes referred to as ‘de-loading’.) In addition, determining the appropriate reserve capacity is also important to achieve both grid stability and PV generation revenue, and machine learning-based methods such as neural network and random forest were recently proposed [
27,
28].
Regarding the study of PV-powered VSMs (hereafter referred to as PV-VSMs), those supported by ESSs are vigorously researched by many researchers [
29,
30]. (Recent works of them are referred to in [
31,
32].) On the other hand, several studies focus on the headroom-based VSMs. Ding et al. proposed a voltage limiting method and adaptive tuning of simulated inertia parameters for stable PV-VSM operation without ESS [
33]; Feldmann and de Oliveira proposed an adaptively controlled PV-VSM for supporting a black start with utilizing headroom [
34]; Zhang et al. proposed the headroom-based PV-VSM control method with multiple PV inverters’ cooperative control [
35]; Yan et al. proposed the methodology of the adaptive switching control between maximum power point tracking mode and VSM mode according to the remaining capacity from PV maximum power [
36]; Jietan et al. proposed synthetic inertia and droop controller with shifting the operating point from MPP [
37].
The provision of pseudo-inertia by PV power sources is an important option for future power systems, and therefore it is important to analyze the operational feasibility of PV-VSM with headroom as virtual inertial energy. However, to the authors’ knowledge, there are few studies that have analyzed PV-VSM in power systems with high IBR ratios in a detailed model (through such as an electromagnetic transient program), including the interaction with the system, except for [
34]. It should be noted that, although a detailed analysis based on a 60th order model was performed in [
34] for a PV-VSM connected to the grid with a 50% IBR installation rate, their study simulated a black start situation and did not include the contingency and solar radiation ramp variations during grid operation.
In this paper, a circuit analysis by PSCAD/EMTDC (one of the tools for electro-magnetic transients program) with a two-generator system model was carried out with the aim of extracting the issues involved in a PV-VSM with headroom control, and the following findings were obtained:
If the headroom of the PV-VSM is insufficient for the required FFR output, PV-VSMs without adequate control of the upper output limit (output limiter) will become unstable in operation. Note that insufficient headroom can be caused by solar radiation fluctuations as well as frequency fluctuations.
The introduction of output limiters to PV-VSMs with maximum power estimation can prevent PV-VSM instability due to a lack of headroom or solar radiation fluctuations.
However, in case the PV-VSMs’ planned generation is high for their headroom, there is a risk of grid instability due to reduced solar radiation. The instability is caused by PV-VSMs being in output-specified control mode (Grid Follow) due to reduced headroom; that is, estimated PV-VSMs’ virtual energy disappears and causes more imbalance. Consequently, insufficient Primary Frequency Response (PFR) from the synchronous machine becomes impossible to compensate rapid frequency reduction by insufficient grid inertia. Therefore, care must be taken to cope with reduced solar radiation during operation of the reserve power supply by the headroom.
This paper is organized as follows:
Section 1 describes the background of the study.
Section 2 describes the simulation model used in the analysis of this paper. In
Section 3, we simulate the case of insufficient headroom in the FFR of the PV-VSM, and discuss the VSM control problems caused by the absence of inertial energy and how to solve them by using a power limiter. In
Section 4, we describe the PV-VSM with output limiting control based on headroom estimation, simulate the system under the assumption of solar irradiance ramp fluctuation and load step-changing, and discuss the issues to be addressed when operating the PV-VSM in the grid.
Section 5 summarizes the conclusions.
3. Simulation of the Step Changing Load Power Fluctuation
In order to verify the behavior of the PV-VSM in situations where the headroom is insufficient for the required regulation of the power supply due to grid disturbances, simulations are performed by connecting two different modules (PV-L, PV-S) with varying PV capacities in each case shown in
Table 4 (12 patterns in total). Each case corresponds to a situation where 1.7% of the load active power at a given time (1% of the base power of the load) increases or decreases in steps on a grid with IBR penetration set at 25%, 50%, and 75%.
The results of the simulations are shown in
Figure 7,
Figure 8,
Figure 9 and
Figure 10. In each figure, the time axis represents the elapsed time after the step change in load active power.
In
Figure 7, it can be seen that, in the case of decreasing load active power (Case2, Case4, Case6), the PV- VSM operates to suppress the active power output to eliminate the imbalance between generation and supply in the grid, regardless of the PV capacity. As the penetration of the PV-VSM increases, the oscillation of the effective power tends to subside in a shorter time, and the frequency of the synchronous generator also represented in
Figure 7 shows that the oscillation of the frequency can be suppressed in a shorter time, regardless of the decrease in inertia. The same tends to be true for the upward output power regulation if the PV source has sufficient capacity. In the simple 1st order transfer function from the swing equation, the time constant is given by
, which corresponds to 0.28 and 0.5 for the synchronous generator and PV-VSM, respectively. At first glance, the time constant of the synchronous generator may appear to be smaller than that of the PV-VSM, but, because the synchronous generator is driven by the turbine, mechanical constraints require a longer time to adjust the output by the governor. IBRs are not subject to these constraints, which allows for fast output adjustment, and thus the increase in IBR penetration allows frequency oscillations to be suppressed in a shorter period of time.
For the cases where the headroom (maximum power) of the PV source is insufficient for the required regulating power (Case1:PVS, Case3:PVS and Case5:PVS), it was confirmed that the system became unstable along with the instability of the PV-VSM operation. From
Figure 8 and
Figure 9, it can be seen that the secondary voltage of the DC/DC converter (the DC side voltage of the inverter) decreases with the imbalance of the input and output power to the capacitor in the destabilized cases. In the control algorithm of PV-VSM, the output voltage command value to the PWM controller is adjusted to increase or decrease the output current in response to changes in the electric angular frequency at the point of interconnection regardless of the PV source capacity. Therefore, the reason for the instability of the operation of the PV-VSM is that the PV-side output power is insufficient to maintain the DC-side capacitor voltage, while the inverter output power has increased due to the decrease in the frequency at the point of interconnection. In addition, it can be seen from
Figure 10 that, in the destabilization case, the operating point of the PV power supply moves to the short circuit side after moving to the maximum power point. This means that, if the PV-VSM is operated without a sufficient margin for the maximum output power of PV, there is a possibility of losing the power supplied by the PV-VSM to the grid when contingency occurs. Therefore, to prevent such unstable operation of the PV-VSM, it is necessary to ensure an appropriate margin for the maximum power or to introduce a limiter in the control system.
Ref. [
36] has exemplified a few simulation results for which the lack of maximum power of the source makes the VSM unstable. This simulation reinforces their result, which is an important issue for PV-VSMs.
In the next section, the impact of solar radiation fluctuations and load fluctuation on the grid is analyzed in the situation where measures to add limiters are implemented in the PV-VSM.