1. Introduction
Nowadays, electric power is very significant in subsistence, including communication, transportation, education, etc. Due to the growth in electric power demand, the Ministry of Energy in Thailand and the Electricity Generating Authority of Thailand (EGAT) prepared the Power Development Plan 2018 (PDP 2018) [
1] to plan sufficient power generation for power demand growth and strengthen the country’s energy security. Moreover, the increasing demand for electricity affects transmission system operations. Thereby, transmission line expansions are required to support the increases in power generation and demand in the future. The TEP has been extensively researched in recent years. Typically, TEP problems are concerned with the reliability and security of power systems.
In addition, the Ministry of Energy created the Alternative Energy Development Plan 2018 (AEDP 2018) [
2] to promote electricity generation from renewable energy resources such as solar PVs and wind turbine generators. This plan will encourage the use of renewable energy to generate electricity instead of fossil fuels. However, renewable energy resources are uncertain in terms of electricity generation. This is because electricity generation from renewable energy depends on the weather and the environment, which are difficult to control and predict. The uncertainty of renewable energy can impact transmission system operation. Additionally, many research works studied power system operation and control when uncertain generations of renewable energy resources were considered. For example, reference [
3] proposed the sampled memory-event-triggered fuzzy to investigate the load frequency control issue when wind power systems penetrate. The proposed method led to mitigating measurement outliers and transmission delays. Besides, an adaptive memory-event-triggered mechanism combined with Takagi–Sugeno (T-S) fuzzy wind turbine systems was proposed to control the uncertainty of wind power generation and reduce the frequency of data communication. An adaptive memory-event-triggered mechanism was presented to select the “necessary” control signal [
4]. These works were proposed to deal with the uncertainty of renewable energy resources and emphasize controlling the system in the short term. However, the TEP is usually long-term, which relies on forecasting to deal with the uncertainty of renewable energy resources. Hence, it is significant to consider the uncertainty of renewable energy in TEP. The primary motivation of this work is to expand the transmission lines to support the increases in electricity demand and uncertainty of solar PV generation so the system can operate without any violation of power system constraints.
The TEP is important in power system research and has been extensively studied in recent years. Commonly, TEP problems are concerned with the reliability and security of power systems [
5]. Reference [
6] proposed developing TEP methods and problem formulations for planning and compiling the modeling decisions and solutions for the TEP problem. Research work in reference [
7] reviewed the TEP research, which includes information on the TEP problem such as modeling, solving methods, reliability constraints, distributed generation in TEP, etc. Reference [
8] presented an outline literature review of the TEP research in more than 140 recent articles, which include literature review insights, the identified gap for guidelines on the TEP problem, and methods for solving TEP. In recent years, Generation Expansion Planning (GEP) and TEP have been extensively carried out. Reference [
9] presented comprehensive reviews of GEP and TEP problems; for example, modeling, solving methods, TEP with reliability criteria, TEP with distributed generation, TEP with various electricity markets, etc. Reference [
10] presented some challenges with the security-constrained TEP; these challenges include deregulation, uncertainties for the security-constrained transmission expansion planning (SCTEP), decision dynamics, a multi-objective problem, a power flow model, integrated planning with natural gas systems, High-Voltage Direct-Current (HVDC), solution methods, the selection of candidate lines, and the N-1 security criterion. Research work in reference [
11] presented the TEP problem, which includes information about the solution method, the treatment of the planning horizon, and considering the electricity sector restructuring. As mentioned above, this paper integrates the comprehensive reviews of the TEP problem so that the guidelines for solving transmission planning can be provided.
For the model for solving the TEP problem, the AC power flow model and the DC power flow model are usually applied as presented in the following references. The TEP problem is solved using the AC power flow model [
12,
13,
14]. The TEP problem is solved using the DC power flow model [
12,
15,
16]. The DC power model is simple and only considers real power, while the AC power flow model considers both real and reactive powers. However, the AC power flow model consumes a lot of computational time, but it is a full model that is usually adapted to the actual system. In conclusion, applying the power system with the AC power flow model is necessary for the planning because the AC power flow model considers both real and reactive powers, which conforms to the actual power system operation. For the planning horizon, there are two types of TEP planning horizons, which are static TEP and dynamic TEP. The static TEP considers only one time for selecting the equipment of the planning horizon. On the other hand, the dynamic TEP considers several sub-periods for pre-selected equipment. As mentioned above, the dynamic TEP can provide the optimal solution for long-term planning, but it is complex and consumes a lot of computational time. Therefore, the static TEP approach is employed for this work. References [
17,
18,
19] present the static TEP method to solve the TEP problem. In addition, the dynamic TEP method to solve the TEP problem was proposed in references [
20,
21,
22].
Various approaches have been developed to solve the TEP problem. Generally, there are two main algorithms for solving TEP, consisting of mathematical and meta-heuristic methods. The mathematical method can find the accurate optimal solution with low computation time. However, it is necessary to convert the power flow equations into a mathematical optimization model, which is complicated. Moreover, because the power system model has to be transformed into linear and nonlinear equations, the mathematical method can only be used for the static approach, and the dynamic approach such as stability analysis cannot be performed. In addition, the advantage of meta-heuristic methods is very straightforward. It is not necessary to convert complex power flow equations into a mathematical optimization model. Although the meta-heuristic methods take a long time to compute, they can find optimal and sub-optimal solutions for large systems. Additionally, this method can also be used for static and dynamic approaches [
7,
8]. As mentioned above, this paper applies the meta-heuristic method to solve the TEP problem. For the reason that the meta-heuristic is one of the methods that has the potential to find the optimal solution within feasible spaces, it is suitable to solve the complex problem of the TEP task. The mathematical methods for the TEP problem were proposed in references [
12,
16,
18,
23,
24,
25]. Furthermore, the meta-heuristic methods for the TEP problem were proposed in reference [
26], which include a Genetic Algorithm (GA), Orthogonal crossover-based Differential Evolution (OXDE), Grey Wolf Optimizer (GWO), Moth–Flame Optimization (MFO), Exchange Market Algorithm (EMA), Sine Cosine Algorithm (SCA) optimization, and Imperialistic Competitive Algorithm (ICA). Moreover, some examples that have been applied to solving the TEP problem were presented: Genetic Algorithm (GA) [
25,
27], Tabu Search (TS) [
28], Particle Swarm Optimization (PSO) [
22,
29], Differential Evolution (DE) [
30,
31] and Imperialist Competitive Algorithm (ICA) [
32].
Machine learning is a modern method for forecasting power system uncertainties. Furthermore, to reduce the uncertainties associated with the renewable energy used in TEP, the forecast for renewable energy uncertainties was considered in conjunction with transmission planning. Commonly, renewable energy sources are widely used for alternative electricity generation, especially solar PV generation. Furthermore, the trend of its installation cost continuously decreases. The Ministry of Energy in Thailand supports the increasing power generation of solar PV [
2]. Thus, solar PV generation is considered in this work. Nowadays, machine learning is increasingly being used to forecast the generation of solar PV. An overview of the machine learning approach used in forecasting solar radiation to forecast solar PV generation was presented [
33]. In addition, a comprehensive review of direct forecasting of PV power generation and optimization of the forecasting model were proposed [
34]. Reference [
35] proposed a comprehensive review of different forecasting solar PV techniques, including impact factors affecting solar PV forecasts and matrices to evaluate the forecast model. Among all forecasting models, the LSTM model is one of the most popular models for time series data prediction and is an appropriate method for forecasting solar PV generation. The LSTM model for forecasting solar PV was proposed in references [
36,
37,
38,
39,
40]. As mentioned above, this paper employs the LSTM model for the prediction of solar radiation combined with the TEP to enhance the performance of solving the TEP problem.
In order to achieve the mentioned gap in the previous research works, this paper proposes a novel static optimization for TEP with the uncertainties of solar PV. The objective functions are to minimize the investment cost of new transmission lines and the operating cost. Additionally, this paper proposes a robust model for solar radiation prediction to estimate power generation and reduce the uncertainties of solar PV generation in the TEP problem. The major contributions of this work are summarized as follows:
In order to obtain the optimal solution of TEP, this paper introduces the BDE algorithm to solve the TEP problem because the BDE algorithm has already been proven to be an accurate convergence, simple structure, and robust method for many optimization problems [
41].
This paper proposes a novel TEP combined with the LSTM model for forecasting solar radiation to deal with the uncertainty of solar PV generation. The proposed method leads to the increased performance of TEP when compared with TEP without solar PV consideration, conventional TEP, and TEP with statistical solar radiation.
This paper is organized as follows.
Section 2 presents details of the TEP model, after which the model of solar PV generation is expressed in
Section 3. The TEP method using the BDE algorithm is proposed in
Section 4.
Section 5 demonstrates the simulation results and provides a discussion. Finally,
Section 6 is the conclusion of this work.
2. TEP Model
This section presents the formulation of the TEP problem, which includes the objective function and constraints. The target of TEP is to install new transmission lines to support the increase in demand and generation in the future with the minimum total system cost.
Furthermore, this paper considers case studies of TEP consisting of TEP without solar PV consideration and TEP with solar PV consideration. For the TEP without solar PV consideration, the existing transmission system with forecasted demand and forecasted generation from the conventional power plants is used. For the TEP with solar PV consideration, the existing transmission system with forecasted demand, forecasted generation from the conventional power plants, and the forecasted solar radiation for solar PV generation are used.
The objective function and constraints are presented in Equations (1)–(7) as follows [
29]:
where
is the total system cost at time
t (M
$),
is the investment cost of the new transmission line at time
t (M
$),
is the operating cost of generation at time
t (M
$),
t and
T are the indices of the initial and final times of the target year of planning (hour).
Moreover, the minimization of the above two objectives under system operation constraints can ensure a solution without any violations for all scenarios. The operation constraints used in this work can be formulated by using the following equations [
29,
42]:
The constraints of active power and reactive power generations:
The constraint of bus voltage:
The constraint of the apparent power flow of each transmission line:
where
and
are active power and reactive power generations at bus
i, respectively.
and
are active power and reactive power demands at bus
i, respectively.
is the number of buses.
and
are voltages at bus
i and
j, respectively.
is the conductance between bus
i and
j.
is the susceptance between bus
i and
j.
is the voltage angle between bus
i and
j.
and
are the minimum and maximum limits of active power generations at bus
i, respectively.
and
are the minimum and maximum limits of reactive power generations at bus
i, respectively.
and
are the minimum and maximum limits of voltage at bus
i, respectively.
is the apparent power flow of transmission lines connecting between bus
i and
j.
is the maximum limit of apparent power flow of transmission lines connecting between bus
i and
j.
4. Proposed Methodology
In this section, the proposed TEP is solved using a meta-heuristic method. Even with the high computation time of the method, the advantage of meta-heuristic methods is that they are very straightforward and it is not necessary to convert power system equations into the optimization model. Furthermore, a meta-heuristic method is particularly suited to solving complex problems. The Differential Evolution (DE) algorithm is widely used to solve the optimization planning and TEP problems [
28,
29]. This algorithm is straightforward, powerful, simple, and converges accurately with minor control variables. Nevertheless, the original DE algorithm cannot be used in the binary domain, which is the specialty of the TEP problem. Consequently, this paper selects the BDE algorithm to solve the optimal TEP problem. Commonly, the installation of new transmission lines is selected from transmission line candidate data using randomization in binary [0,1]. Moreover, the proposed BDE algorithm with parameter adaption in the binary mutation process can improve the algorithm’s performance [
41]. The proposed optimal TEP method using the BDE algorithm is presented in
Figure 2. The process of the TEP method using the BDE algorithm can be described below.
Step 1: Input data consisting of the existing IEEE 24 bus system, transmission line candidates, forecasted demand, and forecasted solar radiation.
Step 2: Set parameters and conditions for the BDE algorithm, consisting of the number of iterations, number of decision variables, number of populations, Scaling Factor (F) and Crossover Rate (CR).
Step 3: Initialize a binary set randomly, used to select the installation of new transmission lines to the IEEE 24 bus system. In addition, the initial F and CR are set to be 0.75.
Step 4: Run Optimal Power Flow (OPF) to evaluate the operating cost and check the constraints for each population.
Step 5: Generate a new population using the mutation process. Moreover, adjust
F and
CR for each population as described in Equations (13) and (14).
where ^ is the XOR operator, & is the AND operator,
is the mutation of
k-th population in
g-th generation,
is the best value in the population in
g-th generation,
is the dimension of the objective function,
is the difference between two populations in the
p-th component and
is initialization at
p-th component of
k-th population in
g-th generation.
where
and
are the mean values of
F and
CR, respectively.
normalrnd is a variable used for randomizing in normal distribution function which has
mF and
mCR as the mean while the standard deviation is fixed as 0.05.
is the scaling factor value of the
k-th population in
g-th generation and
is the crossover rate value of the
k-th population in
g-th generation.
Step 6: Generate a new population using the crossover process which can be described in Equation (15).
where
,
are the binary mutation and crossover rate parameters at
p-th component of
k-th population in
g-th generation, respectively.
is a randomly chosen index
.
Step 7: Run OPF to evaluate the operating cost and check the constraints for each population generated by the crossover process.
Step 8: Select the best population for the next generation as presented in Equation (16).
where
,
are the initialization and crossover vectors of the
k-th population in
g-th generation, respectively.
is the best population for the next generation.
Step 9: Collect the best solution of the population in each iteration for comparing with the best solutions of other iterations.
Step 10: If the maximum number of iterations is reached, the process is stopped and the best solutions are saved; otherwise, go to step 4.
5. Simulation Results and Discussion
In this section, the objective function of TEP is the minimization of the investment cost of new transmission lines and the operating cost of generation. All simulations are operated on the Intel(R) Core (TM) i7-7700 CPU @ 3.60 GHz with 8 GB RAM. The experiment is run in MATLAB R2021a using the MATPOWER tool [
46]. The proposed algorithm is applied to the IEEE 24 bus system, which is provided in reference [
47]. This system contains 24 buses, 38 transmission lines, and 33 generation units. The demand data considered in this paper is greater than three times the original demand [
28]. The installation of solar PV generation is defined to 25% of the peak demand. Solar PV generation units are installed on buses 10, 13, 14, 15, and 18, which have the five highest demands. This paper proposes the TEP combined with the LSTM model for forecasting solar radiation to deal with the uncertainty of solar PV generation. In this work, TEP is solved using the BDE algorithm. The parameters of BDE are set as follows. The number of populations is 20, the number of decision variables is 41, and the maximum number of iterations is 50. 41 transmission line candidates, which are presented in
Table 2 [
32], can be selected for installation in the test system. The accuracy of forecasted solar radiation is investigated by RMSE. The accuracy of forecasted solar radiation and the calculation time of the LSTM model are presented in
Table 3. From the results in
Table 3, the RMSE value is close to 0, which indicates that the LSTM model could predict well. Moreover, the forecasted solar radiation compared with the actual solar radiation of Thailand in 2020 is presented in
Figure 3. The result of the forecasted solar radiation from the LSTM demonstrates that the obtained solar radiation values are close to the actual solar radiation of Thailand in 2020, which can be implied by the RMSE (0.1211). Consequently, the LSTM model is used to forecast solar radiation in the target year of planning for the proposed TEP method, while the solar radiation of Thailand in 2020 is used in the planning for the TEP with statistical solar radiation.
Additionally, the TEP results are studied for two cases, including the TEP without solar PV consideration and the TEP with solar PV consideration, which are presented in
Section 5.1 and
Section 5.2, respectively. Finally, the results from the two cases are discussed in
Section 5.3.
5.1. The TEP without Solar PV Consideration
To ensure that the proposed method for solving TEP can discover the optimal solution, the TEP without solar consideration is investigated by using the BDE algorithm compared with the ATS algorithm. This case is carried out by taking into account the existing system, which is the IEEE 24 bus system, and considering the peak demand of the system without solar PV generation. The result of TEP without solar PV generation is presented in
Table 4. There are 18 transmission lines installed in the system. The total system cost is 1551.74 M
$, which is composed of 770 M
$ from the investment cost and 781.74 M
$ from the operating cost.
In addition, the result of TEP without solar PV consideration is demonstrated when compared with TEP solved using Adaptive Tabu Search (ATS) [
28]. From
Table 4, the result of TEP without solar PV consideration shows that when compared with the TEP using the ATS method. The total cost obtained by the BDE algorithm is lower than the total cost provided by the ATS algorithm. Therefore, it confirms that the TEP without solar PV consideration utilizing the BDE algorithm can discover the optimal solution.
5.2. The TEP with Solar PV Consideration
To verify the contribution of the proposed method, there are three TEP methods with solar PV consideration to be compared. The first is the conventional TEP, which uses the maximum and minimum values of demand and solar PV generation as the considered scenarios for planning. The second is the TEP using hourly data of the solar radiation of Thailand in 2020 and the target year’s demand, called the TEP with statistical solar radiation. Lastly, the proposed method is the TEP combined with the LSTM model used to forecast the target year’s solar radiation. Furthermore, the hourly target year’s demand and the hourly target year’s solar radiation are taken into account in the proposed method. The result of these TEP methods with solar PV consideration can be presented as follows.
5.2.1. The Conventional TEP
Conventionally, in order to achieve a solution that ensures the security of the power system operation, the four worst-case scenarios consisting of maximum demands and maximum solar PV generations, maximum demands and minimum solar PV generations, minimum demands and maximum solar PV generations, and minimum demands and minimum solar PV generations are considered in the TEP problem [
48]. The four worst-case scenarios defined as conventional TEP are shown below.
Scenario 1: maximum demand combined with minimum solar PV generation.
Scenario 2: maximum demand combined with maximum solar PV generation.
Scenario 3: minimum demand combined with minimum solar PV generation.
Scenario 4: minimum demand combined with maximum solar PV generation.
The result of conventional TEP is summarized in
Table 5. There are 19 transmission lines selected to be installed in the system. The total system cost is 1567.3 M
$, which is composed of 859 M
$ from the investment cost and 708.3 M
$ from the operating cost.
5.2.2. The TEP with Statistical Solar Radiation
The TEP with statistical solar radiation is performed by considering the hourly demand and the hourly statistical solar radiation of Thailand in 2020. The result of the TEP with statistical solar radiation is summarized in
Table 6. There are 20 transmission lines selected to be installed in the system. The total system cost is 1651.4 M
$, which is composed of 900 M
$ from the investment cost and 751.4 M
$ from the operating cost.
As mentioned above, the statistical solar radiation in Thailand in 2020 is utilized to estimate solar PV generation. For the reason that the solar radiation used in this case is not a value that will occur in the next 10 years, the obtained solutions may not be optimal. However, this problem can be mitigated when the highly accurate values of forecasted solar radiation for the next 10 years are utilized. Employing the LSTM, which is guaranteed by the training results in
Table 3, to forecast solar radiation for the next 10 years along with TEP optimization should increase the opportunity for discovering the optimal solution.
To obtain the total system cost close to its actual value, the selected transmission line candidates from the result of TEP with the statistical solar radiation method are added to the test system under the forecasted solar radiation obtained from the LSTM. The simulation results show that the operating cost is decreased from 751.4 M
$ to 715.8 M
$, as noticed from the result in
Table 7. The total system cost is 1615.8 M
$, which is composed of 900 M
$ from the investment cost and 715.8 M
$ from the operating cost.
5.2.3. The Proposed TEP with the LSTM for Forecasting Solar Radiation
The proposed TEP with the LSTM for forecasting solar radiation is performed by considering the hourly demand and the hourly forecasted solar radiation obtained from the LSTM model for the target year planning. The result of the proposed TEP with the LSTM model for forecasting solar radiation is summarized in
Table 8. There are 18 selected to be installed in the system. The total system cost is 1468.46 M
$ which is composed of 814 M
$ from the investment cost and 654.46 M
$ from the operating cost.
As mentioned above, the TEP with statistical solar radiation and the proposed TEP with the LSTM model for forecasting solar radiation differ in the solar radiation value utilized. Therefore, two cases are compared to discover the difference. The result of the proposed TEP with the LSTM model for forecasting solar radiation can reduce the investment cost, operating cost, and total system cost by 9.55%, 8.57%, and 9.12%, respectively, when compared with the costs obtained by the TEP with statistical solar radiation when using the forecasted solar radiation from the LSTM.
The comparison of the TEP with statistical solar radiation and the proposed TEP with the LSTM model for forecasting solar radiation is presented in
Table 9. The transmission lines obtained from the proposed TEP with the LSTM model for forecasting solar radiation and the solar PV installation are illustrated in
Figure 4.
Figure 4 presents the installed transmission lines and installed solar PV generation units for the IEEE 24 bus system.
5.3. Discussion
According to the results of the above two studied cases, case 1 has new 18 installed transmission lines for the TEP without solar PV consideration, case 2 has new 19 installed transmission lines for the conventional TEP, new 20 installed transmission lines for the TEP with statistical solar radiation, and new 18 installed transmission lines for the proposed TEP with the LSTM model for forecasting solar radiation.
As mentioned above, the difference in investment costs is minor in these cases. Nevertheless, the operating cost of the proposed TEP with the LSTM model for forecasting solar radiation is significantly lower than the TEP without solar PV consideration, the conventional TEP, and the TEP with statistical solar radiation. This is because, during the planning process, the proposed TEP with the LSTM model for forecasting solar radiation considers the forecasted solar radiation with high accuracy in the planning, which can reduce the operating cost of power generation. Consequently, the total system cost of the proposed TEP is less than that of the TEP without solar PV consideration, the conventional TEP, and the TEP with statistical solar radiation. The result of the proposed TEP method shows the optimal solution plan with the minimum total system cost. In addition, a precise LSTM model can predict the solar radiation in the target year close to its statistical solar radiation value according to the RMSE value as presented in
Table 3. Hence, it can increase the possibility of planning with high system security and minimize the total system cost of TEP.
Furthermore, the comparison of the TEP with statistical solar radiation and the proposed TEP with the LSTM model for forecasting solar radiation is shown in
Table 9. The results show that the obtained result from the proposed TEP varies from the result obtained from the TEP with statistical solar radiation. When the proposed TEP with the LSTM model is employed, the system installing solar PV can advocate more output power of solar PV than the advocated output power of solar PV in the TEP with statistical solar radiation. Thereby, the proposed TEP can reduce the total system cost of TEP.
6. Conclusions
This paper proposes a novel TEP with the LSTM model for forecasting solar PV generation using the BDE algorithm. The solar radiation is forecasted using the LSTM model to estimate solar PV generation for the target year of planning. All simulations of TEP use the IEEE 24 bus system for a planning horizon of 10 years. The objective is to minimize the investment cost of new transmission lines and the operating cost of generators. In this paper, there are two case studies, including the TEP without solar PV consideration and the TEP with solar PV consideration. The TEP without solar PV consideration is carried out by taking into account the existing IEEE 24 bus system. Furthermore, peak demand is considered without solar PV generation. For the TEP without solar PV consideration, the BDE algorithm can reduce the total system cost by 10.98% compared with the TEP without solar PV consideration provided by the ATS algorithm. Consequently, it verifies that the TEP without solar PV consideration utilizing the BDE algorithm can discover the better optimal solution compared with utilizing the ATS algorithm.
For the TEP with solar PV consideration, three TEP methods consisting of the conventional TEP, the TEP with statistical solar radiation, and the proposed TEP with the LSTM for forecasting solar radiation are solved and compared. The conventional TEP is conducted by using the maximum and minimum values of the demand and solar PV generation, which are taken into account for planning. Then, the TEP with statistical solar radiation is performed by considering the hourly demand in the target year of planning and the hourly statistical solar radiation of Thailand in 2020. Finally, the proposed TEP with the LSTM for forecasting solar radiation is performed by considering the hourly demand in the target year of planning and the hourly forecasted solar radiation obtained from the LSTM model for the target year of planning. As mentioned previously, the difference in investment costs is minor in these cases. However, the proposed TEP with the LSTM model for forecasting solar radiation can support more output power of solar PV than the supported output power of solar PV in other cases, which can reduce the operating cost. Therefore, the total system cost of the proposed TEP is lower than the costs of TEP without solar PV consideration, conventional TEP, and TEP with statistical solar radiation. Moreover, an accurate LSTM model can predict solar radiation in the target year close to its statistical value. Furthermore, it can increase the potentiality of planning with high system security and reduce the total system cost of TEP.
Finally, the comparison of the TEP with statistical solar radiation and the proposed TEP with the LSTM model for forecasting solar radiation shows that the proposed TEP with forecasted solar radiation can reduce the investment cost, operating cost, and total system cost of transmission expansion by 9.55%, 8.57%, and 9.12%, respectively, when compared with the TEP with statistical solar radiation when using the forecasted solar radiation from the LSTM. To deal with the uncertain solar PV generation. It can be concluded that the proposed TEP with the LSTM is more appropriate than the TEP with statistical solar radiation. Moreover, future works should consider the LSTM model which has excellent forecasting capability to forecast electricity demand solar PV generation. This will fulfill the uncertain parameters forecast in the TEP. Finally, the system reliability and security of power system operation are very significant especially when uncertain generation from renewable energy sources is increased in the power system; thereby, with the increase in computer and software capabilities, reliability indices and the N-1 security criterion should be taken into account for TEP with uncertain generation from renewable energy sources in future works.