Reproducible Method for Modifying a Published Electricity Network Model for Transmission Expansion Planning
Abstract
1. Introduction
1.1. Transmission Expansion Planning Issues
1.2. Transmission Expansion Planning Models
1.3. Contributions
- Fully developed methodology for adapting a published standard power system model for transmission expansion planning research.
- Insider insights into transmission expansion planning methods in use today.
- Practical, step-by-step guidance through the proposed model updating process.
- Example open-access multi-format modified Nordic-32 model suitable for 2024 Swedish transmission expansion planning studies.
- The foundations of further academic research into improved methods of transmission expansion planning.
1.4. Structure of the Paper
2. Transmission Expansion Modelling Principles
2.1. Purpose of Transmission Expansion Planning Models
2.2. Data Flows for Transmission Expansion Planning
2.3. The Need for Modified or Updated Models
- In response to a connection application for a new connecting project above a certain size; or
- Through a regular (typically annual) process of assessing system requirements in general.
- When seeking to prove a new concept or technology in application to a transmission network, since full-scale experimentation is not possible; and
- To find and to share improved processes and approaches to solving transmission expansion planning problems.
3. Transmission Expansion Model Modification Process
3.1. Key Inputs to the Process
- Original model.
- Target-region planning standards, to inform:
- Contingency cases to include;
- Generation mix;
- Which demand scenarios (cardinal points of load curve) to include;
- Study scope (performance indices (PIs) of interest, e.g., circuit loading, voltage, angular stability…); and
- Performance limits for each PI.
- Statistics/publications from, or about, the target region, to infer information on planning standards where there is no published information.
- Demand data for the target region of interest.
- Reinforcement options and history in the target network.
3.2. Process Flowchart
3.3. Gathering All the Required Data
3.4. Updating the Model
3.5. Dealing with Non-Convergence of Loadflow
3.6. Identifying Performance-Limit Breaches for All Secured Events
3.7. Identifying Appropriate Network Reinforcements
- A new circuit;
- Upgrading voltage level, e.g., 130 kV or 220 kV to 400 kV;
- Reconductoring an existing circuit;
- Series capacitive compensation; and
- Reducing reactive power (Mvar) flows.
- Shunt static compensation;
- Shunt dynamic compensation;
- Revised generator reactive performance charts and limits;
- Revised busbar voltage targets and limits; and
- Revised transformer tap-changer limits.
- Reconductoring an existing circuit;
- Power flow control devices, including series capacitive compensation; and
- New circuits across cross-cuts/boundaries.
3.7.1. Reinforcing to Resolve Circuit Loadings
3.7.2. Reinforcing to Resolve Nodal Voltages
3.7.3. Reinforcing to Resolve Inter-Area Transfers
3.7.4. Cost Estimates for Reinforcement Options
- Upgrade voltage level in urban region, e.g., 220 kV to 400 kV, including tower replacement and some cabling: forecast cost GBP 142 m for 23 km Hackney to Waltham Cross 275 kV upgrade to 400 kV, so GBP 6.2 m per km [48]. (This may be considerably cheaper in rural areas if the same towers can be used and there are no cable sections along the route.)
- New 400 kV circuit: cost GBP 4 m per km [49].
- Reconductoring existing circuit, 232 circuit km Harker to Quernmore Tee 400 kV estimated GBP 100 m, so GBP 0.43 m per km [44].
- New series compensation on circuit: GBP 40 m per circuit [44].
- New power flow control devices on circuit: UK experience is of roughly GBP 7 m per circuit with latest technology, and earlier estimation from the USA suggests USD 100–160k per Mvar [50]. It heavily depends on the ratings required and technology deployed.
- Shunt passive (static) reactive compensation cost: USD 20–40k per Mvar, based on the fixed-series capacitor costs from [50], which can be expected to be similar. UK experience is in the region of GBP 3 m for a 225 Mvar 400 kV bank.
3.8. Estimating Connection Dates
4. Case Study: Modifying the Nordic-32 for Swedish Transmission Expansion Planning Studies
4.1. Scale of Changes from Circa 1990 to 2024
4.2. Assessing Compliance of the Network Against Nordic Planning Standards
4.3. Identifying Appropriate Network Reinforcements
4.3.1. Reinforcement to Resolve Circuit Loadings
4.3.2. Reinforcement to Resolve Nodal Voltages
4.4. Reinforcing the Nordic-32 to Meet Planning Standards with 2024 Data
4.4.1. Single Pass or Incremental Increase in Demand
4.4.2. Transformer Capacity Expansion
4.4.3. Generation Technology Mix
4.4.4. Load Scaling
4.4.5. Generation Dispatch
- Wind is considered to be non-dispatchable, and is either fully on or fully off, and is energised even with P = 0 MW;
- Nuclear is must-run;
- Hydro (all assumed to be reservoir-based); then
- Thermal (represents a mix of gas, oil, and interconnection).
4.5. Full Walkthrough of First Increment
4.5.1. Load Scaling
4.5.2. Generation Dispatch
4.5.3. Reinforcement to Resolve Circuit Loadings
4.5.4. Reinforcement to Resolve Nodal Voltages
- Generator busbars are set at the upper limit in the planning standard (1.05 pu, in this case).
- Load busbars are set to 1 pu.
- Busbars at substations that are at the receiving end of large flows are set at 60% between 1 pu and the upper voltage limit in the planning standard (1.03 pu).
- Busbars at the sending end of large flows are set to the upper limit (1.05 pu).
4.6. Subsequent Increments in Brief
- Use DC contingency analysis to achieve convergence and identify new circuit requirements.
- Use static generators to identify approximate reactive power requirements for converging AC loadflows.
- Use AC contingency analysis to identify final network-reinforcement requirements.
5. Discussion
5.1. Reflections on the Modification Process
5.1.1. The Role of the Planning Standards
5.1.2. The Role of Specific TSO Reinforcement Strategies
5.1.3. The Role of Land Planning
5.1.4. The Role of System Operational Strategy
5.2. Reflections on the Network That Resulted from This Process
5.3. Reflections on the Classic Transmission Expansion Planning Problem
5.4. Further Work
6. Conclusions
- Demonstrable compliance with planning standards, resulting in a model that is realistic to a specific region and its transmission design principles.
- Applicable to any published transmission-system test model.
- Applicable to any system study type for which planning standards define performance indices.
- Adaptable to different types of network reinforcement or national investment strategy.
- Repeatable, such that a series of research studies can follow the same method, and models can, for example, be updated with different years’ data or for different future scenarios.
- Auditable, such that there is no opportunity to strategically select model parameters that are not realistic, but which produce results that back up a hypothesis.
- Ethical, due to auditability and repeatability.
Author Contributions
Funding
Data Availability Statement
Conflicts of Interest
Abbreviations
CEGB | Central Electricity Generating Board |
ETYS | Electricity Ten-Year Statement |
HND | Holistic Network Design |
NESO | National Energy System Operator |
NGET | National Grid Electricity Transmission |
FACTS | Flexible AC Transmission |
PI | Performance Index/Indices |
SVC | Static Var Compensator |
TEC | Transmission Entry Capacity |
MW | Megawatt |
GW | Gigawatt |
MVA | Megavolt-ampere |
Mvar | Megavolt-ampere Reactive |
RMS | Root Mean Square |
NETS | National Electricity Transmission System |
SQSS | Security and Quality of Supply Standard |
SvK | Svenska Kraftnät |
TSO | Transmission System Owner/Operator |
TEP | Transmission Expansion Planning |
PTDF | Power Transfer Distribution Factor |
References
- International Energy Agency. Electricity Grids and Secure Energy Transitions, IEA, Paris. 2023. Available online: https://www.iea.org/reports/electricity-grids-and-secure-energy-transitions (accessed on 9 December 2024).
- United Nations Framework Convention on Climate Change. Technology and Policy Innovations for Emission Cuts in Heavy Industries Unveiled at COP29, UNFCC. Available online: https://unfccc.int/news/technology-and-policy-innovations-for-emission-cuts-in-heavy-industries-unveiled-at-cop29 (accessed on 9 December 2024).
- European Parliament; Council of the European Union. Regulation (EU) 2023/857 of the European Parliament and of the Council Amending Regulation (EU) 2018/842 on Binding Annual Greenhouse Gas Emission Reductions by Member States from 2021 to 2030. 1 April 2023. Available online: http://data.europa.eu/eli/reg/2023/857/oj (accessed on 5 June 2025).
- Karlsson, M. Sweden’s Climate Act—Its origin and emergence. Clim. Policy 2021, 21, 1132–1145. [Google Scholar] [CrossRef]
- Bollen, M.H.; Moreno-Muñoz, A. The power grid as part of a sustainable energy system. In Large-Scale Grid Integration of Renewable Energy Sources, 2nd ed.; IET Surveillance; Chapter 1; The Institution of Engineering and Technology: London, UK, 2024; pp. 1–31. [Google Scholar]
- Vendt, M.; Wallmark, C. Prestudy H2ESIN: Hydrogen, Energy System and Infrastructure in Northern Scandinavia and Finland, RISE Research Institutes of Sweden and Luleå University of Technology, Luleå, Sweden. 2022. Available online: https://energikontornorr.se/wp-content/uploads/2022/11/2022-Prestudy-H2ESIN-Project-report.pdf (accessed on 9 December 2024).
- Det Norske Veritas (DNV). Hydrogen Forecast to 2050: Energy Transition Outlook 2022, DNV, Oslo, Norway. 2022. Available online: https://www.dnv.com/focus-areas/hydrogen/forecast-to-2050/ (accessed on 9 December 2024).
- Zhong, J.; Bollen, M.H.; Rönnberg, S. Towards a 100% renewable energy electricity generation system in Sweden. Renew. Energy 2021, 171, 812–824. [Google Scholar] [CrossRef]
- Department for Energy Security and Net Zero and Ofgem. Connections Action Plan, The National Archives, London. 2023. Available online: https://assets.publishing.service.gov.uk/media/6581730523b70a000d234bb0/connections-action-plan-desnz-ofgem.pdf (accessed on 9 December 2024).
- International Energy Agency. Energy Technology Perspectives 2023, IEA, Paris. 2023. Available online: https://iea.blob.core.windows.net/assets/a86b480e-2b03-4e25-bae1-da1395e0b620/EnergyTechnologyPerspectives2023.pdf (accessed on 9 December 2024).
- National Energy System Operator. Transmission Works Register 19 November 2024, NESO Connections Publication Library. Available online: https://www.neso.energy/publications-library (accessed on 5 June 2025).
- Kraftnät, S. Grid Development Plan 2024–2033, SvK Reports and Referral Responses. 2024. Available online: https://www.svk.se/om-oss/rapporter-och-remissvar/ (accessed on 9 December 2024).
- National Energy System Operator. GB 36-Bus Electricity Transmission Network Model, NESO Strategic Planning Publication Library. Available online: https://www.neso.energy/publications/gb-36-bus-electricity-transmission-network-model (accessed on 5 June 2025).
- National Energy System Operator. ETYS documents and appendices, NESO Strategic Planning Publication Library. Available online: https://www.neso.energy/publications/electricity-ten-year-statement-etys/etys-documents-and-appendices (accessed on 5 June 2025).
- Mehmand, T.M. The Use of Dynamic Equivalents in the Representation of Nordic 32 and Siirtoverkkomalli Aimed at Transmission Capability Assessments. Master’s Thesis, Tampere University, Tampere, Finland, 2016. Available online: https://urn.fi/URN:NBN:fi:tty-201610264646 (accessed on 5 June 2025).
- CIGRÉ. Long-Term Dynamics Phase II—Final Report, WG 38.02.08, Study Committee C4, Technical Brochure 102, E-CIGRÉ, PARIS. 1995. Available online: https://www.e-cigre.org/publications/detail/102-long-term-dynamics-phase-ii-final-report.html (accessed on 5 June 2025).
- Muller, S. Development of Nordic 32 System Model and Performance Analysis Based on Real Operational Statistics. Master’s Thesis, Kungliga Tekniska Högskolan, Stockholm, Sweden, 2019. Available online: https://www.diva-portal.org/smash/get/diva2:1395253/FULLTEXT01.pdf (accessed on 5 June 2025).
- Munkhchuluun, E.; Meegahapola, L. Impact of the solar photovoltaic (PV) generation on long-term voltage stability of a power network. In Proceedings of the 2017 IEEE Innovative Smart Grid Technologies—Asia (ISGT-Asia), Auckland, New Zealand, 4–7 December 2017; pp. 1–6. [Google Scholar] [CrossRef]
- Tirtashi, M.R.S.; Samuelsson, O.; Svensson, J. Control strategies for reactive shunts to improve long-term voltage stability. In Proceedings of the 2013 48th International Universities’ Power Engineering Conference (UPEC), Dublin, Ireland, 2–5 September 2013; pp. 1–5. [Google Scholar] [CrossRef]
- Coteanu, A.; Gheorghe, S. Benefits of using SVC FACTS devices in power transmission systems. EMERG Energy Environ. Effic. Resour. Glob. 2023, 9, 120. [Google Scholar] [CrossRef]
- Kazme, H.Z.; Basumatary, K. Frequency Control Support in Low Inertia Power Grid by Energy Storage Systems: A Techno-Economic Analysis. In Proceedings of the 2022 IEEE International Conference on Power Electronics, Drives and Energy Systems (PEDES), Jaipur, India, 14–17 December 2022; pp. 1–6. [Google Scholar] [CrossRef]
- National Energy System Operator. National Electricity Transmission System Security and Quality of Supply Standard, Version 2.5, NESO Industry Information, Codes. Available online: https://www.neso.energy/industry-information/codes/security-and-quality-supply-standard-sqss/sqss-code-documents (accessed on 5 June 2025).
- National Energy System Operator. Transitional Offers, NESO Industry Information, Connections. Available online: https://www.neso.energy/industry-information/connections/transitional-offers (accessed on 5 June 2025).
- National Energy System Operator. Great Britain’s Connections Reform: Overview Document, NESO Industry Information, Connections. Available online: https://www.neso.energy/industry-information/connections/connections-reform (accessed on 5 June 2025).
- Dhamala, B.; Ghassemi, M. An Extra-High Voltage Test System for Transmission Expansion Planning Studies Considering Single Contingency Conditions. Electronics 2024, 13, 3937. [Google Scholar] [CrossRef]
- Dhamala, B.; Ghassemi, M. Smart Transmission Expansion Planning Based on the System Requirements: A Comparative Study with Unconventional Lines. Energies 2024, 17, 1912. [Google Scholar] [CrossRef]
- Dhamala, B.; Ghassemi, M. A Test System for Transmission Expansion Planning Studies. Electronics 2024, 13, 664. [Google Scholar] [CrossRef]
- Nordel. Nordic Grid Code. 2007. Available online: https://eepublicdownloads.entsoe.eu/clean-documents/pre2015/publications/nordic/planning/070115_entsoe_nordic_NordicGridCode.pdf (accessed on 26 September 2024).
- European Network of Transmission System Operators for Electricity (ENTSO-E). Commission Regulation (EU) 2016/631 of 14 April 2016 establishing a network code on requirements for grid connection of generators. In Official Journal of the European Union; C/2016/2001, OJ L 112; European Union: Brussels, Belgium, 2016; pp. 1–68. [Google Scholar]
- European Network of Transmission System Operators for Electricity (ENTSO-E). Commission Regulation (EU) 2016/1388 of 17 August 2016 establishing a Network Code on Demand Connection. In Official Journal of the European Union; C/2016/5239, OJ L 223; European Union: Brussels, Belgium, 2016; pp. 10–54. [Google Scholar]
- National Grid Electricity Transmission. National Grid Fast-Tracks Overhead Line Upgrade Project to Help Accelerate Connection Dates of 175 Clean Energy Projects, NGET Media Press Releases. Available online: https://www.nationalgrid.com/media-centre/national-grid-fast-tracks-overhead-line-upgrade-project-help-accelerate-connection-dates-175-clean (accessed on 5 June 2025).
- Shen, L.; Jiang, L.; Wang, Q.; Wen, Y.; Liu, T. Multi-Period Transmission Expansion Planning for Renewables-Rich Power Grid Enabling Transfer Capacity Enhancement of Hybrid AC/DC Interface. Energies 2023, 16, 2170. [Google Scholar] [CrossRef]
- National Energy System Operator. Transmission Entry Capacity (TEC) Register, NESO Connection Registers Library. Available online: https://www.neso.energy/data-portal/transmission-entry-capacity-tec-register (accessed on 5 June 2025).
- Energy Networks Association. National Grid Electricity Transmission (NGET), Innovation Project: Optimise Fault Infeed, NGET, SPEN, SSEN Expert Panel, Feb. 10, 2024, NIA2_NGET0053. Available online: https://smarter.energynetworks.org/projects/nia2_nget0053/ (accessed on 5 June 2025).
- National Energy System Operator. First Phase of Stability Pathfinders Delivered, NESO News. Available online: https://www.neso.energy/news/first-phase-stability-pathfinders-delivered (accessed on 5 June 2025).
- European Network of Transmission System Operators for Electricity (ENTSO-E). Future System Inertia 2, ENTSO-E. 23 February 2018. Available online: https://www.entsoe.eu/Documents/Publications/SOC/Nordic/2018/System-inertia.zip (accessed on 11 December 2024).
- Singh, S.N.; David, A.K. Congestion management by optimising FACTS device location. In Proceedings of the International Conference on Electric Utility Deregulation and Restructuring and Power Technologies, London, UK, 4–7 April 2000; Cat. No.00EX382;. pp. 23–28. [Google Scholar] [CrossRef]
- Bollen, M.H.; Chen, Y.; Etherden, N. Risk analysis of alternatives to N-1 reserves in the network. In Proceedings of the 22 nd International Conference on Electricity Distribution, Stockholm, Sweden, 10–13 June 2013. [Google Scholar]
- Hajeforosh, S.F.; Bollen, M.H.; Abrahamsson, L. Dynamic Line Rating Operational Planning: Issues and Challenges. In Proceedings of the 25th International Conference on Electricity Distribution, Madrid, Spain, 3–6 June 2019. [Google Scholar]
- Bollen, M.H.; Wallin, T.; Ohnstad, L.; Bertling, L. On Operational Risk Assessment in Transmission Systems—Weather Impact and Illustrative Example. In Proceedings of the 10th International Conference on Probablistic Methods Applied to Power Systems, Rincón, PR, USA, 25–29 May 2008; pp. 1–6. [Google Scholar]
- Nazir, Z.; Bollen, M.H. Operational risk assessment of transmission Systems: A review. Int. J. Electr. Power Energy Syst. 2024, 159, 109995. [Google Scholar] [CrossRef]
- Azarnia, M.; Bollen, M.J.; Haigh, P.; Katal, F.; Kudahetti, R.; Mousavi, M.; Nazir, Z.; Tavares de Oliveira, T.; Wallmark, C.; Westerlund, P.; et al. Hosting capacity of meshed distribution grids with and without smart solutions. IET Conf. Proc. 2024, 2024, 138–141. [Google Scholar] [CrossRef]
- Chojkiewicz, E.; Paliwal, U.; Abhyankar, N.; Baker, C.; O’Connell, R.; Callaway, D.; Phadke, A. Accelerating transmission capacity expansion by using advanced conductors in existing right-of-way. Proc. Natl. Acad. Sci. USA 2024, 121, e2411207121. [Google Scholar] [CrossRef] [PubMed]
- Office for Gas and Electricity Markets (Ofgem). Transmission Investment Project Appraisal Report; Consultation response by Parsons Brinckerhoff, Ref. 151/10; Ofgem: London, UK, 2010. [Google Scholar]
- National Energy System Operator. Appendix 1 to Holistic Network Design, Pathway to 2030 Summary Report. July 2022. Available online: https://www.neso.energy/document/262676/download (accessed on 13 December 2024).
- Stevenson, W.D. Elements of Power System Analysis; McGraw-Hill: New York, NY, USA, 1982; Volume 4. [Google Scholar]
- National Energy System Operator. Appendix B to Electricity Ten Year Statement, ETYS2023, NESO Publications ETYS. 2023. Available online: https://www.neso.energy/publications/electricity-ten-year-statement-etys/etys-documents-and-appendices (accessed on 5 June 2025).
- The Planning Inspectorate. North London Reinforcement Project. Examining Authority’s Report of Findings and Conclusions and Recommendation to the Secretary of State for Energy & Climate Change, Development Consent Order EN020009. Available online: https://nsip-documents.planninginspectorate.gov.uk/published-documents/EN020009-001686-Annex%20A%20Examining_Authority's_Recommendation_Report_to_the_Secretary_of_State.pdf (accessed on 5 June 2025).
- Hiorns Smart Energy Networks. Review of National Grid Energy Transmission (NGET) Proposals for East Anglia Network Reinforcement with a Focus on the Need and Timing of the Proposed 400 Kilovolt (kV) Line from Norwich to Bramford to Tilbury 400 kV Substations. September 2023. Available online: https://www.suffolk.gov.uk/asset-library/n2t-the-hiorns-report.pdf (accessed on 13 December 2024).
- The European Commission. Use of Non-Conventional Technologies for Increasing Capacity in Transmission Networks. EC Directorate General for Budget. Available online: https://ec.europa.eu/ten/energy/studies/doc/cesi/chapter_7-8_new_technologies_information.pdf (accessed on 5 June 2025).
- IEEE Power System Dynamic Performance Study Committee. Test Systems for Voltage Stability Analysis and Security Assessment, IEEE Nordic Test System Dataset. Available online: https://cmte.ieee.org/pes-psdp/489-2/ (accessed on 5 June 2025).
- Haigh, P. Model Paper, OSF. 28 March 2025. Available online: https://osf.io/ubvpw (accessed on 29 March 2025).
- Svenska Kraftnät (SvK). Peak Load Hour, SvK About the System, Power System Data. Available online: https://www.svk.se/om-kraftsystemet/kraftsystemdata/topplasttimmen/ (accessed on 5 June 2025).
- DIgSILENT GmbH. PowerFactory 2024 User Manual; Online Edition; DIgSILENT GmbH: Gomaringen, Germany, 2024; p. 557. [Google Scholar]
- Kraftnät, S. Short-Term Market Analysis 2023, SvK Reports and Referral Responses. 21 February 2024. Available online: https://www.svk.se/om-oss/rapporter-och-remissvar/ (accessed on 11 July 2024).
- Länsstyrelserna. Vindbrukskollen v8.1.0, Energimyndigheten. 2024. Available online: https://vbk.lansstyrelsen.se/ (accessed on 5 June 2025).
- European Network of Transmission System Operators for Electricity (ENTSO-E). Transparency Platform: Installed Capacity per Production Type, ENTSO-E, Finland and Norway Data. 2024. Available online: https://transparency.entsoe.eu/generation/r2/installedGenerationCapacityAggregation/show (accessed on 16 December 2024).
- DIgSILENT GmbH. Technical Reference, Station Controller (ElmStactrl), Version 2; Online Edition; DIgSILENT GmbH: Gomaringen, Germany, 2022; p. 19. [Google Scholar]
- Holford, W. Holford Rules, Central Electricity Generating Board, later National Grid. 1959. Available online: https://www.nationalgrid.com/sites/default/files/documents/13795-The%20Holford%20Rules.pdf (accessed on 30 January 2025).
Year | MW Total | Mvar Total |
---|---|---|
Original | 10,687 | 2836 |
2024 | ≈25,000 | 2836 |
Voltage Level of Substation | Number of Nodes with at Least One PI Breach Across Contingencies, and Highest Value of that Breach | |||
---|---|---|---|---|
Vpu <0.95 | Vpu >1.05 | Vstep >5% | Circuit Loading > 100% | |
400 kV | 11 of 19, 0.550 pu | 9 of 19, 1.066 pu | 16 of 19, 49% | 3 of 33, 157% |
220 kV, 130 kV | 7 of 13, 0.480 pu | 6 of 13, 1.070 pu | 11 of 13, 55% | 4 of 19, 122% |
Busbar | Cont. Max. Vpu | Base Max. Vpu | Worst-Case Cont. |
---|---|---|---|
4041 | 1.066 | 1.051 | L4041–4044 |
4051 | 1.066 | 1.066 | Base Case |
4072 | 1.059 | 1.059 | L4046–4047 |
4047 | 1.059 | 1.059 | Base Case |
4062 | 1.056 | 1.056 | L4043–4046 |
4063 | 1.054 | 1.054 | L4043–4046 |
4045 | 1.053 | 1.053 | Base Case |
4021 | 1.053 | 1.049 | L4061–4062 |
4032 | 1.051 | 1.049 | L4031–4032 |
2032 | 1.070 | 1.069 | L4045–4051a |
1012 | 1.065 | 1.063 | L4045–4062 |
1011 | 1.064 | 1.062 | L4046–4047 |
1014 | 1.062 | 1.061 | L4046–4047 |
1013 | 1.056 | 1.055 | L4046–4047 |
1022 | 1.055 | 1.051 | L4041–4044 |
Busbar | Cont. Min. Vpu | Base Min. Vpu | Worst-Case Cont. |
---|---|---|---|
4031 | 0.540 | 1.037 | L4011–4021 |
4022 | 0.602 | 0.995 | L4011–4021 |
4032 | 0.631 | 1.049 | L4011–4021 |
4041 | 0.689 | 1.051 | L4011–4021 |
4021 | 0.812 | 1.049 | L4011–4021 |
4044 | 0.824 | 1.039 | L4011–4021 |
4042 | 0.835 | 1.043 | L4011–4021 |
4043 | 0.865 | 1.037 | L4011–4021 |
4061 | 0.870 | 1.039 | L4011–4021 |
4045 | 0.880 | 1.053 | L4011–4021 |
4046 | 0.894 | 1.036 | L4011–4021 |
4012 | 0.936 | 1.024 | L4011–4021 |
4011 | 0.936 | 1.022 | L4011–4021 |
2031 | 0.551 | 1.028 | L4011–4021 |
2032 | 0.819 | 1.069 | L4011–4021 |
1022 | 0.672 | 1.051 | L4011–4021 |
1044 | 0.806 | 1.007 | L4011–4021 |
1041 | 0.840 | 1.012 | L4011–4021 |
1045 | 0.845 | 1.011 | L4011–4021 |
1043 | 0.862 | 1.027 | L4011–4021 |
1021 | 0.948 | 1.031 | L4011–4021 |
Busbar | Cont. Min. Vpu | Base Min. Vpu | Worst-Case Cont. | Resolved by Which Reinforcement, New Cont. Min. Busbar Vpu |
---|---|---|---|---|
4061 | 0.859 | 0.980 | L4061–4062 | 2 × 200 Mvar, 0.989 |
4046 | 0.937 | 0.979 | L4046–4047 | 4046-Cap up to 2 × 200 Mvar, 0.977 |
1044 | 0.912 | 0.940 | L4041–4044 | 1044-Cap up to 3 × 200 Mvar, 0.959 |
1041 | 0.920 | 0.954 | L4041–4044 | 1041-Cap up to 2 × 250 Mvar, 0.964 |
1045 | 0.921 | 0.954 | L4041–4044 | 1041-Cap and 1044-Cap ups, 0.960 |
1022 | 0.938 | 1.010 | L4011–4021 | 1022-Cap up to 4 × 50 Mvar, 0.962 |
1043 | 0.946 | 0.973 | L4041–4044 | 1041-Cap and 1044-Cap ups, 0.982 |
Generation Type | Total Capacity = 50,295 MW | ||
---|---|---|---|
NORTH MW | EQUIV MW | CENTRAL + SOUTH MW | |
Hydro | 13,360 | 6668 | 1353 |
Nuclear | 0 | 1440 | 3202 |
Wind | 10,483 | 3955 | 3134 |
Thermal | 276 | 2855 | 3569 |
TOTAL | 24,119 | 14,918 | 11,258 |
Node | Region | % Regional Share | Hydro MW | Nuclear MW | Wind MW | Thermal MW |
---|---|---|---|---|---|---|
4071 | EQ | 10.0% | 667 | 720 | 1978 | 1427 |
4072 a | EQ | 90.0% | 6001 | 720 | 1978 | 1427 |
4011 | N | 16.0% | 2138 | 0 | 1048 | 276 |
4012 | N | 12.8% | 1710 | 0 | 1048 | 0 |
4021 | N | 4.8% | 641 | 0 | 1048 | 0 |
4031 | N | 5.6% | 748 | 0 | 1048 | 0 |
2032 | N | 13.6% | 1817 | 0 | 1048 | 0 |
1012 | N | 12.8% | 1710 | 0 | 1048 | 0 |
1013 | N | 9.6% | 1283 | 0 | 1048 | 0 |
1014 | N | 11.2% | 1496 | 0 | 1048 | 0 |
1021 | N | 9.6% | 1283 | 0 | 1048 | 0 |
1022 | N | 4.0% | 534 | 0 | 1048 | 0 |
4042 | C+S | 20% | 193 | 640 | 448 | 510 |
4047 | C+S | 20% | 193 | 640 | 448 | 510 |
4051 | C+S | 20% | 193 | 640 | 448 | 510 |
4062 | C+S | 20% | 193 | 640 | 448 | 510 |
4063 | C+S | 20% | 193 | 640 | 448 | 510 |
1042 | C+S | 0% b | 193 | 0 | 448 | 510 |
1043 | C+S | 0% b | 193 | 0 | 448 | 510 |
Node | Region | % Regional Share | Hydro MW | Nuclear MW | Wind MW | Thermal MW |
---|---|---|---|---|---|---|
4071 | EQ | 10.0% | 280 | 720 | 0 | 0 |
4072 | EQ | 90.0% | 2965 | 720 | 0 | 0 |
4011 | N | 16.0% | 570 | 0 | 0 | 0 |
4012 | N | 12.8% | 456 | 0 | 0 | 0 |
4021 | N | 4.8% | 171 | 0 | 0 | 0 |
4031 | N | 5.6% | 199 | 0 | 0 | 0 |
2032 | N | 13.6% | 484 | 0 | 0 | 0 |
1012 | N | 12.8% | 456 | 0 | 0 | 0 |
1013 | N | 9.6% | 342 | 0 | 0 | 0 |
1014 | N | 11.2% | 399 | 0 | 0 | 0 |
1021 | N | 9.6% | 342 | 0 | 0 | 0 |
1022 | N | 4.0% | 142 | 0 | 0 | 0 |
4042 | C+S | 20.0% | 0 | 640 | 0 | 0 |
4047 | C+S | 20.0% | 0 | 640 | 0 | 0 |
4051 | C+S | 20.0% | 0 | 640 | 0 | 0 |
4062 | C+S | 20.0% | 0 | 640 | 0 | 0 |
4063 | C+S | 20.0% | 0 | 640 | 0 | 0 |
1042 | C+S | 0.0% | 0 | 0 | 0 | 0 |
1043 | C+S | 0.0% | 0 | 0 | 0 | 0 |
Circuit | Cont. Max. Load % | Base Load % | Reinforcement |
---|---|---|---|
L4011–4071 | 191.0 | 103.8 | L4011–4071b |
L4012–4071 | 191.0 | 87.3 | L4012–4071b |
L4022–4031a | 181.4 | 104.3 | L4022–4031c |
L4022–4031b | 181.4 | 104.3 | L4022–4031c |
L4012–4022 | 171.9 | 108.3 | L4012–4022b |
L4011–4022 | 167.2 | 87.1 | L4011–4022b |
L4031–4032 | 162.8 | 79.8 | L4031–4032b |
L4071–4072a | 143.2 | 71.6 | L4071–4072c |
L4071–4072b | 143.2 | 71.6 | L4071–4072c |
L4011–4021 | 136.5 | 108.2 | L4011–4021b |
L4011–4012 | 132.5 | 38.3 | L4011–4012b |
L4031–4041a | 129.9 | 77.3 | L4031–4041c |
L4031–4041b | 129.9 | 77.3 | L4031–4041c |
L1043–1044a | 128.8 | 81.7 | L1043–1044c |
L1043–1044b | 128.8 | 81.7 | L1043–1044c |
L4041–4044 | 124.0 | 77.7 | L4041–4044 |
L4042–4043 | 123.4 | 82.4 | L4042–4043 |
L4042–4044 | 120.3 | 61.1 | L4042–4044 |
Busbar or Circuit | Resolved by Reinforcement |
---|---|
4031 | 4031-Cap, 4 × 200 Mvar |
4021 | 4021-Cap, 4 × 200 Mvar |
4022 | 4022 SC, addition of 500 MVA synchronous compensator |
L4022–4031 | L4022–4031d (reactive flows trigger fourth circuit) |
4071 | 4071 SC, addition of 500 MVA synchronous compensator |
L4071–4072 | L4071–4072d (reactive flows trigger fourth circuit) |
1042 | 1042-Cap, 4 × 50 Mvar |
1044 | 1044 SC, addition of 500 MVA synchronous compensator |
1045 | 1045 SC, addition of 500 MVA synchronous compensator |
4042 | 4042-Cap, 2 × 200 Mvar |
GW | Location(s) | Breach, Reinforcement |
---|---|---|
13 | 4021, 4022, 1022, 1013, 1014, 4011 | Overvoltage, reduce target voltage (1.04 pu) |
14 | L1021–1022c | Circuit overloading for AC Contingency Cases (AC Cont.), new circuit |
14 | 4042 | Non-convergence persisting due to voltage at 4042. L4021–4042 over 100% (though less than 150%) but new line will be needed soon, so triggering L4021–4042b now |
15 | 1041, 4031, 4061 | Overvoltage, reduce deltaVmax to 3% to prevent stepping up of 1041-Cap, 4031-Cap, 4061-Cap for overvoltage cases |
17 | L1011–1013c | Circuit overloading for DC loadflow |
17 | L4031–4041d | Circuit overloading for DC contingencies |
17 | L4011–4012a,b L2031–2032a,b | Circuit overloading for DC contingencies, 50% series compensation as X × 0.5 to avoid new circuits |
17 | L1013–1011d | Circuit overloading for DC contingencies |
17 | L1043–1044d | Circuit overloading for DC contingencies |
17 | L1041–1043c | Circuit overloading for DC contingencies |
17 | L4012–4022c | Circuit overloading for DC contingencies |
17 | L4041–4044c | Circuit overloading for DC contingencies |
17 | 4022 | Undervoltage, extra 3 × 200 Mvar on 4022-Cap |
17 | 4042 | Undervoltage, extra 3 × 200 Mvar on 4041-Cap |
17 | 4041 | Undervoltage, extra 3 × 200 Mvar on 4041-Cap |
17 | 4041 | Undervoltage, addition of 1 000 MVA synchronous compensator, 4041-SC |
17 | 1011 | Undervoltage, 2 × 200 Mvar, 1011-Cap |
17 | L2031–2032c | Circuit overloading AC Cont. causing undervoltage, future-proof with circuit |
17 | L1021–1022d | Circuit overloading AC Cont. causing undervoltage, future-proof with circuit |
17 | 4021 | Undervoltage, extra 3 × 200 Mvar on 4021-Cap |
17 | L4044–4045c | Circuit overloading AC Cont. and causing undervoltage, future-proof with circuit |
17 | L4011–4021c | Circuit overloading AC Cont. and causing undervoltage, future-proof with circuit |
17 | L4022–4031a,b,c,d | Circuit overloading AC Cont., already four circuits, reconductoring with 4.63 kA |
17 | L4012–4022d | Circuit overloading AC Cont. causing undervoltage, future-proof with circuit |
17 | 4031 | Undervoltage, addition of 1000 MVA synchronous compensator, 4031-SC |
17 | 1012 | Overvoltage, addition of 2 × 150 Mvar shunt reactor, 1012-Ind |
17 | 4011 | Undervoltage, addition of 1 000 MVA synchronous compensator, 4031-SC |
19 | L1014–1012c | Circuit overloading for DC Cont. |
19 | L4021–4042a,b | Circuit overloading for DC Cont., reconductoring to avoid third circuit, 4.63 kA |
19 | L4031–4041a,b,c,d | Circuit overloading for DC Cont., already four circuits, reconductoring with 4.63 kA |
19 | L4042–4043a,b | Circuit overloading for DC Cont., reconductoring to avoid third circuit, 4.63 kA |
19 | L4032–4044b | Circuit overloading AC Cont. causing undervoltage, future-proof with circuit |
19 | L4032–4032 | Circuit overloading AC Cont., reconductoring to avoid third circuit, 4.63 kA |
19 | L4031–4032a,b | Circuit overloading AC Cont., reconductoring to avoid third circuit, 4.63 kA |
19 | L4011–4071 | Circuit overloading for AC Cont., already four circuits, reconductoring with 4.63 kA |
19 | L4011–4021d | Circuit overloading for AC Cont., new circuit |
19 | L4021–4032b | Circuit overloading for AC Cont., new circuit |
19 | L4041–4061b | Convergence issue for outage, new circuit |
21 | L2031–2032d | Circuit overloading for DC Cont. |
21 | L1013–1011a,b,c,d | Circuit overloading (within 150% of rating) but causing undervoltage, series compensation (50%) a |
21 | 4032 | Undervoltage, 8 × 100 Mvar, 4032-Cap |
21 | 4031–4041a,b,c,d | Undervoltage convergency, increase degree of series compensation to 50% |
21 | 4044 | Undervoltage, addition of 1 000 MVA synchronous compensator, 4044-SC |
21 | L4032–4044b | Convergence issue for outage, new circuit b |
21 | 1042 | Undervoltage, replant 1011-Cap to 5 × 100 Mvar |
21 | L4043–4044b | Convergence issue for outage, new circuit b |
21 | 1022 | Undervoltage, replant 1022-Cap to 2 × 200 Mvar |
21 | L4022–4031a,b,c,d | Undervoltage, 50% series compensation to reduce voltage drop |
21 | L4011–4021 | Undervoltage, 50% series compensation to reduce voltage drop |
21 | L4011–4022 | Undervoltage, 50% series compensation to reduce voltage drop |
21 | L1042–1045b | Undervoltage at other nodes for outage, new circuit b |
21 | 1043 | Undervoltage, upgrade 1043-Cap to 3 × 200 Mvar |
23 | L4021–4042 | Undervoltage, 50% series compensation to reduce voltage drop |
23 | L4032–4042 | Undervoltage, 50% series compensation to reduce voltage drop |
23 | L4032–4044 | Undervoltage, 50% series compensation to reduce voltage drop |
23 | L4043–4046b | Convergence issue for outage, new circuit b |
23 | 4043 | Undervoltage, upgrade 4043-Cap to 3 × 200 Mvar |
23 | L1041–1043d | Circuit overloading AC Cont. causing undervoltage, future-proof with circuit |
25 | L1013–1011 | Circuit overloading beyond 150% in DC cont. Already four circuits, so redispatching generation (hydro 50% for thermal at G16 (500 MW) and G17 (141.3 MW)) c |
25 | L1013–1014 | Circuit overloading beyond 150% in DC cont. and feeding overloads in L1011–1013a,b,c,d, so redispatching generation (hydro 50%, 748.15 MW for thermal at G17 (368.5 MW) and G7 (379.65 MW)) c |
25 | 1022 | Undervoltage, upgrade 1022-Cap to 5 × 100 Mvar instead of 2 × 200 Mvar |
25 d Wind | L1011–1013a,b,c,d | Circuits overloaded >100% in base case, redispatch 180.9 MW hydro from G2 to G7 |
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |
© 2025 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/).
Share and Cite
Haigh, P.; Wallmark, C.; Bollen, M. Reproducible Method for Modifying a Published Electricity Network Model for Transmission Expansion Planning. Energies 2025, 18, 4446. https://doi.org/10.3390/en18164446
Haigh P, Wallmark C, Bollen M. Reproducible Method for Modifying a Published Electricity Network Model for Transmission Expansion Planning. Energies. 2025; 18(16):4446. https://doi.org/10.3390/en18164446
Chicago/Turabian StyleHaigh, Peter, Cecilia Wallmark, and Math Bollen. 2025. "Reproducible Method for Modifying a Published Electricity Network Model for Transmission Expansion Planning" Energies 18, no. 16: 4446. https://doi.org/10.3390/en18164446
APA StyleHaigh, P., Wallmark, C., & Bollen, M. (2025). Reproducible Method for Modifying a Published Electricity Network Model for Transmission Expansion Planning. Energies, 18(16), 4446. https://doi.org/10.3390/en18164446