Time and Cost Overrun in the Saudi Arabian Oil and Gas Construction Industry
Abstract
:1. Introduction
2. Methodology
- Identify main causes of time and cost overruns from previous studies in various countries and industries. To ensure a comprehensive coverage of all relevant causes, the top ranked and frequently cited causes in the literature were aggregated. These causes were adopted as presented in these previous studies with no modifications to the original names, whereas, in some cases, the causes were modified to avoid ambiguity. Moreover, to maximize the validity of the identified causes, the causes cited in studies based on the oil and gas industry were assigned more weight. Next, the pool of identified causes was filtered such that the causes that were deemed to be inapplicable to the Saudi Arabian construction industry were eliminated. For example, government financial difficulties, shortage of construction materials, and floods were omitted as they were deemed to be irrelevant to the study area. Finally, other parameters were introduced based on the opinion of a professional with extensive experience in the Saudi Arabian oil and gas industry. The opinion of the mentioned subject matter expert was obtained to verify the validity, relevance and clarity of the proposed factors. The consulted expert was judged to be in the best position to provide useful insights given his extensive years of experience in the field as well as his experience working as a client, contractor and consultant. Such a unique blend of experience and broad perspective was difficult to find.
- Develop a questionnaire survey in order to assess the level of significance of the identified causes. The respondents were requested to assess the significance of the 38 identified causes based on their experience in the industry. This was accomplished with the aid of a 5-point Likert scale, with 5 corresponding to “extremely significant” and 1 to “insignificant”.
- Obtain responses from 48 oil and gas industry professionals practicing in the Eastern Province of Saudi Arabia. These professionals included 10 contractors, 26 consultants and 12 owners. The purpose of conducting this exercise was to gain an understanding on the main causes of time and cost overrun in oil and gas construction projects, as viewed by the industry professionals.
- Classify causes based on the source of cause for analysis purposes. This classification system led to grouping the 38 identified causes into seven categories. These seven categories are:
- ○
- All parties-related causes: causes induced directly or indirectly by all parties
- ○
- Consultant/designer-related causes: causes induced directly or indirectly by consultant/designer contribution in the project.
- ○
- Contract-related causes: causes influenced by policies of contracting and definition of parties’ relationship, as stated in the contract.
- ○
- Contractor-related causes: causes induced directly or indirectly by contractor performance in the project.
- ○
- External-related causes: external causes such as environment; macroeconomic; government regulations and laws; and market conditions.
- ○
- Owner-related causes: causes induced directly or indirectly by owner’s policies and procedures in the project.
- ○
- Resources-related causes: causes related to manpower (labor), raw material, and equipment.
- Classify causes based on time overrun and cost overrun separately.
- Analyze causes by computing significance index and ranking.
3. Previous Studies
3.1. Time and Cost Overruns in Developing Countries
3.2. Time and Cost Overruns in the Saudi Arabian Construction Industry
3.3. Time and Cost Overrun in the Oil and Gas Industry
4. Assessment of Causes of Time and Cost Overrun
- Respondent must be a contractor, consultant or owner in the oil and gas industry.
- Respondent must be a project manager, engineer, or manager with experience in oil and gas construction projects.
- Respondent must be practicing in the Eastern Province of Saudi Arabia.
5. Findings
6. Discussion
7. Test of Agreement
8. Conclusions and Recommendations
- The present study revealed that “changing of design and scope by client during construction” was the most significant cause of time and cost overrun. This finding suggests that it is of high significance that clients are aware that any change of scope, once the construction of these types of projects has commenced, can be extremely disruptive to the smooth progression of the project. The present study therefore recommends that clients invest sufficient time and funds in selecting the appropriate consultants. Once the proper consultant has been engaged, clients should ensure that their design intentions are understood by consultants.
- The present study concluded that “poor planning and scheduling of project” was among the most significant causes of time and cost overrun. In light of this finding, the study recommends that more attention should be directed at early stages of these projects. In addition, qualified personnel at managerial levels should be assigned to sensitive projects for proper planning of these projects. This should be followed by close monitoring to ensure that the time and cost of the actual project does not deviate from the planned project. Furthermore, periodical meetings should be conducted to ensure proper communication among parties [42].
- According to the findings, the two causes “Inadequate comprehension of scope of work at the bidding stage”, and “underestimating of cost and schedules/overestimating of benefits” were among the most significant causes of time and cost overrun. Therefore, the study recommends the adoption of an alternative bidding system other than the lowest bidder system. For example, the bidding system could be improved by conducting detailed analysis of contractors who would otherwise be disqualified by the lowest bidder system. Furthermore, extensive interviews with bidders in order to clarify vague or unclear issues that should be undertaken. Such precautionary measures could save significant costs during the construction stage and minimize the causes of time and cost overrun associated with unqualified contractors.
- Based on the findings of the present research which, indicated “design errors” as a significant cause of time and cost overrun, the study recommends that consultants develop a system for checking design before the commencement of construction. Moreover, consultants should focus on implementing a proper coordination system between different engineering departments. This is owing to the fact that one of the important causes of design errors in oil and gas construction projects is poor integration between different engineering disciplines.
Author Contributions
Acknowledgments
Conflicts of Interest
References
- Oberlender, G.D. Project Management for Engineering and Construction; McGraw-Hill: New York, NY, USA, 1993. [Google Scholar]
- Jackson, S. Project cost overruns and risk management. In Proceedings of the 18th Annual ARCOM Conference, Association of Researchers in Construction Management, Northumbria University, Newcastle, UK, 2–4 September 2002; pp. 1–10. [Google Scholar]
- Ahmed, S.M.; Azhar, S.; Castillo, M.; Kappagantula, P. Construction Delays in Florida: An Empirical Study; Final Report; Department of Community Affairs: Miami, FL, USA, 2002.
- Oil and Gas Industry Profile: Saudi Arabia. 2016, pp. 1–41. Available online: https://www.projectguru.in/publications/oil-gas-industry-saudi-arabia/ (accessed on 30 December 2016).
- International Energy Agency (IEA). World Energy Outlook; International Energy Agency: Paris, France, 2006. [Google Scholar]
- Dey, P.K. Project risk management using multiple criteria decision-making technique and decision tree analysis: A case study of Indian oil refinery. Prod. Plan. Control 2012, 23, 903–921. [Google Scholar] [CrossRef]
- Kaming, P.F.; Olomolaiye, P.O.; Holt, G.D.; Harris, F.C. Factors influencing construction time and cost overruns on high-rise projects in Indonesia. Constr. Manag. Econ. 1997, 15, 83–94. [Google Scholar] [CrossRef]
- Flyvbjerg, B.; Skamris-Holm, M.K.; Buhl, S.L. What causes cost overrun in transport infrastructure projects? Transp. Rev. 2004, 24, 3–18. [Google Scholar] [CrossRef]
- Assaf, S.A.; Al-Hajji, S. Causes of delay in large construction projects. Int. J. Proj. Manag. 2006, 24, 349–357. [Google Scholar] [CrossRef]
- Lo, T.Y.; Fung, I.W.; Tung, K.C. Construction delays in Hong Kong civil engineering projects. J. Constr. Eng. Manag. 2006, 132, 636–649. [Google Scholar] [CrossRef]
- Merewitz, L. Cost Overruns in Public Works; Institute of Urban and Regional Development, University of California: Berkeley, CA, USA, 1973. [Google Scholar]
- Arditi, D.; Gunaydin, H.M. Total quality management in the construction process. Int. J. Proj. Manag. 1997, 15, 235–243. [Google Scholar] [CrossRef]
- Atkinson, R. Project management: Cost, time and quality, two best guesses and a phenomenon, its time to accept other success criteria. Int. J. Proj. Manag. 1999, 17, 337–342. [Google Scholar] [CrossRef]
- Songer, A.D.; Molenaar, K.R. Project characteristics for successful public-sector design-build. J. Constr. Eng. Manag. 1997, 123, 34–40. [Google Scholar] [CrossRef]
- Avotos, I. Cost-relevance analysis for overrun control. Int. J. Proj. Manag. 1983, 1, 142–148. [Google Scholar] [CrossRef]
- Liu, L.; Zhu, K. A Stage-by-stage factor control framework for cost estimation of construction projects. J. Constr. Eng. Manag. 2007, 133, 91–95. [Google Scholar] [CrossRef]
- Aibinu, A.; Jagboro, G. The effects of construction delays on project delivery in Nigerian construction industry. Int. J. Proj. Manag. 2002, 20, 593–599. [Google Scholar] [CrossRef]
- Sambasivan, M.; Soon, Y.W. Causes and effects of delays in Malaysian construction industry. Int. J. Proj. Manag. 2007, 25, 517–526. [Google Scholar] [CrossRef]
- Morris, S. Cost and time overruns in public sector projects. Econ. Political Wkly. 1990, 25, M154–M168. [Google Scholar]
- Le-Hoai, L.; Lee, Y.D.; Lee, J.Y. Delay and cost overruns in Vietnam large construction projects: A comparison with other selected countries. KSCE J. Civ. Eng. 2008, 12, 367–377. [Google Scholar] [CrossRef]
- Alinaitwe, H.; Apolot, R.; Tindiwensi, D. Investigation into the causes of delays and cost overruns in Uganda’s public sector construction projects. J. Constr. Dev. Ctries. 2013, 18, 33–47. [Google Scholar]
- Flyvbjerg, B.; Skamris-Holm, M.K.; Buhl, S.L. How common and how large are cost overruns in transport infrastructure projects? Transp. Rev. 2013, 23, 71–88. [Google Scholar] [CrossRef]
- Bella, A.B. Cost Overruns and Time Delays in Highway and Bridge Projects in Developing Countries-Experiences from Cameroon. Master’s Thesis, Michigan State University, East Lansing, MI, USA, 2011. [Google Scholar]
- Mansfield, N.R.; Ugwu, O.O.; Doran, T. Causes of delay and cost overruns in Nigerian construction projects. Int. J. Proj. Manag. 1994, 12, 254–260. [Google Scholar] [CrossRef]
- Frimpong, Y.; Oluwoye, J.; Crawford, L. Causes of delay and cost overruns in construction of groundwater projects in a developing countries; Ghana as a case study. Int. J. Proj. Manag. 2003, 21, 321–326. [Google Scholar] [CrossRef]
- Enshassi, A.; AlNajjar, J.; Kumaraswamy, M. Delays and cost overruns in the construction projects in the Gaza strip. J. Financ. Manag. Prop. Constr. 2009, 14, 126–151. [Google Scholar] [CrossRef]
- Abd El-Razek, M.E.; Bassioni, H.A.; Mobarak, A.M. Causes of delay in building construction projects in Egypt. J. Constr. Eng. Manag. 2008, 134, 831–841. [Google Scholar] [CrossRef]
- Al-Khalil, M.I.; Al-Ghafly, M.A. Important causes of delay in public utility projects in Saudi Arabia. Constr. Manag. Econ. 1999, 17, 647–655. [Google Scholar] [CrossRef]
- Zamel, S.A.I. Construction Cost Control in the Eastern Province of Saudi Arabia. Master’s Thesis, King Fahd University of Petroleum and Minerals, Dhahran, Saudi Arabia, 1991. [Google Scholar]
- Al-Dubaisi, A.H. Change Orders in Construction Projects in Saudi Arabia. Master’s Thesis, King Fahd University of Petroleum and Minerals, Dhahran, Saudi Arabia, 2000. [Google Scholar]
- Thuyet, N.V.; Ogunlana, S.O.; Dey, P.K. Risk management in oil and gas construction projects in Vietnam. Int. J. Energy Sector Manag. 2007, 1, 175–194. [Google Scholar] [CrossRef]
- Fallahnejad, M.H. Delay causes in Iran gas pipeline projects. Int. J. Proj. Manag. 2013, 31, 136–146. [Google Scholar] [CrossRef]
- Ruqaishi, M.; Bashir, H.A. Causes of delay in construction projects in the oil and gas industry in the gulf cooperation council countries: A case study. J. Manag. Eng. 2013, 31, 05014017. [Google Scholar] [CrossRef]
- Derakhshanalavijeh, R.; Teixeira, J.M.C. Cost overrun in construction projects in developing countries, gas-oil industry of Iran as a case study. J. Civ. Eng. Manag. 2017, 23, 125–137. [Google Scholar] [CrossRef]
- Kaliba, C.; Muya, M.; Mumba, K. Cost Escalation and Schedule Delays in Road Construction Projects in Zambia. Int. J. Proj. Manag. 2009, 27, 522–531. [Google Scholar] [CrossRef]
- Shehu, Z.; Endut, I.R.; Akintoye, A. Factors Contributing to Project Time and Hence Cost Overrun in the Malaysian Construction Industry. J. Financ. Manag. Prop. Constr. 2014, 19, 55–75. [Google Scholar] [CrossRef]
- Kikwasi, G. Causes and Effects of Delays and Disruptions in Construction Projects in Tanzania. Australasian J. Constr. Econ. Build. Conf. Ser. 2013, 1, 52–59. [Google Scholar] [CrossRef]
- Dominowski, R.L. Research Methods; Prentice-Hall: Englewood Cliff, NJ, USA, 1980. [Google Scholar]
- Enshassi, A.; Mohamed, S.; El Karriri, A.A. Factors Affecting the Bid/No Bid Decision in the Palestinian Construction Industry. J. Financ. Manag. Prop. Constr. 2010, 15, 118–142. [Google Scholar] [CrossRef]
- Bagaya, O.; Song, J. Empirical Study of Factors Influencing Schedule Delays of Public Construction Projects in Burkina Faso. J. Manag. Eng. 2016, 32. [Google Scholar] [CrossRef]
- Aczel, A.D.; Sounderpandian, J.; Saravanan, P.; Rohit, J. Complete Business Statistics, 7th ed.; McGraw-Hill: Boston, MA, USA, 2012. [Google Scholar]
- Al-Sofi, M. Interview, Executive Managing Partner at the Arabian Consulting Engineering Center (ACEC); ACEC: Khobar, Saudi Arabia, 2017. [Google Scholar]
Reference | Country | Industry | Major causes of time and cost overrun |
---|---|---|---|
[7] | Indonesia | High-rise buildings | Time: “design changes”, “poor labour productivity”, “inadequate planning”, and “inadequate planning”, and “resource shortages” Cost: material cost increases due to inflation”, “inaccurate materials estimating”, and “degree of project complexity” |
[24] | Nigeria | Construction project | Cost “finance and payment arrangements”, “poor contract management”, “materials shortages”, “inaccurate estimating”, and “overall price fluctuations” |
[25] | Ghana | Ground water | “monthly payment difficulties from agencies”, “poor contractor management”, “material procurement”, “poor technical performances”, and “escalation of material prices” |
[20] | Vietnam | Building and industrial projects | “poor site management and supervision”, “poor project management assistance”, “financial difficulties of owner”, “financial difficulties of contractor”, and “design changes” |
[26] | Palestine | Construction projects | “price fluctuations of construction materials”, “contractor delays in material and equipment delivery”, and “inflation”. |
[21] | Uganda | Public sector projects | “changes in the work scope”, “delayed payments to contractors”, “poor monitoring and control”, and “high inflation and interest rates” |
[27] | Egypt | Construction projects | “financing by contractor during construction”, “delays in contractor’s payment by owner”, “design changes by owner or his agent during construction”, “partial payments during construction”, and “nonutilization of professional construction/contractual management” |
[9] | Saudi Arabia | Construction projects | Change order |
[10] | China | civil engineering projects | “Inadequate resources due to contractor/lack of capital”, “Unforeseen ground conditions”, “Exceptionally low bids”, “Inexperienced contractor”, “Works in conflict with existing utilities” |
[32] | Iran | Pipeline construction projects | “imported materials”, “unrealistic project duration”, “client-related materials”, “land expropriation”, “change orders” |
[33] | Oman | Oil and gas | “poor site management and supervision by contractors”, “problems with subcontractors”, “inadequate planning and scheduling of the project by contractors”, “poor management of contractors’ schedules”, “delay in delivery of materials” |
[34] | Iran | Oil and gas | “inaccurate cost estimations”, “improper planning”, “frequent design changes”, “inadequate labour/skill availability”, “inflation of costs of machinery” |
[35] | Zambia | road construction projects | Cost “bad or inclement weather due to heavy rains and floods”, “scope changes”, “environmental protection and mitigation costs”, “schedule delay”, “strikes” Time “delayed payments”, “financial processes and difficulties on the part of contractors and clients”, “contract modification”, “economic problems”, “materials procurement” |
[36] | Malaysia | Construction projects | “cash flow problems faced by the contractors” and “late payment from contractors to sub-contractors or suppliers” |
[37] | Tanzania | Construction projects | Causes of delay “design changes”, “delays in payment to contractors”, “information delays”, “funding problems”, “poor project management”, compensation issues and disagreement on the valuation of work done. |
Overall (n = 48) | Owners (n = 12) | Contractors (n = 10) | Consultants (n = 26) | |||||||
---|---|---|---|---|---|---|---|---|---|---|
No. | Causes | SI | RG | RO | SI | RO | SI | RO | SI | RO |
All Parties-related causes | ||||||||||
1 | Incompetent project team | 3.35 | 2 | 12 | 3 | 26 | 3.6 | 10 | 3.44 | 13 |
2 | Personality clash between two or more members from different parties | 2.40 | 3 | 38 | 2.11 | 38 | 2.875 | 36 | 2.22 | 38 |
3 | Poor planning and scheduling of project | 3.72 | 1 | 2 | 3.64 | 3 | 3.8 | 3 | 3.73 | 3 |
Consultant/designer-related causes | ||||||||||
4 | Design errors | 3.65 | 1 | 3 | 3.55 | 5 | 3.7 | 6 | 3.69 | 4 |
5 | Inadequate cost estimating approach /inaccurate material estimation | 3.34 | 2 | 13 | 3.3 | 9 | 3.3 | 23 | 3.42 | 15 |
6 | Inadequate quality control/assurance | 3.34 | 3 | 14 | 3.18 | 16 | 3.6 | 8 | 3.23 | 21 |
7 | Negligence of site visits before/during the bidding process | 3.32 | 4 | 16 | 3.2 | 14 | 3.56 | 12 | 3.2 | 23 |
8 | Inadequate management of contractor’s schedule by consultant | 3.03 | 7 | 27 | 2.78 | 29 | 3.22 | 25 | 3.08 | 28 |
9 | Unforeseen conditions and structural modifications | 3.29 | 5 | 18 | 3.3 | 10 | 3.4 | 19 | 3.16 | 24 |
10 | Weak and insufficient technical studies | 3.28 | 6 | 19 | 3.11 | 18 | 3.44 | 15 | 3.28 | 18 |
Contract-related causes | ||||||||||
11 | Poor communication among the parties | 3.48 | 1 | 7 | 3.73 | 2 | 3.3 | 20 | 3.42 | 14 |
12 | Discrepancies in contract documents | 3.19 | 3 | 23 | 3 | 25 | 3.1 | 32 | 3.46 | 11 |
13 | Poorly defined payment milestones | 3.10 | 4 | 26 | 2.5 | 33 | 3.7 | 5 | 3.09 | 27 |
14 | Lack of communication with suppliers in the engineering and procurement phases | 3.45 | 2 | 8 | 3.55 | 4 | 3.5 | 13 | 3.29 | 17 |
Contractor-related causes | ||||||||||
15 | Financing project by contractor during construction | 2.93 | 9 | 35 | 2.33 | 35 | 3.22 | 24 | 3.25 | 20 |
16 | Inadequate or insufficient contractor experience | 3.30 | 4 | 17 | 3 | 23 | 3.3 | 22 | 3.6 | 7 |
17 | Poor project implementation strategies | 3.20 | 5 | 21 | 3.2 | 15 | 3.2 | 29 | 3.21 | 22 |
18 | Inadequate management and supervision of site | 3.42 | 2 | 9 | 3 | 22 | 4 | 1 | 3.25 | 19 |
19 | Inadequate comprehension of scope of work at the bidding stage | 3.58 | 1 | 4 | 3.36 | 7 | 3.6 | 7 | 3.77 | 2 |
20 | Subcontractor-related problems | 3.20 | 6 | 22 | 3.2 | 13 | 3.4 | 16 | 3 | 29 |
21 | Rework due to errors during construction | 3.18 | 7 | 24 | 2.6 | 32 | 3.4 | 18 | 3.54 | 9 |
22 | Underbidding | 3.38 | 3 | 11 | 3 | 21 | 3.56 | 11 | 3.58 | 8 |
23 | Unreasonable adjustment of project cost by contractors | 3.00 | 8 | 29 | 3 | 27 | 3 | 34 | 3 | 30 |
External-related causes | ||||||||||
24 | Variations in market conditions | 2.96 | 1 | 33 | 3.3 | 8 | 2.7 | 37 | 2.88 | 33 |
25 | Cost inflation of machinery | 2.73 | 2 | 36 | 2.5 | 34 | 2.89 | 35 | 2.8 | 36 |
26 | Impact of hot weather on construction work | 2.47 | 3 | 37 | 2.3 | 37 | 2.6 | 38 | 2.5 | 37 |
Owner-related causes | ||||||||||
27 | Adoption of fast-track project delivery strategy | 3.00 | 7 | 30 | 2.89 | 28 | 3.22 | 26 | 2.88 | 35 |
28 | Deficient documentation and incomplete scope definition | 3.40 | 3 | 10 | 3.36 | 6 | 3.2 | 27 | 3.64 | 6 |
29 | Changing of design and scope by client during construction | 3.79 | 1 | 1 | 3.91 | 1 | 3.8 | 2 | 3.65 | 5 |
30 | Long project approval procedures | 3.02 | 6 | 28 | 3.09 | 20 | 3.1 | 31 | 2.88 | 34 |
31 | Many stakeholders | 3.22 | 5 | 20 | 3.1 | 19 | 3.6 | 9 | 2.96 | 31 |
32 | Poor definition of subsurface data | 2.97 | 8 | 32 | 2.78 | 30 | 3.2 | 28 | 2.92 | 32 |
33 | The lowest bid price system | 3.33 | 4 | 15 | 3.27 | 11 | 3.3 | 21 | 3.42 | 16 |
34 | Underestimating of cost and schedules/overestimating of benefits | 3.49 | 2 | 5 | 3.18 | 17 | 3.5 | 14 | 3.79 | 1 |
Resources-related causes | ||||||||||
35 | Labors’ lack of skills and productivity | 2.96 | 4 | 34 | 2.33 | 36 | 3.1 | 33 | 3.44 | 12 |
36 | Lack of equipment | 2.98 | 3 | 31 | 2.75 | 31 | 3.11 | 30 | 3.09 | 26 |
37 | Manpower shortage | 3.17 | 2 | 25 | 3 | 24 | 3.4 | 17 | 3.12 | 25 |
38 | Material procurement issues | 3.48 | 1 | 6 | 3.27 | 12 | 3.7 | 4 | 3.48 | 10 |
No. | Causes | SI |
---|---|---|
All Parties-related causes | ||
1 | Incompetent project team | 3.35 |
2 | Personality clash between two or more members from different parties | 2.40 |
3 | Poor planning and scheduling of project | 3.72 |
Consultant/designer-related causes | ||
4 | Design errors | 3.65 |
6 | Inadequate quality control/assurance | 3.34 |
8 | Inadequate management of contractor’s schedule by consultant | 3.03 |
9 | Unforeseen conditions and structural modifications | 3.29 |
10 | Weak and insufficient technical studies | 3.28 |
Contract-related causes | ||
11 | Poor communication among the parties | 3.48 |
12 | Discrepancies in contract documents | 3.19 |
13 | Poorly defined payment milestones | 3.10 |
14 | Lack of communication with suppliers in the engineering and procurement phases | 3.45 |
Contractor-related causes | ||
15 | Financing project by contractor during construction | 2.93 |
16 | Inadequate or insufficient contractor experience | 3.30 |
17 | Poor project implementation strategies | 3.20 |
18 | Inadequate management and supervision of site | 3.42 |
19 | Inadequate comprehension of scope of work at the bidding stage | 3.58 |
20 | Subcontractor-related problems | 3.20 |
21 | Rework due to errors during construction | 3.18 |
External-related causes | ||
26 | Impact of hot weather on construction work | 2.47 |
Owner-related causes | ||
28 | Deficient documentation and incomplete scope definition | 3.40 |
29 | Changing of design and scope by client during construction | 3.79 |
30 | Long project approval procedures | 3.02 |
31 | Many stakeholders | 3.22 |
32 | Poor definition of subsurface data | 2.97 |
Resources-related causes | ||
35 | Labors’ lack of skills and productivity | 2.96 |
36 | Lack of equipment | 2.98 |
37 | Manpower shortage | 3.17 |
38 | Material procurement issues | 3.48 |
No. | Causes | SI |
---|---|---|
Consultant/designer-related causes | ||
5 | Inadequate cost estimating approach /inaccurate material estimation | 3.34 |
7 | Negligence of site visits before/during the bidding process | 3.32 |
22 | Underbidding | 3.38 |
23 | Unreasonable adjustment of project cost by contractors | 3.00 |
External-related causes | ||
24 | Variations in market conditions | 2.96 |
25 | Cost inflation of machinery | 2.73 |
Owner-related causes | ||
27 | Adoption of fast-track project delivery strategy | 3.00 |
33 | The lowest bid price system | 3.33 |
34 | Underestimating of cost and schedules/overestimating of benefits | 3.49 |
Category. | No. Causes | SI | Rank |
---|---|---|---|
All Parties | 3 | 3.16 | 5 |
Consultant | 7 | 3.32 | 1 |
Contract | 4 | 3.30 | 2 |
Contractor | 9 | 3.24 | 4 |
External | 3 | 2.72 | 7 |
Owner | 8 | 3.28 | 3 |
Resources | 4 | 3.15 | 6 |
© 2019 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (http://creativecommons.org/licenses/by/4.0/).
Share and Cite
Bin Seddeeq, A.; Assaf, S.; Abdallah, A.; Hassanain, M.A. Time and Cost Overrun in the Saudi Arabian Oil and Gas Construction Industry. Buildings 2019, 9, 41. https://doi.org/10.3390/buildings9020041
Bin Seddeeq A, Assaf S, Abdallah A, Hassanain MA. Time and Cost Overrun in the Saudi Arabian Oil and Gas Construction Industry. Buildings. 2019; 9(2):41. https://doi.org/10.3390/buildings9020041
Chicago/Turabian StyleBin Seddeeq, Abdulaziz, Sadi Assaf, Abdullatif Abdallah, and Mohammad A. Hassanain. 2019. "Time and Cost Overrun in the Saudi Arabian Oil and Gas Construction Industry" Buildings 9, no. 2: 41. https://doi.org/10.3390/buildings9020041
APA StyleBin Seddeeq, A., Assaf, S., Abdallah, A., & Hassanain, M. A. (2019). Time and Cost Overrun in the Saudi Arabian Oil and Gas Construction Industry. Buildings, 9(2), 41. https://doi.org/10.3390/buildings9020041