Next Article in Journal
Building Information Modelling (BIM) Driven Sustainable Cultural Heritage Tourism
Next Article in Special Issue
Study on the Seismic Response Characteristics of Shield Tunnels with Different General Segment Assembly Methods and Widths
Previous Article in Journal
Study on the Correlation Analysis between Urban Morphological Factors and Microclimate Based on Empirical Methods on a University Campus in a Hot-Summer–Cold-Winter Region
Previous Article in Special Issue
Experimental Study on Mechanical Properties of Structured Clay under Different Unloading Rates and Unloading Stress Paths
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Estimation Method for an In Situ Stress Field along a Super-Long and Deep-Buried Tunnel and Its Application

1
Wuhan Municipal Engineering Design & Research Institute Co., Ltd., Wuhan 430023, China
2
Wuhan Urban Construction Investment Development Group Co., Ltd., Wuhan 430023, China
3
School of Civil Engineering, Hubei Engineering University, Xiaogan 432000, China
4
Changjiang River Scientific Research Institute of Changjiang Water Resources Commission, Wuhan 430010, China
*
Author to whom correspondence should be addressed.
Buildings 2023, 13(8), 1924; https://doi.org/10.3390/buildings13081924
Submission received: 27 June 2023 / Revised: 16 July 2023 / Accepted: 25 July 2023 / Published: 28 July 2023

Abstract

:
Aiming at some stress-induced failure phenomena in surrounding rock that occur during the construction of super-long and deep-buried tunnels, a method for estimating the in situ stress in the tunnels based on multivariate information integration is proposed, which uses a small amount of in situ stress measurement, stereographic projection technology, and a numerical simulation method. Firstly, by conducting a macroscopic analysis of the regional geological structure, topography, and pre-excavated small tunnels (such as exploration of adits and pilot tunnels), the strength of the tectonic stress field and the orientation of the principal stresses in the tunnel sections are preliminarily determined. Secondly, the reliability of the in situ stress measurement data were analyzed using full-space stereographic projection and the plane stress projection method. Then, some representative measurement points that reflected the distribution characteristics of in situ stress in the project area, on the whole, were determined. Thirdly, the finite difference (FDM) and multiple regression analysis (MRA) methods were used to inverse the in situ stress field in the project area. The proposed method was applied to a super-long and deep-buried tunnel project in Qinling, and the in situ stress distribution characteristics of the tunnel sections at different mileages were obtained. The results show that both the calculated principal stress values and the azimuth angle of the maximum horizontal principal stress are in good agreement with the measured ones, indicating that the method used in this study is reasonable. Finally, the typical surrounding rock failure phenomena encountered during the excavation of the project were investigated, and targeted treatment measures were proposed. The research results can provide references for support design and disaster management of surrounding rock in deep-buried long tunnels.

1. Introduction

With the rapid development of China’s social economy and the implementation of the Western Development Strategy, significant progress has been made in tunnels and underground engineering, showing a trend in deep-buried, super-long, and extra-large development. The increasing number of tunnels in complex environments poses enormous challenges to the safe construction and healthy operation of engineering projects [1,2,3]. Engineering practice has shown that in situ stress is one of the important basic data requirements for geological environment and crustal stability evaluation and engineering design and construction, and it is also the fundamental force that causes deformation and failure when the environment in which the rock mass is located changes [4,5]. With the increasing attention paid to engineering safety, it has become an essential task to study the distribution characteristics of in situ stress in the project area in advance during the line selection, layout, design, and construction stages of super-long and deep-buried tunnels.
In situ stress testing is the most direct way to understand the in situ stress field in engineering areas. At present, the commonly used in situ stress testing methods include hydraulic fracturing (HF) [6], over-coring [7,8,9], hydraulic testing of pre-existing fractures (HTPF) [10], surface stress relief for rock mass, and so on [11]. However, during the implementation process, it was found that there are still the following shortcomings when using in situ stress testing. On the one hand, most super-long and deep-buried tunnels are subjected to the occurrence environment of long tunnels, large burial depths, complex geological structures, and stratum lithologies. Owing to high cost, long-term testing, and unfavorable on-site measurement conditions, it is difficult to carry out in situ stress testing for the entire line, and the results only reflect sporadic stress fields located near the limited measurement points. On the other hand, the application conditions of in situ stress testing methods are relatively strict, and it is difficult to fully meet this strict requirement in the actual testing process. For example, the over-coring method requires the tested rock mass to meet uniform, continuous, isotropic, and linear elastic conditions, while the HF method assumes principal stress along the vertical direction [8,9,10]. However, under extremely high-stress environments, core disking often occurs in boreholes, which greatly reduces the success rate of in situ stress testing [12,13]. Additionally, in high-stress environments, the testing equipment pressure is limited. Insufficient equipment pressure leads to the formation of wellbore cracks, making it difficult to implement in situ stress testing methods. The HTPF method assumes that the tested rock mass is uniform, continuous, and linearly elastic. When the distance between the tested fractures is greater than 50 m, a stress gradient value needs to be provided [10]. At present, due to limited measured data and geological information, studies typically use numerical simulation technology to invert the distribution characteristic of 3-D in situ stress fields for the entire research area [14,15,16]. However, the accuracy of the in situ stress field obtained using this method depends not only on the reliability and representativeness of the in situ stress testing data but also on numerous factors such as numerical models, boundary conditions, and geological parameters [17].
Numerous engineering practices have shown that a substantial amount of rock mass deformation and failure information is often revealed during the excavation process, although this phenomenon is harmful to engineering construction safety. However, from another perspective, failure phenomena provide an indirect basis for estimating the magnitude and direction of in situ stress. In recent decades, many scholars have conducted in-depth research on the relationship between testing methods, such as the borehole fracturing method [18,19,20,21], the borehole stress relief method [22,23,24,25,26], and the HF method [6,10], and in situ stress. Then, the magnitude and orientation of in situ stress based on failure phenomena and limited testing data can be estimated. With the improvement in computer technology and the continuous development of numerical simulation technology, the comprehensive use of in situ stress testing technology, rock excavation failure phenomenon, back analysis, and numerical simulation methods to obtain the distribution characteristics of the in situ stress field of deep underground projects, has gradually become a commonly used analysis method [27,28,29,30]. This method compensates for the problems of limited or unreliable in situ stress measurement data and provides a feasible approach for determining the 3-D in situ stress field of super-long and deep-buried tunnels. However, in the case of soils and soft rocks, the numerical models used to evaluate stresses and displacements must be based on unconfined conditions, not limited to oedometric parameters [31]. In addition, the back analysis method has been widely applied in computational simulations of tests (namely, direct analyses), sensitivity analyses for the optimal design of experiments, model reduction procedures, and other aspects [32,33]. At the same time, it plays an important role in the mechanical characterization of materials and the non-destructive assessment of possible damages to industrial plant components and civil engineering structures and infrastructures [34].
It can be seen that the current research on initial stress field inversion mostly focuses on how to improve the fitting degree between the calculated stress values at the measurement points and the measured ones, while the research on the effectiveness and representativeness of the measured data for subsequent back analysis is not in-depth enough. In addition, existing inversion methods lack recognition of failure phenomena in the surrounding rock during tunnel excavation. Thus, the obtained in situ stress field cannot match well with the failure characteristics of the surrounding rock. To address the above issues, a comprehensive analysis method that can estimate the 3-D in situ stress field of tunnels passing through multiple geological tectonic units based on incomplete measured stress data and geological information is proposed. The method is designed for use prior to the excavation of deep-buried long tunnels. Firstly, by conducting a macroscopic analysis of the regional geological structure, topography, and failure phenomena of pre-excavated small tunnels, the strength of the tectonic stress field and the orientation of the principal stresses in the tunnel sections are preliminarily determined. Secondly, by use of stereographic projection technology, the reliability of the in situ stress measured results is analyzed, and representative measurement points are selected that can reflect the distribution characteristics of in situ stress in the project area on the whole. On this basis, the FDM and MRA methods are used to complete a back analysis of the in situ stress field in the project area. The method above was directly applied to a super-long and deep-buried tunnel project in Qinling, and the in situ stress distribution characteristics of the tunnel sections at different mileages were obtained. Finally, the typical failure phenomena in the surrounding rock encountered during the excavation of the project were investigated, and targeted treatment measures were also proposed.

2. In Situ Stress Estimation Method for Super-Long and Deep-Buried Tunnels

During the construction of deep-buried tunnels, it is necessary to excavate some small tunnels (such as exploration, auxiliary, and pilot tunnels) in advance to expose stress-induced failure phenomena in the surrounding rock (such as peeling and sudden rock burst phenomena). Although stress-induced failure phenomena are harmful to construction safety, from another perspective, they also provide a new method to explore certain characteristics of in situ stress.
This study proposes a multivariate information integration method for estimating the in situ stress of deep-buried tunnels based on a small amount of stress measurement data and the pre-exposed stress-induced rock failure characteristics of small tunnels in advance. A flowchart for this method is shown in Figure 1. The basic principle and implementation process for the method are described in detail below:

2.1. Macroscopic Characteristic Analysis

Using an analysis of the tectonic history and current tectonic activity within the project region, the orientation of the tectonic stress was inferred as follows:
(1) Using a study on the geological age of the regional geological structure in the project area, the types of main control faults (such as normal, thrust, and strike-slip fault), and the relationship between faults in the near-field zone and tectonic stress, the orientation of the in situ stress field in the project area was preliminarily revealed.
(2) The relationship between the topography and tectonic stress in the project area was studied, and the influence characteristics of the topography on the distribution of in situ stress was preliminarily determined.
(3) In combination with the possible occurrence of failure phenomenon in the surrounding rock of the exploration adits, the strength of the structural stress field and the orientation of the principal stresses in the tunnel sections were preliminarily determined.

2.2. Reliability Analysis and Selection of In Situ Stress Testing Results

Using the in situ stress measurement data, the distribution characteristics of the in situ stress field in the project area were preliminarily analyzed, and the azimuth and inclination angles of the principal stresses were described with stereographic projection technology. Subsequently, the potential deformation and failure characteristics of the surrounding rock of the tunnel were obtained according to the spatial relationship between the measured principal stress direction and tunnel axis. Within the same project area, the measured results should be consistent with the stress state in the macroscopic area. The reliability of the in situ stress measurement should be tested from the following aspects:
(1) When the measured results consider errors, such as rounding, they sometimes do not constitute a stress tensor. Therefore, it is necessary to analyze the complete stress tensor (six components) from the measured values using stereographic projection technology [30]. The orthogonality of three principal stress directions was examined.
(2) Verification of consistency between the measured principal stress direction and macroscopic regional tectonic stress direction.
(3) Verification of the consistency between the measured stress-induced deformation and failure parts of surrounding rock and the inferred position using the spatial relationship between the principal stress and the tunnel axis.
(4) Combined with Section 2.1, the representative measurement data that can reflect the distribution characteristics of the in situ stress in the project area are selected for subsequent back analysis of the in situ stress field.

2.3. Multiple Regression Analysis Method (MRA) for an In Situ Stress Field

MRA of an in situ stress field is an important method for estimating the stress state in a project area. This method has been widely used in many large-scale underground projects [17,26,35]. Based on the theory of geomechanics, this method establishes a mathematical calculation model by dividing the main components of the in situ stress fields, such as the self-weight and tectonic stress field, and obtains the corresponding weights of each factor using multiple regression analysis so that the fitting error between the calculated and measured stress values at the test location is minimized. Based on current research results [35,36], there are four main types of action modes of the in situ stress field in this study. The impact of tectonic action on the in situ stress is achieved by applying unit stress or displacement at the boundary. The load and boundary constraints are plotted in Figure 2.
The calculation process for the MRA method is described as follows [37,38]:
Using the in situ stress field regression value σ k as the dependent variable and the stress value σki for each influencing factor as the independent variable, the form of the regression equation is as follows:
σ k = i = 1 n L i σ k i
where k is the sequence number of the observation points, Li is the multiple regression coefficient for the corresponding independent variable, σ k is the regression-calculated value for the kth observation point, σki is the single-column matrix for the calculated value of the corresponding stress component, and n is the number of working conditions, i = 1, 2, …, n.
Supposing that there are m observation points, each with six stress components, the residual sum of squares Sc can be obtained as follows:
S c = k = 1 m j = 1 6 ( σ j k * σ j k ) 2 = k = 1 m j = 1 6 ( σ j k * i = 1 n L i σ j k i ) 2
where σjk* and σ j k are the measured data and calculated values of the stress component j at the observation point k, respectively, σjki is the numerically calculated value of the stress component j at the observation point k under the i condition, and l = 1, 2, 3, …, 6 refers to σxx, σyy, σzz, σxy, σyz, and σzx, respectively.
Based on the principle of the least square method, a set of Li is obtained to minimize the residual sum of squares Sc, and the solution is unique. The least square method (also known as the least squares method) is a mathematical optimization technique. By minimizing the sum of squares of errors to find the best function that matches the data, it can easily estimate unknown data and minimize the sum of squares of errors between the calculated and measured results. The equation that makes Sc the minimum is:
[ k = 1 m l = 1 6 ( σ l k 1 ) 2 k = 1 m l = 1 6 σ l k 1 σ l k 2 k = 1 m l = 1 6 σ l k 1 σ l k n s y m m e t r y k = 1 m l = 1 6 ( σ l k 2 ) 2 k = 1 m l = 1 6 σ l k 2 σ l k n                                       s y m m e t r y                       k = 1 m l = 1 6 ( σ l k n ) 2 ] { L 1 L 2 L n } = { k = 1 m l = 1 6 σ l k * σ l k 1 k = 1 m l = 1 6 σ l k * σ l k 2             k = 1 m l = 1 6 σ l k * σ l k n }
Solving the system in Equation (3) and obtaining n undetermined regression coefficients L = (L1, L2, …, Ln)T, the initial in situ stress at any point P in the calculation region can be obtained with superimposing the calculated values of the finite element in each working condition. That is:
σ j P = i = 1 n L i σ j P i
where σ j P is the regression-calculated value of the stress component j at any observation point P in the calculation domain and σ j P i is the calculated value of the stress component j at any observation point P in the calculation domain under the i condition.
According to Equation (4), the initial in situ stress field in the calculation region is treated as a linear superposition of the self-weight stress field and the tectonic stress field. To ensure that the obtained initial in situ stress field conforms to the actual distribution characteristic of the stress field, the reliability of the regressed in situ stress field was evaluated using two aspects: (1) the calculated values of the in situ stress component were verified to be basically consistent with the measured ones to ensure that the spatial points are consistent and (2) the consistency of the predicted deformation and failure parts in the surrounding rock of the tunnel under the calculated stress field, as well as the observed deformation and failure phenomena during the tunnel excavation, were verified to ensure that the in situ stress characteristics of the local area were consistent.

3. Project Overview: A Case Study

3.1. Project Introduction

The Hanjiang-to-Weihe River Water Diversion Project, which is called the South-to-North Water Diversion Project in the Shaanxi Province of China, aims to solve the water shortage problem in cities along the Weihe River coast in the central Shaanxi area. The Qinling water conveyance tunnel is a key channel for diverting water from the Hanjiang River to the Weihe River, with a maximum burial depth of about 2002 m, a length of 81.779 km, and an average annual water transmission of 1.505 billion cubic meters. The inlet of the tunnel has a bottom elevation of 537.17 m, and the exit has a bottom elevation of 510.0 m. This study focuses on the north section of the Qinling water conveyance tunnel, which is 41.779 km long (K40 + 000~K81 + 779). The location of the tunnel is shown in Figure 3.

3.2. Geological Conditions

The project area is located in the northern section of the Qinling tunnel, which mainly includes the geomorphic units of the high and middle mountain areas of the Qinling Ridge, as well as the middle and low mountain areas of the northern Qinling Ridge. Under the influence of neotectonics, a relatively complex geomorphic unit was formed by long-term water erosion and cutting. The construction methods in the project area primarily include a TBM section and a drilling and blasting section. The geological conditions in the different sections are as follows:
(1) The TBM construction section is 25,164 m long (K40 + 000~K65 + 164), and its main lithology is granite, quartz diorite, metasandstone, phyllite, and hornblende schist. The rock mass is weakly weathered to slightly weathered, which is severely affected by geological structures. The joint fractures are relatively developed. The main faults that pass through are QF4, f8, f9, f10, f11, f12, f13, f14, f15, f16, f17, QF3, QF3-1, QF3-2, QF3-3, QF3-4, f18, and f19. The rock mass is relatively integrated, but the local stability of the surrounding rock is poor.
(2) The drilling and blasting construction section is 16,615 m long (K65 + 164∼K81 + 779), and the main lithology is granite, granodiorite, granite porphyry, gneiss, hornblende schist, phyllite with sand, mica schist with chlorite schist, and marble with mica schist. The rock mass is weakly weathered to slightly weathered, which is severely affected by geological structures. The joint fractures are well-developed. The main faults that pass through are f21, f22, f23, QF2, f25, and f26. The integrity of the rock mass is poor, but the local stability of the surrounding rock is good.
The materials in the fault fracture zone are primarily composed of fault mud, breccia, Mylonite, and fragmented rock, which are loose and broken and contain water. The surrounding rock of the tunnel has poor self-stability, and its instability is prone to occur during construction.

4. In Situ Stress Analysis Using Multivariate Information Integration

4.1. Macro Characteristic Analysis

4.1.1. Analysis of the Regional Geological Structures

The Qinling water conveyance tunnel belongs to the Qinling Fold System in terms of tectonic units, and its geological structure mainly develops fold and fault structures. It passes through two regional major faults, namely, the Shangnan–Tangzhi fault, which strikes in the EW direction, shows compressive stress, and inclines in the N direction. The Fengzhen–Shanyang fault strikes in the NWW direction, shows tensile stress, and inclines in the N direction. Regional major faults have the characteristics of deep cutting, long extension, and large scale. The strike is mostly in the near EW direction, with a small number in the NE and NW directions, most of which are compressive. The distribution characteristics of major geological structures near the tunnel are shown in Figure 4. Some domestic scholars have deeply discussed the distribution characteristics of the tectonic stress field in this region using focal mechanisms, numerical analysis methods for microstructure, etc. It is believed that the tectonic stress field in this area is mainly extruded in the NW–SE direction [40]. This is basically consistent with the characteristics of the regional tectonic stress field in the North China Plate.
In summary, the main compressive stress direction of the modern tectonic stress field in the project area is generally in the NW or near EW direction, and there may be significant deviations in local areas due to the influence of topography, geological structure, and the ancient tectonic stress field.

4.1.2. Analysis of the Topography in the In Situ Stress Field

Existing studies have shown that the distribution of in situ stress in river valleys generally includes a stress relief zone, stress concentration zone, and stress stability zone [41,42]. The elevation and maximum burial depth of the Qinling water conveyance tunnel project area are approximately 500 m–2500 m and 2002 m, respectively. The valley is relatively narrow, with a general width of 30–50 m and a natural slope of 40°–60°. The topographic and geomorphological features of the river valley along the tunnel are shown in Figure 5. The in situ stress testing indicates that the maximum horizontal principal stress direction is mainly in the NW direction outside the tunnel, but it is close to the EW direction inside the tunnel. The overall direction is between NW and EW, which is consistent with the regional structure and topography [43]. In addition, the lateral pressure coefficient of the maximum horizontal principal stress direction near the river valley outside the tunnel is generally greater than 2.0, indicating that the stress concentration phenomenon in the valley area is obvious. The tectonic stress field is strong, and the testing site is significantly affected by the terrain. The field test results are basically consistent with current research results.

4.1.3. Relationship between Failure Characteristics of the Surrounding Rock and In Situ Stress

Recently, during the construction of the main and branch tunnels, a rock burst was observed. Also, instability in the surrounding rock is relatively common, mainly occurring in the fault fracture zones, weak structural planes, and joint dense zones. In some areas severely affected by geological structures, such as fault zones and lithological contact zones, it is easy to encounter large-scale collapses.
It can be seen that the distribution of in situ stress in the tunnel area is relatively complex. For the surrounding rock of the tunnel with large burial depths of hard and brittle rocks, the tectonic stress field has a strong effect. The stress concentration phenomenon is evident, and rock bursts are prone to occur. For soft rock areas with large burial depths, particularly in areas with fault structures, stress release is the main feature. Large deformation of the surrounding rock and rock mass sliding and collapse are more significant. Therefore, the characteristics of the in situ stress field in the project area are relatively complex, mainly formed by the superposition of self-weight stress and tectonic stress.

4.2. Analysis of In Situ Stress Testing Results

The in situ stress field test of the Qinling water conveyance tunnel mainly uses the HF method and 3-D hydraulic fracturing method. The HF method uses the method recommended by the International Society of Rock Mechanics for in situ stress testing. The principle underlying the 3-D hydraulic fracturing method and its implementation process are detailed in Ref. [43]. The layout of boreholes for in situ stress testing is shown in Figure 6. Among them, three deep boreholes, CZK-2, CZK-3, and SZK-2, were created using the HF method. The stress measurement results are shown in Table 1 and Figure 7, where σv is the vertical principal stress, σH is the maximum horizontal principal stress, and σh is the minimum horizontal principal stress. The 6# testing section used the 3-D hydraulic fracturing method, and the stress measurement results are shown in Table 2. The stress components and maximum horizontal principal stress results after coordinate system transformation are listed in Table 3.
As shown in Table 2 and Figure 7, in situ stress in the project area is dominated by horizontal tectonic stress, but there are certain differences in the distribution characteristics of stress among different boreholes. For boreholes CZK-2 and CZK-3, the relationship between the three principal stresses is basically σH > σv > σh, and the maximum principal stress is mainly horizontal. The predominant direction of the maximum horizontal principal stress is N 37° W to N 52° W, and the lateral pressure coefficient of the maximum horizontal principal stress (σH/σv) ranges from 0.88 to 1.94. However, for borehole SZK-2, the relationship between the three principal stresses is basically σH > σh > σv. The predominant direction of the maximum horizontal principal stress is N 9° E to N 35° W, and the lateral pressure coefficient of the maximum horizontal principal stress (σH/σv) ranges from 2.88 to 5.02.
In addition, to meet the requirements for quantitative analysis of in situ measured stresses, the so-called software ‘GeoStress3D V1.0’ was developed using OOP programming technology, the C++ language, and the open graphics library OpenGL. This method not only verifies the orthogonality of the three principal stresses direction but also determines the in situ stress distribution characteristics at measurement points on each projection plane using plane projection technology. Using the measurement point at the 6# testing section as an example, the stereographic projection of a unit vector of typical principal stress orientations and their projection stress ellipses on the XY, YZ, and YZ planes are shown in Figure 8a. Also, Figure 8b shows a plot of the deformation and failure characteristics of the surrounding rock of the tunnel. In the figure, the red circle Buildings 13 01924 i001, green square Buildings 13 01924 i002, and blue diamond Buildings 13 01924 i003  stand for the unit vector of the orientation of the maximum, intermediate, and minimum principal stresses, respectively (same as below). The three numbers behind Sigma (i.e., Sigma1, Sigma2, and Sigma3) stand for the principal stress values, azimuth, and dip angles, respectively. It can be concluded that the long axial direction of the stress ellipse is inclined to the upper (or lower) reach of the river valley on the XY (or YZ) plane. On the XZ plane, the long axial direction is inclined to the inside mountain. Similarly, the projection features of the stresses at other testing points can also be interpreted.
Thus, the orientation of the maximum horizontal principal stress is orthogonal to the axis of the Qinling water conveyance tunnel (near the NS direction), which is relatively unfavorable for the stability of the cavern. During the actual construction process, some effective measures should be taken to reduce the impact of the secondary stress field on the deformation and failure of surrounding rock after tunnel excavation.

4.3. Selection of Representative Measured Data

Based on the above, it can be concluded that the in situ stress field in the project area has the following characteristics: (1) The in situ stress field is significantly affected by tectonic stress in the shallow part, and as the burial depth increases, the self-weight gradually dominates. (2) The orientation of the maximum horizontal principal stress is between NW and NWW. The lateral pressure coefficient of the maximum horizontal principal stress decreases with increasing burial depth, most of which are less than 1.5. (3) The projection of the measured stress tensor on each plane should conform to the characteristics shown in Figure 8.
It can be seen that the burial depth of borehole SZK-2 is relatively shallow, and the measured results are greatly affected by the topography and geomorphology. Moreover, the measurement points 9#–12# in borehole CZK-3 are significantly affected by local geological defects. Namely, the above measured results are not representative. Thus, ten measurement points, 1–8#, 13#, and 14#, can represent the overall characteristics of the in situ stress field in the project area, which are selected as the basic information for a subsequent back analysis of the in situ stress field.

4.4. MRA of the In Situ Stress Field

4.4.1. Computational Model and Mechanical Parameters for the Rock Masses

The numerical analysis method is widely recognized as an important approach for estimating the stress state in deep-buried tunnels. Here, the commercial software FLAC3D V4.0 was used for numerical calculation. The computational model corresponded to a region of the rock mass measuring 5000 m × 45,000 m × 3600 m (X × Y × Z, where the positive direction of the X-axis and Y-axis point to the east and north, respectively, and the Z-axis extends upwards from an elevation of −1000 m to the mountain top). The computational model and grid division based on regional geology, topography, and geomorphology are plotted in Figure 9a,b. In this model, seventeen typical strata and thirteen major faults were included; the main faults are shown in Figure 9c. In addition, a 3-D solid element (Solid45) was used to establish the finite element calculation model. Different types of strata and faults in the model were simulated using solid units, and the constitutive model was linear elastic. The bottom of the model was constrained, and the tectonic effects were simulated by applying horizontal compressive and shear loads around the model (see Section 2.3). The number of grid elements and nodes were 185,832 and 1,056,155, respectively. The physical and mechanical parameters of the rock masses are listed in Table 4.

4.4.2. Back Analysis of the In Situ Stress Field

Based on Section 2.3, the finite element calculation of regional ground stress field distribution under self-weight stress and three kinds of tectonic action was carried out, and the stress components at the corresponding depths of each borehole were extracted. According to the MRA, the regression coefficients for the four influencing factors affecting the in situ stress field of the Qinling water conveyance tunnel were obtained, and the initial in situ stress field regression equation was preliminarily established as:
σ c a l = 0.93 S g + 2.416 S x + 5.589 S y 16.236 S x y
where σcal is the initial regression stress value; Sg is the self-weight stress value; Sx and Sy are the unit extrusion stresses applied along the horizontal boundary in the x and y directions, respectively; and Sxy is the unit-tangential stress applied along the x and y directions in the horizontal plane.
By comparing the calculation values with those measured (Table 5), it is found that the multiple correlation coefficient is 0.956, and the F-test observed value is 50.51. When the significance level is 0.05, the critical value F0.05 (4, 24 − 4 − 1) is 2.93, namely, F > F0.05. Thus, the precision of the back-analysis is satisfactory.
Figure 10 plots the relationship between the measured value of the principal stress and the calculated values at the measurement points. It can be seen that the measured values at most measurement points are numerically close to the calculated ones, and the absolute error of the stress component is mostly not more than 2 Mpa. The overall error is relatively small. In addition, the maximum horizontal principal stress azimuth at each measurement point is in good agreement with the measured data. The maximum absolute error of the principal stress azimuth is approximately 12°, generally not exceeding 6°. It can be concluded that the optimized back analysis method used in this paper is credible and behaves well when simulating the initial in situ stress field in the project area under complex conditions.

4.5. Distribution Characteristics of the In Situ Stress Field

Figure 11 shows the distribution of the three principal stress contours along the longitudinal section of the axis of the Qinling water conveyance tunnel. The distribution characteristics of the in situ stress field of the tunnel can be described as follows:
(1) The magnitude of in situ stress near the axis of the tunnel increases with the burial depth. The maximum burial depth is approximately 2000 m. The magnitude of the maximum principal stress is as high as 52.65 MPa.
(2) The tunnel has a long route that passes through different geological structural units, resulting in a very complex distribution of the in situ stress field in the surrounding rock. Specifically, when the burial depth of the tunnel is less than 1000 m, the in situ stress field at the tunnel elevation is mainly horizontal, that is, σH > σZ > σh. the lateral pressure coefficient of the maximum horizontal principal stress (σH/σv) ranges from 1.02 to 1.88. When the burial depth of the tunnel is greater than 1000 m, the maximum principal stress at the tunnel elevation is primarily owing to its own weight, that is, σZ > σH > σh. The lateral pressure coefficient of the maximum horizontal principal stress is between 0.7 and 1.1. In general, the lateral pressure coefficient of the principal stress gradually decreases with an increase in burial depth.
(3) Due to the influence of topography and faults, a certain stress concentration phenomenon occurs at the foot of slope. However, there are obvious stress release phenomenon in the fault zone and adjacent areas, and the maximum horizontal principal stress direction also undergoes a certain deviation. Furthermore, the fault and its surroundings show that the vertical principal stress in the rock mass is greater than that of the maximum horizontal principal stress, that is, σZ > σH > σh.
(4) The in situ stress in the fault zone changes sharply, and the stress contour appears to be a phenomenon of ‘hump and mutation’. After reaching a certain distance, it tends to stabilize. Further analysis showed that at the end of the fault, each stress component and principal stress have evident stress concentrations. However, the position of the stress concentration zone is asymmetric at both ends of the fault, which is primarily caused by the difference in the angle between the boundary stress ratio of the fault and the maximum principal stress.

5. Failure Mechanism of the Surrounding Rock and Treatment Method

5.1. Description of Failure Characteristics during Tunnel Excavation

Figure 12 shows the geological profile along the axis of the Qinling water conveyance tunnel from K79 + 900 to K78 + 779. The burial depth of the tunnel in this section ranges from 183 m to 282 m, and more than ten large collapses occurred during its construction. The collapses are mainly located on the left arch and side wall. The height of the collapsed cavity is about 8 m, with a longitudinal extension of 4 m and a circumference of 6 m. After the collapse, the initial convergence deformation of the surrounding rock was large, reaching 10 mm/day. A typical failure image obtained in the surrounding rock is shown in Figure 13.

5.2. Failure Mechanism Analysis

According to the geological data obtained during the excavation, the lithology of the locally damaged area is primarily mica quartz schist with local carbonaceous schist, high mica content, soft lithology, and joint development. Three groups of joints, i.e., straight, smooth, and no filling, are well developed, which can be described as follows:
(a) J1: N 20° W/60° S, spacing from 0.1 m to 0.2 m, extending approximately 1 m.
(b) J2: N 15° W/60° N, spacing from 0.3 m to 0.5 m, extending about 2 m.
(c) J3: N 30° E/55° N, spacing from 0.05 m to 0.1 m, extending about 1 m.
Due to the extremely smooth surface of mica schist, low internal friction angle, and poor shear resistance, unloading deformation occurred during the tunnel excavation. Plastic deformation subsequently occurred when exposed to water, which made it easy for the blocks to cause slip damage to the side wall. It can be concluded that the accident in this project was mainly owing to the collapse caused by the fragmentation of rock mass, soft lithology, and the formation of sliding blocks due to the cutting of the structural plane.

5.3. Targeted Treatment Method and Rationality Verification

5.3.1. Support Measures

Based on geological data and engineering experience, the parameters of Phase I support and lining in the surrounding rock are listed in Table 6. The corresponding cross-section of support is plotted in Figure 14.
Owing to the fragmentation of surrounding rock, the development of fissure water, and poor stability, a collapse is prone to occur after excavation. Therefore, advanced small conduits with a diameter of 42 mm were added to this section of the tunnel. The small conduits are arranged within 120° of the arch, with a longitudinal spacing of 2.0 m/ring, a circumferential spacing of 30 cm, and an external insertion angle ranging from 5° to 10°. The collapsed area was backfilled with C20 spray concrete.

5.3.2. Numerical Simulation Analysis and Verification

To evaluate the feasibility and rationality of the collapse treatment method for surrounding rock, a three-dimensional finite element model (see Figure 15) was established based on the excavation and support conditions of the tunnel at the mileage from K79 + 900 to K78 + 779. In the model, surrounding rock, shotcrete, and secondary lining structures were simulated using 3-D solid element elements. Advanced small conduits and anchors were simulated using rod elements. Steel arches were simulated using beam elements. The mesh model contained 265,508 grid nodes and 142,612 elements.
Using the construction conditions and instability of the surrounding rock, as well as the stress estimation for the tunnel described in Section 4, a numerical simulation was carried out. The calculated results are as follows:
(1) Displacement distribution. Figure 16 and Figure 17 show the distribution characteristics of the displacement field after tunnel excavation with untimely initial support and with timely initial support, respectively. In the case of untimely support, the maximum horizontal displacement at the tunnel sidewall can reach 96.7 mm, and the maximum settlement at the top arch is 44.0 mm. At this time, the soft rock is extremely vulnerable to damage. However, with timely support, the maximum horizontal displacement at the tunnel sidewall can reach 49.3 mm, and the maximum settlement at the top arch is 27.3 mm.
(2) In-stress stress distribution. Figure 18 shows the distribution characteristics of the first and third principal stresses after tunnel excavation. It can be seen that there is a phenomenon of stress concentration in the local area around the tunnel (the intersection of the arch foot and side wall with the bottom plate), and the stress concentration is mainly located in the left arch shoulder and side wall. The above results are basically consistent with the on-site failure phenomenon (see Figure 13), which are in good agreement with the inversion results in Section 4. Furthermore, the values of the major principal compressive stress and third principal stress lie in the ranges −0.23 to −13.2 and 0.26 to −5.74 MPa, respectively.

5.4. Discussion

An in-depth analysis of the failure mechanism of surrounding rock during tunnel excavation at the mileage from K79 + 900 to K78 + 779 was carried out using a combination of the monitoring data, interpretation of rock failure characteristics, treatment measures for rock failure, and numerical simulations of the construction process and characteristics of the rock mass. We believe that the internal cause for the failure of the surrounding rock after the tunnel excavation was the fragmentation of rock mass, soft lithology, and the formation of sliding blocks due to the cutting of the structural plane. The external cause was improper construction and untimely initial support. After the tunnel excavation, it is not timely to carry out pre-grouting with advanced small conduit, bolting, and shotcreting support on the face of the tunnel, which results in unloading deformation of the surrounding rock. Then, plastic deformation occurs when encountering water, causing sliding damage to the side walls and arches. Further analysis showed that the sliding of the rock mass and the weakening of the mechanical properties of the structural plane caused a further adjustment of the stress field in the surrounding rock. In turn, the adjusted stress field led to further deformation of the structural plane. The complex interaction between the evolution of the rock mass structure and the adjustment of the stress field made the deformation of the surrounding rock exhibit certain time-effect characteristics, which was consistent with the maximum deformation of 10 mm/day observed during the tunnel excavation.
It can be concluded that for Class IV rock masses with fractured rock and relatively soft lithology, the failure of surrounding rock is more sensitive to the intensity of rock excavation disturbance. Therefore, in the subsequent construction process, the initial support measures such as adding an advanced small conduit with a diameter of 42 mm should be conducted at the face of the surrounding rock soon after the excavation. Meanwhile, the timely use of C20 sprayed concrete backfilling for collapsed areas should also be carried out. In that case, the impact of tunnel excavation on the stability of surrounding rock can be significantly reduced. Both the monitoring and numerical simulation indicated that during subsequent tunnel excavation, the stability of the surrounding rock was good, and the effectiveness of support measures was reasonably verified.

6. Conclusions

The contribution of this paper is the proposal of a method for in situ stress estimation of super-long and deep-buried tunnels based on multivariate information integration. The prominent features of this method include selecting the effectiveness and representativeness of the stress measurement data, identifying the failure phenomenon in surrounding rock during tunnel excavation, and verifying the results of the in situ stress inversion using multiple information types such as incomplete measurement data and on-site failure characteristics of the surrounding rock. This method was used to estimate the in situ stress in the sections of the super-long and deep-buried tunnel project in Qinling. Also, the failure mechanism and treatment measures of the surrounding rock are discussed. The main findings are as follows:
(1) The magnitude of the in situ stress near the axis of the Qinling water conveyance tunnel increased with the burial depth. The magnitude of the maximum principal stress was as high as 52.65 MPa, and the orientation of the maximum horizontal principal stress was mainly NW–EW.
(2) There were significant differences in the stress state along the deep-buried tunnel. When the burial depth of the tunnel was less than 1000 m, the in situ stress field at the tunnel elevation was mainly horizontal, that is, σH > σZ > σh. When the burial depth of the tunnel was greater than 1000 m, the maximum principal stress at the tunnel elevation was primarily owing to its own weight, that is, σZ > σH > σh.
(3) Compared with other areas, the fault zone and adjacent areas showed evident stress release characteristics, and the maximum horizontal principal stress direction also underwent a certain deviation. Furthermore, the fault and its surroundings showed that the vertical principal stress of rock mass was greater than that of the maximum horizontal principal stress, that is, σZ > σH > σh.
(4) The tunnel section from K79 + 900 to K78 + 779 of tunnel mileage collapsed in numerous locations during the construction process. The research showed that the initial support measures such as adding an advanced small conduit with a diameter of 42 mm should be conducted at the face of the fourth grade of surrounding rock soon after the excavation. The deformation of the surrounding rock after support will be significantly reduced, which will satisfy the construction safety requirements.
However, current in situ stress studies in underground engineering are mainly focused on the in situ stress field around deep hard rocks rather than soft rock tunnels. The in situ stress test method and theoretical verification near the large-deformation tunnel of soft rock are not yet mature and require further exploration.

Author Contributions

Q.P.: methodology, data curation, validation, and writing; X.W.: methodology and supervision; L.H.: investigation and supervision; L.L.: data curation and writing; Y.T.: data curation; C.W.: supervision and funding acquisition. All authors have read and agreed to the published version of the manuscript.

Funding

This research was funded by the National Science Foundation of China (No. 51609018), the Central Non-profit Scientific Research Fund for Institutes of China (No. CKSF2021431/CL), and the Key Project of the National Natural Science Foundation of China (No. 52239009).

Data Availability Statement

The data used to support the findings of this study are included in the article.

Conflicts of Interest

The authors declare no conflict of interest.

References

  1. Lyu, H.M.; Sun, W.J.; Shen, S.L.; Zhou, A.N. Risk assessment using a new consulting process in fuzzy AHP. J. Constr. Eng. Manag. 2020, 146, 04019112. [Google Scholar] [CrossRef]
  2. Jin, Y.F.; Yin, Z.Y.; Zhou, W.H.; Shao, J.F. Bayesian model selection for sand with generalization ability evaluation. Int. J. Numer. Anal. Methods Geomech. 2019, 43, 2305–2327. [Google Scholar] [CrossRef]
  3. Yin, Z.Y.; Jin, Y.F.; Shen, J.S.; Hicher, P.Y. Optimization techniques for identifying soil parameters in geotechnical engineering: Comparative study and enhancement. Int. J. Numer. Anal. Methods Geomech. 2018, 42, 70–94. [Google Scholar] [CrossRef]
  4. Cai, M.F. Principle and Techniques of In-Situ Stress Measurement; Science Press: Beijing, China, 2000. [Google Scholar]
  5. Fu, C.; Wang, W.; Chen, S. Back analysis study on initial geostress field of dam site for Xiluodu hydropower project. Chin. J. Rock Mech. Eng. 2006, 25, 2305–2312. [Google Scholar]
  6. Bjarnason, B. Hydro Fracturing Rock Stress Measurements in the Baltic Shield. Licentiate Thesis, Lulea University, Luleå, Sweden, 1986. [Google Scholar]
  7. Kim, K.; Franklin, J.A. Suggested methods for rock stress determination. Int. J. Rock Mech. Min. Sci. Geomech. Abstr. 1987, 24, 53–73. [Google Scholar]
  8. Sjöberg, J.; Christiansson, R.; Hudson, J.A. ISRM suggested methods for rock stress estimation d Part 2: Overcoring methods. Int. J. Rock Mech. Min. Sci. 2003, 40, 999–1010. [Google Scholar] [CrossRef]
  9. Sjöberg, J.; Klasson, H. Stress measurements in deep boreholes using the Borre (SSPB) probe. Int. J. Rock Mech. Min. Sci. 2003, 40, 1205–1223. [Google Scholar] [CrossRef]
  10. Haimson, B.C.; Cornet, F.H. ISRM suggested methods for rock stress estimation-Part 3: Hydraulic fracturing (HF) and/or hydraulic testing of pre-existing fractures (HTPF). Int. J. Rock Mech. Min. Sci. 2003, 40, 1011–1020. [Google Scholar] [CrossRef]
  11. Liu, Y.F.; Yin, J.M.; Liu, Y.K. Geostress Measurement Methods and Engineering Application; Hubei Science and Technology Press: Wuhan, China, 2014. [Google Scholar]
  12. Ljunggren, C.; Chang, Y.; Janson, T.; Christiansson, R. An overview of rock stress measurement methods. Int. J. Rock Mech. Min. Sci. 2003, 40, 975–989. [Google Scholar] [CrossRef]
  13. Zheng, M.Z.; Li, S.J.; Yao, Z.; Zhang, A.D.; Xu, D.P.; Zhou, J.F. Core discing characteristics and mitigation approach by a novel developed drill bit in deep rocks. J. Cent. S. Univ. 2020, 27, 2822–2833. [Google Scholar] [CrossRef]
  14. Shukla, P.K.; Singha, D.K.; Sain, K. Modeling of in-situ horizontal stresses and orientation of maximum horizhontal stress in the gas hydrate-bearing sediments of the Mahanadi offshore basin. Geomech. Geophys. Geo-Energ. Geo-Resour. 2022, 8, 90. [Google Scholar] [CrossRef]
  15. Liu, J.; Ding, W.; Yang, H.; Wang, R.; Yin, S.; Li, A.; Fu, F. 3D geomechanical modeling and numerical simulation of in-situ stress fields in shale reservoirs: A case study of the lower Cambrian Niutitang formation in the Cen’gong block, South China. Tectonophysics 2017, 712, 663–683. [Google Scholar] [CrossRef]
  16. Krietsch, H.; Gischig, V.; Evans, K.; Doetsch, J.; Dutler, N.O.; Valley, B.; Amann, F. Stress measurements for an in-situ stimulation experiment in crystalline rock: Integration of induced seismicity, stress relief and hydraulic methods. Rock Mech. Rock Eng. 2019, 52, 517–542. [Google Scholar] [CrossRef]
  17. Xu, D.P.; Huang, X.; Jiang, Q.; Li, S.J.; Zheng, H.; Qiu, S.L.; Xu, H.S.; Li, Y.H.; Li, Z.G.; Ma, X.D. Estimation of the three-dimensional in situ stress field around a large deep underground cavern group near a valley. J. Rock Mech. Geotechn. Eng. 2021, 13, 529–544. [Google Scholar] [CrossRef]
  18. Haimson, B.C.; Lee, H. Borehole breakouts and compaction bands in two high-porosity sandstones. Int. J. Rock Mech. Min. Sci. 2004, 41, 287–301. [Google Scholar] [CrossRef]
  19. Leeman, E.R. The measurement of stress in rock: Part I: The principles of rock stress measurements. J. S. Afr. Inst. Min. Metall. 1964, 65, 45–81. [Google Scholar]
  20. Zoback, M.D.; Barton, C.A.; Brudy, M.; Castillo, D.A.; Finkbeiner, T.; Grollimund, B.R.; Moos, D.B.; Peska, P.; Ward, C.D.; Wiprut, D.J. Determination of stress orientation and magnitude in deep wells. Int. J. Rock Mech. Min. Sci. 2003, 40, 1049–1076. [Google Scholar] [CrossRef]
  21. Lund, B.; Zoback, M.D. Orientation and magnitude of geostress to 6.5 km depth in the Baltic Shield. Int. J. Rock Mech. Min. Sci. 1999, 36, 169–190. [Google Scholar] [CrossRef]
  22. Stacey, T.R. Contribution to the mechanism of core discing. J. S. Afr. Inst. Min. Metall. 1982, 82, 269–274. [Google Scholar]
  23. Kaga, N.; Matsuki, K.; Sakaguchi, K. The geostress states associated with core disking estimated by analysis of principal tensile stress. Int. J. Rock Mech. Min. Sci. 2003, 40, 653–665. [Google Scholar] [CrossRef]
  24. Jiang, Q.; Feng, X.T.; Xiang, T.B.; Su, G.S. Rockburst characteristics and numerical simulation based on a new energy index: A case study of a tunnel at 2500 m depth. Bull. Eng. Geol. Environ. 2010, 69, 381–388. [Google Scholar] [CrossRef]
  25. Funato, A.; Ito, T. A new method of diametrical core deformation analysis for in-situ stress measurements. Int. J. Rock Mech. Min. Sci. 2017, 91, 112–118. [Google Scholar] [CrossRef]
  26. Zhang, C.Q.; Feng, X.T.; Zhou, H. Estimation of in-situ stress along deep tunnels buried in complex geological conditions. Int. J. Rock Mech. Min. Sci. 2012, 52, 139–162. [Google Scholar] [CrossRef]
  27. Matsuki, K.; Kaga, N.; Yokoyama, T.; Tsuda, N. Determination of three dimensional in-situ stress from core disking based on analysis of principal tensile stress. Int. J. Rock Mech. Min. Sci. 2004, 41, 1167–1190. [Google Scholar] [CrossRef]
  28. Bell, J.S. Practical methods for estimating geostresses for borehole stability applications in sedimentary basins. J. Pet. Sci. Eng. 2003, 38, 111–119. [Google Scholar] [CrossRef]
  29. Kim, H.; Xie, L.; Min, K.B.; Bae, S.; Stephansson, O. Integrated in situ stress estimation by hydraulic fracturing, borehole observations and numerical analysis at the EXP-1 borehole in Pohang, Korea. Rock Mech. Rock Eng. 2017, 50, 3141–3155. [Google Scholar] [CrossRef]
  30. Feng, X.T.; Hudson, J.A. Rock Engineering Design; CRC Press/Balkema: Leiden, The Netherlands, 2011. [Google Scholar]
  31. Rodríguez, C.A.; Rodríguez-Pérez, Á.M.; López, R.; Hernández-Torres, J.A.; Caparrós-Mancera, J.J. A Finite Element Method Integrated with Terzaghi’s Principle to Estimate Settlement of a Building Due to Tunnel Construction. Buildings 2023, 13, 1343. [Google Scholar] [CrossRef]
  32. Buljak, V.; Cocchetti, G.; Cornaggia, A.; Garbowski, T.; Maier, G.; Novati, G. Materials mechanical characterizations and structural diagnoses by inverse analyses. In Handbook of Damage Mechanics; Springer: New York, NY, USA, 2015; pp. 619–642. [Google Scholar]
  33. Chai, S.B.; Liu, H.; Song, L.; Li, X.P.; Fu, X.D.; Zhou, Y.Q. Static pressure and dynamic impact characteristics of filled jointed rock after frozen-thaw cycle damage. Front. Ecol. Evol. 2023, 11, 1222676. [Google Scholar] [CrossRef]
  34. Maier, G.; Bolzon, G.; Buljak, V.; Garbowski, T.; Miller, B. Synergic Combinations of Computational Methods and Experiments for Structural Diagnoses. In Computer Methods in Mechanics. Advanced Structured Materials; Kuczma, M., Wilmanski, K., Eds.; Springer: Berlin/Heidelberg, Germany, 2010; Volume 1. [Google Scholar]
  35. Zhang, Z.; Gong, R.; Zhang, H.; Lan, Q.; Tang, X. Initial ground stress field regression analysis and application in an extra-long tunnel in the western mountainous area of China. Bull. Eng. Geol. Environ. 2021, 80, 4603–4619. [Google Scholar] [CrossRef]
  36. Zhou, C.; Yin, J.M.; Dong, Z.H.; Liu, Y.K.; Han, X.Y.; Zhang, X.H. The partitioned inversion method of initial stress field of extra-long tunnel considering the direction of boundary load. Chin. J. Rock Mech. Eng. 2022, 41, 2725–2734. [Google Scholar]
  37. Zhang, Q.; Xiang, W.; Yu, X. Back analysis of initial geo-stress field in underground powerhouse of Shuangjiangkou Hydropower Station. China Civil Eng. J. 2015, 48, 86–96. [Google Scholar]
  38. Zheng, C.M.; Zhu, W.S.; Sun, G.F. The application of the least square method in back analysis of 3D initial geostress. In Proceedings of the 2009 International Conference on Artificial Intelligence and Computational Intelligence, Shanghai, China, 7–8 November 2009; Volume 11, pp. 603–607. [Google Scholar]
  39. Liu, F.; Tang, C.A.; Ma, T.; Tang, L. Characterizing rockbursts along a structural plane in a tunnel of the Hanjiang-to-Weihe river diversion project by microseismic monitoring. Rock Mech. Rock Eng. 2019, 52, 1835–1856. [Google Scholar] [CrossRef]
  40. Xu, W.L. A study on tectonic stress field on the middle section of northern Qinling mountain in Shanxi province. Seismol. Geol. 1991, 13, 161–172. [Google Scholar]
  41. Tan, C.X.; Wang, R.J.; Sun, Y. Numerical modelling estimation of the ‘tectonic stress plane’ (TSP) beneath topography with quasiU-shaped valleys. Int. J. Rock Mech. Min. Sci. 2004, 41, 303–310. [Google Scholar] [CrossRef]
  42. Liu, Y.Q.; Li, H.B.; Pei, Q.T.; Yu, C.; Luo, C.W.; Yang, F.W. Study of distribution regularities of in situ stress field in steep and narrow river valleys. Chin. J. Rock Mech. Eng. 2011, 30, 2435–2443. [Google Scholar]
  43. Zhou, C.H.; Yin, J.M.; Ding, X.L.; Ai, K. Complex measurements of geo-stress in deep diversion tunnel and research on distribution characteristic of regional stress field in Qinling mountain. Chin. J. Rock Mech. Eng. 2012, 31, 2956–2964. [Google Scholar]
Figure 1. Flowchart showing the in situ stress estimation method for super-long and deep-buried tunnels.
Figure 1. Flowchart showing the in situ stress estimation method for super-long and deep-buried tunnels.
Buildings 13 01924 g001
Figure 2. Schematic diagram showing applied loads and boundary constraints, (a) Self-weight action, (b) Compressive tectonic stress along the X-direction. (c) Compressive tectonic stress along the Y-direction. (d) Shear tectonic stress in the horizontal plane.
Figure 2. Schematic diagram showing applied loads and boundary constraints, (a) Self-weight action, (b) Compressive tectonic stress along the X-direction. (c) Compressive tectonic stress along the Y-direction. (d) Shear tectonic stress in the horizontal plane.
Buildings 13 01924 g002
Figure 3. Location and layout of the Hanjiang-to-Weihe River Diversion Project. (a) Regional map of the project in China. (b) Geographic location of the project in Shanxi Province, China. (c) Diagram showing the project layout. (Modified from the Ref. [39]).
Figure 3. Location and layout of the Hanjiang-to-Weihe River Diversion Project. (a) Regional map of the project in China. (b) Geographic location of the project in Shanxi Province, China. (c) Diagram showing the project layout. (Modified from the Ref. [39]).
Buildings 13 01924 g003aBuildings 13 01924 g003b
Figure 4. Distribution of major fault structures near the Qinling Tunnel project area. ① Baoji–Xieyuguan–Taiyao fault zone; ② Youfang–Huangtai fault zone; ③ Tangzhi–Shangnan fault zone; ④ Shanyang–Fengzhen fault zone; ⑤ Yangpingguan–Yangxian fault zone; and ⑥ Raofeng–Shiquan fault zone.
Figure 4. Distribution of major fault structures near the Qinling Tunnel project area. ① Baoji–Xieyuguan–Taiyao fault zone; ② Youfang–Huangtai fault zone; ③ Tangzhi–Shangnan fault zone; ④ Shanyang–Fengzhen fault zone; ⑤ Yangpingguan–Yangxian fault zone; and ⑥ Raofeng–Shiquan fault zone.
Buildings 13 01924 g004
Figure 5. Landforms in river valleys along the tunnel.
Figure 5. Landforms in river valleys along the tunnel.
Buildings 13 01924 g005
Figure 6. Layout of boreholes.
Figure 6. Layout of boreholes.
Buildings 13 01924 g006
Figure 7. In situ stress test data using the HF method in the tunnel: (a) CZK-2; (b) CZK-3; and (c) SZK-2.
Figure 7. In situ stress test data using the HF method in the tunnel: (a) CZK-2; (b) CZK-3; and (c) SZK-2.
Buildings 13 01924 g007
Figure 8. Sketch of stereographic projection at the measurement point in the 6# testing section of the Qinling water conveyance tunnel: (a) Sketch showing the stereographic projection of unit vectors of the principal stress orientations; (b) Deformation and failure position of surrounding rock.
Figure 8. Sketch of stereographic projection at the measurement point in the 6# testing section of the Qinling water conveyance tunnel: (a) Sketch showing the stereographic projection of unit vectors of the principal stress orientations; (b) Deformation and failure position of surrounding rock.
Buildings 13 01924 g008
Figure 9. Computational model: (a) entity model; (b) mesh grid; and (c) major fractures.
Figure 9. Computational model: (a) entity model; (b) mesh grid; and (c) major fractures.
Buildings 13 01924 g009
Figure 10. Comparative histogram showing the principal stresses between the measured and calculated values at the measurement points: (a) maximum horizontal principal stress; (b) minimum horizontal principal stress; and (c) vertical principal stress.
Figure 10. Comparative histogram showing the principal stresses between the measured and calculated values at the measurement points: (a) maximum horizontal principal stress; (b) minimum horizontal principal stress; and (c) vertical principal stress.
Buildings 13 01924 g010
Figure 11. Distribution of the principal stress field at the axis of the Qinling water conveyance tunnel (unit: MPa): (a) the first principal stress; (b) the second principal stress; and (c) the third principal stress.
Figure 11. Distribution of the principal stress field at the axis of the Qinling water conveyance tunnel (unit: MPa): (a) the first principal stress; (b) the second principal stress; and (c) the third principal stress.
Buildings 13 01924 g011aBuildings 13 01924 g011b
Figure 12. Geological profile along the axis of the Qinling tunnel from K79 + 900 to K78 + 779.
Figure 12. Geological profile along the axis of the Qinling tunnel from K79 + 900 to K78 + 779.
Buildings 13 01924 g012
Figure 13. Image showing a failure in the surrounding rock of the Qinling tunnel: (a) left arch and (b) left side wall.
Figure 13. Image showing a failure in the surrounding rock of the Qinling tunnel: (a) left arch and (b) left side wall.
Buildings 13 01924 g013
Figure 14. Cross-section of the Phase I support in the surrounding rock (unit: cm).
Figure 14. Cross-section of the Phase I support in the surrounding rock (unit: cm).
Buildings 13 01924 g014
Figure 15. Computational model: (a) mesh model; (b) excavated tunnel and advanced small conduit model; and (c) tunnel system anchors with the shotcrete model.
Figure 15. Computational model: (a) mesh model; (b) excavated tunnel and advanced small conduit model; and (c) tunnel system anchors with the shotcrete model.
Buildings 13 01924 g015
Figure 16. Untimely initial support (unit: m): (a) horizontal deformation and (b) vertical deformation.
Figure 16. Untimely initial support (unit: m): (a) horizontal deformation and (b) vertical deformation.
Buildings 13 01924 g016
Figure 17. Timely initial support (unit: m): (a) horizontal deformation and (b) vertical deformation.
Figure 17. Timely initial support (unit: m): (a) horizontal deformation and (b) vertical deformation.
Buildings 13 01924 g017
Figure 18. Schematic diagram showing the in situ stress field in the surrounding rock (unit: kPa): (a) the first principal stress and (b) the third principal stress.
Figure 18. Schematic diagram showing the in situ stress field in the surrounding rock (unit: kPa): (a) the first principal stress and (b) the third principal stress.
Buildings 13 01924 g018
Table 1. The measured results for in situ stress in the Qinlin water conveyance tunnel.
Table 1. The measured results for in situ stress in the Qinlin water conveyance tunnel.
BoreholeMeasurement
Point No.
PositionDepth (m)σH (MPa)σh (MPa)σV (MPa)σH/σVσH Direction
CZK-21#K50 + 390353.018.1111.269.341.94N 52° W
2#507.8018.5311.6813.441.38N 47° W
3#548.7518.5312.6814.521.28/
4#597.1019.5113.3515.801.23/
5#631.1520.0413.8916.701.20N 37° W
6#646.8520.4914.1417.121.20/
CZK-37#K53 + 940265.509.126.107.031.30/
8#275.4010.216.707.291.40N 40° W
9#285.407.315.307.550.97/
10#310.409.066.548.211.10N 43° W
11#334.407.795.788.850.88/
12#341.408.365.859.030.93/
13#354.4012.498.479.381.33N 46° W
14#363.4013.088.569.621.36/
SZK-215#K64 + 315126.4017.7710.273.545.02N 16° E
16#195.4018.9610.965.473.47N 9° E
17#225.1519.2611.266.303.06/
18#238.2019.8911.396.672.98N 16° W
19#251.2022.0212.527.033.13N 33° W
20#270.9027.7116.717.593.65N 35° W
21#284.2529.8516.857.963.75/
Table 2. In situ stress test data using the 3-D HF method at the 6# testing section.
Table 2. In situ stress test data using the 3-D HF method at the 6# testing section.
Stress OrderFirst Principal Stress σ1Second Principal Stress σ2Third Principal Stress σ3
Magnitude/MPa25.415.514.1
Inclination/(°)38523
Azimuth/(°)28611218
Note: position, K67 + 350; borehole burial depth, 1000 m.
Table 3. Stress component conversion results at the 6# test hole.
Table 3. Stress component conversion results at the 6# test hole.
TypeStress Components/MPaHorizontal Principal Stress and Lateral Pressure Coefficient
σxxσyyσzzσxyσyzσzxσH/MPaσh/MPaλ = σH/σZ
Values14.721.119.22.14.61.221.714.11.1
Note: position, K67 + 350; borehole burial depth, 1000 m.
Table 4. Physical and mechanical parameters of the rock mass.
Table 4. Physical and mechanical parameters of the rock mass.
Type of Rock Mass Deformation
Modulus/(GPa)
Poisson Ratio Bulk Density/(kg/m3)
Granite (γ5)37.050.2026.6
Quartz diorite (δ4)24.300.2227.0
Variable sandstone12.670.2826.0
Sericite thousand rocks, quartz metasandstone7.660.3126.5
Hornblende schist, sericite mudstone15.480.2726.5
Granite (γ3)24.400.2126.5
Granodiorite, granite porphyry23.330.2226.9
Black cloud plagioclase gneiss15.080.2626.1
Mica schist, green clay, quartz schist6.810.3226.1
Dali rock sandwiched by mica schist17.770.2627.0
Mica quartz schist, chlorite schist10.620.3026.2
Faults1.000.3323.5
Table 5. Comparison between the measured data obtained using a field test and the calculated results using numerical simulation.
Table 5. Comparison between the measured data obtained using a field test and the calculated results using numerical simulation.
BoreholesMeasurement
Point No.
Data Originσx
/MPa
σy
/MPa
σz
/MPa
τxy
/MPa
σH
/MPa
σh
/MPa
Azimuth
/(°)
CZK-21#Measured15.51 13.86 9.34 −3.32 18.11 11.26 N 52° W
Calculated14.11 14.62 12.73 −1.63 16.01 12.72 N 40.52° W
2#Measured14.75 15.46 13.44 −3.41 18.53 11.68 N 42° W
Calculated15.60 15.64 15.82 −1.50 17.11 14.12 N 44.59° W
3#Measured15.30 15.91 14.52 −2.91 18.53 12.68 N 42° W
Calculated16.03 15.93 16.72 −1.45 17.43 14.53 N 43.99° W
4#Measured16.11 16.75 15.80 −3.06 19.51 13.35 N 42° W
Calculated16.47 16.27 17.64 −1.42 17.80 14.95 N 43.03° W
5#Measured16.12 17.81 16.70 −2.96 20.04 13.89 N 37° W
Calculated16.83 16.58 18.43 −1.39 18.10 15.31 N 42.38° W
6#Measured16.44 18.19 17.12 −3.05 20.49 14.14 N 37° W
Calculated16.92 16.65 18.63 −1.39 18.18 15.40 N 42.23° W
CZK-37#Measured7.35 7.87 7.03 −1.49 9.12 6.10 N 40° W
Calculated9.44 11.22 6.57 −3.57 14.00 6.65 N 38.01° W
8#Measured8.15 8.76 7.29 −1.73 10.21 6.70 N 40° W
Calculated10.19 12.70 7.40 −3.78 15.43 7.46 N 35.81° W
13#Measured10.55 10.41 9.38 −2.01 12.49 8.47 N 44° W
Calculated10.31 13.26 9.50 −4.02 16.06 7.51 N 34.94° W
14#Measured10.90 10.74 9.62 −2.26 13.08 8.56 N 46° W
Calculated10.22 13.32 10.21 −3.77 15.84 7.69 N 33.82° W
Table 6. Support parameters of the surrounding rock.
Table 6. Support parameters of the surrounding rock.
LocationSpray C20 Concrete Thickness (cm)Steel ArchesSecondary Lining
SpecificationSpacing (m)GradeThickness (cm)
Arches21I161.2C3040
Side walls21C3040
Motherboard///C3045
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Pei, Q.; Wang, X.; He, L.; Liu, L.; Tian, Y.; Wu, C. Estimation Method for an In Situ Stress Field along a Super-Long and Deep-Buried Tunnel and Its Application. Buildings 2023, 13, 1924. https://doi.org/10.3390/buildings13081924

AMA Style

Pei Q, Wang X, He L, Liu L, Tian Y, Wu C. Estimation Method for an In Situ Stress Field along a Super-Long and Deep-Buried Tunnel and Its Application. Buildings. 2023; 13(8):1924. https://doi.org/10.3390/buildings13081924

Chicago/Turabian Style

Pei, Qitao, Xiaonan Wang, Lihong He, Lu Liu, Yong Tian, and Cai Wu. 2023. "Estimation Method for an In Situ Stress Field along a Super-Long and Deep-Buried Tunnel and Its Application" Buildings 13, no. 8: 1924. https://doi.org/10.3390/buildings13081924

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop