1. Introduction
China’s wind power industry has been in rapid development since 2005. By the end of 2013, the total installed wind power capacity reached 94.41 GW, ranking first in the world. However, large-scale installed wind power capacity results in the problem of abandoned wind power. In 2013, the average equivalent utilization hour of wind power in some Chinese provinces was only 1,400 h, and the total abandoned wind power reached 20 TW·h. Since wind turbines’ power generation efficiency cannot be guaranteed, generation companies’ investment enthusiasm in wind power is gradually decreasing. The current situation is not beneficial to the wind power industry’s sustainable development [
1].
In China, the wind power consumption problem remains the main bottleneck of wind power’s large-scale development. The reasons for abandoned wind power are two-fold. On the one hand, wind power is intermittent and unstable [
2], increasing the difficulty of system scheduling problems. On the other hand, wind power output is anti-load distributed [
3,
4,
5]. China’s wind resources are mainly distributed in the “Three north-areas” which are far away from load demand centers, and local load demand cannot meet the consumption requirements [
6,
7]. Besides, mismatched grid infrastructures and uncoordinated interest relationships of wind power, grid enterprise and thermal power also influence wind power grid connection [
8,
9].
Current, literature about wind power consumption problems concentrates on two aspects: local consumption schemes and wind power delivery. Since wind power output is uncertain, thermal power, hydro power or other traditional power sources are required to provide backup service for wind power delivery [
10,
11,
12]. However, general wind power delivery has a series of constraints, such as power transmission capacity, transmission power stability, load demand and other factors [
13,
14]. Local consumption methods include building pumped storage power station, developing electric vehicles, utilizing energy storage systems,
etc. [
15,
16,
17,
18,
19,
20]. Energy storage systems (ESSs) can achieve peak shifting, decrease the influence of wind power uncertainty and improve wind power utilization rate. Therefore, ESSs have great application potential for wind power consumption problems.
There are four major methods to improve systems’ wind power consumption capacity, including improving system adjustment ability [
21], improving power grid transmission capacity [
22,
23], improving wind power grid connection technology performance [
24,
25] and improving wind power scheduling operation levels [
26,
27]. Improving wind power scheduling operation level is the key to solving wind power consumption problems [
8]. The above literatures are mainly focused on optimizing wind power consumption problems from the power generation side. Considering time-of-use price (TOU price) and ESSs both have the capacity to influence demand load distribution, this paper tries to optimize the power system scheduling problem from power generation side and load demand side, which means optimizing units’ combined output structure and demand load distribution at the same time. This paper introduces DRSs and ESSs to the wind power consumption optimization model, and optimizes real-time outputs of thermal units and wind turbines, real-time charging-discharging behavior of energy storage systems to thus achieve the system’s maximum energy-saving benefits.
The rest of the paper is organized as follows:
Section 2 presents the demand response model. The model divides 24 h of one day into peak, flat and valley load periods according to their load demands and calculates load variation amounts according to the elasticity coefficients.
Section 3 presents the energy storage system’s charging and discharging model. The model takes the energy storage system’s capacity limitation, power limitations, and energy consumption coefficients as the constraints. In
Section 4, Latin Hypercube Sampling (LHS) and Kantorovich distance method are used, respectively, to simulate wind power output scenarios and construct a reduction strategy scenario.
Section 5 builds a power generation scheduling optimization model with wind power;
Section 6 builds another model considering the influences of ESSs and DRPs.
Section 7 divides thermal units’ power generation coal consumption function into segments to transform the quadratic function into a linear function, and deals with the multiplication of two binary variables in the objective functions to simplify the calculation. In
Section 8 we perform a case study and simulation to compare the influences of demand response and energy storage systems on a power grid’s wind power consumption capacity.
Section 9 highlights the main conclusions of the paper.
2. Demand Response Model
Demand side management (DSM) means controlling user-behavior by changing their electric use habits, improving terminal electricity efficiency and other measures. DSM could decrease total electric consumption while guaranteeing meeting users’ demand. There are many types of DSM mechanisms, for example Rate basing, Energy-saving benefit sharing, RDM Plus and so on [
28]. This paper chooses time-of-use price (TOU price) to study its influence on power efficiency. With the influence of TOU price, users would decrease load demand in peak load periods and transfer their demand into flat or valley load periods, making the demand load curve become smoother.
Users Load demand should be calculated by its real load demand and corresponding line-loss rate. The total load demand for all users should be a summation of all types and voltage levels users’ load demands. Therefore, total demand load before implementing the TOU price
could be calculated by Equation (1):
wherein
I is user type number;
i is the index for time,
i = 1,2,…,
I;
K is voltage level number;
k is the index for voltage level,
k = 1,2,…,
K;
T is time length;
t is the index of time,
t = 1,2,…,
T;
is the load demand of user
i in voltage level
k without TOU price;
I is the number of user types;
K is the number of voltage levels;
lk is the line-loss rate of voltage level
k,
.
Demand load after implementing TOU price is:
wherein
Likt is the load demand of user
i in voltage level
k with TOU price; Δ
Likt is the variation amount of load demand.
We divide 24 h into peak, flat and valley load periods according to total demand load
. When TOU price is implemented, demand load in the peak, flat and valley load periods would change. For different users, the load demand variation amount in different time periods (peak, flat and valley) would be different, which could be represented by their demand elasticity coefficients. Equation (3) shows the demand elasticity coefficients for different users.
wherein
s is the index for time,
s = 1,2,…,
T;
eikst is user demand elasticity coefficient of user
i in voltage level
k, it reflects the influence of price variation at time
t on load demand variation amount at time
s. If
s =
t,
eikst represents its influence on users’ load demand when price changes in the current period; and if
s ≠
t,
eikst represents its influence on other period’s load demand when price changes in the current period.
Considering the mutual influence of three periods, user
i in voltage level
k demand elasticity coefficients matrix
Eik could be expressed as Equation (4):
wherein Δ
Likp, Δ
Likf and Δ
Likv are respectively total demand variation amount of user
i in voltage level
k in three periods after TOU price. Based on Equations (3) and (4) Δ
Likp, Δ
Likf and Δ
Likv could be calculated by Equation (5):
wherein
,
and
are respectively the total demand loads of user
i in voltage level
k in three periods, and they could be calculated by Equations (6)–(8):
Assume the demand load change rate in the same period (peak, flat or valley) is fixed. Then peak, flat and valley periods’ load demand with TOU price could be calculated according to Equation (2), wherein Δ
Likt in different periods could be calculated by Equation (9):
The load demand after TOU price
Gt could be expressed as Equation (10):
From the above analysis, TOU price would influence load demand distribution and units’ output power. Therefore, TOU price can be regarded as a function of independent variables Δ
Likp, Δ
Likf and Δ
Likv. The variable
Gt can be calculated by Equation (11):
3. Energy Storage Systems Charging and Discharging Model
In traditional electricity generation mode power generation, transmission and allocation progresses are happening at almost the same time. This characteristic would influence electric system’s planning, construction, scheduling and controlling mechanisms. Energy storage systems are both power sources and loads; in valley load period, ESSs could charge as a load, and in peak periods ESSs could discharge as a power source. Large-scale energy storage system could effectively decrease peak-valley load ratio, improve electricity quantity, improve power supply stability and promote renewable energy grid connection.
While charging or discharging the ESS itself would also consume some energy. Therefore, considering energy conversion efficiency ESSs’ charging-discharging behavior at time t should meet Equation (12):
wherein
is the index for time,
;
Q0 is the initial storage electricity of the ESSs;
is the storage electricity of ESSs at time
;
is the charging power of ESSs at time
t;
is the discharging power of ESSs at time
t;
Pess is the energy conversion efficiency coefficient of ESS. Equation (12) states that the original storage energy plus charging gains minus the current storage capacity and then multiplies energy efficiency coefficient should be equal to the summation of discharging.
Assume ESSs could not charge and discharge at the same time, its charging-discharging status should meet Equation (13):
wherein
is charging power of the ESSs at time
t;
is discharging power of ESSs at time
t.
ESSs charging and discharging power is constrained by its max power limitations:
wherein
is the max charging power limitation of the ESSs;
is the max discharging power limitation of the ESSs.
The electricity storage in ESSs should be not more than the total storage capacity:
wherein
is the storage capacity of ESSs.
4. Wind Power Uncertainty Simulation
Before studying the wind power consumption problem, wind power output and basic wind scenarios should be obtained. Wind turbine output is closely related with wind velocity at the wind turbine’s hub part. Therefore, wind power output could be calculated by Equation (17) [
29]:
wherein
w is the available wind power output; ρ is air density;
A is the swept area of wind turbine’s blades;
v is wind velocity at wind turbine’s hub part;
cw is a nonlinear function concerning Tip Speed Ratio (TSR) and pitch angle.
In the actual calculation, the nonlinear factors in Equation (17) have little influence on wind power output [
30], therefore, this paper chooses a piecewise linear function to simplify the calculation of wind power output [
31]. Wind power is limited by incoming wind velocity. If the incoming wind velocity is lower than wind turbine’s cut-in wind velocity or higher than cut-out wind velocity, a wind turbine would not generate power. The wind turbine’s available output power could be calculated by Equation (18):
wherein
M is wind turbine number;
m is the index of wind turbine,
m = 1,2,…,
M;
is the available output of wind turbine
m at time
t;
vt is the real-time wind velocity at time
t;
vin and
vout are respectively wind turbine cut-in and cut-out wind velocities;
vm,rated is the rated wind velocity of wind turbine
m;
wm,rated is the rated output of wind turbine
m.
4.1. Wind Power Output Scenario Simulation
There are many existing methods to simulate wind power output scenarios [
32,
33]. The Monte Carlo method is a relatively accurate and widely used sampling method. The method has good adaptability, and its errors are only related to the standard deviation and sample size. However, its accuracy is constrained by both the stochastic sampling reliability and the simulation times. Therefore, The Monte Carlo method would consume large amounts of computation time to achieve a satisfactory accuracy. To overcome this flaw of the Monte Carlo method, the Latin Hypercube Sampling method (LHS) has been put forward [
33]. It do not require as large amounts of computation time as the Monte Carlo method. Therefore, this paper chooses LHS to simulate wind power output scenarios, the details are as follows [
34]:
Assume X is a H-dimensional random variable. The individual elements
xh (
h = 1,2,…,
H) of X are independent of each other. And
Fh (
h = 1,2,…,
H) is the probability distribution function for element
xh, then:
For a given simple size
N, divide the domain of
yh into
N non-overlapping intervals of equivalent length, the length of each interval is 1/N. Then for an interval (
n-1,
n), choose a point of
as its sampling value
xhn. Assume
phn is a uniformly distributed random variable, and its domain is [0, 1]. Then for the
n-th sampling,
yhn is the probability value of the
h-th element
xh of
X, and
yh should be in interval
. Therefore the
n-th sampling result could be calculated by Equation (20):
Once all the elements are sampled, X could be obtained. Then define a sampling result matrix ().
Assume
h(
x) is a transformation function of two input variables, for example
x1 and
x2. And the estimate of expectation value
of
h(
x) could be calculated as:
Sample variance depends on the method used to simulate the sample. The variance of random sample is:
The variance of the sample simulated by Latin Hypercube method is:
According to Equations (22) and (23), the LHS method decreases the sample variance if cov(
h(
x1),
h(
x2)) < 0. Literature [
35] has indicated that when the sample size
N is big enough (much larger than the number of elements
H), the covariance term is asymptotically non-positive. Therefore, it is easier for LHS to achieve convergence than for simple random sampling.
4.2. Wind Power Scenario Reduction Strategy
The LHS method could be used to get a wind power output scenarios set. Some similar scenarios should be deleted to simplify the calculation complexity. The basic concept of scenario reduction is to compare a scenario with other scenarios and remove the closest one. The bigger the scenario number, the bigger the scenario reduction workload.
To overcome this problem, many well-known scenario reduction methods have been put forward [
36,
37,
38,
39,
40]. Römisch,
et al. [
37] reviewed available scenario reduction techniques and discussed the related open problems. This paper chooses the Kantorovich distance method [
27,
39], and sets to minimize the Kantorovich distance between the initial scenario and the removed scenario as the reduction objective.
Assume
is a scenario set for a
T-length time period, and its scenario number is
H. Therefore,
, the element of
is
and the probability of
sh is
ph.
could be obtained by LHS method. By scenario reduction we could get a reduced scenario set
Q, which contains all the remaining scenarios after scenario reduction.
, the element of
Q is
and the probability of
is
qr. The Kantorovich distance could be calculated by Equations (24) and (25):
Define a removed scenario set
R, which contains all removed scenarios. Then the Kantorovich distance could be calculated by Equation (26):
Approximately regard
qr as the summation of the scenario’s occurrence probability in the initial scenario and the closest removed scenario’s occurrence probability. The details are:
Then build a wind power scenario reduction optimization method based on Equations (24)–(29). Assume
NR is the number of scenarios that have been removed. The optimized scenario reduction method can be expressed by Equation (30):
According to Equation (30), the scenario reduction mechanism would influence the reduction result directly. To set appropriate scenario removing number, this paper sets the maximum reduction strategy as Equation (31):
Equation (31) is to ensure the similar degree of the scenario set after scenario and the initial scenario set is in the required range. The scenario reduction model consists of Equations (24)–(31). To solve this model, this paper uses the multi-stage heuristic algorithm, referring to [
33].
5. Power Generation Scheduling Optimization Model with Wind Power
Power generation scheduling schemes are determined by user demand. The scheduling center makes power generation plans for generation units based on the demand load curve. Since wind power has low variable cost, improving the wind power utilization level could decrease energy consumption during power generation. However, since wind power is intermittent and unstable, backup services are needed for its grid connection. This makes system scheduling problems more complicated. Therefore, how to allocate units’ output and get more economic benefits is the key problem for power generation scheduling. To decrease energy consumption, this paper sets to minimize coal consumption as the optimization goal and builds energy-saving power generation scheduling mode. The optimization objective is expressed as Equation (32):
wherein
J is thermal unit number;
j is the index for thermal unit,
j = 1,2,…,
J;
ujt is a 0–1 variable,
ujt = 1 represents unit
j is on operation at time
t and
ujt = 0 represents unit
j is shutdown at time
t;
Sjt is startup coal consumption of unit
j;
gjt is the output of unit
j at time
t;
fj(
gjt) is a quadratic function for power generation coal consumption, its equation is:
wherein
aj,
bj and
cj are coal consumption parameters of thermal unit
j. The scheduling schemes should meet the following constraints:
(1) Electricity demand and supply balance constraint:
wherein
pj is the auxiliary power consumption rate of unit
j;
pm is the auxiliary power consumption rate of wind turbine
m.
(2) System maximum backup service constraints:
wherein
is max limitation of thermal unit
j at time
t;
Rt is the backup service demand without TOU price and ESSs at time
t;
is the max limitation of system spinning reserve without TOU price and ESSs at time
t;
is the max climbing limitation of unit
j output power.
(3) System minimum backup service constraints:
wherein
is the min limitation of thermal unit
j at time
t;
is the min limitation of system spinning reserve without TOU price and ESSs at time
t;
is the max climbing limitation of unit
j output power.
(4) Wind power real-time output constraint:
wherein λ
t is the equivalent utilization coefficient of wind power at time
t.
(5) Thermal units output constraint:
(6) Thermal units power climbing constraint:
(7) Thermal units’ start time constraints:
wherein
is the continuous operation time of unit
j at time
t−1;
is the min operation time limitation of unit
j.
(8) Thermal units’ downtime constraints:
wherein
is the continuous shutdown time of unit
j at time
t−1;
is the min limitation shutdown time of unit
j.
The scheduling model achieves energy-saving by controlling the startup-shutdown and units output. Therefore, the decision variables in the model are units’ startup-shutdown statue variable ujt, units’ output variable gjt and wind power’s real-time output variable wm,t.
6. Power Generation Scheduling Optimization Model Considering ESSs and DRPs
DRPs and ESSs could change demand load distribution. The distribution would influence the power generation scheduling scheme. Therefore, a power generation scheduling scheme can be optimized with the influence of DPRs and ESSs. According to the operation mechanism, DRPs and ESSs could help load shifting, decrease load volatility and decrease units’ scheduling pressure. Then, units with high effectiveness and low coal consumption rate would output more, units with low effectives and high coal consumption level would output less or not generate. In this way, system average coal consumption could be decreased.
According to the above analysis, this paper sets thermal units’ real-time output, operation statue, wind power real-time output, ESSs real-time charging and discharging power and TOU price change as the decision variables and builds a power generation scheduling optimization model with ESSs and DRPs. The optimization objective is still minimizing total coal consumption:
The scheduling schemes should meet the following constraints Equations (1)–(16),(18),(33),(38)–(43).
Besides, they should meet constrains of ESSs and backup services:
(1) ESSs charging and discharging constraint:
(2) The max and min backup service limitation constraints of wind power considering ESSs and DRPs:
wherein
is the max limitation of system spinning reserve with TOU price and ESSs at time
t:
wherein
is the min limitation of system spinning reserve with TOU price and ESSs at time
t. 7. Linear Processing
The decision variables of the optimization model contains continues variables and 0–1 variables, which is a mixed integer optimization problem. Thermal units’ real-time output is a decision variable, the relationship between the real-time output and coal consumption is expressed as a quadratic function
fj(
g). The optimization objective function contains a multiplication of a 0–1 variable and a quadratic term. Therefore, the power generation scheduling optimization problem is a mixed integer nonlinear programming problem [
41]. Algorithms for mixed integer nonlinear programming problems are general complicated with slowly convergence. Therefore, referring to [
42] this paper divides thermal units’ power generation coal consumption function into segments. In each segment the relationship could be expressed in a linear function. In this way the quadratic optimization problem is transferred into a linear optimization (shown in
Figure 1).
Figure 1.
Liner processing of quadratic function.
Figure 1.
Liner processing of quadratic function.
Assume the quadratic function has been divided into
N segments. Then the function could be expressed as a piecewise linear function [
42]
. When
g ∊ [
gmin +
nΔ,
gmin + (
n+1)Δ]:
In Equation (48) n = 0,1,…,N−1 and Δ is the length of the segments Δ = (gmax− gmin)/N.
For optimization of objective Equations (32) and (44), the multiplication of two binary variables should be dealt with. This paper divides the calculation of startup-shutdown coal consumption
into two parts,
i.e., unit startup part and shutdown part. And the startup-shutdown coal consumption of unit
j at time
t could be calculated by Equations (49) and (50):
wherein
and
are respectively startup and shutdown coal consumption of unit
j at time
t;
and
are coal consumption coefficient of thermal unit startup and shutdown, in this simulation
. And total coal consumption amount could be calculated by Equation (51):
The simulation has been implemented in the GAMS optimization software using CPLEX 11.0 linear solver. The CPU time required for solving the problem for different case studies with an idea pad 450 series laptop computer powered by core T4300 processor and 2 GB of RAM was less than 10 s.
8. Case Study
8.1. Simulation Scenarios
To study ESSs’ and DRPs’ influence on system wind power consumption capacity, this paper sets four simulation scenarios:
Case 1: Basic scenario. In this case ESSs and DRPs are not considered, it is a scheduling optimization problem with wind power.
Case 2: ESSs scenario. In this case ESSs are taken into consideration but DRPs is not. Four energy storage systems are added into the scheduling system. The storage capacity is 400 MW and the charging-discharging power limitation is 80 MW.
Case 3: DRPs scenario. In this case DRPs is taken into consideration but ESSs are not. The electricity price in peak load period and valley load period are respectively increased and decreased by 25%.
Case 4: ESSs and DRPs scenario. In this case both ESSs and DRPs are taken into consideration. Four energy storage systems are added into the scheduling system and the electricity price in peak load period and valley load period are increased and decreased by 25% respectively.
8.2. Basic Data
To simulate the model proposed by this paper, 10 thermal units, one wind power farm and four energy storage systems are chose as the simulation system. According to demand load distribution characteristics and voltage level, users could be classified into A and B types. Both A and B have I, II and III three different voltage level users. Load demand distributions of users are shown in
Figure 2. The line-loss of voltage level I, II and III are respectively 5.5%, 5.0% and 4.5%. Electricity prices before implementing TOU of user type AI, AII and AIII are respectively 464, 444 and 424 Yuan/MW·h, and of user type BI, BII and BIII are respectively 623, 593 and 563 Yuan/MW·h.
According to the TOU price mechanism, 24 h are divided into three periods, namely peak load, flat load and valley load periods. Valley load period contains time zone 0:00–5:00 and 21:00–24:00, flat load period contains 5:00–8:00 and 14:00–19:00 and peak load period contains 8:00–14:00 and 19:00–21:00. Electricity price in the peak load period is increased by 25% and in the valley period is decreased by 25%. Demand elasticity coefficients matrixes of type A and B are:
Figure 2.
Load distribution of various users in different voltage ranges (MW).
Figure 2.
Load distribution of various users in different voltage ranges (MW).
The max limitation of storage energy of an energy storage system is 100 MW·h, the max limitation of its charging and discharging power is 20 MW. The initial storage energy of an energy storage system is 0 MW·h. The coefficients of thermal units are listed in
Table 1. From unit 1# to unit 10#, the installed capacity, coal consumption coefficient, pollutant emission coefficient and startup-shutdown time are decreasing while energy efficiency is decreasing.
Table 1.
Coefficients of thermal power units.
Table 1.
Coefficients of thermal power units.
Unit | | | | | aj | bj | cj | | | Sit | θi |
---|
(MW) | (MW) | (MW/h) | (MW/h) | (h) | (h) | (t) |
---|
1# | 250 | 600 | 280 | −280 | 6.44 × 10−6 | 0.274 | 11.71 | 8 | 8 | 25.6 | 4.9% |
2# | 200 | 500 | 240 | −240 | 8.08 × 10−6 | 0.282 | 9.79 | 8 | 8 | 23.1 | 5.3% |
3# | 200 | 450 | 210 | −210 | 1.12 × 10−5 | 0.293 | 8.88 | 7 | 7 | 22.3 | 5.2% |
4# | 180 | 400 | 180 | −180 | 1.84 × 10−5 | 0.297 | 8.48 | 7 | 7 | 19.6 | 5.7% |
5# | 150 | 350 | 150 | −150 | 2.40 × 10−5 | 0.304 | 7.27 | 6 | 6 | 16.2 | 6.1% |
6# | 150 | 300 | 150 | −150 | 3.66 × 10−5 | 0.308 | 6.17 | 5 | 5 | 15.4 | 7.1% |
7# | 120 | 300 | 120 | −120 | 3.74 × 10−5 | 0.317 | 5.26 | 4 | 4 | 12.3 | 6.8% |
8# | 100 | 250 | 100 | −100 | 4.59 × 10−5 | 0.328 | 4.65 | 4 | 4 | 8.1 | 7.3% |
9# | 70 | 150 | 70 | −70 | 4.15 × 10−5 | 0.332 | 3.54 | 3 | 3 | 4.3 | 8.3% |
10# | 30 | 100 | 50 | −50 | 9.01 × 10−5 | 0.337 | 1.43 | 2 | 2 | 2.1 | 7.7% |
In this case the total installed wind power capacity is 1000 MW. Based on the wind power output scenario simulation method in
Section 4.1., we used Matlab to get 100 kinds of basic wind power output scenarios. Then we remove scenarios according to the introduced scenario reduction strategy, and finally keep 20 kinds of basic wind power output scenarios as the basic data of the optimization model. To simplify the calculation, this paper uses the average value of wind power output in 24 h in the 20 cases as available wind power output, as shown in
Table 2.
Table 2.
24 h output power of wind farm.
Table 2.
24 h output power of wind farm.
Time | Available wind power (MW·h) | Time | Available wind power (MW·h) | Time | Available wind power(MW·h) |
---|
1 | 581.5 | 9 | 716.9 | 17 | 480.0 |
2 | 726.2 | 10 | 495.4 | 18 | 372.3 |
3 | 646.2 | 11 | 572.3 | 19 | 264.6 |
4 | 680.0 | 12 | 633.8 | 20 | 406.2 |
5 | 667.7 | 13 | 732.3 | 21 | 523.1 |
6 | 683.1 | 14 | 923.1 | 22 | 310.8 |
7 | 843.1 | 15 | 812.3 | 23 | 415.4 |
8 | 747.7 | 16 | 756.9 | 24 | 566.2 |
8.3. Simulation Results
8.3.1. Case 1: Self-Scheduling Results of System in the Basic Scenario
Case 1 is a reference for the other three cases. ESSs and DRPs are not considered in this case. With the objective of minimizing power generation coal consumption, thermal units and wind power output scheduling results are optimized.
Figure 3 shows their output structure in Case 1. According to
Figure 3, in flat and valley load periods, load is mainly allocated to unit 1#, 2# and 3#. In those periods, unit 1# is always in full generation statue and unit 2# almost in full generation statue. In peak load period unit 4#, 5# and 7# are called.
Figure 3.
Thermal units and wind power output in Case 1.
Figure 3.
Thermal units and wind power output in Case 1.
In the flat load period and valley load period, load demand and load variation are relatively small, so units with high energy efficiency and small pollutant emission has a priority to be called, so units 1# and 2# are called all the time and unit 3# is called to adapt to the load variation. In the peak load period, load demand increases and changes quickly, units 1# and 2# are already in full power generation statue. Although unit 3# is better than other units, unit 3# could not meet the load variation requirement since it need more time to startup-shutdown than small capacity units. Therefore, units with smaller capacity and shorter startup-shutdown time were called to generate. In Case 1, the total coal consumption is 12,006 t.
8.3.2. Case 2: Self-Scheduling Results of System in the ESSs Scenario
In Case 2, this paper considers ESS’ influence on load demand and system wind power consumption capacity. Compared with Case 1, the electricity balance constraint is changed and charging-discharging constraint of ESSs is added in this case.
Figure 4 shows thermal units and wind power output structure in Case 2. According to
Figure 4, in the flat load period and valley load period, the output structure is similar to that in Case 1. Load is mainly allocated to units 1# and 2# and unit 3# is called for adaptation. In the peak load period units 4#, 5# and 8# are called.
Figure 4.
Thermal units and wind power output in Case 2.
Figure 4.
Thermal units and wind power output in Case 2.
The energy storage system can influence the demand load curve by its charging and discharging behavior, making the load curve smoother and load demand changes not as quickly as that in Case 1. Compared with Case 1, small installed capacity units’ output decreased, units 2# and 3# output increased (such as 4–7 and 15–17 period). In Case 2 the total coal consumption is 11,702 t.
8.3.3. Case 3: Self-Scheduling Results of System in the DRPs Scenario
In Case 3, TOU price’s influence on load demand is considered and the electricity price in the peak load period and valley load period are respectively increased and decreased by 25%. According to Equations (1)–(11) load demand with demand response could be calculated. Demand load curves with and without demand response are drawn in
Figure 5. When considering demand response load demands in peak load period were decreased and load demand in valley load period was increased.
The optimized thermal units and wind power output structure of this case are shown in
Figure 6. In Case 3, large capacity units’ output steadily, and other units were mainly called in peak load period. Because of the influence of demand response, the demand load curve has become much smoother, which makes units 1# and 2# generate steadier and the units called for peak shaving could be used for wind power’s backup service. In Case 3 total coal consumption is 11,258 t.
Figure 5.
Load demand curve before and after considering demand response.
Figure 5.
Load demand curve before and after considering demand response.
Figure 6.
Thermal units and wind power output in Case 3.
Figure 6.
Thermal units and wind power output in Case 3.
8.3.4. Case 4: Self-Scheduling Results of the System in the ESSs and DRPs Scenario
In Case 4 the influence of ESSs and DRPs are considered. The optimized thermal units and wind power output structure are shown in
Figure 7. Compared with the former three cases, units 1# and 2# generate steadily, unit 3# generates in the flat load period, and unit 5# is called in the flat and peak load period.
Figure 7.
Thermal units and wind power output in Case 4.
Figure 7.
Thermal units and wind power output in Case 4.
With the influence of ESSs and DRPs, system’s demand load curve has become smoother. Load was mainly allocated to high energy efficiency and small pollutant emission units. In the valley load period, the demand load was increased and small capacity thermal units could act as backup service, so wind power output increased significantly. In Case 4 total coal consumption is 11,022 t, which is the lowest of the four cases.
8.4. Result Analysis
To compare wind power consumption, and the system’s economic and environmental benefits in different cases this paper comparatively analyzes demand load, wind power output, energy storage system charging-discharging behavior, thermal units’ output and system’s economic and environmental benefits in four cases.
8.4.1. Demand Load
The system’s load structure in the four cases is listed in
Table 3. Compared with Case 1, in Case 2, the load proportions of the valley load and flat load periods increased while the load proportion of the peak load period decreased. The maximum demand load decreased while the minimum demand load remained the same, and the peak-valley ratio decreased from 2.26 to 2.20. In Case 3, load proportions changed like those in Case 2 but more dramatically so. The maximum demand load decreased and the minimum demand load increased, and the peak-valley ratio decreased from 2.26 to 1.77. In Case 4 the variation amount is the maximum. The peak load proportion decreased from 41.06% to 37.21% while the valley load proportion increased from 25.93% to 28.05%. The peak-valley ratio decreased to 1.63. Those results show that both ESSs and DRPs could help load shifting. The load shifting effect reaches the maximum when both ESSs and DRPs are introduced.
Table 3 lists the load demand structures in the four cases.
Table 3.
Load demand structure in four cases.
Table 3.
Load demand structure in four cases.
Cases | Load structure (%) | Max load (MW) | Min load (MW) | Peak-Valley ratio |
---|
Valley | Flat | Peak |
---|
Case 1 | 25.93 | 33.01 | 41.06 | 2905 | 1284 | 2.26 |
Case 2 | 26.09 | 33.16 | 40.74 | 2830 | 1284 | 2.20 |
Case 3 | 28.38 | 34.35 | 37.27 | 2561 | 1445 | 1.77 |
Case 4 | 28.50 | 34.29 | 37.21 | 2483 | 1525 | 1.63 |
8.4.2. Wind Power Output
Compared with Case 1, wind power output increased from 12,810 MW·h to 14,173 MW·h and the wind power consumption ratio increased from 88.0% to 97.4% in Case 4. Wind power output in Case 1 is the lowest. According to
Table 4 in Case 1, abandoned wind power exists in time period 1–3, 5, 15, 16–17, 24 and the total abandoned power is 174 MW·h. Abandoned wind power in four cases are 1747, 1234, 1164 and 383 MW·h, respectively. Wind power output in Case 4 achieves its maximum value. Wind power output mainly increased in flat and valley load periods (time period 0–4 and 15–17).
Table 4 shows wind power consumption situations in the four cases, and wind power output in the four cases is drawn in
Figure 8.
Table 4.
Wind power consumption situations in four cases.
Table 4.
Wind power consumption situations in four cases.
Cases | Wind power output (MW·h) | Total abandoned wind (MW·h) | Wind power output proportion of the total output (%) | Wind power consumption ratio (%) |
---|
Case 1 | 12,810.1 | 1747 | 26.1 | 88.0 |
Case 2 | 13,322.6 | 1234 | 27.2 | 91.5 |
Case 3 | 13,392.4 | 1164 | 28.1 | 92.0 |
Case 4 | 14,173.4 | 383 | 29.7 | 97.4 |
Figure 8.
Wind power output in the four cases.
Figure 8.
Wind power output in the four cases.
According to the above results, energy storage system and demand response could change demand load distribution to some extent and decreased the peak-valley ratio. In this way, DRPs and ESSs could relieve the scheduling pressure caused by wind power output anti-load distributed characteristics, improve power system wind power consumption capacity and decrease abandoned wind power.
In Case 1, wind power could output effectively only in the peak load period. In the valley load period load is mainly allocated to highly efficient units (units 1# and 2#) and abandoned wind power exists. With the influence of ESSs and DRPs the demand load curve becomes smoother and demand load in the valley load period increased. Small capacity units used for peak shaving would be called less. Therefore, small capacity units could provide backup service for wind power in valley load periods. Increased load demand in valley load periods gives wind power more space to output, so abandoned wind power decreased.
8.4.3. ESSs Charging and Discharging Behavior
Energy storage system’s charging and discharging behaviors in Case 2 and Case 4 are listed in
Table 5. Energy storage systems mainly charge in the valley load and flat load periods, which would increase load demand, and discharge in the peak load period, which could supply electricity for power systems. Compared with Case 1, energy storage systems would be more involved in load shifting, and charging-discharging electricity increased in Case 4.
Table 5.
Charging and discharging optimization results of energy storage system (MW·h).
Table 5.
Charging and discharging optimization results of energy storage system (MW·h).
Scenarios | Valley period | Flat period | Peak period |
---|
Charging | Discharging | Charging | Discharging | Charging | Discharging |
---|
Case 2 | 80.5 | 0.5 | 75.8 | - | - | 155.8 |
Case 4 | 131.3 | 51.3 | 156.3 | 156.3 | 62.6 | 142.6 |
8.4.4. Thermal Power Output
Thermal units’ total output keeps decreasing from Case 1 to Case 4. Unit 1# remains in full generation mode in the four cases, and unit 2#’s output increased from 10,975 MW in Case 1 and Case 2 to 11,023 MW in Case 3 and 11,565 MW in Case 4. The output of unit 3# also increased from Case 1 to Case 4. Conversely, the unit 4#, 5# and 7# output decreased. Unit 8# is only called to generate in Case 2.
For thermal units, the smoother demand load curve reduces the load shifting requirement, which means less startup-shutdown times. Units with high efficiency and low pollutant emission are more called to generate. In this way, power generation coal consumption and startup-shutdown coal consumption are decreased. However, with the influence of ESSs and DRPs, thermal units’ total electricity sales decreased. With wind power utilization efficiency improving the market share and profits of thermal units would both decrease. Therefore, a coordination mechanism should be applied to balance the benefit relationship between thermal and wind power.
Table 6 lists the output allocation of thermal power units in the four cases.
Table 6.
Output allocation of thermal power units in four cases (MW).
Table 6.
Output allocation of thermal power units in four cases (MW).
Unit | Case 1 | Case 2 | Case 3 | Case 4 |
---|
1# | 14,400 | 14,400 | 14,400 | 14,400 |
2# | 10,975 | 10,975 | 11,023 | 11,565 |
3# | 5873 | 5873 | 6216 | 6448 |
4# | 3437 | 3437 | 3283 | 2705 |
5# | 2823 | 2823 | 1100 | 600 |
6# | 0 | 0 | 0 | 0 |
7# | 120 | 120 | 0 | 0 |
8# | 0 | 0 | 650 | 0 |
Total output | 37,629 | 36,672 | 35,718 | 35,196 |
8.4.5. System’s Economic and Environmental Benefits
Thermal units’ coal consumption and pollutant emission in the four cases are listed in
Table 7 (wherein coal cost is 600 Yuan/t and consume 1 t coal would emit 2.89 t CO
2 and 2.05 kg SO
2 [
43]). Compared with Case 1, thermal units’ output and startup-shutdown coal consumption decreased, system’s average coal consumption decreased and CO
2 and SO
2 emission decreased in Case 4. Therefore, system’s power generation cost and pollutant emission cost decreased.
Compared with Case 1, Case 2 decreased coal consumption by 304.5 t, which means a decreased coal cost of 18.3 × 10
4 Yuan. Compared with Case 3, Case 4 could also decrease coal consumption and pollutant emissions. Part of the economic benefits could be used to build a reasonable cost-effective distribution mechanism and provide subsidies for energy storage systems. This could help energy storage systems achieve a fiscal balance and promote long-term development of the energy storage industry.
Table 7 lists the system coal consumptions and pollutant emissions in the four cases.
Table 7.
System coal consumption and pollutant emission in four cases.
Table 7.
System coal consumption and pollutant emission in four cases.
Cases | Thermal power | System coal cost (g/kW·h) | Generation cost (104 Yuan) | CO2 (t) | SO2 (kg) |
---|
Output (MW·h) | Coal (g/kW·h) | Start-stop coal (g/kW·h) |
---|
Case 1 | 37,629 | 319.08 | 3.15 | 244.70 | 720 | 34,699 | 24,613 |
Case 2 | 36,672 | 319.10 | 2.81 | 238.49 | 702 | 33,819 | 23,989 |
Case 3 | 35,718 | 315.96 | 2.63 | 236.95 | 677 | 32,615 | 23,136 |
Case 4 | 35,196 | 313.17 | 1.75 | 231.03 | 661 | 31,854 | 22,595 |
For system efficiency, the introduction of TOU price and energy storage systems could decrease abandoned wind power and decrease total coal consumption. The average power generation coal cost would decrease obviously. For environment protection, the introduction of TOU price and energy storage systems could improve system’s energy-saving levels. Compared with Case 1, the other three cases decreased coal consumption by 30.45 t, 720.9 t and 984.3 t, respectively, CO2 emission by 907.5 t, 2148.3 t and SO2 emission by 2733.4 t, 624.3 kg, 1477.9 kg and 2017.9 kg.
According to the above analysis, TOU price and energy storage systems could help increase wind power consumption capacity, decrease energy consumption, decrease pollutant emissions and achieve environmental benefits.