1. Introduction
Infrastructure systems are characterized by requiring a large amount of financial capital for their construction [
1,
2]. A holistic definition of infrastructure systems indicates that they have environmental, social, and governance impacts on project stages, such as planning, building, and operating [
3]. In this way, understanding the social components is critical for increasing resilience [
4]. Additionally, they can be integrated into a combination of two or more infrastructure systems [
5]. In this context, infrastructure systems, such as buildings, bridges, facilities, energy, transportation networks, among others, play a pivotal role in providing vital services to mankind [
5,
6]. According to ref. [
7], by 2030, Latin America and the Caribbean will need to invest USD 2,220,736 million in developing infrastructure systems, particularly water, sanitation, energy, transportation, and telecommunications, in order to meet the Sustainable Development Goals (SDGs). Of that total, 59% is required for developing new infrastructure systems, while 41% for maintaining the existing assets and replacing assets that are obsolescent [
7]. According to the Inter-American Development Bank [
7], investments by countries can be grouped as follows: Central America: USD 612.8 billion; Caribbean: USD 19.6 billion; Andean: 457.9 billion; Southern Cone: USD 1130.4 billion. In this way, private and public sectors have a great opportunity to join efforts for closing both investment gaps and reaching SDGs.
These are typically structured using project finance (PF) and public–private partnerships (PPPs). Regarding capital structure, the study conducted by [
8] found that infrastructure systems structured under PPPs are usually financed by a combination of equity and debt in different proportions, with debt generally exceeding 70%, although sometimes reaching 100%. Similar findings were also found by [
9], who indicated that the percentage of debt was between 65% and 90%, compared to 25% and 35% for typical companies. Likewise, [
10] indicated that the capital structures of most PPPs developed through PF were highly leveraged, with equity financing covering between 10% and 30% of capital expenditures (Capex) and debt between 90% and 70%. Additionally, although studies have been conducted by analyzing infrastructure systems from a financial perspective, they include neither sustainable nor convertible debt. These studies have mainly focused on the optimization [
11,
12,
13], financing [
14,
15,
16,
17,
18], and analysis of risks [
19,
20,
21,
22,
23].
Considering all the above-mentioned points, ref. [
24] indicated that infrastructure system financing is an open field for academic researchers. However, empirical studies remain limited, despite their importance in professional and academic arenas. Thus, areas of knowledge from different perspectives could be indicated, particularly in risks [
25,
26,
27,
28] and capital structure [
1,
2,
29,
30,
31], thus, further encouraging extended studies. This could also provide insights for stakeholders in order to encourage private sector investments [
32].
Given that infrastructure systems could be financed by equity and/or debt, it is important to consider that some debt mechanisms can convert into equity shares. This is the case in mezzanine debt [
3]. Thus, given that convertible debt has a contingent claim from lenders, this could cause capital structure to change once during a project’s life-cycle when the outstanding debt is converted into equity shares [
33]. When this happens, equity investments would increase participation in the capital structure [
3].
Thus, lenders could convert outstanding debt into equity shares based on criteria or parameters. This study deals with the capital structure evolution when infrastructure systems are financed with convertible financial mechanisms indexed with sustainable criteria and exercised by an American-type option. In this scenario, capital structure could change if goals or covenants related to sustainability are accomplished, and the option is exercised. It is important to note that financial options are classified as American and European. The former can be exercised at any time during the life of the option, while the latter can only be exercised at a specific time [
34]. In this case, debt must be a sustainable financial mechanism and infrastructure systems must have sustainability impacts. In this way, it is important to impact investors’ behavior and, thus, shift the investment industry mindset concerning SISs. That means that higher financial returns could result from better operation performances, lower financial costs, and an adequate financing strategy, which should include sustainable financial resources. In this way, SISs could reduce operational costs by focusing on efficiency [
35].
In this regard, [
36] argued that it is necessary to change traditional shareholders’ maximization of sustainable value creation as only the viable way forward. Likewise, [
37] provided a remarkable description of financial and sustainable investments, indicating no difference between the two, given that both types of investments create social, financial, and environmental value, which [
38] confirmed.
Although empirical studies have mainly focused on analyzing the capital structure of infrastructure investments [
31,
39,
40,
41], to the best of our knowledge, no elements in the current literature have analyzed the capital structure evolution. Therefore, to fill this gap, this study proposes a methodology for analyzing capital structure in sustainable infrastructure systems. Thus, a mathematical model that identifies the impact on the final capital structure according to investment plans and capital structures per period is developed. Additionally, this proposal integrates a framework that involves sustainable financing, capital markets, and public–private sectors.
The current study provides a two-fold contribution to the literature. First, the present study allows for a better understanding of how capital structure changes, even if debt is converted to equity shares, from a mathematical perspective. Its analysis provides critical new evidence and insights on this topic. Second, this study integrates the main stakeholders into a framework, allowing for a complete outline at all stages of an infrastructure system. In this way, this study provides a roadmap that researchers and professionals can use to improve their understanding of how infrastructure could be financed.
The remainder of the paper is organized as follows: In
Section 2, we present the materials and methods used in this study. In
Section 3, we explain the methodological proposal. In
Section 4, we apply the methodological proposal in a case study. In
Section 5, we conclude the study.
3. Methodological Proposal
The methodological approach to financing SISs was structured in steps.
Figure 1 shows a scheme that summarized, in a general way, the proposed methodology. Subsequently, each step was systematically integrated into a sustainable financial framework. This methodology could provide a better description of the SIS structuring process and how to improve strategic decision making, particularly in regard to financing issues. Although this proposal was designed for the Colombian case, it can be applied to any country or sector, considering the application of specific tax benefits. In this way, the methodology proposed can become a financial tool that strengthens the financing process, helping boost the development of SISs and close the coverage gap.
3.1. Structuring Process
In Colombia, private investors can present two types of proposals to carry out projects: (1) with public resources and (2) without public resources. The main difference between the two is based on the public funding issue. In the first type of proposal, the private initiative with public resources (PIPR), the amount of public financing cannot be more than 30% of the value of the original contract. Such proposals would be conditioned on infrastructure availability. For example, operating projects must comply with service levels and quality standards. In the second type of proposal, the private initiative without public resources (PIWPR), there is no public funding; therefore, projects must be financed exclusively by operating income.
Figure 2 is a flowchart showing what private investors must do to propose an infrastructure project. According to the Colombian PPPs Law, this process takes no more than 18 months.
Considering that almost all financial models adopt a bottom-up approach to PPP projects [
46], this proposal used a strategy that prioritized input identification. Thus, this proposal considered two stages in implementing infrastructure projects to present an approach to a sustainable financial scheme that incorporates sustainability criteria into a financial model. The first had two stages, preparation and construction; they were unified for practical effects at the development stage. The second was the operating and maintenance (O&M) stage. The two stages were explained as follows.
3.2. Development Stage
Intending to keep track of the capital structure’s evolution during the development stage, which includes both the preparation and the construction stages, this work presents a mathematical model that enables the identification of impacts on the final capital structure based on an investment plan and capital structure per period. As shown in
Table 1, this proposal used three financial sources: equity, senior debt, and mezzanine debt.
This proposed mathematical approach can be adjusted to any financing process, which includes equity, senior debt, and/or mezzanine debt. The main elements were as follows, and, based on the proposal, assumptions were raised in items four, five, and six.
The investment plan could be divided into two stages. The first stage (preparation) has a duration of
x periods and the second stage (construction) has a duration of
k periods. Thus, the development stage, which combines the above stages, has a duration of
x +
k periods. This way, each investment can be given by
Ii, where
i indicates each period and, thus,
This equation enables an investment curve according to the construction plan; therefore, it does not use the distributed cost uniformly. In addition, O&M would have a duration of n periods and not have an investment plan. In this manner, the project’s total duration would be given by x + k + n periods, which includes the preparation, construction, and O&M stages. Additionally, the sustainability factor is also included in the investment plan.
- 2.
Each period can have a different capital structure. Thus, equity investment, given by %
Ei, could be different at each period
i; therefore, the total debt provided by the senior and mezzanine debt would be the complement (1 − %
Ei). As a result, Equation (6) is mandatory. This model can be used in any scenario. For example, lenders can limit the sponsors’ investment strategy through guarantees, covenants, or letters of credit; thus, project debts could be disbursed after a 100% equity investment or pari passu. The final capital structure would be given by the participation of the total equity and debt between the total Capex, which is shown in the “Final Capital Structure” column in Equations (4) and (5), respectively. Another method can calculate the weighted average between total equity and total Capex per period (Equation (10)). Similarly, the weighted average could be used, as shown in Equation (11).
- 3.
Interest rates in senior debt (
Kdsi) and mezzanine debt (
Kdmi) could be different at each period
i. Therefore, according to the project’s risk and development stage duration, it would be possible to have an interest rate arrangement per each period
i. Due to intrinsic risk, the relation between these interest rates follows Equation (8). The average cost of debt funding, which includes both senior and mezzanine debt, could be calculated as shown in Equation (12).
- 4.
Interest generated at each period i by accumulated debt, which includes senior and mezzanine debt, must be paid according to the capital structure of each period i.
- 5.
The investment plan, which includes both the construction contract and inflation, would be signed by sponsors through a SPV with a construction company. The total interest paid during the development stage can be calculated as the difference between the total Capex and the investment plan, which are given by
and Equation (9), respectively. Therefore, if the project is financed only by sponsors, this difference must be equal to zero, and if there is debt at the development stage, the total Capex must include the investment plan plus interest.
- 6.
A sustainability factor (SF) is defined as an increase in the investment at each period
i. According to [
47], this could be approximately 5%.
Fiscal benefits could play a pivotal role in encouraging eco-innovations in the financial area [
48]. Thus, based on the mathematical approach presented, the following consideration was considered in the proposal. Private investors, validated by competent authorities, who invest in improving the environment, would have the right to deduct the value of such investments from their annual income in the appropriate tax year; this deduction cannot be more than 20% of taxable income. Thus, since corporate income tax payments must be paid one year later, the benefits can be considered one year after the investment.
However, given that projects only have investment expenses in the development stage, the projects would not have either income or expenses, and, therefore, would not have taxable income. This proposal suggests that tax benefits obtained at this stage could be used as fiscal credit at the O&M stage. Similarly, this assumption was evaluated in the case study. In this way, Capex invested by private investors during the development stage for developing water and sanitation projects, particularly for improving the quality of wastewater discharges to rivers, could be transformed into cash benefits during the O&M stage. Therefore, the total benefits provided by this regulation can be calculated as follows.
Recently, the average involvement of equity investment and debt in Colombian water-sector projects, with more than 5000 users, was 67% and 33%, respectively [
49]. This indicates that the water sector requires new strategies for increasing its financial resources, especially debt instruments. Additionally, the average weighted average cost of capital (WACC) in these projects was 12.76% [
49]; this indicated that benefits could be obtained by achieving less expensive financial resources than debt, improving corporate value.
3.3. Operating and Maintenance Stage
Having modeled the evolution of the capital structure during the development stage, in the O&M stage, the model must incorporate the sustainable criteria into cash flows, particularly in free cash flow, debt cash flow, and equity cash flow. This project was carried out using financial engineering techniques as one of the main supports for PF schemes. In addition, it was structured as a PIPR project and based on the BOT (build, operate, and transfer) method for PPP projects. Accordingly, sponsors must create a SPV for developing infrastructure projects, and when the concession duration is over, they must transfer the assets (infrastructure projects) to the government. Therefore, the terminal value was not considered in the financial valuation process. In the Colombian case, according to PPP law 1508/2012, the maximum duration is 30 years, including extensions [
44].
To begin the mathematical modeling of the O&M stage, this stage was divided into two parts: operational and financing.
Figure 3, based on the cash flow waterfall, shows the first part with the main drivers for encouraging the involvement of private investors in the water sector, aiming at increasing regional coverage through sustainable infrastructure projects.
The main assumptions were presented below:
According to PPP law 1508/2012 [
44], PIPR projects can obtain financial resources from the Colombian Government. These resources are called “Future Funds”, and are conditioned by their availability, service levels, quality standards, and service continuity. These funds may not exceed 30% of the contract’s originally agreed value and are delivered only at the O&M stage. This scheme assumed that fee structure subsidies given to users were not part of the “Future Funds”.
Private investors using legal entities would be able to take annual deductions from their taxable income for environmental control and improvement investments. This value cannot exceed 20% of taxable income.
Income tax can be established per section.
From a programming perspective, Algorithm 1 shows how the capital structure can be calculated at the O&M stage, which can occur when the criteria are achieved; therefore, the debt–equity conversion could be executed.
Algorithm 1. Capital Structure Programming. Source: author’s, based on Table 1. |
1 Conversion Debt-Equity = False |
2 For i = 1 to n − 1 |
3 If Criteriai = Certify and Conversion Debt-Equity = False Then |
4 % Debti = (Debti − Mezzaninei)/Asseti |
5 % Equityi = (Equityi + Mezzaninei)/Asseti |
6 Conversion Debt-Equity = True |
7 Else |
8 % Debti = (Debti − Amortizationi)/Asseti |
9 % Equityi = Equityi/Asseti |
10 End if |
11 Next i |
As mentioned above, the return expected by lenders could take the form of interest, given by the
interest rate, and in the case of changing debt per equity share, dividends or profits obtained by lenders selling their equity shares before the concession is over. In this last scenario, creating a primary and secondary financial market for assets indexed to infrastructure projects is mandatory. This enables private investors to have a diversified project portfolio and, therefore, manage trades of equity shares of different projects, generating liquidity in the capital market. Accordingly, it would be possible to build a new infrastructure by creating more eco-innovative mechanisms and developing financial instruments to encourage sustainable infrastructure [
50]. In addition, financing should be more innovative and adapted to the SIS’s needs [
51].
This work suggests that if private investors finance projects using financial mechanisms indexed with sustainable criteria, the capital structure could change if goals and covenants related to sustainability criteria are accomplished and if an American-type option or warrant is exercised. In short, the conversion of outstanding debt per equity share would be sub-ordinated to sustainability criteria. In this way, this condition must be included in the deal.
This study did not intend to identify or propose a method for finding an optimal capital structure approach in infrastructure systems. On the contrary, this proposal intended to show how capital structure changes during the O&M stage. In this way,
Figure 4 shows not only how operational, but also financial sections can be integrated into the capital structure when outstanding debt is transformed into equity shares.
3.4. Proposal for Validating Debt Pay Capacity
The importance of the control and monitoring mechanisms implemented by sponsors, lenders, and governments led to the use of indicators able to measure a project’s capacity to pay for debt service and compliance with the infrastructure’s quality and service levels. In practice, the primary mechanisms used by financial institutions are the debt service coverage ratio (DSCR) and the loan life coverage ratio (LLCR) [
52], which measure the coverage of free cash flow (FCF) on debt services (interest plus repayment) during the credit period.
Figure 5 shows how the indicators explained above are related.
Table 2 indicates the DSCR and LLRC average for different sectors.
These indicators can help evaluate default situations. In this regard, [
53] stated that the PF default event occurs when specific indicators related to debt service and project flows drop below a certain level. In project monitoring, an auditing SPV can be used to validate compliance with fundamental indicators or conditions of projects so that financial institutions can require the issuance of certificates [
54].
Figure 5.
DCSR and LLCR as indicators of debt service capacity. Source: authors’ own based on Aragonés et al. [
53], Borgonovoa et al. [
52], Gatti [
55], and Moszoro [
56].
Figure 5.
DCSR and LLCR as indicators of debt service capacity. Source: authors’ own based on Aragonés et al. [
53], Borgonovoa et al. [
52], Gatti [
55], and Moszoro [
56].
Table 2.
DSCR and LLRC average for sectors. Source: Gatti [
55].
Table 2.
DSCR and LLRC average for sectors. Source: Gatti [
55].
Sector | DSCR | LLRC |
---|
Power | | |
Merchant plants | 2.00x–2.25x | 2.25x–2.75x |
With a tolling agreement | 1.50x–1.70x | 1.50x–1.80x |
Regulated business | 1.40x–1.45x | 1.40x–1.45x |
Transportation | 1.35x–1.50x | 1.40x–1.60x |
Telecommunication | 1.35x–1.50x | 1.35x–1.50x |
Water | 1.20x–1.30x | 1.30x–1.40x |
A financial model’s primary objective is to test the project’s financial viability [
46]. For that reason, considering that both indicators must be higher than one, both in a graphical way and as an extension to the DSCR and LLCR indicators, this proposal also contributed to the construction of a new method for monitoring debt-service capacity, as shown in
Figure 6. Zone A indicates that the project does not have the debt service capacity to pay; therefore, the operating or capital structure would have to be reconsidered. Zone B shows that the project can service its debt during a specific calculated period; however, it would not generate enough future FCF to pay the debt service. In Zone C, current and future debt service payments can be conducted with the FCF. Zone C is the ideal zone for any project. Finally, in Zone D, the project cannot service its debt during a specific period; however, the project would generate enough future FCF to service its debt, unlike in Zone B.
Other indicators identified in the literature and used to analyze the financial viability of infrastructure projects included the adjusted net present value, modified internal rate of return, self-financing capacity, equity ratio in risk [
57], decoupled net present value [
58], and the project life coverage ratio [
25,
26,
27,
28,
29,
30,
31,
32,
33,
34,
35,
36,
37,
38,
39,
40,
41,
42,
43,
44,
45,
46,
47,
48,
49,
50,
51,
52,
53,
54,
55,
56,
57,
58,
59].
3.5. Financing Sustainable Infrastructure Projects through Capital Markets
Promoting the implementation of innovative models, particularly in the social infrastructure sector (where coverage gaps are wide) would articulate the environmental variables related to sustainable development. As a result, supporting the Colombian capital market and investing in mitigating climate change has become the most important challenges in Latin America, particularly in Colombia.
Due to there being a historic window of opportunity to develop a sustainable financial system [
60], a complete funding framework for SISs should be based on a clear understanding of the complementary roles of public and private funding and how the two of them can work together to achieve complex, long-term social objectives [
61]. In this way, many public financial institutions work with private financing to close the viability gap for investors in green projects [
62].
As a proposal for financing SISs,
Figure 7 allows for the identification, under a systemic approach, of prominent participants in a sustainable financial framework. This proposal was based on PPP and PF schemes, and incorporated the Colombian capital market to raise sustainable financial recourses provided by special investors. Therefore, the primary objective of a sustainable financial framework should be to create value by implementing financial assets in ways that shape real wealth to support the long-term demand of a sustainable economy [
60]. Consequently, a revision of the financial regulations would be required to remove constraints on sustainable infrastructure investments, especially by institutional investors such as pension funds and insurers, and to create a rollover mechanism for sustainable infrastructure assets through debt and equity markets [
60]. In this way, creating a sustainable financial framework would be a great opportunity to defeat restrictions that avoid a complete recognition of environmental and social criteria in financial decision making.
Additionally, the generation of new market rules leading to long-term investment can help reduce GHG (greenhouses gas) emissions by improving quality of life. This initiative mobilizes financial and technological resources, requiring PPP schemes that link players in the private sector, prompting them both to develop public infrastructures and to provide financial strategies aligned with sustainable interests.
In the Colombian case, Decree 1385/2015 allowed both pension funds and insurance companies to finance PPP projects [
63]. Additionally, with the growth of infrastructure investments, specialized investors such as private equity funds are increasingly using mezzanine capital as a mechanism of investment in this area [
64]. However, sustainability criteria are not completely considered in the financial decision-making process. According to [
27], it is important to align the design of investment plans for this kind of investor with sustainability criteria as the essential first step.
In this framework, the sponsor must create a SPV, which is the investment vehicle. If the sponsor is not a public utility company (PUC), the SPV must establish a contract with one. The SPV has a BOT (build–operate–transfer) contract with the Colombian government, which could provide it with loan guarantees. The SPV is financed by both the sponsor (cash or in-kind) and the sustainable infrastructure market through sustainable mezzanine-type debt. There, investors with a high credit rating, such as institutional investors, could centralize funding requests into groups for financing SISs. A sustainable mezzanine-type debt could be, thus, structured as proposed in this work, which aims to incorporate social, environmental, and economic criteria into financing decisions. Thus, the project would help attract financial resources from private investors, such as pension funds, multilateral banks, and investment funds, dedicated to encouraging sustainable project development.
Since private investors invest to provide public utilities (a state responsibility), the Colombian government could provide financial guarantees that would make it cheaper than usual to raise financial resources. Although this argument could represent a good approach at the theoretical level, it would not work at the practical level.
The need for a new framework corresponds to a lack of research on new theories about innovations in financing strategic infrastructures and efforts to create new financing systems, as indicated in [
65]. Moreover, the scientific literature on investment and financing that addresses climate change and sustainable development remains limited, and knowledge gaps are substantial [
66]. In this context, sustainability plays a strategic role in infrastructure development. Sustainability is supported by the benefits of improving quality and coverage levels and encourages eco-friendly investments. However, developing a sustainable market project in Latin America would be a considerable challenge, particularly in Colombia [
67,
68].
This type of development requires increasing current levels of investment, boosting infrastructure improvements, and prioritizing the implementation of financing mechanisms related to climate change and, thus, sustainable development [
67]. Therefore, a financing mechanism is fundamental to the success of an investment connecting the creation of infrastructure and economic development with sustainable development. Indeed, much of the required economic development and infrastructure financing can be found in developing countries [
69]. Thus, for economic growth derived from SIS investments in Colombia, the government, the private sector, the capital market, and the research community must actively work together to establish and promote a new behavioral sustainable development model.
Therefore, creating a new business model for developing SISs would provide an opportunity to establish a market for climate derivatives. Colombia does not have an organized market or over-the-counter (OTC) derivatives related to the environment [
70]. Climate change represents a development challenge; therefore, integrating sustainability criteria into generating infrastructure projects should begin with planning and integrating these elements [
71].
4. Case Study
To apply the methodological proposal, the wastewater treatment plant “Aguas Claras” project was used as a case study. This project was located in the municipality of Bello, Antioquia, and was managed by Aguas Nacionales. This was a subsidiary company of Empresas Públicas de Medellín (EPM). EPM is one of the largest utility companies in Colombia. It is Colombia’s largest secondary-type treatment plant. It is operated on a 45-hectare lot in Bello, treating wastewater from both Bello and Medellín and removing more than 80 percent of pollution. To stabilize the sludge, Aguas Claras had six bio-digesters with a capacity of 8700 cubic meters.
This megaproject conducts the wastewater of the municipalities of Medellín and Bello to the site; wastewater receives secondary treatment through activated sludge before being discharged into the Medellín River. The plant has a treatment capacity of 5 m3/s and processes more than 70% of the wastewater for a total coverage of 95%. This percentage should be added to the San Fernando wastewater treatment plant, which is currently in operation. Aguas Claras is predicted to be three times larger in infrastructure and treatment capacity than the San Fernando plant.
These facilities are expected to receive 120 tons of organic matter from the wastewater produced daily by industries, commerce, and housing, with material exposed to biological, chemical, and physical processes, and then returned to the Medellín River. The goal was to cause the river to exceed the internationally accepted dissolved oxygen levels, indicating decontamination. Thus, by reducing the organic load, the river would increase its dissolved oxygen content to a minimum of 5 mg/L. This result would comply with the requirements of the environmental authority, Area Metropolitana del Valle de Aburrá. The wastewater would be transported through an interceptor 8 kilometers long and 2.4 m wide. In the future, this project is expected to serve urban developments and recreational spaces, such as the cities’ Christmas lighting and parks [
72].
4.1. Investment Plan
The investment plan required COP 1.47 billion and was executed for six years at the development stage, which ran from 2012 to 2017. For this project, the Inter-American Development Bank granted a USD 450 million credit to EPM (in turn, EPM provided its subsidiary Aguas Nacionales with the money). To financially evaluate the project and the proposal’s implementation, the capitalized funds were the equity investments, as confirmed by [
73].
Figure 8 shows the planned investment curve. This amount represented the value of the contract signed with the building company and accounted for inflation without the construction interests.
4.2. Development Stage
To validate the mathematical modeling of the capital structure’s evolution, the following information was considered, as shown in
Table 3.
Assumptions:
Planned investment curve: data based on Aguas Nacionales S.A. E.S.P.
According to Egler and Frazao [
14], the sustainability factor could be approximately 5%.
Capital structure per period: Although the project was 100% funded by own resources, to apply the methodological proposal based on primary information, it was considered that in the event of acquiring debt, the capital structure per period would behave as presented in
Table 4. The debt funds would be a sustainable financial mechanism in COP issued by the SPV.
The interest rate: Given that the Colombian capital market (and the Latin American one) has little experience in financing sustainable development, the last green bonds emission interest rate (issued by Bancolombia S.A. in December 2016) was considered as referent; it was equal to an IBR + 2.2% at seven years (the IBR is the banking reference indicator in Colombia). This was the first time that a Latin American bank issued this type of financial mechanism [
74]. Accordingly, given the project’s duration and characteristics, a 3.5% spread was considered.
IBR values were obtained from the Bank of the Republic of Colombia and Bancolombia, and projected by the authors.
Cash flows were projected in current prices.
Table 4 shows the last table’s values mathematically modeled according to the proposal developed. The equations were developed in
Table 1 and shown in parenthesis.
As mentioned above, it was important to include project funding strategies that provided profit to both public and private parties. Therefore, special characteristics had to be considered in this conceptual framework. This framework included a special focus on the relation among different cash flows, such as the free cash flow (FCF), debt cash flow (DCF), and equity cash flow (ECF), and was mentioned several times by [
75,
76,
77] because of its importance in the financial world, especially in the areas of project investment and firm valuation. Equation (16) and
Figure 9 show the relationships among the different cash flows and return rates. Additionally,
Table 5 shows the projected cash flows as well as the equity internal rate of returns (equity IRR). As you can see, when the fiscal benefits were included, the equity IRR was higher.
Figure 10a,b show the evolution of the capital structure and WACC during the project’s life-cycle.
The increasing development of the infrastructure requires not only the inclusion of new actors and the mobilization of more financial resources, but also the linking of environmental and social criteria to the structuring of projects, especially in the financing process. Consequently, concerns about constructing sustainable infrastructure resilient to climate change must transform how public–private sector policies are determined. Such policies must lead to redirecting investment and financing to market mechanisms that involve the generation of eco-innovative financial products with elements that promote sustainable development.
Figure 11 shows the proposal’s application for validating the debt service capacity. Zone A (in red) was highlighted in order to indicate when the project cannot pay the debt service. In any other case, the project could pay the debt service.
5. Conclusions
The increasing development of infrastructure requires not only the inclusion of new actors and the mobilization of more financial resources, but also the linking of environmental and social criteria to the structuring of projects, especially in the financing process. Consequently, concerns about constructing sustainable infrastructure resilient to climate change must transform how public–private sector policies are determined. Such policies must lead to redirecting investment and financing to market mechanisms that involve the generation of eco-innovative financial products with elements that promote sustainable development.
To develop an infrastructure that minimizes greenhouse gas emissions without compromising financial viability, specific financial mechanisms must be developed. This goal is supported by the SDGs, which encourage research and development that contribute to and promote sustainable development through new mechanisms and instruments [
78]. Thus, Colombia is responding to the global challenge to reduce GHG emissions through a new way of developing infrastructure that should improve coverage in regions lacking infrastructure systems. If the world wants to achieve the SDGs, adequate infrastructure development is part of the answer. Therefore, a standard and clear model is crucial. Such a model would benefit project developers, lenders, and public sector institutions [
47].
This research showed that factors such as financing and investment should be directly related to financial, environmental, and social criteria, allowing decision makers to analyze such factors holistically and obtain information about each process, particularly financing. In addition, market-led mechanisms, such as benefits, taxes, grace periods, debt forgiveness, duty-free machinery, and new regulations, could drive an infrastructure market based on sustainable criteria and, thus, the creation of a primary and secondary market of stocks and debts issued by sponsors or investment vehicles (SPVs). Such actions would allow the expansion of investment options through the Integrated Latin American Market (MILA). Implementing capital markets based on sustainable investments could eventually influence other sectors, such as transportation, energy, and telecommunications.
Further research on sustainable finance should involve the flexibility assessment of the creation of sustainable projects as a strategic tool for encouraging private investment through PPP schemes, in which private investors and public sector development projects consider sustainability, accessibility, and reliability in the provision of SISs. These analyses should account for the sensitivity and dynamics of the available financial resources. For this proposal, the real options theory would capture aspects related to a project’s capacity that relate to sustainable financial resources. Additionally, an interesting research topic would be analyzing cost overruns/underperformance of mega-projects, which have sustainable impacts. For example, what could happen to a sub-ordination arrangement if a project is over budget or revenues are less than projected? Overruns in megaprojects were widely studied in refs. [
79,
80]; in this way, further research should also allow to widen the frontier of knowledge on this issue.
As a theoretical contribution, this study developed a sustainable financial framework, which included a mathematical model that allowed for an understanding of how capital structure changes during a project’s life-cycle, considering a financial mechanism sub-ordinated to sustainability criteria. This paper contributes to the project management and infrastructure literature by exploring the main financial topics that practitioners and academics involved in project assessment must consider when developing SISs
Finally, this proposal contributes to the state-of-the-art in SIS financing decisions. In addition, given the need to satisfy the requirements of SDGs, the relationships between sustainability, project management, and infrastructure are an emerging field for contributions of innovative proposals that would allow the achievement of those programs’ goals. In this regard, there is a great deal of room for a better understanding of the relationship between financial market development and sustainable development.
Despite the contributions of this work, limitations should be acknowledged. Although the framework was designed for the Colombian context, it could also be used in other countries considering the application of specific tax benefits, which was the major limitation of this research. Additionally, in order to compare the effects and the performances of initial investment plans with those involved in the newly proposed methodology and model, it was not possible to obtain real data. Moreover, in Colombia, the convertible financial mechanism market is not fully developed. Therefore, bringing this proposal to real scenarios may take time. Consequently, this proposal may also be a further step in advancing toward developing a sustainable financial framework of convertible mechanisms that can be applied in a real-world context. In addition, it is worth mentioning that this paper was derived from the Doctoral dissertation of Juan David González-Ruiz [
81].