Contested Knowledges in Hydroelectric Project Assessment: The Case of Canada’s Site C Project
Abstract
:1. Introduction
2. Contested Knowledges: Conceptual Discussion
3. Historical and Regulatory Context of British Columbia’s Site C Project
The Commission recommends that Cabinet defer issuing an Energy Project Certificate for Site C until an acceptable load forecast demonstrates that construction of Site C must begin immediately in order to avoid supply deficiencies, and a comparison of alternative system plans demonstrates that Site C is the best project to meet the anticipated shortfalls [53] (p. 23).
4. Contesting Environmental Knowledge in Regulatory Decision-Making: Cumulative Effects and Greenhouse Gas Emissions
The Panel cannot conclude on the likely accuracy of Project cost estimates because it does not have the information, time, or resources. This affects all further calculations of unit costs, revenue requirements, and rates [61].
4.1. Cumulative Effects
We also noted in our comments on the EIS Guidelines that in order to assess the cumulative environmental effects of the proposed Project and the cumulative implications for [Constitution Act] Section 35(1) rights, the initial case for consideration or the “baseline case” must include the historical circumstances, since these circumstances are essential to the understanding of the seriousness of the potential impacts on established Treaty rights, and which circumstances would include the WAC Bennett Dam, Peace Canyon Dam and the Peace Project Water Use Plan [66].
BC Hydro’s approach to cumulative effects assessment for the Site C project is based on accepting the present state of the Peace River and the Peace Athabasca Delta as the baseline condition upon which to add the incremental impacts from construction and operation of the Site C dam. This approach does not fully consider the cumulative impact from all BC Hydro’s flow management operations against an unregulated, undammed river. The point here is that the WAC Bennett dam was proposed, and constructed, in a time when no environmental assessment legislation or process was in place. If the Bennett dam project was proposed today it is very unlikely that such dramatic regulation of the flow regime on the Peace River would be found to be justifiable in the circumstances. The project would then either be modified to limit the scope of the impact to the hydrology of the Peace River, or the project would be cancelled. Using the existing conditions as the baseline, conveniently incorporates the extensive impacts from the WAC Bennett Dam into the baseline, and avoids looking holistically at the collective impacts of all BC Hydro’s flow management upon the flows and ecology of the Peace River downstream of the dams. The usual argument for not doing this in cumulative effects assessments is that it is unfair to saddle the current proponent or project with the responsibility to cumulatively assess the impacts of all relevant projects and activities on the receiving environment. This argument often succeeds and hence cumulative effects assessment typically becomes more an exercise in assessing incremental effects of the proposed project, than a comprehensive assessment of cumulative effects. The current circumstances before us are unique in that BC Hydro presently manages two dams on the Peace River and, in the event of the Site C project being approved, would manage all three dams on the Peace River. This provides a compelling argument for BC Hydro to assess the full impact of its operations on the Peace River. The WAC Bennett Dam damage is done and no one is going to ask for that dam to be decommissioned. Given that is the case, the tolerance for accepting Site C incremental impacts to downstream environments should be correspondingly low [67].
BC Hydro also believes that a pre-development case would be inherently unreliable. There are two methods by which a pre-development case could be developed. Firstly, if direct, reliable data about the pre-development state is available, that information could be used. BC Hydro is not aware of data from the pre-development era. Secondly, in the absence of data from the pre-development era, a model would have to be built based on various assumptions in order to emulate pre-development conditions. The longer the period of time between current conditions and the pre-development era, the greater the uncertainty would be [68].
The Panel concluded that Nalcor’s approach to cumulative effects assessment was less than comprehensive and that participants had raised valid concerns that contributed to a broader understanding of the potential cumulative effects of the Project. The Panel recognized the challenges involved, including limited information about past projects such as the Churchill Falls project, and the built-in disincentive for proponents to identify adverse cumulative effects when they are perceived as a potential threat to project approval [69].
The development of a baseline for evaluation of cumulative effects is more than a description of current conditions, which alone can discount the effects of past changes as simply the ‘new normal.’ Baseline development requires a retrospective analysis of how VEC conditions have changed over time and whether that change is significant in terms of the sustainability of the VEC [70].
The EIS will include a narrative discussion of existing hydro-electric generation projects on the Peace River (W.A.C. Bennett Dam and the Peace Canyon Dam). The narrative will include the description of any existing studies of changes to the environment resulting from those projects that are similar to potential changes resulting from the project, including any mitigation measures that were implemented, and any long term monitoring or follow up program that were conducted. The effectiveness of those mitigation measures and key results of monitoring or follow-up programs would be described. This narrative discussion should include historical data, where available and applicable, to assist interested parties to understand the potential effects of the Project and how they may be addressed [60].
I’d like to know more about the arguments that you’ve used and managed; they must be magical. In addition, managed to convince the agency and environmental assessment office of the Province to go ahead and exclude the two dams. Because even if there is a narrative, it does not preclude the proponent to do a cumulative effect assessment, especially if in the narrative you acknowledge that the previous dams had effects.
…
Do I understand that the major argument was that you did not have the data? I mean, the Peace Canyon Dam had the Environmental Impact Assessment done. The Bennett Dam—when you build a dam, you have data. I mean, even if it is 1957, you would have data [71].
While the Panel understands that, according to the CEA Agency Operational Policy Statement, past or existing physical activities may be helpful in predicting the effects of a designated project, it is not the sole intent of assessing past or existing projects. The Panel believes that providing a narrative with no analysis or conclusions on the cumulative effects of the existing hydroelectric facilities does not suit the needs of a cumulative effects assessment [61] (p. 259).
…
The Panel disagrees with BC Hydro’s assertion that there was limited information available to conduct a cumulative effects assessment, particularly given the information from participants. The Panel received numerous testimonies from Aboriginal and non-Aboriginal participants about the effects of the Bennett and Peace Canyon Dams. This information was provided first-hand (by people who were alive at that time) or second-hand (by participants who learned of the effects from previous generations). The Panel understands that there is existing information in various formats such as air photos, environmental impact studies, research from various provincial and independent bodies, and historic maps of changing land tenure [61] (p. 259).
The Panel concludes that, whether the Project proceeds or not, there is a need for a government-led regional environmental assessment including a baseline study and the establishment of environmental thresholds for use in evaluating the effects of multiple, projects in a rapidly developing region [61] (p. 261).
…
Because of the importance of cumulative effects assessment, the Panel concludes that there is a need to improve and standardize cumulative effects assessment methods [61] (p. 262).
4.2. Greenhouse Gas Emissions
The portfolio including the Project has lower operational GHG emissions than both portfolios not including the Project. The Clean Generation portfolio selects a municipal solid waste resource option, which includes GHG emissions from fuel combustion [77].
5. Conclusions
Author Contributions
Funding
Conflicts of Interest
Appendix A
References
- Zarfl, C.; Lumsdon, A.E.; Berlekamp, J.; Tydecks, L.; Tockner, K. A global boom in hydropower dam construction. Aquat. Sci. 2015, 77, 161–170. Available online: https://link-springer-com.ezproxy.library.ubc.ca/article/10.1007%2Fs00027-014-0377-0 (accessed on 10 January 2019). [CrossRef]
- World Commission on Dams. Dams and Development: A New Framework for Decision-Making; Earthscan Publications Ltd.: London, UK, 2000; ISBN 978-185-383-798-2. [Google Scholar]
- George, M.W.; Hotchkiss, R.H.; Huffaker, R. Reservoir sustainability and sediment management. J. Water Resour. Plan. Manag. 2016, 143, 04016077. Available online: https://ascelibrary-org.ezproxy.library.ubc.ca/doi/abs/10.1061/(ASCE)WR.1943-5452.0000720 (accessed on 10 January 2019). [CrossRef]
- Hammersley, M.; Scott, C.; Gimblett, R. Evolving conceptions of the role of large dams in social-ecological resilience. Ecol. Soc. 2018, 23, 40–49. Available online: https://doaj.org/article/c1e9eb0446be41c683aee690258f273c (accessed on 10 January 2019). [CrossRef]
- Ho, M.; Lall, U.; Allaire, M.; Devineni, N.; Kwon, H.H.; Pal, I.; Raff, D.; Wegner, D. The future role of dams in the United States of America. Water Resour. Res. 2017, 53, 982–998. Available online: https://agupubs-onlinelibrary-wiley-com.ezproxy.library.ubc.ca/doi/full/10.1002/2016WR019905 (accessed on 10 January 2019). [CrossRef] [Green Version]
- Calder, R.S.D.; Schartup, A.T.; Li, M.; Valberg, A.P.; Balcom, P.H.; Sunderland, E.M. Future impacts of hydroelectric power development on methylmercury exposures of Canadian indigenous communities. Environ. Sci. Technol. 2016, 50, 13115–13122. Available online: https://pubs.acs.org/doi/abs/10.1021/acs.est.6b04447 (accessed on 10 January 2019). [CrossRef] [PubMed]
- Doelle, M. The Lower Churchill Panel Review: Sustainability assessment under legislative constraints in Canada. In Sustainability Assessment; Gibson, R., Ed.; Routledge: London, UK, 2016; pp. 124–140. [Google Scholar]
- Macdonald, D.; Lesch, M. Management of Distributive Conflicts Impeding Expansion of Interprovincial Hydroelectricity Transmission. J. Can. Stud. 2015, 49, 191–221. Available online: http://ezproxy.library.ubc.ca/login?url=https://search-proquest-com.ezproxy.library.ubc.ca/docview/1806500135?accountid=14656 (accessed on 10 January 2019). [CrossRef]
- Mercer, N.; Sabau, G.; Klinke, A. Wind energy is not an issue for government: Barriers to wind energy development in Newfoundland and Labrador, Canada. Energy Policy 2017, 108, 673–683. [Google Scholar] [CrossRef]
- Scott, D.N.; Smith, A.A. Sacrifice Zones in the Green Energy Economy: The New Climate Refugees. Transnatl. Law Contemp. Probl. 2016, 26, 371. Available online: http://link.galegroup.com.ezproxy.library.ubc.ca/apps/doc/A497798899/LT?u=ubcolumbia&sid=LT&xid=f939c3c5 (accessed on 10 January 2019).
- Besant-Jones, J. A view of multilateral financing from a funding agency. In Financing Hydro Power Projects ‘94, Proceedings of the International Water-Power and Dam Construction Conference, Frankfurt, Germany, 22–23 September 1994; First European Communications: London, UK.
- Usher, A.D. The Mechanism of ‘Pervasive Appraisal Optimism’. In Dams as Aid: A Political Anatomy of Nordic Development Thinking; Usher, A.D., Ed.; Taylor & Francis: London, UK, 1997; ISBN 978-128-011-598-1. [Google Scholar]
- Ansar, A.; Flyvbjerg, B.; Budzier, A.; Lunn, D. Should we build more large dams? The actual costs of hydropower megaproject development. Energy Policy 2014, 69, 43–56. Available online: https://www-sciencedirect-com.ezproxy.library.ubc.ca/science/article/pii/S0301421513010926?via%3Dihub (accessed on 10 January 2019). [CrossRef] [Green Version]
- Flyvbjerg, B.; Bruzelius, N.; Rothengatter, W. Megaprojects and Risk: An Anatomy of Ambition; Cambridge University Press: Cambridge, UK, 2003; ISBN 052-180-420-5. [Google Scholar]
- Khagram, S. Dams and Development: Transnational Struggles for Water and Power; Cornell University Press: Ithaca, NY, USA, 2004; ISBN 080-148-907-5. [Google Scholar]
- Klingensmith, D. One Valley and a Thousand: Dams, Nationalism and Development; Oxford University Press: New Delhi, India, 2007; ISBN 019-568-783-3. [Google Scholar]
- Zwarteween, M.; Ahlers, R.; Bakker, K. Large Dam Development: From Trojan Horse to Pandora’s Box. In The Oxford Handbook of Megaproject Management; Flyvbjerg, B., Ed.; Oxford Handbooks: Oxford, UK, 2017; pp. 556–576. ISBN 978-019-873-224-2. [Google Scholar]
- Flyvbjerg, B. What You Should Know About Megaprojects and Why: An Overview. Proj. Manag. J. 2014, 45, 6–19. Available online: https://doi-org.ezproxy.library.ubc.ca/10.1002/pmj.21409 (accessed on 10 January 2019). [CrossRef]
- Grant, H.M. Resource rents from Aboriginal lands in Canada—Royal Commission on Aboriginal Peoples. 1994. Available online: http://publications.gc.ca/collections/collection_2016/bcp-pco/Z1-1991-1-41-83-eng.pdf (accessed on 10 January 2019).
- Hendriks, R.; Raphals, P.; Bakker, K. Site C: Summary of Key Research Results. Available online: http://watergovernance.sites.olt.ubc.ca/files/2017/11/UBC-Report-Site-C-Key-Issues-Full-Report-1.pdf (accessed on 22 March 2018).
- Bakker, K.; Christie, G.; Hendriks, R. Report #1: First Nations and Site C. Available online: http://watergovernance.sites.olt.ubc.ca/files/2017/11/Briefing-Note-1-First-Nations-and-Site-C.pdf (accessed on 10 January 2019).
- Bakker, K.; Christie, G.; Hendriks, R. Report #2: Assessing Alternatives to Site C—Environmental Effects Comparison. Available online: http://watergovernance.sites.olt.ubc.ca/files/2017/11/Briefing-Note-2-Site-C-Environmental-Effects.pdf (accessed on 10 January 2019).
- Bakker, K.; Christie, G.; Hendriks, R. Report #3: The Regulatory Process for the Site C Project. Available online: http://watergovernance.sites.olt.ubc.ca/files/2017/11/Briefing-Note-3-Regulatory-Process.pdf (accessed on 10 January 2019).
- Hendriks, R. Report #4: Comparative Analysis of Greenhouse Gas Emissions of Site C versus Alternatives. Available online: http://watergovernance.sites.olt.ubc.ca/files/2017/11/Report-4-Site-C-Comparative-GHG-analysis.pdf (accessed on 10 January 2019).
- Hendriks, R.; Raphals, P.; Bakker, K. Report #5: Reassessing the Need for Site C. Available online: http://watergovernance.sites.olt.ubc.ca/files/2017/11/2-Site-C-Economics-Report-FINAL.pdf (accessed on 10 January 2019).
- Program on Water Governance, UBC. Report #6: Employment—Site C versus the Alternative Portfolios. Available online: http://watergovernance.sites.olt.ubc.ca/files/2017/11/UBC_Briefing_Note_Comparative_Employment_Assessment_of_Site_C_versus_Alternatives.pdf (accessed on 14 March 2018).
- Hendriks, R.; Raphals, P.; Bakker, K. Submission F106-1/2. August 2017. Available online: http://www.bcuc.com/site-c-inquiry.html#Sub-1 (accessed on 10 January 2019).
- Raphals, P.; Hendriks, R. Submission F106-5. October 2017. Available online: http://www.bcuc.com/site-c-inquiry.html#Sub-1 (accessed on 10 January 2019).
- Hendriks, R.; Raphals, P. Submission F106-6. October 2017. Available online: http://www.bcuc.com/site-c-inquiry.html#Sub-1 (accessed on 10 January 2019).
- Hendriks, R.; Raphals, P.; Bakker, K. Submission F106-7-11. October 2017. Available online: http://www.bcuc.com/site-c-inquiry.html#Sub-1 (accessed on 10 January 2019).
- British Columbia Utilities Commission. British Columbia Utilities Commission Inquiry Respecting Site C—Project No. 1598922—Final Report to the Government of British Columbia. BCUC: Vancouver, Canada. Available online: http://www.bcuc.com/Documents/wp-content/11/11-01-2017-BCUC-Site-C-Inquiry-Final-Report.pdf (accessed on 10 January 2019).
- Ostrom, E. Governing the Commons; Cambridge University Press: Cambridge, UK, 2015. [Google Scholar]
- Jessop, B. State Theory: Putting the Capitalist State in Its Place; Penn State Press: University Park, PA, USA, 1990. [Google Scholar]
- Coutard, O. (Ed.) The Governance of Large Technical Systems; Routledge: London, UK, 2002. [Google Scholar]
- Scott, J.C. Seeing Like a State: How Certain Schemes to Improve the Human Condition Have Failed; Yale University Press: New Haven, CT, USA, 1998. [Google Scholar]
- Hajer, M.; Versteeg, W. A decade of discourse analysis of environmental politics: Achievements, challenges, perspectives. J. Environ. Policy Plan. 2005, 7, 175–184. Available online: https://www-tandfonline-com.ezproxy.library.ubc.ca/doi/abs/10.1080/15239080500339646 (accessed on 10 January 2019). [CrossRef]
- Boelens, R. Water, Power and Identity: The Cultural Politics of Water in the Andes; Routledge: London, UK, 2015. [Google Scholar]
- Menga, F.; Swyngedouw, E. (Eds.) Water, Technology and the Nation-State; Routledge: London, UK, 2018. [Google Scholar]
- Boelens, R.; Shah, E.; Bruins, B. Contested Knowledges: Large Dams and Mega-Hydraulic Development. Water 2019, 11, 416. [Google Scholar] [CrossRef]
- Evenden, M. Allied Power: Mobilizing Hydro-Electricity during Canada’s Second World War; University of Toronto Press: Toronto, ON, Canada, 2015; ISBN 1442626259. [Google Scholar]
- Webster, K.L.; Beall, F.D.; Creed, I.F.; Kreutzweiser, D.P. Impacts and prognosis of natural resource development on water and wetlands in Canada’s boreal zone. Environ. Rev. 2015, 23, 78–131. [Google Scholar] [CrossRef] [Green Version]
- Sandwell, R.W. (Ed.) Powering up Canada: The History of Power, Fuel, and Energy from 1600; McGill-Queen’s Press-MQUP: Montreal, QC, Canada, 2016; Volume 6, ISBN 077-359-952-5. [Google Scholar]
- Macfarlane, D.; Kitay, P. Hydraulic Imperialism: Hydroelectric Development and Treaty 9 in the Abitibi Region. Am. Rev. Can. Stud. 2016, 46, 380–397. Available online: https://www-tandfonline-com.ezproxy.library.ubc.ca/doi/abs/10.1080/02722011.2016.1228685 (accessed on 10 January 2019). [CrossRef]
- Choquette, L.; Carlson, H.M. Home is the Hunter: The James Bay Cree and Their Land; UBC Press: Vancouver, BC, Canada, 2008; ISBN 9780774814942. [Google Scholar]
- Jenson, J.; Papillon, M. Challenging the citizenship regime: The James Bay Cree and transnational action. Polit. Soc. 2000, 28, 245–264. Available online: https://journals-sagepub-com.ezproxy.library.ubc.ca/doi/abs/10.1177/0032329200028002005 (accessed on 10 January 2019). [CrossRef]
- Manore, J. Cross-Currents: Hydroelectricity and the Engineering of Northern Ontario; Wilfrid Laurier University Press: Waterloo, ON, Canada, 1999; ISBN 088-920-317-2. [Google Scholar]
- Schiehll, E.; Raufflet, E. Hydro-Québec and the Crees: The challenges of being accountable to First Nations–case and teaching notes. Int. J. Teach. Case Stud. 2013, 4, 243–258. [Google Scholar] [CrossRef]
- Ariss, R.; Fraser, C.M.; Somani, D.N. Crown Policies on the Duty to Consult and Accommodate: Towards Reconciliation. McGill J. Sustain. Dev. Law 2017, 13, 1. Available online: https://mcgill.ca/mjsdl/files/mjsdl/2_volume_13_ariss.pdf (accessed on 10 January 2019).
- Booth, A.; Skelton, N.W. “We are fighting for Ourselves”—First Nations’ Evaluation of British Columbia and Canadian Environmental Assessment Processes. J. Environ. Assess. Policy Manag. 2011, 13, 367–404. Available online: https://www.jstor.org/stable/enviassepolimana.13.3.367?seq=1#page_scan_tab_contents (accessed on 10 January 2019). [CrossRef]
- Peyton, J. Unbuilt Environments: Tracing Postwar Development in Northwest British Columbia; UBC Press: Vancouver, BC, Canada, 2017; ISBN 978-077-483-304-2. [Google Scholar]
- Waldram, J. As Long as the Rivers Run: Hydroelectric Development and Native Communities in Western Canada; University of Manitoba Press: Winnipeg, MB, Canada, 1988; ISBN 978-088-755-631-9. [Google Scholar]
- BC Hydro. Site C Clean Energy Project Environmental Impact Statement; Figure 4.2: General project location and regional topography; CEAR #63919-421; BC Hydro: Vancouver, BC, Canada, 2013. [Google Scholar]
- British Columbia Utilities Commission. Site C Report: Report & Recommendations to the Lieutenant Governor-in-Council; British Columbia Utilities Commission: Vancouver, BC, Canada, 1983; pp. 1, 50, 85, 23. [Google Scholar]
- BC Hydro. Rate Design Application. Evidentiary Update on Load Resource Balance and Long Run Marginal Cost; BC Hydro: Vancouver, BC, Canada, 2016; p. 12. [Google Scholar]
- BC Hydro. Electric Load Forecast Fiscal 2013 to Fiscal 2033; BC Hydro: Vancouver, BC, Canada, 2012; p. 21. [Google Scholar]
- BC Hydro. BC Hydro Integrated Resource Plan; Planning Environment, Table 5-5; BC Hydro: Vancouver, BC, Canada, 2013; pp. 5–37. Available online: https://www.bchydro.com/content/dam/BCHydro/customer-portal/documents/corporate/regulatory-planning-documents/integrated-resource-plans/current-plan/0005-nov-2013-irp-chap-5.pdf (accessed on 10 January 2019).
- Lazard. Lazard’s Levelized Cost of Energy Analysis; Version 11.0; Lazard: Hamilton, Bermuda, 2017; Available online: https://www.lazard.com/media/450337/lazard-levelized-cost-of-energy-version-110.pdf (accessed on 10 January 2019).
- Lazard. Lazard’s Levelized Cost of Storage Analysis; Version 3.0; Lazard: Hamilton, Bermuda, 2017; Available online: https://www.lazard.com/media/450338/lazard-levelized-cost-of-storage-version-30.pdf (accessed on 10 January 2019).
- Canadian Environmental Assessment Act, 2012 (CEAA 2012). Available online: http://laws-lois.justice.gc.ca/eng/acts/C-15.2/20100712/P1TT3xt3.html (accessed on 10 January 2019).
- Canadian Environmental Assessment Agency. Agreement to Conduct a Cooperative Environmental Assessment Including the Establishment of a Joint Review Panel, of the Site C Clean Energy Project. Available online: https://www.ceaa.gc.ca/050/documents/54272/54272E.pdf (accessed on 10 January 2019).
- Site C Joint Review Panel. Report of the Joint Review Panel: Site C Clean Energy Project BC Hydro. Available online: https://www.ceaa-acee.gc.ca/050/documents/p63919/99173E.pdf (accessed on 10 January 2019).
- Province of British Columbia. British Columbia Utilities Commission Inquiry Respecting Site C—Terms of Reference. Order of the Lieutenant Governor in Council, Order in Council 244, Section 3. Available online: http://www.bclaws.ca/civix/document/id/oic/oic_cur/0244_2017 (accessed on 10 January 2019).
- Canadian Environmental Assessment Agency. Cumulative effects assessment practitioners guide. Prepared by The Cumulative Effects Assessment Working Group and AXYS Environmental Consulting Ltd. Available online: https://www.ceaa.gc.ca/43952694-0363-4B1E-B2B3-47365FAF1ED7/Cumulative_Effects_Assessment_Practitioners_Guide.pdf (accessed on 10 January 2019).
- Lee, P.; Hanneman, M. Atlas of land cover, industrial land uses and industrial-caused land change in the Peace Region of British Columbia. Global Forest Watch Canada Report #4: International Year of Sustainable Energy for All. Available online: https://www.ceaa-acee.gc.ca/050/documents/p63919/96538E.pdf (accessed on 10 January 2019).
- Canadian Environmental Assessment Agency. Site C Clean Energy Project—Draft Environmental Impact Statement Guidelines. Available online: https://www.ceaa-acee.gc.ca/050/evaluations/document/55123?culture=en-CA (accessed on 10 January 2019).
- Treaty 8 Tribal Association. Site C Clean Energy Project Joint Review Panel Hearings—Summary Report Treaty 8 First Nations. 3 February 2014. Available online: https://www.ceaa-acee.gc.ca/050/documents/p63919/98286E (accessed on 8 January 2019).
- Parks Canada. Parks Canada Comments on the Draft Environmental Impact Statement (EIS) for the Site C Clean Energy Project; CEAR #63919-922; Parks Canada: Gatineau, QC, Canada, 2013.
- BC Hydro. Response to Public Comments Related to the EIS Guidelines (10 April 2012) for the Site C Clean Energy Project. Topic Summary Cumulative Effects Assessment. Available online: https://www.ceaa-acee.gc.ca/050/documents/p63919/57624E.pdf (accessed on 14 August 2018).
- Nalcor Energy. Part A Project Planning and Description. In Lower Churchill Hydroelectric Generation Project Environmental Impact Statement; Nalcor Energy: St. John’s, NL, Canada, 2010; Volume 1, pp. 9–28. [Google Scholar]
- Gunn, J.; Bram, F.N. Conceptual and methodological challenges to integrating SEA and cumulative effects assessment. Environ. Impact Assess. Rev. 2011, 31, 154–160. [Google Scholar] [CrossRef]
- Canadian Environmental Assessment Agency; British Columbia Environmental Assessment Office. In the Matter of the Joint Review Panel Established to Review the Site C Clean Energy Project Proposed by British Columbia Hydro and Power Authority. Volume 26, pp. 192–198. Available online: https://www.ceaa-acee.gc.ca/050/documents/p63919/98144E.pdf (accessed on 14 August 2018).
- BC Government, BC Hydro. Province Announces Site C Clean Energy Project—News Release. Available online: https://www.sitecproject.com/news-and-information/province-announces-site-c-clean-energy-project (accessed on 31 July 2018).
- BC Hydro. Greenhouse Gas Emissions. In Site C Clean Energy Project Environmental Impact Statement; BC Hydro: Vancouver, BC, Canada, 2013; Volume 2, Section 15. [Google Scholar]
- BC Hydro. Greenhouse Gases Technical Report. In Site C Clean Energy Project Environmental Impact Statement; BC Hydro: Vancouver, BC, Canada, Appendix S; 2012. [Google Scholar]
- Site C Clean Energy Project Joint Review Panel. Revised Public Hearing Schedule—Released 6 December 2013. Available online: http://www.ceaa-acee.gc.ca/050/documents/p63919/96899E.pdf (accessed on 31 July 2018).
- BC Hydro. BC Hydro Submission to the British Columbia Utilities Commission Inquiry into the Site C Clean Energy Project. Appendix G: Site C GHG Emission Reductions. Available online: http://www.bcuc.com/Documents/wp-content/09/DOC_90101_F1-1-BCH_submission_SiteC_Public.pdf (accessed on 14 August 2018).
- BC Hydro. Site C Clean Energy Project Environmental Impact Statement; BC Hydro: Vancouver, BC, Canada, 2013; Volume 1, Section 5. 5-70.
- Office of the Premier. Government will complete Site C construction, will not burden taxpayers or BC Hydro customers with previous government’s debts—News Release. Available online: https://news.gov.bc.ca/releases/2017PREM0135-002039 (accessed on 24 April 2018).
- British Columbia Supreme Court. West Moberly First Nations v British Columbia, BCSC 270 (CanLII). Available online: http://canlii.ca/t/hql7n (accessed on 25 April 2018).
- British Columbia Supreme Court. Yahey v. British Columbia, BCSC 1302 (CanLII). Available online: http://canlii.ca/t/gkd05 (accessed on 25 April 2018).
- Kurjata, A. West Moberly and Prophet River First Nations file court claim to stop Site C. Available online: http://www.cbc.ca/news/canada/british-columbia/site-c-dam-court-case-1.4489679 (accessed on 24 April 2018).
- Sage Legal. West Moberly First Nations application for Interim Injunction. Available online: https://www.sagelegal.ca/injunction-application/ (accessed on 24 April 2018).
- Palmer, V. Getting Site C to point of no return a damning progress report, so far. Available online: http://vancouversun.com/opinion/columnists/vaughn-palmer-getting-site-c-to-point-of-no-return-a-damning-progress-report-so-far (accessed on 24 April 2018).
- Eliesen, M. Submission F13-1, F13-2. August & October 2017. Available online: http://www.bcuc.com/site-c-inquiry.html (accessed on 14 March 2018).
- Swain, H. Submission F36-1, F36-2. August & October 2017. Available online: http://www.bcuc.com/site-c-inquiry.html (accessed on 14 March 2018).
- Prophet River and West Moberly First Nations. Submissions F28-1, F28-2, F28-3. August & October 2017. Available online: http://www.bcuc.com/site-c-inquiry.html (accessed on 14 March 2018).
- United Nations. United Nations Declaration on the Rights of Indigenous Peoples; United Nations: New York, NY, USA, 2008. [Google Scholar]
- Askew, H.; Snelgrove, C.; Wrightson, K.; Couturier, D.; Koebel, A.; Nowlan, L.; Bakker, K. Between Law and Action: Assessing the State of Knowledge on Indigenous Law, UNDRIP and Free, Prior and Informed Consent with Reference to Fresh Water Resources. West Coast Environmental Law, University of British Columbia: Vancouver, BC, Canada.
- Slattery, B. Aboriginal Rights and the Honour of the Crown. Supreme Court Law Rev. 2005, 29, 433–445. [Google Scholar]
- Department of Justice Canada. Principles respecting the Government of Canada’s relationship with Indigenous peoples. Available online: http://www.justice.gc.ca/eng/csj-sjc/principles-principes.html (accessed on 15 March 2018).
Projects Assessed under the Canadian Environmental Assessment Act | Number of Significant Environmental Effects |
---|---|
Site C Project | 20 |
New Prosperity Gold and Copper Mine Project | 5 |
Lower Churchill Hydroelectric Generation Project | 5 |
Jackpine Mine Expansion Project | 5 |
Pacific Northwest LNG | 3 |
Encana Shallow Gas Infill Development Project | 2 |
Cheviot Coal Project | 2 |
Kemess North | 2 |
Northern Gateway Project | 1 |
White Pines Quarry | 1 |
LNG Canada | 1 |
Labrador-Island Transmission Link | 1 |
Activity | GHG Emissions Estimates | |
---|---|---|
Conservative | Likely | |
(tonnes CO2e) | (tonnes CO2e) | |
Construction (8 years) | 1,483,708 | 997,225 |
Operations (100 years) | 5,824,820 | 4,343,633 |
TOTAL (108 years) | 7,308,528 | 5,340,858 |
Attribute | Units | Site C Energy Used in BC | Site C Surplus Energy Exported | Total |
---|---|---|---|---|
Generation (100 years) | (GWh) | 476,300 | 33,700 | 510,000 |
Avoided GHGs—alternative “clean” portfolio | (Mt CO2e) | 19 | 15 | 34 |
© 2019 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (http://creativecommons.org/licenses/by/4.0/).
Share and Cite
Bakker, K.; Hendriks, R. Contested Knowledges in Hydroelectric Project Assessment: The Case of Canada’s Site C Project. Water 2019, 11, 406. https://doi.org/10.3390/w11030406
Bakker K, Hendriks R. Contested Knowledges in Hydroelectric Project Assessment: The Case of Canada’s Site C Project. Water. 2019; 11(3):406. https://doi.org/10.3390/w11030406
Chicago/Turabian StyleBakker, Karen, and Richard Hendriks. 2019. "Contested Knowledges in Hydroelectric Project Assessment: The Case of Canada’s Site C Project" Water 11, no. 3: 406. https://doi.org/10.3390/w11030406
APA StyleBakker, K., & Hendriks, R. (2019). Contested Knowledges in Hydroelectric Project Assessment: The Case of Canada’s Site C Project. Water, 11(3), 406. https://doi.org/10.3390/w11030406