Research on Collaborative Risk Management Mechanism of Mega Projects: A Tripartite Evolutionary Game Model Considering the Participation of Insurance Institution
Previous Article in Journal
Cyber Evaluation and Management Toolkit (CEMT): Face Validity of Model-Based Cybersecurity Decision Making
Previous Article in Special Issue
Deploying Bottleneck Management Strategies for Ameliorating Critical Delays in Building Construction Projects: A Case for Developing Country of Iran
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Mitigating Financial Risks in Sustainable Public–Private Partnership Infrastructure Projects: A Quantitative Analysis

School of Engineering, Design and Built Environment, Western Sydney University, Sydney, NSW 2747, Australia
*
Author to whom correspondence should be addressed.
Systems 2024, 12(7), 239; https://doi.org/10.3390/systems12070239
Submission received: 24 April 2024 / Revised: 27 June 2024 / Accepted: 30 June 2024 / Published: 2 July 2024

Abstract

:
Economic recession from the coronavirus outbreak continues to have negative rippling effects on local and international financial investments in public–private partnership (PPP) projects in Ghana, a developing country. Together with poor reports on operating cash-inflows for PPP projects such as those covering schools, hospitals, railways, fishing harbors, cocoa warehouses, recreational parks and affordable housing, there is an urgent need to develop and institutionalise sustainable and robust financial risk management measures. These measures are meant to mitigate financial losses, promote sustainability practices and prolong the longevity of infrastructure developments within PPP pacts. Therefore, this study aims to assess the mitigation measures of PPP infrastructure management in Ghana. Primary data from survey questionnaires were utilised in this study, with the data obtained from PPP practitioners and experts. Data were grouped into project type, sectors and practitioners of PPP projects to aid the analysis using tools such as the Kruskal–Wallis test, the Mann–Whitney U test and factor analysis. The results demonstrate sustainable and green finance, the innovative skills and competencies of project teams, green financial risk models and inclusive cost reduction strategies as crucial to minimising financial risks in PPP project delivery. These findings have significant implications for PPP practitioners and researchers in Ghana and similar developing countries to understand and develop measures to respond to financial risks for sustainable PPP project development and future research studies.

1. Introduction

Public–private partnership (PPP) is rapidly becoming the preferred procurement method for sustainable project development in the 21st century [1,2]. PPP pools the resources of private entities and the public sector together in the delivery of projects and services such as schools, hospitals, recreational parks, light rails, airports, affordable houses, agricultural produce and COVID-19 vaccines [3]. The private sector largely bears the financial risks in the design, construction and management of the project. Also, private investors pay for the financial liabilities of feasibility studies, maintenance, transfer costs and decommissioning expenses of the project within a concession period [4]. The public sector, including the national (federal) and state governments, districts, councils and public institutions, assumes the risks of the facilitation and supervision of project delivery [5]. Accordingly, a critical risk factor in value-for-money in PPP project execution is financial risks. The financial risks of PPP projects refer to the financing challenges (inability to attract enough capital to initiate the project) and operational losses (recording more project costs than revenue) as well as mismanagement of project funds and corrupt practices that siphon investment capital and revenues [6]. The outbreak of COVID-19 worsened the financial stance of PPP projects, resulting in a reduction in financial investment in PPP projects. According to the World Bank, the pandemic put a cap on the capital injection into PPP projects with a decline in financial investments of 52% from $96.7 billion to $45.7 billion [7,8]. These problems created a cashflow crisis for operators of the PPP infrastructure, especially in developing nations like Ghana [9]. The pandemic delayed the completion of the Pokuase road interchange project in Accra and twenty-two (22) hospitals across the country, creating additional expenditure for these PPP infrastructure projects [10,11].
Furthermore, recent data from the World Bank and climate reports have reported rising cases of disasters from extreme weather changes which have resulted in the financial loss of over AUD 4.3 trillion together with deaths and the destruction of infrastructure projects in Ghana [12,13]. These unfortunate climate change incidents undermine sustainable infrastructure development and increase the cost of repair for PPP infrastructure [14,15]. For instance, the Accra–Cape coast road and Tema motorway linking the three major cities of Accra, Tema (industrial hub) and Cape Coast have experienced infrastructure being washed away and potholes due to persistent rainfall. These incidents have increased the maintenance costs of the roads, leading to additional loans being secured to redevelop the projects. Additionally, Boateng [16] mentioned that twenty (20) key affordable residential houses and multi-story commercial buildings collapsed in Ghana between 2000 and 2020 due to increased climate hazards such as flooding and strong winds. The financial costs associated with revamping these collapsed PPP infrastructures were huge in addition to compensating families who lost their loved ones in the collapsed building incidents. Moreover, most of the recreational centres under PPP contracts in Ghana are in a depilated state because of weather changes [17,18]. Existing recreational centres have a poor maintenance culture due to financial challenges (limited funds for renovation) [19]. Furthermore, little progress has been made in the reduction of carbon emissions from the inclusive management of infrastructures in PPP contract arrangements in the Ghanaian economy [20]. Also, the lack of disability-friendly features in most PPP infrastructure developments in the country is worrying, with most infrastructures failing the inclusion tests of development for those in the disability community [21]. With the promulgation of the Persons with Disability Act (2006) in Ghana, existing public buildings within PPP arrangements at the national and local levels are supposed to be retrofitted to disability-friendly status at extra project costs. Failure of project managers to meet these disability accessibility regulatory requirements also result in fines and financial charges to the project management organisations [22]. Moreover, the inclusion of sophisticated smart and technology-inspired PPP infrastructure features to assist the disabled and aged in Ghanaian society add up to the construction and operational costs [20,23]. To address these challenges, this study assesses the mitigating strategies for financial risks in sustainable public–private partnership infrastructure projects in Ghana.
The novelty of this research includes the presentation of guidelines of measures critical in financial risk management for practitioners to develop practical project policies and practice models. It is the first of its kind from Ghana with measures to guide the mitigation of financial risks using empirical data from PPP practitioners in the country. The practice guidelines on financial risk management will be instrumental in fostering infrastructure development in the country. The checklist of financial risk mitigation measures is relevant for future studies and theoretical development in PPP research. The outcomes will enrich the existing literature and scholarly investigations into measures addressing financial challenges in attaining sustainable PPP infrastructure projects from a developing economy perspective. The section afterward is a review of the literature followed by the research methodology. The results and discussions come next with conclusions at the end of the article.

2. Literature Review

2.1. PPP Concept

The concept of public institutions collaborating with private entities to provide services and infrastructures under public–private partnership (PPP) agreements has been around for centuries [24]. The concept was well publicised in the Roman Empire, and it was used in building and expanding highway networks. PPP was common in the delivery of postal letters and the operation and transportation of farm produce and military mercenaries to fight opponents [25]. This gave birth to the “manceps” model, which allows competitive tendeIring and bidding to allow the private sector to be involved in public projects. During the Middle Ages, the PPP concept was instrumental in the development of fortified ports and towns in Europe against reprisal attacks from invading adversaries [26,27]. In the industrial revolution era, the rapid development of towns into cities and the emergence of new technologies from private inventors and organisations brought the government and the private sector together [28]. While the government has made laws to protect the intellectual property rights of private entities, these private corporations contribute to the supply of technology, jobs and consumables to the public to ease the pressures on governments [29,30]. In the latter part of the 20th century, the United Kingdom (UK) government rebranded these public–private collaborations under the term Public Finance Initiatives (PFIs). The PFI model has been seen in the delivery of major infrastructure projects across the UK, and it is the precursor to the modern PPP models around the world [31]. Examples of PPP infrastructure projects include the Sydney Harbour Tunnel (Australia), Abbotsford Hospital (Canada), Shantou Coastal New Town Project (China), Underground Tunnel projects in London (UK) and California Fuel Cell Partnership projects (United States). In PPP arrangements, a concessionary period is allowed to finance, build and operate, after which the project will be transferred to the owner (in most cases, the public sector) [32]. The key partners of the public sector and private corporations share risks and benefits from the projects based on the terms and conditions agreed upon in PPP contracts [7,33].

2.2. PPP Arrangements in Ghana

Public–private partnership (PPP) arrangements have become prominent in Ghana’s socio-economic development, dating back to the 1990s within the fourth republic constitution era [19]. The preceding events that sparked the acceptance of the private sector in the public space are the various Economic Recovery Programs (ERPs) and Structural Adjustment Programs (SAPs) in the 1980s [34]. These programs encouraged the privatisation of state-owned enterprises constructed under the first republican government of the country [35]. Fast-forward, in the 2000s, the government of Ghana formalised PPP initiatives with the creation of the Ministry of Private Sector and Presidential Special Initiatives [19]. The goal of this governmental arm was to solicit the support of private investors within Ghana and overseas to provide services and construct infrastructures for the country. In the 2000s, a document was drafted and issued by the government to assist in the administration of PPP contracts in the country [36]. However, this document lacked parliamentary support as it was not comprehensive enough to cover important contract administration issues within PPPs. As part of the course of governance history in the country, in the 2010s (2010–2019), the Ghanaian government introduced another policy to guide the operation of PPP activities, and the presidency became actively involved in its administration by attaching PPP issues to the Ministry of Finance and Ministry of Planning [37]. The PPP national was relaunched to support the evaluation and monitoring of projects with the support of private finance. The cabinet of Ghana approved a bill, and it was introduced to parliament in 2015 to begin the formal passage of a statutory law guiding PPPs [35,38]. Upon deliberations and changes to the bill, it received presidential assent into law in 2020 (Public Private Partnership Act 1039 [36,39]). Within the PPP Act, the concept and localisation of PPP terminologies are outlined together with the responsibilities of the various stakeholders. In Ghana, PPP contract risks including financial burdens are borne by private investors. Pressing areas of infrastructure development such as water, road networks, housing, power (electricity) and school buildings have seen the operation of PPP contracts [40]. Infrastructure projects such as the redevelopment of Kojokrom market, water treatment plants in the Asutsuare, Tema and Pokuase interchanges and Ofankor health center were built within the PPP arrangements [35]. In the 2020s, the attention of PPP arrangements has shifted to building more sustainable, low-carbon and renewable projects to solve the country’s socio-economic development challenges in different regions of the country [41].

2.3. Sustainable PPP Infrastructures

In the delivery of public infrastructures, the PPP arrangement has been noted as playing a significant role in the attainment of the United Nations Sustainable Development Goals (UNSDGs) [42]. Goal 17 (Partnerships), Goal 13 (Climate Action) and Goal 11 (Sustainable cities and communities) are some of the examples of UNSDGs that form the foundation of the construction and management of sustainable PPP infrastructures [43]. Sustainability in PPP infrastructures stem from the quest to champion social inclusivity and diversity of cultures, resolve the climate crisis and protect environmental resources for future, unborn generations in addition to economic prosperity [44]. Cheng et al. [45] mentioned sustainability in PPP infrastructures from the longevity of buildings and maintaining projects to fulfil their purpose to advance social progress and desired outcomes for non-profit state partners. Sustainability within the context of PPP projects also goes beyond the three triangles of project management, cost, quality and time, integrating social, economic and environmental dimensions of development [46]. The social dimension of PPP infrastructures can be explained by the less or no-profit orientation of the project to support communities and the disadvantaged in society. This includes infrastructures that have a high propensity to contribute to social advancement and change of lifestyles through the provision of jobs, affordable transport and houses as well as social support networks [41,47]. As a partner in the PPP infrastructure, the public sector ensures that this is achieved through regulations and good governance structures [39]. Efforts regarding the environmental sustainability of PPP projects are seen in measures to mitigate the climate crisis which is not helpful to the survival of PPP projects. PPP infrastructures also contribute to the release of an enormous amount of emissions into the atmosphere, which deepens climate change challenges [48,49]. PPP infrastructures such as road construction utilise fossil fuel products and account for more than 30% of carbon emissions. Measures to transition to more sustainable and lower to zero carbon PPP contracts are being supported with legislations and policies in many countries [14].

2.4. Financial Risks of PPP Infrastructure Projects

Financial risks are major obstacles to sustainable project transition and success [50,51]. In public–private partnership-sponsored infrastructure projects, Aladaǧ and Işik [4] explained that financial risks arise from poor operational models in financial management worsened by external economic challenges of interest and inflation rate fluctuations, the default of loan repayment and failure to meet revenue targets. Forms of financial risk exist in different projects depending on the capital structure, risks and the state of operating controls. Outside the confines of the projects are market risks comprising local or international economic crises that limit the flow of infrastructure finance [8,52]. The financial crisis of 2007 to 2008 and the 2020–2023 COVID-19 outbreak had widespread effects on internal and external financial support for PPP investments in infrastructures [53]. During these periods of financial difficulty, the operation of projects came to a halt, affecting revenue targets negatively with additional costs from personal and protective gadgets and health and safety protocols. Akomea-Frimpong, Jin and Osei-Kyei [6] provide a guiding list of fifty-four (54) operation- and investment-related financial risks with a comprehensive review of studies. Revenue risks, lapses in contractual agreements on borrowing, high-interest costs that affect the repayment capacity of projects and soaring administrative expenditure for projects are listed as financial risks [54,55]. Studies emphasise the shortage of project finding with limited alternatives to a sustainable source of capital for projects in lower and middle-income economies. Xenidis and Angelides [56] and Zhang, Li, Li and Zhang [8] further mentioned the complexities of securing project finance for capital in developing nations because of poor loan credit and repayment ratings, which compound access to adequate financial packages. Emerging challenges of climate change and sustainability-backed issues have called for additional mitigation measures in the management of the financial risks of PPP infrastructure [44]. However, extant literature is available on financial risk management; therefore, the relevance of this study is in developing sustainable infrastructure projects for PPP contracts.

3. Research Methodology

3.1. Survey Questionnaire Data

To extract financial risk mitigation measures (FRMMs) for sustainable public–private partnership infrastructure projects, a comprehensive literature review was conducted using scholarly depositories of publications including Scopus, ProQuest, Web of Science, ScienceDirect and Google Scholar. These scholarly and bibliographic sources are commonly used and popular in engineering and construction management research [57]. The keywords utilised in the search for literature in these databases were “financial risk controls”, “mitigation strategies on financial risks”, “financial control measures”, “public-private partnerships”, “sustainable public-private partnerships (PPPs)” and “PPP projects”. The search showed 334 relevant research articles, projects and institutional reports, which were thoroughly analysed. A total of 32 key FRMM variables were extracted from the literature (see Table 2). To ascertain the relevance of the 32 FRMMs to Ghanaian PPP infrastructure projects, a pilot study was conducted with 12 PPP experts in Ghana: 5 academics and 7 industry practitioners. The experts confirmed that all of the FRMMs are important without any comments.
Following pilot testing, a questionnaire was drafted with two sections, namely, basic information about the participants (Section 1) and the financial risk mitigation measures on a 5-point Likert scale (Section 2). The questions asked in Section 1 were related to the educational background, work experience, project types, sectors and job titles of the respondents concerning PPP infrastructure projects in Ghana. The results are presented in Table 2. In the second part of the questionnaire (Section 2), participants in the survey were requested to respond to 32 FRMMs based on their agreement or disagreement with the statements (from strongly disagree to strongly agree). To distribute the questionnaire, PPP practitioners, academics and experts in Ghana for questionnaire responses served as the target population. A participant must be significantly participating in the activities of PPP infrastructure projects in Ghana for at least 5 years to take part in the data collection [58]. A thorough search of the social media profiles of PPP experts in Ghana revealed 78 potential participants who were contacted and accepted to be part of the data collection. The 78 potential participants invited 187 other experts who are knowledgeable and experienced in PPP infrastructure activities in Ghana using the snowballing sampling technique. The number of participants whose names, career positions and email contacts were gathered was 265. The survey questionnaire was keyed into Qualtrics software (Version 3.2.0), and the link generated was shared via emails with the participants. Responses were received from 251 participants out of 265 questionnaires emailed with 5 not fully filled in (less than 10% of responses to the statements in the questionnaire). The 5 responses were deleted with the remaining 246 responses retained for data analysis (see Table 1).

3.2. Analytical Procedure for the Dataset

The entire data’s reliability was tested using Cronbach’s alpha (CA). The CA analysis showed a score of 0.865, a representation of the strong consistency and reliability between the variables within the questionnaire survey above the threshold of CA of 0.7 [54,59]. Following the reliability test, the normality test used was the Shapiro–Wilk test (SW). The test results of the SW indicated a non-normal distribution at p-values no greater than 0.05. The W statistic in the SW test showed a score of 0.938 (p < 0.05), further supporting the non-normal distribution of the dataset. According to King and Eckersley [60] and Razali and Wah [61], the W statistic represents the measurement of comparison between the order and the standardisation of the distribution of the dataset in relation to the normality curve. Due to the distribution-free nature (non-normal distribution) of the dataset, it was appropriate to further test the data with non-parametric statistical techniques. First, the Kendall’s concordance W test (that is, Kendall’s W coefficients) was conducted to assess the level of agreeability of the raters within each of the groups of the dataset: sector, project type and practitioners [62]. The Kendall’s W coefficient was utilised when the attributable features were less or equal to seven (7). The greater the attributes (that is, more than seven (7)), the more suitable the chi-square approximation [63], hence the usage of the chi-square (critical values) with the degree of freedom in addition to the significance level. From Table 3, the chi-square is 44.985 (critical value) for the groups in rating the financial risk mitigation measures of PPP infrastructure projects. With these critical values being less than the computed chi-square values in Table 3, they affirm the genuineness, association and consistency of the agreement in the ratings of each of the groups [40,64]. Second, the critical differences of the respondents in the data groups were determined using the Mann–Whitney (MW) U test (sectors) and the Kruskal–Wallis (KW) test (project types and practitioners) together with the mean ranking (see Table 4, Table 5 and Table 6) [65]. The two statistical tools (MW U and KW tests) are quantitative non-parametric models [66]. Finally, the entire dataset was analysed using exploratory factor analysis (EFA). EFA is a factor reduction technique that can group several variables (or factors) that are correlated into different clusters. The following requirements must be met in conducting an effective EFA. The Cronbach’s alpha, which has already been established to be more than 0.7, confirms the reliability of the dataset [67]. The Kaiser–Meyer–Olkin (KMO) test for the assessment of sufficient level of the data and the level of correlation (Bartlett’s sphericity test) are the other fundamental conditions of EFA analysis with the results reported in Section 4.2 [68,69].
Table 2. Financial risk management measures for PPP infrastructure projects.
Table 2. Financial risk management measures for PPP infrastructure projects.
S/NFinancial Risk Mitigation MeasuresSources
FRMM1Review PPP financial agreements from Ghana’s Ministry of FinanceChou and Pramudawardhani [70] and Akomea-Frimpong et al. [71]
FRMM2Involve community leaders and stakeholders in financial risk management plans Dansoh et al. [72] and Babatunde et al. [73]
FRMM3Consult Ghanaian financial experts on PPP projects Akomea-Frimpong et al. [74]
FRMM4Long-term financial feasibility and sustainability evaluation of the project Khahro et al. [75] and Du et al. [76]
FRMM5Early detection of expenditure in fighting climate disasters in the project Akomea-Frimpong, Agyekum, Amoakwa, Babon-Ayeng and Pariafsai [14] and Osei-Kyei et al. [77]
FRMM6Spend within the project budget Mazher et al. [78] and Castelblanco, Guevara and Salazar [53]
FRMM7Apply sustainable financial instruments to reduce operating costsJiang et al. [79]
FRMM8Review the influence of financial risks on environment and carbon emissions of the projectMete et al. [80] and Akomea-Frimpong, Jin and Osei-Kyei [44]
FRMM9Make use of financial data from international institutions and Ghana’s parliamentXu, Liu, Zhou and Lu [51] and Mazher, Chan, Choudhry, Zahoor, Edwards, Ghaithan, Mohammed and Aziz [78]
FRMM10Embrace sustainable PPP financial contract management practices Almarri and Boussabaine [81] and Akomea-Frimpong, Jin and Osei-Kyei [44]
FRMM11Promote diversity and inclusion in financial management Helmy et al. [82] and Osei-Kyei et al. [83]
FRMM12Financial budgeting in the transition to sustainable projects Kulshreshtha et al. [84] and Akomea-Frimpong, Jin and Osei-Kyei [44]
FRMM13Lifecycle financial risk analysis of the sustainability of PPP projectsWibowo and Alfen [85] and Jiang, Yang, Jiang, Martek and Gao [79]
FRMM14Net-zero transition cost management skills Mete, Hocquet, Sanchez, Talebian, Nilsson, Choi, Kyoung Lee, Lee and Moon [80] and Kamel et al. [86]
FRMM15Implement net-zero procurement cost measures Akomea-Frimpong, Agyekum, Amoakwa, Babon-Ayeng and Pariafsai [14] and El-Kholy and Akal [87]
FRMM16Ensure high professionalism and competence of the project finance teamJiang, Yang, Jiang, Martek and Gao [79] and Zhang, Li, Li and Zhang [8]
FRMM17Apply sustainable value-for-money modelsAmeyaw et al. [88] and Khahro, Ali, Hassan, Zainun, Javed and Memon [75]
FRMM18Cost and benefit evaluation of the energy consumption of infrastructuresKissi et al. [89] and Ohene et al. [90]
FRMM19Leadership commitment to the financial sustainability of projects Tan et al. [91]
FRMM20Affordable user fees to attract more revenue Akomea-Frimpong et al. [92]
FRMM21Robust and transparent financial reporting systems Castelblanco, Guevara and Salazar [53] and Akomea-Frimpong, Jin and Osei-Kyei [6]
FRMM22Institutionalise audit controls and committees Jiang, Yang, Jiang, Martek and Gao [79]
FRMM23Equip project team with green and sustainable financial management skills Osei-Kyei, Jin, Nnaji, Akomea-Frimpong and Wuni [77] and Xu, Liu, Zhou and Lu [51]
FRMM24Constant updates in the financial risk response plan Almarri and Boussabaine [81]
FRMM25Minimum and sustainable revenue guarantee to private investorsKavishe and Chileshe [93], Kuru and Artan [94]
FRMM26Eradicate corruption and misuse of project fundsIshawu et al. [95] and Akomea-Frimpong, Jin, Osei-Kyei and Pariafsai [74]
FRMM27Sustainable renegotiation of financial contracts Glumac, Han, Schaefer and van der Krabben [5]
FRMM28Allow for a green participative budgetary process Alnour et al. [96], Kamel, Khallaf and Nosaier [86]
FRMM29A reasonable concession period for the recoupment of private investmentXu, Liu, Zhou and Lu [51] and Sun et al. [97]
FRMM30Sustainable budgetary funding from the governmentAladaǧ and Işik [4]
FRMM31Inflation-linked operating revenue from the projectBabatunde, Perera, Zhou and Udeaja [73] and Angelides and Xenidis [33]
FRMM32Borrow green finance at the lowest interest charges Akomea-Frimpong et al. [98]

4. Results and Discussions

4.1. Criticality Assessment of Financial Risk Mitigation Measures

The results of the critical assessment of measures of financial risk in PPP infrastructure development are presented in this section. Three categories of criticality assessment are undertaken in this section in reference to the key PPP sectors, practitioners and forms of projects. The criticality assessment was taken to justify the inclusion or inclusion of the 32 FRMM variables (refer to Table 1) for factor analysis (Section 4.2). Using the means (MS) of the data, the criticality threshold was benchmarked at 50% (2.5) or more of the five ranks on the Likert Scale (≥2.5). The MS of 2.5 or greater was utilised in ranking variables in construction, PPP and engineering management literature such as publications by Nguyen, Nguyen, Doan and Dang [55], Zhang [99] and Cheung and Chan [100]. From Table 4, Table 5 and Table 6, the MS demonstrates that all of the FRMMs attained more than 2.5 mean scores, indicating their relevance in the subsequent analysis. Furthermore, the key sectoral differences in the management strategies of financial risk were analysed using the Mann–Whitney U test (significant at 0.05). The null hypothesis set explains that there are no differences in the approach to managing financial risk in the two sectors while the alternative hypothesis states otherwise [101]. The findings in Table 4 show the significance (S) of the analysis for all FRMM variables (p-value < 0.05) between the two sectors of the FRMMs, hence the rejection of the null hypothesis (RNH). This means that the two sectors hold different views and possibly use different strategies in mitigating adverse financial outcomes from projects. In Table 5 and Table 6, PPP practitioners and project types are assessed in response to the mitigation strategies for PPP financial risks. The hypothesis of the Kruskal–Wallis test was no disagreements among practitioners and the type of project on the FRMMs [102,103]. Except for FRMM2, FRMM12 (Table 5) and FRMM16 (Table 6), where the null hypothesis was accepted (ANH), all the FRMM variables produced significance values less than 0.05. With these results, the rejection of the null hypothesis (RNH) ensued, which is explained by the practitioners and project types having different measures in minimising financing and operating losses. In the case of FRMM2, respondents hold the same view that it is important to get involved with traditional and community leaders in the design and implementation of financial measures to foster PPP infrastructure success. In FRMM12 and FRMM16, respondents also hold a common view that it is important that project team members are equipped with innovative skills in budgeting and financial management in transitioning to sustainable PPP infrastructure management across the country (Ghana).

4.2. Factor Analysis

To extract the principal groups of the financial risk mitigation measures together with the assessment of the underlying relationships that exist between FRMMs, an exploratory factor analysis (EFA) was conducted. Fabrigar et al. [104] and Howard [105] mentioned that EFA is a preferable technique to discover and assess the nature of the structure of the factors underlying a dataset when no prior hypotheses of the dataset have been established. Before the EFA, the following conditions were met [106,107]. First, the internal consistency reliability test produced a Cronbach’s alpha score of 0.865 which is above the standard threshold, ≥0.7 score [7]. Secondly, the correlation matrix scores exhibiting the interrelationships of the FRMMs were established at ≥0.3 (at the significance level of 5%, p-values < 0.05) [108]. Third, the Kaiser–Meyer–Olkin (KMO) test together with Bartlett’s test of sphericity (BTS) ensued with scores showing 0.887 for the KMO test and 7757.43 for BTS (approximation chi-square) recorded at the significance of 0.0000 (5% significance level). The results show the sample’s adequacy, the fitness of the model and sustainability for factor analysis together with disproving the identified correlation matrix of the datasets [109]. The stage was then set for factor analysis with the extraction method set as principal component analysis (PCA) using the varimax orthogonal rotation option at a Kaiser normalisation convergence from seven iterations [110]. PCA was selected for the extraction of the factors due to its superior dimension reduction and uncorrelated features which keep maximum information and variances of the dataset in the process of extracting principal groups [111,112]. Compared to other rotation methods in EFA analysis, the varimax rotation method is orthogonal in nature, which optimises the variances within the data distribution with greater correlation between the principal groups and the sub-component variables [68]. The outcome of the EFA produced six principal components with more than 1.0 of the eigenvalues and cumulative variance explained as 71.011% (see Table 7). In the process of checking the factor loadings, it was discovered that three of the FRMMs produced factor loadings below 0.7; therefore, they were removed [113]. These include FRMM (0.043), FRMM8 (0.174) and FRMM19 (0.142). The remaining twenty-nine FRMMs with factor loadings more than 0.7 are shown in Table 7 [114]. Lastly, the multicollinearity among the factors related to the principal component analysis was checked, and the clear boundary that was set was that any correlation coefficient among the variables with 0.5 or above was considered multicollinear. From the analysis, all of the correlation coefficients were below 0.5, indicating no multicollinearity within the factors of the principal components [115,116].

4.3. Discussion of the Results

The results from the assessment of the data in the previous section can be interpreted as follows.
  • Component 1: Resilient budgets and financial plans
This group of FRMMs constitutes 24.192% of the variance explained of the measures in ensuring the financial success of PPP infrastructure projects in Ghana. The starting point to realising resilient financial risk management is to design budgets and financial plans [117]. This includes the development of rigorous budgetary and financial policies at the national level either from the Parliament of Ghana or ministerial budgets to direct builders and operators of the existing thirty (30) PPP infrastructures [19]. Without a detailed financial risk management plan before the financial closure stage, there could be a soaring of financial risks because there are plans to identify and manage project cost hotspots and limited revenues. At the firm and project levels, a participatory approach towards budgeting and financial planning within project teams is recommended to embrace expert and consulting advice on project budgets from academics and institutions that support PPP projects. Academic professionals from Ghana’s topmost educational institutions such as Kwame Nkrumah University of Science and Technology (College of Arts and Building Environment) and the University of Ghana (School of Engineering Sciences) can be helpful in designing financial budgets for projects. Furthermore, institutions and groups like the Ghana Institute of Engineers, KPMG and Project Management Institute (PMI) Ghana as well as governmental and private firms must be part of developing financial plans for PPP infrastructures. An inclusive budgeting process should allow for the perspectives of traditional and community leaders to be part of budgeting decisions and financial transactions. Traditional land rights and customs must be respected and recognised in the process of drawing up strategic long-term budgets for projects. Ghana is a culturally diverse country with different tribes and land ownership titles, so it is important that families and traditional owners are compensated and catered for in the future financial plans of projects [52]. Also, a careful strategy to achieve financial resilience should be designed to meet unexpected hikes in project costs and revenue shortfalls [118]. Responsive financial strategies and constant budget updates should be activated in the face of the financial turmoil the country Ghana has been facing in the last few years [119]. Financial plans to transform existing and under-construction PPP projects in Ghana into low-carbon, climate-resilient and possibly net-zero projects should be drafted with the support of the Ministry of Finance, international donor partners and project teams [5].
  • Component 2: Ensure inclusive cost controls.
Component 2 accounts for 18.135% of the variation in the dataset in explaining the effects of inclusive cost control measures for successful PPP infrastructure delivery in Ghana. Implementation of an inclusive cost management framework should be a prime goal of project managers with multidisciplinary and multidimensional approaches to gather enough cost information and allow all project participants to be part of financial risk management [120]. This starts with having a project cost budget put together competent staff such as a cost estimator, a quantity surveyor and an accountant who know a lot about the Ghanaian economy, the key expenses of projects and the implications of each expenditure. For instance, the exemplary leadership and competency of financial advisors in cost controls were instrumental in executing the Tema Motorway Interchange project, estimated at AUD 60 million [121]. A realistic cost plan for the effect of climate-related disasters on a project should be developed early and implemented throughout the lifecycle. This cost plan should be inclusive of maintenance fees and relief payments to affected stakeholders and communities. Also, a comprehensive organisational approach to reporting costs to various stakeholders together with integrated cost controls on financial risks should be enhanced in the wake of technological advancements. To frame comprehensive working cost management, previous reports on the expenditure of similar projects can be analysed and utilised to develop new cost budgets [122,123]. The reliance on previous cost reports should receive wide acceptance and recognition from key stakeholders towards improving the success of the project with the introduction of project audit committees and cost trackers. Cost management strategies such as option, swap and forward contracts are useful in minimising excessive project costs in a developing economy like Ghana where the cost of living crisis has impacted negatively on the prices of construction, labour and materials. Sustainable financial instruments such as green bonds and equity should be solicited to finance projects [124]. Excessive project costs also arise from rising operation and maintenance costs emboldened by increasing inflation and exchange rate risks. [4]. Effective cost strategies should also promote practices that reduce environmental challenges towards net-zero infrastructures and sustainable profitability for financiers [125].
  • Component 3: Apply sustainable funding strategies.
This principal component explains 12.114% of the variance in the dataset. Sustainable and green finance is the future of Ghana’s infrastructural development [126]. Chen et al. [127] and de Marco et al. [128] mentioned that sustainable debt (loan) funds allocated to assist PPPs should cover a lengthy period with the capacity to manage the revenue risks of PPP projects. Sustainable funding approaches ensure the interest fees on contracted loans to build a project are predicated on the loan agreement’s terms and conditions [129]. Even though it has been noted that the borrowing rates of infrastructure funds in Ghana are high, sustainable finance products such as green loans are granted on lower interest charges [124]. Recent events such as the COVID-19 pandemic and the economic crisis have worsened Ghana’s economic position in attracting funds from local and international lenders [130,131]. The outcomes of the crisis have increased the interest rate to 27–35% on borrowings to support infrastructural projects [132]. To manage this risk, PPP project managers should agree on favourable and sustainable contractual terms on principal loans, loan loss, high debt, conflicting problems between the interests of creditors and debtors, repayments and the timeframe to repay loans. The increment in the financial investments of PPP infrastructures can be augmented through the extension of concession periods for projects. Concession periods influence hedging and the management of revenue mobilisation through long-term income generation packages. In addition, the financing risks associated with PPP capital can be disbursed through sustainable equity funds, retirement funds and insurance coverage when the agreed time is declared for the project [117,133]. As an open and mixed economy, the private sector and the national government have access to different funding instruments within a reasonable concession period in Ghana for repayment and debt restructuring [134]. Cudjoe et al. [135] and Kukah et al. [136] articulated that the application for funding in renewable energy infrastructure projects in Ghana has gained popularity as the country explores different measures to end its intermittent electricity crisis [50].
  • Component 4: Practise revenue-boosting measures
Component 4 comprises measures to improve the revenue mobilisation of PPP infrastructures in Ghana at 8.721% of the variance explained. Sun, Jia and Wang [97] mentioned that to attract financial capital and increase the revenue of projects, a minimum revenue guarantee could be agreed upon at the onset of a project. This means that the public institutions in Ghana together with the national government should be obliged to allow private financiers to enjoy a minimum amount of cash flow to offset their expenses [137]. User-oriented prices should be designed to attract more people to utilise the infrastructure facilities built within the PPP arrangements. One suggestion is to build a positive brand for PPP infrastructures through the provision of quality and affordable prices. This could attract more Ghanaians to patronise the PPP infrastructures. Generally, user reviews on public facility management in the country are poor, preventing people from using public projects [101]. In Ghana, public facilities are hardly maintained, repaired, or repainted, leading to low interest in their usage [138]. To increase revenues, these problems should be resolved by improving quality standards and offering regular maintenance of facilities. A common unethical practice among public servants is to either steal or channel incomes from projects into their personal accounts. Project teams should institute effective revenue tracking systems to avoid this anomaly together with measures to minimise operating expenses.
  • Component 5: Promote innovative skills and competencies.
Component 5 reflects 4.928% of the explanation of the variance in the spread in the dataset. Innovative financial skill acquisition and competency development among project teams are important in achieving sustainable and net-zero PPP infrastructures in Ghana [139]. In this regard, financial education in the form of soft or hard skills is required to make significant changes in the current models of investments in infrastructure projects [140]. Skills in environmental assessment, net-zero and social impacts together with the financial position of the project should influence creativity, with alternative and renewable financial solutions towards sustainable PPP infrastructures [141]. Already, the understanding of new investments in PPP projects among project teams is well documented, but it is the competencies and technical know-how on the transition to sustainable net-zero project management that are lacking in the PPP sector. Offering these innovative skills will be valuable with traditional cost management skills in terms of time, cost and quality [142].
  • Component 6: Build green financial risk analysis models
The variance explained by this group of FRMM is 2.921% of the exploratory factor analysis. This group emphasises building and using a sustainable financial risk analysis approach to PPP infrastructures within Ghana. It entails listing international, local and cross-industry scenarios to measure and mitigate financial losses with cost and benefit analysis [143,144]. PPP project management firms and teams should design robust financial risk identification and mitigation scores to guide the improvement of financial outcomes. Financial risk tools such as fuzzy techniques, objective benchmarking, key performance indicators, FMEA (failure, modes and effects analysis) and probability/impact ranking approaches should embrace social–cultural and environmental factors within the Ghanaian PPP project setting [145]. Green financial risk models are essential in feasibility studies in project forecasting measures to deal with macroeconomic risks. In this information age of newer technologies, PPP infrastructure projects accentuate the need to address data and information on raw materials, health and safety, labour and the subcontracting of projects together with transparent reporting systems [146]. Financial information on climate change, the circular economy, wearable safety gadgets and diversity policies was sourced from the Ghana database section on the World Bank, International Monetary Fund (IMF) and Ministry of Finance, Ghana websites to aid budget forecasting and project schedules [5,147].

5. Implications of the Study

This study is relevant to practitioners of PPP project management within Ghana and similar developing nations in the process of updating existing project policies and designing new policies and frameworks towards mitigating financial risks. The results could aid the development of sustainable models on financial risks to improve profitability and attract investment. Moreover, at the firm level, strategic changes could happen with the framing of internal controls on responsibilities towards the minimisation of financial risk. At the project level, the complexities and confusion that are associated with financial management could be resolved with multidimensional budgets for project management knowledge areas. Project teams involved in PPP infrastructure projects should be guided to develop lifecycle-based financial models to countermeasure the financial challenges of PPP infrastructure development. To investors (private sector) who are interested in Ghana’s PPP infrastructure projects, this article offers insights into the key financial risks that are likely to hamper the maximisation of their investment. This study will provide potential investors with an understanding of the above and guidance on the key financial risk factors influencing PPP investments. Accordingly, investors can take precautionary measures to tackle these risks and improve upon the outcomes of their financial investments. Investors will know the roles they will play in mitigating financial risks. Future research works will benefit from this article on who to consult to gain data and the critical areas that need further investigation concerning financial management in PPP infrastructure development in Ghana.

6. Conclusions

In this study, financial risk mitigation measures towards sustainable PPP infrastructure projects in Ghana were analysed using 32 variables extracted from the existing literature, including project reports and institutional reports. Through a questionnaire survey, experts and practitioners on PPP infrastructure responded to the 32 FRMMs. The results revealed financial risk management measures from feasibility studies on the financial viability of projects, the use of sustainable financial risk assessment models and a call for the involvement of community leaders and users to be part of financial risk management plans. This study has also revealed that project teams should apply inclusive cost reduction strategies, advocate for sustainable funding of projects and equip team members to have sustainable and net-zero-based financial management skills. Additionally, the public sector must provide facilitation support in supervising PPP projects, therefore reducing the project’s operational expenses. The public sector supervises the financial management of PPP projects to ensure that the project team complies with Ghana’s financial regulations. Also, the public sector reviews the progress reports of projects to detect and prosecute individuals involved in financial mismanagement scandals. Debt and risk hedging strategies should be permitted or altered at the discretion of PPP implementation and supervisory committees to cater to unexpected financial risks. The financial risk management measures covered some of the emerging sustainability issues during the pre-construction, construction and post-construction stages of PPP infrastructure projects. From this study, the following limitations must be addressed in future studies. Key stakeholders such as users of PPP infrastructures and community leaders were not involved in the data collection process. Additionally, the sample of data utilised in this study is from practitioners on the existing 30 mega and national infrastructure projects within the PPP arrangements, with almost all of the projects concentrated in Accra and Kumasi, the two metropolitan cities in Ghana. Practitioners in other major regional areas and local councils were not part of this study due to time and financial resource constraints. Future studies should include these stakeholders in an extended data collection timeframe. Furthermore, it is recommended that stakeholders from the public sector, particularly the Ministry of Finance, and the Bank of Ghana stabilise the cedi through effective fiscal and monetary policies. The stabilisation of the Ghanaian currency will increase the confidence of local and foreign investors in PPP projects in the country. Future studies should explore measures to overcome these data collection challenges and increase the sample size to gain a holistic insight into managing the budget and financing losses of projects. Emerging issues that impact the financial management of projects such as diversity and inclusion, climate change, the circular economy and the transition to smart technologies in construction have not been thoroughly addressed in PPP infrastructure in Ghana. Furthermore, different PPP projects have peculiar challenges in achieving economic sustainability, health and safety for construction workers and social benefits to the community; therefore, further research should be conducted involving project-specific studies.

Author Contributions

Conceptualisation of the paper, literature review, methodology, data collection, cleaning and analysis and writing (original draft preparation and editing) all completed by I.A.-F.: supervision and review of the article completed by X.J. and R.O.-K. All authors have read and agreed to the published version of the manuscript.

Funding

This research received no external funding.

Data Availability Statement

Data for the study will be made available by the corresponding author upon request.

Acknowledgments

A very big thank you to the reviewers and editors for handling this article and providing comments and editorial support to make this article publishable. This article is part of the PhD thesis work of the corresponding author, so it has been supported by supervisors, the Western Sydney University and anonymous participants who took part in the survey questionnaire. Thank you all for making this thesis work and paper development a success.

Conflicts of Interest

The authors declare no conflicts of interest.

References

  1. Rahman, H.Z.; Miraj, P.; Andreas, A. Exploring public-private partnership scheme in operation and maintenance stage of Railway Project. Sustainability 2019, 11, 6517. [Google Scholar] [CrossRef]
  2. Osei-Kyei, R.; Jin, X.; Nnaji, C.; Akomea-Frimpong, I.; Wuni, I.Y. Review of risk management studies in public-private partnerships: A scientometric analysis. Int. J. Constr. Manag. 2022, 23, 2419–2430. [Google Scholar] [CrossRef]
  3. Baxter, D.; Casady, C.B. A coronavirus (COVID-19) triage framework for (sub) national public–private partnership (PPP) programs. Sustainability 2020, 12, 5253. [Google Scholar] [CrossRef]
  4. Aladaǧ, H.; Işik, Z. Role of Financial Risks in BOT Megatransportation Projects in Developing Countries. J. Manag. Eng. 2017, 33. [Google Scholar] [CrossRef]
  5. Glumac, B.; Han, Q.; Schaefer, W.; van der Krabben, E. Negotiation issues in forming public–private partnerships for brownfield redevelopment: Applying a game theoretical experiment. Land Use Policy 2015, 47, 66–77. [Google Scholar] [CrossRef]
  6. Akomea-Frimpong, I.; Jin, X.; Osei-Kyei, R. A holistic review of research studies on financial risk management in public–private partnership projects. Eng. Constr. Archit. Manag. 2021, 28, 2549–2569. [Google Scholar] [CrossRef]
  7. Alteneiji, K.; Alkass, S.; Abu Dabous, S. Critical success factors for public–private partnerships in affordable housing in the United Arab Emirates. Int. J. Hous. Mark. Anal. 2020, 13, 753–768. [Google Scholar] [CrossRef]
  8. Zhang, S.; Li, J.; Li, Y.; Zhang, X. Revenue Risk Allocation Mechanism in Public-Private Partnership Projects: Swing Option Approach. J. Constr. Eng. Manag. 2021, 147, 04020153. [Google Scholar] [CrossRef]
  9. Osei-Kyei, R.; Chan, A.P. Risk assessment in public-private partnership infrastructure projects. Constr. Innov. 2017, 17, 204–223. [Google Scholar] [CrossRef]
  10. Amponsah, R.A. Infrastructural projects implementations challenge in Ghana. Pentvars Bus. J. 2013, 7, 40–57. [Google Scholar] [CrossRef]
  11. Sidote, M.N.; Goodman, Z.T.; Paraggio, C.L.; Tutu, R.A.; Stoler, J. Measurement invariance of a household water insecurity metric in Greater Accra, Ghana: Implications for test-retest reliability. Int. J. Hyg. Environ. Health 2022, 240, 113922. [Google Scholar] [CrossRef] [PubMed]
  12. Pedersen, J.S.T.; Santos, F.D.; van Vuuren, D.; Gupta, J.; Coelho, R.E.; Aparício, B.A.; Swart, R. An assessment of the performance of scenarios against historical global emissions for IPCC reports. Glob. Environ. Change 2021, 66, 102199. [Google Scholar] [CrossRef]
  13. UNEP. Climate Change Undermines Nearly all Sustainable Development Goals; UNEP: Nairobi, Kenya, 2023. [Google Scholar]
  14. Akomea-Frimpong, I.; Agyekum, A.K.; Amoakwa, A.B.; Babon-Ayeng, P.; Pariafsai, F. Toward the attainment of climate-smart PPP infrastructure projects: A critical review and recommendations. Environ. Dev. Sustain. 2023, 1–35. [Google Scholar] [CrossRef]
  15. Andreasen, M.H.; Agergaard, J.; Møller-Jensen, L.; Oteng-Ababio, M.; Yiran, G.A.B. Mobility disruptions in Accra: Recurrent flooding, fragile infrastructure and climate change. Sustainability 2022, 14, 13790. [Google Scholar] [CrossRef]
  16. Boateng, F.G. Building collapse in cities in Ghana: A case for a historical-institutional grounding for building risks in developing countries. Int. J. Disaster Risk Reduct. 2020, 50, 101912. [Google Scholar] [CrossRef]
  17. Cobbinah, P.B.; Poku-Boansi, M.; Peprah, C. Urban environmental problems in Ghana. Environ. Dev. 2017, 23, 33–46. [Google Scholar] [CrossRef]
  18. Narh, S.N.; Takyi, S.A.; Asibey, M.O.; Amponsah, O. Garden city without parks: An assessment of the availability and conditions of parks in Kumasi. Urban For. Urban Green. 2020, 55, 126819. [Google Scholar] [CrossRef]
  19. Akomea-Frimpong, I.; Jin, X.; Osei-Kyei, R.; Kukah, A.S. Public–private partnerships for sustainable infrastructure development in Ghana: A systematic review and recommendations. Smart Sustain. Built Environ. 2023, 12, 237–257. [Google Scholar] [CrossRef]
  20. Ayetor, G.; Quansah, D.A.; Adjei, E.A. Towards zero vehicle emissions in Africa: A case study of Ghana. Energy Policy 2020, 143, 111606. [Google Scholar] [CrossRef]
  21. Amoah, C.; Bamfo-Agyei, E.; Simpeh, F. Disable access compliance to university infrastructure: Built environment students’ perceptions. Prop. Manag. 2023, 41, 681–697. [Google Scholar] [CrossRef]
  22. Ansah, S.K.; Owusu, K. State of public buildings in Ghana after the passage of the Persons with Disability Act (Act 715): The case of tertiary institutions. J. Constr. Proj. Manag. Innov. 2012, 2, 448–463. [Google Scholar]
  23. Danso, A.K.; Tudzi, E.P.; Ayarkwa, J.; Asiedu-Ampem, G.; Donkor-Hyiaman, K.A. Accessibility of pedestrian infrastructure along arterial roads to persons with disabilities in Kumasi. Ghana J. Dev. Stud. 2023, 20, 25–58. [Google Scholar] [CrossRef]
  24. Cheung, E.; Chan, A.P.; Kajewski, S. Reasons for implementing public private partnership projects. J. Prop. Invest. Financ. 2009, 27, 81–95. [Google Scholar] [CrossRef]
  25. Ke, Y.; Wang, S.; Chan, A.P.; Cheung, E. Research trend of public-private partnership in construction journals. J. Constr. Eng. Manag. 2009, 135, 1076–1086. [Google Scholar] [CrossRef]
  26. Feng, K.; Wang, S.; Li, N.; Wu, C.; Xiong, W. Balancing public and private interests through optimization of concession agreement design for user-pay PPP projects. J. Civ. Eng. Manag. 2018, 24, 116–129. [Google Scholar] [CrossRef]
  27. Le, Y.; Shan, M.; Chan, A.P.; Hu, Y. Overview of corruption research in construction. J. Manag. Eng. 2014, 30, 02514001. [Google Scholar] [CrossRef]
  28. Rossi, M.; Civitillo, R. Public Private Partnerships: A general overview in Italy. Procedia-Soc. Behav. Sci. 2014, 109, 140–149. [Google Scholar] [CrossRef]
  29. Devapriya, K.A.K. Governance issues in financing of public-private partnership organisations in network infrastructure industries. Int. J. Proj. Manag. 2006, 24, 557–565. [Google Scholar] [CrossRef]
  30. Nelson, R.R.; Baltin, B.; Feighner, B. Public-Private Financing Structures Used in the United States to Develop Convention Hotels. J. Conv. Event Tour. 2012, 13, 135–146. [Google Scholar] [CrossRef]
  31. Lattemann, C.; Kupke, S.; Schneider, A.M.; Stieglitz, S. Public private partnerships as an inter-organizational initiative for the diffusion of broadband technologies in Europe. In Proceedings of the 16th European Conference on Information Systems, ECIS 2008, Galway, Ireland, 9–11 June 2008. [Google Scholar]
  32. Akomea-Frimpong, I.; Jin, X.; Osei-Kyei, R. Fuzzy Analysis of Financial Risk Management Strategies for Sustainable Public-Private Partnership Infrastructure Projects in Ghana. Infrastructures 2024, 9, 76. [Google Scholar] [CrossRef]
  33. Angelides, D.C.; Xenidis, Y. PPP infrastructure investments: Critical aspects and prospects. In Policy, Finance and Management for Public-Private Partnerships; Blackwell Publishing Ltd.: Hoboken, NJ, USA, 2009; pp. 165–179. [Google Scholar]
  34. Tsamenyi, M.; Onumah, J.; Tetteh-Kumah, E. Post-privatization performance and organizational changes: Case studies from Ghana. Crit. Perspect. Account. 2010, 21, 428–442. [Google Scholar] [CrossRef]
  35. Osei-Kyei, R.; Chan, A.P.C. A best practice framework for public-private partnership implementation for construction projects in developing countries: A case of Ghana. Benchmarking 2018, 25, 2806–2827. [Google Scholar] [CrossRef]
  36. Darko, D.; Zhu, D.; Quayson, M.; Hossin, M.A.; Omoruyi, O.; Bediako, A.K. A multicriteria decision framework for governance of PPP projects towards sustainable development. Socio-Econ. Plan. Sci. 2023, 87, 101580. [Google Scholar] [CrossRef]
  37. Bissiri, M.; da Silva, P.P.; Moura, P.; Figueiredo, N.C. Are West Africa’s policy, planning, and regulatory frameworks missing the harmonization piece of the power pooling-renewable energy puzzle? Energy Policy 2024, 190, 114161. [Google Scholar] [CrossRef]
  38. Owusu, E.K.; Chan, A.P.; Hosseini, M.R. Impacts of anti-corruption barriers on the efficacy of anti-corruption measures in infrastructure projects: Implications for sustainable development. J. Clean. Prod. 2020, 246, 119078. [Google Scholar] [CrossRef]
  39. Sarkar, D.; Sheth, A. Public private partnership model for sustainable bus rapid transit system in Ahmedabad, India. Int. J. Constr. Manag. 2023, 23, 1233–1243. [Google Scholar] [CrossRef]
  40. Kukah, A.S.K.; Owusu-Manu, D.-G.; Badu, E.; Edwards, D.J. Exploring influencing factors for private sector participation in PPP power projects: Case of Ghana. J. Facil. Manag. 2024, 22, 310–324. [Google Scholar] [CrossRef]
  41. Owusu-Manu, D.-G.; Mankata, L.M.; Debrah, C.; Edwards, D.J.; Martek, I. Mechanisms and challenges in financing renewable energy projects in sub-Saharan Africa: A Ghanaian perspective. J. Financ. Manag. Prop. Constr. 2021, 26, 319–336. [Google Scholar] [CrossRef]
  42. Horan, D. A framework to harness effective partnerships for the sustainable development goals. Sustain. Sci. 2022, 17, 1573–1587. [Google Scholar] [CrossRef]
  43. Latif, M.H.; Amjad, M.; Qamar, A.; Asim, M.; Mahmood, W.; Khalid, W.; Rehman, A. Nexus implementation of sustainable development goals (SDGs) for sustainable public sector buildings in Pakistan. J. Build. Eng. 2022, 52, 104415. [Google Scholar] [CrossRef]
  44. Akomea-Frimpong, I.; Jin, X.; Osei-Kyei, R. Mapping studies on sustainability in the performance measurement of public-private partnership projects: A systematic review. Sustainability 2022, 14, 7174. [Google Scholar] [CrossRef]
  45. Cheng, Z.; Wang, H.; Xiong, W.; Zhu, D.; Cheng, L. Public–private partnership as a driver of sustainable development: Toward a conceptual framework of sustainability-oriented PPP. Environ. Dev. Sustain. 2021, 23, 1043–1063. [Google Scholar] [CrossRef]
  46. Kirikkaleli, D.; Ali, M.; Altuntaş, M. Environmental sustainability and public–private partnerships investment in energy in Bangladesh. Environ. Sci. Pollut. Res. 2022, 29, 56068–56078. [Google Scholar] [CrossRef] [PubMed]
  47. Du, J.; Wang, W.; Gao, X.; Hu, M.; Jiang, H. Sustainable operations: A systematic operational performance evaluation framework for Public–Private Partnership transportation infrastructure projects. Sustainability 2023, 15, 7951. [Google Scholar] [CrossRef]
  48. Hoeft, M.; Pieper, M.; Eriksson, K.; Bargstädt, H.-J. Toward Life Cycle Sustainability in Infrastructure: The Role of Automation and Robotics in PPP Projects. Sustainability 2021, 13, 3779. [Google Scholar] [CrossRef]
  49. Wang, Y.; Shao, Z.; Tiong, R.L. Data-driven prediction of contract failure of public-private partnership projects. J. Constr. Eng. Manag. 2021, 147, 04021089. [Google Scholar] [CrossRef]
  50. Fernandes, C.; Ferreira, M.; Moura, F. PPPs—True Financial Costs and Hidden Returns. Transp. Rev. 2015, 36, 207–227. [Google Scholar] [CrossRef]
  51. Xu, L.; Liu, N.; Zhou, L.; Lu, L. Fiscal Risk Management of Public–Private Partnership Projects: A Multidimensional Identification and Assessment Framework. Eng. Manag. J. 2023, 36, 166–192. [Google Scholar] [CrossRef]
  52. Morea, D.; Balzarini, M. Bankability of a public private partnership in agricultural sector: A project in sub Saharan Africa. Agric. Econ. 2019, 65, 212–222. [Google Scholar] [CrossRef]
  53. Castelblanco, G.; Guevara, J.; Salazar, J. Remedies to the PPP crisis in the COVID-19 pandemic: Lessons from the 2008 global financial crisis. J. Manag. Eng. 2022, 38, 04022017. [Google Scholar] [CrossRef]
  54. Maqbool, R.; Sridhar, H. Governing Public–Private Partnerships of Sustainable Construction Projects in An Opportunistic Setting. Proj. Manag. J. 2024, 55, 86–101. [Google Scholar] [CrossRef]
  55. Nguyen, H.D.; Nguyen, T.A.; Doan, V.V.; Dang, C.N. Assessing critical barriers and success factors of PPP projects in emerging economies: A case of Vietnam. J. Eng. Des. Technol. 2023. ahead-of-print. [Google Scholar] [CrossRef]
  56. Xenidis, Y.; Angelides, D. The financial risks in build-operate-transfer projects. Constr. Manag. Econ. 2005, 23, 431–441. [Google Scholar] [CrossRef]
  57. Kukah, A.S.; Akomea-Frimpong, I.; Jin, X.; Osei-Kyei, R. Emotional intelligence (EI) research in the construction industry: A review and future directions. Eng. Constr. Archit. Manag. 2022, 29, 4267–4286. [Google Scholar]
  58. Kuru, K.; Artan, D. A canvas model for risk assessment and performance estimation in public–private partnerships. Int. J. Constr. Manag. 2020, 20, 704–719. [Google Scholar] [CrossRef]
  59. Malek, M.S.; Gundaliya, P. Negative factors in implementing public–private partnership in Indian road projects. Int. J. Constr. Manag. 2023, 23, 234–242. [Google Scholar] [CrossRef]
  60. King, A.P.; Eckersley, R. Statistics for Biomedical Engineers and Scientists: How to Visualize and Analyze Data; Academic Press: Cambridge, MA, USA, 2019. [Google Scholar]
  61. Razali, N.M.; Wah, Y.B. Power comparisons of shapiro-wilk, kolmogorov-smirnov, lilliefors and anderson-darling tests. J. Stat. Model. Anal. 2011, 2, 21–33. [Google Scholar]
  62. Sun, Y.; Liu, M.; Hao, S.; Wei, M. Investment risk assessment of social capital in urban rail transit Public-Private Partnership projects. J. Asian Archit. Build. Eng. 2023, 1–19. [Google Scholar] [CrossRef]
  63. Cheung, E.; Chan, A.P.; Kajewski, S. Suitability of procuring large public works by PPP in Hong Kong. Eng. Constr. Archit. Manag. 2010, 17, 292–308. [Google Scholar] [CrossRef]
  64. Cheung, E.; Chan, A.P.; Lam, P.T.; Chan, D.W.; Ke, Y. A comparative study of critical success factors for public private partnerships (PPP) between Mainland China and the Hong Kong Special Administrative Region. Facilities 2012, 30, 647–666. [Google Scholar] [CrossRef]
  65. Osei-Kyei, R.; Chan, A.P. Perceptions of stakeholders on the critical success factors for operational management of public-private partnership projects. Facilities 2017, 35, 21–38. [Google Scholar] [CrossRef]
  66. Ismail, S.; Haris, F.A. Constraints in implementing public private partnership (PPP) in Malaysia. Built Environ. Proj. Asset Manag. 2014, 4, 238–250. [Google Scholar] [CrossRef]
  67. Zhang, X. Factor analysis of public clients’ best-value objective in public–privately partnered infrastructure projects. J. Constr. Eng. Manag. 2006, 132, 956–965. [Google Scholar] [CrossRef]
  68. Kukah AS, K.; Owusu-Manu, D.G.; Badu, E.; Edwards, D.J. Evaluation of risk factors in Ghanaian public-private-partnership (PPP) power projects using fuzzy synthetic evaluation methodology (FSEM). Benchmarking Int. J. 2023, 30, 2554–2582. [Google Scholar] [CrossRef]
  69. Wuni, I.Y.; Shen, G.Q.; Osei-Kyei, R. Quantitative evaluation and ranking of the critical success factors for modular integrated construction projects. Int. J. Constr. Manag. 2020, 22, 2108–2120. [Google Scholar] [CrossRef]
  70. Chou, J.-S.; Pramudawardhani, D. Cross-country comparisons of key drivers, critical success factors and risk allocation for public-private partnership projects. Int. J. Proj. Manag. 2015, 33, 1136–1150. [Google Scholar] [CrossRef]
  71. Akomea-Frimpong, I.; Jin, X.; Osei-Kyei, R. Financial risk maturity model for public-private partnership infrastructure project in Ghana: Modelling and Validation. In Proceedings of the 44th Australasian Universities Building Educators, Melbourne, Australia, 27–29 October 2021; pp. 22–32. [Google Scholar]
  72. Dansoh, A.; Frimpong, S.; Ampratwum, G.; Dennis Oppong, G.; Osei-Kyei, R. Exploring the role of traditional authorities in managing the public as stakeholders on PPP projects: A case study. Int. J. Constr. Manag. 2020, 20, 628–641. [Google Scholar] [CrossRef]
  73. Babatunde, S.O.; Perera, S.; Zhou, L.; Udeaja, C. Stakeholder perceptions on critical success factors for public-private partnership projects in Nigeria. Built Environ. Proj. Asset Manag. 2016, 6, 74–91. [Google Scholar] [CrossRef]
  74. Akomea-Frimpong, I.; Jin, X.; Osei-Kyei, R.; Pariafsai, F. Critical managerial measures on financial risks of sustainable public–private partnership projects: A PRISMA review. J. Financ. Manag. Prop. Constr. 2023, 28, 398–422. [Google Scholar] [CrossRef]
  75. Khahro, S.H.; Ali, T.H.; Hassan, S.; Zainun, N.Y.; Javed, Y.; Memon, S.A. Risk severity matrix for sustainable public-private partnership projects in developing countries. Sustainability 2021, 13, 3292. [Google Scholar] [CrossRef]
  76. Du, J.; Wu, H.; Jin, R. Capital structure of public–private partnership projects: A sustainability perspective. Sustainability 2019, 11, 3505. [Google Scholar] [CrossRef]
  77. Patel, T.D.; Haupt, T.C.; Bhatt, T. Fuzzy probabilistic approach for risk assessment of BOT toll roads in Indian context. J. Eng. Des. Technology. 2020, 18, 251–269. [Google Scholar] [CrossRef]
  78. Mazher, K.M.; Chan, A.P.; Choudhry, R.M.; Zahoor, H.; Edwards, D.J.; Ghaithan, A.M.; Mohammed, A.; Aziz, M. Identifying measures of effective risk management for public–private partnership infrastructure projects in developing countries. Sustainability 2022, 14, 14149. [Google Scholar] [CrossRef]
  79. Jiang, W.; Yang, Q.; Jiang, J.; Martek, I.; Gao, F. Operational risk management of public–private partnership infrastructure projects: A bibliometric literature review. Buildings 2022, 12, 1905. [Google Scholar] [CrossRef]
  80. Mete, G.; Hocquet, R.; Sanchez, F.; Talebian, S.; Nilsson, A.; Choi, G.; Kyoung Lee, S.; Lee, E.; Moon, J. Reaching Net-Zero Industry through Public-Private Partnerships. Leadership Group for Industry Transition, Stockholm Environment Institution. 2021. Available online: https://www.sei.org/publications/reaching-net-zero-industry-public-private-partnerships (accessed on 12 January 2024).
  81. Almarri, K.; Boussabaine, H. Re-evaluating the risk costing agenda in PPP projects. Built Environ. Proj. Asset Manag. 2021, 11, 22–37. [Google Scholar] [CrossRef]
  82. Helmy, R.; Khourshed, N.; Wahba, M.; El Bary, A.A. Exploring critical success factors for public private partnership case study: The educational sector in egypt. J. Open Innov.: Technol. Mark. Complex. 2020, 6, 142. [Google Scholar] [CrossRef]
  83. Osei-Kyei, R.; Tam, V.; Ma, M. Effective strategies for developing retirement village public–private partnership. Int. J. Hous. Mark. Anal. 2020, 14, 821–841. [Google Scholar] [CrossRef]
  84. Kulshreshtha, R.; Kumar, A.; Tripathi, A.; Likhi, D.K. Critical Success Factors in Implementation of Urban Metro System on PPP: A Case Study of Hyderabad Metro. Glob. J. Flex. Syst. Manag. 2017, 18, 303–320. [Google Scholar] [CrossRef]
  85. Wibowo, A.; Alfen, H.W. Identifying macro-environmental critical success factors and key areas for improvement to promote public-private partnerships in infrastructure: Indonesia’s perspective. Eng. Constr. Archit. Manag. 2014, 21, 383–402. [Google Scholar] [CrossRef]
  86. Kamel, M.; Khallaf, R.; Nosaier, I. Net present value-time curve behaviour of public private partnership projects. Int. J. Constr. Manag. 2023, 23, 1924–1931. [Google Scholar] [CrossRef]
  87. El-Kholy, A.M.; Akal, A.Y. Assessing and allocating the financial viability risk factors in public-private partnership wastewater treatment plant projects. Eng. Constr. Archit. Manag. 2021, 28, 3014–3040. [Google Scholar] [CrossRef]
  88. Ameyaw; Adjei-Kumi, T.; Owusu-Manu, D.G. Exploring value for money (VfM) assessment methods of public-private partnership projects in Ghana: A theoretical framework. J. Financ. Manag. Prop. Constr. 2015, 20, 268–285. [Google Scholar] [CrossRef]
  89. Kissi, E.; Babon-Ayeng, P.; Aigbavboa, C.; Duah, D.; Danquah-Smith, E.; Tannor, R.A. Examining green road construction components: The case of Ghana. Built Environ. Proj. Asset Manag. 2023, 13, 682–699. [Google Scholar] [CrossRef]
  90. Ohene, E.; Hsu, S.-C.; Chan, A.P. Feasibility and retrofit guidelines towards net-zero energy buildings in tropical climates: A case of Ghana. Energy Build. 2022, 269, 112252. [Google Scholar] [CrossRef]
  91. Tan, Y.; Shuai, C.; Shen, L.; Hou, L.; Zhang, G. A study of sustainable practices in the sustainability leadership of international contractors. Sustain. Dev. 2020, 28, 697–710. [Google Scholar] [CrossRef]
  92. Akomea-Frimpong, I.; Jin, X.; Osei-Kyei, R. Managing financial risks to improve financial success of public—Private partnership projects: A theoretical framework. J. Facil. Manag. 2021. ahead-of-print. [Google Scholar] [CrossRef]
  93. Kavishe, N.; Chileshe, N. Critical success factors in public-private partnerships (PPPs) on affordable housing schemes delivery in Tanzania: A qualitative study. J. Facil. Manag. 2019, 17, 188–207. [Google Scholar] [CrossRef]
  94. Okudan, O.; Budayan, C.; Dikmen, I. Development of a conceptual life cycle performance measurement system for build–operate–transfer (BOT) projects. Eng. Constr. Archit. Manag. 2021, 28, 1635–1656. [Google Scholar] [CrossRef]
  95. Ishawu, M.; Guangyu, C.; Adzimah, E.D.; Mohammed Aminu, A. Achieving value for money in waste management projects: Determining the effectiveness of public–private partnership in Ghana. Int. J. Manag. Proj. Bus. 2020, 13, 1283–1309. [Google Scholar] [CrossRef]
  96. Alnour, M.; Awan, A.; Hossain, M.E. Towards a green transportation system in Mexico: The role of renewable energy and transport public private partnership to curb the emissions. J. Clean. Prod. 2024, 442, 140984. [Google Scholar] [CrossRef]
  97. Sun, H.; Jia, S.; Wang, Y. Optimal equity ratio of BOT highway project under government guarantee and revenue sharing. Transp. A: Transp. Sci. 2019, 15, 114–134. [Google Scholar] [CrossRef]
  98. Akomea-Frimpong, I.; Kukah, A.S.; Jin, X.; Osei-Kyei, R.; Pariafsai, F. Green finance for green buildings: A systematic review and conceptual foundation. J. Clean. Prod. 2022, 356, 131869. [Google Scholar] [CrossRef]
  99. Zhang, X. Criteria for selecting the private-sector partner in public–private partnerships. J. Constr. Eng. Manag. 2005, 131, 631–644. [Google Scholar] [CrossRef]
  100. Cheung, E.; Chan, A.P. Risk factors of public-private partnership projects in China: Comparison between the water, power, and transportation sectors. J. Urban Plann. Dev. 2011, 137, 409–415. [Google Scholar] [CrossRef]
  101. Osei-Kyei, R.; Chan, A.P. Empirical comparison of critical success factors for public-private partnerships in developing and developed countries: A case of Ghana and Hong Kong. Eng. Constr. Archit. Manag. 2017, 24, 1222–1245. [Google Scholar] [CrossRef]
  102. Roumboutsos, A.; Anagnostopoulos, K.P. Public–private partnership projects in Greece: Risk ranking and preferred risk allocation. Constr. Manag. Econ. 2008, 26, 751–763. [Google Scholar] [CrossRef]
  103. Umar, A.A.; Zawawi, N.A.W.A.; Abdul-Aziz, A.-R. Exploratory factor analysis of skills requirement for PPP contract governance. Built Environ. Proj. Asset Manag. 2019, 9, 277–290. [Google Scholar] [CrossRef]
  104. Fabrigar, L.R.; Wegener, D.T.; MacCallum, R.C.; Strahan, E.J. Evaluating the use of exploratory factor analysis in psychological research. Psychol. Methods 1999, 4, 272. [Google Scholar] [CrossRef]
  105. Howard, M.C. A review of exploratory factor analysis decisions and overview of current practices: What we are doing and how can we improve? Int. J. Hum.-Comput. Interact. 2016, 32, 51–62. [Google Scholar] [CrossRef]
  106. Jin, X.H.; Zhang, G.; Yang, R.J. Factor analysis of partners’ commitment to risk management in public-private partnership projects. Constr. Innov. 2012, 12, 297–316. [Google Scholar] [CrossRef]
  107. Mohd Som, R.; Omar, Z.; Ismail, I.A.; Alias, S.N. Understanding leadership roles and competencies for public-private partnership. J. Asia Bus. Stud. 2020, 14, 541–560. [Google Scholar] [CrossRef]
  108. Henson, R.K.; Roberts, J.K. Use of exploratory factor analysis in published research: Common errors and some comment on improved practice. Educ. Psychol. Meas. 2006, 66, 393–416. [Google Scholar] [CrossRef]
  109. Hair, J.F. Multivariate Data Analysis; Kennesaw State University: Kennesaw, GA, USA, 2009. [Google Scholar]
  110. Binz, C.; Hair, J.F., Jr.; Pieper, T.M.; Baldauf, A. Exploring the effect of distinct family firm reputation on consumers’ preferences. J. Fam. Bus. Strategy 2013, 4, 3–11. [Google Scholar] [CrossRef]
  111. Abdi, H.; Williams, L.J. Principal component analysis. Wiley Interdiscip. Rev. Comput. Stat. 2010, 2, 433–459. [Google Scholar] [CrossRef]
  112. Thomaz, C.E.; Giraldi, G.A. A new ranking method for principal components analysis and its application to face image analysis. Image Vis. Comput. 2010, 28, 902–913. [Google Scholar] [CrossRef]
  113. Toriola-Coker, L.; Owolabi, H.; Alaka, H.; Bello, W.A.; Pathirage, C. Critical success factors (CSFs) for motivating end-user stakeholder’s support for ensuring sustainability of PPP projects in Nigerian host communities. J. Eng. Des. Technol. 2023, 21, 902–926. [Google Scholar] [CrossRef]
  114. Chan, A.P.C.; Lam, P.T.I.; Chan, D.W.M.; Cheung, E.; Ke, Y.J. Critical Success Factors for PPPs in Infrastructure Developments: Chinese Perspective. J. Constr. Eng. Manag. 2010, 136, 484–494. [Google Scholar] [CrossRef]
  115. Farrar, D.E.; Glauber, R.R. Multicollinearity in regression analysis: The problem revisited. Rev. Econ. Stat. 1967, 92–107. [Google Scholar] [CrossRef]
  116. Sinan, A.; Alkan, B.B. A useful approach to identify the multicollinearity in the presence of outliers. J. Appl. Stat. 2015, 42, 986–993. [Google Scholar] [CrossRef]
  117. Kumar, L.; Jindal, A.; Velaga, N.R. Financial risk assessment and modelling of PPP based Indian highway infrastructure projects. Transp. Policy 2018, 62, 2–11. [Google Scholar] [CrossRef]
  118. Pellegrino, R.; Vajdic, N.; Carbonara, N. Real option theory for risk mitigation in transport PPPs. Built Environ. Proj. Asset Manag. 2013, 3, 199–213. [Google Scholar] [CrossRef]
  119. Mensah, L.; Arku, F.K. The drivers of external debt in Ghana. Afr. J. Econ. Manag. Stud. 2024. ahead of print. [Google Scholar] [CrossRef]
  120. Man, Q.; Sun, C.; Fei, Y.; Skitmore, M.; Bai, Y.; Lu, W. Government motivation-embedded return guarantee for urban infrastructure projects based on real options. J. Civ. Eng. Manag. 2016, 22, 954–966. [Google Scholar] [CrossRef]
  121. Osei, K.N. Report of the Committee on Roads and Transport on the 2022 Annual Budget Estimates of the Ministry of Roads and Highways. 2021. Available online: https://ir.parliament.gh/handle/123456789/2120 (accessed on 13 March 2024).
  122. Hopkinson, M. The Project Risk Maturity Model: Measuring and Improving Risk Management Capability; Routledge: London, UK, 2017. [Google Scholar]
  123. Mu, S.; Cheng, H. Modeling Contractor’s Risk Management Capability in Metro Projects. In ICCREM 2013: Construction and Operation in the Context of Sustainability; American Society of Civil Engineers: Reston, VA, USA, 2013; pp. 702–711. [Google Scholar]
  124. Akomea-Frimpong, I.; Adeabah, D.; Ofosu, D.; Tenakwah, E.J. A review of studies on green finance of banks, research gaps and future directions. J. Sustain. Financ. Invest. 2021, 12, 1241–1264. [Google Scholar] [CrossRef]
  125. Le, P.T.; Chileshe, N.; Kirytopoulos, K.; Rameezdeen, R. Investigating the significance of risks in BOT transportation projects in Vietnam. Eng. Constr. Archit. Manag. 2020, 27, 1401–1425. [Google Scholar] [CrossRef]
  126. Agyekum, K.; Opoku, A.; Oppon, A.J.; Opoku, D.-G.J. Obstacles to green building project financing: An empirical study in Ghana. Int. J. Constr. Manag. 2020, 2922–2930. [Google Scholar] [CrossRef]
  127. Chen, S.; Huang, Z.; Drakeford, B.M.; Failler, P. Lending interest rate, loaning scale, and government subsidy scale in green innovation. Energies 2019, 12, 4431. [Google Scholar] [CrossRef]
  128. de Marco, A.; Mangano, G.; Zou, X.Y. Factors influencing the equity share of build-operate-transfer projects. Built Environ. Proj. Asset Manag. 2012, 2, 70–85. [Google Scholar] [CrossRef]
  129. Du, J.C.; Han, X.S.; Shi, P.M.; Ge, J.J. Determine optimal capital structure for metro PPP projects to reduce financial risks: Theory and empirical analysis. In Proceedings of the International Conference on Management Science and Engineering-Annual Conference Proceedings, Harbin, China, 17–19 July 2013; pp. 2105–2111. [Google Scholar]
  130. Cheng, M.; Liu, G.; Xu, Y. Can joint-contract functions promote PPP project sustainability performance? A moderated mediation model. Eng. Constr. Archit. Manag. 2021, 28, 2667–2689. [Google Scholar] [CrossRef]
  131. Baxter, D.; Casady, C.B. Proactive and strategic healthcare public-private partnerships (PPPs) in the coronavirus (COVID-19) epoch. Sustainability 2020, 12, 5097. [Google Scholar] [CrossRef]
  132. Ahmed, H.M.; El-Halaby, S.I.; Soliman, H.A. The consequence of the credit risk on the financial performance in light of COVID-19: Evidence from Islamic versus conventional banks across MEA region. Future Bus. J. 2022, 8, 21. [Google Scholar] [CrossRef]
  133. Han, Z.; Porras-Alvarado, J.D.; Sun, J.; Zhang, Z. Monte carlo simulation-based assessment of risks associated with public-private partnership investments in toll highway infrastructure. Transp. Res. Rec. 2017, 2670, 59–67. [Google Scholar] [CrossRef]
  134. Ahenkan, A. Mainstreaming public–private partnership in national development: How ready is Ghana? Bus. Strategy Dev. 2019, 2, 220–227. [Google Scholar] [CrossRef]
  135. Cudjoe, D.; Nketiah, E.; Obuobi, B.; Adu-Gyamfi, G.; Adjei, M.; Zhu, B. Forecasting the potential and economic feasibility of power generation using biogas from food waste in Ghana: Evidence from Accra and Kumasi. Energy 2021, 226, 120342. [Google Scholar] [CrossRef]
  136. Kukah, A.S.K.; Owusu-Manu, D.-G.; Badu, E.; Edwards, D.J. Reasons for entering into Ghanaian public-private partnership (PPP) power projects. J. Eng. Des. Technol. 2022, 22, 854–878. [Google Scholar] [CrossRef]
  137. Eyiah-Botwe, E.; Aigbavboa, C.O.; Thwala, W.D. Curbing PPP construction projects’ failure using enhanced stakeholder management success in developing countries. Built Environ. Proj. Asset Manag. 2020, 10, 50–63. [Google Scholar] [CrossRef]
  138. Amoatey, C.T.; Ameyaw, Y.A.; Adaku, E.; Famiyeh, S. Analysing delay causes and effects in Ghanaian state housing construction projects. Int. J. Manag. Proj. Bus. 2015, 8, 198–214. [Google Scholar] [CrossRef]
  139. Falana, J.; Osei-Kyei, R.; Tam, V.W. Towards achieving a net zero carbon building: A review of key stakeholders and their roles in net zero carbon building whole life cycle. J. Build. Eng. 2023, 82, 108223. [Google Scholar] [CrossRef]
  140. Oteng-Abayie, E.F.; Dramani, J.B. Time-frequency domain causality of prime building cost and macroeconomic indicators in Ghana: Implications for project selection. Constr. Manag. Econ. 2019, 37, 243–256. [Google Scholar] [CrossRef]
  141. Quashie, R.; Fugar, F.D.; Antwi-Afari, P.; Ng, S.T. Evaluating the key competency skills of construction professionals for the attainment of circular construction in developing economies. Clean. Prod. Lett. 2024, 6, 100060. [Google Scholar] [CrossRef]
  142. Davis, P.; Walker, D. Building capability in construction projects: A relationship-based approach. Eng. Constr. Archit. Manag. 2009, 16, 475–489. [Google Scholar] [CrossRef]
  143. Bai, L.; Wang, H.; Huang, N.; Du, Q.; Huang, Y. An environmental management maturity model of construction programs using the AHP-entropy approach. Int. J. Environ. Res. Public Health 2018, 15, 1317. [Google Scholar] [CrossRef] [PubMed]
  144. Eadie, R.; Perera, S.; Heaney, G. Capturing maturity of ICT applications in construction processes. J. Financ. Manag. Prop. Constr. 2012, 17, 176–194. [Google Scholar] [CrossRef]
  145. Hopkinson, M. Improving risk management capability using the project risk maturity model-a case study based on UK defence procurement projects. PM World Today 2011, 13. Available online: https://www.taylorfrancis.com/chapters/mono/10.4324/9781315237572-12/uk-mod-defence-procurement-agency-project-risk-maturity-model-case-study-martin-hopkinson (accessed on 2 April 2024).
  146. Valipour, A.; Yahaya, N.; Md Noor, N.; Kildienė, S.; Sarvari, H.; Mardani, A. A Fuzzy Analytic Network Process Method for Risk Prioritization in Freeway Ppp Projects: An Iranian Case Study. J. Civ. Eng. Manag. 2015, 21, 933–947. [Google Scholar] [CrossRef]
  147. Lam, K.C.; Chow, W.S. The significance of financial risks in BOT procurement. Build. Res. Inf. 1999, 27, 84–94. [Google Scholar] [CrossRef]
Table 1. Overview of questionnaire responses.
Table 1. Overview of questionnaire responses.
Characteristics No. of Responses (n)Percent (%)
Educational Qualification:
Diploma93.66
Undergraduate 15864.23
Masters6325.61
PhD166.50
Total246100.00
Work Experience:
Years—6–1014358.13
Years—11–15 9137.00
Years—≥15 124.88
Total246100.00
Categories of responses:
1. PPP sector
Private 14157.32
Public 10542.68
Total246100.00
2. PPP project type
Social6225.20
Economic10442.28
Environmental8032.52
Total246100.00
3. PPP practitioner (job title)
Project manager7229.27
Quantity surveyor5622.76
Risk manager6727.24
Accountant5120.73
Total246100.00
Table 3. Summary of the Kendall’s concordance test.
Table 3. Summary of the Kendall’s concordance test.
CharacteristicsSectorPractitionersProject Type
PrivatePublicProject ManagersQuantity SurveyorsRisk ManagersAccountantSocialEconomicEnvironmental
Participants in the survey (N)141105725667516210480
Kendall’s W test0.3260.4160.2580.3470.2890.4030.3710.2970.342
Chi-square (X2)843.123712.451451.367335.124412.567264.147378.478703.641478.437
Critical value of X244.98544.98544.98544.98544.98544.98544.98544.98544.985
Degrees of freedom313131313131313131
Asymptotic significance0.0000.0000.0000.0000.0000.0000.0000.0000.000
Table 4. Key financial risk mitigation measures based on the data of the PPP sectors.
Table 4. Key financial risk mitigation measures based on the data of the PPP sectors.
PPP SectorsMann–Whitney U Test
Public SectorPrivate Sector
S/NMSSDRankMSSDRankU-Statp-ValueSign./Decision
FRMM24.830.6423.871.241712.5280S, RNH
FRMM224.710.6533.131.272310.6170S, RNH
FRMM314.690.543.031.25255.5540S, RNH
FRMM204.100.64104.821.2947.6620S, RNH
FRMM254.370.6554.781.33521.7550S, RNH
FRMM154.340.6164.731.37615.8650S, RNH
FRMM64.250.6274.631.43722.0470S, RNH
FRMM84.190.6684.581.3588.8080S, RNH
FRMM194.120.6294.471.41914.9820S, RNH
FRMM14.090.63114.341.381011.9080S, RNH
FRMM34.050.62124.241.44112.0610S, RNH
FRMM144.850.6114.151.47124.1530S, RNH
FRMM262.970.62244.081.361311.8450S, RNH
FRMM173.870.74134.021.47148.1530S, RNH
FRMM213.850.73143.951.44152.0860S, RNH
FRMM283.740.59153.911.39167.9270S, RNH
FRMM53.670.65164.911.4522.0920S, RNH
FRMM113.440.64173.851.431811.0310S, RNH
FRMM243.380.82183.791.42190.0070S, RNH
FRMM183.320.65193.431.42011.960S, RNH
FRMM103.240.73203.371.46214.140S, RNH
FRMM323.160.84213.231.44222.0730S, RNH
FRMM73.130.96224.921.37119.870S, RNH
FRMM93.020.88232.651.42292.0190S, RNH
FRMM302.940.98254.881.4311.9570S, RNH
FRMM162.830.9262.841.38321.9770S, RNH
FRMM272.740.97272.821.483120.0440S, RNH
FRMM42.690.88282.731.39305.1630S, RNH
FRMM132.651.05292.941.44242.0860S, RNH
FRMM292.610.93302.621.472811.9270S, RNH
FRMM122.570.45312.591.432713.2020S, RNH
FRMM232.530.93322.541.412615.910S, RNH
Table 5. Perspectives of PPP practitioners concerning financial risk mitigation measures.
Table 5. Perspectives of PPP practitioners concerning financial risk mitigation measures.
Perspectives of PPP PractitionersKruskal–Wallis Test
Project ManagersQuantity SurveyorsRisk ManagersAccountantsH-Stat.p-ValueSig./Decision
FRMMMSSDRank MSSDRank MSSDRankMSSDRank
FRMM14.831.4713.031.25282.591.08322.840.40315.690.00S, RNH
FRMM34.621.3822.681.11313.651.21192.730.303245.030.00S, RNH
FRMM44.591.3733.41.08253.131.19262.910.413012.520.00S, RNH
FRMM64.531.4244.721.0753.541.01213.020.492916.720.00S, RNH
FRMM74.431.4154.671.2264.311.18113.050.292813.620.00S, RNH
FRMM24.381.4464.621.2573.811.24173.110.37271.740.27INS, AAH
FRMM84.291.3874.570.8983.391.16233.170.642651.310.00S, RNH
FRMM54.181.4582.721.3093.211.29253.210.352511.620.00S, RNH
FRMM114.091.4594.411.37104.021.19153.270.24247.750.00S, RNH
FRMM324.031.43104.371.36112.851.15293.360.08235.310.00S, RNH
FRMM143.991.44114.311.32124.471.1853.440.29227.940.00S, RNH
FRMM233.761.40124.281.24133.971.34163.490.16216.810.00S, RNH
FRMM163.561.38134.241.16143.611.23203.530.202011.630.00S, RNH
FRMM153.491.34144.171.17152.721.05303.570.171911.420.00S, RNH
FRMM213.381.43154.131.26163.521.23223.640.291831.430.00S, RNH
FRMM303.321.42164.051.29174.291.21123.710.111712.410.00S, RNH
FRMM93.211.42173.941.26184.451.1963.760.20168.520.00S, RNH
FRMM173.171.39183.851.21193.281.24243.830.301516.300.00S, RNH
FRMM283.131.43193.811.30204.561.3323.870.111427.300.00S, RNH
FRMM103.071.44203.721.31214.241.25133.920.171328.800.00S, RNH
FRMM183.041.38213.671.20224.491.1544.100.331238.900.00S, RNH
FRMM262.951.40224.891.2724.391.33154.140.051114.900.00S, RNH
FRMM192.911.41233.491.20242.871.20284.190.35107.120.00S, RNH
FRMM272.861.42244.781.2533.741.26184.250.2096.620.00S, RNH
FRMM222.821.43253.251.26264.411.3184.320.23839.120.00S, RNH
FRMM202.791.41263.191.25274.531.1834.370.2779.400.00S, RNH
FRMM122.751.41274.961.2212.631.16314.470.3169.250.00S, RNH
FRMM312.691.45282.631.35324.421.3574.850.1210.100.89INS, AAH
FRMM132.661.46292.771.34304.341.23104.590.2047.090.00S, RNH
FRMM242.611.39304.481.2344.111.36144.720.25319.800.00S, RNH
FRMM292.591.36313.551.18233.091.32274.770.09299.000.00S, RNH
FRMM252.541.37322.891.15294.621.3114.530.26510.030.00S, RNH
Table 6. Analysis of project PPP types on financial risk management measures.
Table 6. Analysis of project PPP types on financial risk management measures.
PPP Infrastructure Project TypesKruskal–Wallis Test
Economic ProjectsSocial ProjectsEnvironmental ProjectsH-Statp-ValueSign./Decision
FRMMMSSDRank MSSDRankMSSDRank
FRMM114.851.0714.101.63143.150.07326.190.00S, RNH
FRMM94.810.7422.751.71303.190.723131.200.00S, RNH
FRMM154.780.7234.731.8523.280.79307.110.00S, RNH
FRMM84.730.7844.691.7633.320.612914.900.00S, RNH
FRMM174.690.7254.631.6243.410.642811.120.00S, RNH
FRMM64.580.4364.551.8553.491.062719.310.00S, RNH
FRMM214.420.4074.492.0863.551.222615.920.00S, RNH
FRMM24.410.3184.432.1873.651.31255.570.00S, RNH
FRMM104.380.3594.371.9183.711.202413.720.00S, RNH
FRMM14.340.29104.332.1693.751.302312.540.00S, RNH
FRMM134.320.23114.281.91103.791.142211.190.00S, RNH
FRMM74.260.06124.251.95113.821.252126.130.00S, RNH
FRMM164.220.13134.211.84123.821.15200.210.84INS, AAH
FRMM44.160.11144.191.78133.831.181926.820.00S, RNH
FRMM144.080.20152.712.07324.041.311817.830.00S, RNH
FRMM184.030.15164.081.90154.261.241743.120.00S, RNH
FRMM273.920.23174.032.03164.311.27160.041.05S, RNH
FRMM323.810.01183.972.02174.431.30155.590.00S, RNH
FRMM193.740.09193.912.04184.491.311412.130.00S, RNH
FRMM263.720.18203.881.88194.511.22139.910.00S, RNH
FRMM313.690.02213.701.73204.511.101213.140.00S, RNH
FRMM233.620.17223.621.82214.541.161110.290.00S, RNH
FRMM293.560.02233.551.79224.571.201020.320.00S, RNH
FRMM53.530.10243.432.06234.581.31911.110.00S, RNH
FRMM303.490.07253.382.08244.601.35816.910.00S, RNH
FRMM33.470.00263.271.83254.611.23731.290.00S, RNH
FRMM223.410.15273.151.70264.711.07618.100.00S, RNH
FRMM203.220.01283.061.91274.821.27513.320.00S, RNH
FRMM283.150.09292.931.95284.861.24412.390.00S, RNH
FRMM253.020.12302.731.75314.871.1539.110.00S, RNH
FRMM122.950.00312.830.45294.910.00212.131 0.00S, RNH
FRMM242.610.00324.761.3414.950.001 7.54210.00S, RNH
Table 7. Components, factor loadings, eigenvalues and variance explained from the factor analysis.
Table 7. Components, factor loadings, eigenvalues and variance explained from the factor analysis.
S/NFinancial Risk Mitigation Measure (FRMM)Components/Factor Loadings
123456
Component 1Resilient budgets and financial plans
FRMM2Involve community leaders and stakeholders in financial risk management plans 0.914
FRMM3Consult Ghanaian financial experts on PPP projects 0.901
FRMM6Spend within the project budget 0.871
FRMM12Financial budgeting in the transition to sustainable projects 0.856
FRMM24Constant updates in the financial risk response plan 0.825
FRMM28Allow for a green participative budgetary process 0.781
FRMM30Sustainable budgetary funding from the government0.763
Component 2Ensure inclusive cost controls
FRMM5Early detection of expenditure in fighting climate disasters in the project 0.883
FRMM7Apply sustainable financial instruments to reduce operating costs 0.852
FRMM10Embrace sustainable PPP financial contract management practices 0.844
FRMM11Promote diversity and inclusion in financial management 0.813
FRMM15Implement net-zero procurement cost measures 0.776
FRMM22Institutionalise audit controls and committees 0.723
Component 3Apply sustainable funding strategies
FRMM1Review PPP financial agreements from Ghana’s Ministry of Finance 0.896
FRMM9Make use of financial data from international institutions and Ghana’s parliament 0.853
FRMM26Eradicate corruption and misuse of project funds 0.826
FRMM27Sustainable renegotiation of financial contracts 0.782
FRMM29A reasonable concession period for the recoupment of private investment 0.768
FRMM32Borrow green finance at the lowest interest charges 0.715
Component 4Practise revenue-boosting measures
FRMM17Apply sustainable value-for-money models 0.864
FRMM20Affordable user fees to attract more revenue 0.831
FRMM25Minimum and sustainable revenue guarantee to private investors 0.806
FRMM31Inflation-linked operating revenue from the project 0.767
Component 5Promote innovative skills and competencies
FRMM14Net-zero transition cost management skills 0.897
FRMM16Ensure high professionalism and competence of the project finance team 0.885
FRMM23Equip the project team with green and sustainable financial management skills 0.747
Component 6Build green financial risk analysis models
FRMM13Lifecycle financial risk analysis on the sustainability of PPP projects 0.828
FRMM18Cost and benefit evaluation of the energy consumption of the infrastructures 0.756
FRMM21Robust and transparent financial risk reporting systems 0.729
Eigenvalues5.4193.7643.1052.8451.7931.041
Variance explained (%)24.19218.13512.1148.7214.9282.921
Cumulative variance explained (%)24.19242.32754.44163.16268.0971.011
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Akomea-Frimpong, I.; Jin, X.; Osei-Kyei, R. Mitigating Financial Risks in Sustainable Public–Private Partnership Infrastructure Projects: A Quantitative Analysis. Systems 2024, 12, 239. https://doi.org/10.3390/systems12070239

AMA Style

Akomea-Frimpong I, Jin X, Osei-Kyei R. Mitigating Financial Risks in Sustainable Public–Private Partnership Infrastructure Projects: A Quantitative Analysis. Systems. 2024; 12(7):239. https://doi.org/10.3390/systems12070239

Chicago/Turabian Style

Akomea-Frimpong, Isaac, Xiaohua Jin, and Robert Osei-Kyei. 2024. "Mitigating Financial Risks in Sustainable Public–Private Partnership Infrastructure Projects: A Quantitative Analysis" Systems 12, no. 7: 239. https://doi.org/10.3390/systems12070239