Next Article in Journal
Simultaneous Heterotrophic Nitrification and Aerobic Denitrification of High C/N Wastewater in a Sequencing Batch Reactor
Previous Article in Journal
A Comparative Study of Biological and Ozonation Approaches for Conventional and Per- and Polyfluoroalkyl Substances Contaminant Removal from Landfill Leachate
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Modeling and Monitoring of Drawdown Flushing and Dredging Toward Sustainable Sluicing in a Wide Philippine Reservoir

1
Institute of Hydraulic Engineering and River Research, Department of Landscape, Water and Infrastructure, BOKU University, Am Brigittenauer Sporn 3, 1200 Vienna, Austria
2
The World Bank, Washington, DC 20433, USA
3
GLM Engineering PSC, San Juan, PR 00907, USA
4
Vienna Model Basin Ltd., 1200 Vienna, Austria
5
Institute of Civil Engineering, University of the Philippines Diliman, Quezon City 1101, Philippines
*
Author to whom correspondence should be addressed.
Water 2025, 17(17), 2514; https://doi.org/10.3390/w17172514
Submission received: 24 June 2025 / Revised: 12 August 2025 / Accepted: 18 August 2025 / Published: 22 August 2025
(This article belongs to the Section Water Erosion and Sediment Transport)

Abstract

Reservoir sedimentation, a global challenge causing an annual loss of 0.8–1% of reservoir storage capacity, disrupts fluvial sediment continuity and impacts ecology and societal needs. This study focuses on the Pulangi IV reservoir in the Philippines, a shallow and wide reservoir facing significant sedimentation issues. The research aims to investigate drawdown flushing and dredging of a flushing channel for future sustainable drawdown sluicing. A test flushing event was conducted and monitoring data, including discharge, suspended sediment concentration, bathymetry, and grain size distribution, were collected. Laboratory analyses, such as critical shear stress tests, were performed for model calibration. A 3D reservoir model and a 1D sediment transport model were applied incorporating cohesive sediment behavior. Scenarios were simulated to assess drawdown flushing, dredging and downstream impacts. Results highlight the importance of drawdown level, with cohesive sediment properties playing a critical role. Sedimentation downstream of the dam, resulting from dumped or flushed sediments, was low. However, downstream ecological and morphodynamic monitoring was found to be essential for all modeled strategies. This study demonstrates potential for establishing a flushing channel enabling future sustainable drawdown sluicing during floods by conducting repeated drawdown flushing in combination with dredging in the upper reservoir.

1. Introduction

Reservoir sedimentation totaling more than 100 billion metric tons is a critical global challenge interrupting sediment continuity from rivers to the ocean [1]. According to Annandale et al. [2], sedimentation causes an annual loss of 0.8–1% of reservoir storage capacity, as reported by the International Commission on Large Dams (ICOLD) [3], and this net loss persists despite the continued construction of new dams. Reservoir sedimentation disrupts ecological and societal systems both upstream and downstream, with upstream sedimentation degrading aquatic habitats [4], increased flood levels upstream of reservoirs [5,6] and downstream sediment starvation causing riverbed degradation [4,7], loss of habitat [4], as well as fine sediment deposits and infiltration into the riverbed [2,8,9,10,11]. Moreover, sediment accumulation in reservoirs reduces their storage capacity, compromising reservoir benefits and revenue [12]. These impacts develop incrementally until the end of the reservoir’s lifetime under the “design life approach” for reservoir planning, when deposits encroach on dam structures and intakes [2,13]. All reservoirs act as sediment traps [14] resulting in unsustainable storage capacity and sediment deficits downstream of the reservoir. Sustainable long-term sediment management is required to maintain long-term reservoir storage, instead of planning for reservoir lifetimes of e.g., 50 to 100 years [13,15]. This sustainable approach requires the appropriate design of new dams and, to a larger extent, extending the lifetime of existing reservoirs against the challenge of sedimentation [16]. The aim is to transform reservoir storage into sustainable capacity, satisfying inter-generational equity. This involves implementing sediment management techniques and modification of conventional economic evaluation of reservoir projects to favor sustainable outcomes [2]. Sedimentation problems exacerbated by additional factors including land use changes, changes in discharge, acceleration or deceleration of soil erosion, and climate change [17,18,19]. Impacts of sedimentation on benefits including hydropower generation, water supply, floods, aquatic ecology, infrastructure or dam safety, are summarized in [4,5,15].
Two categories of hydropower plants can be distinguished [20]. The first, storage hydropower, involves the retention of water in a reservoir, released as needed to shift wet season releases into periods of lower flows to sustain power production [20]. Active storage is large compared to dead storage, and may additionally be used for irrigation, water supply or flood retention [15]. The second, run-of-river hydropower plants, as described by [20,21], operate without storage capacity or with capacity only sufficient for daily power peaking. Dead storage may be larger than active storage [15]. Okumura & Sumi [12] found a negative impact on power generation (reduced water use efficiency) due to the loss of storage capacities in both storage and run-off river hydropower plants.
The Pulangi IV hydropower plant in the Philippines exemplifies the challenges posed by reservoir sedimentation, in this case for a shallow and wide reservoir. Commissioned in 1985, the reservoir operated as a run-of river hydropower plant with an initial storage capacity of 70 Mm3. However, the 2019 bathymetric study revealed a 76% loss of capacity, with only 17 Mm3 remaining [22]. Without intervention, projections suggest that reservoir capacity could drop to as low as 5 Mm3 by 2030 [23], which may be considered the end of the reservoir’s useful lifetime. The project’s feasibility study [24] estimated a reservoir lifetime of 50 years (reached in 2037), by which time the original trap efficiency, estimated at 40% (after [25]), would be reduced to zero. Data from the National Power Corporation (NPC) [22] estimated a sedimentation rate 1.70 Mm3y−1 from 1987 to 2014, but capacity loss has more recently decreased to 0.79 Mm3y−1 due to three phases of dredging operations with a total volume of around 1.25 Mm3y−1 starting in 2007, plus reduced trap efficiency. This reservoir’s shallow and wide geometry exacerbates sedimentation, with sediment deposits forming wide deltaic lobes and near-dam deposits, a geometry ill-suited to sediment removal by the much narrower channels created by sluicing or flushing. These challenges highlight the need for effective and sustainable sediment management strategies tailored to the unique characteristics of shallow and wide reservoirs. Further challenges arise from the effect of Pulangi IV reservoir on the downstream reach, sediment starvation as sediments accumulated in the reservoir, and the potential for extreme sediment releases during management, both of which may impair ecological conditions below the dam.
Multiple sediment management options for reservoirs are available [26,27,28,29]. Morris [13] published a classification of management alternatives regarding reservoir sedimentation which included: (i) reducing sediment yield, (ii) routing sediments to minimize deposition, (iii) removing deposited sediment and (iv) applying adaptive strategies to minimize sediment impacts. With regard to management category (i) “reducing sediment yield” from Morris [13], sediment yield due to land conversion and climate change in the Pulangi IV catchment are already higher than a tolerable amount (11.2 t ha−1y−1) and simulations of the Pulangi IV catchment indicate that sediment yield may change between −2.4% (2050) and +12.4% (2080) for RCP 4.5, and between −0.6% (2050) and +20% (2080) for RCP 6.0 [30]. For category (ii), drawdown sluicing during floods and ‘compartmented reservoirs’ were mentioned as sediment pass-through strategies [13]. For category (iii) dredging as well as empty flushing were given as examples for sub-categories ‘mechanical removal’ and ‘hydraulic scour’, respectively [13].
Sluicing was described in detail by Morris [13] as the maximization of sediment passage through a reservoir by lowering the water level during a flood, which is most effective in hydrologically small reservoirs (such as in this case study). It was also noted that sluicing is inexpensive compared to other methods, such as dredging, and that it might become increasingly relevant later in the reservoir’s lifetime because of shrinking reservoir capacity. One major advantage cited is that it does not result in high suspended sediment loads downstream during flood events. This contrasts to emptying and flushing, which produce concentrations much higher than natural levels. This makes sluicing an environmentally friendly technique. An example of optimized sluicing operations for shallow and wide reservoirs reducing trapping of sediments is given in [31]. A “compartmented reservoir” refers to the hydraulic short-circuiting of sediment-laden inflows within the reservoir by using internal barriers or modified geometries created by dredging [13]. This strategy is most relevant for wide and shallow reservoirs, like Pulangi IV.
In contrast, Morris [13] mentioned that flushing releases high peaks in suspended sediment concentrations (SSC > 100 g/L), which can require complex environmental monitoring and mitigation. Morris and Fan [16] also describe flushing as the emptying of the reservoir to allow the river to erode deposits and discharge them through low-level outlets (LLO). The process was noted to typically consist of three stages: (i) the ‘drawdown’ stage, where upstream sediments are transported to the LLO with relatively smaller amounts of sediment being released; (ii) the ‘empty’ stage, during which the transported sediments are released through the LLO, producing peak sediment concentrations; and (iii) the ‘refill’ stage, a period when clear water may be released downstream to help flush the sediments through the river system. Flushing and sluicing operations are mentioned by CIGB, ICOLD [32] to have a major constraint, which is the requirement for excess water availability. Sediment pass-through is mentioned to be successful when the reservoir capacity is less than 5% of the mean annual runoff, which is the case for the Pulangi IV reservoir. Favorable conditions for drawdown flushing include: steep longitudinal slope and narrow valley (narrow reservoir) [16,33]. Lacking these conditions, flushing efficiency is low for shallow and wide reservoirs. Lai et al. [34] propose factors for drawdown flushing efficiency, including width, and depth, sediment composition, inflow of water and sediment, outlet configuration and reservoir operation. Kantoush et al. [35], for example, experimentally investigated the influence of free-flushing, pressure flushing and drawdown flushing regarding the width and shallowness of reservoirs and found a negative correlation of flushing efficiency with the width and depth of the reservoir. Drawdown flushing was by far the most efficient measure for sediment removal, but the sustainable reservoir capacity depends on the ratio between the width of the self-forming flushing channel and the width of the reservoir. A flushing channel much narrower than the overall width of a wide reservoir limits the ratio of sustainable capacity to original capacity [34] when dependent on flushing alone. A RESCON2 [36] assessment of Pulangi IV reservoir indicated that drawdown flushing, sluicing and dredging could contribute to sustainable management of the reservoir. For category (iii) use of dredging as management strategy [13], the disposal of dredged material from the reservoir and its downstream effects on morphology and ecology need consideration [4,8]. Permitting limitations and costs can also represent important constraints [5].
State-of-the-art methods for assessing sediment management measures span various spatial dimensions and approaches, including economic evaluation tools like RESCON2, numerical models combined with monitoring, and physical models. Sumi et al. [27] provide examples of 1D and 2D numerical studies, while highlighting the growing application of 3D numerical models, particularly in scenarios where velocity variations over the flow depth, such as in channel bends, are critical. In contrast, Annandale et al. [15] primarily discuss 1D and 2D models, with 1D models being used for long-term assessments of entire reservoirs and 2D models for detailed simulations near dams, where lateral water and sediment movement is significant, or for short-term events such as individual floods. Although Annandale et al. [15] explicitly mention 3D models only in the context of physical models, the increasing use of multidimensional numerical models is attributed to advancements in computational capacity. Lai et al. [34] provide a comprehensive review of hydraulic flushing in reservoirs, utilizing numerical models ranging from 1D to 3D, including fully Navier–Stokes-based models without the hydrostatic assumption, offering insights into their application and limitations. In this review, non-hydrostatic’ 3D model applications on drawdown flushing are described [37,38,39,40,41], reproducing flushing channels in various degrees of similarity. E.g., Ref. [40] simulated a relatively narrow reservoir using 3D hydrodynamics with a 2D numerical sediment transport model, successfully validated with observations, where a flushing channel developed during drawdown. The model was then found to be a successful tool to propose strategies to increase flushing efficiency. Lai [34] mentions that model calibration is not critical for 3D hydrodynamics, however limitations on 3D models are given especially due to scales in space and time. For large reservoirs, one must restrict time scale to a short period, e.g., one empty flushing event, as contrasted to 1D models which can simulate multiple events each year over a period of many decades. Concerning sediment transport, Lai [34] further mentions that the accuracy depends on the adopted empirical sediment transport equation and, due to the occurrence of cohesive material near the gates, proper measurement of cohesive properties. Modeling of cohesive sediments, including their erosion behavior, considers various influencing factors such as physical, electrochemical, and biological processes [42] and largely affects sediment transport and morphology for both rivers and reservoirs. Consolidation also affects cohesive sediment transport, particularly in reservoirs, as sediment layers exhibit varying bulk densities over consolidation time [42].
Moreover, successful modelling of flushing operations heavily relies on a detailed spatial-temporal monitoring of these operations, both within the reservoir and in the river downstream. This includes monitoring discharge, water levels, sediment concentrations, conducting bathymetric surveys, collecting sediment samples, performing laboratory analyses, and accounting for the cohesive properties of the samples [5,15]. Furthermore, ecological monitoring on habitat quality in both the reservoir and the river downstream is essential, especially due to the high amounts of SSC released during flushing. As an example, ref. [8] conducted an event-based monitoring on reach and local scale considering morphology with respect to fine sediments, turbidity, bed composition and fine sediment infiltration combined with monitoring macroinvertebrates and fish.
For the Pulangi IV reservoir, Tabios [43] summarizes a numerical study for pressure flushing (flushing with either zero or only partial water level drawdown), performed in 2005. It showed local effects near the intake, resulting in around 0.05 Mm3 removal for a release of 730 m3s−1 for 12 h through the bottom sluice gates (BS). Tabios [43] introduced an additional numerical study from 2011 (2D model based on [44]) that proposed a sediment flushing protocol based on inflow and reservoir width. The study recommended that higher inflow should correspond to a greater gate opening, resulting in a larger drawdown. He found for 12 h flushing duration that flushed sediment volume increased with greater sluice gate opening and more water level drawdown, whereas reservoir inflow had less effect, with an optimal inflow range of 150 to 200 m3/s with no reduction in hydropower generation. For the investigated sluice gate openings of 0.2 to 2.0 m and the reservoir inflow between 100 and 300 m3, flushed sediment volume was between 10,000 and 50,000 m3. Tabios [43] also found consistency with flushing operations conducted in 2007, indicating 18,000 m3 flushed out sediments in 15 h. Comparisons with test flushing operations performed in 2007 indicated that sediment drawdown flushing operations were successful and should be continued. For [45,46], drawdown sluicing was modeled (numerically and physically) in combination with a dredged channel and a dike (compartmented reservoir created by side-casting dredged material), showing evidence for a highly effective sediment routing through the reservoir during a flood with a two-year return period. However, the dredging volume was substantial (5 Mm3), prompting consideration of a combined approach involving dredging in the upper reservoir and flushing in the lower reservoir before a continuous flushing channel is established. The more sustainable drawdown sluicing operations, such as in [31,45,46], can be considered in the future, as well. This combined sediment management approach also includes discharge of dredged material to the river downstream. Due to the shallow and wide reservoir geometry and the various bifurcated channels crossing the multi-lobe reservoir delta, a finer spatial scale and the use of more detailed, three-dimensional numerical methods were appropriate. Cohesive sediments, which dominate in the lower and middle sections of the reservoir, need to be accounted for during modeling.
The aim of this detailed case study on a shallow and wide reservoir was to evaluate and optimize sediment management strategies, with a particular focus on establishing a flushing channel to enable sustainable sediment passage through drawdown sluicing in the future. This included:
  • Monitoring of drawdown flushing based on a single test flushing event.
  • Preparation of a calibration dataset including laboratory analyses (e.g., grain size distribution, critical shear stress test).
  • Calibration of a 3D numerical reservoir model and a 1D model for the river downstream, both incorporating cohesive sediment behavior.
  • Modeling scenarios to develop a continuous flushing channel in the shallow and wide Pulangi IV reservoir enabling sustainable sediment routing through drawdown sluicing in the future.
  • Modelling the downstream impacts of drawdown flushing on sediment transport and morphology.
  • Analyzing the scouring and transport of dredged sediments from the reservoir, which were dumped in the river downstream of the dam.

2. Materials and Methods

2.1. Pulangi IV Case Study (Mindanao, Philippines)

The Pulangi IV case study (Mindanao, Philippines: coordinate location 7°47′12″ N Latitude and 124°1′28″ E Longitude) was conducted by ESMAP of the World Bank (funded by the Austrian Ministry of Finance). The hydropower plant has an installed capacity operating at 270 m3s−1 and 110 m design head. The earth-filled dam has 7 spillways and 2 bottom sluice gates (BS, Figure 1) adjacent to the intake headworks (HW), delivering water to a headrace channel terminating in a surge pond and penstocks. Pulangi IV is operated as a run-of river project with daily peaking. Catchment size is 3114 km2 with a mean discharge of 152 m3/s [24] and a coefficient of variation of 0.22 (data from 1953–1977), indicating a uniformly distributed discharge throughout the year. Pulangi IV was commissioned in 1985 with a volume of 70 Mm3 [47,48] and an average depth of only 6.3 m.

2.1.1. Scenarios

Three scenarios were considered in the reservoir with specific settings of inflow Qin, initial reservoir water level Winit, drawdown level Wmin and gate openings B (Table 1). Drawdown water level represents the elevation immediately upstream of the sluice gates. Two scenarios were modeled for the Pulangi river downstream of the dam. Scenario C-75 in the reservoir (Figure 2a) reproduces the test flushing event undertaken during monitoring in January 2020 (Section 2.2), where the reservoir inflow Qin was around half of mean flow. According to the operator’s experience, gates were opened stepwise leading to a maximum reservoir outflow Qout of 835 m3s−1 before gates were closed. Due to the highly unsteady flow process, the model simulation ended 5.8 h after gates were opened, when reservoir level had lowered from 284.6 to 281.0 m. By comparison, the minimum operating level (OL) is 279.0 m. Scenario C-75 also monitored parameters in the river downstream of the dam (Table 1).
Scenario 1-250 (Figure 2a) and 2-250 (Figure 2b) aimed at the investigation of drawdown flushing effects under more favorable conditions (Table 1) such as elevated inflow (higher than mean flow), additional water level drawdown Δh (1m above min. OL), increased gate opening B at BS and maximum turbine discharge QT (set to the design discharge of the hydropower plant). The initial reservoir water level was set to the maximum operation water level (max OL), and drawdown was applied to a level where the drawdown cone was numerically stable (280.0 m). Scenario 1-250 was performed on the existing bathymetry (2019).
For scenario 2-250 (Figure 2b), a dredged flushing channel in the upper reservoir was considered, with the idea of extending the flushing channel in the lower reservoir through drawdown operation alone. The width of the channel was estimated by the empirical relation from Atkinson [49], correlating flushing channel width Wf (m) to flushing discharge Qf (m3s−1):
Wf = 12.8 Qf0.5
For a flushing inflow of 250 m3s−1 (Qf) the channel width (Wf) is 202 m (Equation (1)), and this was used as an initial estimate of the flushing channel design width at the midpoint along the channel length. Part of the dredged material was considered for deposition to form a dike along the right-hand side of the channel to help funnel flow along the dredge cut. The total dredged material from the flushing channel amounted to 2,220,445 m3 (Table 1), of which 374,502 m3 was designated for the dike. The other portion of the material was considered to be discharged below the dam (scenario D, Table 1). Side casting of dredged material to form this dike supports the sediment routing strategy ‘compartmented reservoir’ [13]. Figure 2c shows a potential final state of such a flushing channel, where a channel bed slope of 0.003 is predetermined by the connection of bed levels of the river upstream with the level at the bottom sluice gate. This flushed channel would represent 5 Mm3 of sediment if dredged completely and could then be used for future efficient sediment routing through drawdown sluicing.
For the Pulangi river downstream of the dam, an additional scenario (D) was considered to evaluate discharge of material from the dredged channel (Figure 2b) into the river gorge downstream of the dam (Table 1). A potential and accessible site was identified at G (Figure 1a). Dredged material of 6000 m3 was deposited, corresponding to a height of 2 m, and the scouring and transport in the river downstream was modeled for 72 h (Table 1).

2.1.2. Topography

The first available bathymetry and topographic survey dates to year 2000 [22], followed by measurement campaigns in 2010, 2012 (only lower reservoir), 2014 and 2019. Those campaigns, using GPS RTK and total station measurements, had different point densities with highest being in 2010. Part of the bathymetry in 2014 was surveyed using echolot and completed with data from GPS RTK and total stations. The modeling study of Pulangi IV reservoir was performed with the most recent bathymetry data from the 2019 measurement campaign, and gaps were filled up with data from earlier campaigns.
In earlier years the main flow in this wide and shallow reservoir followed its northern and western side. However, as the delta grew in this area, the main flow shifted progressively eastward after 2010, eventually creating various bifurcated channels and three main depositional lobes of in the delta. Bathymetry data were denser along those more-accessible bifurcated channels crossing the delta and in the lower part of the reservoir, representing areas of discharge during mean flow conditions. The various channels were represented by a Digital Elevation Model (DEM) with the Triangulated Irregular Network (TIN) grid established within ARCGIS. A DEM model for the Pulangi River old channel downstream of the dam was also created as a TIN surface. Bathymetric data for Pulangi River downstream of the dam, representative of 2011, were provided by NPC [22], which were combined with the DEM from [50].

2.2. Monitoring and Laboratory Analyses

2.2.1. Field Measurement Campaign 2020 (Test Flushing Event)

Monitoring was performed from 20 to 24 January 2020, focusing on documenting the test flushing event of 22 January 2020. At the reservoir inflow location (BB, Figure 1a) discharge and suspended sediment concentration (SSC) were measured. Reservoir inflow was measured continuously using a 2D electromagnetic current meter (Infinity FM with data logger, JFE Advantech) in combination with water level loggers (HOBO, Onset) using the velocity area method [51]. It consists of measurements of stream velocity (1 s interval), water depth and distance across the channel between observation verticals. Discharge of a vertical was derived from the product of mean normal velocities over the depth vm, the water depth at the vertical profile and the distance between the verticals. Total discharge in the cross-section was calculated by summing up the discharges of the verticals. Eight verticals were measured at the 34.4 m wide trapezoidal cross section BB. Instantaneous cross-sectional profiling was performed at regular intervals during the test flushing event. SSC was measured continuously using turbidity sensors (Infinity-CLW, Nishinomiya, Japan; JFE Advantech Co., Ltd., Nishinomiya, Japan) in combination with water level loggers (HOBO, Onset, Bourne, MA, USA). Furthermore, bailing samples were taken to validate the turbidity sensors. Cross section sampling using a depth integrated sampler (SGLN, Bundesamt für Umwelt, Bern, Switzerland) and an improvised sampler (water bottle, holder frame and rope) were also performed at BB. Average cross-sectional SSC was calculated by using the integration method by dividing the flow area into several verticals. Depth-averaged velocity-weighted SSC is achieved when the inflow into the measuring device is isokinetic [52].
During test drawdown the reservoir level (provided by [22]) dropped from 284.62 m to 281.0 m. The duration of the water level drawdown was 5.83 h between opening and closing of sluice gates, with turbines operated continuously. Total discharge at the outlet of the reservoir is BS and HW (Figure 1a). Turbine discharge QT, the HW abstraction rate (Figure 1a) was provided by the owner [22]. Discharge by the bottom sluice gates (BS) was calculated using a sluice gate equation [43], as discharge could not be measured directly due to high flow velocities and the lack of secure and appropriate accessibility.
Turbidity sensors (Infinity-CLW Nishinomiya, Japan; JFE Advantech Co. Ltd., Nishinomiya, Japan) in combination with water level loggers (HOBO, Onset, Bourne, USA) were installed downstream of the sluice gates (BS, Figure 1a) for continuous measurements. However, data could not be retrieved due to cable breakage by the high discharge velocity. Instead, direct near-bank samples were taken at 5 min intervals. Sampling verticals in the water column was neither possible nor needed as high turbulence created completely mixed conditions.
In the power channel (CB in Figure 1a) discharge was measured using a 2D electromagnetic current meter (Infinity FM with data logger, JFE Advantech, Nishinomiya, Japan) and compared with ADCP (Teledyne Stream Pro, Manila, Philippines) measurements by applying the same method as adopted at the reservoir inflow (BB). Due to the uniform cross-section of the power channel, only 6 verticals were measured covering the total channel width of 42 m. Water level was monitored with level loggers (HOBO, Onset). Temporal variation of SSC was measured continuously using a turbidity sensor (Infinity-CLW, JFE Advantech Co., Ltd.). Cross-sectional SSC was measured by depth integrating samples using similar verticals as for discharge measurement.
A photogrammetric survey was conducted of the gorge of the old river at G. Monitoring was performed approximately 200 m downstream of the Pulangi reservoir, selecting the site based on its accessibility and suitability for water level monitoring. To derive the geometry of the cross-section, terrestrial photogrammetry was employed and analyzed with Agisoft Photoscan Professional (version 1.2.6.2834). Additionally, a water level logger (HOBO, Onset) was installed in the channel at G which, in combination with calculated discharge at BS and HW, served as a basis for calculating a rating curve (Q-W) during reservoir drawdown. This rating curve was needed for the hydrodynamic calibration of the 1D numerical model downstream of the dam.
A single-beam bathymetric survey was performed in the area of the lower reservoir (Figure 1a) before and after the test sluice event. Reservoir samples (Figure 1a) were taken in the lower and middle reservoir by inserting plastic pipes (5 cm dia.) 1.0 m into the deposited sediments. Samples were capped hermetically for transport to the laboratory for analyses.

2.2.2. Laboratory Analyses

SSC analysis for 15 samples was performed in the Laboratory at CMU (Central Mindanao University, Philippines) by 45 µm pore-size filtration assisted by a vacuum pump in accordance with DIN 38 409, 2 [53]. At BOKU University, plastic pipes from the reservoir sampling were cut into various samples representing layers, each around 10 cm depth. Grain density was analyzed for 3 samples using the gas pycnometer method after EN ISO 17892-3 [54] using a Helium pycnometer (AccuPyc II 1340, Micrometrics, Norcross, GA, USA). Dry bulk density and porosity for 10 samples was determined by the ratio of mass of the material of a selected depth layer to the volume defined by the plastic pipe. After drying at 105 °C and weighting, bulk density and porosity were calculated. Critical shear stress tests [55,56] for 16 samples were performed in the laboratory at BOKU University using the test rig illustrated in Figure 3.
This allowed the determination of shear stress limits for erosion as described in [42]. Critical bed shear stress was determined on samples which were aligned with the bed in the measurement section, using hydraulic loss and local measurements based on disturbance-free laser-optical techniques (Particle Image Velocimetry and Laser Doppler Velocimetry). The test reach extends for a length of 2.7 m with a rectangular cross section (0.188 × 0.094 m). By constantly increasing discharge shear stress, threshold values for surface and mass erosion of the sample were detected. To evaluate possible bias caused by storing and possible drying out of samples, 6 samples were also submerged in water for 1 week before performing the tests.

2.3. Numerical Methods

2.3.1. Three-Dimensional Hydrodynamic Model (RSim-3D), 2D Sediment Transport Model (iSed)

Pulangi IV reservoir was simulated using the sediment transport model iSed version 2.16 [57,58], which was coupled with the 3D hydrodynamic model RSim-3D version 2.27 [59]. The model RSim-3D solves Reynolds-averaged Navier–Stokes equations on an unstructured grid using the Finite Volume method. Polyhedral cells with vertical walls are generated from cell centroids by applying Voronoi decomposition [60] and dividing the water column into n cells in the vertical direction. The location and density of cell centroids is defined by the user, which enables full control of the stored variables in the domain. Moreover, orthogonality of cell faces is guaranteed enabling non-orthogonal terms to be neglected in the discretized equations, reducing numerical diffusion. Turbulence closure is provided by two-equation models, where the k-ε model by Launder and Spalding [61] is the standard method. The model works with steady state as well as unsteady conditions. Details on the model are given in Tritthart [59] and Tritthart & Gutknecht [62]. The model was successfully applied in various studies on rivers [63,64], reservoirs [65,66] and laboratory experiments [67,68].
The sediment transport model iSed [57,58], coupled (two-way) with a hydrodynamic model (e.g., RSim-3D), is capable of simulating both bedload and suspended sediment transport. For bedload transport a variety of formulas that account for non-uniform sediment transport can be selected. Suspended sediment transport is implemented by a 2D or 3D equation of convection-diffusion type including additional exchange terms for the interaction with the riverbed [69,70]. The evolution of the riverbed over time follows the Exner equation. Grain sorting is implemented by an exchange layer concept. Cohesive sediments are implemented in iSed after [42]. The integration in the model is shown in [65]. Concerning aggregation of particles due to cohesion, settling velocity can be adapted by the modeler with respect to the sediment concentration to account for hindered settling [71]. On the other hand, a computation using the empirical formulation of settling velocity after Krone [71], derived in laboratory studies, can be selected:
wc = Ks4/3,
where K represents an empirical constant and s is the suspended sediment concentration in g/L. Deposition occurs when the bed shear stress falls below the critical shear stress (τd,part), with the deposition rate determined by its relation to the critical shear stress thresholds (τd,full and τd,part), the settling velocity (w) and a probability factor Pd:
P d = 1 τ τ d , f u l l
The partial deposition rate Qd (for τd,full < τ < τd,part) additionally considers an equilibrium sediment concentration ceq:
Qd = Pdw⋅(cceq)
Pd is set to 0 when τ < τd,part, turning off deposition. Erosion is implemented in two stages after [42]. Surface erosion applies when bed shear stress τ is larger than a critical shear stress for surface erosion (τc,s), shifting to mass erosion when the critical shear stress value for mass erosion (τc,m) is exceeded. Erosion rate is integrated using surface erosion rate Mse and mass erosion rate Mme, respectively. Erosion flux after [65] for surface and mass erosion (sero,s, sero,m) is implemented according to the following equations:
s e r o , s = M s e ρ b τ τ c , s τ c , m τ c , s   for τ c , s τ τ c , m
s e r o , m = M m e ρ b τ τ c , m τ c , m + M s e ρ b   for τ τ c , m
where ρb represents the bulk density. Further details on the cohesive model, implemented in iSed, are given in [42,65].

2.3.2. One-Dimensional Hydrodynamic and Sediment Transport Modeling by HEC-RAS

HEC-RAS is a widely used 1D numerical model including hydrodynamic and sediment transport modeling. Similar to the sediment transport model of the reservoir, the model for the river downstream of the dam is also capable of incorporating cohesive sediments [72]. Details are given in [73].

2.4. Numerical Model Implementation

2.4.1. Reservoir Model (RSim-3D, iSed)

Steady state 3D hydrodynamic model runs were performed by matching model outflow and inflow, and these were used as the initial condition for modeling unsteady water level drawdown. These unsteady 3D hydrodynamic model simulations were conducted using a fixed bed. This model run was refined by unsteady modeling using the two-way coupled approach of the models RSim-3D and iSed. Such a model approach was needed to avoid instabilities regarding the outflow condition at BS and the establishment of a stable drawdown cone. Time step Δt in the fixed bed model was chosen between 360 and 2880 s. The number of iterations per time step, as well as the relaxation parameters essential for 3D hydrodynamic modeling [62], were optimized to reach sufficiently small residuals as well as a reliable mass conservation.
The following unsteady morphodynamic model runs, featuring two-way coupling between iSed and RSim-3D, were applied using the unsteady fixed bed runs as initial condition including flow fields and boundary conditions. The morphodynamic time step was set between 90 s at the beginning of the drawdown, but requiring refinement to a value between 15 and 5 s during the later stages of simulation. The level of refinement strongly depended on the model’s ability to reach the target water level at the sluice gate, estimated by the previous fixed-bed 3D hydrodynamic model. The bed at the model outlet needed to be fixed to reach numerically stable solutions in the drawdown cone near the BS.
The unstructured computational mesh for the 3D numerical model used 284,466 hexahedral cells distributed over 6 vertical layers. Cell size varied over the DEM domain to represent the 2019 surface. Distance between cell centroids was generally 35 m. Smaller average cell sizes (5 to 15 m between cell centroids) were used at the inflow channel to the reservoir, the bifurcated channels in the upper reservoir, and the central part of the middle and lower reservoir, where scouring was expected during drawdown. The smallest cell sizes were applied near the dam at the BS using a rectangular configuration (2 × 1.5 m). A mesh adaptation was needed along the flushing channel (scenarios 1-250 and 2-250) using a rectangular arrangement instead of a hexagonal one for improved representation of the linear geometrical configuration.
The DEM was interpolated onto the mesh, and the location of the upper- and lower boundary Qin, and Qout were defined. Discharge through the power intake (HW) was added to the outflow boundary of the BS gates, as these two structures are adjacent to one another and this simplification was not expected to influence results. The sluice gate geometry was approximated by blocking the upper three cell rows in the 3D mesh.
The sediment transport model iSed was built on the same mesh configuration defined in RSim-3D using 4 layers with a total depth of 3.5 m defined based on reservoir sampling (Section 2.2.1). The sampled grain size distribution was interpolated over the computational domain for each layer based on the samples (Section 2.2.2). Sediment properties including grain density, pore content and cohesive parameters were defined according to the values from sample analysis to compute suspended sediment transport for cohesive behavior implemented after [65]. Bedload transport was omitted due to lack of information on the sediment properties in the upper reservoir including the various bifurcated channels (Figure 2a). Additionally, the bed was assumed to be fixed in these areas to avoid instabilities arising from high flow forces in combination with missing information on larger grain size fractions (e.g., sand).
Modelling reservoir drawdown was computationally expensive due to the large domain and the small time scales. One of the 790 nodes at the Austrian VSC4 supercomputer [74], comprising two Intel Skylake Platinum 8174 Processors with 24 cores each, was used. Depending on the number of iterations and the relaxation coefficients the simulation time was up to 25 times real time. Thus, the sensitivity analysis of the reservoir model considering cohesive parameters was applied only for the last 20 min of drawdown, where changes in bed levels due to erosion were expected to be highest. Sensitivity of other sediment transport parameters is evaluated in Tritthart et al. 2011 [57,58].

2.4.2. One-Dimensional Sediment Transport Model of Pulangi River Below the Dam (HEC-RAS)

The HEC-RAS model was built using the QGIS Plugin RiverGIS [75] River geometries, such as the stream centerline, cross-sections, flow paths dividing the main channel and floodplains, as well as data for estimating roughness and ineffective flow areas, were derived in conjunction with the DEM prepared for this reach.
Calibration of the 1D hydraulic model HEC-RAS was conducted at site G, where measurements were performed to derive a rating curve. The calibration process involved adjusting the Manning coefficient and comparing simulated water levels to observed values derived from the rating curve. Sensitivity analyses were conducted to evaluate the influence of geometric variations, roughness, number of discharge classes (6, 13 and 26 classes between Q = 200 m3s−1 and 800 m3s−1), and boundary conditions on model performance. Statistical metrics, including the Nash-Sutcliffe Efficiency (NSE) and Sum of Square Errors (SSE), were used to assess the model’s accuracy and reliability.
The test flushing event C-75 in the Pulangi river downstream of the dam was modeled with the 1D numerical model using sediment concentration SSC derived from the measurement campaign as the upper boundary. A quasi-steady sediment transport modeling approach was used, as the unsteady approach based on the Saint-Venant-equations was not numerically stable. However, this provided sufficient accuracy as the gates were opened stepwise. A plausibility check of the 1D sediment transport model was applied after [76] since data for model calibration and validation were unavailable. Thereby, compared to hydrodynamic models, it is recommended to change only one parameter at once. Initial model boundary parameters comprised a fixed bed (river incised in rock, Figure 1c), sediment load input time series from the reservoir model c(t), grain size distributions of the transported sediment di (averaged over all reservoir samples), cohesive sediment parameters (τcrit,M, τcrit,S) and the active layer thickness (dex). The next steps included:
  • Selection of sediment transport formulas based on model assumptions and numerical instabilities (sensitivity analysis),
  • Selection of the sorting method (plausibility check and dismissal of unsuitable methods), and
  • Selection of the fall velocity formula (sensitivity analysis).
Based on this selection process a further sensitivity analysis was performed including parameters for roughness n, cohesion [72] and active layer thickness dex.
For the additional scenario D investigating the scouring of dredged material from the reservoir, which was discharged to the gorge downstream of the dam, a potential site was identified at G (Figure 1a). Dredged material of around 6000 m3 was deposited, corresponding to a thickness of 2 m along 85 m of channel length. Scouring and transport of this sediment along the river downstream was modeled for 72 h.

3. Results and Discussion

3.1. Monitoring

3.1.1. Sediment Analysis

Grain size distribution analysis (Figure 4) was performed for 15 samples. The dominant sizes were silt (37.2 to 56.8%) and clay (40.3 to 62.7%). Only three samples contained a sand fraction (>0.0625 mm) greater than 15%, with two of these taken from the northernmost sample point P5 near the river inflow.
The top layer sample (0 to 0.20 m) of P5 (Figure 1) contained 83% sand and the following layer (0.20 to 0.30 m) contained 15.9% sand. The average of all samples from 2020 results in a mean diameter dm of 0.035 mm and a d90 of 0.091 mm. Pre-dam analysis from 1976 showed a dm of 0.158 mm and a d90 of 0.356 mm [24] for riverbed sediments. The difference between pre-dam analysis and the 2020 monitoring demonstrates the accumulation of fine sediments (mostly clay and silt) in the lower reservoir, supporting the need to consider cohesion during modeling of this reservoir.
Grain density was analyzed for three samples giving an average of 2656 kg/m3 + 0.095. Dry bulk density for 10 samples at different locations in the reservoir, distributed over various depths, ranged from 590 kg/m3 to 790 kg/m3 with an average value of 680 kg/m3. Porosity ranged from 70.38% to 77.93% with an average value of 74.43%. Comparing initial weight of the analyzed samples with values from [77] for clay and silt showed good agreement.
Critical shear stress values measured at 16 locations and depth layers demonstrated a high variability in terms of location, depth layer as well as in the visual process evaluation during the critical shear stress tests. Mean and standard error values for of τc,se and τc,me are listed in Table 2.
The six samples stored in water for a week to evaluate the potential effects of drying during storage, resulted in lower critical values. These were found to be more realistic, as potential effects of drying during storage were reduced. Sample P3 is shown as a representative example of the area between the upper and lower reservoirs, whereas sample P11 represents the area near the BS. Cohesion was apparent for all layers except for the deepest analyzed layer of P3 highlighting the high variability of deposited sediments. Moreover, neighboring samples could also vary significantly. Finally, minimum and maximum values from all 16 samples were evaluated as a basis for estimating the model’s sensitivity on cohesion.

3.1.2. Discharge, Water Level and SSC

Water level at the reservoir inflow (BB) was clearly influenced by the backwater from reservoir operation, prohibiting calculation of a rating curve. A steady state inflow of 73.5 m3s−1 defined reservoir inflow Qin (BB) during the test flushing event, as derived from measurements at 9 cross sections (Qin = 73.5 ± 2.17 m3s−1, Figure 5).
Turbine discharge QT (60 ± 22 m3s−1) provided by the operator [22] was in agreement with ADCP measurements. Cross sectional averaged SSC at BB was determined as 207 ± 63 mg/L (Figure 5). Results from the dam construction feasibility study in 1976 (pre-dam condition, [24]) showed lower concentration values at BB for a comparable discharge. The increase may be attributed to enhanced erosion in the basin due to land use changes and climate change [30]. The individual cross sectional SSC measurements and the calculated SSC (Figure 5), using derived rating curves (RC) to combine those measurements with continuous near-bank turbidity sensor measurements, were in agreement for BB (reservoir inflow) and CB (power channel). Inflow was relatively constant for around 24 h during monitoring after opening the gates. Discharge Qout (BS) (Figure 5) represents the sluice gate equation [43] based on gate opening B and reservoir water level. Maximum and minimum SSC measurements at BS using near-bank bailing samples were delineated (Figure 5), although some individual measurements deviate.
Sediment load at BS during the drawdown flushing event (Q75) was calculated using delineated minimum and maximum SSC, which ranged between 30,050 m3 and 51,796 m3. By considering the average gate opening B of 1.36 m and a maximum of B = 5 m (Figure 5), the observed load is approximately comparable with numerical results from Tabios [43], where a 12 h hour drawdown flushing event at 100 m3/s inflow and 2 m gate opening resulted in loads between 46,000 m3 and 52,000 m3. However, Tabios [43] does not mention the level of drawdown reached by the 2D hydrodynamic model. Sediment load at the power channel during C-75 was calculated with 4348 ± 459 m3 between opening and closing of the gates, which was slightly lower than the cumulative sediment load measured at the reservoir inflow (5754 m3). Considering the relatively constant inflow of water and sediment into the reservoir, it is clearly evident that SSC (up to 19.9 g/L) and calculated sediment loads (up to at least 51,796 m3) peaks during drawdown sluicing at BS while the gates were open (Figure 5). Elevated SSC concentrations were mentioned by [13] as a disadvantage of drawdown flushing compared to other management operations (e.g., drawdown sluicing). However, concentrations >100 g/L were not observed due to the very limited drawdown. Nevertheless, a monitoring program targeting macroinvertebrates and fish [8] is required to monitor environmental impact, and the maximum concentration released can be controlled by limiting the drawdown rate. SSC in the power channel (Figure 5), measured at CB 2350 m downstream of HW, also peaked during the gate operations (SSC up to 8.5 g/L), and reached a plateau of around 1.2 g/L (value from cross-sectional SSC measurement t = 21.8 h after gate opening). This plateau lasted until around t = 30 h, indicated by the SSC calculated from rating curves, before reaching SSC concentrations close to the inflowing concentrations. Risks of turbine abrasion (depending on the sand fraction in the sediment mixture) and siltation in the power channel and SP should be carefully considered and monitored. Turbine abrasion will become increasingly important as the delta with higher sand fraction approaches the power intake (HW).
Calculated discharge from the reservoir Qtot, including bottom sluice gates and turbines, was approximated with a polynomial function over the flushing time t (Qtot = 2 · 10−19 t5 − 4 · 10−14 t4 + 6 · 10−10 t3 + 2 · 10−6t2 + 0.002 t + 87.142, R2 = 0.95) and served as the boundary condition for the reservoir numerical model. Measurements at BB, BS, and CB were used as sediment input to the reservoir model and the 1D model in the old river downstream of the dam.
Water level measurements in the gorge downstream of the gates (G), using the cross sections derived with the photogrammetric survey, were clearly correlated to gate opening B during the drawdown event. Therefore, a rating curve at G was derived under steady-state conditions (W = 3.0 · 10−7 Q2 + 7.8 · 10−3 Q + 261.51, R2 = 0.98) as the flushing gates were opened incrementally, allowing for stable flow measurements. In contrast, the closing of the gates resulted in unsteady flow conditions, making the rating curve unreliable during this phase. To ensure accuracy, only the portion of the rating curve corresponding to increasing discharge was used for calibration of the 1D model downstream of the dam.

3.2. Simulation of Pulangi IV Reservoir

3.2.1. Model Calibration and Scenarios

Morphodynamic calibration of the sediment transport model iSed was performed with the help of measured bathymetry changes in the lower reservoir before and after the test flushing event in 2020. Parameters for the cohesive model were set to values presented in [42] (Table 3), whereas critical shear stress values were set in accordance with test runs considering critical shear stress test results using wetted samples (Table 2). Equilibrium concentration ceq was estimated to be equal to the concentration of reservoir inflow cin at Q = 250 m3/s. It fell in the range of values proved in literature [42,78]. Settling velocity was chosen using equation 2 proposed by [71]. Surface and mass erosion rates (Mse, Mme) were adjusted using a power law [79]. Calibration performance was assessed by the difference between the modelled and observed net volume change considering erosion and sedimentation along the low flow channel in the observation area in the lower reservoir. Figure 6 shows measured and modeled erosion and deposition in the observation area in the lower reservoir.
Bathymetry from monitoring for the test flushing event in 2020 was different from the modeled bathymetry based on 2019 measurements, as is obvious in cross section CS1 (Figure 6a) and the longitudinal profile LS (Figure 6c). As bed levels near the BS needed to be fixed to achieve numerical stability, the model was not able to reproduce the observed erosion in the proximity of BS (around 16,000 m3), as seen in Figure 6. The need for the fixed bed should be seen as local effect having in mind the large model domain of the shallow and wide reservoir modeled in detail with 3D hydrodynamics, which is larger than other 3D reservoir models [37,39,40,41]. Moreover, gates are not included in the model domains of the 3D reservoir models, mentioned above. By using the parameters summarized in Table 3, net volume difference ΔS in the observation area including the 16,000 m3 associated with the fixed bed near the BS, the modeled release ΔS was slightly higher (+ 6563 m3) than observed ΔS, representing a volumetric error of 10%. However, modeled erosion at the upstream end of the observation area was larger and may be underestimated by the bathymetric survey as profiles were not taken at the exact same locations before and after the test drawdown event (Figure 6b). Those unquantifiable measurement errors could reduce the 10% volumetric error. In general, measured and modeled bathymetry changes do match well, especially regarding the evolving flushing channel. This is in accordance with other 3D modeling studies, where flushing channels could also be reproduced [37,39,40,41].
Water level drawdown for the calibration scenario (C-75) is shown in Figure 7a. Modeled drawdown from 284.6 m to 281.0 m is comparable with observations during the simulation period, which ended when gate closure caused the water level to rise. Calibration of the hydrodynamic model RSim-3D against measured water levels at the model inflow (BB) for the test flushing event (C-75) showed relatively small deviations (<0.15 m) between measured and modeled water levels. The agreement indicates proof of a successful 3D hydrodynamic model calibration. The slightly elevated modeled water level can also be attributed to insufficient resolution or outdated bathymetry measurements in the river entering the reservoir.
Modeled suspended sediment volume change ΔS for C-75 was compared with suspended sediment load calculated from sediment transport field measurements during the test flushing event (Figure 7b). The upper boundary of measured suspended sediment concentrations (C-75 obs, max), transferred to sediment load (L), showed agreement with the modeled calibration scenario C-75. By comparing the cumulative reservoir inflow of 5754 m3 against the released sediments at BS and HW, the maximum difference between observation (C-75 obs, max) and the model is 2486 m3, representing an error of only 4.8% to 5.4%, corresponding to the maximum and minimum sediment loads at BS of 46,000 m3 to 52,000 m3.
Modeled sediment volume change ΔS showed a steeper gradient at the end of drawdown flushing due to the abrupt start of mass erosion, whereas the observed sediment load indicated an earlier onset of mass erosion. This effect can be attributed to the fixed bed at the model outlet, where local erosion of deposited sediments is expected during the initial stage of drawdown [34]. Three-dimensional numerical results of bed shear stress at the drawdown cone support this, as critical shear stress values are exceeded much earlier. The need to fix bed levels in parts of the upper reservoir for numerical stability may also contribute to the shallower modeled gradient in ΔS at the beginning of the simulation. Another reason for the lag between simulation and observation may be because bank erosion—as implemented in [38]—is not considered. This could reduce numerical instabilities in the upper part (bifurcated channels in the delta), but on the other hand it increases simulation time and adds further instabilities [38]. Additionally, that only one parameter set for modeling cohesion across the entire reservoir was possible within the model, may also contribute to this issue, as measured critical shear stress values were not uniform in the lower reservoir and may vary even more significantly in the sandier, deltaic region of the upper reservoir. Deposit consolidation, expressed by varying bulk densities, may also contribute to differences in timing of modeled and observed erosion. Nevertheless, the final sediment volume change at the end of the flushing period corresponded well with measured loads.
Due to higher discharges at BS, water level drawdown for 1-250 and 2-250, shown in Figure 7a, indicated a shorter duration in comparison to C-75, although the initial water level was higher. However, the duration for 2-250 was longer than for 1-250 due to the higher volume in the dredged channel (Figure 2b). In the observation area, ΔS was highest for 2-250, although the difference to 1-250 was small with + 2.5% (Figure 7b). When considering the total reservoir, 1-250 was higher than 2-250 (+12%), a result of bed shear stress far below critical shear stress values in the dredged channel (2-250). Considering a drawdown level of 181.0 m, differences in ΔS between the scenarios reached +7% and +33% for 2-250 and 1-250, respectively, when compared to C-75. These relatively small changes may be related to the shorter duration of the scenarios with higher discharges when critical shear stress values are exceeded and cause erosion of the cohesive sediments. This provides indications that the gradual increase in gate openings, as applied for C-75, is more effective than the theoretically constant opening over the whole period.
Similarity with 2D numerical results from Tabios [43], as described in analogy for the monitoring of scenario C-75 (Section 3.1.2), cannot be concluded with certainty. For 250 m3s−1 reservoir inflow and less sluiced discharge (~−30%) distributed over a longer period, the 2D model estimates sediment loads of 47,000 m3 to 53,000 m3. Tabios [43] does not mention the level of drawdown reached by the 2D hydrodynamic model, which—as already described in Section 3.1.2—is an important innovation reached by the application of the 3D hydrodynamic model approach. However, Tabios seems to consider a drawdown flushing event including drawdown over all three stages according to Morris [16]: drawdown, free-flow period while the reservoir is empty (or close to empty), and the refill. Ongoing modeling of the free-flow period (nearly empty reservoir) using the 3D reservoir model would thus indicate a higher erosion potential, which is limited by the flow retreating into the developed flushing channel.
Figure 8 shows erosion differences in the lower reservoir for the higher discharge scenarios (1-250 and 2-250) and lower drawdown level. Figure 8a,d can be compared with Figure 6c given the same drawdown level of 281.0 m. 1-250 predicts larger erosion areas than scenario 2-250 and C-75 (Figure 6c), although magnitudes are smaller.
Comparable findings were achieved for the lower drawdown level (280 m), simulated for 1-250 and 2-250. The deeper channel in Figure 8d is clearly distinguishable when compared to Figure 8b. For both scenarios in Figure 8, lower drawdown level increased erosion near the BS. However, an upstream to downstream erosion progress was detectable for 2-250. The upstream area with the beginning erosion was located immediately downstream of the end of the dredging channel. This increases the chance that the dredging channel is possibly connecting the upper reservoir to the lower reservoir when multiple drawdown events are performed. By simulating a single drawdown flushing event, it cannot be stated with certainty that the initial dredging channel can be transformed to a fully established sluicing channel through the entire reservoir, as depicted in Figure 2c. However, scenarios with higher reservoir inflow might increase the chance due to progressive erosion (upstream to downstream direction) [34]. On the other hand, drawdown flushing is less effective for 2-250 than for 1-250, when the width of the flushed channel in the lower reservoir is considered (Figure 2a,b). Lai [34] defines the ratio between this width and the width of the reservoir as a criterion for reaching a sustainable reservoir capacity. In the case of the shallow and wide Pulangi IV reservoir, this ratio is unfavorable in any case, suggesting that drawdown flushing—combined with dredging—is just one component of a broader approach toward sustainable sediment management. However, for all considered scenarios drawdown was considered effective even though the water level was not lowered below the min OL, thus sustaining continuous power generation during drawdown flushing. Hauer et al. [4] highlight the necessity of a significant (or complete) drawdown, which conflicts with continuous hydropower operation. Drawdown below min OL was not tested in the scenarios considered in this case study, to test the effectiveness of sediment release without interrupting power production.

3.2.2. Sensitivity Analysis

A sensitivity analysis for cohesive model parameters on ΔS was performed for the last 20 min of drawdown flushing, where changes in ΔS (%) were highest due to the highest water level drawdown gradient. ΔS was measured in the observation area in the lower reservoir (Figure 6). The reduction of settling velocity w on average by 80%, using values for hindered settling [42] instead of Equation (2), increased ΔS by 13% for C-75, and decreased ΔS for 1-250 by −5%. Th86e increased ΔS (less net erosion) seems counterintuitive for C-75. However, while erosion volume increased in the flushed channel, sedimentation along the banks of the channel increased to an even greater extent. In Figure 6c, this sedimentation, also mentioned in [13], is clearly discernible for C-75. In contrast, the sedimentation outside the channel was lower for 1-250, as shown in Figure 8a,b, which might be attributed to the higher reservoir inflow. A decrease of ceq by 75% was not sensitive regarding ΔS. As a result, critical shear stress values for surface erosion (τc,se) and mass erosion (τc,me), were identified as the most sensitive adjustment parameters for the cohesive sediment transport model iSed (Table 4).
By setting critical shear stress values to the minimum and maximum values determined during monitoring (Table 2), modeled ΔS changed between −103% and +73%. Sensitivity of critical shear stress values to changes in ΔS is also plotted in Figure 7b, indicating the range of erosion volume achievable by drawdown flushing. As the model allows just one general cohesive parameter set for layers at all depths over the whole reservoir, this method was found suitable to cope with model uncertainties regarding the high variability of critical shear stress values determined by sampling various locations and depth layers. Future improvements to the iSed model code could include the consideration of varying cohesive parameters based on the location and layer depth. Additionally, consolidation could be addressed by accounting for varying bulk densities and porosities.

3.3. Pulangi River Downstream of Reservoir

Results of the 1D sediment transport model HEC-RAS for the old river downstream of the dam between BS and C (Figure 1a) were worked out in Tasser [80].

3.3.1. Calibration and Sensitivity Analysis of the Hydrodynamic Model

Calibration of the hydraulic model downstream of Pulangi reservoir (G) using cross section measurement taken during the test flushing event achieved best results with a Manning coefficient of n = 0.037. The model demonstrated a high degree of accuracy, as indicated by a Nash-Sutcliffe Efficiency (NSE) coefficient of 0.984 and a Sum of Square Errors (SSE) value of 0.41 m2. The mean absolute error between modeled and measured water surface elevation was 16 cm, with an error range between -29 cm and +18 cm. Sensitivity analysis revealed that the model is highly sensitive to geometric variations, particularly in the narrowing of the riverbed, which significantly impacts flow behavior due to the Venturi effect. Due to limited survey data, the riverbed profile was adjusted by increasing its width based on airborne imagery, which improved the model’s performance. Conversely, the model showed low sensitivity to changes in roughness and no influence from the number of discharge classes (13 classes between Q = 200 m3s−1 and 800 m3s−1) or the upstream boundary condition, respectively.
The agreement between the simulated and observed water levels, particularly in the mid-range discharge scenarios, validates the model’s reliability for hydraulic predictions of existing conditions. It was also found to be reliable to use a single Manning coefficient (n) for the entire model, as applied in e.g., [81,82]. This approach was justified by the low sensitivity of the model to variations in roughness, similar channel characteristics along the length of the channel, and the lack of sufficiently detailed data to support spatially variable roughness coefficients.

3.3.2. Plausibility Check and Sensitivity Analysis of the Sediment Transport Model

A plausibility check after Dahl et al. [76], applied for the test flushing event (2020) with a discharge of Q = 75 m3s−1, resulted in the selection of two sediment transport formulas—Toffaleti [83] and Laursen [84]—which exhibited numerical stability and gave plausible results. Other formulas, such as Meyer-Peter & Müller [85], Yang [86], Wilcock-Crowe [87] and Engelund & Hansen [88] were disregarded due to their limited applicability for fine sediments flushed from the reservoir. The active layer concept was selected as sorting method because of its stability and the fine sediments. Following the suggestion by Tritthart et al. [89], the initial value of the active layer depth dex, typically ranging from 1 to 4 × d90, was selected as 4 × d90, resulting in 0.364 m. Based on the plausibility check, a sensitivity analysis was performed for the test flushing event including two sediment transport formulas and five fall-velocity methods. The 28,000 t of cumulative sediments flushed during the event, derived as a mean value from the monitoring campaign, were mostly transported through the model reach. Deposition varied depending on the transport formula used, ranging between 13% (Toffaleti [83]) and 5% (Laursen [84]) of the sediments discharged from the reservoir. The Toffaleti formula led to a more continuous deposition over the reach whereas the Laursen equation indicated deposition located in pools. The selection of fall velocity method was not sensitive with regard to the fraction of deposition in the reach. A further sensitivity analysis resulted in a high sensitivity to cohesion assumptions. The difference in total depositions along the reach between enabled and disabled cohesion was 6.3% and 0.7% for the Toffaleti and Laursen equations, respectively. On the other hand, the critical shear stress values τc for cohesion, the variation of the roughness parameter n and the active layer depth dex were not found to be sensitive when modeling the test flushing event in the Pulangi River downstream of the reservoir. The model resulted in distributed deposits in the upper reach (up to 0.03 m for Toffaleti) or locally in pools (up to 0.22 m for Laursen). Deposits consisted of fine and medium sand, whereas finer sediments were transported through the reach completely. The generally low sedimentation rates do not suggest that flushing with clear water after filling is necessary for the studied, as indicated to be a possibility in Morris [13], though it could be required for the release of greater sediment volumes and when considering the entire river below the dam, which has a declining bed slope. A long-term monitoring of downstream impacts by sedimentation, as well as the resulting ecological impacts is highly recommended [4,8]. Additionally, since drawdown flushing is not considered as environmentally friendly as sluicing [13], it can be considered as a transitional phase toward the development of a sustainable sluicing channel (cf. Figure 2c).
Detailed monitoring as a basis for model calibration should be performed in the future. A more differentiated variation of roughness, given the high sensitivity of roughness parameters, would lead to more reliable hydrodynamic results such as in Dahl et al. [76]. Concerning the 1D sediment transport model, the lack of calibration and validation data is of utmost importance. The provided results, based on the plausibility check and sensitivity analysis [76], can only offer an initial assessment, which should be supported by calibration data from field monitoring. Other studies on sediment transport [82,90,91] suggest that the applied 1D model can deliver highly accurate results regarding sediment transport when monitoring data are available.

3.3.3. Scouring of Dredged Material from a Containment Structure (Scenario D)

At the position (G) selected for a potential dredged sediment containment area, 130 m downstream of the dam, elevated shear stress between 10 and 20 Nm−2 was modeled due to the narrower channel with a width of 52.0 m at the upstream end to 16.5 m at the downstream end of the containment area. A discharge of Q = 200 m3s−1 was capable of completely eroding the contained material and transporting it downstream (Figure 9) within 72 h. 95% (Laursen) and 89% (Toffaleti) of the eroded material of the containment area could be transported through the modeled reach, resulting in low volumes of fine and coarse sand deposits. Large areas of deposits did not occur along the study reach.
Sensitivity was evaluated for parameters Q, τc,se τc,me, n, and dex with respect to the duration of the erosion in the containment area. In general, parameters were sensitive to shorter durations (Table 5).
After 12 h, 55% of the material was eroded for a discharge of Q = 200 m3s−1. By increasing discharge Q, erosion volume in the containment area is enhanced, following a quadratic relationship (ΔS = 0.0054Q2 − 7.1139Q − 2052.1; R2 = 0.9981). This yields greater changes in erosion (ΔS) when lower discharge levels are adjusted. Higher discharges led to similar erosion rates ranging from 72% at Q = 500 m3s−1 to 74% at Q = 700 m3s−1. After 24 h, erosion rates were almost independent of Q, ranging between 88% and 91%. Thus, sensitivity to Q over the tested discharges ranged between 19% and 1.9% for 12- and 72-h simulation periods, respectively. The sensitivity of bed roughness ranged between 17.9% and 1.3%. Highest sensitivity on the erosion of dredged sediments was found for the active layer depth dex, ranging between 33% and 4.9%. Larger dex led to acceleration of erosion within the first phase (<48 h). In contrast to the previous parameters, the variation of critical shear stress values ranging between measured values, evaluated from reservoir samples during monitoring (Table 2), indicated a maximum range of only 3.2% after 12 h regarding the eroded fraction.
For reservoir flushing and scouring of dredged material from a containment structure (scenario D), extensive monitoring of downstream impacts regarding sedimentation, water quality and ecological impacts is highly recommended in the future, such as in [8]. Additionally, using dredged material from the channel in scenario 2-250 (Figure 2b), complete disposal of the dredged channel volume into the river downstream would represent about 360 times more sediment than simulated here. Dredging in combination with drawdown flushing could contribute to a sustainable pass-through strategy [13]. It is possible that repetitive drawdown events could reduce the amount of dredging. However, this is heavily dependent on the sand content in the upper reservoir.

4. Conclusions

Effective sediment management in shallow and wide reservoirs such as Pulangi IV requires a combination of measures for sustainable long-term management. Long-term sediment and ecological monitoring combined with scenario-based numerical modeling can support decision-making to preserve hydropower generation while minimizing environmental impacts.
Suspended sediment concentration during drawdown flushing is high and requires ecological and morphological monitoring, and drawdown rates and durations should be adjusted considering downstream limits in sediment concentration and river morphological impacts. In contrast, suspended sediment concentration during drawdown sluicing would typically not exceed the natural spectrum of floods, when conducted during flood inflow events.
The 3D reservoir model—a model larger than those used for most comparable studies—for the shallow and wide reservoir (surface area of 11 km2) provided detailed results for drawdown flushing in the lower reservoir area, with the modeling of cohesive sediment properties found to be crucial. Drawdown was combined with a dredged flushing channel and a dike in the upper reservoir to better channel flows during drawdown sluicing of floods. Sensitivity analysis allowed the assessment of variability, based on extensive sampling and critical shear stress tests. The model was found to align well with bathymetric measurements. Performing sufficient water level drawdown was crucial for effective erosion, but in the tested limited drawdown scenarios, hydropower generation continued uninterrupted for this detailed case study. A gradual opening of the gates was more effective than a theoretically time-invariant (constant) opening. Downstream sedimentation from flushed and dredged sediment discharge was low, though calibration and validation data could be improved by long term monitoring.
Combining flushing with dredging in the upper reservoir suggests the potential for establishing a flushing channel which, with repeated operations, especially during elevated discharge, could enable future sustainable drawdown sluicing during floods without exceeding natural SSC levels. On a larger scale, downstream sediment and aquatic ecological impacts must be addressed to reestablish the sediment balance from rivers to oceans. This effort should also include measures to reduce sediment yield caused by land conversion and climate change. These findings can inform sediment management practices in other reservoirs with similar challenges.

Author Contributions

Conceptualization, M.G., M.T., S.P., G.M., N.E., P.K. and H.H.; methodology, M.G., M.T., S.P., G.M., P.L., G.IIIQ.T., N.E. and H.H.; software, M.G. and M.T.; validation, M.T., G.M. and G.IIIQ.T.; formal analysis, M.G., S.P. and P.L.; investigation, M.G., M.T., S.P., P.L., G.IIIQ.T. and N.E.; resources, G.IIIQ.T., P.K. and H.H.; data curation, M.G., S.P., P.L., G.IIIQ.T. and N.E.; writing—original draft preparation, M.G., M.T., S.P. and P.L.; writing—review and editing, G.M., G.IIIQ.T., N.E., P.K. and H.H.; visualization, M.G., S.P. and P.L.; supervision, M.T., G.IIIQ.T., N.E., P.K. and H.H.; project administration, G.IIIQ.T., N.E. and P.K.; funding acquisition, H.H. All authors have read and agreed to the published version of the manuscript.

Funding

This research was funded by the Austrian Federal Ministry of Finance through ESMAP of the World Bank (Washington D.C., U.S.), initiated by Habersack, H.

Data Availability Statement

The data presented in this study are available on request from the corresponding author. Restrictions apply to the availability of the data obtained from NPC, which may only be passed over with the permission of NPC.

Acknowledgments

The authors thank Martin Hinterleitner and the team from the University of the Philippines Diliman and the Central Minadao University (CMU) for preparation and monitoring of the test flushing event in January 2020, the World Bank team for support and safe travel, the operator of Pulangi IV hydropower plant NPC for providing data and support, Marina Golja for supporting laboratory analyses and Theo Tasser for supporting numerical modeling.

Conflicts of Interest

Author G.M. was employed by the company GLM Engineering PSC. Author P.L. was employed by the company Vienna Model Basin Ltd. The remaining authors declare that the research was conducted in the absence of any commercial or financial relationships that could be construed as potential conflicts of interest. The funders had no role in the design of the study; in the collection, analyses, or interpretation of data; in the writing of the manuscript; or in the decision to publish the results.

Abbreviations

The following abbreviations are used in this manuscript:
NPCNational Power Cooperation
RCPRepresentative concentration pathway
SSCSuspended sediment concentration
LLOLow-level outlets
BSBottom sluice gate
HWHeadworks
OLOperation level
SPSurge pond
PHPower house
CConfluence
BBBusco bridge
GGorge
CBCrystal bridge
DEMDigital Elevation Model
TINTriangulated Irregular Network
NSENash-Sutcliffe Efficiency
SSESum of Square Errors
RCRating curve
LSLong section

References

  1. Syvitski, J.P.M.; Vörösmarty, C.J.; Kettner, A.J.; Green, P. Impact of Humans on the Flux of Terrestrial Sediment to the Global Coastal Ocean. Science 2005, 308, 376–380. [Google Scholar] [CrossRef]
  2. Annandale, G.W.; Randle, T.J.; Langendoen, E.J.; Hotchkiss, R.H. Reservoir sedimentation management: A sustainable development challenge. Hydrolink 2018, 3, 72–75. [Google Scholar]
  3. International Commission on Large Dams (ICOLD). Sedimentation and Sustainable Use of Reservoirs and River Systems [Draft Bulletin 147]. International Commission on Large Dams. 2009. Available online: https://www.icoldchile.cl/boletines/147.pdf (accessed on 28 March 2025).
  4. Hauer, C.; Wagner, B.; Aigner, J.; Holzapfel, P.; Flödl, P.; Liedermann, M.; Tritthart, M.; Sindelar, C.; Pulg, U.; Klösch, M.; et al. State of the art, shortcomings and future challenges for a sustainable sediment management in hydropower: A review. Renew. Sustain. Energy Rev. 2018, 98, 40–55. [Google Scholar] [CrossRef]
  5. Randle, T.J.; Morris, G.L.; Tullos, D.D.; Weirich, F.H.; Kondolf, G.M.; Moriasi, D.N.; Annandale, G.W.; Fripp, J.; Minear, J.T.; Wegner, D.L. Sustaining United States reservoir storage capacity: Need for a new paradigm. J. Hydrol. 2021, 602, 126686. [Google Scholar] [CrossRef]
  6. Holubova, K.; Capekova, Z.; Szolgay, J. Impact of Hydropower Schemes on Bedload Regime and Channel Morphology of the Danube River. In Proceedings of the Second International Conference on Fluvial Hydraulics, Naples, Italy, 23–25 June 2004. [Google Scholar]
  7. Kondolf, G.M. PROFILE: Hungry water: Effects of dams and gravel mining on river channels. Environ. Manag. 1997, 21, 533–551. [Google Scholar] [CrossRef]
  8. Hauer, C.; Holzapfel, P.; Flödl, P.; Wagner, B.; Graf, W.; Leitner, P.; Haimann, M.; Holzer, G.; Haun, S.; Habersack, H.; et al. Controlled Reservoir Drawdown—Challenges for Sediment Management and Integrative Monitoring: An Austrian Case Study—Part B: Local Scale. Water 2020, 12, 1055. [Google Scholar] [CrossRef]
  9. Espa, P.; Batalla, R.J.; Brignoli, M.L.; Crosa, G.; Gentili, G.; Quadroni, S.; Bryhn, A.C. Tackling reservoir siltation by controlled sediment flushing: Impact on downstream fauna and related management issues. PLoS ONE 2019, 14, e0218822. [Google Scholar] [CrossRef]
  10. Kemp, P.; Sear, D.; Collins, A.; Naden, P.; Jones, I. The impacts of fine sediment on riverine fish. Hydrol. Process. 2011, 25, 1800–1821. [Google Scholar] [CrossRef]
  11. Sear, D.A.; Frostick, L.B.; Rollinson, G.; Lisle, T.E. The significance and mechanics of fine-sediment infiltration and accumulation in gravel spawning beds. In Salmonid Spawning Habitat in Rivers: Physical Controls, Biological Responses, and Approaches to Remediation, Proceedings of the Symposium 65, Bethesda, MD, USA, 11–13 September 2008; Sear, D.A., DeVries, P., Eds.; American Fisheries Society: Bethesda, MD, USA, 2008; pp. 149–174. [Google Scholar]
  12. Okumura, H.; Sumi, T. Reservoir Sedimentation Management in Hydropower Plant Regarding Flood Risk and Loss of Power Generation. In Proceedings of the International Symposium on Dams for a Changing World, the 80th Annual Meeting of ICOLD, Kyoto, Japan, 1–6 June 2013. [Google Scholar]
  13. Morris, G.L. Classification of Management Alternatives to Combat Reservoir Sedimentation. Water 2020, 12, 861. [Google Scholar] [CrossRef]
  14. Dufresne, M.; Dewals, B.; Erpicum, S.; Archambeau, P.; Pirotton, M. Flow patterns and sediment deposition in rectangular shallow reservoirs. Water Environ. J. 2012, 26, 504–510. [Google Scholar] [CrossRef]
  15. Annandale, G.W.; Morris, G.L.; Karki, P. Extending the Life of Reservoirs: Sustainable Sediment Management for Dams and Run-of-River Hydropower; World Bank Group: Washington, DC, USA, 2016; ISBN 978-1-4648-0838-8. [Google Scholar]
  16. Morris, G.L.; Fan, J. Reservoir Sedimentation Handbook; McGraw-Hill Book Co.: New York, NY, USA, 1998. [Google Scholar]
  17. Yasarer, L.M.W.; Sturm, B.S.M. Potential impacts of climate change on reservoir services and management approaches. Lake Reserv. Manag. 2016, 32, 13–26. [Google Scholar] [CrossRef]
  18. Sirikaew, U.; Seeboonruang, U.; Tanachaichoksirikun, P.; Wattanasetpong, J.; Chulkaivalsucharit, V.; Chen, W. Impact of Climate Change on Soil Erosion in the Lam Phra Phloeng Watershed. Water 2020, 12, 3527. [Google Scholar] [CrossRef]
  19. Mouris, K.; Schwindt, S.; Pesci, M.H.; Wieprecht, S.; Haun, S. An interdisciplinary model chain quantifies the footprint of global change on reservoir sedimentation. Sci. Rep. 2023, 13, 20160. [Google Scholar] [CrossRef]
  20. Wagner, B.; Hauer, C.; Schoder, A.; Habersack, H. Hydropower Technologies. In Encyclopedia of Sustainable Technologies, 2nd ed.; Elsevier: Amsterdam, The Netherlands, 2024; Volume 1–4. [Google Scholar] [CrossRef]
  21. Anderson, D.; Moggridge, H.; Warren, P.; Shucksmith, J. The impacts of “run-of-river” hydropower on the physical and ecological condition of rivers. Water Environ. J. 2015, 29, 268–276. [Google Scholar] [CrossRef]
  22. National Power Corporation. Pulangi IV Hydroelectric Plant. Available online: https://www.napocor.gov.ph/?s=Pulangi+IV (accessed on 9 May 2025).
  23. Eftymiou, N. (The World Bank, Washington, DC, USA); Habersack, H. (BOKU University, Vienna, Austria). Sediment Management Study for Pulangi IV Reservoir. Technical Report on Rapid Screening of Effective Sediment Management Strategies. The World Bank: Washington, DC, USA, 2020. (Unpublished work). [Google Scholar]
  24. Republic of the Philippines; National Power Corporation. Pulangi River Development, Maramag Hydroelectric Project, Feasibility Report, Volume III, Appendix A: Hydrology; Sofrelec: Paris, France, 1978.
  25. Brune, G.M. Trap Efficiency of Reservoirs. Trans. Am. Geophys. Union. 1953, 34, 407–418. [Google Scholar] [CrossRef]
  26. Kondolf, G.M.; Gao, Y.; Annandale, G.W.; Morris, G.L.; Jiang, E.; Zhang, J.; Cao, Y.; Carling, P.; Fu, K.; Guo, Q.; et al. Sustainable sediment management in reservoirs and regulated rivers: Experiences from five continents. Earth’s Future 2014, 2, 256–280. [Google Scholar] [CrossRef]
  27. Sumi, T.; Kantoush, S.; Esmaeili, T.; Ock, G. Reservoir sediment flushing and replenishment below dams: Insights from Japanese case studies. In Gravel-Bed Rivers; Tsutsumi, D., Laronne, J.B., Eds.; John Wiley & Sons Ltd.: Hoboken, NJ, USA, 2017; pp. 385–414. [Google Scholar] [CrossRef]
  28. Wagner, B.; Habersack, H.; Hauer, C.; Schoder, A. Sedimentmanagement bei Wasserkraftwerken. Wasserkraft 2013, 39, 10–11. [Google Scholar]
  29. Schleiss, A.; Oehy, C. Verlandung von Stauseen und Nachhaltigkeit. Wasser. Energ. Luft. 2002, 94, 227–234. [Google Scholar] [CrossRef]
  30. Panondi, W.; Izumi, N. Climate Change Impact on the Hydrologic Regimes and Sediment Yield of Pulangi River Basin (PRB) for Watershed Sustainability. Sustainability 2021, 13, 9041. [Google Scholar] [CrossRef]
  31. Lee, C.; Foster, G. Assessing the potential of reservoir outflow management to reduce sedimentation using continuous turbidity monitoring and reservoir modelling: Continuous turbidity to assess reservoir sedimentation. Hydrol. Process. 2013, 27, 1426–1439. [Google Scholar] [CrossRef]
  32. CIGB; ICOLD. Sedimentation and Sustainable Use of Reservoirs and River Systems [Sédimentation et Utilisation Durable des Réservoirs et Systèmes Fluviaux]; CRC Press; Balkema, Taylor & Francis Group: Leiden, The Netherlands, 2007; ISBN 978-1-032-32727-3. [Google Scholar]
  33. Sumi, T. Evaluation of Efficiency of Reservoir Sediment Flushing in Kurobe River. In Proceedings of the 4th International Conference on Scour and Erosion (ICSE-4), Tokyo, Japan, 5–7 November 2008; pp. 608–613. [Google Scholar]
  34. Lai, Y.G.; Huang, J.; Greimann, B.P. Hydraulic flushing of sediment in reservoirs: Best practices of numerical modeling. Fluids 2024, 9, 38. [Google Scholar] [CrossRef]
  35. Kantoush, S.A.; Schleiss, A.J. Channel formation during flushing of large shallow reservoirs with different geometries. Environ. Technol. 2009, 30, 855–863. [Google Scholar] [CrossRef]
  36. Efthymiou, N.P.; Palt, S.; Annandale, G.W.; Karki, P. Reservoir Conservation Model: RESCON 2 Beta, Economic and Engineering Evaluation of Alternative Sediment Management Strategies; The World Bank: Washington, DC, USA, 2017. [Google Scholar]
  37. Haun, S.; Olsen, N.R.B. Three-dimensional numerical modelling of the flushing process of the Kali Gandaki hydropower reservoir. Lakes Reserv. Res. Manag. 2012, 17, 25–33. [Google Scholar] [CrossRef]
  38. Olsen, N.R.B.; Haun, S. Numerical Modelling of Bank Failures during Reservoir Draw-Down. In Proceedings of the River Flow 2018—E3S Web of Conferences, Les Ulis, France, 5–8 September 2018; EDP Sciences: Les Ulis, France, 2018; Volume 40, p. 03001. [Google Scholar] [CrossRef]
  39. Saam, L.; Mouris, K.; Wieprecht, S.; Haun, S. Three-dimensional numerical modelling of reservoir flushing to obtain long-term sediment equilibrium. In Proceedings of the 38th IAHR World Congress, Panama City, Panama, 1–6 September 2019. [Google Scholar]
  40. Esmaeili, T.; Sumi, T.; Kantoush, S.A.; Kubota, Y.; Haun, S. Numerical study on flushing channel evolution, case study of Dashidaira reservoir, Kurobe River. J. Jpn. Soc. Civ. Eng. 2015, 71, 115–120. [Google Scholar] [CrossRef]
  41. Esmaeili, T.; Sumi, T.; Kantoush, S.A.; Kubota, Y.; Haun, S.; Ruther, N. Three-dimensional numerical study of free-flow sediment flushing to increase the flushing efficiency: A case-study reservoir in Japan. Water 2017, 9, 900. [Google Scholar] [CrossRef]
  42. U.S. Department of the Interior. Cohesive Sediment Transport. In Erosion and Sedimentation Manual; U.S. Department of the Interior: Denver, CO, USA, 2006. [Google Scholar]
  43. Tabios, G.Q., III. Reservoir Sedimentation Studies. In Water Resources Systems of the Philippines: Modeling Studies; Singh, V.P., Ed.; World Water Resources; Springer: Cham, Switzerland, 2020; Volume 4, pp. 165–210. ISBN 978-3-030-25400-1. [Google Scholar]
  44. Zhao, D.H.; Shen, H.W.; Tabios, G.Q.; Lai, J.S.; Tan, W.Y. Finite-Volume Two-Dimensional Unsteady-Flow Model for River Basins. J. Hydraul. Eng. 1994, 120, 863–883. [Google Scholar] [CrossRef]
  45. Glas, M.; Pessenlehner, S.; Lichtneger, P.; Tritthart, M.; Morris, G.L.; Tabios, G.; Efthymiou, N.; Karki, P.; Habersack, H. Physical and Numerical Sediment Modelling at the Pulangi Reservoir. In Proceedings of the Vienna Water Conferences, Vienna, Austria, 21–25 August 2023. [Google Scholar]
  46. Morris, G. (GLM Engineering PSC, San Juan, PR, USA); Efthymiou, N. (The World Bank, Washington, DC, USA); Habersack, H. (BOKU University, Vienna, Austria). Global Sediment Management Study: Sediment Management Study—Pulangi IV Hydropower Reservoir, Mindanao, Philippines. Executive Summary. 2021. (Unpublished work). [Google Scholar]
  47. Paguntalan, R.B. Water Resources Utilization in the Upper Pulangi River Basin, Bukidnon, Philippines. Ph.D. Thesis, Central Luzon State University, Science City of Muñoz, Nueva Ecija, Philippines, 2003. [Google Scholar]
  48. CMA Geoservices & Construction Corporation (CMA) (CMA Geoservices & Construction Corporation, Maramag, Bukidnon, Philippines). Final Report on the Engineering Preparatory Works for the Dredging/Desilting of Pulangi IV HE Plant Complex, 2002. (Unpublished work).
  49. Atkinson, E. (HR Wallingford, Wallingford, UK). The Feasibility of Flushing Sediment from Reservoirs, 1996. (Unpublished work).
  50. ASF DAAC. ALOS PALSAR Radiometric Terrain Corrected High Resolution, Includes Material JAXA/METI 2007. Available online: https://search.asf.alaska.edu/#/ (accessed on 19 March 2020).
  51. Herschy, R. The velocity-area method. Flow. Meas. Instrum. 1993, 4, 7–10. [Google Scholar] [CrossRef]
  52. DVWK. Schwebstoffmessungen, Regeln zur Wasserwirtschaft Nr. 125/1986; Kommissionsvertrieb Verlag Paul Parey: Hamburg/Berlin, Germany, 1986. [Google Scholar]
  53. DIN 38 409 Part 2. Deutsche Einheitsverfahren zur Wasser-, Abwasser- und Schlammuntersuchung; Summarische Wirkungs- und Stoffkenngrößen (Gruppe H); Bestimmung des Gesamttrockenrückstandes, des Filtrattrockenrückstandes und des Glührückstandes (H 1). Available online: https://www.din.de/de/mitwirken/normenausschuesse/naw/wdc-beuth:din21:1334102 (accessed on 25 February 2020).
  54. EN ISO 17892-3; Geotechnische Erkundung und Untersuchung—Laborversuche an Bodenproben—Teil 3: Bestimmung der Korndichte. Austrian Standards International: Vienna, Austria, 2016. Available online: https://www.austrian-standards.at/de/shop/onorm-en-iso-17892-3-2016-08-15~p2244129 (accessed on 25 February 2020).
  55. Lichtneger, P.; Golja, M.; Schobert, J.; Sindelar, C.; Habersack, H.; Hauer, C. Critical Shear Stresses of Reservoir Sediments Determined from Bore Core Samples Using CD-SED Hydraulic Test Channel. BOKU University: Vienna, Austria, 2026; manuscript in preparation. [Google Scholar]
  56. Lichtneger, P. (The World Bank, Washington, DC, USA); Habersack, H. (BOKU University Vienna, Austria); Morris, G. (GLM Engineering PSC, San Juan, PR, USA); Efthymiou, N. (The World Bank, Washington, DC, USA); Karki, P. (The World Bank, Washington, DC, USA). Global Sediment Management Study: Sediment Management Study—Pulangi IV Hydropower Reservoir, Mindanao, Philippines. Physical Model Report, 2021. (Unpublished work).
  57. Tritthart, M.; Schober, B.; Habersack, H. Non-Uniformity and Layering in Sediment Transport Modelling 1: Flume Simulations. J. Hydraul. Res. 2011, 49, 325–334. [Google Scholar] [CrossRef]
  58. Tritthart, M.; Liedermann, M.; Schober, B.; Habersack, H. Non-Uniformity and Layering in Sediment Transport Modelling 2: River Application. J. Hydraul. Res. 2011, 49, 335–344. [Google Scholar] [CrossRef]
  59. Tritthart, M. Three-dimensional numerical modelling of turbulent river flow using polyhedral finite volumes. In Wiener Mitteilungen; Vienna University of Technology: Vienna, Austria, 2005; Volume 193. [Google Scholar]
  60. Voronoi, G. Nouvelles Applications des Paramètres Continus à la Théorie des Formes Quadratiques, Deuxième Mémoire, Recherches sur les Paralléloèdres Primitifs. J. Reine Angew. Math. 1908, 134, 198–287. [Google Scholar] [CrossRef]
  61. Launder, B.E.; Spalding, D.B. The Numerical Computation of Turbulent Flows. Comput. Methods Appl. Mech. Eng. 1974, 3, 269–289. [Google Scholar] [CrossRef]
  62. Tritthart, M.; Gutknecht, D. Three-Dimensional Simulation of Free-Surface Flows Using Polyhedral Finite Volumes. Eng. Appl. Comput. Fluid Mech. 2007, 1, 1–14. [Google Scholar] [CrossRef]
  63. Tritthart, M.; Gutknecht, D. 3-D Computation of Flood Processes in Sharp River Bends. Proc. Inst. Civ. Eng. Water Manag. 2007, 160, 233–247. [Google Scholar] [CrossRef]
  64. Glas, M.; Glock, K.; Tritthart, M.; Liedermann, M.; Habersack, H. Hydrodynamic and Morphodynamic Sensitivity of a River’s Main Channel to Groyne Geometry. J. Hydraul. Res. 2018, 56, 714–726. [Google Scholar] [CrossRef]
  65. Prenner, D. Application of 3D Hydrodynamic and Sediment Transport Models for Reservoir Management. Master’s Thesis, BOKU University, Vienna, Austria, 2015. [Google Scholar]
  66. Kessler, C. Variantenuntersuchung der Verlandungsprozesse von Speicherseen der Vorarlberger Illwerke Basierend Auf Numerischer Modellierung. Master’s Thesis, BOKU University, Vienna, Austria, 2013. [Google Scholar]
  67. Glas, M.; Tritthart, M.; Zens, B.; Keckeis, H.; Lechner, A.; Kaminskas, T.; Habersack, H. Modelling the Dispersal of Riverine Fish Larvae: From a Raster-Based Analysis of Movement Patterns within a Racetrack Flume to a Rheoreaction-Based Correlated Random Walk (RCRW) Model Approach. Can. J. Fish. Aquat. Sci. 2017, 74, 1474–1489. [Google Scholar] [CrossRef]
  68. Farhadi, A.; Mayrhofer, A.; Tritthart, M.; Glas, M.; Habersack, H. Accuracy and Comparison of Standard kk-ϵϵ with Two Variants of k-ω Turbulence Models in Fluvial Applications. Eng. Appl. Comput. Fluid Mech. 2018, 12, 216–235. [Google Scholar] [CrossRef]
  69. Haimann, M.; Hauer, C.; Tritthart, M.; Prenner, D.; Leitner, P.; Moog, O.; Habersack, H. Monitoring and Modelling Concept for Ecological Optimized Harbour Dredging and Fine Sediment Disposal in Large Rivers. Hydrobiologia 2018, 814, 89–107. [Google Scholar] [CrossRef]
  70. Tritthart, M.; Haimann, M.; Habersack, H.; Hauer, C. Spatio-temporal variability of suspended sediments in rivers and ecological implications of reservoir flushing operations. River Res. Applic. 2019, 35, 918–931. [Google Scholar] [CrossRef]
  71. Krone, R.B. Flume Studies of Transport of Sediment in Estuarial Shoaling Processes; Technical Report; Hydraulic Engineering and Sanitary Engineering Research Laboratory, University of California: Berkeley, CA, USA, 1962. [Google Scholar]
  72. Partheniades, E. Erosion and Deposition of Cohesive Soils. J. Hydraul. Div. ASCE 1965, 91, 105–139. [Google Scholar] [CrossRef]
  73. Brunner, G.W. HEC-RAS: River Analysis System: Hydraulic Reference Manual, version 5.0; U.S. Army Corps of Engineers, Hydrologic Engineering Center (HEC): Davis, CA, USA, 2016.
  74. Vienna Scientific Cluster (VSC4). Available online: https://vsc.ac.at/home/ (accessed on 9 February 2025).
  75. Pasiok, R.; Dębek, L. RiverGIS. Available online: http://rivergis.com/ (accessed on 20 March 2020).
  76. Dahl, T.A.; Heath, R.E.; Gibson, S.A.; Nygaard, C.J. HEC-RAS Unsteady Flow and Sediment Model of the Mississippi River: Tarbert Landing to the Gulf; MRGP Report No. 25; U.S. Army Corps of Engineers, Mississippi Valley Division & Engineer Research and Development Center: Vicksburg, MS, USA, 2018.
  77. Lara, J.M.; Pemberton, E.L. Initial Unit-Weight of Deposited Sediments. In Proceedings of the Federal Inter-Agency Sedimentation Conference, Jackson, MS, USA, 23 January 23–1 February 1963; U.S.D.A.: Washington, DC, USA, 1963; p. 28. [Google Scholar]
  78. Liu, J.; Shen, Y.; Wang, X. Flocculation Properties of Cohesive Fine-Grained Sediment in the Three Gorges Reservoir under Variable Turbulent Shear. J. Mt. Sci. 2022, 19, 2286–2296. [Google Scholar] [CrossRef]
  79. Ternat, F.; Boyer, P.; Anselmet, F.; Amielh, M. Erosion Threshold of Saturated Natural Cohesive Sediments: Modeling and Experiments. Water Resour. Res. 2008, 44, W11434. [Google Scholar] [CrossRef]
  80. Tasser, T. Morphodynamische Modellierung der Auswirkungen von Stauraummanagementmaßnahmen im Pulangi Fluss, Philippinen. Master’s Thesis, BOKU University, Vienna, Austria, 2020. [Google Scholar]
  81. Berghout, A.; Meddi, M. Sediment Transport Modelling in Wadi Chemora during Flood Flow Events. J. Water Land. Dev. 2016, 31, 23–31. [Google Scholar] [CrossRef]
  82. Tarar, Z.R.; Ahmad, S.R.; Ahmad, I.; Khan, Z.M.; Washakh, R.M.A.; Ateeq-Ur-Rehman, S.; Bui, M.D. Effect of Sediment Load Boundary Conditions in Predicting Sediment Delta of Tarbela Reservoir in Pakistan. Water 2019, 11, 1716. [Google Scholar] [CrossRef]
  83. Toffaleti, F.B. A Procedure for Computation of Total River Sand Discharge and Detailed Distribution, Bed to Surface; Technical Report No. 5; Committee on Channel Stabilization, U.S. Army Corps of Engineers: Washington, DC, USA, 1968.
  84. Laursen, E.M. Total Sediment Load of Streams. J. Hydraul. Div. Am. Soc. Civ. Eng. 1958, 84, 1530-1–1530-36. [Google Scholar] [CrossRef]
  85. Meyer-Peter, E.; Müller, R. Formulas for Bedload Transport. In Proceedings of the 2nd IAHR Congress, Stockholm, Sweden, 7–9 June 1948. [Google Scholar]
  86. Yang, C.T. Incipient Motion and Sediment Transport. J. Hydraul. Div. Am. Soc. Civ. Eng. 1973, 99, 1679–1704. [Google Scholar] [CrossRef]
  87. Wilcock, P.R.; Crowe, J.C. Surface-Based Transport Model for Mixed-Size Sediment. J. Hydraul. Eng. 2003, 129, 120–128. [Google Scholar] [CrossRef]
  88. Engelund, F.; Hansen, E. A Monograph on Sediment Transport in Alluvial Streams; Technical University of Denmark: Copenhagen, Denmark, 1967; p. 63. [Google Scholar]
  89. Tritthart, M.; Liedermann, M.; Klösch, M.; Habersack, H. Innovationen in der Modellierung von Sedimenttransport und Morphodynamik basierend auf dem Simulationsmodell iSed. Osterr. Wasser-Abfallwirtsch. 2012, 64, 544–552. [Google Scholar] [CrossRef]
  90. Mohammad, M.E.; Al-Ansari, N.; Issa, I.E.; Knutsson, S. Sediment in Mosul Dam reservoir using the HEC-RAS model. Lakes Reserv. Res. Manag. 2016, 21, 235–244. [Google Scholar] [CrossRef]
  91. Mustafa, A.S.; Sulaiman, S.O.; Al-Alwani, K.M. Application of HEC-RAS model to predict sediment transport for Euphrates River from Haditha to Heet 2016. Al-Nahrain J. Eng. Sci. 2017, 20, 570–577. [Google Scholar]
Figure 1. Overview (a) and long section (b) of the Pulangi reservoir. Arrows indicate flow direction. Relevant sites (blue text): bottom sluice gate (BS), headworks (HW), surge pond (SP), powerhouse (PH), confluence (C). Measurement sites (red text): Busco Bridge (BB), gorge (G), Crystal Bridge (CB). Reservoir samples taken during the monitoring in 2020 are marked with red points (characteristic samples P3, P5 and P11 are labeled), and the bathymetric observation area in the lower reservoir is marked with a red dashed line. Pictures (Pessenlehner, S.) show the reservoir, BS and the old river downstream of the dam incised in rock (c).
Figure 1. Overview (a) and long section (b) of the Pulangi reservoir. Arrows indicate flow direction. Relevant sites (blue text): bottom sluice gate (BS), headworks (HW), surge pond (SP), powerhouse (PH), confluence (C). Measurement sites (red text): Busco Bridge (BB), gorge (G), Crystal Bridge (CB). Reservoir samples taken during the monitoring in 2020 are marked with red points (characteristic samples P3, P5 and P11 are labeled), and the bathymetric observation area in the lower reservoir is marked with a red dashed line. Pictures (Pessenlehner, S.) show the reservoir, BS and the old river downstream of the dam incised in rock (c).
Water 17 02514 g001
Figure 2. Topographic maps for investigated scenarios: (a) Digital Elevation Model (DEM) showing the existing bathymetry (2019) of Pulangi IV reservoir used for scenario C-75 and 1-250; (b) DEM for scenario 2-250 includes a dredged flushing channel in the upper reservoir with a dike (red line) on the orographic right-hand side; (c) DEM for a fully established flushing channel with a dike on the orographic right-hand side (not modeled). Dashed blue lines show the beachline for reservoir water level 285.5 m (max OL) Inflow and outflow boundaries (BB, BS) are indicated with green lines.
Figure 2. Topographic maps for investigated scenarios: (a) Digital Elevation Model (DEM) showing the existing bathymetry (2019) of Pulangi IV reservoir used for scenario C-75 and 1-250; (b) DEM for scenario 2-250 includes a dredged flushing channel in the upper reservoir with a dike (red line) on the orographic right-hand side; (c) DEM for a fully established flushing channel with a dike on the orographic right-hand side (not modeled). Dashed blue lines show the beachline for reservoir water level 285.5 m (max OL) Inflow and outflow boundaries (BB, BS) are indicated with green lines.
Water 17 02514 g002
Figure 3. Critical shear stress test rig [56] at BOKU University.
Figure 3. Critical shear stress test rig [56] at BOKU University.
Water 17 02514 g003
Figure 4. Grain size distribution analysis. Pre-dam analysis (1976) is given in black dotted lines, samples from 2020 are shown with red dashed lines. Averaged grain size distributions are indicated by dots and solid lines.
Figure 4. Grain size distribution analysis. Pre-dam analysis (1976) is given in black dotted lines, samples from 2020 are shown with red dashed lines. Averaged grain size distributions are indicated by dots and solid lines.
Water 17 02514 g004
Figure 5. Measured discharge (black lines) and SSC (colored lines and symbols) during the test sluice event performed in January 2020. Reservoir inflow was observed at BB, outflow was observed in the power channel through HW at CB, as well as downstream of the sluice gates (BS). Red crosses indicate measured SSC downstream of BS, green triangles show SSC at CB and orange diamonds represent incoming SSC. Continuous SSC curves (green and yellow lines) are shown for derived rating curves (RC) between turbidity sensors, bank near and cross-sectional measurements. Minimum and maximum calculated SSC at BS are indicated by dashed blue and red lines, respectively. Stepwise sluice gate openings B for both gates are shown in magenta using a third axis.
Figure 5. Measured discharge (black lines) and SSC (colored lines and symbols) during the test sluice event performed in January 2020. Reservoir inflow was observed at BB, outflow was observed in the power channel through HW at CB, as well as downstream of the sluice gates (BS). Red crosses indicate measured SSC downstream of BS, green triangles show SSC at CB and orange diamonds represent incoming SSC. Continuous SSC curves (green and yellow lines) are shown for derived rating curves (RC) between turbidity sensors, bank near and cross-sectional measurements. Minimum and maximum calculated SSC at BS are indicated by dashed blue and red lines, respectively. Stepwise sluice gate openings B for both gates are shown in magenta using a third axis.
Water 17 02514 g005
Figure 6. Model calibration of erosion and deposition in the observation area (bounding line with semi-circles) in the lower reservoir: (a) cross section including measured (before and after test sluice event in 2020) and modeled states. (b) measured bed level differences, calculated from the bathymetry measured before and after the test flushing event (2020). Track for single-beam measurement before and after are indicated with magenta and green lines. (c) modeled bed level differences of the calibrated model. (d) long section (LS) along the flushed channel including measured and simulated bed levels.
Figure 6. Model calibration of erosion and deposition in the observation area (bounding line with semi-circles) in the lower reservoir: (a) cross section including measured (before and after test sluice event in 2020) and modeled states. (b) measured bed level differences, calculated from the bathymetry measured before and after the test flushing event (2020). Track for single-beam measurement before and after are indicated with magenta and green lines. (c) modeled bed level differences of the calibrated model. (d) long section (LS) along the flushed channel including measured and simulated bed levels.
Water 17 02514 g006
Figure 7. Modeled and observed (a) water level drawdown W and (b) released sediment volume ΔS over the flushing period for all scenarios considered. Observations represent cumulative sediment load L through BS and HW (measured in the power channel). ΔS within the bathymetry area in the lower reservoir is indicated with solid lines, total ΔS is given by dashed lines. Dotted lines show model’s sensitivity of ΔS to minimum and maximum critical shear stress values observed during monitoring conducted for the last 20 min. ΔS for drawdown level 181.0 m are marked with rectangles. Modeling of C-75 stopped before reaching the grey box, where the gates closed.
Figure 7. Modeled and observed (a) water level drawdown W and (b) released sediment volume ΔS over the flushing period for all scenarios considered. Observations represent cumulative sediment load L through BS and HW (measured in the power channel). ΔS within the bathymetry area in the lower reservoir is indicated with solid lines, total ΔS is given by dashed lines. Dotted lines show model’s sensitivity of ΔS to minimum and maximum critical shear stress values observed during monitoring conducted for the last 20 min. ΔS for drawdown level 181.0 m are marked with rectangles. Modeling of C-75 stopped before reaching the grey box, where the gates closed.
Water 17 02514 g007
Figure 8. Modeled bed level changes Δz for drawdown flushing scenarios with Q =250 m3/s inflow, initial reservoir water level of 285.5 m (max OL) and a constant gate opening of 3 m: (a) 1-250 (drawdown level 281.0 m); (b) 1-250 (drawdown level 280.0 m); (c) 2-250 (drawdown level 281.0 m); (d) 2-250 (drawdown level 280.0 m). Filled contours show erosion (blue) and sedimentation (red). Contours of the initial DEM from 2019 are shown as grey lines. The observation area in the lower reservoir is drawn as line with semi-circles.
Figure 8. Modeled bed level changes Δz for drawdown flushing scenarios with Q =250 m3/s inflow, initial reservoir water level of 285.5 m (max OL) and a constant gate opening of 3 m: (a) 1-250 (drawdown level 281.0 m); (b) 1-250 (drawdown level 280.0 m); (c) 2-250 (drawdown level 281.0 m); (d) 2-250 (drawdown level 280.0 m). Filled contours show erosion (blue) and sedimentation (red). Contours of the initial DEM from 2019 are shown as grey lines. The observation area in the lower reservoir is drawn as line with semi-circles.
Water 17 02514 g008
Figure 9. Longitudinal profile of the river downstream showing bed levels Z (m) and modeled water surface (m) for Q = 200 m3s−1 (left ordinate). Bed elevation changes Δz (m) for both transport formulas considered (Laursen and Toffaleti) indicate a complete souring of deposited material at the containment structure downstream of the Pulangi IV dam (right ordinate).
Figure 9. Longitudinal profile of the river downstream showing bed levels Z (m) and modeled water surface (m) for Q = 200 m3s−1 (left ordinate). Bed elevation changes Δz (m) for both transport formulas considered (Laursen and Toffaleti) indicate a complete souring of deposited material at the containment structure downstream of the Pulangi IV dam (right ordinate).
Water 17 02514 g009
Table 1. Summary of investigated scenarios for the reservoir model and the Pulangi river downstream of the dam.
Table 1. Summary of investigated scenarios for the reservoir model and the Pulangi river downstream of the dam.
ParameterParameter DescriptionUnitScenarios for Pulangi IV Reservoir Model
C-75 1-250 2-250
Qinreservoir inflowm3s−175250250
Winitinitial reservoir water levelm284.62max OL = 285.5max OL = 285.5
Wminminimum drawdown water level m281.0280.0280.0
Δhwater level drawdown heightm3.624.54.5
Bgate opening for the two bottom sluice gates (BS) during drawdown flushingmrange: 0 to 5.0 1
average: 1.36
3.03.0
QTturbine dischargem3s−160 ± 22 2275275
Qoutreservoir outflow through the two BS gates and the turbines (HW): Qout = f(W, B, QT) 355 ± 269959 ± 21959 ± 21
Tsimulation timeh5.834.404.80
ΔDdredging volumeMm3--2.2
scenarios for Pulangi river downstream of the dam
C-75D
Qindischargem3s−1Qout of reservoir 2200 to 800
T h5.8372
ΔDdumping volumem3-6000 m3
Notes: 1 Gate opening B was increased stepwise over T. Differences in B between both gates occurred. 2 measured during monitoring of the test flushing event.
Table 2. Critical shear stress test results.
Table 2. Critical shear stress test results.
Descriptionτc,se (Nm−2)τc,me (Nm−2)
16 samples2.84 ± 3.115.91 ± 3.23
6 samples, stored in water for 1 week0.81 ± 0.404.81 ± 1.46
P3 (6 to 16 cm), stored in water for 1 week0.8193.29
P3 (42 to 48 cm), stored in water for 1 week0.398 to 0.4962.321 to 4.033
P3 (48 to 52 cm), stored in water for 1 week0.340 to 0.513no value 1
P11 (0 to 15 cm), stored in water for 1 week1.3735.815
P11 (30 to 37 cm), stored in water for 1 week0.9134.033
16 samples, minimum value0.3402.321
16 samples, maximum value12.20512.141
Notes: 1 Transition from surface to mass erosion was smooth or not detectable (no value). Sample contained sand.
Table 3. Cohesive parameters determined during calibration and serving as a basis for estimating the sensitivity of the sediment transport model based on [42].
Table 3. Cohesive parameters determined during calibration and serving as a basis for estimating the sensitivity of the sediment transport model based on [42].
Parameter NameParameterValue
Critical shear stress value for full depositionτd,full0.000010
Critical shear stress value for partial depositionτd,part0.60
equilibrium concentrationceq823 mg/L = cin
Surface erosion rate constantMse2.5 · 10−5 ms−1
Mass erosion rate constantMme2.1 · 10−4 ms−1
Critical shear stress value for surface erosionτc,se1 Nm−2
Critical shear stress value for mass erosionτc,me3.5 Nm−2
Settling velocitywRef. [71]
Table 4. Sensitivity analysis for cohesive parameters of the sediment transport model iSed.
Table 4. Sensitivity analysis for cohesive parameters of the sediment transport model iSed.
ParameterParameter Value/Change (%)Change in ΔS (%)
C-751-2502-250
τc,minτc,se = 0.398 Nm−2/−60%−103%−72%−56%
τc,me = 2.321 Nm−2/−34%
τc,maxτc,se = 12.205 Nm−2/+1121%+72%+73%+51%
τc,me = 12.205 Nm−2/+249%
w1after [42]/−80%+13-5%-
ceq2207 mg/L/−75%−1%+3%-
Notes: 1 Decrease in % was calculated on average over all concentration classes. 2 Value of 207 mg/L represents concentration cin at reservoir inflow for Q = 75 m3s−1.
Table 5. Sensitivity analysis for relative erosion (%) based on completely deposited sediments at the Pulangi River downstream of the reservoir. Relative erosions are evaluated separately over time.
Table 5. Sensitivity analysis for relative erosion (%) based on completely deposited sediments at the Pulangi River downstream of the reservoir. Relative erosions are evaluated separately over time.
Parameter 1Δ Parameter 1 (%)Parameter 2Δ Parameter 2 (%)Relative Erosion (%)
Q (m3s−1) t = 12 ht = 24 ht = 48 ht = 72 h
200---558897100
300+50--62909899
400+100--68909899
500+150--72909898
600+200--73909999
700+250--74919999
range (%) *:+250 192.81.61.9
τc,se (Nm−2) τc,me (Nm−2) t = 12 ht = 24 ht = 48 ht = 72 h
1-4-558998100
12.2+112012.2+20551859598.5
0.340−662.31−42548897100
range (%) *:1186 2473.23.01.91.5
n --t = 12 ht = 24 ht = 48 ht = 72 h
0.037---548897100
0.033−11--47829699
0.041+11--65919899
range (%) *:22--17.98.62.11.3
dex---t = 12 ht = 24 ht = 48 ht = 72 h
4 d90---558998100
1 d90−75--31619397
8 d90+100--639198101
12 d90+200--649198100
range (%) *:275 33.030.25.84.2
Note: * Range in (%) is defined by maximum minus minimum value. The use of bold represents sub-headers.
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Glas, M.; Tritthart, M.; Pessenlehner, S.; Morris, G.; Lichtneger, P.; Tabios, G.I.Q.; Eftymiou, N.; Karki, P.; Habersack, H. Modeling and Monitoring of Drawdown Flushing and Dredging Toward Sustainable Sluicing in a Wide Philippine Reservoir. Water 2025, 17, 2514. https://doi.org/10.3390/w17172514

AMA Style

Glas M, Tritthart M, Pessenlehner S, Morris G, Lichtneger P, Tabios GIQ, Eftymiou N, Karki P, Habersack H. Modeling and Monitoring of Drawdown Flushing and Dredging Toward Sustainable Sluicing in a Wide Philippine Reservoir. Water. 2025; 17(17):2514. https://doi.org/10.3390/w17172514

Chicago/Turabian Style

Glas, Martin, Michael Tritthart, Sebastian Pessenlehner, Gregory Morris, Petr Lichtneger, Guillermo III Q Tabios, Nikolaos Eftymiou, Pravin Karki, and Helmut Habersack. 2025. "Modeling and Monitoring of Drawdown Flushing and Dredging Toward Sustainable Sluicing in a Wide Philippine Reservoir" Water 17, no. 17: 2514. https://doi.org/10.3390/w17172514

APA Style

Glas, M., Tritthart, M., Pessenlehner, S., Morris, G., Lichtneger, P., Tabios, G. I. Q., Eftymiou, N., Karki, P., & Habersack, H. (2025). Modeling and Monitoring of Drawdown Flushing and Dredging Toward Sustainable Sluicing in a Wide Philippine Reservoir. Water, 17(17), 2514. https://doi.org/10.3390/w17172514

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop