Next Article in Journal
Mathematical Modelling to Predict the Best Inclination Angle for Maximum Distillate Output of A Solar Still
Previous Article in Journal
Cellulose Triacetate/Zinc Oxide Membrane for Bioethanol Recovery via Pervaporation
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Proceeding Paper

Case Study: Rapid Seismic Assessment of Existing Hospitals in Karachi †

by
Aslam Faqeer Mohammad
1,*,
Rashid A. Khan
2,
Muhammad Afnan Siddiqui
2 and
Muhammad Hammad
2
1
Civil Engineering Department, NED University of Engineering & Technology, Karachi 75270, Pakistan
2
Earthquake Engineering Department, NED University of Engineering & Technology, Karachi 75270, Pakistan
*
Author to whom correspondence should be addressed.
Presented at the 12th International Civil Engineering Conference (ICEC-2022), Karachi, Pakistan, 13–14 May 2022.
Eng. Proc. 2022, 22(1), 8; https://doi.org/10.3390/engproc2022022008
Published: 23 September 2022
(This article belongs to the Proceedings of The 12th International Civil Engineering Conference)

Abstract

:
Hospitals are considered to be safe havens as they have to remain functional during an earthquake or any other natural calamity. However, in past, the performance of the hospitals in high seismic regions is seen to be poor, raising the intensity of life lost in such calamities. To prevent disruption in functionality or any damage to the infrastructure of the hospital, it is mandatory to perform pre and post-earthquake assessments and evaluate the integrity of structural as well as functional aspects of the hospital. This research paper outlines a modified Rapid Visual Screening (RVS) procedure with FE analytical method similar to ASCE41-17. The developed procedure is a three-tier process that is tested on three major hospital buildings in the city of Karachi, a metropolitan city known as the financial hub of Pakistan. The developed procedure begins with the RVS process that considers the structural elements and their vulnerability either at full structure or at the element level. This process then further combines with the evaluation of Demand-Capacity Ratios (DCR) for the entire structure to obtain a physical model with the vulnerabilities that need further non-linear evaluation or physical interventions are developed.

1. Introduction

It is widely accepted that hospitals and other health facilities should be prepared to deal with any crisis as masses tend to rush to these facilities in wake of disasters. Generally, this is true, but some events in the past have demonstrated that the behavior of hospital buildings is like any other and is subject to damage and collapse, in such a case a hospital would not be able to function in a most critical situation. Hospitals have been observed to have performed poorly in wake of earthquakes as accounted by Jain et al. [1]. Similarly, During the devastating earthquake dated 8 October 2005 shocked Pakistan’s Northern area with a magnitude of Mw = 7.6 in the early morning, affecting an area of approximately 30,000 km2. The destruction that was observed in an aftermath of the Earthquake was extensive [2]
According to the EERI reconnaissance report around 574 medical facilities were either affected partially or fully put out of commission which constitutes 70% of facilities in the area [2]. Among the hospitals affected were hospitals Combined Military Hospital (CMH) Muzaffarabad which completely collapsed shown in Figure 1 and another hospital Ayub Medical College in Abbottabad which was evaluated incorrectly, nonstructural damage was categorized as structural damage, and patients were put in the front yard. This disrupted the operations of the hospitals significantly in a critical situation this was caused due to the fact there was no post-seismic evaluation technique present at the time [3].
Karachi plays a significant role in Pakistan’s economy, as it constitutes around 20% of Pakistan’s economy and industrial sector contributions are around 30% of the whole of Pakistan. 95% of Pakistan’s international trade is handled by the two ports located in Karachi i.e., Karachi Port and Port Qasim [4].
Karachi is located Southwest of Pakistan and is vulnerable to both Earthquakes and tsunamis. Bilham et al. have presented the historical data of the earthquakes as well as a potential overview of earthquake sources near Karachi. Bilham et al. indicated that there are four major faults near Karachi and several destructive Earthquakes and tsunamis have occurred in the past. Despite that, a more troubling conclusion was made by Bilham et al. that Karachi’s seismic hazard is much like Los Angles, in addition to that the only difference that makes conditions even extreme is the proximity to the subduction zones which are not present in Los Angeles [5].
When it comes to providing healthcare there is a shortage of health facilities for the rapidly increasing population of Karachi. Currently, there are only 33 hospitals, 271 health centers, and 152 dispensaries. It is estimated to be around 15,000 beds, among which 9000 are tertiary and teaching hospitals apart from those around 6000 are present in secondary and primary care facilities. If we calculate the ratio of beds to people it comes out to be 1 to 1700 in the tertiary category of health facilities and 1 to 1020 for all other public health facilities. Apart from the public sector, it can be estimated that there are 6600 beds in the private sector distributed over a total of 356 large and small hospitals [6].
Based on the above sentiments, the current state of the health care system located in Karachi is already deficient; therefore, it becomes imperative to conduct the Rapid Seismic Assessment of hospitals in the Karachi region. Otherwise, if not taken into account it could have disastrous outcome if the health care system collapse during a strong event of an earthquake. This study particularly focuses on the structural assessment of health care facilities. Identification of structural irregularity such as plan, vertical, torsional, etc shown in Figure 2.

2. Methodology

The seismic evaluation of hospitals is an extensive process as compared to other buildings as a building may be of the same dimension as a hospital but the number of components in a hospital is very intricate as compared to residential or commercial facilities. Therefore, hospitals need to be accessed accordingly. Furthermore, the hospital must remain in a functional state structurally as well as based on functionality. The components that are not structural are termed as non-structural components and play an equivalent role. These non-structural components are great hazards inside and in the surrounding of the facility as falling objects and equipment can cause injuries, deaths, functional hindrance, and economic loss for the health facility. In various cases, hospitals have been not able to function properly even after a week of the event.
Various methods exist to assess medical facilities but they differ from one another in the expense, precision, and level of complexity that is observed in performing the assessment. The proven techniques are ASCE 41 [7], FEMA P-154 [9], ATC-40 [10], WHO [11], and PAHO [12], which not only provide the desired earthquake resistance but also reduce the cost incurred in terms of life and monetary factors following an Earthquake. The seismic assessment is performed in a systematic procedure the structure is assessed in four stages. The four stages in the assessment are presented in Figure 3.
This study is limited to Tier 1 and Tier 2 phases. A modified approach to the tier-1 RVS procedure was applied to the structures. The procedure was made incorporating ASCE-41 [7], FEMA-154 [9], ATC-40 [10], WHO [11], WHO/EURO [13], and Nepal Guidelines [14] and was then modified for Pakistan.

3. Case Study Buildings

3.1. General Features

The general features of the three selected hospital buildings presented in this study are given below in Table 1. The structural systems of buildings 1 and 2 are concrete framed systems consisting of concrete slabs, beams, columns, shear walls, and foundation, while the third building consists of a concrete flat slab with edge beams supported by RC shear walls and columns. The raft-type foundation is provided as a foundation for all the structures.

3.2. Material Properties

The design compressive strengths for the buildings selected are presented below in Table 2. The strengths of building 2 and 3 are based on actual data. While the strengths of building 3 are taken as general construction practice. The yield strength of the steel rebar is 60 ksi for all the buildings.

3.3. Site and Hazard Information

All the buildings are located in Karachi, having dense soil or soft rock. The site class “D” is selected for all three buildings from the VS30 map [15]. The seismic assessments of the buildings are carried out considering the buildings are found to be in the moderate seismic zone (zone 2B for Karachi as mentioned in the seismic zoning map of Pakistan for Karachi). Soil type Sd (stiff soil) is used and seismic coefficients were taken as Ca = 0.24 and Cv = 0.32 from UBC-97 [16].

3.4. Loading and Performance Criteria

The dead load of the buildings consists of the self-weight including 3in thick finishes as well as an additional load for the infill masonry which was taken as 36 psf superimposed dead load and any other superimposed load according to the architectural plans. Live load is taken as 100 psf for the buildings. The buildings are evaluated as a concrete moment frame. Considering the occupancy use of the building, the seismic assessment exercise performed for the immediate occupancy (IO) performance level as one of the limit states reported in ASCE-41 [7] corresponding to a 475 years recurrence interval of an earthquake.

3.5. Tier-1 Analysis

The buildings that were assessed for the tier-01 analysis using the ASCE 41-17 [7]. Various parameters modified for Pakistan’s condition are also incorporated in the tier-01 analysis. The assessment performed indicates several non-compliant items found in the structures in the Tier-01 category.
Table 3 and Table 4 show various results of the Tier 1 analysis that are non-compliant, which would further be investigated. The visual inspection suggests that there is a significant chance of damage occurring in building 1 as the number of irregularities found non-complaint is more than the buildings 2 and 3.

3.6. Tier-2 Analysis

The structural system of the buildings comprises of reinforced concrete moment frame. Further investigation is required to ascertain that the buildings are safe. To do so, Tier-2 is performed for immediate occupancy level incorporating moderate to high seismicity [7]. The FEA models of the buildings are developed using a commercially viable computation tool named CSI ETABS. The plan and 3-D view of the models are shown in Figure 4.
Torsional irregularity found in non-compliant in Tier-1 is further evaluated in Tier-2. The maximum to average displacement ratio check was deployed to assess the structure in both principal directions X and Y. The maximum to average displacement ratio should be less than 1.2 for compliancy. Building-03 passes the torsional irregularity check, however, building-01 and 02 were found deficient in the torsional irregularity check after tier-02 analysis. Building-01 fails by 16% while building-02 exceeds the limit by a margin of more than 25%.
Multiple soft stories are being developed in both X and Y principal directions in all three structures. This was determined by comparing the stiffness of consecutive stories. The difference in stiffness between two adjacent stories should be less than 30% for compliance. There are severe soft-story occurring in the structure as the difference of stiffness in the stories in which this irregularity is occurring are up to 82%, 60%, and 65% simultaneously in building-01, 02, and 03.
The percentage difference of the masses between two adjacent floors should be within 50%. The structures were found to be compliant as an outcome of this irregularity check. All the structures passed this check by a reasonable margin as the difference in mass was observed to be less than 16% in all of the structures.
Building-01 was found to be compliant with the weak-story irregularity while building-02 and 03 were non-compliant. This was evaluated by comparing the shear strength of the structure on each story to adjacent stories. The criteria for compliance is the shear strength of the adjacent story should not be less than 80%. Building-01 passes the check with a higher margin as the difference does not exceed 10%, while building-02 and building-03 fail the check by a margin of 7% and 30%.
The inter-story drift limit for hospital buildings is 1% for immediate occupancy limit state performance level. The three structures considered in this study failed the inter-story drift limit check. Building-01, 02, and 03 exceed the limiting value by the code. If we compare the three buildings building-02 fails to a greater extent than the other two buildings.

4. Conclusions

Hospitals are termed as safe havens in wake of any kind of disaster but hospitals themselves are susceptible to damage particularly in strong seismic events the only possible solution to keep the hospital functional in such an event is to identify the existing deficiencies in the structure and mitigate it. A modified Rapid Visual Screening (RVS) procedure was adopted in this paper catering to the requirement of construction norms of Pakistan and applied to the three hospital buildings located in Karachi. The existing sources of vulnerabilities found in tier-1 were re-evaluated in the tier-2 phase. During the tier-1 evaluation phase, building-01 and building-02 were found more susceptible to damage in an earthquake, building-03 was comparably better than building-01 and 02 because building-03 had no severe plan irregularities. All three buildings were further evaluated in tier-02 and linear finite element models were developed employing a commercially viable software CSI ETABS. The three buildings failed the inter-story drift check, they exceeded the code prescribed value by a large extent. Building-01 showed compliancy in weak-story irregularity by a reasonable extent as the difference in strength was observed up to only 10% while the limit is 20%, on the other hand, building-02 and 03 failed the check by crossing the limit and the difference of strength was observed to be 27% and 52%. All three buildings failed the soft-story check and the difference in stiffness was found to be 82%, 60%, and 65% while the limit was 30%. Mass irregularity showed compliance for all the structures as the difference in mass did not even exceed 16%. Building-01 and 02 failed the torsional irregularity by 16% and 25% crossing the limit, on the contrary building-03 passes the torsional irregularity check because building-03 has a regular plan. The three structures need to be further evaluated in the tier-3 phase and if still found deficient it would be recommended that the building need to be retrofitted.

Author Contributions

Conceptualization, R.A.K. and A.F.M.; methodology, M.A.S. and M.H.; software, M.H.; validation, A.F.M., M.A.S. and R.A.K.; formal analysis, M.A.S., M.H. and A.F.M.; investigation, M.A.S. and A.F.M.; resources, R.A.K.; data curation, M.A.S.; writing—original draft preparation, M.A.S.; writing—review and editing, A.F.M. and R.A.K.; visualization, A.F.M.; supervision, R.A.K.; project administration, R.A.K.; funding acquisition, R.A.K. All authors have read and agreed to the published version of the manuscript.

Funding

The work presented in the paper is a part of the project “Seismic Analysis of Hospitals of Karachi” which is a National Research Project for Universities (NRPU) ID 11357 project sanctioned and funded by Higher Education Council (HEC) Pakistan.

Institutional Review Board Statement

Not applicable.

Informed Consent Statement

Not applicable.

Data Availability Statement

Not applicable.

Acknowledgments

The authors would like to acknowledge Higher Education Commission (HEC) for the provision of the fund that were utilized in the project under the banner of National Research Program for Universities. We hereby acknowledge NED University of Engineering and Technology for the support and, facilitation during the project and Computers and Structures, Inc. for the provision of the licensed version of the Finite Element software.

Conflicts of Interest

The authors have no conflict of interest to declare. All co-authors have seen and agree with the contents of the manuscript and there is no financial interest to report. We certify that the submission is original work and is not under review at any other publication.

References

  1. Jain, S.K.; Lettis, W.R.; Murty, C.V.R.; Bardet, J.-P. Bhuj, India Earthquake of January 26, 2001, Reconnaissance Report. In Earthquake Spectra; Earthquake Engineering Research Institute: Oakland, CA, USA, 2002; Volume 18. [Google Scholar]
  2. Hussain, S.; Khazai, B.; Nisar, A.; Dellow, G. Learning from Earthquakes: The Kashmir Earthquake of October 8 2005: Impacts in Pakistan. In EERI Special Earthquake Report (February 2006); Earthquake Engineering Research Institute: Oakland, CA, USA, 2006. [Google Scholar]
  3. Durrani, A.J.; Elnashai, A.S.; Hashash, Y.M.; Kim, S.J.; Masud, A. The Kashmir Earthquake of October 8, 2005: A Quick Look Report; Mid-America Earthquake Center, University of Illinois at Urbana: Champaign, IL, USA, 2005. [Google Scholar]
  4. Robotka, B. Political Turmoil in a Megacity: The Role of Karachi for the Stability of Pakistan and South Asia. Pakistan Vis. 2013, 14, 1. [Google Scholar]
  5. Bilham, R.; Lodi, S.; Hough, S.; Bukhary, S.; Khan, A.M.; Rafeeqi, S.F.A. Seismic hazard in Karachi, Pakistan: Uncertain past, uncertain future. Seismol. Res. Lett. 2007, 78, 601–613. [Google Scholar] [CrossRef]
  6. Master Plan Group Offices City District Government Karachi; M/s Engineering Consultant International (Pvt.) Limited; M/s PADCO-AECOM. Karachi Strategic Development Plan 2020. Available online: http://shehri.org/2020.pdf (accessed on 22 May 2022).
  7. American Soiciety of Civil Engineers. ASCE Standard, ASCE/SEI, 41-17, Seismic Evaluation and Retrofit of Existing Buildings; American Society of Civil Engineers: Reston, VA, USA, 2017. [Google Scholar] [CrossRef]
  8. Taranath, B.S. Structural Analysis and Design of Tall Buildings: Steel and Composite Construction; CRC Press: New York, NY, USA, 2016. [Google Scholar]
  9. Applied Technology Council. Rapid Visual Screening of Buildings for Potential Seismic Hazards: A Handbook, 3rd ed.; Applied Technology Council: Redwood City, CA, USA, 2015. [Google Scholar]
  10. Comartin, C.; Niewiarowski, R.; Rojahn, C. ATC-40 Seismic Evaluation and Retrofit of Concrete Buildings; Report No. SSC 96-01; Applied Technology Council: Redwood City, CA, USA, 1996. [Google Scholar]
  11. World Health Organization; Pan American Health Organization. Hospital Safety Index: Guide for Evaluators, 2nd ed.; World Health Organization: Copenhagen, Denmark, 2015. [Google Scholar]
  12. Pan American Health Organization. Principles of Disaster Mitigation in Health Facilities; Pan American Health Organization: Washington, DC, USA, 2000. [Google Scholar]
  13. WHO/EURO. Health Facility Seismic Vulnerability Evaluation a Handbook; World Health Organization: Copenhagen, Denmark, 2006. [Google Scholar]
  14. Guragain, R.; Pandey, B.H.; Shrestha, S.N. Guidelines for Seismic Vulnerability Assessment of Hospitals, 1st ed.; National Society for Earthquake Technology-Nepal (NSET): Kathmandu, Nepal, 2004. [Google Scholar]
  15. Lodi, S.; Kumar, M.; Samad, M.; Wasim, A. Predictive Relationship for Estimation of Vs30 Using Shallow Bore Logs for Karachi. Geotech. Geol. Eng. 2015, 33, 559–573. [Google Scholar] [CrossRef]
  16. International Conference of Building Officials. Uniform Building Code, Volume 2; International Conference of Building Officials: Whittier, CA, USA, 1997. [Google Scholar]
Figure 1. Damage to Combined Military Hospital (CMH) in Muzaffarabad (a) Front View (b) Back View [3].
Figure 1. Damage to Combined Military Hospital (CMH) in Muzaffarabad (a) Front View (b) Back View [3].
Engproc 22 00008 g001
Figure 2. Plan and Vertical Irregularities. (a) Torsional Irregularity [7] (b) Re-entrant Corner [7] (c) Soft Story [8].
Figure 2. Plan and Vertical Irregularities. (a) Torsional Irregularity [7] (b) Re-entrant Corner [7] (c) Soft Story [8].
Engproc 22 00008 g002
Figure 3. Seismic Evaluation Procedure.
Figure 3. Seismic Evaluation Procedure.
Engproc 22 00008 g003
Figure 4. Typical Plan and Finite Element Model (a) Building-01 FEM 3-D (b) Building-01 Plan View (c) Building-02 FEM 3-D (d) Building-02 Plan View (e) Building-03 FEM 3-D (f) Building-03 Plan view.
Figure 4. Typical Plan and Finite Element Model (a) Building-01 FEM 3-D (b) Building-01 Plan View (c) Building-02 FEM 3-D (d) Building-02 Plan View (e) Building-03 FEM 3-D (f) Building-03 Plan view.
Engproc 22 00008 g004
Table 1. General Features.
Table 1. General Features.
Building # 1Building # 2Building # 3
Year of Construction202020042019
# of Stories080816
Basement010102
Area4762.95 m21038.19 m23467.85 m2
Typical Story Height4.2672 m3.5676 m4 m
Total Height32.6136 m30.1752 m77.62 m
Table 2. Design Compressive Strength.
Table 2. Design Compressive Strength.
Building # 1Building # 2Building # 3
MPaMPaMPa
Beams25.8522.7527.58
Slabs25.8522.7527.58
Columns 32.57827.5827.58
Shear Walls32.57827.5827.58
Foundation32.57827.5827.58
Table 3. Tier-01 Rapid Visual Screening Horizontal Irregularities.
Table 3. Tier-01 Rapid Visual Screening Horizontal Irregularities.
Horizontal IrregularityBuilding 1Building 2Building 3
Plan IrregularityNCNCC
Re-entrant CornerCNCC
Non-Parallel SystemCCC
Out-of-Plane OffsetNCNCC
Torsion IrregularityNCNCC
Slab Opening (Greater than 50% of Slab)CCC
Presence of CantileverNCCC
Visible Deflection of BeamCCC
Lateral Column DriftNCNCNC
Visible Deflection of SlabCCC
Short/Captive ColumnNCCC
Diaphragm ContinuityCCC
Table 4. Tier-01 Rapid Visual Screening Vertical Irregularities.
Table 4. Tier-01 Rapid Visual Screening Vertical Irregularities.
Vertical IrregularityBuilding 1Building 2Building 3
SetbackNCCC
Complete Load PathCCC
RedundancyCCC
Weak StoryNCNCNC
Soft StoryNCNCNC
Vertical Discontinuity (Pickup Column)NCCC
PoundingNCNCNC
Strong Column Weak BeamCCC
Mass IrregularityNCNCNC
Transfer to Shear WallCCC
No Flat Slab FramesCCNC
Height to thickness wall ratio not less than 8CCC
The infill walls are not cavity wallsNCCC
Opening adjacent to Shear wall less than 15% of wall lengthCCC
Infill walls are continuous to the soffits of the beamCCC
Opening at Exterior masonry shear wall is not less than 4 ft longNANANA
NC = Non-Complaint, C = Complaint, NA = Not Applicable.
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Share and Cite

MDPI and ACS Style

Mohammad, A.F.; Khan, R.A.; Siddiqui, M.A.; Hammad, M. Case Study: Rapid Seismic Assessment of Existing Hospitals in Karachi. Eng. Proc. 2022, 22, 8. https://doi.org/10.3390/engproc2022022008

AMA Style

Mohammad AF, Khan RA, Siddiqui MA, Hammad M. Case Study: Rapid Seismic Assessment of Existing Hospitals in Karachi. Engineering Proceedings. 2022; 22(1):8. https://doi.org/10.3390/engproc2022022008

Chicago/Turabian Style

Mohammad, Aslam Faqeer, Rashid A. Khan, Muhammad Afnan Siddiqui, and Muhammad Hammad. 2022. "Case Study: Rapid Seismic Assessment of Existing Hospitals in Karachi" Engineering Proceedings 22, no. 1: 8. https://doi.org/10.3390/engproc2022022008

Article Metrics

Back to TopTop