4. Decarbonized Coal-Based Super-Critical Power Plants, Main Design Characteristics, and Assessment Methodology
As a targeted industrial process to be decarbonized by membrane systems, a 330 MW net output coal power plant was investigated, using lignite coal as a fuel. The decarbonization yield is 90% the same as most of the CCS projects [
93]. As can be distinguished from
Figure 4, the flue gas out of the coal combustion process must be subjected to particulate matter (NO
x and SO
x) removal before the CO
2 capture process.
Table 7 presents the main technical assumptions of investigated CFPP and membrane.
All processes were modeled and simulated by using ChemCAD software. The paper analyzed different parameters of the compressor pressure, membrane surface area, and vacuum pump pressure (if used) in many cases to estimate the techno-economic influence of the analyzed CO2 capture solutions and achieve the membrane efficiency of 90% and CO2 purity of 95% with at least the minimum energy consumption required. However, power consumption in membrane technology is only the energy required for the main driving machines such as compressors and vacuum pumps.
To evaluate the techno-economic influence of the analyzed CO
2 capture solutions, the following indicators have been proposed [
96]:
—specific primary energy consumption for avoiding CO
2 emissions;
where
: the overall efficiency of energy solutions without CCS technology,
: the overall efficiency of energy solutions with CCS technology,
: the CO2 pollutant in kg/kWh produced by the CFPP without capture technology,
: the CO2 pollutant in kg/kWh produced by the CFPP with capture technology.
—takes into account the energy penalty
of the energy solution because of the extra heat consumption demanded in the chemical absorption process (
—Equation (2)), and the electricity consumption required by the capture process using membranes (
—Equation (3)):
where
: the net power generated for the energy solution without capture solution;
: the net power generated for the energy solution with capture solution.
The levelized cost of electricity (
) was calculated by Equation (4), considering the annualized
and
costs, a specified CO
2 recovery (
and the CO
2 recovery flow (
, where 6570 demonstrates 75% of annual capacity of hours:
Both recovery and avoided costs of CO
2 indicators are calculated by taking the consideration
,
, and specific CO
2 emissions for energy solution with and without CCS solution:
In order to set the economic indicators, several data on the unit costs of the components are presented in
Table 8. The presented costs are calibrated to the year 2022 based on the index demonstrated on the Chemical Engineering online site [
97].
In order to be able to determine whether an investment project, in this case, the CFPP with and without CO2 capture, is economically appropriate, an economic and financial analysis is required that considers all cash flows in and out of the established meter. The economic and financial indicators calculated in this analysis are as follows:
Net present value (
) calculated with Equation (7):
where
: the realized revenues for a year
(€/year);
: the operating and maintenance expenses for the year
, with taxes and duties but without depreciation (€/year);
: the annuity for the year
, if a loan was taken (€/year);
: the realized equity investment for the year
(€/year);
: the discount rate, which for the energy sector is 8%.
Internal rate of return (
) was determined utilizing Equation (8).
for an investment project is equal to the discount rate for which is 0.
Discounted payback period (
) was determined by Equation (9).
is the period of time after which the initial investment is recovered.
The profitability index (
) was calculated using Equation (10)
where
: the discounted investment. An investment project is economically efficient if
≥ 1; for
< 1 the project is economically inefficient.
5. Results and Discussion
In Case A (no vacuum pump used), various compressor pressures (1.5–10 bar) were used, while all other parameters were fixed. CO2 capture efficiency rose visibly with the increase of 1st compressor pressure (CP1), and the power consumption value rose as well. On the other hand, when CP1 was fixed and 1st membrane surface (SA1) differed from 100,000 to 1,000,000 m2, CO2 capture efficiency and power consumption increased significantly depending on the raising of CO2 captured. The 90% efficiency required for the process was obtained at 8.5 bar and 300,000 m2 SA1, while the energy consumption at this point was about 153 MW, and CO2 purity was 49%. However, the maximum CO2 purity achieved was 64% at 9.5 bar and 100,000 m2, which is quite low. The results show increasing the membrane surface area leads to a decrease in CO2 purity due to the other particles (e.g., N2) that pass through the membrane with CO2 molecules at a higher membrane surface.
Case B demonstrates the utilization of vacuum pump (VP) pressures (0.05–0.5 bar) while the other parameters are constant. The results showed an obvious increase in CO2 capture efficiency when VP pressure decreased due to the high-pressure difference across the membrane unit. Thus, the power consumption value rose with the decrease of VP pressure. The 90% efficiency required for the process was obtained at 5.5 bar CP1, 200,000 m2 membrane SA1, and 0.15 bar VP pressure. At the same parameters, the CO2 purity was 68% and power consumption was about 145 MW. Moreover, the highest CO2 purity value was achieved at 2 bar CP1, 0.05 bar VP pressure, and 100,000 m2, which is 84%.
Since CO2 capture efficiency requires a large surface area and CO2 purity needs a low surface area to be high, 2-stages of membrane units have been recommended to manipulate and increase both the values of CO2 capture efficiency and CO2 purity (case C).
In case C, different parameters of CP
1 (2–10 bar) were used where all other parameters were constant. Consequently, the CO
2 capture efficiency increased obviously with increasing CP
1, and the power consumption rose as well. The 2nd compressor pressure (CP
2) rose from 2 to 10 bar while fixing all other components, influenced and increased the 2nd membrane efficiency, and also impacted the CO
2 purity. The moment when SA
1 increased and all other parameters were constant, CO
2 capture efficiency and power consumption rose excessively due to the CO
2 captured rising. On the other hand, the leading factor that influenced the CO
2 purity was the 2nd membrane surface (SA
2), which increased from 5000 to 100,000 m
2, where CO
2 purity decreased constantly with the increase of the surface area. The efficiency and CO
2 purity required for the process (90%, and 95%, respectively) were achieved at 8 bar CP
1, 4 bar CP
2, 600,000 m
2 SA
1, and 40,000 m
2 of SA
2. Moreover, the energy consumed in this case was around 189 MW, which is almost 57% of the total output of energy (330 MW). As shown in
Figure 7, the flue gas exits from the second membrane has to be sent back to the mixer as a recirculated flue gas in order to increase CO
2 capture efficiency.
The parameters (such as VP, SA1, and CP1) were selected and fixed for all the following figures only to illustrate the variations among the variants.
In
Figure 8, the influence of VP and CP
1 on CO
2 capture efficiency was analyzed. In the (no vacuum) line, the maximum capture efficiency value achieved was 87% at high CP
1 (10 bar), while in 0.05 bar VP, the efficiency was much more than other efficiencies, reaching 99.9 % at 10 bar CP
1 due to the high-pressure difference around the membrane. The impact of reducing VP on process efficiency was also clearly apparent. Moreover, it was also demonstrated that CO
2 capture efficiency increases when CP
1 increases successively because of the high CO
2 content passed via the membrane unit.
Figure 9 presents how the CO
2 purity differs based on the compressor and vacuum pump pressure. The necessity of utilizing a vacuum pump is clear to increase CO
2 purity, where the highest amount achieved in no vacuum case is 62%. This value is poor compared with CO
2 purity after using different vacuum pump pressures. On the other hand, increasing compressor pressure value leads to high CO
2 purity till a specific value of the pressure where other molecules (such as N
2) will pass through the membrane decreasing CO
2 purity.
The impact of increasing vacuum pump pressure on CO
2 capture efficiency at various CP
1 is demonstrated below in
Figure 10. The efficiency lines go down decreasingly at different CP
1, as a result of the reduction of the pressure difference across the membrane. For example, CO
2 capture efficiency at the point where CP
1 and VP
1 are 10, 0.5 bar, respectively, is higher than what is at 5.5 bar CP
1 and VP
1 of 0.05 bar due to the high pressure difference.
In
Figure 11, the CO
2 capture efficiency rises directly when the membrane surface increases in various CP
1 values. At 10 bar CP
1, it is evident that the efficiency over different membrane surface areas is almost steady at 100% due to the flow that is almost fully captured and being passed through the membrane.
Figure 12 demonstrates the influence of the membrane surface at different compressor pressures. The power consumption increases continuously as the membrane surface increases at any CP
1 (1.5–10 bar); it is also noticeable that the power consumption columns are taller when the CP
1 rises due to the high gas flow that passed through the membrane unit. Typically, the power consumption required relies basically on the compressor and vacuum pump energy, and also on the power needed to compress the CO
2 stream at 70 bar which increases constantly with the rise of the membrane surface.
In
Figure 13, the impact of the SA
1 with various CP
1 on CO
2 purity has been examined, where the purity reduced slightly at 1.5 bar because of the low compressor pressure value utilized, while at 5 bar the CO
2 purity level was favorable in 100,000 m
2 of SA
1, almost 70% mole. As discussed before in the results section (case A), when the membrane surface increases the CO
2 purity decreases constantly.
Figure 14 below shows the effect of CP
2 on CO
2 capture efficiency in different CP
1. It is noticeable that CO
2 capture efficiency increases crucially when the CP
1 rises, reaching almost 100 % at 10 bar and CP
2 at 4 bar. The figure also demonstrates that CP
2 has a low impact on CO
2 capture efficiency due to its location after the 1st membrane unit (see
Figure 7). The explication of that tiny decrease in CO
2 capture efficiency regarding CP
2 is that the increase of CP
2 leads to a rise in the 2nd membrane CO
2 efficiency which drives a decrease in the recirculated flow to the mixer, finally reducing the flow rate entering the 1st membrane.
Figure 15 represents the influence of different SA
1 on CO
2 capture efficiency. The CO
2 capture efficiency line goes up obviously with the increase of SA
1 because of the high stream flow passed via the membrane at a higher membrane surface, obtaining almost 95% at 600,000 m
2.
In
Figure 16, the impact of CP
1 on power consumption at different CP
2 has been shown. The main factor that influences the total power consumption rate is CP
1 because of the recirculated flue gas that fuses with the primary flue stream to generate a high flow rate that boosts the power needed to pressure the flow at the 1st compressor. Since the high CP
2 pressures increase the 2nd membrane efficiency, the low recirculated flow decreases constantly, thus providing a lower flow rate entering the 1st compressor, which demonstrates why power consumption reduces at high CP
2.
Figure 17 shows the effect of the 2nd membrane surface area on CO
2 purity at different CP
2. All CO
2 purity lines go down permanently with the increase of membrane surface due to the transit of other components that pass through larger membrane surface (like N
2) producing low CO
2 purity. Furthermore, the CP
2 affects CO
2 purity, where higher CP
2 leads to less CO
2 purity.
Figure 18 below represents the CO
2 purity difference between the 1st and 2nd stages regarding various CP
2. Firstly, it is distinguished that the CO
2 purity of the 2nd membrane is much higher than that of the first because of the low surface area (20,000 m
2) used in the 2nd membrane, which shows the significance of utilizing 2-stages of membrane unit. Typically, CO
2 purity is reduced at high pressures. The influence of high CP
2 on the 2nd membrane is more than in the first due to its location (see
Figure 7).
On the other hand,
Figure 19 demonstrates the variation of CO
2 purity of single-stage (with and without vacuum pump) and 2-stages membrane based on 1st compressor pressure. Low CO
2 purity is remarkable in the 1-stage of the membrane (with and without a vacuum pump) due to the high membrane surface used (400,000 m
2). Integrated 2-stages of membrane increase the CO
2 purity with the rise of CP
1 reaching almost 99% at 6 bar. It is observable that all the steam flow contents which passed through the 2nd membrane are CO
2 molecules. However, the usage of the 2nd stage of the membrane is highly recommended to increase CO
2 purity.
Figure 20 exhibits how the CO
2 capture efficiency of single-stage (with and without a vacuum pump) and the 2-stage membrane is affected by 1st compressor pressure. The CO
2 capture efficiency line of single-stage with vacuum is remarkably higher than other lines, where the usage of a vacuum pump increases the pressure difference across the membrane unit, producing high CO
2 capture efficiency.
Figure 21 demonstrates the impact of 1st compressor pressure on power plant efficiency at different 1-single stage membrane surfaces. As shown, high compressor pressure increases the energy consumption required for CCS, which drives to decrease the power plant efficiency. As described before, a high membrane surface such as 700,000 m
2 increases CO
2 capture efficiency, therefore, generating a significant demand for energy to compress the CO
2 flow. Thus, the power plant efficiency decreases.
Figure 22 shows a comparison of power plant efficiencies regarding 1-stage (no vacuum used), 1-stage (with vacuum), and 2-stages of the membrane. As mentioned above, high compressor pressure decreases the power plant efficiency either for the 1-single stage or 2-stages of the membrane. As shown, the power plant efficiency of 2-stages is higher than the efficiency of one stage due to the lower energy demanded for the 2-stage of membrane case.
Figure 23 represents the difference in capital cost of various membrane surfaces of the 1-single stage based on different 1st compressor pressure. The capital cost lines of the surfaces increase and go up noticeably achieving 10,000 €/kWh at 10 bar of 700,000 m
2. High surfaces raise the capital cost and also high compressor pressure influences the cost due to the high CO
2 content passed through the membrane, which increases the power consumption required.
The influence of SA
1 on CO
2 capture efficiency of one (with and without VP) and 2-stages of the membrane is shown in
Figure 24. The case where the 1-single stage of the membrane with vacuum is used has the highest values of CO
2 capture efficiency due to the high-pressure difference across the membrane unit. At 400,000 m
2 of SA
1, 1-stage (with vacuum) of membrane achieved almost 100% CO
2 capture efficiency. While, in the same point, CO
2 capture efficiency is less by around 6% and 13% for 1-stage (no vacuum) and 2-stages of the membrane, respectively.
Figure 25 exhibits the variation of power plant efficiency of single-stage (with and without vacuum pump) and 2-stages of membrane regarding SA
1. As noticed from the figure, at 200,000 m
2, the power plant efficiency for 2-stages and no vacuum case of the membrane are almost the same, which are the highest, while utilization of vacuum pump in the 1-stage reduces the power plant efficiency by around 16% because of the low power consumption needed for capture CO
2 comparing with 1-stage no vacuum case. By increasing SA
1 the power plant efficiency lines of all stages go down constantly due to the increase of CO
2 capture efficiency with SA
1 increase, which leads to high demands of energy.
Figure 26 represents the effect of SA
1 on discounted payback period (DPP) of 1-stage (with and without vacuum pump) and 2-stages of the membrane. The SA
1 of 1-stage (no vacuum) of the membrane has a low influence on DPP, which is the best case due to the low requirements of energy for CO
2 capture compared with other cases. It is observable that increasing SA
1 leads to an increase in DPP because of the high demand for power consumption.
To evaluate the technical and economic assessment for the case A, the different parameters in
Table 9 are chosen based on the optimum results of CO
2 capture efficiency, CO
2 purity, and power consumption (
Figure 27). To abbreviate the surface area and compressor pressure parameters of case A, it was considered that case A
12 represents 200,000 m
2 of 1st membrane surface and 8 bar of 1st compressor pressure, and case A
13 represents 200,000 m
2 of 1st membrane surface and 10 bar of 1st compressor pressure. For 400,000 m
2 SA
1 and 6 bar of CP
1, the abbreviation is A
21 and along with others.
Table 10 demonstrates the evaluation and economical estimation with the analyzed solutions considering the indicators presented above of single-stage membrane technology. By fusing the single-stage of the membrane without vacuum pump utilization, the net power plant efficiency decreases by (31–50%) based on the membrane surface and compressor pressure values utilized. Generally, increasing the membrane surface or compressor station unit drives an increase in the power plant efficiency loss. As demonstrated in the paper, the electrical consumption required for a membrane system increases vastly with the increase of CP
1 in addition to membrane surface impact. The LCOE increases with the increase of membrane surface from 200,000 to 500,000 m
2 of (44–56%) at compressor pressure of 8 bar. The CO
2 avoided cost is higher on the 200,000 m
2 membrane surface than on other surfaces at the same compressor pressure due to the low power required to capture CO
2.
By presuming the CO
2 tax is 82 €/ton and retail electricity cost is 160 €/MWh and considering that all carbon certificates are sold, the assumptions for all cases are in the Tables below. The economic evaluation of the 1-single stage of the membrane (no vacuum used) was analyzed in
Table 11. As summarized, by increasing the membrane surface from 200,000 to 500,000 m
2 at the same compressor pressure, the net present value increases at 400,000 m
2 by around 25%, then reduces by 1% at 500,000 m
2 membrane surface due to the increase of energy consumption needed for the CO
2 capture process.
To evaluate the technical and economic assessment for the case B, the different parameters in
Table 12 are chosen based on the optimum results of CO
2 capture efficiency, CO
2 purity, and power consumption.
Table 13 summarizes the assessment with the examined solutions based on the indicators shown above at a 1-stage of membrane technology with vacuum pump usage. In all analyses, the vacuum pump pressure was assumed to be 0.25 bar. After the integration, the net power plant efficiency decreased by 42% at 200,000 m
2 and 8 bar, then reduced constantly, reaching mitigation of 59% of the main net power plant efficiency at 500,000 m
2. As explained in the paper, the high pressure difference across the membrane module guides an increase in the power plant efficiency loss. The table shows that LCOE increases by 23% with the increase of membrane surface from 200,000 to 400,000 m
2 and by 16% with the increase from 400,000 to 500,000 m
2 due to the high demands of energy CO
2 capture. In terms of CO
2 avoided cost, for the 200,000 m
2 membrane surface the cost is less than 400,000 and 500,000 m
2 by around 33% and 49%, respectively, at compressor pressure 8 bar because of the low energy required for the CO
2 capture process.
Table 14 demonstrates the economic evaluation for different parameters which were examined. The net present value in the economic assessment decreases by 24% when the membrane surface increases from 200,000 to 400,000 m
2, and also decreases if the surface differs from 400,000 to 500,000 m
2 by around 21% at 8 bar CP
1. On the other hand, the DDP scale increases with the membrane surface increase reaching 15.5 years at 500,000 m
2 due to the high power consumption that increases with the rise of SA
1.
To estimate the technical and economic assessment for the case C, the different parameters in
Table 15 are chosen based on the optimum results of CO
2 capture efficiency, CO
2 purity, and power consumption.
Table 16 shows the technical estimation of 2-stages of membrane integrated into CFPP. As demonstrated, increasing SA
1 drives the decrease of the net power plant efficiency by 14% when the surface is increased from 200,000 to 600,000 m
2 at 6 bar of CP
1. Integrating 2-stages of the membrane increases the LCOE by about 50% at 8 bar compressor pressure and 400,000 m
2 membrane surface. By considering the impact of CP
1 on CO
2 avoided cost, the values of the cost decrease with CP
1 increasing (6–10 bar) by around 66% at 200,000 m
2 of SA
1.
In terms of economic assessment of 2-stages of the membrane,
Table 17 summarizes it, where the net present value decreases with the increase of SA
1 from 200,000 to 600,000 m
2 by 59%. It is noticeable that increasing SA
1 impacts directly on the DPP, where DPP decreases from almost 15 to 11 years with the rise of SA
1 200,000–600,000 m
2.
The sensitivity assessment for 1-stage, no vacuum, SA1 of 500,000 m2, CP1 6 bar is given (as an example). For all cases, the variation is approximately the same. The influence of the CO2 tax and the CO2 capture efficiency on the levelized cost of electricity is remarkable. Taking into account that CO2 avoided cost is over 100 €/t for almost all cases, we calculated a possible 140 €/t of CO2 tax which allows us to increase the profitability index from 1.93 to 2.44.
Different economic parameters of 1- and 2-stages of the membrane are compared in
Table 18 considering the optimal CO
2 capture efficiency and purity. According to the table, increasing the membrane stages leads to an increase in CO
2 purity, but at the same time increases the power consumption and investment cost of the project, which is also due to the usage of more equipment that requires energy to function.
In order to provide a clear vision regarding modeling using the CHEMCAD process with membrane, a comparison between the current and other papers studied from technical and economical points of view has been presented in
Table 19 below.
The current paper focused on using membrane technology integrated into CFPP in the coming years (at least 5 years); in that time, regarding the improvements of pieces of equipment and performance, we believe the efficiency of equipment (such as compressors and vacuum pumps) could be enhanced. However, the difference between using a compressor or pump efficiency of 90% instead of 85% leads to 6% decrease in the energy consumption at the CO2 capture efficiency of 90%.
Study
1 represents a paper studied by Xuezhong He and May-Britt Hägg [
8], while study
2 demonstrates a research article authored by Xuezhong He; Jon Arvid Lie; Edel Sheridan; and May-Britt Häg [
99], study
3 exhibits an article studied by Van der Sluus; Hendriks; and K. Blok [
100], and study
4 shows a paper studied by Merkel; Lin H; Wei X; and Baker [
101]. The current study shows an increase regarding the economic side compared with study
1 due to the elevated flue rate, which is almost 76% higher, which also explains why the power consumption of the present paper is larger as well. On the other hand, the capture efficiency and purity of CO
2 is more than the others because of the high CO
2 permeance and the 1st compressor pressure used.