1. Introduction
In the field of transportation infrastructure, long-span prestressed concrete continuous rigid-frame bridges are highly regarded for their exceptional spanning capacity, minimal support requirements, high traffic flow efficiency, and esthetic appeal [
1,
2,
3,
4,
5]. Nevertheless, the segmental construction of such large-span continuous rigid-frame bridge structures generally entails a prolonged and intricate construction process. According to conventional closure techniques, the multi-span closure process requires multiple structural system transformations. As construction progresses, both the structural configuration of the bridge and its load-bearing mechanisms undergo continuous evolution. The final dead-load internal forces within the structure are intrinsically linked to the closure sequence. Distinct construction sequences, characterized by varying initial dead-load internal forces, exhibit differential magnitudes of creep-induced internal force redistribution during structural system transitions. Furthermore, the adoption of different closure sequences significantly impacts both the construction schedule and project costs. Therefore, the selection of an appropriate closure sequence is paramount.
The first long-span prestressed concrete continuous rigid-frame bridge was the Bendendorf Bridge, constructed in 1964 in what was then West Germany, with a main span of 208 m. This bridge utilized thin-walled piers in place of the bulky T-shaped piers typical of rigid-frame bridges, with the side spans formed as a continuous system and the central span equipped with a shear hinge. This bridge type represented the prototype of the continuous rigid frame, maintaining the primary load-bearing characteristics of the T-shaped rigid-frame bridge. The Bendendorf Bridge not only exemplified the advantages of the cantilever construction method but also broke new ground in structural form with the pier-beam consolidation, creating a continuous rigid-frame system with hinges [
6]. Subsequently, as high-grade highways demanded smoother and more comfortable driving conditions, the T-shaped rigid-frame bridges with multiple expansion joints could no longer adequately meet the requirements, leading to significant development in the long-span continuous rigid-frame system, which began to be widely applied globally. With further advancements in building materials and construction methods, the Hamanako Bridge in Japan, with a main span of 240 m, was constructed in the 1970s [
7]; and in 1985, Australia built the then world’s longest continuous rigid-frame bridge, the Gateway Bridge, with spans of 145 m + 260 m + 145 m [
8]. In China, the construction of long-span continuous rigid-frame bridges started later, with the introduction of continuous rigid-frame bridge design and construction from abroad in 1988. In 1990, China completed its first long-span continuous rigid-frame bridge, the Guangdong Luoxi Bridge, with a main span of 180 m [
9]. The Luoxi Bridge was the first in China to employ a high-tonnage prestressing system, marking a milestone in the development of rigid-frame bridges in the country. Since then, continuous rigid-frame bridges in China have entered a phase of rapid development. To date, China has constructed over 80 continuous rigid-frame bridges with main spans exceeding 200 m and countless others with spans less than 200 m [
10].
Currently, the mature construction technology for continuous rigid-frame bridges generally follows the sequence of “symmetrical cantilever casting → side-span closure → central-span closure”. Due to the large span, multiple continuous spans, and high degree of indeterminacy of long-span continuous rigid-frame bridges, the completion of such bridges requires a long and complex process of structural system transformation. For continuous rigid-frame bridges with multiple spans, this construction sequence results in a prolonged construction period and high costs. Consequently, the traditional closure techniques have the drawback of an extended construction cycle. More significantly, the variability in the closure process can have a pronounced impact on the final permanent load internal force distribution of the multi-span continuous systems. After closure, the bridge structure transitions from a statically determinate to a statically indeterminate one, leading to a redistribution of internal forces. Different closure sequences can also result in considerable differences in the redistribution of internal forces due to creep and temperature changes, thereby affecting the overall mechanical performance of the bridge [
11,
12,
13,
14]. Therefore, optimizing the bridge closure process, reducing the number of internal force redistributions, and simplifying the calculation of structural internal forces have become important research areas for promoting the efficient and sustainable construction in the bridge engineering field.
Closure is one of the most critical construction steps in the construction of continuous rigid-frame bridges [
15]. Li [
16] has proposed a novel closure technique based on the equivalent load method, which involves pre-tensioning the tendons in the bottom slab of the box girder to eliminate the need for counterweights during closure. This approach effectively reduces disturbances during the closure process and aims for efficient construction, but it lacks analysis from the perspective of different closure sequences. Weng [
17] and others have developed eight closure schemes for a seven-span continuous rigid-frame bridge based on four principles: closing the side spans before the central span, closing the central span before the side spans, alternating the closure of side and central spans, and sequential closure. These schemes provide a comprehensive mechanical basis for the final closure construction plan, but they do not involve research into and an analysis of simultaneous closure schemes for both side and central spans. Yuan Hui and others [
18] have conducted research on the simultaneous closure of a four-span continuous rigid-frame bridge, analyzing the internal forces, deflections, and post-construction impacts of sequential and simultaneous closures, demonstrating the feasibility of simultaneous closure. Wu Haishan and colleagues [
19] have further proposed a method for the simultaneous casting of the side-span straight section and closure section using hanging baskets from a construction technology perspective. The study shows that this method has a minimal impact on the forces and deflections of the main girder on the central-span side, but it causes significant disturbance to the main girder on the side span and does not consider the long-term stability of the bridge’s alignment.
In light of this, this paper, based on the advantages of the simultaneous closure of side and central spans in continuous rigid-frame bridges, such as controlling deflection, evenly distributing loads, and reducing the number of statically indeterminate members [
20,
21,
22,
23,
24,
25,
26,
27], and in conjunction with the construction project of the right span of the Huangdong Daning River Bridge, a three-span continuous rigid-frame bridge in Guangxi, addresses the complex internal force conditions caused by low construction efficiency, the impact of Asynchronous Closure on concrete shrinkage and creep, the influence of temperature changes on measurement values, and the variation in temporary loads. This paper proposes a construction scheme for the simultaneous closure of multi-span continuous systems, analyzing the impact on the stress of the main girder, the alignment of the main girder, and the displacement of the pier top under the sequences of step-by-step closure and simultaneous closure after the completion of the bridge and over a ten-year period of shrinkage and creep. This provides a construction scheme for continuous rigid-frame bridges that ensures correct alignment, reasonable stress distribution, and rapid bridge completion.
2. Theoretical Analysis
For long-span continuous rigid-frame bridges, the geometric alignment and stress states of the main girder during closure construction under different procedures are influenced by cumulative factors from prior construction stages, such as concrete shrinkage, creep, and temperature variations. These factors lead to discrepancies between as-built outcomes and theoretical predictions, resulting in construction deviations. The theoretical analysis aims to establish quantitative relationships between critical parameters (e.g., creep effects) and structural responses of the bridge system. By formulating these dependencies, we identify dominant factors governing the deflection behavior of the two closure methods (synchronous vs. asynchronous). The derived relationships serve as predictive tools to provide a theoretical foundation for deflection calculations in similar large-span bridge projects.
2.1. Theoretical Analysis of Deflection Calculation Under Asynchronous Closure
The theoretical framework of this study is grounded in Chapter 6 of the first edition of
High-Pier Long-Span Continuous Rigid-Frame Bridges [
28]. In staged construction, the proportional coefficient
formed at point
is a time function related to the loading age
, as follows:
In Equation (1), represents the casting moment of segment and indicates that section 0 has just started pouring concrete.
To address temporal discrepancies in staged construction, a unified time coordinate system is implemented. This approach resolves ambiguities arising from discrepancies in load application ages, ensuring consistency between theoretical loading timelines and actual field conditions—a prerequisite for accurate long-term performance evaluation. The creep-induced deflection, accounting for time-dependent material behavior, is calculated as follows:
In Equation (2), represents the relative height; represents the temperature difference between the two measurements before and after tensioning; and represent the elastic modulus and cross-sectional area of the pier and abutment, respectively; represents the self-weight of the large beam of segment ; represents the time of the completion of segment ; and indicates that section 0 has just started pouring concrete.
The deflection under self-weight follows similar rules to creep and compression, and the calculation of deflection due to self-weight is as follows:
In Equation (3), , , represent the equivalent force arm from segment to the center of segment ; represents the self-weight of the large beam of segment ; represents the time of the completion of segment ; represents the casting moment of segment ; represents the abscissa of point ; represents the coordinate of the midpoint of segment ; and represent the elastic modulus and moment of inertia of the segment, respectively; and represent the shear modulus and cross-sectional area of the segment, respectively; and denotes the length of segment .
The deflection caused by the prestressing tension is expressed as follows:
In Equation (4), denotes the tension force of cable at cross-section and denotes the tensioning time at segment .
Under asynchronous closure, the deflection at point
before and after the tensioning of segment
is calculated as follows:
In summary, the process of asynchronous closure involves complex internal force changes. Due to variations in measurement timing and environmental conditions, all of which affect deflection, the influence of concrete shrinkage and creep is particularly significant. These factors can cause the main girder to gradually deflect downwards, impacting the long-term alignment of the bridge. Additionally, temperature changes induce thermal expansion and contraction effects in the main girder, thereby affecting the accuracy of deflection measurements. Moreover, fluctuations in temporary construction loads also influence the distribution of internal forces. These interwoven factors complicate the calculation and measurement of deflection, necessitating a comprehensive consideration to ensure the structural safety and performance of the bridge.
2.2. Theoretical Analysis of Deflection Calculation Under Synchronous Closure
The theoretical analysis of deflection calculation under the synchronous closure of side and middle spans of a bridge primarily considers the structural forces and deformations. By employing the finite element method, the bridge is discretized into multiple units, and the deflection is determined by solving the equilibrium equations of mechanics.
Based on the analysis of individual beam elements, the rotation angle of the cantilever beam in a continuous rigid-frame bridge is
The deflection at point
is calculated as follows:
The double integral can be interpreted as an area integral over a triangular region bounded by three vertical lines:
. By changing the order of integration and integrating with respect to
first, the expression becomes
To numerically approximate the integral over the interval
, the domain is partitioned into
K subintervals. Within each subinterval, the integrand is treated as a constant (evaluated at the midpoint value), thereby reducing the integral to a summation:
In Equation (9),
represents the bending moment at the midpoint of segment
after the completion of segment
and
denotes the torsional moment at the midpoint of segment
following the construction of segment
.
We can represent the moment of elastic deformation using a step function:
After the completion of section A, the height at Point B is
In Equation (13), represents the completion moment of section; denotes the tensioning moment of section ; and and respectively indicate the elastic modulus of the pier and the cross-sectional area.
Under the condition of the synchronous closure of side and middle spans, the height at point
is calculated as follows:
By combining Equations (13) and (14), Equation (15) can be derived:
Although
Section 2.1 and
Section 2.2 both address theoretical deflection calculations, they diverge fundamentally in their treatment of load types and temporal scales.
Section 2.1 employs elastic analytical methods for girder deflection analysis, incorporating time-dependent factors such as concrete shrinkage, creep, and tendon tensioning effects. This approach is tailored for the rapid analysis of asynchronous closure construction. In contrast,
Section 2.2 simplifies the girder model by considering only instantaneous elastic deformation (time-independent), making it suitable for the rapid evaluation of synchronous closure scenarios.
These distinct assumptions necessitate separate governing equations. This paper theoretically deduces the deflection calculation of the existing synchronous closing technology. By determining the main factors affecting the deflection of the two closing methods (concrete shrinkage and creep, tensile force, etc.), the deduced relationship will be used as a prediction tool to provide a theoretical basis for the deflection calculation of similar long-span bridge projects.