Next Article in Journal
Spatial-Temporal Variation in the Impacts of Urban Infrastructure on Housing Prices in Wuhan, China
Previous Article in Journal
Conceptualisation of the Three-Dimensional Matrix of Collaborative Knowledge Barriers
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Optimum Design of Hybrid Renewable Energy System for Sustainable Energy Supply to a Remote Island

1
Smart City Construction Engineering, University of Science & Technology (UST), 217, Gajeong-ro, Yuseong-gu, Daejeon 34113, Korea
2
Department of Land, Water and Environmental Research, Korea Institute of Civil Engineering and Building Technology (KICT), Daehwa-dong 283, Goyangdae-Ro, Ilsanseo-Gu, Goyang-Si, Gyeonggi-do 10223, Korea
*
Author to whom correspondence should be addressed.
Sustainability 2020, 12(3), 1280; https://doi.org/10.3390/su12031280
Submission received: 21 January 2020 / Revised: 3 February 2020 / Accepted: 5 February 2020 / Published: 10 February 2020
(This article belongs to the Section Energy Sustainability)

Abstract

:
Renewable energy technologies can not only help in mitigating the greenhouse gas (GHG) emissions but it can also be very useful for electricity generation at remote locations, where no other means of power are available. The present study focuses on the techno-economic optimum design of a small hybrid renewable energy system (HRES) consisting of wind-solar as primary energy sources. The HRES was modelled for a remote island (Deokjeok-do Island, South Korea) using real electricity consumption data for one complete year. A daily mean load of 24,720 kWh was entered at Deokjeok-do Island with a peak load of 2291.54 kW. Average annual values of wind speed and daily solar radiations were estimated to be 3.6 m/s (10 m height) and 4.13 kWh/m2, respectively. A total of 8760 simulations were performed to achieve the hourly load demand of the mentioned island. In order to deal with the surplus and electricity deficit, two different types of energy storage systems (ESS) were modelled i.e., battery and pumped hydro storage (PHS). Four different HRESs were also evaluated as the most suitable based on levelized cost of energy (LCOE) and net present cost (NPC). A detailed economic break-down of each component and the impact of different sensitivity variables on decision making have also been discussed in detail.

1. Introduction

With the rapid increase in the population of the world over the last few decades, it has now become a serious challenge for governments and energy policymakers to fulfil the electricity requirements of the majority of the people. According to the international energy agency (IEA), 1 out of 5 people in the world had no access to electricity until 2010 [1]. Most of the people having no access to electricity live in remote areas, such as villages and islands. One of the solutions is main grid extensions to such remote areas, but, for locations which are quite a far from main areas, this solution is not a feasible choice, not only from a technical point of view but economically as well. So, one of the best alternatives is to build an independent electricity production unit at such sites consisting of locally available renewable energy resources such as wind and solar [2,3,4,5,6].
Starting at now, numerous relevant examinations of presenting HRES at a remote territory have been driven far and wide. For instance, A.P. Navarro et al. [7] arranged a blend structure involving biomass and wind to plan a power plant with a limit of 40 MW in Spain. Beside the guideline framework, their organized HRES moreover involved various parts, for instance, extra generators, ESS and biogas generators too. H. Borhanazad et al. [8] completed an examination to analyze the breeze qualities, sun controlled radiations and hydro ability of different territories in Malaysia for commonplace zap. M. Jibran et al. [9] surveyed the biomass capacity of Pakistan and expressed that biomass can produce 24% of the total electricity demand of the country. They thought about biomasses, for instance, city strong waste (MSW), bagasse and local creatures compost in their assessment. Binayak B. et al. [10] thought about an extraordinarily commendable model of HRES for town zap, containing wind-PV-hydro as fundamental vitality sources. They showed that presenting such HRESs at remote zones can be monetarily more affordable when contrasted with customary assets of vitality, for example, atomic. Mazzola et al. [11] organized a PV-biomass based HRES for a network in India and coordinated its money related probability too. The creators referenced that LCOE can be reduced up to 40% at whatever point differentiated and analyzed against power age from diesel generators. Furthermore, Jameel A. et al. [12] analyzed the HRES involving wind-PV-biomass as fundamental vitality hotspots for a network in Pakistan called the Kallar Kahar. The examination was driven for various conditions and analysts proposed the foundation of HRES near recently referenced site dependent on strong moderate financial outcomes.
South Korea is one of such countries which has a large number of islands within its territory. Most of these islands are connected with a central grid for fulfilling electricity requirements. However, there are also few islands which are situated at quite a large distance from the mainland, making it impossible to connect them with a central grid. One of such islands is Deokjeok-do Island (latitude: 37.22°, longitude: 126.15°), which is situated at a distance of almost 50 km from Incheon seaport. Currently, most of the electricity being generated here comes from fossil fuels but the government intends to make the mentioned island, along with other nearby islands, 100% diesel-free. In the present study, an independent and off-grid hybrid renewable energy system (HRES) is designed and optimized to supply the environmental-friendly energy for the island.
There are a number of studies that have been conducted recently in order to determine the feasibility of installing HRES in remote areas of South Korea. For instance, S. Baek et al. [13] considered Busan, a large metropolitan city in South Korea, for developing an optimal renewable energy power generation system. The study used the electricity consumption data of Busan City for the year 2013 and performed multiple scenario-based case studies. They considered only wind and solar as primary energy sources and found that the lowest LCOE corresponded to a value of approximately 0.399 $/kWh with 100% renewable energy fraction (REF). In another empirical study, S. Baek et al. [14] designed renewable energy power systems for the largest international airport of South Korea i.e., Incheon international airport. The authors’ used current load (100% load), 120% load and 140% load as the base input values for three different scenarios, respectively. On the basis of economic parameters such as LCOE and NPC, the authors stated that all the electricity requirements of the mentioned airport can be fully covered by renewable energy only.
Similarly, S. Baek et al. [15] also designed an optimal HRES for an emerging island of South Korea known as Yeongjong Island. This small island has critical importance in the economy of South Korea as the Incheon international airport is situated on this island. The authors strongly recommended the installation of HRES consisting of 11 Generic 10kW wind turbines and 357kW of PV panels with LCOE of 0.545 $/kWh and NPC corresponded to almost 3.51 million USD. A very similar study was also performed by H. Kim et al. [16] focusing on Jeju Island, the largest island in South Korea. The authors generated multiple scenarios under two major categories i.e., grid-connected and off-grid power generation systems. They found that a grid-connected HRES will be the most suitable for Jeju Island consisting of PV-wind-battery-converter with the lowest LCOE. E. Park and S. J. Kwon [17] suggested a novel method to use HRES for powering electric-powered (EP) taxis in Daejeon, South Korea. They came up with the three most suitable (lowest LCOE and highest REF) HRESs for this purpose: most reliable case (grid-connected) with LCOE 0.425$/kWh and REF 0.82, most optimal case (grid-connected) with LCOE 0.180$/kWh and REF 0.79, and most optimal off-grid case with LCOE 0.461$/kWh and REF 1.0. Similarly, E. Park and S. J. Kwon [18] and K. Yoo et al. [19] also suggested an optimal, independent HRES for Gadeokdo Island and Ulleungdo Island in South Korea, respectively. Some of the other case studies are also prominent in this regard for South Korea [20,21].

1.1. Concept of Hybrid Renewable Energy System (HRES)

Hybrid renewable energy system (HRES) or simply, renewable energy system comprises of at least two types of renewable energy resources such as wind potential and solar potential. The main idea about the concept of HRES is to supply cheap and sustainable electricity to areas especially quite away from mainland. HRES may be connected to the main power station or it can also be a separate electricity generation system, with its own system for dealing with excess electricity. Figure 1 shows the conceptual design of a typical HRES in which pumped hydro storage (PHS) is being used as an energy storage system (ESS). There are three types of energy sources mentioned in Figure 1, wind, solar and water stored at a particular height. One of the advantages of such HRES is also that it can utilize rainwater very efficiently to produce electrical power. As shown in Figure 1 that rainwater can be stored in the upper reservoir (UR) and then it can be allowed to run down to rotate the hydro turbine rotor for producing electrical power. Lower reservoir (LR) collects the water and pump stores it back into the UR [2,3,4,5,6].
The main objectives of the current work include:
  • Studying the feasibility of designing small HRES consisting of wind and solar as primary energy sources. The intended capacity of small HRES is 1 MW.
  • Designing PHS for storing surplus electricity
  • Comparing PHS with batteries on economic grounds
  • Investigating multiple scenario-based cases of HRES on the basis of detailed techno-economic analysis.

1.2. Profile of Deokjeok-Do Island, South Korea

Deokjeok-do is an island in South Korea, situated 45 km away from Incheon City. The total area of Deokjeok-do Island is almost 21 km2 with a population over 17,000. This island is too far from the mainland of the country, therefore it is not economically feasible to connect this place with a grid in order to supply electricity. Therefore, Deokjeok-do generates its own electricity using diesel fuels, but recently, the local administration has shown its interest to make Deokjeok-do, a green island in terms of electricity generation. This study analyzes the available renewable energy potential at the local site and then suggests an optimal HRES based on economic evaluations. Figure 2 shows the geographical location of Deokjeok-do Island.
Although small HRES can also integrate other renewable energy resources such as tidal, biomass and food-waste along with just wind-solar nexus. All of these resources are available at the studied site but due to the unavailability of such data, these technologies were not considered in the current study and only wind-solar were investigated.

2. Materials and Methods

This section presents some of the important details about Deokjeok-do Island such as electric load and the potential of available renewable energy sources.

2.1. Assessment of Electricity Consumption

So, as to ideally plan an HRES, electricity data, for example, top load, day by day normal power utilization and hourly consumption profile are of basic significance. The easy-accessibility of electricity data empowers planning a progressively optimal HRES.
Figure 3 demonstrates the month to month power utilization at Deokjeok-do [23]. The mean daily burden was observed to be roughly 24,720 kWh with pinnacle heap of 2292 kW regularly happening during the winter season, and complete yearly power utilization approaches to an estimation of 7.3 GWh. The power utilization in winter is much larger than other seasons because of the frequent utilization of room warming facilities fueled by electric power.

2.2. Estimation of Renewable Energy Potential

The present study will consider only two renewable energy sources namely wind and solar. The potential of each source will be estimated and how it can affect the power production, is analyzed at first.

2.2.1. Wind Resources Assessment

The authors [22] have studied the wind characteristics at Deokjeok-do and found that most of the winds are coming from the south-west with an average wind speed of 3.6 m/s at a 10 m height. There are two important statistical parameters needed to be estimated while analyzing the wind potential, called the Weibull probability density function (PDF) and cumulative distribution function (CDF), respectively and can be defined mathematically as:
P D F   =   f v   =   k c v c k 1 e x p [ v c k ]   ( v > 0 ; k , c > 0 )
C D F   =   F v   =   1 e x p [ v c k ]
where, k, c and v are Weibull shape parameter, Weibull scale factor and wind speed, respectively. k determines the x-axis of Weibull distribution whereas c determines the y-axis. The accurate estimation of these two important parameters is of critical importance. There are a lot of methods to estimate these variables but the empirical method will be deployed in the current study due to its accuracy and robustness [22]. In the following equations, vm is mean wind speed, n is number of wind data, σ is the standard deviation and Γ is called gamma function.
v m =   1 n [ i = 1 n v i ]
σ 2   =   1 n 1 i = 1 n v i v m 2
k   =   σ v m 1.086   1 k 10
c   =   v m Γ 1 + 1 k
Figure 4 shows the wind characteristics of Deokjeok Island prepared using wind data (2005–2015) measured at 10 m height as measured by Korean Metrological Administration (KMA) [24] and analyzed by the authors [22]. The most frequent wind speed is 4 m/s as shown in Figure 4b.

2.2.2. Solar Resources Assessment

A study conducted by O. Nematollahi and K.C. Kim [25] estimated the solar potential over different parts of South Korea. The authors used 24 locations to cover the whole country and stated the monthly radiation and clearness index of each of the 24 locations. The solar data used by them were collected for five years (2011–2015) and originally recorded by Korean meteorological administration (KMA). The authors averaged out all the five years of data and reported the final results. The present study will use, the results of O. Nematollahi and K.C. Kim [25] to estimate the solar resources of Deokjeok-do Island. Out of these 24 locations, Incheon City is the nearest to Deokjeok-do Island, therefore solar radiations over Incheon city will be considered identical as over Deokjeok-do Island because of the facts that data were averaged out for five years.
Figure 5 shows the estimated solar radiations over Deokjeok-do Island used as input for HOMER pro simulations.

2.3. HOMER Pro Simulation

In the present study, the plan for renewable energy installed at Deokjeok-do Island is optimized using HOMER pro software (Hybrid Optimization Model for Electric Renewables) [26]. All the above-mentioned data such as load, wind and solar potential were inputted to HOMER pro. Table 1 presents the essential characteristics (technical as well as economic) of all the equipment selected for the present study.
It must be mentioned that equipment was selected after carefully following the guidelines provided by previous authors [13,14,15,16,17,18,19,20,21,22] except wind machine, which was shortlisted by adopting the technique recommended by the authors [27].
Leonics MTP-413F was selected as the converter as recommended by Busaidi et al. [28] and Akikur et al. [29] for medium-sized HRES such as generating electricity between 5 GWh to 10 GWh annually. This model was also recommended by Mandelli et al. [30] based on its low capital and replacement costs, respectively. Similarly, a kinetic model of battery (6CS25P) manufactured by Surrette is by far the most commonly used battery model for such type of feasibility studies due to its economic benefits (only 1 USD replacement cost). There are many different types of PV modules available but solar module named CS6X-325P manufactured by Canadian Solar Inc. is best suitable for Deokjeok-do due to its long lifetime (25 years) and high efficiency (20%). Apart from the technical superiority of CS6X-325P over other PV modules. One other advantage is that this PV panel has a very low capital cost ($1.5/W). Wind turbine model was selected according to the wind characteristics of Deokjeok-do and the detailed procedure can be found in the previous study by the authors [27].
Table 1 summarizes all the selected equipment modules and essential details.
Figure 6 displays the HOMER model developed for present work having separate transmission lines for direct current (DC) and alternate current (AC).

2.4. Pumped Hydro Storage (PHS) as Alternate Energy Storage System (ESS)

Although HOMER pro only models batteries as default ESS, other types of ESSs can also be designed separately and compared with batteries. One of such energy storage systems is pumped hydro storage which is a mechanical type of ESS, as shown in Figure 1. Surplus electricity from HRES is consumed by a pump to lift the water in order to fill the upper reservoir (UR). On the other hand, the electricity deficit of HRES is compensated by running a hydro turbine, which uses stored water in UR. Lower reservoir (LR) can be a tank or it can also be some other natural water resource such as a river or sea, depending upon the geographical characteristics of the local site. In the current case, as Deokjeok-do is an island, so the sea will be considered as a lower reservoir.
In the customary PHS for coal-fired power plants or atomic plants, two water stores are required to be situated on the upper mountain and the lower valley. With the innovation improvement, seawater can now likewise be utilized as a lower water reservoir, especially in cases of remote islands where there will probably not be a sufficient new water source. Furthermore, remote islands are encompassed by the ocean, and in this way, geographical characteristics are also a reason to use seawater as the lower reservoir. The possibility of utilizing seawater for PHS was first analyzed by Japan [32], and a small power plant based on PHS as ESS was developed at Okinawa, with an approximate effectiveness of 77% [33].

Modelling of PHS

The accurate size determination of each component of PHS is significantly important in the designing process. The size of the pump must be greater than the maximum surplus electricity from HRES and similarly, the size of the hydro turbine must also be larger than the maximum electricity deficit. In the current case, there is no need to design LR, as stated above that LR will be the sea. Accurate size determination of UR is the most complex step in PHS designing process. For designing UR, pump flow rate ( q p t ) and hydro turbine flow rate ( q t t ) must be known at first place. Pump flow rate can be defined as follows [34]:
q p t   =   ɛ p P H R E S p t ρ g h   =   c p . P H R E S p t
where ɛ p is overall pumping efficiency (0.5), P H R E S p t is surplus power from HRES to pump, ρ is water density (1000 kg/m3), g is the acceleration due to gravity (9.8 m/s2), h is UR height (60 m assumed) and c p is called the water pumping coefficient (3.06 m3/kWh), respectively. Similarly, the turbine flow rate can be defined as follows:
q t t   =   P t H R E S t ρ g h ɛ t   =   P t H R E S t c t
where P t H R E S t is the power from the hydro turbine to HRES, ɛ t is turbine efficiency (0.65) and c t is called the turbine generating coefficient (0.106 kWh/m3), respectively. Amount of water in UR at any time t Q U R   t , can be estimated from the following equation:
Q U R   t   =     Q U R   t 1 1 α + q p t q t t
where α is called the evaporation and leakage loss coefficient, which is assumed to be 10% for the current study. The cost of each component of PHS is estimated by using guidelines provided by T. Ma et al. [35].

3. Results and Discussion

This section will present the analysis on the basis of detailed technical and economic calculations and characteristics of the most ideal energy systems best-suited for Deokjeok-do. There were a total of 551,035 systems generated by HOMER pro simulations but the number of feasible systems solutions were limited to only 232,683.
Out of all the feasible system solutions (232,683), two systems (base cases) were selected as the most appropriate choice based on lowest possible net present cost (NPC) and lowest possible levelized cost of energy (LCOE). Both systems are defined as below:
  • HRES A (base case): Energy system having lowest NPC
  • HRES B (base case): Energy system having lowest LCOE
Table 2 shows the values of some variables for base cases (HRES A and HRES B) and for many other sensitivity cases. The values of sensitivity variables are selected in such a way that same numbers have been added and reduced from base values of variables as it is apparent from Table 2 as well. There can be multiple other combinations of sensitive variables which can be investigated, but that will make this study too lengthy and out of the scope of current purpose.

3.1. Optimum HRESs with Battery as ESS

Table 3 summarizes the essential characteristics of two optimal energy systems with batteries as the only option for energy storage. As batteries are one of the most expensive components of an HRES [32,34], so alternate ESS such as pumped hydro storage (PHS) will also be designed for both systems and costs will be compared with each other (Section 3.2). Net present cost (NPC) of energy system A is 11.3 million USD (lowest) whereas the lowest LCOE is 0.123 USD/kWh in case of energy system B. Table 3 conjointly displays the values of sensitivity variables at which optimum system solutions are obtained. Project lifetime of system A (15 years) is a smaller time period than that of system B (25 years), that’s conjointly one amongst the explanations for low NPC of system A. Generally speaking, energy systems with low LCOE are preferred because of the fact that governments can support to reduce the overall NPC of the project via different subsidiary schemes related to renewable energy projects. So, relatively high NPC can be acceptable in some cases but high LCOE produces serious drawbacks related to the selection of the project.
Table 4 shows the total capacity of all equipment selected for system A and system B. Each HRES comprises of one wind turbine and almost 1000 kW capacity converter. Solar panel capacity of HRES B (3157 kW) is larger than HRES A (2504 kW), due to which the initial cost of HRES B is more than HRES A. One point must be mentioned here that by choosing a suitable wind turbine according to local wind characteristics, each HRES may have different system architectures as compared to the current scenario [17]. However, choosing a suitable wind turbine for any site requires a complex analysis involving extreme wind speed (EWS), turbulence intensity (TI) and local geographical characteristics, which are out of the scope of present work, so not performed here [22,27].
Adding different renewable energy resources such as biomass, tidal energy and food-waste to both systems, will definitely change the architecture of both systems as it is presented in Table 4. Doing so, may reduce the LCOE but will definitely increase the overall NPC. Such an investigations have not been performed here due to unavailability of such data at the local site. However, it is highly recommended to integrate as many renewable resources as available on the local site with the basic HRES just consisting of wind and solar energy.
Table 5 shows the summary of electricity production by each component and electricity consumption as well. As it is clear from the Table that PV panels are the main contributors of power generation in both cases. Both systems can independently fulfil all the electricity demand of Deokjeok-do Island, as it is also clear from Table 5 as well.
One shortcoming of the current study is that the simulated data shows results for only one year of electricity demand (7,296,369 kWh). As the project is planned for 20 years, so it is not known whether the systems selected in Table 4 be able to fulfil all the electricity demands of the island or not for upcoming years? One way to address this issue will be probably to use the ‘simulated electricity demand’ data of the studied site. However, unfortunately, such data are also not available. So, it is assumed that electricity demand will remain fixed during all next 20 years. Although, the electricity demand selected (7,296,369 kWh/year) in this study was the highest number for the last 20 years.
Figure 7 and Figure 8 show the NPC and annualized costs of all the equipment of both system solutions, respectively. Both the figures indicate that solar panels are the most expensive equipment and also, their annual maintenance cost is the highest as well for both systems. Capital cost includes different type of costs occurred at the start of the project such as equipment cost, installation cost, labor cost and transportation costs. As it is clear from Figure 7 and Figure 8 that capital cost is almost 70% of the total NPC and annual cost. The second type of cost is annually occurring operating and maintenance cost which includes workers’ salaries, annual cleanliness cost, fuel cost and electricity cost to run the auxiliary equipment at the power plant. Replacement cost is used to buy new equipment during the project running time, once the lifetime of any equipment has finished, as shown in Table 1. Salvage are those benefits which are obtained by selling all the project equipment and other items after the project lifetime of 20 years. In Figure 7 and Figure 8, positive cash flow represents costs and negative cash flow (salvage) are benefits.
Figure 9 shows the impact of wind turbine hub height on the economics of both systems i.e., HRES A and HRES B (NPV is the net present value which is the difference between present values of benefits and costs, NPV > 0 is must [27]). It is important to estimate the appropriate hub height as it has a direct effect on the electricity generated by wind turbine, which subsequently changes the values of NPV and LCOE. As the hub height increases, wind turbine rotor interacts with relatively higher wind speeds as compared to lower heights, which generates more electricity but, at the same time cost of tower increases and VICE VERSA for lower hub heights. So, it is a trade-off between more electricity and the cost of the tower. Figure 9 determines the optimal hub-height for each case.
Finally, Table 6 shows the annual amount of pollutant gases emissions due to the operation of both systems.

3.2. Optimum HRESs with PHS as ESS

HOMER Pro software automatically considers batteries as default ESS for storing surplus electricity from HRES. However, batteries are one of the most expensive components of any HRES [18]. Therefore, it was decided to design an alternate ESS such as PHS and compare the results with batteries on economic grounds. Table 7 shows the values of all important parameters related to the designed PHS for both optimal HRESs. The technical and economical methodologies for preparing Table 7 have already been covered in Section 2.4 respectively and can also be found in reference [34]. Both systems have equal sizes of hydro turbines, whereas the size of the pump is slightly higher in case of system B. Table 7 also shows the amount of water that must be put inside UR at t = 0 (even before the start of operation). This is due to the fact that at the start of operation (during few early days) there will always be electricity deficit in case of both systems, therefore, it will require additional electricity from the hydro turbine to successfully fulfil the electricity demand of Deokjeok-do Island. It is also clear from Table 7 that PHS is slightly cheaper than batteries in terms of initial investment for both optimal system solutions.
Figure 10 shows the amount of water in UR throughout the year for both systems A and B. During the summer season UR is almost fully filled with water for system A whereas it is winter season for system B. On average basis, water level in UR is less than 50% for 252 days in case of system A and it is 298 days for system B. Minimum levels of water in UR for both systems have already been mentioned in Table 7. One of the reasons for very low water level during winter and summer seasons (in case of HRES A and HRES B respectively) is due to the high consumption of electricity during these days. In South Korea, during the winter season, the minimum temperature passes below -15 °C which requires relatively more electrical energy for heating the indoors of buildings, resulting in high-demand of electricity. Similar conditions can be associated with the summer season in terms of cooling the indoors of buildings. Although Figure 10 just shows the water level in UR at any time of the year, this behavior can be associated with the demand for electricity during the year. The trends are different in both cases mainly due to the different architecture of both systems as shown in Table 4.

3.3. Sensitivity Cases

In spite of the fact that the most ideal framework arrangements have just been clarified in detail in the above segments. In any case, it is additionally of basic significance to quickly explain a portion of the other alternate framework arrangements based on economic assessments. So, as to accomplish this objective, Figure 11 has been readied, which demonstrates numerous framework arrangements acquired by superimposing NPC over LCOE. Figure 11 demonstrates an aggregate of 81 ideal framework solutions obtained by varying the values of all sensitivity referenced in Table 2.

4. Conclusions

The current study aimed to design and optimize an off-grid hybrid renewable energy system (HRES) for a remote island of South Korea, where no other means of power generation are available. The study considered two different types of renewable energy resources, namely wind and solar. Two of the most suitable HRESs were recommended based upon the lowest NPC (System A) and LCOE (System B), respectively.
The daily mean AC load was estimated to be 24,720 kWh with 2292 kW as peak load, which occurs typically during the winter season. Annual mean wind speed was measured to be 3.6 m/s (10 m height) with 4.13 kWh/m2 as daily solar radiations. The total net present cost for energy system A was estimated to be 11.3 million $ whereas for energy system B, it corresponds to a slightly higher value i.e., 17.6 million $. However, cost of electricity for energy system A is relatively higher than energy system B as it is 0.159$/kWh for energy system A and 0.122$/kWh for energy system B. Both systems consist of one STX 93/2000 wind turbine and 2504 kW PV panels (System A) and 3157 kW PV panels (System B). The annual electricity demand of the island is 7,296,369 kWh. System A can produce 9,016,674 kWh/year whereas system B can produce 9,812,942 kWh/year. The study also designed the pumped hydro storage (PHS) to deal with the surplus and deficit of electricity for both systems and compared the economics with the battery as well. The analysis showed that PHS can be a cheaper choice as the total capital cost for constructing PHS was estimated to be 1.34 million USD for system A (1.80 million USD for battery) and 1.45 million USD for system B (1.58 million USD for battery). Apart from above-mentioned system solutions, NPC and LCOE of multiple other systems were also estimated by varying the values of input variables such as discount rate, project lifetime and daily load.

Author Contributions

All data were collected and analyzed by S.A. who also devised the methodology and wrote the manuscript. C.-M.J. provided his guidance and supervision for this study. All authors have read and agreed to the published version of the manuscript.

Funding

This study was funded by major project funding from the Korea Institute of Civil Engineering and Building Technology [grant number 20200034-001].

Conflicts of Interest

The authors declare no actual or potential conflicts of interest.

References

  1. IEA. Measuring Progress Towards Energy for All: Power to the People? In World Energy Outlook 2012; [Chapter 18]; International Energy Agency: Paris, France, 2012. [Google Scholar]
  2. Upadhyay, S.; Sharma, M.P. A review on configurations, control and sizing methodologies of hybrid energy systems. Renew. Sustain. Energy Rev. 2014, 38, 47–63. [Google Scholar] [CrossRef]
  3. Eriksson, E.L.V.; Gray, E.M. Optimization and integration of hybrid renewable energy hydrogen fuel cell energy systems–A critical review. Appl. Energy 2017, 202, 348–364. [Google Scholar] [CrossRef]
  4. Khare, V.; Nema, S.; Baredar, P. Solar–wind hybrid renewable energy system: A review. Renew. Sustain. Energy Rev. 2016, 58, 23–33. [Google Scholar] [CrossRef]
  5. Balamurugan, P.; Ashok, S.; Jose, T.L. Optimal operation of biomass/wind/PV hybrid energy system for rural areas. Int. J. Green Energy 2009, 6, 104–116. [Google Scholar] [CrossRef]
  6. Goel, S.; Sharma, R. Performance evaluation of stand-alone, grid connected and hybrid renewable energy systems for rural application: A comparative review. Renew. Sustain. Energy Rev. 2017, 78, 1378–1389. [Google Scholar] [CrossRef]
  7. Perez-Navarro, A.; Alfonso, D.; Álvarez, C.; Ibáñez, F.; Sanchez, C.; Segura, I. Hybrid biomass-wind power plant for reliable energy generation. Renew. Energy 2010, 35, 1436–1443. [Google Scholar] [CrossRef]
  8. Borhanazad, H.; Mekhilef, S.; Saidur, R.; Boroumandjazi, G. Potential application of renewable energy for rural electrification in Malaysia. Renew. Energy 2013, 59, 210–219. [Google Scholar] [CrossRef]
  9. Zuberi, M.J.S.; Torkmahalleh, M.A.; Ali, S.H. A comparative study of biomass resources utilization for power generation and transportation in Pakistan. Int. J. Hydrog. Energy 2015, 40, 11154–11160. [Google Scholar] [CrossRef]
  10. Bhandari, B.; Lee, K.T.; Lee, C.S.; Song, C.K.; Maskey, R.K.; Ahn, S.H. A novel off-grid hybrid power system comprised of solar photovoltaic, wind, and hydro energy sources. Appl. Energy 2014, 133, 236–242. [Google Scholar] [CrossRef]
  11. Mazzola, S.; Astolfi, M.; Macchi, E. The potential role of solid biomass for rural electrification: A techno economic analysis for a hybrid micro grid in India. Appl. Energy 2016, 169, 370–383. [Google Scholar] [CrossRef]
  12. Ahmad, J.; Imran, M.; Khalid, A.; Iqbal, W.; Ashraf, S.R.; Adnan, M.; Khokhar, K.S. Techno economic analysis of a wind-photovoltaic-biomass hybrid renewable energy system for rural electrification: A case study of Kallar Kahar. Energy 2018, 148, 208–234. [Google Scholar] [CrossRef]
  13. Baek, S.; Park, E.; Kim, M.G.; Kwon, S.J.; Kim, K.J.; Ohm, J.Y.; del Pobil, A.P. Optimal renewable power generation systems for Busan metropolitan city in South Korea. Renew. Energy 2016, 88, 517–525. [Google Scholar] [CrossRef]
  14. Baek, S.; Kim, H.; Chang, H. Optimal hybrid renewable airport power system: Empirical study on Incheon International Airport, South Korea. Sustainability 2016, 8, 562. [Google Scholar] [CrossRef] [Green Version]
  15. Baek, S.; Kim, H.; Chang, H. Optimal hybrid renewable power system for an emerging Island of South Korea: The case of Yeongjong Island. Sustainability 2015, 7, 13985–14001. [Google Scholar] [CrossRef] [Green Version]
  16. Kim, H.; Baek, S.; Park, E.; Chang, H.J. Optimal green energy management in Jeju, South Korea–On-grid and off-grid electrification. Renew. Energy 2014, 69, 123–133. [Google Scholar] [CrossRef]
  17. Park, E.; Kwon, S.J. Renewable electricity generation systems for electric-powered taxis: The case of Daejeon metropolitan city. Renew. Sustain. Energy Rev. 2016, 58, 1466–1474. [Google Scholar] [CrossRef]
  18. Park, E.; Kwon, S.J. Towards a Sustainable Island: Independent optimal renewable power generation systems at Gadeokdo Island in South Korea. Sustain. Cities Soc. 2016, 23, 114–118. [Google Scholar] [CrossRef]
  19. Yoo, K.; Park, E.; Kim, H.; Ohm, J.; Yang, T.; Kim, K.; del Pobil, A. Optimized renewable and sustainable electricity generation systems for Ulleungdo Island in South Korea. Sustainability 2014, 6, 7883–7893. [Google Scholar] [CrossRef] [Green Version]
  20. Oh, S.D.; Yoo, Y.; Song, J.; Song, S.J.; Jang, H.N.; Kim, K.; Kwak, H.Y. A cost-effective method for integration of new and renewable energy systems in public buildings in Korea. Energy Build. 2014, 74, 120–131. [Google Scholar] [CrossRef]
  21. Park, E. Potentiality of renewable resources: Economic feasibility perspectives in South Korea. Renew. Sustain. Energy Rev. 2017, 79, 61–70. [Google Scholar] [CrossRef]
  22. Ali, S.; Lee, S.M.; Jang, C.M. Statistical analysis of wind characteristics using Weibull and Rayleigh distributions in Deokjeok-do Island–Incheon, South Korea. Renew. Energy 2018, 123, 652–663. [Google Scholar] [CrossRef]
  23. Shin, Y.; Koo, W.Y.; Kim, T.H.; Jung, S.; Kim, H. Capacity design and operation planning of a hybrid PV–wind–battery–diesel power generation system in the case of Deokjeok Island. Appl. Therm. Eng. 2015, 89, 514–525. [Google Scholar] [CrossRef]
  24. Korean Meteorological Administration (KMA). Available online: https://data.kma.go.kr/ (accessed on 28 September 2018).
  25. Nematollahi, O.; Kim, K.C. A feasibility study of solar energy in South Korea. Renew. Sustain. Energy Rev. 2017, 77, 566–579. [Google Scholar] [CrossRef]
  26. Homer Pro Software. Available online: https://www.homerenergy.com/products/pro/index.html (accessed on 28 September 2018).
  27. Ali, S.; Lee, S.M.; Jang, C.M. Techno-economic assessment of wind energy potential at three locations in South Korea using long-term measured wind data. Energies 2017, 10, 1442. [Google Scholar] [CrossRef] [Green Version]
  28. Al Busaidi, A.S.; Kazem, H.A.; Al-Badi, A.H.; Khan, M.F. A review of optimum sizing of hybrid PV–Wind renewable energy systems in Oman. Renew. Sustain. Energy Rev. 2016, 53, 185–193. [Google Scholar] [CrossRef]
  29. Akikur, R.K.; Saidur, R.; Ping, H.W.; Ullah, K.R. Comparative study of stand-alone and hybrid solar energy systems suitable for off-grid rural electrification: A review. Renew. Sustain. Energy Rev. 2013, 27, 738–752. [Google Scholar] [CrossRef]
  30. Mandelli, S.; Barbieri, J.; Mereu, R.; Colombo, E. Off-grid systems for rural electrification in developing countries: Definitions, classification and a comprehensive literature review. Renew. Sustain. Energy Rev. 2016, 58, 1621–1646. [Google Scholar] [CrossRef]
  31. Ali, S.; Jang, C.M. Evaluation of PV-Wind Hybrid Energy System for a Small Island. In Wind Solar Hybrid Renewable Energy System; IntechOpen: London, UK, 2019. [Google Scholar]
  32. Li, R.; Wu, B.; Li, X.; Zhou, F.; Li, Y. Design of wind-solar and pumped-storage hybrid power supply system. In Proceedings of the 2010 3rd International Conference on Computer Science and Information Technology, Chengdu, China, 9–11 July 2010; Volume 5, pp. 402–405. [Google Scholar]
  33. Brown, P.D.; Lopes, J.P.; Matos, M.A. Optimization of pumped storage capacity in an isolated power system with large renewable penetration. IEEE Trans. Power Syst. 2008, 23, 523–531. [Google Scholar] [CrossRef]
  34. Ma, T.; Yang, H.; Lu, L.; Peng, J. Technical feasibility study on a standalone hybrid solar-wind system with pumped hydro storage for a remote Island in Hong Kong. Renew. Energy 2014, 69, 7–15. [Google Scholar] [CrossRef]
  35. Ma, T.; Yang, H.; Lu, L. Feasibility study and economic analysis of pumped hydro storage and battery storage for a renewable energy powered Island. Energy Convers. Manag. 2014, 79, 387–397. [Google Scholar] [CrossRef]
Figure 1. Conceptual design of a typical hybrid renewable energy system (HRES) [22].
Figure 1. Conceptual design of a typical hybrid renewable energy system (HRES) [22].
Sustainability 12 01280 g001
Figure 2. Location of Deokjeok-do Island in South Korea.
Figure 2. Location of Deokjeok-do Island in South Korea.
Sustainability 12 01280 g002
Figure 3. Monthly electric load at Deokjeok-do Island [23].
Figure 3. Monthly electric load at Deokjeok-do Island [23].
Sustainability 12 01280 g003
Figure 4. Wind conditions at Deokjeok-do Island (a) Wind rose (b) Weibull plot [22].
Figure 4. Wind conditions at Deokjeok-do Island (a) Wind rose (b) Weibull plot [22].
Sustainability 12 01280 g004
Figure 5. Monthly solar radiations at Deokjeok-do Island [13].
Figure 5. Monthly solar radiations at Deokjeok-do Island [13].
Sustainability 12 01280 g005
Figure 6. HOMER model [31].
Figure 6. HOMER model [31].
Sustainability 12 01280 g006
Figure 7. Net present cost (NPC) breakdown for both systems (a) System A (b) System B.
Figure 7. Net present cost (NPC) breakdown for both systems (a) System A (b) System B.
Sustainability 12 01280 g007
Figure 8. Annualised cost breakdown for both systems (a) System A (b) System B.
Figure 8. Annualised cost breakdown for both systems (a) System A (b) System B.
Sustainability 12 01280 g008
Figure 9. Effect of wind turbine hub height on the economics of both systems.
Figure 9. Effect of wind turbine hub height on the economics of both systems.
Sustainability 12 01280 g009
Figure 10. Amount of water in UR.
Figure 10. Amount of water in UR.
Sustainability 12 01280 g010
Figure 11. Feasible HRES solutions with NPC superimposed over levelized cost of energy (LCOE) (a) Interest rate: 4%; HRES Life: 15 years (b) Interest rate: 6%; HRES Life: 20 years (c) Interest rate: 8%; HRES Life: 25 years.
Figure 11. Feasible HRES solutions with NPC superimposed over levelized cost of energy (LCOE) (a) Interest rate: 4%; HRES Life: 15 years (b) Interest rate: 6%; HRES Life: 20 years (c) Interest rate: 8%; HRES Life: 25 years.
Sustainability 12 01280 g011
Table 1. Selected Equipment.
Table 1. Selected Equipment.
EquipmentModelCapital Cost ($/kW)Replacement Cost ($/kW)O&M Cost ($/year)Lifetime (years)
ConverterMTP-413F 25kW8008001010
BatterySurrette 6CS25P250250120
PV PanelCS6X-325P150015003025
Wind TurbineSTX 93/20002,889,7472,889,747112,37520
Table 2. Sensitivity Variables (HOMER Inputs).
Table 2. Sensitivity Variables (HOMER Inputs).
Average Daily Electricity Consumption (kWh/day)Interest Rate (%)Project’s Total Life (Years)Case
25,000620Base
20,000415Sensitivity
30,000825Sensitivity
Table 3. Both HRES Planned.
Table 3. Both HRES Planned.
VariableUnitSystem ASystem B
NPCMillion $11.317.61
LCOE$/kWh0.1580.123
Total Load Scaled AveragekWh/day20,00020,000
Nominal Interest Rateper cent84
HRES Lifeyears1525
Table 4. Systems Architecture.
Table 4. Systems Architecture.
Component ModelUnitSize (System A)Size (System B)
PV PanelsCS6X-325PkW25043157
BatterySurrette 6 CS 25Pstrings71976269
Wind TurbineSTX 93/2000ea.11
System ConverterLeonics MTP-413F 25kWkW10061009
Dispatch StrategyHOMER Cycle ChargingN/AN/AN/A
Table 5. Electricity Production Details.
Table 5. Electricity Production Details.
Electricity DetailsUnitSystem ASystem B
ValuePercent of Total ProductionValuePercent of Total Production
PV productionkWh/annul5,173,54257.37.305,969,81060.83
WT productionkWh/annual3,843,13242.623,843,13239.16
TotalkWh/annual9,016,674100.009,812,942100.00
DemandkWh/annual7,296,36980.927,296,36974.35
SurpluskWh/annual1,033,28811.461,821,88418.57
UnmetkWh/annual3,6310.043,6760.04
Table 6. Pollutants Emission.
Table 6. Pollutants Emission.
PollutantUnitSystem ASystem B
CO2kg/annum795700
COkg/annum8.837.77
Unburned Hydrocarbonskg/annum00
Particulate Matterkg/annum00
SO2kg/annum00
NOxkg/annum5.524.86
Table 7. Pumped hydro storage (PHS) Design for Both Systems.
Table 7. Pumped hydro storage (PHS) Design for Both Systems.
ParameterUnitSystem ASystem B
Maximum hourly deficit of electricity during the yearkW10051009
Size of hydro turbinekW10201020
Maximum hourly surplus electricity during the yearkW35784211
Size of pumpkW36004220
UR sizem3229,770255,300
Minimum level of water in URm3275,72459,54
Date of min. water level in URdate12/20/2017 11:00:0010/29/2017 7:00:00
Amount of water in UR at t = 0m3528,47199,134
Capital Cost of hydro turbineMillion $0.6120.612
Capital Cost of pumpMillion $0.490.58
Capital Cost of URMillion $0.229770.2553
Total capital cost of PHSMillion $1.334971.44544
Total capital cost of battery bankMillion $1.80121.575

Share and Cite

MDPI and ACS Style

Ali, S.; Jang, C.-M. Optimum Design of Hybrid Renewable Energy System for Sustainable Energy Supply to a Remote Island. Sustainability 2020, 12, 1280. https://doi.org/10.3390/su12031280

AMA Style

Ali S, Jang C-M. Optimum Design of Hybrid Renewable Energy System for Sustainable Energy Supply to a Remote Island. Sustainability. 2020; 12(3):1280. https://doi.org/10.3390/su12031280

Chicago/Turabian Style

Ali, Sajid, and Choon-Man Jang. 2020. "Optimum Design of Hybrid Renewable Energy System for Sustainable Energy Supply to a Remote Island" Sustainability 12, no. 3: 1280. https://doi.org/10.3390/su12031280

APA Style

Ali, S., & Jang, C. -M. (2020). Optimum Design of Hybrid Renewable Energy System for Sustainable Energy Supply to a Remote Island. Sustainability, 12(3), 1280. https://doi.org/10.3390/su12031280

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop