Next Article in Journal
Influences of Silica Fume on Compressive Strength and Chemical Resistances of High Calcium Fly Ash-Based Alkali-Activated Mortar
Next Article in Special Issue
An Analytical Study of the Latest Trends of Free-Form Molds
Previous Article in Journal
A Study on Risk Measurement of Logistics in International Trade: A Case Study of the RCEP Countries
Previous Article in Special Issue
A Deep Learning Model Development to Predict Safety Accidents for Sustainable Construction: A Case Study of Fall Accidents in South Korea
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Improving Sustainable Project Success Strategies Focused on Cost and Schedule for Electrical Construction Project Management

1
Department of Civil Engineering, Kangwon National University, Samcheok-si 25913, Korea
2
Department of Architectural Engineering, Pusan National University, Busan 46241, Korea
3
Department of Architectural Engineering, Changwon National University, Changwon-si 51140, Korea
*
Author to whom correspondence should be addressed.
Sustainability 2022, 14(5), 2653; https://doi.org/10.3390/su14052653
Submission received: 29 December 2021 / Revised: 21 February 2022 / Accepted: 23 February 2022 / Published: 24 February 2022
(This article belongs to the Special Issue Research and Practice of Sustainable Construction Project Management)

Abstract

:
Electrical contractors encounter problems such as limited construction sites, schedule interference, and inefficient communication with other contractors when they typically subcontract with general contractors. Electrical projects require effective and systematic project management strategies to overcome these problems and achieve the desired goal. In an electrical construction project, individual tasks are interconnected at different stages, including pre-construction planning (PCP) and project execution (PE). Therefore, analyzing the effect of task strings on the project success in terms of schedule and cost performance is necessary. The main objective of this study is to perform a static analysis to compare successful and failed projects with a focus on the cost and schedule performances, using the PCP and PE task strings in electrical construction projects. To achieve this, a continuous PCP-PE task strings implementation score was calculated for each PE group in terms of cost and schedule, and successful and failed projects on unweighted and weighted values were compared and analyzed by performing an independent sample t-test. Consequently, it was confirmed that the use of most task strings had a positive effect on the cost success at a confidence level of 95%, and that only the subcontractor management group had a positive effect on the schedule success. Hence, it was derived that the usage of task strings for these groups is recommended for cost success in electrical construction, and continuous PCP-PE task strings do not have a positive effect on schedule success; therefore, it is recommended to use the PCP-PE task strings only for specific groups for schedule success in electrical construction. Demonstrating the relationship between the PCP and PE tasks, the findings of this study are expected to help electrical contractors achieve a better performance using effective project management strategies.

1. Introduction

1.1. Background and Research Objectives

Effective execution of planned work is crucial to improving project performance in the construction industry [1]. Unreliable project management and execution increases waste and reduces productivity, thereby increasing the rate of failure in construction projects. In particular, poor planning and lack of control over construction execution requires rework that results in a large amount of lost productivity [2]. The conventional lean construction concept, which emerged in the construction industry in the mid-1990s, is applied to overcome these project management problems [3]. Lean construction is defined as a method of designing production systems to minimize time, material waste, and create maximum value [4]. That is, lean philosophy promotes the efficient use of resources [3,5,6,7,8,9,10] and highlights the reduction of wastes that ultimately have serious environmental effects [11,12,13,14,15].
Electrical contractors, as subcontractors, are exposed to disadvantages, such as schedule interference, limited workspace, and inefficient communication with other trades [16], which ultimately causes reduced productivity and schedule delays in electrical projects [17,18]. Therefore, electrical contractors need more systematic and effective project management strategies to solve these problems and achieve the desired project goals efficiently. Many studies have been conducted to analyze various management aspects of electrical construction projects. Studies include the analysis of the effect of change orders on electrical contractors [19,20], scheduling [21], and design/construction project considerations [22], productivity benchmarking [23], electrical worker safety [24], absenteeism factors of electricians [25], conceptual planning process [26], coordination of mechanical, electrical, and plumbing trades [18,27,28], using building information modeling by electrical contractors [29,30], human resource recruitment and detainment strategies [31], and prefabrication in electrical construction [32]. However, although many studies have been conducted on electrical construction projects, management strategies have not been investigated sufficiently to successfully implement them into projects.
Project management became an issue to be considered at the organizational level [33], and this need led to the concept of organizational project management maturity in the late 1990s [34]. Many project maturity models have been introduced and related studies have been conducted. Iqbal (2013) provided an overview of the existing project maturity model [35], and Yazici (2009) showed that the contribution of project management maturity to better project performance is largely determined by organizational culture characteristics [36]. In particular, the International Journal of Managing Projects in Business published a special issue in 2014 on the topic of project management maturity. In addition, Pasian (2014) pointed out the decisive role of non-process factors in achieving mature project management for projects that are not precisely defined [37]. In addition, studies on more successful project management have been conducted using the project management maturity model [38,39,40,41]. Therefore, it is necessary to quantify and analyze the degree of management to successfully carry out the project in the field of electrical construction.
In electrical construction projects, individual tasks of pre-construction planning (PCP) and project execution (PE) are correlated with each other at different stages [16]. Relevant tasks in PCP-PE must be linked and completed consecutively to achieve an efficient PE, instead of completing PCP or PE tasks separately. Therefore, a continuous task string model was developed which consists of specific combinations of the PCP and PE tasks [1]. The PCP-PE task string model can be utilized to recognize the task relationship between planning and execution. It can eliminate unnecessary tasks and improve project productivity by efficiently using PCP-PE task strings. However, to verify the effect on PCP-PE task strings, it is necessary to investigate its impact on project performance. In particular, the effectiveness of continuous task strings on project performance must be quantified in terms of the schedule and cost success [42], which are significant in construction projects. The main objective of this study is performing the static analysis to compare successful and failed projects with a focus on the cost and schedule, using task strings of PCP and PE in electrical constructions. Meeting project cost and schedule is an important factor contributing to project success. Therefore, this paper is limited to success in terms of cost and schedule.

1.2. Research Methodology

This study involved the following steps:
(1)
Review the existing studies on PCP and PE, and the concept of PCP-PE task strings.
(2)
Collect data of 50 recently completed projects from 25 electric companies in the United States.
(3)
Evaluate the importance of cost and schedule success for 239 continuous task strings by 29 electrical experts.
(4)
Introduce methods for applying the unweighted/weighted value to quantify the performance of task strings implementation.
(5)
Develop hypotheses regarding the mean of successful and failed projects to statistically analyze the effect of task strings.
(6)
Calculate continuous PCP-PE task strings implementation score for each PE group in terms of cost and schedule.
(7)
Compare and analyze successful and failed projects on unweighted and weighted values by performing an independent sample t-test.

2. Preliminary Study

2.1. Existing Studies of PCP and PE

2.1.1. PCP

Project planning was included in some textbooks as part of the project control and management process in the 1970s and early 1980s [43,44]. In the late 1980s and early 1990s, several independent studies were conducted on construction project planning [45,46]. Furthermore, Gigado (2004) presented a systematic approach for planning that could improve and standardize the PCP process of prime contractors [47]. The proposed model provides a best practice approach to the PCP processes of prime contractors. Since the late 1990s, there has been relatively few studies on planning; however, advanced formalized plans are needed to maintain competitiveness in an increasingly dynamic construction industry [48].
Menches and Hanna (2006) proposed a model PCP process that included 123 planning tasks performed by electrical contractors using the data collected. Menches (2006) statistically compared the differences in the implementation of planning tasks between successful and failed projects to complement the baseline planning process. Consequently, 46 critical tasks consistently performed on successful projects, were selected for inclusion in the PCP process. These tasks were classified into ten categories: (1) team selection and turnover, (2) administrative setup, (3) scope and contract review, (4) material-handling plan, (5) buyout process, (6) layout and sequencing plan, (7) budget preparation, (8) tracking and control, (9) schedule development, and (10) construction-execution kickoff meeting. Kim et al. (2013) investigated the frequency of the execution of these tasks and achieved cost and schedule successes. Thus, five groups were excluded, and eleven PCP tasks in only five groups are listed in Table 1.

2.1.2. PE

Nasr (2009) developed an electrical PE process using 85 tasks by constructing a model using tasks performed on successful projects [49]. The tasks were classified into the following 14 categories: (1) mobilization, (2) document management, (3) material management, (4) tool management, (5) subcontractor management, (6) safety, (7) communication, (8) coordination, (9) scope and change control, (10) scheduling, (11) cost control and billing, (12) quality management, (13) labor management, and (14) project closeout. Kim et al. (2015) investigated the achieved cost and schedule. Therefore, only the coordination group was excluded, and 47 PE tasks in 13 groups are listed in Table 2.

2.2. Concept of Task String

From the contractor’s perspective, after engineering and design completion, construction projects typically progress through the stages of bidding, PCP, PE, and commissioning (or closing) [48]. PCP tasks are associated with PE tasks because PCP tasks are used to plan and manage various systems to efficiently manage PE tasks. Therefore, related planning and execution tasks must be executed sequentially in line with the project phases to achieve effective project management. A combination of planning and execution tasks is defined as task strings because it must start with PCP and progress continuously through the completion of PE.
For example, in the PCP phase, material handling plans involve the process of ordering, receiving, preparing, and storing major equipment and materials at the site. These planning tasks relate to material management tasks performed during the PE phase and include receiving material deliveries, checking packaging for damage, comparing deliveries against invoices, and storing materials according to the storage plan. Therefore, material handling plans should be derived during the PCP phase to effectively implement material management tasks during the PE phase. In this case, the two tasks are called continuous task strings between the PCP and PE phases [1]. Kim et al. (2015) provided the results of modeling continuous task strings and examining their effects on project performance. This study introduces a new concept called continuous task strings consisting of particular combinations of PCP and PE tasks that are expected to improve project performance. In addition, 3910 combination tasks of the PCP (46 tasks) and PE (85 tasks) phases were reduced to 239 task strings, as shown in Table 3. However, the effect of continuous PCP-PE task strings on project performance has not been explored and verified adequately.

3. Continuous PCP-PE Task Strings Performance Analysis Plan for Project Success

3.1. Data Collection

Data from 50 completed projects were collected from 25 electric companies in the United States to perform PCP-PE task string analysis. They were randomly selected from a list of 2000 electrical members of the National Electrical Contractors Association. Each company provided data on successful and failed projects. The data consisted of information on PCP-PE task execution and project performance, categorized as success or failure in terms of schedule and cost. A project was classified as a failed project if the target cost and schedule were not met; otherwise, it was classified as a successful project. In terms of cost, 30 of 50 electricity projects were classified as successful and 20 as failed, whereas 42 and 8 projects were classified as successful and failed, respectively, considering the schedule criterion. That is, in terms of schedule and cost, success and failure were classified according to the degree of achievement, and the degree was investigated through a survey. To quantify the performance of implementing 239 continuous PCP-PE task strings to project success, electrical experts prioritized their importance considering the cost and schedule success criteria. The survey was sent via email to 75 electricians, and 29 surveys were collected, yielding a response rate of 38.7%.

3.2. Measurement Method of Implementing Continuous PCP-PE Task Strings

3.2.1. Implementation of Unweighted Task Strings

The continuous PCP-PE task string performance score measures the level of performance for electrical projects. The task strings were grouped into 13 PCP tasks versus PE groups according to the PE task category. Thus, the PCP-PE task string implementation score quantified the extent to which task strings were implemented within the PCP-task-to-PE group during the PCP and PE stages. For simplicity, the task strings were weighted uniformly to avoid bias, and the mean score was in the range of 0–1. A mean value of 1 indicates that all task strings within each PCP-task-to-PE- group have been implemented for the project (success or failure project), whereas a mean value of 0 indicates that no task string has been implemented. The PCP-PE task string implementation score is calculated as Equation (1):
UTS IS = i = 1 n   ( TS i ) / N ,
where UTSIS is the unweighted task string implementation score, TSi represents the i-th task string performance, and N is the number of task strings on PCP task-to-PE group.

3.2.2. Weighted Task Strings Implementation

The weights of each task string were also applied to reflect their relative importance, and the continuous PCP-PE task strings implementation score was calculated using Equation (2); five to seven electrical experts rated the importance of each task string to achieve schedule and cost success on a Likert scale of 0 to 4 (0 = not important, 4 = very important). The raw score was converted to a 0–10 score by multiplying it by 2.5 to make the relative importance clearer. These transformed cost and schedule importance mean scores were used as weight values for the PCP-PE task strings.
WTS IS = i = 1 n j = 1 m   ( TS i W j × 2.5 ) / N ,  
where WTSIS represents the weighted task string implementation score, TSi is the i-th task string implementation, Wj represents the j-th relative importance of the task string, and N is the number of task strings on PCP task-to-PE group.

3.3. Hypothesis Setting

An independent samples t-test was performed considering the cost and schedule success to determine the differences in the work string usage. This analysis was conducted to statistically determine any significant differences between the projects with successes and failures in task string implementation. An independent sample t-test requires measuring dependent variables on a ratio scale or an interval, whereas the independence, normality, and equal variance must be satisfied. The independent variables are successful and failed projects in terms of the schedule and cost, and the dependent variables are the continuous PCP-PE work string implementation score means. In addition, Levene’s test was used as an inferential statistic test to assess the equality of population variances. In this study, the effect of work strings on project performance was analyzed by dividing it into the cost and schedule criteria. The continuous PCP-PE task string implementation score means for successful and failed projects for 13 PE task category groups were comparatively analyzed by dividing them into unweighted and weighted PCP-PE task strings. Figure 1 shows that the four analysis results are derived in terms of the cost and schedule performances. The null Hypothesis (H1) is ‘The PCP-PE task strings implementation score means for successful and failed projects are the same’ and the alternative Hypothesis (H2) is ‘The PCP-PE task strings implementation score means for successful and failed projects are different.’ This was verified at a confidence level of 95%.
Hypothesis 1 (H1).
The PCP-PE work string implementation score means for successful and failed projects are the same.
Hypothesis 2 (H2).
The PCP-PE work string implementation score means for successful and failed projects are different.

4. Performance Analysis of the Effect of Work Strings on Cost and Schedule

4.1. Analysis of Cost Success and Failure

4.1.1. Effect of Unweighted Task Strings

The continuous PCP-PE work string implementation score was calculated as an unweighted task string in terms of cost. Figure 2 presents the mean PCP-PE task string implementation scores for successful and failed projects. The mean of the successful projects is always higher than that of the failed projects; thus, a correlation exists between the obtained means. However, because this is just a comparison of the mean values, the distribution of the overall values is difficult to analyze.
Table 4 shows the results of the independent sample t-test for cost performance to explore the differences in task string usage, indicating that many PCP-task-to-PE groups significantly differ between successful and failed projects. As the analysis was performed at a confidence level of 95%, the p-value was not greater than 0.05, the null hypothesis was rejected, and the alternative hypothesis was accepted. That is, the difference between the mean values indicates that successful projects have a higher probability of success owing to the use of task strings than that of the failed projects, including the mobilization, document management, material management, tool management, communication, cost control and billing, scheduling, labor management, quality management, and project closeout. However, the other groups did not exhibit significant results statistically. Thus, with the exception of the subcontractor management, scope change, safety management, and control, which did not produce statistically significant results, task-string groups are predicted to contribute considerably to cost success.

4.1.2. Effect of Weighted Task Strings

Figure 3 presents the results obtained considering a weighted continuous PCP-PE task string implementation score in terms of successful and failed projects. Similar to the unweighted task strings, the mean of successful projects is always higher than that of failed projects; thus, a correlation exists between the mean values. Table 5 shows the results of an independent sample t-test for cost performance. Additionally, an independent sample t-test was performed to investigate the differences in the work string usage. As the p-value is not greater than 0.05, the alternative hypothesis is accepted. That is, many work-string groups significantly differed between successful and failed projects at a confidence level of 95%. These results are consistent with those of the unweighted work-string groups. However, the three task-string groups (subcontractor management, scope change & control, and safety management) did not produce statistically significant results, which indicates that the effectiveness of the strings in the PE phase is difficult in these three groups. Therefore, the task strings are predicted to have a positive effect on the cost success; thus, the use of task strings for cost success in electrical construction projects is recommended.

4.2. Analysis of Schedule Success and Failure

4.2.1. Effect of Unweighted Task Strings

Figure 4 demonstrates the continuous PCP-PE task strings implementation mean score for unweighted work strings in terms of successful and failed projects considering the schedule performance. Except for the communication group, all of the means of the successful projects are always higher than those of the failed projects. Table 6 describes the results of an independent sample t-test for schedule performance to investigate the differences in the task strings usage. The PCP-PE task strings implementation score includes the mean of successful and failed projects considering the schedule performance. Only the p-value of subcontractor management was 0.036 when the analysis was at a confidence level of 95%. Thus, the null and alternative hypothesis were rejected and accepted, respectively, indicating that the influence of work strings usage within the group differed between the successful and failed projects. Consequently, using task strings is predicted to increase the probability of project success.
However, ten different task-string groups, including mobilization, document management, material management, scope change and control, communication, scheduling, cost control and billing, labor management, quality management, and project closeout, did not produce statistically significant results. The p-values of tool and safety management were 0.055 and 0.076, respectively, indicating a significant difference between the successful and failed projects at a confidence level of 90%. That is, the three task-string groups (tool management, safety management, and subcontractor management) can contribute significantly to schedule success at a confidence level of 90%.

4.2.2. Effect of Weighted Task Strings

Figure 5 shows the mean of continuous PCP-PE task-string implementation scores for successful and failed projects concerning the schedule performance. Unlike Figure 4, all of the mean values of the successful projects, including the communication group, are always higher than those of the failed projects. Table 6 lists the results of an independent sample t-test concerning the schedule performance. The p-value of subcontractor management was 0.034, which rejected the null hypothesis. Therefore, the effect of task-string usage was predicted to differ significantly between the successful and failed projects at a confidence level of 95% concerning the schedule performance.
However, in Table 7, 10 task strings groups, including mobilization, communication, document management, material management, scope change and control, scheduling, quality management, cost control and billing, project closeout, and labor management, did not produce statistically significant results. In addition, p-values of tool management and safety management were 0.055 and 0.075, respectively, showing a significant difference between the success and failure projects at the 90% confidence level. Therefore, this means that most of the task strings do not have a positive effect on the schedule success.
In Figure 5, mean values of the successful projects were always higher than those of the failed projects; thus, it seemed that there was a correlation between the mean values. However, the statistical analysis in Table 6 demonstrates significantly different results between the correlated mean values. This is because the mean value is different for each distribution; therefore, it cannot be clearly determined that the successful projects contributed more positively than the failed projects using PCP-PE task strings. In addition, the results illustrate that cost had a positive effect on the use of task strings compared to schedules. Consequently, it is recommended to use task strings only in certain groups for achieving schedule success in electrical construction projects.

5. Validation of Continuous PCP-PE Task Strings

To validate that continuous PCP-PE work strings contribute to project success, the impact of task strings implementation on project success was investigated in terms of cost and schedule performance. The basic concept of validation is to ensure that the implementation of continuous PCP-PE work strings contribute to the success of the project. For verification, 50 sets of electrical projects were divided into two groups: successful and failed projects. In total, 30 of the 50 electricity projects were classified as cost-successful and 42 on schedule. Furthermore, the impact of the task strings’ performance on project success was evaluated to identify valuable work strings. The following four hypotheses were developed to identify worthwhile work strings:
Hypothesis 3 (H3).
Work strings are critical to project success when performed frequently in successful projects.
Hypothesis 4 (H4).
Work strings are less critical to project success when performed less frequently in successful projects.
Hypothesis 5 (H5).
Work strings do not contribute to project success when performed frequently in failed projects.
Hypothesis 6 (H6).
Work strings are required for project success when performed less frequently in failed projects.
Hypotheses H1 and H4 showed that several task strings contribute to project success. However, H2 and H3 confirmed that some task strings do not contribute to project success. Thus, the effectiveness of work strings is validated when they are implemented frequently in successful projects and less frequently in failed projects. Figure 6 shows the validation process concept.
As shown in Figure 6, work strings implemented in more than 50% of successful projects (A) and less than 50% of failed projects (B) were confirmed to have contributed to project success. On the other hand, task strings implemented in less than 50% of successful projects (C) or implemented in more than 50% of failed projects (D) were invalidated. For validation, 239 work strings ranked in the Best/Better/Basic work string categories were analyzed in terms of schedule and cost performance. Based on the percentage of task string performance in successful and failed projects, each task string was constructed to identify the categories it should contain. Figure 7 graphically shows plots of each task string for successful and failed projects. On the 239 continuous work strings, those included in both A and B were identified as task strings contributing to project success. Therefore, the impact of 196 action strings on cost success and the impact of 145 task strings on schedule success was determined. The verification results are described in Table 8.
In total 66.9% of ranked task strings were validated for cost success and 74.1% for schedule success. In particular, better work strings were identified more than other rank strings, especially with a cost success rate of 85.4% and a schedule success rate of 100%. However, a relatively small number of basic task strings were validated in terms of their contribution to project success, representing 62.4% in cost success and 57.1% in schedule success, respectively. The validation of the effectiveness of work strings was confirmed in terms of cost and schedule success. In other words, more than 67% of task strings were found to contribute to project success. A list of high-value work strings (best task strings) is summarized in Table 9.

6. Discussion

To quantitatively evaluate the subjective project maturity, this study analyzed whether continuous PCP-PE task strings affect project success in terms of cost and schedule through a survey of electricians. Project maturity refers to an organization’s ability to master a project [50]. Companies with high project maturity are considered more likely to succeed than companies with low project maturity. Measuring project maturity can be subjective rather than objective [51]. Some of the most important work on project maturity focuses primarily on the operations performed by organizations and project people [52]. In addition, projects either fail or succeed for no particular reason. In other words, a project does not fail or succeed on one variable, but is influenced by many other factors.
Mullaly (2014) emphasized the need to consider both organizational and contextual factors and pointed out the need for a conditional perspective on project maturity assessment both in the project process and the context [53]. Furthermore, it was considered that the situational factor was underestimated because the maturity model has a repeatable process and the process itself is an appropriate tool to improve the project management maturity. Many studies have suggested the need to identify organizational-level determinants to achieve higher levels of maturity [39,54,55,56,57]. In addition, some studies have emphasized that they do not consider organizational-level determinants and other contextual factors that shape organizational project management maturity [58,59].

7. Conclusions

A continuous task-string model was developed by linking the PCP and related PE tasks to improve the performance of electrical construction projects. In this study, statistical analyses were performed to test the effect of 13 categories on project success using continuous PCP-PE task strings. Independent sample t-tests were performed using 50 completed projects to compare the successful and failed projects concerning the cost and schedule performance. The conclusions are drawn as follows:
First, it was confirmed that the use of most task-string groups had a positive effect on the cost success at a confidence level of 95%. Positive results were obtained for unweighted and weighted task strings in 10 of the 13 categories: mobilization, document management, material management, tool management, communication, scheduling, cost control and billing, quality management, labor management, and project closeout. The use of task strings for these groups is recommended for achieving cost success in electrical construction projects.
Second, it was confirmed that the use of continuous PCP-PE task strings had a positive effect on schedule success only in the subcontractor management group at a confidence level of 95%. Among the other categories, it was confirmed that the tool and safety management groups had a positive relationship at only a confidence level of 90%. A total of ten PCP-PE task-string groups, including mobilization, document management, material management, communication, scope change and control, scheduling, cost management and billing, quality management, labor management, and project closeout, did not produce statistically significant results for project success. Therefore, continuous PCP-PE task strings do not have a positive effect on the schedule success, and it is recommended to use PCP-PE task strings only for certain groups to achieve schedule success in electrical construction projects.
Third, the mean values of task-string score for successful projects were approximately higher than those of the failed projects; thus, it seemed that the mean values differed. However, statistical analysis demonstrated that there were no significant differences between the successful and failed projects in several categories. Therefore, the mean value of successful projects is not always higher than that of failed projects in the distribution of actual mean values. In the case of groups with a mean value that did not produce a statistically significant result, the project cannot always succeed even if task stings are used.
In this study, it was confirmed that continuous PCP-PC task strings can be applied to electricity projects to improve cost and schedule performances. This study provides empirical evidence to support the possibility that the introduced task string implementation can significantly help electricity construction projects. By leveraging the developed task strings to help contractors fully understand the relationship between certain tasks and beneficial outcomes, they can be used as task-level strategies that might lead to project success. In addition, it can contribute to research on the establishment of management strategies to implement projects successfully in the field of electrical construction. This study was conducted on general projects; however, in future research, additional task strings that have a considerable effect on the project characteristics should be identified for the expansion of continuous PCP-PE task strings.

Author Contributions

Conceptualization, D.Y.K.; methodology, J.K. and D.Y.K.; validation, J.L. and D.Y.K.; formal analysis, J.L. and D.Y.K.; investigation, H.-C.L. and D.Y.K.; resources, H.-C.L. and D.Y.K.; data curation, J.K.; writing—original draft preparation, J.K. and D.Y.K.; writing—review and editing, J.L. and D.Y.K.; visualization, J.L.; supervision, D.Y.K.; project administration, D.Y.K. All authors have read and agreed to the published version of the manuscript.

Funding

This study was supported by 2021 Research Grant from Kangwon National University and by Basic Science Research Program through the National Research Foundation of Korea (NRF) funded by the Ministry of Education (NRF-2021R1I1A3049510).

Institutional Review Board Statement

Not applicable.

Informed Consent Statement

Not applicable.

Data Availability Statement

Not applicable.

Conflicts of Interest

The authors declare no conflict of interest. The funders had no role in the design of the study; in the collection, analyses, or interpretation of data; in the writing of the manuscript, or in the decision to publish the results.

References

  1. Kim, D.Y.; Menches, C.L.; O’Connor, J.T. Stringing construction planning and execution tasks together for effective project management. J. Manag. Eng. 2015, 31, 04014042. [Google Scholar] [CrossRef]
  2. Meeks, S.E. Enhanced Work Packaging: Design through Workface Execution; Implementation Resource Rep. 272-2; Construction Industry Institute: Austin, TX, USA, 2011. [Google Scholar]
  3. Francis, A.; Thomas, A. Exploring the relationship between lean construction and environmental sustainability: A review of existing literature to decipher broader dimensions. J. Clean. Prod. 2020, 252, 119913. [Google Scholar] [CrossRef]
  4. Koskela, L.; Ballard, G.; Howell, G.; Tommelein, I. The Foundations of Lean Construction. Design and Construction: Building in Value; Routledge: London, UK, 2002; pp. 211–226. [Google Scholar]
  5. Bae, J.W.; Kim, Y.W. Sustainable value on construction projects and lean construction. J. Green Build. 2008, 3, 155–167. [Google Scholar] [CrossRef]
  6. Bidarianzadeh, G.R.; Fortune, C.J. Lean thinking and the delivery of sustainable construction projects. In Proceedings of the 18th Association of Researchers for Construction Management Conference, Northumbria, UK, 2–4 September 2002; Volume 2, pp. 2–4. [Google Scholar]
  7. Degani, C.M.; Cardoso, F.F. Environmental performance and lean construction concepts: Can we talk about a clean construction? In Proceedings of the 27th Annual Conference of the International Group for Lean Construction (IGLC), Dublin, Ireland, 3–5 July 2002; pp. 1–13. [Google Scholar]
  8. Horman, M.J.; Riley, D.R.; Pulaski, M.H.; Leyenberger, C. Lean and Green: Integrating Sustainability and Lean Construction. In Proceedings of the CIB World Building Congress, International Council for Research and Innovation in Building and Construction, Toronto, ON, Canada, 1–7 May 2004; pp. 2–7. [Google Scholar]
  9. Khodeir, L.M.; Othman, R. Examining the interaction between lean and sustainability principles in the management process of AEC industry. Ain Shams Eng. J. 2018, 9, 1627–1634. [Google Scholar] [CrossRef]
  10. Nahmens, I. From lean to green construction: A natural extension. In Proceedings of the Construction Research Congress, Seattle, WA, USA, 5–7 April 2009; pp. 1058–1067. [Google Scholar]
  11. Ballard, G.; Howell, G. Lean project management. Build. Res. Inf. 2003, 31, 119–133. [Google Scholar] [CrossRef]
  12. Eriksson, P.E. Improving construction supply chain collaboration and performance: A lean construction pilot project. Supply Chain. Manag. Int. J. 2010, 15, 394–403. [Google Scholar] [CrossRef]
  13. Green, S.D. The missing arguments of lean construction. Constr. Manag. Econ. 1999, 17, 133–137. [Google Scholar] [CrossRef]
  14. Jorgensen, B.; Emmitt, S. Lost in transition: The transfer of lean manufacturing to construction. Eng. Constr. Archit. Manag. 2008, 15, 383–398. [Google Scholar] [CrossRef] [Green Version]
  15. Mao, X.; Zhang, X. Construction process reengineering by integrating lean principles and computer simulation techniques. J. Constr. Eng. Manag. 2008, 134, 371–381. [Google Scholar] [CrossRef]
  16. Kim, D.Y. Construction Planning and Execution Strategies for Enhancing Project Success on Electrical Construction Subcontracts. Ph.D. Thesis, The University of Texas, Austin, TX, USA, 2011. [Google Scholar]
  17. Guo, S.J. Identification and resolution of work space conflicts in building construction. J. Constr. Eng. Manag. 2002, 128, 287–295. [Google Scholar] [CrossRef]
  18. Horman, M.J.; Orosz, M.P.; Riley, R.D. Sequence planning for electrical construction. J. Constr. Eng. Manag. 2006, 132, 363–372. [Google Scholar] [CrossRef]
  19. Hanna, A.S.; Russell, J.S.; Nordheim, E.V.; Bruggink, M.J. Impact of change orders on labor efficiency for electrical construction. J. Constr. Eng. Manag. 1999, 125, 224–232. [Google Scholar] [CrossRef]
  20. Hanna, A.S.; Camlic, R.; Peterson, P.A.; Lee, M. Cumulative effect of project changes for electrical and mechanical construction. J. Constr. Eng. Manag. 2004, 130, 762–771. [Google Scholar] [CrossRef]
  21. Noyce, D.A.; Hanna, A.S. Planned schedule compression concept file for electrical contractors. J. Constr. Eng. Manag. 1997, 123, 189–197. [Google Scholar] [CrossRef]
  22. Rowings, J.E.; Federle, M.O.; Rusk, J. Design/build methods for electrical contracting industry. J. Constr. Eng. Manag. 2000, 126, 15–21. [Google Scholar] [CrossRef]
  23. Hanna, A.S.; Peterson, P.; Lee, M. Benchmarking productivity indicators for electrical/mechanical projects. J. Constr. Eng. Manag. 2002, 128, 331–337. [Google Scholar] [CrossRef]
  24. Abudayyeh, O.; Federicks, T.; Palmquist, M.; Torres, H.N. Analysis of occupational injuries and fatalities in electrical contracting industry. J. Constr. Eng. Manag. 2003, 129, 152–158. [Google Scholar] [CrossRef]
  25. Hanna, A.S.; Menches, C.L.; Sullivan, K.T.; Sargent, J.R. Factors affecting absenteeism in electrical construction. J. Constr. Eng. Manag. 2005, 131, 1212–1218. [Google Scholar] [CrossRef]
  26. Menches, C.L.; Hanna, A.S. Conceptual planning process for electrical construction. J. Constr. Eng. Manag. 2006, 132, 1306–1313. [Google Scholar] [CrossRef]
  27. Riley, D.R.; Varadan, P.; James, J.S.; Thomas, H.R. Benefitcost metrics for design coordination of mechanical, electrical, and plumbing systems in multistory buildings. J. Constr. Eng. Manag. 2005, 131, 877–889. [Google Scholar] [CrossRef]
  28. Korman, T.M.; Tatum, C.B. Prototype tool for mechanical, electrical, and plumbing coordination. J. Comput. Civ. Eng. 2006, 20, 38–48. [Google Scholar] [CrossRef]
  29. Khanzode, A.; Fischer, M.; Reed, D. Benefits and lessons learned of implementing building virtual design and construction (VDC) technologies for coordination of mechanical, electrical, and plumbing (MEP) systems on a large healthcare project. ITcon 2008, 13, 324–342. [Google Scholar]
  30. Hanna, A.; Boodai, F.; El Asmar, M. State of practice of building information modeling in mechanical and electrical construction industries. J. Constr. Eng. Manag. 2013, 139, 04013009. [Google Scholar] [CrossRef]
  31. Rojas, E. Identifying, recruiting, and retaining quality field supervisors and project managers in the electrical construction industry. J. Manag. Eng. 2013, 29, 424–434. [Google Scholar] [CrossRef]
  32. Said, H. Prefabrication best practices and improvement opportunities for electrical construction. J. Constr. Eng. Manag. 2015, 141, 04015045. [Google Scholar] [CrossRef]
  33. Aubry, M.; Hobbs, B.; Thuillier, D. A new framework for understanding organisational project management through the PMO. Int. J. Proj. Manag. 2007, 25, 328–336. [Google Scholar] [CrossRef]
  34. Cooke-Davies, T. Project management maturity models. In The Wiley Guide to Managing Projects; Morris, P.G.W., Pinto, J.K., Eds.; John Wiley & Sons: Hoboken, NJ, USA, 2004. [Google Scholar]
  35. Iqbal, S. Organizational maturity: Managing programs better. In Program Management: A Life Cycle Approach; Levin, G., Ed.; CRC Press/Auerbach: Boca Raton, FL, USA, 2013. [Google Scholar]
  36. Yazici, H.J. The role of project management maturity and organizational culture in perceived performance. Proj. Manag. J. 2009, 40, 14–33. [Google Scholar] [CrossRef]
  37. Pasian, B.L. Extending the concept and modularization of project management maturity with adaptable, human and customer factors. Int. J. Manag. Proj. Bus. 2014, 7, 186–214. [Google Scholar] [CrossRef]
  38. Cleland, D.I.; Ireland, L.R. Project Management—Strategic Design and Implementation, 4th ed.; McGraw-Hill: New York, NY, USA, 2002. [Google Scholar]
  39. Grant, K.P.; Pennypacker, J.S. Project management maturity: An assessment of project management capabilities among and between selected industries. IEEE Trans. Eng. Manag. 2006, 53, 59–68. [Google Scholar] [CrossRef]
  40. Kerzner, H. Using the Project Management Maturity Model, 2nd ed.; Wiley: Hoboken, NJ, USA, 2005. [Google Scholar]
  41. Torres, L. A Contingency View on the Effect of Project Management Maturity on Perceived Performance. Ph.D. Thesis, Skema Business School, Raleigh, NC, USA, 2014. [Google Scholar]
  42. Lim, J.; Kim, S.; Kim, J.J. Dynamic simulation model for estimating in-situ production quantity of PC members. Int. J. Civ. Eng. 2020, 18, 935–950. [Google Scholar] [CrossRef]
  43. Kerzner, H. Planning. In Project Management: A Systems Approach to Planning, Scheduling, and Controlling; John Wiley & Sons, Inc.: Hoboken, NJ, USA, 2006; pp. 345–360. [Google Scholar]
  44. Oglesby, C.H.; Parker, H.W.; Howell, G. Productivity Improvement in Construction, 1st ed.; McGraw-Hill Higher Education: New York, NY, USA, 1989; pp. 85–89. [Google Scholar]
  45. Laufer, A.; Shpira, A.; Cohenca-Zall, D.; Howell, G.A. Prebid and Preconstruction Planning Process. J. Constr. Eng. Econ. 1993, 119, 426–444. [Google Scholar] [CrossRef]
  46. Laufer, A.; Tucker, R.L. Is construction project planning really doing its job? A critical examination of focus, role and process. Constr. Manag. Econ. 1987, 5, 243–266. [Google Scholar] [CrossRef]
  47. Gidado, K. Enhancing the prime contractor’s pre-construction planning. J. Constr. Res. 2004, 5, 87–106. [Google Scholar] [CrossRef]
  48. Menches, C.L. Effect of Pre-Construction Planning on Project Performance. Master’s Thesis, University of Wisconsin-Madison, Madison, WI, USA, 2006. [Google Scholar]
  49. Nasr, Z.J.B. Electrical Project Management Mode. Master’s Thesis, The University of Texas at Austin, Austin, TX, USA, 2009. [Google Scholar]
  50. Görög, M. A broader approach to organisational project management maturity assessment. Int. J. Proj. Manag. 2016, 34, 1658–1669. [Google Scholar] [CrossRef]
  51. Andersen, E.S.; Jessen, S.A. Project maturity in organisations. Int. J. Proj. Manag. 2003, 21, 457–461. [Google Scholar] [CrossRef]
  52. Ibbs, C.W.; Kwak, Y.H. Assessing project management maturity. Proj. Manag. J. 2000, 31, 32–43. [Google Scholar] [CrossRef]
  53. Mullaly, M. If maturity is the answer, then exactly what was the question? Int. J. Manag. Proj. Bus. 2014, 7, 169–185. [Google Scholar] [CrossRef]
  54. Brooks, N.; Clark, R. Using maturity models to improve project management practice. In Proceedings of the POM 20th Annual Conference of the Production and Operations Management Society, Orlando, FL, USA, 1–5 May 2009. [Google Scholar]
  55. Lee, L.S.; Anderson, R.M. An Exploratory Investigation of the Antecedents of the IT Project Management Capability. E-Serv. J. 2006, 5, 27–42. [Google Scholar] [CrossRef]
  56. Thiry, M. Program Management; Gower, Farnham, Surrey; Routledge: London, UK, 2010. [Google Scholar]
  57. Wheatley, M. Maturity matters. PM Netw. 2007, 21, 49–53. [Google Scholar]
  58. Hillson, D. Assessing organizational project management capability. J. Facil. Manag. 2003, 2, 298–311. [Google Scholar] [CrossRef]
  59. Thomas, J.; Mullaly, M. Understanding the value of project management: First steps on an international investigation in search of value. Proj. Manag. J. 2007, 38, 74–89. [Google Scholar] [CrossRef]
Figure 1. Effects analysis structure for task strings.
Figure 1. Effects analysis structure for task strings.
Sustainability 14 02653 g001
Figure 2. Mean of unweighted task strings implementation scores for cost.
Figure 2. Mean of unweighted task strings implementation scores for cost.
Sustainability 14 02653 g002
Figure 3. Mean of weighted task strings implementation scores for cost.
Figure 3. Mean of weighted task strings implementation scores for cost.
Sustainability 14 02653 g003
Figure 4. Mean of the unweighted work-string implementation scores for schedule.
Figure 4. Mean of the unweighted work-string implementation scores for schedule.
Sustainability 14 02653 g004
Figure 5. Mean of the weighted task-string implementation scores for schedule.
Figure 5. Mean of the weighted task-string implementation scores for schedule.
Sustainability 14 02653 g005
Figure 6. Validation of task string implementation.
Figure 6. Validation of task string implementation.
Sustainability 14 02653 g006
Figure 7. Scatterplot of task string implementation.
Figure 7. Scatterplot of task string implementation.
Sustainability 14 02653 g007
Table 1. Example list of PE groups and tasks.
Table 1. Example list of PE groups and tasks.
PCP Group No.PCP GroupPCP No.PCP Task
1Team Selection & Turnover2Hold turnover meeting between project manager and estimator
3Hold separate turnover meeting between field supervisor and project manager
2Scope & Contract Review7Review plans, schedule, and specifications (Field supervisor)
9Conduct site visit
10Compare estimated materials and work activities to planned performance
11Identify value engineering and prefabrication opportunities and how to simplify the tasks
12Prepare construction takeoff
3Budget Preparation27Develop, review, or expand cost code schemes
4Layout & Sequencing Plan30Develop layout drawings and installation sequence
31Develop including panel, field instructions, pull, or conduit
schedules
5Tracking & Control38Customize the control system and computerized tracking, i.e., schedule/database, and so on, for the current project
Table 2. List of PE groups and tasks.
Table 2. List of PE groups and tasks.
PE Group No.PE GroupPE No.PE Task
1Team Selection & Turnover1Setup office trailer and in a convenient location in a timely manner
2Setup and lay down storage trailer area
7Make sure the foreman has everything he or she needs to get started
2Document Management8Make use of a project file
9Use a documentation control system
10Use an RFI processing and tracking system
11Use a change order processing and tracking system
12Keep all schedule documents including delays
3Material Management17Review of material and supplier bid documents
19Establish delivery dates
22Ensure good material handling on site
23Communicate all material information to the field
25Lock in the necessary prices
27Make sure the invoice matches the material costs
4Tool Management28Review contract drawing, specifications, and bid
29Schedule deliveries and pickups
5Subcontractors Management31Determine the scope of work for the subcontractors
32Establish subcontracts
33Determine the subcontractors’ schedule
34Request submittals and shop drawings
35Inform the site about the subcontractors
37Ensure the subcontractors are capable of doing the job
6Safety Management39Identify safety issues with the existing work
40Plan for additional needs for safety equipment
42Perform work walks to ensure the safety rules
7Communication43Receive support from the company Chief Executive
Officer or Vice President
44Communicate with the foreman
45Communicate with the subcontractors and vendors
46Communicate with the owner and general contractor
8Scope & Change Control54Track change orders
9Scheduling57Identify milestone dates and review the schedule
58Identify work that impacts electrical activity
60Review the schedule with the site
61Update the work schedule regularly
10Cost Control & Billing63Use cost codes, i.e., cost breakdown
64Track labor costs
65Track subcontractor and material costs
66Include issued change orders
68Compare the project costs to the budget
11Quality Management72Check the quality that the site needs
73Check the installation quality through on-site visits
74Perform test results/commissioning
12Labor Management77Maintain the correct staff power and crew mix level
78Ensure labor hours are turned in
13Project Closeout79Ensure that all punch list items are signed off on
82Ensure that all purchase/change orders are closed
84Turn all project closeout documents over to the general contractor
Table 3. Example list of PCP task-to-PE task.
Table 3. Example list of PCP task-to-PE task.
Task Strings No.PCP No. PCP TaskPE Group
13Hold separate turnover meeting between field supervisor and project manager Mobilization
27Review specifications, plans, and schedule (Field supervisor)
39Conduct site visits
411Identify prefabrication opportunities, value engineering and how to simplify the work
53Hold separate turnover meeting between field supervisor and project manager
2363Hold separate turnover meeting between field supervisor and project manager Project Closeout
23738Customize the computerized control and tracking system (database/schedule, etc.)
for the current project
2383Hold separate turnover meeting between field supervisor and project manager
23938Customize the computerized control and tracking system (database/schedule, etc.)
for the current project
Table 4. Effect of unweighted task strings usage on cost success.
Table 4. Effect of unweighted task strings usage on cost success.
Group No.PCP Task-To-PE GroupSuccess ProjectsFailure ProjectsMean
Difference
t
Statistic
Sig.
(Two-Tailed)
Eta
Square
NMSDNMSD
1Mobilization300.730.04200.450.060.284.230.0000.272
2Document Management300.630.26200.420.270.212.810.0070.141
3Material Management300.620.24200.360.240.263.730.0010.225
4Tool Management300.670.28200.410.330.262.920.0050.151
5Subcontractor Management300.590.29200.490.340.10
6Safety Management300.570.37200.390.360.18
7Communication300.580.32200.350.340.232.450.0180.111
8Scope Change & Control300.460.37200.380.390.08
9Scheduling300.570.36200.240.280.333.440.0010.198
10Cost Control & Billing300.570.23200.310.260.263.780.0000.229
11Quality Management300.630.29200.450.330.182.050.0460.081
12Labor Management300.590.32200.170.270.424.880.0000.332
13Project Closeout300.680.27200.490.300.192.390.0210.106
Table 5. Effect of weighted task strings usage on cost success.
Table 5. Effect of weighted task strings usage on cost success.
Group No.PCP Task-To-PE GroupSuccess ProjectsFailure ProjectsMean
Difference
t
Statistic
Sig.
(Two-Tailed)
Eta
Square
NMSDNMSD
1Mobilization303.771.10202.331.321.434.180.0000.266
2Document Management303.541.45202.341.491.202.840.0070.144
3Material Management303.531.39202.041.381.493.740.0000.226
4Tool Management303.881.68202.401.921.482.890.0060.148
5Subcontractor Management303.341.65202.761.940.58
6Safety Management303.272.12202.242.061.03
7Communication302.981.68201.701.771.282.580.0130.122
8Scope Change & Control302.682.19202.272.350.41
9Scheduling303.432.15201.411.682.023.540.0010.207
10Cost Control & Billing303.241.33201.731.471.513.780.0000.229
11Quality Management303.171.49202.231.660.942.100.0410.084
12Labor Management303.461.85200.981.592.484.920.0000.335
13Project Closeout303.491.48202.441.561.052.400.0200.107
Table 6. Effect of unweighted work strings usage on schedule success.
Table 6. Effect of unweighted work strings usage on schedule success.
Group No.PCP Task-To-PE GroupSuccess ProjectsFailure ProjectsMean
Difference
t
Statistic
Sig.
(Two-Tailed)
Eta
Square
NMSDNMSD
1Mobilization420.630.2780.540.230.09
2Document Management420.560.2980.500.240.06
3Material Management420.540.2780.390.220.15
4Tool Management420.600.3280.360.280.241.960.0550.074
5Subcontractor Management420.590.2980.340.340.252.160.0360.089
6Safety Management420.540.3780.290.350.261.810.0760.064
7Communication420.480.3580.560.35-0.09
8Scope Change & Control420.460.3780.250.390.21
9Scheduling420.470.3880.290.270.18
10Cost Control & Billing420.480.2780.360.260.12
11Quality Management420.580.3280.440.300.14
12Labor Management420.450.3780.280.320.18
13Project Closeout420.620.2980.530.350.09
Table 7. Effect of weighted task strings usage on schedule success.
Table 7. Effect of weighted task strings usage on schedule success.
Group No.PCP Task-To-PE GroupSuccess ProjectsFailure ProjectsMean
Difference
t
Statistic
Sig.
(Two-Tailed)
Eta Square
NMSDNMSD
1Mobilization423.641.5683.131.350.51
2Document Management423.361.7583.021.480.34
3Material Management423.321.6782.371.340.95
4Tool Management423.832.0682.301.791.531.970.0550.075
5Subcontractor Management423.701.8582.102.151.602.190.0340.091
6Safety Management422.992.0381.571.981.421.820.0750.065
7Communication422.431.8382.941.83-0.51
8Scope Change & Control422.632.1181.442.211.19
9Scheduling422.982.4181.851.681.13
10Cost Control & Billing422.531.4881.881.310.65
11Quality Management423.021.6782.341.570.68
12Labor Management422.722.2481.691.941.03
13Project
Closeout
423.301.6582.901.960.40
Table 8. Validation results.
Table 8. Validation results.
Project PerformanceRanking of Task StringsOriginal Task Strings No.Validated Task Strings No.Validated Task Strings (%)
Cost SuccessBasic18611662.4
Better484185.4
Best5360.9
Schedule SuccessBasic23313357.1
Better55100.0
Best11100.0
Table 9. Validated best task strings for cost and schedule.
Table 9. Validated best task strings for cost and schedule.
Project
Performance
Task Strings No.PCP No.PCP TasksPE No.PE Tasks
Cost Success53Hold separate turnover meeting between project manager and field supervisor2Setup storage trailer and lay down area
5611Identify value engineering and prefabrication opportunities and how to simplify the work17Review bid documents for materials and vendors and any vendor responsibilities
17111Identify value engineering and prefabrication opportunities and how to simplify the work58Identify work that impacts electrical activity
Schedule Success1267Review plans, specifications, and schedule (Field supervisor)33Determine the subcontractors’ schedule
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Share and Cite

MDPI and ACS Style

Kim, J.; Lim, J.; Lim, H.-C.; Kim, D.Y. Improving Sustainable Project Success Strategies Focused on Cost and Schedule for Electrical Construction Project Management. Sustainability 2022, 14, 2653. https://doi.org/10.3390/su14052653

AMA Style

Kim J, Lim J, Lim H-C, Kim DY. Improving Sustainable Project Success Strategies Focused on Cost and Schedule for Electrical Construction Project Management. Sustainability. 2022; 14(5):2653. https://doi.org/10.3390/su14052653

Chicago/Turabian Style

Kim, Janghwan, Jeeyoung Lim, Hyoung-Chul Lim, and Dae Young Kim. 2022. "Improving Sustainable Project Success Strategies Focused on Cost and Schedule for Electrical Construction Project Management" Sustainability 14, no. 5: 2653. https://doi.org/10.3390/su14052653

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop