5.2. New Design Parameters of Pre-Splitting Blasting
In the engineering practice of NPM, the core technology of the PRPBT is bidirectional energy concentrated pre-splitting blasting technology [
6]. As a kind of pre-splitting blasting technology, this technology can realize the directional transmission of explosive energy along the direction of the shaped tube through the combination of the shaped charge tube and the explosive and then realize the directional fracture of rock mass along the roof cutting direction.
The determined parameters of pre-splitting blasting including charge structure, sealing length and the number of single initiations were mainly determined by field investigation. Existing results have presented that the pre-splitting blasting effect is judged by indirect indexes such as gangue retaining pressure, the periodic weighting length and the loading of a single hydraulic prop near the gangue rib [
28]. The measured result of the indirect index could grasp the roof cutting effect, but it cannot form a systemic design method for the key parameters of pre-splitting blasting. Therefore, the fissure rate along the borehole length is proposed to design the parameters of pre-splitting blasting and assess its effectiveness. The obtained process of the fissure rate can be described as follows: first, the video of roof fracture development along the borehole depth was obtained. Second, the number of the developed fracture zones including lateral fissures, vertical fissures, bedding separations and annular fractures was recorded per meter. Based on the result of the number of developed fracture zones, the lengths of the developed fracture zones were analyzed. Third, the length of the developed fracture zone per meter is called the fissure rate. Hence, the fissure rate is calculated by the observation result, it can be expressed by the following equation:
where
is the crack rate within one meter along the borehole length, %; and
is the crack length within one meter, m.
Based on the successful practice of the PRPBT in many coal mines, this study adopted a dynamic adjustment strategy regarding the single borehole. The strategy was described as follows: (1) A single borehole charge structure (
Figure 12) was determined according to the borehole length. In the meantime, the sealing length was also obtained. (2) Then field tests were conducted according to the design strategy. The borehole peeping equipment was used to view the crack development along the borehole direction. The fissure rate was calculated based on the peeping result of crack development. (3) Based on the fissure rate, the charge structure and the sealing length were adjusted dynamically. The single borehole pre-splitting blasting test was conducted again according to the charge structure until the demand for the fissure rate was met for the PRPBT. The pre-splitting blasting strategies are presented in
Table 7.
In the field test process, an energy-gathering tube with a length of 1.5 m, an outer diameter of 42 mm and an inner diameter of 36.5 mm was adopted. A three-grade emulsion explosive roll with a diameter of 35 mm and a length of 300 mm was used. Explosive rolls were connected by a millisecond delay detonator. After the pre-splitting blasting works of each strategy were finished, the borehole peeping was conducted to observe the fissure development.
The peeping results of each strategy are shown in
Table 8. The analysis of the peeping results along the borehole lengths of 3.0 m, 5.0 m, 7.0 m and 9.0 m was obtained. Regarding the charge structures of 3 + 3 + 3 + 2 + 1 and 3 + 3 + 3 + 3 + 1, in the shallow section within the borehole length of 3.0 m, no fissures developed (
Table 8A,B). This was because the sealing length was 2.7 m and the explosion-induced blasting energies had difficulty acting effectively in this section. At the borehole length of 5.0 m, fissures occurred in the borehole, but there were no bidirectional fissures. At the borehole lengths of 7.0 m and 9.0 m, bidirectional fissures occurred in the borehole. It can be concluded that the bidirectional fissures mainly developed in the deep section of the borehole and the pre-splitting blasting effect was relatively poor in the shallow section. Based on the charge structures of 3 + 3 + 3 + 2 + 1 and 3 + 3 + 3 + 3 + 1, the explosive rolls were added in the deep section, then the charge structure of 4 + 3 + 3 + 2 + 1 was formed. As shown in
Table 8C, no fissures occurred in the sealing section of the borehole; the bidirectional fissures occurred in the sections along the borehole lengths of 5.0 m and 7.0 m. At the borehole length of 9.0 m, fissures occurred in three directions and the rock mass was cracked. Through the analysis of the peeping results for the charge structures of 3 + 3 + 3 + 2 + 1, 3 + 3 + 3 + 3 + 1 and 4 + 3 + 3 + 2 + 1, it can be seen that the pre-splitting blasting is poor in the shallow section of the borehole.
Compared with the charge structures of 3 + 3 + 3 + 2 + 1, 3 + 3 + 3 + 3 + 1 and 4 + 3 + 3 + 2 + 1, to obtain a better pre-splitting blasting effect at the shallow part, the sealing length was decreased to 2.4 m and the explosive rolls were added. The charge structures of 4 + 3 + 3 + 3 + 1, 4 + 3 + 3 + 3 + 2 and 4 + 4 + 3 + 3 + 2 were proposed. As for the charge structure of 4 + 3 + 3 + 3 + 1, the bidirectional fissures developed at the borehole length of 3.0 m and 5.0 m, while the fissures with three directions occurred at the borehole lengths of 7.0 m and 9.0 m. Concerning the charge structures of 4 + 3 + 3 + 3 + 2 and 4 + 4 + 3 + 3 + 2, it can be seen that the bidirectional fissures developed in the whole section of the borehole and a better pre-splitting blasting effect was achieved. As for the charge structure of 4 + 4 + 3 + 3 + 2, the dimensions of the bidirectional fissures were greater than the charge structure of 4 + 3 + 3 + 3 + 2, and the pre-splitting blasting effect was better. It is concluded that the charge structure of 4 + 4 + 3 + 3 + 2 can achieve a better pre-splitting blasting effect than the other charge structures.
To further assess the pre-splitting blasting effect of different charge structures, the fissure rate was also obtained. As shown in
Figure 13, the maximum value of the fissure rate for the charge structures of 3 + 3 + 3 + 2 + 1, 3 + 3 + 3 + 3 + 1 and 4 + 3 + 3 + 2 + 1 were 20%, 23% and 21% when the borehole length was less than 3.0 m, respectively. However, the maximum value of the charge structures of 4 + 3 + 3 + 3 + 1, 4 + 3 + 3 + 3 + 2 and 4 + 4 + 3 + 3 + 2 increased to 86%, 90% and 92%, respectively. The fissure rates of the charge structures of 4 + 3 + 3 + 3 + 1, 4 + 3 + 3 + 3 + 2 and 4 + 4 + 3 + 3 + 2 were greater than the charge structures of 3 + 3 + 3 + 2 + 1, 3 + 3 + 3 + 3 + 1 and 4 + 3 + 3 + 2 + 1. The results of the fissure rate were consistent with the peeping results. Hence, the charge structure was determined as 4 + 4 + 3 + 3 + 2.
5.3. Field Application
According to the results of the new design parameters of the PRPBT, it can be acquired that the roof cutting height was 10.0 m, the roof cutting angle was 15°, the charge structure was 4 + 4 + 3 + 3 + 2 and the sealing length was 2.4 m. Additionally, to meet the requirement of panel 5201 coal production, the daily mining progress should be greater than 4.8 m, namely, the daily pre-splitting blasting progress was 4.8 m/d. Then there were eleven boreholes that needed to be blasted every day. Considering the work arrangement, three boreholes were blasted each time and four blast times were arranged.
To evaluate the performance of the newly designed pre-splitting blasting strategy, comprehensive field observations, including borehole peeping observation and the field measurement of roof suspension, were conducted in the tailgate 5201. The borehole peeping observation was measured using borehole peeping equipment with the mode of CXK12(A). The development of roof suspension was measured by flexible tape and a laser range finder. After the newly designed pre-splitting blasting strategy was implemented, the field observations were conducted within 200 m behind the goaf. The observation results regarding the fissures’ development are presented in
Figure 14. As shown in
Figure 15, the bidirectional fissures developed in the blasting borehole.
Based on investigating the peeping results of pre-splitting blasting, the roof suspension in the goaf was also investigated on site and the measured range was within 200 m behind the goaf. There are only three roof suspensions, and the maximum value of the roof suspension was only 3.2 m
2, which was about 0.1 times the average value before using the newly designed strategy. After adopting the newly designed strategy, the hard main roof collapsed fully in the goaf, as shown in
Figure 15. It can be seen that the newly designed strategy achieves a better pre-splitting blasting effect and can also significantly reduce the roof suspension in the goaf. Notably, this study is based on the specific condition of Dadougou coal mine; the results can provide technical reference and theoretical guidance for other coal mines with similar conditions.