1. Introduction
Public-Private Partnerships (PPPs) have become useful instruments to improve the road infrastructure sector in multiple jurisdictions worldwide [
1,
2,
3]. These initiatives involve long-term arrangements in which each risk is shared between private and public actors or shifted to the actor that can manage it best [
4]. In a typical PPP road infrastructure project, the risk allocation process consists of multiple contractual transactions in which the private sector assumes specific project-related risks and agrees to design, build, finance, operate, and maintain the asset in exchange for adequate financial returns [
5]. Consequently, PPPs can be beneficial to the public and private parties because they facilitate project delivery, provide long-term operation and maintenance services, and ensure suitable compensations throughout projects’ lifecycle phases [
6,
7]. Moreover, PPP investments are crucial to empowering communities and achieving sustainable development, which is important because the United Nations (UN) has identified the development of proper infrastructure as one of its Sustainable Development Goals (SDGs) [
8].
Public agencies have traditionally procured and developed PPPs through solicited proposals (SPs) procedures, which often involves competitive tendering processes [
9]. However, to manage the deficient ability of the public sector to formulate PPP initiatives, some jurisdictions employ unsolicited proposals (USPs) to develop PPP initiatives that are originated within the private sector [
10]. In this context, the USP method is defined as a PPP approach in which a private investor identifies and proposes a public project to a public agency without any formal invitation [
11]. For both initiation processes (i.e., SPs and USPs), researchers and practitioners highlight the benefits associated with the ability of public agencies to transfer risks to private partners, as well as the capacity of the private sector to deliver projects according to pre-established service-based performance outputs [
10].
However, despite their potential benefits, several road PPP development processes worldwide (originated by either SP or USP) have been affected by multiple difficulties taking place across projects’ lifecycle phases. Scholars argue that such difficulties are mainly because PPP transactions are affected by opportunism, uncertainty, and bounded rationality phenomena in the long-term [
12,
13,
14,
15]. The literature indicates that these challenges may be exacerbated within the transportation sector because, in this domain, public-private agreements usually involve a combination of autonomous private partners and high transaction and supervision costs from the public authorities [
16,
17,
18]. Risk allocation and management processes, as a result, seemingly play a crucial role in overcoming development barriers and enhancing private sector’s efficiencies, while reducing costs associated with safeguarding public interests. This is because implementing proper risk management mechanisms contributes to increase contractual transparency, improve communication between public and private counterparties, enhance problem-solving procedures, and facilitate conflict-resolution practices [
19,
20,
21,
22,
23].
PPP scholars have conducted studies focused on getting a better understanding of how to improve risk management and allocation practices [
23,
24,
25,
26,
27,
28,
29]. However, the literature on this subject remains fragmented and inconclusive. Researchers appear to adopt the perspectives of either public or private sectors when analyzing assessment frameworks, governance structures, and optimization models, among other risk-related topics [
30,
31]. There is little evidence of research examining how risk management is done in multiple real projects and how it should be done in practice. For instance, most papers use interviews or surveys and do not directly examine PPP contractual documents and legislation [
23,
30,
32,
33]. Furthermore, research in this domain does not seemingly differentiate among different project delivery methodologies (e.g., Build-Operate-Transfer, Design-Build-Operate-Maintain, Design-Build-Finance-Operate-Maintain) or initiation mechanisms (e.g., solicited and unsolicited proposals) [
25,
32,
34]. It seems to mainly focus on delivery approaches employed in specific countries (e.g., Australia, China, and the UK) [
23,
33,
35] or sectors (e.g., utilities and health care) [
36,
37,
38,
39]. Additionally, concerning sustainability, although scholars recognize it as an important topic for PPPs, there is scarce evidence of PPP research available on the relationship between sustainability and risk management for different PPP types [
34,
40].
In this context, risk is a topic that has been extensively studied from multiple perspectives, and it can be connected to the origin and resolution of multiple PPP difficulties within the road infrastructure sector [
19,
29,
31]. Allocation and management procedures are essential to establish how each one of the risks associated with road PPPs is transferred, shared, and managed among public and private counterparties [
29,
41]. Taking into account that these procedures are specified in the contract agreement, this document becomes a key instrument to systematically study the way responsibilities are distributed between project participants and the mechanisms through which risk and incentives are assigned to PPP partners [
26,
29]. Consequently, to improve risk management and enhance PPP development, the PPP contract is a crucial tool to cohesively examine the relationship between project risks and management factors related to project delivery methodologies, initiation mechanisms, governance structures, and sustainability issues [
19,
31,
41,
42].
Building on literature related to road infrastructure, PPP governance, risk management, and sustainability, this study seeks to get a better understanding of the PPP risk management practices in the road infrastructure sector [
2,
12,
14,
28,
29,
32,
43,
44,
45,
46,
47,
48]. In order to do that, authors examine risk allocation processes from an integrated perspective by incorporating managerial (i.e., different project initiation approaches) and sustainability (i.e., economic, social, and environmental aspects) considerations into the analysis. To achieve this goal, this study assesses PPP contracts in the Chilean road infrastructure market and examines the perception of key PPP actors in Chile. With this in mind, the authors intend to address a current research gap in the extant literature: The study of PPP risks from an integrated perspective, based on data incorporated from multiple real cases, and by considering management and sustainability implications.
Consequently, this study leads to answer: (1) How do project initiation processes (i.e., solicited and unsolicited proposals) influence risk allocation mechanisms within the Chilean road PPP market? Furthermore, (2) what sustainable implications emerge from such risk allocation mechanisms? By answering these questions, this work seeks to gain insight into the differences between SPs and USPs and provide a comparative analysis of risk allocation schemes in conjunction with their sustainability-related implications. The authors seek to achieve this goal by conducting a comprehensive content analysis of contractual documents of all the Chilean road PPP projects since 2010. The content analysis is supported by semi-structured interviews with Chilean PPP experts and the development of a risk allocation matrix. This allows the authors to further compare and examine the PPP contracts at the light of experts’ opinions and risk allocation procedures in multiple projects. In this sense, this study strengthens the PPP body of knowledge by exploring risk allocation practices and their sustainability implications across different initiation processes.
3. Materials and Methods
This study seeks to understand risk allocation mechanisms in road PPP development by examining managerial (i.e., project initiation processes, solicited and unsolicited proposals) and sustainability (i.e., economic, social, and environmental impacts) considerations. To do so, the authors employed elements from three knowledge domains: PPP development, sustainability, and risk allocation and management. Because these three fields are extensive and can be analyzed from several perspectives, this study uses PPP contracts as its main analytical instrument and as a common point to jointly explore these three topics. Contracts have been used for PPP investigations before because they are the representation of governance mechanisms, and as such, they are the result of public-private interactions and decision-making processes [
19,
31,
41,
42]. In this paper, as a result, contracts are employed as a means to explore decisions made concerning assigning and sharing project risks at the light of initiation processes and sustainability dynamics.
This work focuses on Design–Build–Finance–Operate–Maintain (DBFOM) transactions developed after 2010 within the road infrastructure sector in the Chilean PPP market. This is because several reasons: (1) Chile was chosen as a case of study given that this country has developed a consolidated highway concession system that includes 32 road PPP transactions since 1993, a number similar to the road PPP projects developed in countries, such as USA (32 initiatives) and Canada (30 initiatives) [
112]; (2) the road infrastructure sector comprises the highest number of PPP transactions among all economic sectors in Chile (i.e., since 2010, the total number of PPP agreements in Chile includes ten roads, nine airports, three hospitals, two urban projects, and two hydropower projects) [
113]; (3) the whole set of road projects developed under Law 24010 are toll road initiatives that comply with the characteristics of Design–Build–Finance–Operate–Maintain agreements as described in the PPP literature [
15,
112,
114,
115]; and (4) since 2010, Chile has conducted ten road concession initiatives thanks to the implementation of new PPP enabling legislation (i.e., Law 24010) directed to enhance PPP development in the road infrastructure sector [
113]. Furthermore, since 2010 several developing and developed countries have increased their interest in developing PPP programs influenced by the 2008 global economic crisis [
31,
116,
117].
The research methodology is organized as follows:
Section 3.1 introduces the data sources used for the analysis (i.e., a literature review, the contract documents, and semi-structured interviews);
Section 3.2 details the content analysis developed to identify risk allocation procedures; and
Section 3.3 describes the procedure for conducting and analyzing the semi-structured interviews.
3.1. Data Sources
3.1.1. Literature Review
The first step towards analyzing PPP risks in SPs and USPs in this study was to identify the most important risks for public-private agreements and define them based on the PPP-related literature. Building on the multiple PPP- and risk-related studies [
2,
23,
29,
33,
42,
118], the authors established a list of the most relevant risks for public-private initiatives.
Table 1,
Table 2 and
Table 3 show the risk list developed, including their corresponding descriptions. Risk descriptions are based on multiple investigations in which the selected risks have been defined and analyzed. In line with that,
Table 1 depicts the political and economic risks associated with PPPs. These concerns are usually examined across the initial or general phases of the PPP projects.
Table 2 depicts risks related to the project site and construction activities within the construction phase. Finally,
Table 3 describes the operation and termination risks.
3.1.2. Contract Documents
The goal of this study was to examine risk allocation procedures in Chilean SPs and USPs within the road infrastructure sector. This analysis was done to gain insight into different risk management mechanisms and analyze their sustainability implications. This analysis was conducted by exploring the most recent DBFOM highway contracts with financial closure (i.e., road PPP contracts with financial closure as established in Law 20410) from 2013 to 2019. As shown in
Table 4, ten projects met these parameters, accounting for a total of 369 km roadway and an initial total investment of USD 3348 million. This set of initiatives differ in scope, duration, and other project parameters. These projects were selected given that those variations allow a suitable comparative and longitudinal analysis through the total sample of the highway DBFOM that reached financial close within the current PPP legal framework. Specifically, all PPP road contracts in Chile are fully integrated DBFOM contracts that imply project finance schemes with user charges, in this case, toll collection.
The authors analyzed both the request-for-proposal documents and the PPP contracts with their corresponding addenda. This information was obtained from the official online platform of the Chilean government for PPP procurement processes [
113]. Each project included multiple documents that comprised around 400–500 pages in total.
3.1.3. Semi-Structured Interviews
Apart from contractual documents, data collection efforts also included ten face-to-face semi-structured interviews with PPP experts. These interviews were conducted to improve research validity by improving external trustworthiness. As shown in
Table 5, all of the interviewees possessed eminent practical experience in Chilean PPP projects. For this research, each one of the interviewees was chosen because of his/her experience and role according to the field of experience (i.e., academic, project manager, contract manager, consultant, government official, or O&M contractor). In this regard, the authors searched for professionals with more than 5 years of experience in road PPP projects. The group of experts included multiple backgrounds within the public and private sectors: Consultants, contract managers, academics, project managers, O&M contractors, and government officials. All interviews lasted between 60 and 100 min and were recorded to facilitate analysis and to ensure accuracy.
The authors developed a questionnaire protocol that every experienced professional received and approved. The questions were designed in order to find implications and insights instead of quantities and numeric indicators. The questionnaire elaboration process was based on a comprehensive literature review to implement bias-reduction mechanisms employed in other studies [
29,
95,
117,
120,
121,
122,
123,
124,
125,
126,
127]. The questions were focused on the most critical risks, due to their impact, risks that have arisen more disputes and renegotiations, changes and flexibility in risk allocation, and issues related to sustainability and risks. Consequently, ten face-to-face interviewees were developed.
3.2. Content Analysis
Based on the contract documentation and PPP-related Acts collected, this study used content analysis to identify risk allocation procedures. This methodology was chosen because makes replicable inferences by interpreting and coding text [
128]. Moreover, it is an effective observational research method to systematically evaluate the content of documents, analyze recorded communications [
129], and characterize extensive datasets [
130]. It can be applied through qualitative or quantitative perspectives and inductive or deductive approaches [
131]. Consequently, for this study and considering the collected information, the authors implemented an inductive and qualitative technique to improve the comprehension of risk management in SPs and USPs.
Following the analytical framework proposed by Nguyen et al. [
29], a three-stage approach was implemented to ensure replicability and reliability [
132]. First, a conceptual risk matrix was developed. Building one PPP-related literature and Chilean institutional documents focused on PPP development and risk management [
2,
29,
32,
112,
133,
134], a total of 36 risks were identified as necessary for studying the Chilean context. Second, based on the risk matrix, the analysis rubric was designed to examine contracts and tender documents. Third, the rubric was filled using data related to contracts and tender documents. This information was subsequently organized and qualitatively examined to identify both relevant contractual provisions and the way each one of the 36 risks identified from the literature was allocated in each PPP project under analysis.
3.3. Analysis of Semi-Structured Interviews
The aim of conducting these interviews was to examine qualitatively risk perceptions about what the respondents considered the most critical risks. In this sense, the interviews contributed to examine further the risk allocation mechanisms identified from the PPP-related literature and Chilean PPP documents. They also helped to confirm the findings obtained from the content analysis of contracts and tender documents. Moreover, because experts were asked to suggest additional risk allocation criteria, interviews complemented the information collected during the content analysis stage. Overall, the semi-structured interviews were analyzed to determine risk allocation critical factors associated with risk impacts, contractual disputes, and changes in risk allocation and risk management practices.
5. Discussion
5.1. Similarities in Risk Allocation between SPs and USPs
The findings indicate that most of the risks were homogeneously allocated across the studied projects regardless of their initiation processes. These were mostly assigned to private developers and grouped in categories, such as financing, project site, construction, and operation. According to Kivleniece and Quelin [
48], these allocation patterns are consistent with risk allocation criteria for PPPs, as discussed in the PPP literature [
23,
33,
135]. Moreover, this high proportion of risk allocated to private partners was expected given that road PPPs are autonomous structures. This means that, for the Chilean road infrastructure sector, risk allocation processes encourage private partners to assume an important number of risks, motivating them to look for private efficiencies and profit incentives. In other words, although private partners are required to deal with a high number of PPP-related limitations and uncertainties within the Chilean market, they seemingly seek to implement efficient and effective procedures across projects’ lifecycles in order to obtain their corresponding economic and financial returns. As a result, based on these allocation practices, Chilean contracting authorities are mainly focused on verifying and monitoring contractual compliance.
In line with that, the findings also suggest that Chilean authorities have made important efforts focused on developing well-designed PPP contracts for both SPs and USPs. According to the studied PPP reports and semi-structured interviews, most procurement documents and contractual provisions have been drafted with the intention of implementing transparent PPP development processes, which have been beneficial in terms of attracting PPP investors. Although such efforts indicate an inclination towards properly implementing contractual governance instruments, they have faced multiple challenges across several lifecycle phases in some projects. Most of these challenges can be associated with not implementing suitable relational mechanisms, as one of the respondents (i.e., project manager from the public sector) claimed: “[C]oncessionaires from certain countries have less interest in entering this market, (for example) French (companies) considered the (Chilean PPP) contracts very complicated because French people are more used to build trust by (orally) discussing and negotiating PPPs”.
Most of the respondents (R1–R4, and R6–R7) considered as highly critical all the risks assumed by private partners within the studied initiatives. They argued, for instance, that allocating the design risk is problematic in Chile. According to the interviewees, it opens the door to claim for renegotiations, given that, for SPs, projects’ conceptual designs are developed by the contracting authority without private partners’ participation. On the other hand, various respondents (R1, R2, R3, R6, and R7) considered archeology and fossils as one of the most critical risks because it can severely delay the construction phase. A private consultant highlighted the criticality of this risk: “[T]here was a PPP project where thousands of indigenous bones were found; after two years, the archeologists had not recovered even 10% of the bones; consequently, the project was early terminated”. Accordingly, respondents added that this risk could be mitigated in projects’ early stages by improving communication between public and private organizations.
On this matter, it is essential to consider that some allocation patterns offer opposite perspectives as compared to what the international literature reports for similar risk management practices in other jurisdictions [
23,
33,
42,
118]. In the UK and China, for example, Chan et al. [
33] and Bing et al. [
23] found that the private partner borne the
inflation risk. Moreover, in Australia, the UK, China, and India, the private party usually assumes
price adjustment risks [
23,
33,
42,
118]. These cases differ from the Chilean experience, because Chilean PPPs allow for more protection to the private partner in some cost-related risks (e.g.,
inflation, price adjustments, revenue during construction, and
revenue payment). Interviewees highlighted this higher protection to the private sector. For instance, one private consultant exposed that:
“[R]isk distribution … was extremely favorable for the private sector …, not only in terms of prices and profits but also in terms of the arbitration mechanism that is especially favorable for concessionaires”.
On the other hand, while in Australia, the UK, and India
site acquisition is traditionally allocated to the public sector [
23,
118], in Chile, such risks are shared. This indicates that Chilean PPPs allow for private partners to facilitate land acquisition procedures by reducing transaction and supervision efforts of public authorities. Furthermore, various respondents (R1, R2, R3, and R7) argued that
connections to the site were one of the most critical risks, and more public involvement is required to create incentives for the public services companies to facilitate procedures and reduce utility charges. Interviewees highlighted the criticality of this risk as one private consultant indicated that this risk affects the budget and the schedule of the projects given that
“public companies do not have incentives to expedite and reduce the costs associated with utility works”.
Finally, it is worth noting that the public party uniformly bore three main risks. In respect to
political opposition to the project, this includes factors considering how local governments, pressure groups, users, and residents may offer resistance to PPP development. According to the literature, as in the Chilean case, the public sector usually assumes this risk given that private investors perceive political risks as a critical aspect that may influence the decision to participate or not in PPP projects [
56,
79,
136,
137]. On the other hand, regarding risks related to
disposal of surplus land and
termination by the contracting authority, the literature and interviews provide scarce evidence of allocation and management practices. This suggests that allocation procedures for such concerns have not traditionally been studied, and further research is required for both risks.
5.2. Differences in Risk Allocation between SPs and USPs
The findings confirm that, despite the similarities in risk-related procedures, the studied contracts exhibit significant differences concerning allocation patterns between USPs and SPs. In general, risks were allocated more uniformly in USPs (i.e., 32 risks) than SPs (i.e., 27 risks), which implies that the government prefers to reduce variations in risk allocation procedures for USPs. This pattern suggests that Chilean authorities seem to prioritize standardization in USPs in order to safeguard competition conditions [
138]. In doing so, Chilean authorities seem to prefer contractual over relational governance mechanisms.
Higher standardization in USPs aims to minimize conflicts and avoid litigation, due to the higher risk-exposure of such projects. This is because USPs are first-structured by private partners who are interested in winning the future project bid. However, this may also indicate that, for USPs, the contracting authority has a limited amount of time and resources to discuss and negotiate contractual and procurement documents properly [
71]. In other words, this may suggest that Chilean contracting authorities do not have enough capacity to facilitate the implementation of efficient relational mechanisms and are mostly focused on delivering road PPP projects through applying contractual instruments. Interviewees highlighted this issue, as one public project manager commented that
“the government has an incentive to award as many contracts as possible, which is against good planning (and control) practices since this means low-supervision efforts across projects’ phases”.
The allocation patterns for
performance, delay by construction subcontractor, and
ground condition clearly show that risk management practices may have significant variations between USPs and SPs. Regarding this, for example, Hodges [
66], explored the problems associated with unsolicited proposals, including Chile, with a particular focus on risks associated with contract transparency and competition conditions. According to this author, in order to cope with transparency issues in unsolicited initiatives, governments usually allocate some of the most significant risks to private partners (i.e.,
ground condition, delay by construction subcontract, and
performance). Along with that, Yun et al. [
10] and Marques [
65] concluded that such allocation practices mean that the private sector needs to excel in managing USPs to develop these types of projects successfully.
The findings also confirm that contextual factors play an important role in terms of developing SP initiatives. Chilean authorities seem to prefer mechanisms directed towards incorporating projects’ unique features into the risk allocation processes of SPs. This facilitates contractual and financial closure procedures because it contributes to clarifying the risk exposure of PPP investors [
79]. As shown in
Table 7, for instance, while
change in law was allocated to the public sector in all USPs, it was shared in SP4. The way such risk is partially transferred to private partners is described in one of the contract provisions for SP4:
“In the event of regulatory changes related to the Environment Impact Assessment System (EIAS) taking place between the contract award ceremony and the beginning of the construction phase […] It will be the total responsibility of the concessionaire to obtain the corresponding Environmental Qualification Permits”.
Similarly, while the public party bore demand risk for every USP, this was transferred to the private partner in SP1 and SP4. For these two initiatives, it is clear that this allocation procedure was implemented because the uncertainty associated with traffic counts was low. SP4, for instance, is the only interurban project connecting La Serena (i.e., one of the main capital cities in Chile) with the national network. SP1, on the other hand, is a 5 km toll road (i.e., the shortest interurban project in Chile) that has been developed as a way to extend the period of an already-finished concession. In both projects, as a result, the demand risk was not significant and, consequently, government agencies did not need to ensure a minimum fixed level of revenues in case of the traffic volumes being lower than expected.
5.3. Analysis of Risk Allocation and Sustainability
Based on the studied PPP contracts and responses from the interviewees, there are two main risks related to the three-dimensional concept of sustainable development: [E]nvironmental impact and natural hazards and protesters. These two concerns are mostly linked to environmental and social sustainability issues. Both risks were considered as some of the most critical ones by most of the interviewees (R1–R4, and R6–R7). This criticality highlights the relevance of sustainability in PPP risk allocation processes. In this regard, one private consultant emphasized that “environmental risks usually involve other risks such as acts of God or change in the law”. Also, a public project manager expressed that the protest-related risk “has never really been addressed”, and a public contract manager added that “communities often do not value the relevance of the infrastructure investment, and certain opportunistic behaviors appear to increase the demands of the project because they perceive the private company as a very profitable partner; communities should be involved in the planning phase (of the PPP projects)”.
Although public and private PPP experts recognize the importance of sustainability-related concepts for PPPs, highway PPP projects in Chile have been developed without fully considering the environmental and social dimensions of sustainability. This is in part because public hearings with communities affected by PPP projects are not legally required in this country [
8]. Although environmental impact assessments (EIAs) have been implemented in some Chilean initiatives (as an optional pre-construction process), they seemingly do not facilitate the analysis of the relationships between
environmental impact and natural hazards and project construction and operation performance. In this matter, a public project manager exposed that
“although they [environmental-related risks] are apparently assigned to the private sector they are shared to the public when there are overlaps or cost overruns”. Considering the above, homogenizing the allocation of this risk to share it between the parties may be a solution; consequently, an academic proposed that
“these risks should not be allocated exclusively to the private partner. These risks should be shared due to the influence of the general public over environmental agencies”.
Given the limitations associated with EIAs and social consultation processes, communities are seemingly not included in the governance scheme of PPPs (at least in the procurement phase). This is in part because the inclusion of communities requires the implementation of good communication channels between the general public and public and private partners. However, Chilean government agencies have proven unable to implement relational mechanisms focused on building trust and collaboration patterns among all stakeholders. Therefore, Chilean PPPs have created value on a limited basis, given that most road concessions seem to focus on generating economic value, without comprehensively incorporating strong social value-creation mechanisms. This seeming preference for economic value has created a reinforcing cycle in which total value (i.e., the sum of economic and social value) continually diminishes project after project. Consequently, for the Chilean case, neglecting social participation reinforces social disapproval for the PPP program, which in turn reinforces protests and affects private value capture mechanisms.
The literature supports this finding. For instance, Kivleniece and Quelin [
48] argue that this pattern of behavior is more frequent in road PPPs because such initiatives tend to have autonomous governance structures. This makes communities likely to feel excluded and judge the participation of private companies in PPPs as contrary to their social norms and values. As a result, projects are perceived as illegitimate what encourages distrust among public authorities, private partners, and communities, motivating an increase in protests and complaints.
Additionally, Caldwell et al. [
57] suggest that mutual understanding must be achieved to improve the social environment. Based on that, the collected evidence suggests that the Chilean government must improve the inclusion of environmental entities and community-based organizations within the PPP planning phase to enhance the application of relational mechanisms, increase PPP value, and improve legitimacy, thus, reducing the likelihood of protests against PPP projects. In line with that, the private sector must also contribute by building trust with communities. This contribution can help to reduce negative perceptions about public-private agreements and enhance the receptiveness of local communities towards PPPs [
136]. Doing so may also reduce the impact of protests on the monetary value of the projects, improve the ways public sector authorities recognize their political accountabilities and social responsibilities [
139], and expand the protection of social welfare in the long-term.
Apart from the literature, interviewees highlighted the fact that
protests, which is currently one of the most critical risks for Chilean PPPs, had not been allocated in any of the contract documents of the projects under study. Respondents argued that before the 2019 protests in Chile, the government did not consider this concern as a likely risk because they thought that the communities across the country widely supported the national PPP program. However, during the October 2019 protests, some of the movements that obtained more support were the ones focused on
“no more electronic toll collection” or
“no more toll roads”. Between October and December 2019, protestors damaged more than 50 toll facilities, and the central government reduced the toll fees of several PPP highways nationwide [
140]. The public authority must pay all the costs associated with the reconstruction of such facilities and the reduction of users’ fees, due to the absence of proper allocation procedures. This situation is an example that no matter how unlikely a risk may seem, it must be thoroughly analyzed and accordingly allocated.
6. Validation
Overall, data were collected longitudinally, involving all the authors and multiple PPP experts. This was done to obtain reliable evidence to identify risks, allocation patterns, and management and sustainability implications. In this context, triangulation was employed to conduct reliable data collection procedures and implement a consistent case study methodological approach [
141,
142]. In this way, this study was strengthen based on three different sources: Contractual documents for each project (i.e., PPP concessionaire agreement and addenda, request for proposals, and operation reports), interviews with ten Chilean PPP experts (i.e., informants had knowledge about at least one PPP project under study), and PPP-enabling legislation (i.e., Act 20410, Act 20123, and Decree 900).
The validation process involved the following objectives: (1) Ensure the inclusion of all significant risks within the analysis procedure; (2) verify the identification of risk allocation procedures in the contractual documents; (3) achieve a reliable interview process; and (4) guarantee data reliability for the case study analysis. The first objective was accomplished through conducting a broad literature review to identify the key risks to be allocated in PPP projects (i.e., political, economic, project site, construction, operation, and termination risks). The second goal was accomplished by following the analytical framework developed by Nguyen et al. [
29]. This framework consisted of building a risk analysis rubric to examine the contractual documents. For this process, the authors assigned roles, two analysts and two supervisors. In this regard, the roles of supervisors were assigned to the most experienced researchers (i.e., the second and third authors). The analysts (i.e., the first and fourth authors) first reviewed the contracts and interview transcripts, took notes, copied the relevant text segments related to each risk, and established risk allocation of every risk in each one of the projects. In case of discrepancies, both analysts discussed their disagreements. If there was no agreement for any risk allocation procedure after two rounds of discussion, the four participants (including the two supervisors) reviewed and discussed all remaining discrepancies until achieving a consensus. At the end of the process, the analysis rubric and the allocation processes were independently reviewed by the second and third authors.
The third objective was achieved by developing a selection criteria process for the interviewees. Such a process sought to select experts with ample experience in diverse roles within the public and private domains. Moreover, a questionnaire was designed based on a comprehensive literature review to obtain key insights associated with the management and sustainability implications of risk allocation procedures. Finally, to accomplish the fourth objective, triangulation procedures were employed to examine data collected from three different sources: Contractual documents (i.e., PPP concessionaire agreement and addenda, request for proposals, and operation reports), interviews with ten Chilean PPP experts (i.e., informants had knowledge about at least one PPP project under study), and PPP-enabling legislation (i.e., Act 20410, Act 20123, and Decree 900). This study used triangulation to compare risk allocation procedures identified in contractual documents with Chilean PPP-enabling legislation and interviews. This comparison allows for increasing the reliability of the findings through a cross-checking process. This process increases the convergence of results, and allows for obtaining a further understanding of the underlying motives of risk allocation procedures.
7. Conclusions
The PPP-related literature offers multiple examples of studies focused on risk management, risk allocation practices, experiences, and pitfalls of USPs among countries. However, scholars have not thoroughly neither examined the differences between SPs and USPs concerning risk allocation processes nor their sustainable implications. Based on such a research gap, this study employed content analysis of documental evidence and semi-structured interviews of PPP experts to examine how risks are assigned in solicited and unsolicited public-private agreements. The authors focused on Chile, one of the most stable PPP markets worldwide. The analysis uncovered sustainable insights and relationships among multiple risks within different types of projects. A deeper understanding of managerial implications associated with PPPs can be attributed to these findings.
In contrast to previous PPP risk allocation studies, this paper focused on SPs, USPs, and their sustainability implications. A risk content analysis procedure was conducted to examine how risks were allocated in seven SPs and three USPs in road PPP projects in Chile. Results indicate that most of the risks were allocated homogeneously for all projects through the implementation of efficient contractual governance mechanisms. However, this also suggests that, in terms of risk management practices, Chilean authorities have not thoroughly implemented relational instruments as complements of such contractual tools. A comparative analysis of the ten projects analyzed in this study uncovered some interesting practices that reveal the differences in risk allocation procedures between SPs and USPs, in conjunction with their sustainability-related implications.
First, most of the risks were homogenously allocated across all projects and were assigned to the private sector. These risks are related to contextual factors (e.g., political and economic) and project concerns (e.g., financing, project site, construction, and operation). This high exposure for the private partners incentivizes not only private players’ autonomy, but also their need to implement efficient management procedures across all projects’ lifecycle phases. Based on that, public authorities are mainly focused on implementing contractual compliance and accountability processes.
Second, although most risks are transferred to private partners, some significant risks are mutually shared between public and private counterparties. These mostly refer to construction costs and revenue-related risks. This allocation pattern is different from the standard practice in countries, such as the UK and Australia, and means that Chilean officials have sought to improve the attractiveness of their PPP initiatives, and enhance their contractual instruments by offering protection to the private sector’s interests.
Third, the findings confirm that there are significant variances between risk allocation patterns in different project initiation processes. For USPs, the Chilean government has sought to standardize contractual and procurement mechanisms in order to attract investors, safeguard competition conditions, and thus, reducing transaction and supervision costs. This reduces the likelihood of having conflicts and litigation, given the higher risk exposure of these projects. In contrast, for SPs, contracting authorities seem to incorporate contextual factors into their managerial procedures, thus, implementing risk allocation procedures by considering projects’ unique features. This allocation pattern seems to suggest that Chilean authorities prefer to be flexible in terms of adjusting some risks based on the unique features of each project. Hence, the public sector seeks to reduce the tension between the long-term nature of PPP contracts and the need for flexibility in low-risk projects.
Fourth, most of the interviewees considered sustainability-related risks (i.e., environmental impact and natural hazards and protests) as some of the most critical concerns for both SPs and USPs. However, PPP development efforts in Chile have not fully incorporated the environmental and social dimensions of sustainability into their procurement and management procedures. The exclusion of such dimensions in the PPP governance structure has triggered value-creation mechanisms mainly focused on the private sector. This, in turn, has reduced the amount of total value in road PPPs because of the increasing social disapproval of the PPP program. Consequently, the Chilean government must improve relational mechanisms associated with community consultation processes in order to enhance citizen engagement and PPP legitimacy. Given the increasing influence of community organizations, this analysis suggests that Chilean agencies should enhance stakeholder analyses to understand their dependencies, concerns, perceptions, interests, responsibilities, and roles in order to develop a sustainable PPP program.
This research contributes in several ways to multiple bodies of knowledge. First, although scholars have extensively discussed PPP governance mechanisms [
51,
55,
61], and examined multiple PPP risk management procedures [
24,
124,
135] in various infrastructure domains, this paper goes beyond previous research by examining the influence of managerial considerations (i.e., different project initiation mechanisms in DBFOM projects) into risk allocation mechanisms from an integrated perspective. Second, while PPP risk allocation procedures have been widely studied before [
24,
29,
143], few studies have analyzed PPP risks from a sustainability-related perspective. In this regard, this work uncovered the environmental and social implications of PPP risk allocation procedures within the road infrastructure sector. Third, researchers in engineering and managerial fields have focused on improving their understanding of how to improve risk management and allocation practices by developing mathematical models [
24,
144,
145,
146], analyzing surveys [
23,
24,
25,
26,
27,
28,
29], or evaluating interview-related data [
16,
31,
111,
147]. However, this study examined real PPP contractual documents (i.e., PPP agreements, procurement documents, and PPP-enabling legislation) to gain insight into the relationship among PPP initiation processes, sustainability, and risk management. Fourth, this research provides evidence on how Latin American countries deal with PPP contracts and risk management practices. This is important because, in comparison to other jurisdictions [
23,
32,
33,
35,
118,
148], there is little scholarly evidence on how PPPs have been implemented in this region for more than two decades. Fifth, although researchers have widely studied governance mechanisms and their relationships with community consultation and value creation processes [
48], this study goes beyond by examining the link between risk allocation procedures, contractual instruments, and relational governance mechanisms. This has allowed the authors to examine how neglecting sustainability-related risks (e.g., protests) in the PPP planning phase may contribute to diminish PPP value, thus, decreasing the overall PPP program legitimacy and increasing protests in the long-term.
Despite the multiple contributions of this study, future research could explore five main research avenues. First, researchers can conduct risk allocation studies focused on Chilean non-highway PPP projects, such as urban infrastructure, airports, hydropower infrastructure, jails, seaports, healthcare infrastructure, and other public facilities. Second, future research can explore the influence of relational governance mechanisms on risk management through the PPP project’s lifecycle. Third, a comparative study of risk allocation patterns can be conducted between Latin American countries or between developing and developed countries to understand similarities and differences among jurisdictions and explore the motivations underlying these procedures. Fourth, future research could also explore further implications of relational governance mechanisms, such as information sharing, commitment, communication strategies, trust, coordination mechanisms, collaboration, and dispute resolution on risk management practices in road PPP projects. Fifth, researchers can conduct studies focused on the relationship between complexity and performance in PPPs based on procurement complex performance (PCP) issues.
Overall, the findings of this study challenge the traditional approach for understanding risk allocation patterns across PPPs in the road infrastructure sector. USPs have been traditionally understood in the literature as a mechanism used by governments to expedite PPP procurement processes by allowing private counterparties to materialize ideas for public-private initiatives. Nevertheless, this study shows that, in terms of risk management practices, the influence of private partners in USPs may cover not only the procurement phase, but also all the other stages of the projects’ lifecycle. The manner in which risks tend to be homogenously allocated in unsolicited initiatives within the Chilean market demonstrates this influence. This allocation strategy seeks to reduce the time and resources required to assess not only procurement documents in unsolicited transactions, but also conflicts and litigations across the construction, operation, and termination phases.
On the other hand, in terms of SPs, the analysis indicates that the Chilean government has tried to balance public and private interests by considering how each project’s specific characteristics influence the way risks are managed. This approach intends to improve projects’ attractiveness among private investors. However, for both USPs and SPs, the way in which the Chilean government handles risk allocation procedures may endanger public interests if risks are not adequately identified and allocated. In this regard, this study shows that sustainability-related risks play a crucial role in achieving successful allocation processes. Consequently, not promoting governance structures focused on deeply involving community consultation processes can significantly reduce public support and social legitimacy towards PPP program—thus, increasing protests in the long-term.