Next Article in Journal
Flying Capacitor Double Dual Boost DC-DC Converter
Previous Article in Journal
An Implementation of Communication, Computing and Control Tasks for Neuromorphic Robotics on Conventional Low-Power CPU Hardware
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

The Change in Maintenance Strategy on the Efficiency and Quality of the Production System

Department of Industrial Engineering, Faculty of Mechanical Engineering, University of Zilina, Univerzitna 8215/1, 010 26 Zilina, Slovakia
*
Author to whom correspondence should be addressed.
Electronics 2024, 13(17), 3449; https://doi.org/10.3390/electronics13173449
Submission received: 2 July 2024 / Revised: 23 August 2024 / Accepted: 28 August 2024 / Published: 30 August 2024
(This article belongs to the Section Industrial Electronics)

Abstract

:
The presented contribution deals with the research of the maintenance strategy and procedures for improving maintenance processes in order to increase the efficiency and quality of the production system. It is based on a thorough analysis of the research of the available literary sources published in foreign and domestic scientific journals. The subsequent proposal includes defining new goals and maintenance performance indicators relevant to today’s production systems to track improvements in the sustainable development of the production system. There are also basic principles of the maintenance strategy with links to the production system and the choice of strategy for the organization. This paper emphasizes the audit of maintenance management and the implementation of quality in maintenance. Next, a new procedure for changing the maintenance strategy is described. This process includes reviewing the criticality of machines and equipment and their structural units, then resource and capacity planning and inputs for maintenance management, and the impact of maintenance on the operating costs of the production system. This was based on which partial projects in companies were verified—automotive industry (spare parts, preventive maintenance, planned maintenance, RCFA, TPM), rubber industry (quality, production efficiency), pharmaceutical industry (preventive and predictive maintenance), engineering industry (TPM, LOTO, RCM). The overall verification of the creation of the maintenance strategy and the proposed methodology was carried out on the basis of the outputs of the sub-projects and overall projects in the following companies with positive results—glass industry, chemical industry, and operational research (research and development of equipment for non-reactor parts of nuclear power plants). Ten steps of the audit of the current state of the management of maintenance processes were proposed, to ensure economic improvements in the costs of maintenance processes and operating costs, ensuring competitiveness. A methodology for changing the maintenance strategy focused on the efficiency, quality, and costs of the production system was proposed. The average benefits from the implementation of strategy changes in organizations reached at least the following: (1) increase in production efficiency—OEE (7%), (2) improvement in production quality (20%), (3) improvement in performance (15%), and (4) reduction in maintenance process costs (10%) in implemented projects.

1. Introduction

In recent years, we have experienced a tremendous boom in the digitalization of processes that speed up decision-making processes in manufacturing companies. The use of machine learning algorithms and artificial intelligence is gradually becoming a normal part of our lives. At the same time, newly designed production and assembly systems need maintenance systems for the maintenance management and diagnostics of production equipment. Enterprises [1] need to identify tools and technologies for maintenance planning and management in line with Industry 4.0 approaches. The focus is on the application of a maintenance prediction program, the implementation of technical diagnostics equipment, the implementation of smart sensors, the interconnection of equipment using the Internet of Things, and the use of mobile applications in maintenance.
The concept of Industry 4.0 [2,3,4,5] helps industrial enterprises to achieve rapid adaptation of new production and enable timely response against occurring faults caused by new production ramp-up and emerging production equipment failures by using an intelligent maintenance system integrated into a digital twin. The maintenance manager uses standard indicators such as OEE (overall equipment effectiveness), MTTR (Mean Time to Repair), MTBF (Mean Time Between Failure), R (t) (Probability of trouble-free operation), F(t) (Probability of Failure), A (Availability), λ (Intensity of disturbances), and availability and reliability of machines and equipment. These indicators take a picture of the state of operation of the production and assembly lines in detail for decision making. The above indicators are obtained from data sensed by sensors on the plant floor.
Maintenance departments are still “fighting fires” instead of tackling their problems systematically. Instead of waiting for problems to occur, prevention is a better goal. Although this strategy may be a bit costly initially, it is much less costly compared to waiting for problems [6,7]. Maintenance performance is concerned with four areas: maintaining critical systems, fixing the problem faster than before, determining the causes of frequent failures, and, finally, identifying the 20% of failures that occupy 80% of the available resources.
The most common troubleshooting process in maintenance includes identifying faults and where machine failures occur, analyzing faults, defining cause relationships, defining goals, and planning resources to eliminate and prevent faults [8]. Maintenance is the combination of all practical, managerial, and administrative activities throughout the life cycle of an installation to maintain or restore it to a state in which it can perform its required function. It is also defined as all the necessary and essential activities that are required to maintain a system throughout its life cycle in an operational and functional state or to restore it to a state in which it can perform its intended function [9,10]. The importance of the maintenance function has increased over time due to its role and impact on the rest of the working environment in the organization, i.e., by improving product quality and machine availability. Effective maintenance contributes to increased value through more profitable use of resources, improved product quality, and reduced rework and scrap [11]. The maintenance is categorized into two main areas, i.e., preventive maintenance, which includes all planned maintenance activities such as condition monitoring and periodic inspection, while corrective maintenance has to do with all unplanned maintenance activities to restore failure (Figure 1).
As always, the basic commitment of creation is to deliver the goods, but an effective maintenance strategy affects the production capacity of the machines used to produce these products [12]. Therefore, maintenance can be considered as an organizational purpose that works in concert with production. When others reiterate that production produces products, others also say that maintenance produces the capacity for production.
A company’s profitability and survival may not be sustained without maintaining product quality. High quality can serve as a major edge to a company’s competitive advantage and long-term profitability in the modern global economy. Normally, it is said that equipment/machines that lack maintenance and break down often lose speed and therefore cause defects (breakdowns). This equipment usually out of control production processes. Obviously, a process that is out of control leads to the production of defective products and increases the cost of production, which minimizes profit [13,14].
Profitability is the result of price and productivity recovery. Consequently, productivity determines the efficiency and effectiveness of the production process. According to the APQC (American Productivity & Quality Center), cited by [15], when analyzing the profitability of maintenance, the impact of the work area is also measured, for example, by guaranteeing the role of maintenance within the life cycle of the machine. In general, maintenance improvement aims to reduce operating costs and increase product quality [16,17].
Certainly, if there is a connection or rather a link between maintenance and profitability, the diagram in Figure 2 shows how these two objectives are linked together.
Maintenance strategy and maintenance activities are managed in accordance with the established maintenance policy and with the intention of achieving the desired objectives. The maintenance strategy for the production support process (as part of the company’s strategy) can be based on and support the company’s objectives and strategy, perspectives, and background.
For the development of the maintenance strategy, the enterprise strategy provides information on the expected production and product portfolio, expected production expansion and contraction programs, expected changes in production equipment and other tangible assets, logistical aspects of production processes, expected financial resources, and the way production equipment is operated and used (it provides information on the expected variability in the use of production equipment and the resulting expected intensity of use of the calendar time pool, the required times of use and operation, the consequent required volumes of maintenance activities, etc.).
For the purposes of the maintenance strategy, these data are expanded into a more detailed and specific form (e.g., the structure and number of production facilities, data on their reliability, in particular the requirements for the volume of preventive and corrective maintenance in standard hours, possibly also in financial terms, the requirements for mechanical, electrical, and other maintenance, the expected structure of internal and external maintenance, outsourcing, serviceability, criticality of inclusion in production lines and processes, the effects of downtime, etc.).
The results achieved in the medium and long term depend on the maintenance strategy. It is mainly about efficiency, productivity, economic efficiency, and the fulfillment of basic maintenance requirements, in particular, the following:
  • Keeping assets in a serviceable and adequate condition;
  • Preventing breakdowns;
  • Operational troubleshooting;
  • Reducing the environmental impact of the operation of the equipment;
  • Ensuring operational safety;
  • Incurring optimum maintenance costs;
  • The objectives should be hierarchical, quantified, realistic, and mutually aligned. If a company chooses a strategy, it must implement it consistently if it is to be successful.
Strategies can focus on, for example, the following:
  • Seeking opportunities that make the most of strengths;
  • Overcoming weaknesses to exploit opportunities;
  • Using strengths to eliminate risks;
  • Preventing weaknesses from being attacked, etc., [18,19].
The required level of maintenance of the long-term asset, the model of excellence, is based on the following:
  • “world-class” best practice maintenance experience, but for specific organizations, it must be tailored to their internal and external conditions [20,21];
  • From a methodological point of view, it is more efficient and practical to determine the levels of excellence directly by individual audit criteria and for individual management audit questions;
  • This process is extremely difficult and objective information is often lacking, so it is necessary to take an expert to intuitive approach to determining the level of excellence;
  • Benchmarking can be a great help if the required data can be obtained.
The expected benefit, provided the organization’s strategy is properly integrated into maintenance management, is a significant improvement in its performance, efficiency, and overall economic effectiveness. If the implementation of the strategy is to be successful, it must be known in the organization and supported by maintenance management [22,23].
It is about creating a sense of belonging amongst the workforce at the company and the workplace. Motivation should be the feeling that their work is meaningful.
In the process of developing a strategy, a long-term program of improvement and change is created, including a change in working style. In the long term, a flat organizational structure and the use of small, autonomous, and flexible groups are best suited to achieving this in a flexible way. It is common to see a change in organizational structure with a change in management. Thus, if maintenance is centralized, it is changed to decentralized and vice versa. Similarly, the trend in companies is to focus on the “core business” and to separate other activities—in the case of maintenance, not to outsource them [24,25,26,27].
There is currently no coherent view of the different organizational structures and their models for businesses, and, in principle, there should be no reason why. Each form of maintenance organization has its pros and cons. Similarly, in-house maintenance is not automatically better or worse than contractor maintenance. It is up to the management of the enterprise to consider the specific conditions, make the most of the strengths, and counteract the weaknesses of each system.
When designing the methodology for changing the maintenance strategy with an impact on the efficiency and quality of the production system, there is analysis of the research of the available literary sources published in scientific foreign and domestic journals.
Several maintenance methods emerged to cover needs in industrial processes: preventive maintenance (periodic review and cleaning systems), predictive maintenance (analysis of equipment using physical variables), and corrective maintenance [28,29,30].
Predictive maintenance has been extensively studied during the last thirty years by academic researchers and industrial practitioners. The recent literature discusses several designs for predictive maintenance based on Industry 4.0’s main technologies, such as IIoT, Cloud Computing, and Big Data Analytics. This development offers an excellent opportunity to use condition-monitoring data intelligently within predictive maintenance, combining the ability to collect data with an effective and integrated analysis of them [31].
When the maintenance contribution in the production profit is more than its cost, it is considered cost-effective, and the same thing can be said about any investment maintenance [32,33,34,35,36].
The E-manufacturing paradigm was enabled by ubiquitous Internet and telecommunication facilities, which helped manufacturing operations to achieve a predictive near-zero-downtime performance as well as to synchronize with the business systems [37].
The literature on maintenance strategy formulation and selection has so far been very limited. Maintenance strategy selection is a critical decision-making problem for the maintenance managers working in the process plant, manufacturing companies, etc., [38,39,40]. In manufacturing, the goal of learning is not to obtain knowledge but to use it to make decisions through reasoning. Compared with learning, reasoning focuses on making decisions [41,42,43].
Most of the architectures in the literature were designed to address a specific aspect of maintenance, rather than provide a comprehensive framework that incorporates all types of maintenance. This lack of a conceptual framework makes it difficult for modern firms to design and implement effective and efficient maintenance strategies [44,45,46,47].
Solutions for maintenance processes were found in the current literature, based on which a new strategy change procedure was created, oriented to the area of the production system (efficiency, quality, operational costs). The impact of maintenance represents a total of 15 to 60% of the total costs of operating all manufacturing. The maintenance activity requires strategies and planning to meet the needs of quality, safety, and productivity. The growth of the concepts of Industry 4.0 brings new opportunities and challenges. We performed a systematic literature review methodology that resulted in a total of 47 articles on methods, architectures, and technologies aligned with the application of predictive maintenance. This study critically analyzes the studies considering the main challenges of the area, including the visualization of possible standardizations and difficulties in their implementation [48].
The added value of the created proposal is precisely in the verification and fine-tuning of the maintenance strategy change procedure with practical verification.
The translated contribution is based on publication sources that have been verified on sub-projects. The added value and novelty in the research are the methodology of changing the maintenance strategy, which focuses not only on reducing the costs of maintenance processes, but also on improving the efficiency and quality and reducing the operating costs of the production system. The overall proposal was verified on complex strategy change projects with a positive result.

2. Methodology

The maintenance objectives and strategies are intended to guide maintenance management to achieve “excellence” in the maintenance of physical assets. The developed maintenance strategy requires the development of support programs for its implementation. This output should take the form of proposals for improving maintenance with a time horizon of solutions of usually up to one year (exceptionally longer), with defined responsibilities for solvers and implementers, resources, and individual implementation milestones. The same attention as when designing support programs must be paid to their implementation.

2.1. Maintenance Strategies for Long-Term Asset (LTA)

The marketing strategy is based on the organization’s municipal business strategy, which describes the organization and the services provided, the key customers, and their degree of satisfaction. It describes an analysis of financial performance and a survey of the competitive and market environment plus strengths, weaknesses, and key business competitive factors. The strategy of the organization provides the business vision of the organization, the specifics of the mission, the main goals, and the business plan for achieving them, as well as creating the required maintenance strategy. Characteristics of production equipment and other fixed assets that result from the maintenance strategy are the following:
  • The structure and numbers of production facilities;
  • Data on their reliability, durability, sustainability, maintenance, and availability, in particular, the requirements for preventive maintenance and maintenance volume in standard hours, post-failure maintenance, in standard hours, and, where appropriate, in financial terms;
  • Mechanical, electrical, and other maintenance requirements;
  • The expected structure of internal and external maintenance service provision;
  • Criticality of equipment to production lines and machines;
  • The impact of downtime on production.
Areas for maintenance care for fixed assets are the following:
  • Maintenance management encompasses all management activities that determine the objectives, strategies, and responsibilities of maintenance and that management applies by such means as planning, directing, and controlling maintenance and improving methods in the organization, including economic considerations.
  • Maintenance objectives represent the goals assigned and adopted for maintenance activities; these objectives may include, for example, availability, cost reduction, product quality, environmental protection, and safety.
  • The maintenance plan is a structured set of tasks that includes the activities, procedures, resources, and scheduling required to carry out maintenance.
  • The development of a specific LTA maintenance strategy could be based on the proposed corporate strategy development model. The basis for the design of the maintenance strategy is the acquisition of correct and objective input data and information and their transformation into the required maintenance strategy and subsequent maintenance improvement projects based on them.

2.2. Algorithm Design for Development of Maintenance Strategy and Concept

The methodology for the development of the maintenance strategy and concept defined the input data, information, and starting points. The development of the “Maintenance Strategy” document can be based on team-work and in cooperation with the various departments that are either directly or indirectly affected by the processes. Prior to release, the document should be reviewed by the organization’s senior management, regarding the feasibility and security of the required resources. It should be borne in mind that this document is intended to set the guidelines for maintenance management to achieve excellence in long-term asset maintenance. The final output must be the identification of key tasks to bridge the gap between the current state and the target state of maintenance management excellence in the organization. This output should take the form of maintenance improvement in project themes with a time horizon for resolution of generally up to one year and exceptionally longer, and with defined responsibilities for the developers and implementers of these projects, resources, and individual milestones for implementation.
The output of the Figure 3 algorithm is a “Maintenance Strategy” document with a time horizon of up to three years and a “Maintenance Concept Development” document with a horizon of about 1 to 1.5 years and a “Maintenance Strategy” for 10 years. The algorithm indicates the creation of a strategy that begins with the analysis of the basic characteristics of production equipment and their maintenance requirements and the current results of maintenance audits. This strategy is based on the excellence model and the maintenance audit. Subsequently, a maintenance strategy concept is created, which contains selected elements—areas of strategy excellence (graphically marked part—gray color). The output of the maintenance concept is a 3-year strategy proposal. Subsequently, projects are proposed for implementation on an annual basis, which are then evaluated, and the current maintenance strategy is updated.

2.3. Maintenance Management Audit

An audit is a systematic, independent, and documented process of obtaining objective evidence and evaluating it objectively to determine the extent to which the audit criteria of the audit are being met (sometimes also called a status assessment of maintenance processes). Audit criteria are a set of policies, procedures, or requirements that are used as evidence against which objective evidence is compared [49,50]. Records, reports, statements of fact, or other information that relate to the audit criteria and are verifiable may be considered as audit evidence. Audit findings are then the results of the evaluation of the collected audit evidence against the audit criteria. An audit finding may be the following:
  • Compliance or non-compliance (with the audit criteria);
  • Compliance or non-compliance (with regulatory requirements or with regulatory requirements);
  • An opportunity for improvement;
  • A record of good practice [51,52,53,54].
Based on the above criteria for maintenance audits, a system of questions (indicators) and their assessment should be designed to enable practical auditing of possession management in organizations of different types and focuses.
The biggest challenge is evaluating the answers to these questions and quantifying the level of fulfillment of the criteria and requirements contained therein. The evaluation should consider the rating (1—low importance, 2—medium importance, 3—high importance). The questions containing the criteria and the actual answer must be formulated not only in qualitative terms, but also evaluated in terms of percentage points (0% is absolute non-fulfillment of the criterion and 100% is absolute perfect fulfillment of the required criterion).
An even more challenging problem is the determination of the ideal value of the ideal quality criterion of maintenance management. This involves knowing such ideal values as the optimal proportion of preventive maintenance, the optimal proportion of external (outsourced) maintenance, the optimal size of maintenance resources, the optimal ratio of the number of managers and technicians to the number of manual maintainers, etc. An important aid in this area is the benchmarking of maintenance management, carried out at the level of plants in one organization, then between organizations of the same production focus at the national level, and, where appropriate, at the international level. Work of this type is currently in its infancy.
A team-based way of handling responses is preferable to a single worker’s solution. Each question represents one quality indicator of maintenance management, and in addition to the qualitative answer, the quality level Q in percentage is to be assigned based on expert judgement of the level achieved for that indicator (question). The average quality level of the indicator for each area of maintenance management shall be determined by a weighted average (1) as follows:
Q i = j = 1 n i w i j Q i j j = 1 n i w i j
where (Q—the average quality level of indicator i in that area of maintenance management),
W (i—the value of the j-th indicator (question) in the i-th maintenance management area).
Qij—the quality level of the j-th indicator (answer to the question) in the i-th maintenance management area and not the number of indicators (questions) set in the i-th maintenance management area. For example
Qi = (2 × 95 + 3 × 85 + 3W + 3 × 70 + 3 × 65 + 2 × 78 + 3 × 90)/(2 + 3 + 3 + 3 + 3 + 2 + 3) = 1565/19 ≈ 81%
The calculation is performed by averaging the quality level of the indicators of the first maintenance management area.
The basis for the evaluation of the maintenance audit is the qualitative and quantitative written responses (Figure 4) and external benchmarking shown in Table 1.
In the analyzed state of external benchmarking, Nordic countries had lower targets than world-class enterprises based on the literature research and publications [55,56,57,58]. What we wanted to draw attention to this to the professional and scientific community.
These quantitative results give an immediate insight into the weaknesses of maintenance management. The most important part of the audit is the qualitative answers to the individual questions and their thorough evaluation. The set of questions (indicators) presented is certainly not definitive and exhaustive. It should be considered as an open system that can be further expanded and refined based on experience. [59,60,61,62,63]
The result of this maintenance audit must be a proposal for corrective action to eliminate the causes of the identified deficiencies and to prevent their recurrence. To ensure competent and reliable production facilities while eliminating material and human factors, to maintain absolute quality (100% excellent product condition), it is necessary to implement quality maintenance [64,65,66,67] for which it is necessary to determine the following:
  • Conditions for lining up and setting up for the first time;
  • Conditions for preventive maintenance to achieve a state of zero defects;
  • Determine the causes and consequences that affect the magnitude of deviation from the nominal value;
  • Determine the control and measurement of defined operating and technical conditions of the equipment at time intervals;
  • Based on the magnitude of the deviations, a maintenance plan for the machinery and equipment. [68,69,70,71,72,73]

3. Results

The proposed strategy change procedure was based on current audits. The research in maintenance strategy and the procedure of improving maintenance processes to increase the efficiency and quality of the production system is based on the audits carried out in Slovak companies, where the projects of maintenance strategy development were implemented. At the same time, knowledge from the APVV (Slovak research and development agency), for example, project Integrated Modular System of a Factory Twin and VEGA grant projects (The Ministry of Education, Research, Development, and Youth of the Slovak Republic is the central body of the state administration of the Slovak Republic for elementary, secondary and higher education, educational facilities, lifelong learning, and for the state’s support for research, development, and youth), for example, VEGA 1/0524/22: Research of a proactive approach to the sustainability of production systems in crisis conditions in the context of the green economy, and VEGA 1/0633/2024: Research and support of the synergistic effect of optimization of assembly processes was applied [74,75,76,77,78,79].
On the basis of which partial projects in companies were verified (Continental—automotive industry (areas: spare parts, preventive maintenance, planned maintenance, FCA, TPM), Continental Tires Slovakia—rubber industry (areas: quality, production efficiency), Zentiva—pharmaceutical industry (solved areas: preventive and predictive maintenance), PSL—engineering industry (areas: TPM, LOTO, RCM)), the overall verification of the creation of the maintenance strategy and the proposed methodology was carried out on the basis of the outputs of the sub-projects and overall projects in the following companies with a positive result (Johns Manville—glass industry (glass and mineral fibers), RONA—glass industry, Fortischem—chemical industry, VÚEZ—operational research (research and development of equipment for non-reactor parts of nuclear power plants)). Potential areas of improvement and maintenance issues have been identified based on sub-projects as follows:
  • Lack of planning of maintenance activities, weaker planning (lack of planning).
  • Informal communication of the work to be performed with maintenance (flow of requirements).
  • Lack of leadership of maintenance staff on afternoon and night shifts. Most work performed ad-hoc, without work orders.
  • Working independently, without collaboration.
  • Lack of a plan for work to be performed outside of breakdowns.
  • Insufficient, weak reporting.
  • Lack of autonomous maintenance.
  • Duplicated work, many things are controlled by the supervisor and by the maintenance person.
  • No defined standards for specific work.
  • Lack of motivation of shift maintenance for performing the work. It could perform it faster.
  • Lack of criteria for evaluating the productivity of the maintenance worker. (What he wrote down did not correspond with what he performed.)
  • Work by individuals or small groups without collaboration.
  • Multi-level hierarchical structure of maintenance.
  • Inappropriate ratio of maintenance worker’s activities, inappropriate organization of work (Figure 5 and Figure 6).
  • Lack of planning worker.
  • Failure to carry out preventive maintenance and planned repairs due to the following:
  • planned preventive maintenance and planned repairs—production does not make equipment available.
  • production puts equipment on standby—no maintenance capacity.
  • planned repairs—maintenance capacity is available; production makes the equipment available—spare part (SP) according to EN13306 is not in stock.

3.1. Proposed Change to the Maintenance Strategy

By analyzing the potential for improvement and by analyzing the processes carried out by which the company organizes its activities and resources to achieve its long-term goals, to ensure the competitiveness and profit of the company, the steps to change the strategy have been proposed in Figure 7. The strategy change steps are as follows:
  • Analysis of the current situation, maintenance audit.
  • Benchmarking.
  • Criticality assessment of machinery and equipment.
  • Evaluation of current maintenance processes.
  • Selection of a new maintenance strategy.
  • Comparison of the existing maintenance system and the proposed maintenance system.
  • Implementation of a new maintenance strategy.
Before choosing a strategy, it is necessary to familiarize yourself with the individual concepts of maintenance strategies.
Based on familiarization with the individual strategies, we proposed 10 areas of improvement in the audit of the maintenance strategy (in Slovak understanding, management assessment of the status of maintenance processes):
  • Management strategy, goals, and indicators
Analysis of the maintenance strategy for +3 years and more, breakdown of the strategy into activities, what results are achieved in fulfilling the strategy and goals of the maintenance department, and what KPIs in maintenance are monitored.
2.
Preparation and approval of the maintenance budget
How is the maintenance budget defined, breakdown analysis into items, evaluation of budget utilization and trend, and budget controlling.
3.
Organizational structure of maintenance, competence, and responsibility
Evaluation of the organizational structure, assessment of the number of maintenance workers and determination of the number of maintenance workers, matrix of competences, and responsibilities of maintenance workers.
4.
Strategy for carrying out maintenance activities
Categorization of technological units, evaluation of the methodology for machine categorization (critical machine), choice of maintenance strategy for individual categories, and ratio of corrective versus preventive maintenance and trend.
5.
Reactive maintenance system—after failure
How is maintenance after a failure—reporting, start-up, progress, statistics, results, production feedback, and optimization of interventions.
6.
Preventive maintenance system
How and who creates preventive maintenance plans, the content and scope of the introduction of the PU concept, the content of individual PU performances, intervals, and their setting, and the calendar of preventive activities.
7.
Autonomous maintenance system
Content and scope of introduction, content and form of AU standards, comprehensibility for operators, and spot check of compliance directly in production.
8.
Safety of work on machines and equipment
Analysis of the approach to occupational safety in the framework of repairs—establishment—planned maintenance interventions, risk assessment system associated with the safety of the work of maintenance workers, and results and trends in the development of injuries and near-accidents.
9.
Management of administration and management of spare parts
Objectives and strategy in the area of ND management, analysis of inventory structure (quantity, value, storage time), ND selection methodology for storage, determination of level height (min., max.) for stored parts, optimization of inventory height, location of ND warehouses and records, and arrangement and organization of ND warehouses.
10.
Knowledge management and development of maintenance workers
Maintenance qualification requirements, development plan, form of development, and planned and drawn investments for development.
The area of the maintenance strategy change algorithm is summarized in 10 steps, where we focused on all maintenance processes as follows:
  • FFM: Failure-Finding Maintenance, i.e., a functional test or inspection of a hidden failure of the equipment. Depending on the results, repairs are carried out.
  • CBM: Condition-Based Maintenance, i.e., the maintenance activities consist of periodical inspections or online measurement of the technical condition of the equipment. Depending on the measured condition, repairs are planned or carried out.
  • TBM: Time-Based Maintenance, i.e., this means regular periodic maintenance.
  • SM: Scheduled Maintenance, i.e., the maintenance activities are carried out based on the use of the equipment (i.e., time, hours, operations etc.). It is independent of the condition of the equipment.
  • MOD: Modification, i.e., it must be changed. This does not mean it has to be technical—it can be a change of spare parts or instruction.
  • RTF: Run to Failure, i.e., the failure will be solved when it occurs. No preventive maintenance.
Based on the benefits of and reduction in maintenance costs, a suitable strategy concept is selected. As a result of analyses of studies from past periods and current experience, a recommended annual plan for changing the maintenance strategy was proposed (Figure 8). Control milestones are defined to verify the task performance of the strategy development project, as shown in Figure 9. In designing the schedule, we focused on the maintenance system, the maintenance processes, and the maintenance staff, who are scheduled to perform each task on a week-by-week basis.
It is necessary to develop an RACI matrix (Responsible, Accountable, Consulted, Informed) for the different maintenance processes and responsibilities for activities within the maintenance management system. The sequence of steps begins with the indicator design system.
Current maintenance management indicators need to be reviewed. Table 2 presents a proposal of maintenance indicators to meet the milestones of the new strategy development project. To effectively commission the system and maintain it at the optimum life-cycle cost in the long term, maintenance and provisioning activities need to be planned and the necessary resources procured.
These activities start early in the conception and development phase and continue throughout the subsequent stages of the life cycle. The objectives of maintenance activity planning and maintenance assurance are as follows:
  • Develop a maintenance concept and add maintenance and maintenance assurance requirements to the system requirements;
  • To determine the effect of system maintainability design in the form of maintenance requirements and to optimize the maintenance concept;
  • Define the maintenance provisioning requirements and the maintenance plan;
  • Specify the resources required.

3.2. Evaluation of Maintenance System Selection Alternatives and Optimization Procedure Analysis Steps

The objective of the evaluation of alternatives is to select a maintenance assurance system. The analysis of the optimization procedure for operation and maintenance provisioning is part of the inherent development system. Optimal benefits are obtained when these analyses consider all system factors (cost, schedule, operational characteristics, and maintenance provisioning) before system development is completed. The following steps are to be performed in the evaluation and analysis of the optimization procedure:
  • Identify criteria that are related to maintenance provisioning requirements, cost, and availability;
  • Select or develop models or analytical relationships between the maintenance provisioning design and the operational or any other identified evaluation criteria;
  • Perform an optimization procedure or evaluation that uses the developed relationships or models, and select the best alternative(s) based on the developed criteria;
  • Perform sensitivity analyses of those variables that have a high degree of risk or a significant impact on the maintenance provision, cost, or availability of the new system;
  • Document the results of the optimization procedure and evaluation, including any risks and assumptions involved.

4. Discussion

Following research into a maintenance strategy and maintenance process improvement procedure to increase the efficiency and quality of the production system through the application of the proposed methodology/algorithm for changing the maintenance strategy, results were achieved, which showed a positive impact on the production efficiency and quality. As part of the project solution, control meetings between the project team and company management took place on a regular basis, where the results achieved during the change in the maintenance strategy were positively evaluated and further improvements were proposed.

4.1. Achieved Impact of Maintenance Strategy Change on Production Efficiency

The overall equipment effectiveness (OEE) rating is a function of losses due to faults (interruptions), power losses due to reduced speeds and queuing times, and low quality of the products produced (Figure 10).
Maximizing the efficiency of equipment operations and minimizing costs over its life cycle could be ensured by eliminating the “six major losses” that significantly affect the efficiency of equipment on schedule. It was mainly about reducing failures resulting from equipment defects, rearranging, and setting up (changing jig, tool, etc.), eliminating inactivity, idling and small breaks, process errors and repairs (screw-ups and quality defects in need of correction), and reduction in time between machine start-up and stable operation. The determined critical OEE value of 72% was reached at the level of 82% during the project solution.

4.2. Impact of a Change in Maintenance Strategy on Production Quality

Through the new designs and the entire methodology of PPM (preventive planned maintenance), as well as all other supporting processes, detailed analysis of line object failures has been enabled. New possibilities have been opened for more efficient and faster problem analysis and corrective action to improve and stabilize the process, especially the production quality process.
However, due to the implementation of the so-called zero interval, improvements can already be seen in some indicators after a shorter period. Other important indicators can be estimated, or the expected improvement can be determined, but only after a certain period. The indicators that can be realistically assessed now relate to the number of materials discarded in the six-hour interval before the failure occurred. As can be seen in Table 3, the improvement in this indicator is approximately 24% compared to the initial situation. This means that 23.76% more blanks were discarded in the six-hour interval before the failure than before the introduction of the new preventive planned maintenance. This is also because its introduction has reduced the frequency of failures. The new preventive maintenance has thus had a positive impact on both factors, resulting in the improvement in the indicator.
A follow-up indicator that can also be measured in a shorter period after the introduction of PPM is the number of meters of semi-finished products discarded due to machinery.
The improvement in the two-week interval can be seen in Table 4. After the introduction of the proposals, the incidence of semi-finished products scrapped due to machinery decreased by 23.01% and the number of all semi-finished products scrapped, irrespective of the reason for scrapping, decreased by about 16%. These are significant improvements, which may be slightly distorted by the shortness of the monitoring interval, but the improving trend is evident. Talking not only about semi-finished products discarded due to machines is important because machines can still have an impact on other cases as well.
The previous indicators and improvements were expressed only for the production line whose winding station design was the subject of a pilot verification of the proposed methodology.
The financial evaluation of the design solutions and estimates of improvements have already been calculated for all five extrusion lines. This is because most of the quality indicators are related to the whole process and the new PPM plan will be gradually introduced on the other lines as well.
This financial assessment and the estimate of expected savings can be seen in Table 5. Three basic indicators (Scrap I, WOT—work off, downtime/faults) have been selected. For all indicators, improvements were estimated based on the changes made, experience, and especially in view of the improving indicators interpreted above. For Scrap I, the expected improvement after a certain period is at the level of four to seven percent. In this case, this is a lower expectation percentage because only tread and sidewall wastes do not enter Scrap I. The price saving is thus at a level of around €20,000 per month on average. For WOT, based on the intermediate results, improvements of up to 13 to 17 percent are expected. This amounts to an average of around €16,500 per month for both semi-finished products together with rework costs. A final indicator that directly reflects potential savings is the duration of downtime caused by failures. Here again, according to the assumptions and intermediate results, a reduction of 10 to 15 per cent in the duration of breakdowns is expected. In financial terms, this translates to an average of around €1150.
The cost of implementing design solutions is minimal. There is no need to purchase new equipment, software, or external help. Everything will be performed within the shutdown lines as before, with the same number of internal staff, etc. The only cost has been the salaries of the staff in setting up the PPM plan and training them. This cost was estimated at approximately €1100.
As a result, an average monthly saving of €36,500 is expected after the implementation of the proposed solutions on all lines. This represents an average annual saving of €438,200. It can be argued that this is a significant cost saving, which is mainly due to the improvement in the quality of the production process by using the newly designed PPM plan in the context of quality. It should be noted that everything so far only applies to the single most critical design unit within all five production lines of the production system.
Once the PPM plan is extended to the whole lines, even greater savings and improvements in the quality of the production process can be expected, as shown in Figure 11.

4.3. Impact of the Strategy Change on Spare Parts

As we found from the analysis of the current situation in the enterprises, most of the interviewed enterprises determine the size of the insurance stock and the associated signal level only by estimation, which is not supported either by calculation or by statistical methods.
Therefore, for a more objective and professional determination of the basic data for ND inventory management, we recommend their determination by calculation. However, the value determined by calculation may not be final but may still be adjusted as necessary by the responsible staff but based on the underlying calculations.
In the enterprise under analysis, it determines signal levels and order sizes by estimation, which is not very accurate, and some values may be incorrect. Therefore, we want to use calculations to determine the safety stock, signal levels, etc., and then compare the two options.
The following algorithm will be used for the calculations, for which data such as historical consumption data, the criticality of the ND SP, and the delivery time from the supplier are important. The algorithm can be seen in Figure 12. In Table 6, we can see based on which criteria we divide the items into groups A, B, and C.
The ABCX spare parts categorization is a comprehensive SP analysis where various data are examined such as how the part affects the functionality of the machine, the lead time of the part, the failure rate of the part, whether there is a replacement for the part, whether it is used in critical machines, whether it can be manufactured or refurbished, and whether it is a standard standardized part or a consumable part.
In Table 6, we see that category A has the most critical parts and category X the least. The overall criticality of spare parts (SP) is based on several criteria, which are then input into a matrix to determine the resulting SP criticality value.
After evaluating these sub-criteria, we develop a matrix that shows the real criticality of the work. The matrix is shown in Figure 13. We also call the criticality of the SP determined in this way the safety factor, which we then use to calculate the safety margins and signal levels.
The part located at position A1D shows the highest criticality and the part located at position C3F shows the lowest criticality. The overall criticality of the parts is more complex and is recommended for implementation in the SP Logistics Procurement and Management System. However, it can also be combined with other methods. The individual criteria are also assigned a score; after summing, the most critical part has a score of 4 and conversely, the least critical part has a score of −1.
Having made calculations based on the criticality of the SP, past consumption, and lead times to determine the new safety stock, signal levels, batch sizes, and minimum and maximum stock, we can say that for several items, the values were unreasonably high. The total value of the stock items decreased from €62,258.70 to €38,684.78 for the new variant, which is a reduction of €23,573.92. The comparison can be seen in Table 7 and Figure 14.

4.4. Impact of the Change in Strategy on the New Maintenance Organization

The proposed phased sequence of planned maintenance change steps, the change in staffing levels, is per Figure 12. This results in a reduction in maintenance staff from 77 to 53. The above change followed the plan to change the maintenance strategy by milestones (Figure 9). The change was implemented by reducing shift maintenance workers and sending workers to preventive maintenance tasks, as shown in Figure 15 and Figure 16. This achieves the same production and quality efficiency (or higher) with fewer workers, reduction in direct maintenance costs, and reduction in the need for SP. The reduction in maintenance capacities during the strategy plan change is shown in Table 8.
At the end of this contribution, the achieved impacts of the implemented changes in the maintenance strategy on one project implemented in a manufacturing company are presented.

5. Conclusions

The benefits of the proposal were presented in the Discussion, which are presented in Chapter 4. This change in strategy determines the complex functioning of the emergency strategy (Table 9) during which the achieved goals must be reassessed and the schedule for the next two years determined. This change in strategy determines the comprehensive operation of the emergency strategy, as shown in Table 9. Through the method of implementation, the measures, and the distribution of responsibilities in accordance with the requirements of the current internal and external environment, the aim is to provide the necessary resources for the different facilities to make the production process work and to ensure competitiveness.
Due to the current economic problems with the emergence of COVID, the energy crisis, and the war, every company should re-evaluate its maintenance strategy to update its maintenance processes and to determine a so-called emergency maintenance strategy to remain competitive. It is necessary to focus on the data that provide us with the required information. At the same time, we will prepare for the implementation of an intelligent maintenance system. For the suitability of the methodology for changing the maintenance strategy, we verified it in various areas of the industry. Regarding whether it has general application, we conclude that it does.

Author Contributions

Conceptualization, M.R. and P.B.; methodology, M.R.; software, P.B.; validation, M.R. and P.B.; formal analysis, K.S.; investigation, V.B.; resources, M.R.; data curation, M.R.; writing—original draft preparation, V.B.; writing—review and editing, V.B.; visualization, K.S.; supervision, G.G.; project administration, V.B.; funding acquisition, V.B. All authors have read and agreed to the published version of the manuscript.

Funding

This work was supported by the VEGA 1/0524/22 and VEGA 1/0633/24.

Data Availability Statement

Data are contained within the article.

Conflicts of Interest

The authors declare no conflicts of interest.

References

  1. Bubeníková, E.; Bubeník, P. Internet of things (IoT). Technológ Roč. 2017, 9, 131–134. [Google Scholar]
  2. Peniak, P.; Bubeníková, E. Validation of IoT secure communication gateway for constrained devices. In Proceedings of the International Conference on Applied Electronics (AE), Pilsen, Czech Republic, 8–9 September 2019; pp. 1–5. [Google Scholar] [CrossRef]
  3. Rakyta, M.; Fusko, M. Manažment konfigurácie údržby pre “Priemysel 4.0”. In Údržba 2016 = Mainte-Nance 2016: Sborník Mezinárodní Odborné Konference: 12. a 13. Října 2016, Konferenční Centrum AV ČR—Zámek Liblice; Česká Zemědělská Univerzita: Praha, Czech Republic, 2016; pp. 25–33. ISBN 978-80-213-2668-2. [Google Scholar]
  4. Campbell, J.D.; Reyes-Picknell, J.V.; Kim, H.S. Uptime: Strategies for Excellence in Maintenance Management; CRC Press: Boca Raton, FL, USA, 2015. [Google Scholar]
  5. Legát, V. Management a Inženýrství Údržby; Kamil Mařík-Professional Publishing: Praha, Czech Republic, 2016. [Google Scholar]
  6. Mushavhanamadi, K.; McGloin, K. Investigating the Risk Management Systems in the South African Banking Industry. In Proceedings of the International Conference on Industrial Engineering and Operations Management, Johannesburg, South Africa, 29 October–1 November 2018; pp. 1230–1237. [Google Scholar]
  7. Mushavhanamadi, K.; Selowa, T.B. The impact of plant maintenance on quality productivity in Gauteng breweries. In Proceedings of the International Conference on Industrial Engineering and Operations Management, EOM Society International, Washington, DC, USA, 27–29 September 2018; pp. 1743–1753. [Google Scholar]
  8. Dowler, P. CAOM-2.0: The inevitable evolution of a data model. Astron. Data Anal. Softw. Syst. XXI 2012, 461, 339. [Google Scholar]
  9. Blanchard, B.S.; Verma, D.C.; Peterson, E.L. Maintainability: A Key to Effective Serviceability and Maintenance Management; John Wiley & Sons: Hoboken, NJ, USA, 1995; Volume 13. [Google Scholar]
  10. Alsyouf, I. Cost Effective Maintenance for Competitve Advantages. Ph.D. Thesis, Växjö University Press, Växjö, Sweden, 2004. [Google Scholar]
  11. Al-Najjar, B. The lack of maintenance and not maintenance which costs: A model to describe and quantify the impact of vibration-based maintenance on company’s business. Int. J. Prod. Econ. 2007, 107, 260–273. [Google Scholar] [CrossRef]
  12. Duffuaa, S.O.; El-Ga’aly, A. Impact of inspection errors on the formulation of a multi-objective optimization process targeting model under inspection sampling plan. Comput. Ind. Eng. 2015, 80, 254–260. [Google Scholar] [CrossRef]
  13. Bubeník, P.; Horák, F. Knowledge-based systems to support production planning. Teh. Vjesn. 2014, 21, 505–509. [Google Scholar]
  14. Rakyta, M.; Binasova, V. Totálne Produktívna Údržba—TPM; EDIS: Žilina, Slovakia, 2016; ISBN 978-80-554-1210-8. [Google Scholar]
  15. Grenčík, J.; Rakyta, M.; Legát, V.; Meško, J.; Zvolenský, P.; Valent, O.; Pošta, J.; Kmoch, J.; Hrubec, J.; Tomčo, M.; et al. Manažérstvo Údržby 2: Synergia Teórie a Praxe, 1st ed.; BEKI Design: Košice, Slovakia, 2020; p. 697. ISBN 978-80-553-3539-1. [Google Scholar]
  16. Rakyta, M. Údržba Ako Zdroj Produktivity; GEORG: Žilina, Slovakia, 2002; ISBN 80-968324-3-3. [Google Scholar]
  17. Lee, J.; Ni, J.; Qio, H. Intelligent Prognostics Tools and E-Maintenance; Wichita University: Wichita, KS, USA, 2006; 487p. [Google Scholar]
  18. Preez, J. Thesis Presented in Partial Fullment of the Requirements for the Degree of Master of Science in the Faculty of Industrial Engineering at Stellenbosch University; Stellenbosch University: Stellenbosch, South Africa, 2011; 123p. [Google Scholar]
  19. Vyatkin, V. Function Blocks for Embedded and Distributed Control Systems Design; Standard IEC 61499; ISA: Auckland, New Zealand, 2007. [Google Scholar]
  20. Shirose, K. TPM Team Guide; Productivity Press, Inc.: Cambridge, MA, USA, 1995. [Google Scholar]
  21. Peniak, P.; Rástočný, K.; Kanáliková, A.; Bubeníková, E. Simulation of Virtual Redundant Sensor Models for Safety-Related Applications. Sensors 2022, 22, 778. [Google Scholar] [CrossRef] [PubMed]
  22. Peniak, P.; Bubenikova, E.; Kanalikova, A. Extended gateway model for OPC UA/IoT device integration. In Proceedings of the 2021 IEEE 19th World Symposium on Applied Machine Intelligence And Informatics (SAMI 2021), Herl’any, Slovakia, 21–23 January 2021; pp. 155–159. [Google Scholar] [CrossRef]
  23. Durica, L.; Micieta, B.; Bubenik, P.; Binasova, V. Manufacturing Multi-Agent System with Bio-Inspired Techniques: Codesa-Prime. MM Sci. J. 2015, 2015, 829–837. [Google Scholar] [CrossRef]
  24. Micieta, B.; Binasova, V.; Haluska, M. The approaches of advanced industrial engineering in next generation manufacturing systems. Commun.-Sci. Lett. Univ. Zilina 2014, 16, 101–105. [Google Scholar] [CrossRef]
  25. Micieta, B.; Macek, P.; Binasova, V.; Dulina, L.; Gaso, M.; Zuzik, J. Modular Intelligent Control System in the Pre-assembly Stage. Electronics 2024, 13, 1609. [Google Scholar] [CrossRef]
  26. Micieta, B.; Binasova, V.; Marcan, P.; Gaso, M. Interfacing the Control Systems of Enterprise-Level Process Equipment with a Robot Operating System. Electronics 2023, 12, 3871. [Google Scholar] [CrossRef]
  27. Bona, G.D.; Cesarotti, V.; Arcese, G.; Gallo, T. Implementation of Industry 4.0 technology: New opportunities and challenges for maintenance strategy. Procedia Comput. Sci. 2021, 180, 424–429. [Google Scholar] [CrossRef]
  28. Grenčík, J.; Rakyta, M.; Legát, V.; Meško, J.; Zvolenský, P.; Valent, O.; Pošta, J.; Kmoch, J.; Hrubec, J.; Tomčo, M.; et al. Manažérstvo Údržby—Synergia Teórie a Praxe; Slovenská Spoločnosť Údržby—BEKI Design: Košice, Slovakia, 2013; 630p, ISBN 978-80-89522-03-3. [Google Scholar]
  29. Mohan, T.R.; Roselyn, J.P.; Uthra, R.A.; Devaraj, D.; Umachandran, K. Intelligent machine learning based total productive maintenance approach for achieving zero downtime in industrial machinery. Comput. Ind. Eng. 2021, 157, 107267. [Google Scholar] [CrossRef]
  30. Al-Najjar, B. On establishing cost-effective condition-based maintenance: Exemplified forvibration-based maintenance in case companies. J. Qual. Maint. Eng. 2012, 18, 401–416. [Google Scholar] [CrossRef]
  31. Duffuaa, S.O.; Haroun, A.E. Maintenance Organization; Springer: Singapore, 2009; pp. 3–15. [Google Scholar] [CrossRef]
  32. Moore, W.J.; Starr, A.G. An intelligent maintenance system for continuous cost-based prioritization of maintenance activities. Comput. Ind. 2006, 57, 596. [Google Scholar] [CrossRef]
  33. Lee, J.; Singh, J. Intelligent Maintenance Systems and Predictive Manufacturing. In Proceedings of the 48th SME North American Manufacturing Research Conference, NAMRC 48At, Cincinnati, OH, USA, 22–26 June 2020. [Google Scholar]
  34. Wakefield, R.; Watson, T. A reappraisal of Delphi 2.0 for public relations research. Public Relat. Rev. 2014, 40, 577–584. [Google Scholar] [CrossRef]
  35. Alzghoul, A.; Backe, B.; Löfstrand, M.; Byström, A.; Liljedahl, B. Comparing a knowledge-based and a data-driven method in querying data streams for system fault detection: A hydraulic drive system application. Comput. Ind. 2014, 65, 1126–1135. [Google Scholar] [CrossRef]
  36. Crone, S.F.; Kourentzes, N. Feature selection for time series prediction—A combined filter and wrapper approach for neural networks. Neurocomputing 2010, 73, 1923–1936. [Google Scholar] [CrossRef]
  37. Wan, J.; Li, X.; Dai, H.N.; Kusiak, A.; Martinez-Garcia, M.; Li, D. Artificial-intelligence driven customized manufacturing factory: Key technologies, applications, and challenges. Proc. IEEE 2021, 109, 377–398. [Google Scholar] [CrossRef]
  38. Lu, Y.; Zheng, H.; Chand, S.; Xia, W.; Liu, Z.; Xu, X. Outlook on human-centric manufacturing towards Industry 5.0. J. Manuf. Syst. 2022, 62, 612–627. [Google Scholar] [CrossRef]
  39. Pekarcikova, M.; Trebuna, P. Modelling and projecting of disassembly processes. Procedia Eng. 2012, 48, 557–561. [Google Scholar] [CrossRef]
  40. Więcek, D.; Więcek, D.; Dulina, L. Materials requirement planning with the use of activity based costing. Manag. Syst. Prod. Eng. 2020, 28, 3–8. [Google Scholar] [CrossRef]
  41. Gasova, M.; Gaso, M.; Stefanik, A. Advanced industrial tools of ergonomics based on Industry 4.0 concept. Procedia Eng. 2017, 192, 219–224. [Google Scholar] [CrossRef]
  42. Bubenikova, E.; Holecko, P.; Pirnik, R. Optimisation of video-data transmission in telematic system. Adv. Electr. Electron. Eng. 2013, 11, 123–134. [Google Scholar] [CrossRef]
  43. Micieta, B.; Binasova, V.; Lieskovsky, R.; Krajcovic, M.; Dulina, L. Product segmentation and sustainability in customized assembly with respect to the basic elements of industry 4.0. Sustainability 2019, 11, 6057. [Google Scholar] [CrossRef]
  44. Mičieta, B.; Howaniec, H.; Dulina, Ľ.; Zuzik, J. Indication, Solution, Prevention: A Holistic Approach to Financial, Industrial Engineering, and Business Problem Analysis; (188 Nowoczesność przemysłu i usług= Modernity of industry and services); Silesian University of Technology: Gliwice, Poland, 2023. [Google Scholar]
  45. Dulina, L.; Zuzik, J.; Furmannova, B.; Kukla, S. Improving Material Flows in an Industrial Enterprise: A Comprehensive Case Study Analysis. Machines 2024, 12, 308. [Google Scholar] [CrossRef]
  46. Kuric, I.; Klarák, J.; Sága, M.; Císar, M.; Hajdučík, A.; Wiecek, D. Analysis of the possibilities of tire-defect inspection based on unsupervised learning and deep learning. Sensors 2021, 21, 7073. [Google Scholar] [CrossRef]
  47. Krajčovič, M.; Matys, M.; Gabajová, G.; Komačka, D. Utilization of Immersive Virtual Reality as an Interactive Method of Assignment Presentation. Electronics 2024, 13, 1430. [Google Scholar] [CrossRef]
  48. Abidi, M.H.; Mohammed, M.K.; Alkhalefah, H. Predictive Maintenance Planning for Industry 4.0 Using Machine Learning for Sustainable Manufacturing. Sustainability 2022, 14, 3387. [Google Scholar] [CrossRef]
  49. Arena, S.; Manca, G.; Murru, S.; Orrú, P.F.; Perna, R.; Reforgiato Recupero, D. Data Science Application for Failure Data Management and Failure Prediction in the Oil and Gas Industry: A Case Study. Appl. Sci. 2022, 12, 10617. [Google Scholar] [CrossRef]
  50. Supadulchai, P. Reasoning-Based Capability Configuration Management in Adaptable Service Systems; NTNU: Nórsko, Trondheim, Norway, 2008; 238p. [Google Scholar]
  51. Carsodo, D.; Ferreira, L. Application of Predictive Maintenance Concepts Using Artificial Intelligence Tools. Appl. Sci. 2021, 11, 18. [Google Scholar] [CrossRef]
  52. Frazzon, E.; Israel, E.; Albrecht, A.; Pereira, C.; Hellingrath, B. Spare parts supply chains operational planning using technical condition information from intelligent maintenance systems. Ann. Rev. Control 2014, 38, 147–154. [Google Scholar] [CrossRef]
  53. Haarman, M.; Delahay, G. VDM XL, Value Driven Maintenance & Asset Management; Managing Aging Plants: Dordrecht, The Netherlands, 2015. [Google Scholar]
  54. Moubray, J. Reliability-Centered Maintenance; Industrial Press: New York, NY, USA, 1997; 448p, ISBN 978-08-31131-46-3. [Google Scholar]
  55. Psarommatis, F.; Gökan, M.; Azamfirei, V. Envisioning maintenance 5.0: Insights from a systematic literature review of Industry 4.0 and a proposed framework. J. Manuf. Syst. 2023, 68, 376–399. [Google Scholar] [CrossRef]
  56. Psarommatis, F.; Sousa, J.; Medonca, J.P.; Kiritsis, D. Zero-defect manufacturing the approach for higher manufacturing sustainability in the era of industry 4.0: A position paper. Int. J. Prod. Res. 2022, 60, 73–91. [Google Scholar] [CrossRef]
  57. Pinciroli, L.; Baraldi, P.; Zio, E. Maintenance optimization in industry 4.0. Reliab. Eng. Syst. Saf. 2023, 234, 109204. [Google Scholar] [CrossRef]
  58. Raja, H.A.; Kudelina, K.; Asad, B.; Vaimann, T.; Kallaste, A.; Rassölkin, A.; Khang, H.V. Signal Spectrum-Based Machine Learning Approach for Fault Prediction and Maintenance of Electrical Machines. Energies 2022, 15, 9507. [Google Scholar] [CrossRef]
  59. Silvestri, L.; Forcina, A.; Introna, V.; Santolamazza, A.; Cesarotti, V. Maintenance transformation through Industry 4.0 technologies: A systematic literature review. Comput. Ind. 2020, 123, 103335. [Google Scholar] [CrossRef]
  60. Sirvio, K. Intelligent Systems in Maintenance Planning and Management. In Intelligent Techniques in Engineering Management; Kahraman, C., Çevik Onar, S., Eds.; Intelligent Systems Reference Library: Berlin, Germany, 2015; Volume 87. [Google Scholar]
  61. Stuchlý, V.; Poprocký, R.; Rakyta, M.; Grenčík, J. Navrhovanie Procesov Údržby; Žilinská Univerzita v Žiline: Žilina, Slovakia, 2017; EDIS—Vydavateľské centrum ŽU; 542s; ISBN 978-80-554-1315-0. [Google Scholar]
  62. Teoh, Y.K.; Gill, S.S.; Parlikad, A.K. IoT and Fog-Computing-Based Predictive Maintenance Model for Effective Asset Management in Industry 4.0 Using Machine Learning. IEEE Internet Things J. 2023, 10, 2087–2094. [Google Scholar] [CrossRef]
  63. Tessoni, V.; Amoretti, M. Advanced statistical and machine learning methods for multi-step multivariate time series forecasting in predictive maintenance. Procedia Comput. Sci. 2022, 200, 748–757. [Google Scholar] [CrossRef]
  64. Firdaus, N.; Ab-Samat, H.; Prasetyo, B.T. Maintenance strategies and energy efficiency: A review. J. Qual. Maint. Eng. 2023, 29, 640–665. [Google Scholar] [CrossRef]
  65. Hichri, B.; Driate, A.; Borghesi, A.; Giovannini, F. Predictive Maintenance Based on Machine Learning Model. In Artificial Intelligence Applications and Innovations; Maglogiannis, I., Iliadis, L., Macintyre, J., Cortez, P., Eds.; AIAI 2022; IFIP Advances in Information and Communication Technology; Springer: Cham, Switzerland, 2022; Volume 647. [Google Scholar] [CrossRef]
  66. Hivarekar, N.; Jadav, S.; Kuppusamy, V.; Singh, P.; Gupta, C. Preventive and Predictive Maintenance Modeling. In Proceedings of the 2020 Annual Reliability and Maintainability Symposium (RAMS), Palm Springs, CA, USA, 27–30 January 2020; pp. 1–6. [Google Scholar] [CrossRef]
  67. Rakyta, M.; Bubenik, P.; Binasova, V.; Micieta; Staffenova, K. Advanced Logistics Strategy of a Company to Create Sustainable Development in the Industrial Area. Sustainability 2022, 14, 12659. [Google Scholar] [CrossRef]
  68. Stofkova, J.; Krejnus, M.; Stofkova, K.R.; Malega, P.; Binasova, V. Use of the analytic hierarchy process and selected methods in the managerial decision-making process in the context of sustainable development. Sustainability 2022, 14, 11546. [Google Scholar] [CrossRef]
  69. Bubenik, P.; Capek, J.; Rakyta, M.; Binasova, V.; Staffenova, K. Impact of strategy change on business process management. Sustainability 2022, 14, 11112. [Google Scholar] [CrossRef]
  70. Dodok, T.; Cubonova, N.; Cisar, M.; Ivanov, V. Automatic Generation of the Machining Processes for Turned Components in CAD/CAM System. In Advances in Manufacturing Engineering and Materials II: Proceedings of the International Conference on Manufacturing Engineering and Materials (ICMEM 2020), 21–25 June 2021, Novy Smokovec, Slovakia; Springer International Publishing: Berlin/Heidelberg, Germany, 2021; pp. 404–410. [Google Scholar]
  71. Kuric, I.; Klackova, I.; Domnina, K.; Stenchlak, V.; Saga, M. Implementation of predictive models in industrial machines with proposed automatic adaptation algorithm. Appl. Sci. 2022, 12, 1853. [Google Scholar] [CrossRef]
  72. Sun, Z.; Guo, Y.; Sun, Z.; Yang, S.; Hao, B. Maintenance cost prediction for the vehicle based on maintenance data. Proc. Inst. Mech. Eng. Part D J. Automob. Eng. 2023, 238, 1550–1556. [Google Scholar] [CrossRef]
  73. Zonta, T.; Da Costa, C.A.; Righi, R.D.R.; De Lima, M.J.; Da Rindade, E.S.; Li, G.P. Predictive maintenance in the Industry 4.0: A systematic literature review. Comput. Ind. Eng. 2020, 150, 106889. [Google Scholar] [CrossRef]
  74. VEGA Project no. 1/0480/03: Draft Methodology for the Assessment and Correction of Risks Caused by Equipment Failure in Production. The Ministry of Education, Research, Development and Youth of the Slovak Republic. Responsible investigator: doc. Ing. Miroslav Rakyta, PhD. Project. 2003.
  75. VEGA Project no. 1/2065/05: A Model for Rapid Diagnostics and Increasing the Partial and Total Availability of the Production System Using Elements of Virtual Reality and Simulation. The Ministry of Education, Research, Development and Youth of the Slovak Republic. Responsible Investigator: doc. Ing. Miroslav Rakyta, PhD. Project. 2005.
  76. KEGA Project no. 3-1163-03: Visualization Models for the Group of Subjects Design of Production Processes and Systems, Operational Management with a Connection to the Economic Management of Production Processes and Systems. The Slovak Research and Development Agency doc. Ing. Miroslav Rakyta, PhD. Project. 2003.
  77. VEGA 1/0524/22: Research of a Proactive Approach to the Sustainability of Production Systems in Crisis Conditions in the Context of the Green Economy. The Ministry of Education, Research, Development and Youth of the Slovak Republic. Responsible Investigator: Ing. Vladimira Binasova, PhD. Project. 2022.
  78. VEGA 1/0633/2024: Research and Support of the Synergistic Effect of Optimization of Assembly Processes. The Ministry of Education, Research, Development and Youth of the Slovak Republic. Responsible Investigator: prof. Ing. Branislav Mičieta, PhD. Project. 2024.
  79. APVV-19-0305: Integrated Modular System of a Factory Twin. The Slovak Research and Development Agency. Responsible Investigator: prof. Ing. Branislav Mičieta, PhD. Project. 2019.
Figure 1. Overview of maintenance.
Figure 1. Overview of maintenance.
Electronics 13 03449 g001
Figure 2. Connection between maintenance and profitability.
Figure 2. Connection between maintenance and profitability.
Electronics 13 03449 g002
Figure 3. Algorithm for creating a maintenance strategy and concept.
Figure 3. Algorithm for creating a maintenance strategy and concept.
Electronics 13 03449 g003
Figure 4. Internal audit.
Figure 4. Internal audit.
Electronics 13 03449 g004
Figure 5. Daily snapshot of a Measurement and Regulatory Technology (MART) maintenance worker.
Figure 5. Daily snapshot of a Measurement and Regulatory Technology (MART) maintenance worker.
Electronics 13 03449 g005
Figure 6. Daily snapshot of a shift maintenance worker.
Figure 6. Daily snapshot of a shift maintenance worker.
Electronics 13 03449 g006
Figure 7. Maintenance strategy change algorithm.
Figure 7. Maintenance strategy change algorithm.
Electronics 13 03449 g007
Figure 8. RACI matrix.
Figure 8. RACI matrix.
Electronics 13 03449 g008
Figure 9. Maintenance strategy change plan.
Figure 9. Maintenance strategy change plan.
Electronics 13 03449 g009
Figure 10. Graph OEE.
Figure 10. Graph OEE.
Electronics 13 03449 g010
Figure 11. The impact of a change in maintenance strategy on the production quality of a production system.
Figure 11. The impact of a change in maintenance strategy on the production quality of a production system.
Electronics 13 03449 g011
Figure 12. Parameter determination algorithm for SP inventory management.
Figure 12. Parameter determination algorithm for SP inventory management.
Electronics 13 03449 g012
Figure 13. Proposed spare parts criticality matrix.
Figure 13. Proposed spare parts criticality matrix.
Electronics 13 03449 g013
Figure 14. Comparison of inventory values.
Figure 14. Comparison of inventory values.
Electronics 13 03449 g014
Figure 15. Procedure for reducing maintenance capacity.
Figure 15. Procedure for reducing maintenance capacity.
Electronics 13 03449 g015
Figure 16. Reduction in maintenance capacities by profession.
Figure 16. Reduction in maintenance capacities by profession.
Electronics 13 03449 g016
Table 1. External benchmarking [51].
Table 1. External benchmarking [51].
IndicatorNordic Benchmarking AnalysisWorld Class
Overall equipment efficiency (OEE)76.4>90%
Actual running time as % of planned running time (emergency)88.1>90–95%
Maintenance costs as % of company turnover4.1<3
Maintenance costs as % of the replacement value of fixed assets3.0<1.8%
Inventory of spare parts and materials as % of man-hours for maintenance0.8<0.25%
Man-hours for preventive maintenance as % of man-hours for maintenance38.440%
Maintenance man-hours after failure as % of maintenance man-hours29.85%
Man-hours planned and scheduled as % of man-hours for maintenance63.0>90–95%
Table 2. KPI indicators for management (BSC maintenance).
Table 2. KPI indicators for management (BSC maintenance).
Maintenance Balance Score CardPlant Operation ReviewEngineering TiresPlant Engineering ManagerMaintenance ManagerMaintenance Area Leader
EffectivenessCompressed air consumption Machine Group average (Nm3/ton) per monthPlant total (Nm3/ton) per monthArea total (Nm3/ton) per monthMachine Group average (Nm3/ton) per day
Overtime maintenance staff (var+fix) Plant status (%) each monthArea status (%) each monthShift status (%) each day
Mean Time Between Failure (MTBF)Plant average (h) per month for all machineriesMachine Group Average (h) per monthPlant average (h) per month for all machineriesMachine Group Average (h) per monthMachine Group Average (h) per month
Mean Time To Repair (MTTR)Plant average (h) per month for all machineriesMachine Group Average (h) per monthPlant average (h) per month for all machineriesMachine Group Average (h) per monthMachine Group Average (h) per month
Long Time Breakdown (LTB) “A machine” total (LTB) per month“A machine” total (LTB) per month“A machine” total (LTB) per day
Average Waiting Time for Craftsman Area Total (h) per monthArea Total (h) per month
Maintenance Maturity RatioPlant average (%) per month for all machineriesMachine Group average (%) per monthPlant average (%) per month for all machineriesMachine Group average (%) per monthMachine Gropu average (%) per mount
Manhour costPlant Total (Local currency & €) per monthMachine Group average (€ per StdT) per yearPlant Total (Local currency & €) per monthArea Total (Local currency) per monthMachine Gropu average (Hours) per day
Spare parts costPlant Total (Local currency & €) per monthMachine Group average (€ per StdT) per yearPlant Total (Local currency & €) per monthArea Total (Local currency) per monthMachine Group Average (Local currency) per day
Externam services costPlant Total (Local currency & €) per monthMachine Group average (€ per StdT) per yearPlant Total (Local currency & €) per monthArea Total (Local currency) per monthMachine Group Average (Local currency) per day
Major Repair Machine Group average (€ per StdT) per yearPlant Total (Localcurrency & €) per monthArea Total (Local currency) per monthMachine Group Average (Local currency) per month
Non Productive Material stock value Machine Group Status (€) each yearPlant status (Localcurrency & €) each monthArea status (Local currency) per monthMachine Gropu Status (€) each month
ProcessMachine Tolerance Check (MTC) Fulfillment Machine Group Status (€) each monthArea Status (%) each monthArea Status (%) each monthMachine Gropu Status (€) each month
Planned Maintenance Fulfillment (excluding MTC) Machine Group Status (€) each monthArea Status (%) each monthArea Status (%) each monthMachine Gropu Status (€) each month
Training & development measures fulfillment Plant Status (%) each monthArea Status (%) each monthShift Status (%) each month
Indirect InfluenceTEEP/OEE Machine Group Status TEEP (%) each month“A machine” TEEP average (%) per month“A machine” OEE average (%) per month“A machine” OEE average (%) per day
Accident Rate (Plant) Plant Status (Accident/1mio. Hours) per monthArea Status (Accident/1mio. Hours) per monthShift Status (Accident/1mio. Hours) per month
Internal SuppliersMachine availability rate for Planned Maintenance Area Status (%) each monthArea Status (%) each monthMachine Gropu Status (%) each month
Critical Spare parts availability rate Plant Status (%) each mountPlant Status (%) each mountArea Status (%) each month
Table 3. Comparison of discarded materials after the introduction of the new PPM.
Table 3. Comparison of discarded materials after the introduction of the new PPM.
Discarded Material before Failure
Original state (%)Status (%)Improvement (%)
29.8422.7523.76
Table 4. Comparison of the number of rejected semi-finished products.
Table 4. Comparison of the number of rejected semi-finished products.
The Number of Rejected Semi-Finished Products
A Type of EliminationOriginal State (%)Status (%)Improvement (%)
As a result of machinery and equipment80461923.01%
All the reasons5821488716.05%
Table 5. Table of economic evaluation of proposals.
Table 5. Table of economic evaluation of proposals.
Economic Evaluation of Design Solutions
IndicatorExpected Improvement (%)Expected Savings (€)Average (€)
Min.Max.
Scrap I4–7%14,566.39 €25,491.19 €20,028.79 €
WOT13–17%14,244.82 €18,627.84 €16,436.33 €
Downtime/disruptions10–15%921.32 €1381.99 €1151.66 €
Cost 1100.00 €1100.00 €1100.00 €
Monthly saving28,632.53 €44,401.01 €36,516.77 €
Annual saving343,590.40 €532,812.14 €438,201.27 €
Table 6. Criteria for determining the overall criticality of SP.
Table 6. Criteria for determining the overall criticality of SP.
CategoryDescription
AA spare part without which a machine cannot function, with a high failure rate, with a long procurement time, without replacement, used in critical machines.
BA spare part without which the machine can run (at least suboptimal), which has high reliability, which can be manufactured/purchased/repaired in a short time, and which has a replacement.
CConsumables, wear parts (filters, bits, belts).
XObsolete or never used spare parts.
Table 7. Comparison of the current situation with the new situation.
Table 7. Comparison of the current situation with the new situation.
Original Values New Values
Total value of stock items in €62,258.70 €38,684.78 €
Total number of stock items31,4016998
Table 8. Reduction in maintenance capacities during the strategy plan change.
Table 8. Reduction in maintenance capacities during the strategy plan change.
ProfessionCurrent StatusM1 (PW 1–8)M2 (PW 9–16)M3 (PW 17–24)M4 (PW 25–32)M5 (PW 33–40)Pre-Post Period
Planner3332221
MaRT daily1518141414132
MaRT shift12888884
Daily locksmith2724232318198
Shift locksmith1212128848
Electrician7766661
Cleaner1111110
Total77736762575324
Table 9. Description of emergency strategy.
Table 9. Description of emergency strategy.
DescriptionApprovesFrequencyDocument
1. Risk factors influencing the emergency maintenance strategy are defined for lines, machines and equipment, maintenance processes.MC/MM1 × a yearList of risk factors, processes.
2. Elaboration of a matrix of responsibility and authority in the event of a maintenance emergency.MM1 × a yearMatrix of responsibilities for handling a maintenance emergency.
3. Elaboration of the categorization of critical lines of machines and equipment in lines (A, B, C).MT/MM1 × a yearList of machines by priority.
4. Declaring the maintenance system for individual categories of machines.MC/MM1 × a yearMaintenance concept for machines and equipment.
5. For critical machines of category A, development of a flow chart of duties and responsibilities for emergency removal.MC/MM1 × a yearContinuous process diagram of the realization of the created emergency state.
6. On category A machinery and equipment, development of a list of critical structural units.MT/MM1 × a yearList of critical structural units.
7. Develop a list of risky spare parts for category A machines and critical structural units.MT/MM1 × a yearList of critical spare parts.
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Rakyta, M.; Bubenik, P.; Binasova, V.; Gabajova, G.; Staffenova, K. The Change in Maintenance Strategy on the Efficiency and Quality of the Production System. Electronics 2024, 13, 3449. https://doi.org/10.3390/electronics13173449

AMA Style

Rakyta M, Bubenik P, Binasova V, Gabajova G, Staffenova K. The Change in Maintenance Strategy on the Efficiency and Quality of the Production System. Electronics. 2024; 13(17):3449. https://doi.org/10.3390/electronics13173449

Chicago/Turabian Style

Rakyta, Miroslav, Peter Bubenik, Vladimira Binasova, Gabriela Gabajova, and Katarina Staffenova. 2024. "The Change in Maintenance Strategy on the Efficiency and Quality of the Production System" Electronics 13, no. 17: 3449. https://doi.org/10.3390/electronics13173449

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop