Our model is applied to a real gold underground mine. For confidentiality, we have omitted the identity of the mining company. The ore is processed, but not refined for commercialization. The products commercialized are gravimetric and flotation concentrates. In the case study, the stockpiles are not considered, so all mined material is processed.
To compare the results of the deterministic and probabilistic models, we apply both to the real case.
3.1. Deterministic Model
The deterministic problem is based on the model currently employed by a real underground gold mine. It does not consider uncertainty for the calculation of the CoG, which is assumed to be constant. Also, this model considers a known tonnage-grade curve and fixed extraction and processing capacities. For these reasons, income is constant throughout the mining project except for the mine closure year for obvious reasons.
The original data were modified by a white noise for confidentiality reasons. The variables and parameters for the deterministic case are summarized in
Table 1.
The static CoG was calculated by Equation (6). As was mentioned, the constant CoG and the corresponding constant average grade of 4.4 (g/t) along the entire time horizon implies a very inflexible policy that ignores the geological and the operational uncertainties. Note that the CoG is linear on the mining, processing, and overhead per tonne. It means that the CoG increases linearly as costs increase, and it implies that for increasing costs, the metal mined requires higher ore grades to keep the business profitable.
The results of the deterministic model are summarized in
Table 2, indicating that the optimal CoG is
, LoM is 7 years, the cash flow is USD 112,335,120, and the NPV is USD 36,043,086.
In
Table 3, the results are detailed through a simplified cash flow statement. As the CoG, the rock mined is constant along the LoM, except during the last year when production decreases before mine closure. Consequently, processed material, mining costs, processing costs, OPEX, and free cash flow are constant along the first six years. The total overhead per ton is constant, as well as the total overhead during the first six years. By the seventh year, the remaining reserves are totally depleted, and for that reason the processed material, costs, and revenues diminish.
Summarizing the results of
Table 3, we can say that for the first six years, the annual results are as follows: the total rock extracted, as well as processed rock, are 328,500 tonnes, the mining cost is USD 14,848,200, the processing cost is USD 3,285,000, the overhead is USD 9,000,900, OPEX is USD 27,134,100, and the free cash flow is USD 31,965,463. In the seventh year, the results are as follows: the total rock extracted, as well as processed rock, are 90,110 tonnes, the mining cost is USD 4,072,962, the processing cost is USD 901,098, the overhead is USD 2,469,008, OPEX is USD 7,443,068 and the free cash flow is USD 8,768,344. Note that the overhead diminishes in the last year because the production diminishes as well, and we assume for the deterministic model a constant overhead of expenses per tonne
(USD/t).
Therefore, the results show us a rigid and non-robust scheduling of the mining operation, which is incompatible with the changing conditions due to geological, operational, and financial uncertainties.
3.2. Probabilistic Model
In order to apply GA, we select an initial population of individuals
for the variables
,
,
for
and
to start the optimization. The values are shown in
Table 4.
The optimization with Monte Carlo simulations was carried out using the @Risk Palisade 2015 software as follows: first, we fix a population of individuals
and many scenarios are generated according to a specific probability distribution. The NPV is maximized for each scenario, solving the problems (1)–(5) for the generated scenarios. The solving of each optimization problem is called iteration. After that, we calculate the average NPV, completing a trial which can be valid if all restrictions are met or not valid if contrary. If the trial result meets the stopping criteria, which could be a limited number of tests or a convergence criterion, the optimization ends; otherwise, a new population is proposed and a new trial is performed [
25].
The tonnage-grade curves were estimated by the conditional simulation process to obtain tonnage-grade curves, and the model includes five curves, each of which corresponds to the average of 25 conditional simulations in which the capping value was modified as an estimation parameter, establishing for each curve a capping value of 30, 40, 50, 60 and 70 g/t, respectively. The estimation process was carried out by the mining company, taking into account the confidentiality of the data. In that way, the five tonnage-grade curves were obtained (
Figure 3). These five scenarios were used to generate thousands of geological scenarios by combining them through a discrete uniform distribution. This allows for combining optimistic and non-optimistic scenarios, treating them as equally probable. Mathematically, let
be a CoG,
be a tonnage-grade curve,
be the corresponding tonnage and
be the corresponding average grade. Then, the scenarios of the tonnage-grade curve at cutoff
are generated as realizations of the random variables, as follows:
and
and a particular
realization of these variables is denoted by
and
, respectively.
After many operations of selection, crossover, and mutation, the algorithm implemented in @Risk converged to the solution summarized in
Table 5. The number of iterations per trial, the trials, and the valid trials are shown in
Table 5. To determine the convergence of the algorithm, we implemented the stopping criteria (SC). The convergence of the probabilistic optimization is depicted in
Figure 4.
The NPV distributions for the initial and the optimized values are shown in
Figure 5.
Comparing the deterministic results and the probabilistic ones, we note an improvement on the cash flow and the NPV. Indeed, the average NPV of the probabilistic model increases USD 21,142,372 compared to the deterministic NPV. Furthermore, the probabilistic model generates a dynamic CoG and a material processing around 438,000 tonnes per year the first four years, decreasing to 364,299 tonnes the fifth year and increasing to 438,000 tonnes the sixth year, as the end of LoM is approaching. Instead, the deterministic case considers a constant CoG and a material processing value of 328,000 tonnes per year the first six years, and decreases to 90,110 tonnes the seventh year. The comparison between the results of production is shown in
Figure 6. The high costs required to maintain equipment in operation suggest that the optimal solution is to utilize machinery, such as the mill, at its maximum capacity. Thus, the optimal solution tends involve maintaining a constant level of production. Generally, the production falls during the last years of operations, and the mineral reserves are depleted. However, the solution obtained indicates that it is more convenient to anticipate the decline in production to the fifth year. To maintain a mostly constant production, it would be necessary to modify the cutoff grade, which explains the fluctuation of the cutoff grade during the Life of Mine.
The variation coefficient for the probabilistic NPV is 10.36%, which indicates that the risk is moderate, considering that mining projects are highly risky. Instead, the deterministic NPV has no associated uncertainty and it can not capture the inherent risk of the mining business.
As for costs, the mining costs per tonne are the same for the deterministic and probabilistic cases, but the total mining costs vary, detailed as follows: the probabilistic case gives us higher mining costs than the deterministic case, because at the probabilistic setting more rock is extracted than in the deterministic one. Taking into account that all the rock extracted is processed by assumption, we analogously conclude that the processing costs are higher for the probabilistic model. Instead, the total overhead is fixed in both cases to 9,000,900 dollars, but the overhead per tonne is 27.4 (USD/t) for the deterministic model, 20.6 (USD/t) at years 1, 2, 3, 4, 6, and is 24.7 (USD/t) at year 5 for the probabilistic approach, which reveals a lower overhead for the probabilistic instance than the deterministic one. The efficiency in relation to the overhead is higher for the probabilistic model, because with the same resources the company produces more at the probabilistic setting than in the deterministic one. This efficiency is reflected in the OPEX, as follows: indeed, for these expenses, the probabilistic results show more efficiency than the deterministic ones, as can be seen in
Table 3 and
Table 6. Further, the overhead per tonne impacts the CoG, which follows from Equation (6). Thus, the probabilistic solution shows an increase in production compared to the deterministic results with the same overhead, which implies a lower overhead per tonne and, consequently, a lower CoG in the probabilistic case.
Finally, on the one hand, for the probabilistic model, the obtained LoM was 6 years and the CAPEX was USD 83,226,000. On the other hand, the LoM for the deterministic model was 7 years and the CAPEX was USD 88,226,000. Hence, LoM and CAPEX decrease when uncertainty is considered, and it could make the project more attractive for investors and creditors because the profit is expected to be earned in less time, diminishing the opportunity cost and the initial investment, thereby easing the project initiation phase.
In summary, either the CoG, the process capacity, or the LoM show that the probabilistic model provides better financial results than the deterministic one. The results of the probabilistic model are summarized in
Table 6. These results were calculated using the last sampling, corresponding to the last iteration of the last valid trial performed by @Risk.
We conclude that the results reveal the relevance of the decision variables of our model, because they vary significantly when uncertainty is considered, producing an increase in the NPV.
3.3. Sensitive Analysis
The reviewed literature considers various variables and uncertainties associated with the optimization of cutoff grades. In the case of gold deposits, geological and economic uncertainties are commonly identified as the key variables in stochastic models. Unlike the models consulted, economic uncertainty related to gold prices was not factored in, despite the constant macroeconomic and geopolitical changes worldwide that frequently impact forecast confidence intervals in commonly used time series.
Regarding operating costs, the proposed model treats mining and processing costs as variable, meaning they fluctuate according to the set processing capacity. Meanwhile, general costs are treated as fixed in the free cash flow structure, meaning they do not vary with the volume of processed tons. This aspect of the model has the two following objectives: first, to assess the impact of fixed costs on total operating costs by altering the plant’s processing capacity without changing general costs, i.e., maintaining the same personnel and direct support areas, main activities, general and administrative (G&A) costs, and sustainability expenses; second, to evaluate the change in cutoff grade when adjusting the processing capacity while keeping the general cost component fixed.
A sensitivity analysis is presented below, with variables including mineral prices and operating costs, considering the historical price of gold over the past 10 years and the company’s historical operating costs (
Figure 7):
This sensitivity analysis reveals that a gold price below USD 1200/oz leads to a negative NPV, indicating the project is unprofitable and financially unfeasible. Conversely, a price above USD 1800/oz yields a positive NPV, suggesting the investment would be profitable across all cost scenarios analyzed.