Next Article in Journal
Evaluating SWAT Performance to Quantify the Streamflow Sediment Yield in a Highly Urbanized Basin
Previous Article in Journal
Changes of Significant Wave Height, Energy Period and Wave Power in Italy in the Period 1979–2018
 
 
Please note that, as of 4 December 2024, Environmental Sciences Proceedings has been renamed to Environmental and Earth Sciences Proceedings and is now published here.
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Proceeding Paper

Selection of Appropriate Coastal Protection Structure Using AHP Method †

Faculty of Civil Engineering, University of Rijeka, 51 000 Rijeka, Croatia
*
Author to whom correspondence should be addressed.
Presented at the 4th EWaS International Conference: Valuing the Water, Carbon, Ecological Footprints of Human Activities, Online, 24–27 June 2020.
Environ. Sci. Proc. 2020, 2(1), 4; https://doi.org/10.3390/environsciproc2020002004
Published: 8 August 2020

Abstract

:
The selection of an appropriate coastal protection structure using multi-criteria analysis method AHP (analytic hierarchy process) was presented by a case study of a beach reconstruction in the Kostanj Bay (north-western part of Croatia). The newly designed beach (about 300 m long) will be formed on the western part of the bay by the additional filling of the natural rocky coastline with gravel and building reinforced concrete seawalls towards the sea. The beach will be protected by a submerged breakwater. Five different alternatives were analysed and defined by a different design of the protective breakwater. The first alternative, without the submerged breakwater, was considered as the baseline alternative. An additional four alternatives were examined based on four criteria and five sub-criteria, which considered the technical, economic, social and environmental impacts. The sensitivity of the ranking for the considered alternatives was analysed using five criteria importance scenarios.

1. Introduction

The complexity of decision making in coastal management is a result of multiple objectives that must be satisfied, different criteria and measures that are used to valorise the achievement of these objectives, and the multiple stakeholders that are usually involved in the process. To support this kind of decision-making processes, different methods can be applied, such as multi-criteria analyses (MCA) methods [1,2,3,4]. MCA methods have been regularly applied in coastal management: for determining coastal vulnerability to wave impacts using the AHP (analytic hierarchy process) method and GIS in Santa Catarina Spain [5]; defining priority actions for waterfront development incorporating local stakeholder preferences using developed MCA method ENCoRe in Greece [6]; selecting deep-water sea port’s construction site using AHP and fuzzy ratio assessment (ARAS-F) methods in the Baltic Sea [7]; and identifying and prioritizing critical infrastructure vulnerabilities in the coastal community of Scarborough, Maine, USA, using AHP [8].
This paper presents the methodology for selecting an appropriate coastal protection structure (construction of protective submerged breakwater) using multi-criteria analysis method AHP, which was demonstrated by a case study for the beach reconstruction in the Kostanj Bay (located in the north-western part of Croatia, near the city of Rijeka). Five alternatives were analysed according to four criteria and five sub-criteria. The importance of each criterion and sub-criterion are defined by a different weight factor.
The aims of this paper were threefold: first, verify whether the AHP method is suitable for decision making in coastal management when selecting an optimal breakwater design; second, present a methodology for preparing the input data for the AHP analysis of a specific case study; third, give some suggestion for the AHP application on similar problems in coastal management and for further research.

2. Materials and Methods

2.1. AHP Method

AHP is a priority method applicable to problems that can be represented by a hierarchical structure [9]. The top of the hierarchy is the goal, one level lower are the criteria, and there is the possibility of adding more levels for sub-criteria. The lowest level is represented by alternatives. The AHP method is based on estimating the pair-wise relative priorities (weight, importance, preference) of criteria to the goal and alternatives to each (sub)criterion. Pair-wise comparison matrix for criteria with respect to the goal, and pair-wise comparison matrices for alternatives (one matrix for each criterion) were generated using a pair-wise comparison scale shown in Table 1. This method also allows a direct assessment of the criteria regarding the goal and of the alternatives regarding each criterion, which was applied only to criteria importance in this research.
The columns in matrices are normalized in order to calculate the priority vector for criteria and the priority vectors for alternatives regarding each criterion. As a result, the overall priority matrix of alternatives is formed in which the columns are priority vectors of alternatives for each criterion. The overall priority vector of alternatives is calculated by multiplying this matrix with the priority vector of criteria. The overall priority vector defines the priority (weight) of each alternative with respect to the goal so that the ranking of alternatives can be defined. In the case of the pair-wise comparison of alternatives or criteria, the consistency of pair-wise comparison matrices of alternatives and criteria, as well as the overall priority matrix are evaluated by computing the inconsistency index (which should be lower than 0.1) to assure that the judgments are consistent. For ranking alternatives using the multi-criteria method AHP, the following steps should be performed:
  • Defining the problem (the goal, the criteria, the alternatives) and defining the hierarchy;
  • Performing a pair-wise comparison of criteria in respect to the goal or defining the weight/importance of each criterion (this must be done also for sub-criteria with respect to criteria);
  • Performing a pair-wise comparison of the alternatives with respect to each criterion or evaluating the alternatives against each criterion;
  • Applying the AHP method to estimate the overall priority vector of the alternatives with respect to the goal;
  • Forming the rank-list of alternatives;
  • Performing the sensitivity analysis;
  • Making the final decision.

2.2. Case Study

The case study analysed in this paper was the reconstruction of a beach in Kostanj Bay located in the north-western part of Croatia, in the city of Rijeka (Figure 1).
The City of Rijeka is the third largest city in Croatia and the second largest coastal city. According to the 2011 Census, the city had a population of 128,624 inhabitants, with a metropolitan area of 245,054 inhabitants. Rijeka has a humid subtropical climate (Cfa) with warm summers and relatively mild winters. Although Rijeka has never been among the most popular tourist destinations in Croatia, it has gained noticeable interest as a cultural and tourist destination in recent years. The bathing season in Rijeka starts in spring and lasts until late autumn. A series of smaller and larger beaches are located on the eastern and western border of Rijeka. As a result of steep coastline, natural rocky beaches prevail, with several natural and artificial gravel beaches.
The Kostanj was the first public beach in Croatia adapted for people with disabilities. Since the current interests and needs surpass the capacity of 300 visitors, the City of Rijeka has decided to extend and reconstruct this beach. The newly designed beach will be formed upon the existing beach and will extend over a coastline length of approximately 300 m, from the northeast to northwest. The beach will be extended by building reinforced concrete seawalls, with similar elevations to the existing beach. Experiences with the long-term maintenance of the Kostanj beach show increased nourishment activities every year before the start of the tourist season, as well as repeated repairs of concrete coastal elements damaged by increased erosion from waves. Therefore, as an additional element, a protective submerged breakwater is planned. This structure should contribute to the protection of other coastal structures from the destructive action of the sea waves, but also the reduction of the gravel beach erosion. The protective submerged breakwater was selected because it has good performance in dissipating wave energy and reducing wave heights in front of the beach structure, and it is well suited for the local site conditions characterised by a steep rocky shoreline. Alternative protective structures, including both soft and hard measures, were dismissed at the preliminary stage of the decision-making process because of their high costs or because they are less suited for local conditions (steep rocky shoreline, wave climate, etc.).
For this purpose, five alternatives, defined by a different design and position of the submerged breakwater, were considered. In alternative A1, the beach will be extended to the western part of the bay by filling the natural rocky coastline and constructing reinforced concrete seawalls, without any protective structure (a baseline alternative). The condition given by the investor was that a submerged breakwater should be placed for the beach protection, thus the alternatives from A2 to A5 have the same beach structure as A1, but they differ in the design, dimensions, and location of the protective submerged breakwater. Detailed information on each alternative is given in Figure 2 and Table 2.
Once the location, design, and dimensions of the submerged breakwater were defined, the performance of each alternative was tested by a numerical wave model [10]. Namely, to assess the performance of a breakwater in reducing wave heights and energy, a third-generation wave model SWAN was applied [11]. Although a submerged breakwater also affects the circulation and sediment transport, these processes are negligible in comparison to wave forces in these conditions. The model was forced by a 50 year return period wave spectrum defined by a significant wave height, 3.5 m from the south-southwest (SSE) direction. The spatial domain was defined by the bathymetry with superimposed breakwater geometry. The results from the SWAN model show a reduction in the significant wave heights in front of the new beach, as well as the wave energy dissipation at the breakwater [10]. These results were considered when comparing and evaluating the alternatives from the technical, economic, environmental, and social point of view (Table 2).

3. Results

3.1. Definition of Criteria

The goal of the MCA in this paper was to select the best breakwater design according to defined criteria and their importance. Four categories of criteria were defined considering the problem and its solutions (alternatives): the technical, economic, environmental, and social criteria.
The technical criterion (T) is divided into the following three sub-criteria:
  • the decrease in the significant wave height along the new and existing coastal structure (T1)—this is directly related to the wave forces acting on the structure (stronger reduction of the wave heights suggests lower wave forces and less potential damages to the structure);
  • the dissipation of the wave energy (T2)—the wave energy should be dissipated as much as possible and as far as possible from the structure to ensure that no breaking waves reach the beach structure; and
  • the effect on the protection of the newly built coastal structure (T3)—coastal structures, such as the concrete walls, can be vulnerable to the scouring at the toe, which may have a negative impact on the structure stability, therefore a rubble protection placed in front of the concrete wall has an additional positive effect.
The economic criterion (EC) is divided into the following two sub-criteria:
  • the complexity of the structure of the breakwater (EC1)—if the breakwater is placed close to (in front of) the coastal wall, it can be built directly from the beach, which is more practical and less expensive than building a detached breakwater from a floating equipment; and
  • the volume of the breakwater (how much material is needed) (EC2)—the volume of the breakwater is directly related to the volume of rubble mound material and the price of the construction.
The environmental criterion (EN) evaluates the impact of alternatives on the improvement of the habitat conditions. The breakwater provides both food and refuge for the fish, therefore the surface area is positively correlated with the number and diversity of local species [12].
The social criterion (S) analyses the impact of alternatives on swimmers (the entrance in the water) and for boat approaches to the shore. The depth of the breakwater crown is positioned 2.0 m below sea level, which is deep enough not to pose an obstacle to swimmers or the approach of small boats. However, during extreme ebb phases, swimmers may feel the bottom consisting of large stone blocks when entering the sea, which may be less comfortable in comparison to the natural sea bottom. This may present a negative effect on the breakwater positioned in front of the beach. On the other hand, detached breakwaters do not affect the swimmers, but they may pose an issue for the approach of slightly larger boats during an extreme ebb phase, which is less likely in this location.
The importance that is given to criteria (Scenario S1) based on the authors’ expert judgement was: 30% for the technical criteria (33.33% for each sub-criterion), 40% for the economic criteria (of which 40% for the sub-criterion EC1, and 60% for the sub-criterion EC2), 15% each for environmental (EN), and social criterion (S). The technical and economic criteria were given more importance than the environmental or social criterion in this case, because the environmental and social impacts are not crucial for a construction of these dimensions. Between the technical and economic criteria, a slight advantage was given to the economic criteria because the technical ones—the dissipation of wave energy and reduction of wave heights—were very similar when comparing the considered alternatives.

3.2. Pairwise Comparison of Alternatives

The pair-wise comparison of the alternatives A2 to A5, with respect to each criterion (sub-criterion), was performed based on the data and descriptions of alternatives presented in Table 2 using the pair-wise comparison scale from Table 1. Table 3 shows the preferences of each alternative (given in rows) in relation to other alternatives (given in columns) with respect to a specific criterion (sub-criterion). A positive value indicates that the alternative in that row is better than the alternative in a corresponding column.
The inconsistency of the pairwise comparison of alternatives is 0.00 for EC2, EN and S; 0.03 for T3 and EC2; 0.04 for T2; and 0.05 for T1. Therefore, the assessment is consistent.

3.3. Results from AHP

Based on the analysis performed using the AHP method (and the ideal synthesis mode) according to the selected criteria importance (Scenario S1), the best alternative is A3 (0.334), followed by A2 (0.272), A5 (0.219) and A4 (0.175), as presented in Figure 3. The overall consistency is 0.02. A more detailed insight in the final ranking is given in Figure 4 derived from the sensitivity graph.
To test the sensitivity, four more scenarios of criteria importance were considered and evaluated:
  • Scenario S2: T 25%, EC 35%, EN 30% and S 10%—more importance is given to the environmental criterion; technical, economic and social criteria are given less importance in comparison to S1;
  • Scenario S3: T 45%, EC 35%, EN 10% and S 10%—more importance is given to the technical criterion; economic, environmental and social criteria are given less importance in comparison to S1;
  • Scenario S4: T 40%, EC 30%, EN 15% and S 15%—more importance is given to the technical criterion, less to economic one, with no change in the environmental and social criteria importance in comparison to S1; and
  • Scenario S5: T 30%, EC 50%, EN 10% and S 10%—more importance is given to the economic criterion, less to the technical, environmental and social criteria in comparison to S1.
The importance of sub-criteria was not changed. Results of the AHP analyses based on all the criteria importance scenarios are presented in Table 4.

4. Discussion and Conclusions

The alternative A3 was ranked as the best solution (optimal design of the breakwater) in all the criteria importance scenarios (Table 4). If only the technical criterion was applied, the best alternative would be A5, while A2 would be the best if only the economic criterion was considered. The possibility to include both environmental and social criteria in addition to technical and economic criteria provides a more holistic assessment of the potential benefits and impacts of each alternative, and helps to form a more reliable decision.
The advantage of the AHP method, the possibility to make a pair-wise comparison of the alternatives according to each criterion (both quantitatively and qualitatively), has proven to be useful in selecting the design of breakwater since not all criteria could have been quantitatively assessed in this planning stage. The analyses proved that the AHP method is a useful tool for decision making when selecting an optimal design of coastal structures, such as breakwaters. Further research will focus on: more detailed numerical modelling of coastal processes [13], combining quantitative and qualitative criteria, more detailed selection and quantification of social and environmental criteria, and the inclusion of stakeholders in the process of decision making.

Author Contributions

Conceptualization, B.K.; methodology, B.K., N.K., I.R.; software, B.K., N.K., I.R.; validation, B.K., N.K., I.R.; formal analysis, B.K.; investigation, B.K., N.K., I.R.; resources, B.K.; data curation, B.K., N.K.; writing—original draft preparation, B.K., N.K., I.R.; writing—review and editing, B.K., N.K., I.R.; project administration, B.K.; funding acquisition, B.K. All authors have read and agreed to the published version of the manuscript.

Funding

This research was funded by the University of Rijeka projects: Implementation of innovative methodologies, approaches and tools for sustainable river basin management (uniri-tehnic-18-129), Hydrology of water resources and identification of flood and mudflow risks in karst (uniri-technic-18-54) and Geo-hazard in Kvarner Bay area (uniri-tehnic-18-97).

Conflicts of Interest

The authors declare no conflict of interest.

References

  1. Triantaphyllou, E. Multi-Criteria Decision Making Methods: A Comparative Study; Kluwer Academic Publishers: Dordrecht, The Netherlands, 2000; ISBN 978-0-7923-6607-2. [Google Scholar] [CrossRef]
  2. Figueira, J.; Greco, S.; Ehrogott, M. Multiple Criteria Decision Analysis: State of the Art Surveys. In International Series in Operations Research & Management Science; Springer: New York, NY, USA, 2005; Volume 78, ISBN 978-0-387-23081-8. [Google Scholar] [CrossRef]
  3. Huang, I.B.; Keisler, J.; Linkov, I. Multi-criteria decision analysis in environmental sciences: Ten years of applications and trends. Sci. Total Environ. 2011, 409, 3578–3794. [Google Scholar] [CrossRef] [PubMed]
  4. Hajkowicz, S.; Collins, K. A Review of Multiple Criteria Analysis for Water Resource Planning and Management. Water Resour. Manag. 2007, 21, 1553–1566. [Google Scholar] [CrossRef]
  5. Serafim, M.B.; Siegle, E.; Corsi, A.C.; Bonetti, J. Coastal vulnerability to wave impacts using a multi-criteria index: Santa Catarina (Brazil). J. Environ. Manag. 2019, 230, 21–32. [Google Scholar] [CrossRef] [PubMed]
  6. Papatheochari, T.; Coccossis, H. Development of a waterfront regeneration tool to support local decision making in the context of integrated coastal zone management. Ocean Coast. Manag. 2019, 169, 284–295. [Google Scholar] [CrossRef]
  7. Zavadskas, E.K.; Turskis, Z.; Bagočius, V. Multi-criteria selection of a deep-water port in the Eastern Baltic Sea. Appl. Soft Comput. 2015, 26, 180–192. [Google Scholar] [CrossRef]
  8. Johnston, A.; Slovinsky, P.; Yates, K.L. Assessing the vulnerability of coastal infrastructure to sea level rise using multi-criteria analysis in Scarborough, Maine (USA). Ocean Coast. Manag. 2014, 95, 176–188. [Google Scholar] [CrossRef]
  9. Saaty, T.L. The Analytic Hierarchy Process, 2nd ed.; RWS Publications: Pittsburg, CA, USA, 1996. [Google Scholar]
  10. Grahovac, A.; Krvavica, N.; Ružić, I. Seawall construction impact on wave dynamics of natural coast. Zbornik Radova Građevinskog Fakulteta u Rijeci 2018, 21, 179–191. (In Croatian) [Google Scholar] [CrossRef]
  11. Booij, N.; Ris, R.C.; Holthuijsen, L.H. A third-generation wave model for coastal regions, Part I: Model description and validation. J. Geophys. Res. 1999, 104, 7649–7666. [Google Scholar] [CrossRef]
  12. Pizzolon, M.; Cenci, E.; Mazzoldi, C. The onset of fish colonization in a coastal defence structure (Chioggia, Northern Adriatic Sea). Estuar. Coast. Shelf Sci. 2008, 78, 166–178. [Google Scholar] [CrossRef]
  13. Postacchini, M.; Lalli, F.; Memmola, F.; Bruschi, A.; Bellafiore, D.; Lisi, I.; Zitti, G.; Brocchini, M. Model chain approach for coastal inundation: Application to the bay of Alghero. Est. Coast. Shelf Sci. 2019, 219, 56–70. [Google Scholar] [CrossRef]
Figure 1. Location of the case study area.
Figure 1. Location of the case study area.
Environsciproc 02 00004 g001
Figure 2. Alternatives A1–A5 of the coastal protection structures implementation and their cross-sections (from [10]).
Figure 2. Alternatives A1–A5 of the coastal protection structures implementation and their cross-sections (from [10]).
Environsciproc 02 00004 g002
Figure 3. Result of the AHP method application for Scenario S1.
Figure 3. Result of the AHP method application for Scenario S1.
Environsciproc 02 00004 g003
Figure 4. Performance sensitivity for Scenario S1.
Figure 4. Performance sensitivity for Scenario S1.
Environsciproc 02 00004 g004
Table 1. The AHP (analytic hierarchy process) method pair-wise comparison scale [9].
Table 1. The AHP (analytic hierarchy process) method pair-wise comparison scale [9].
Intensity of Weight, Importance, PreferenceDefinition
1Equal importance (no preference)
3Moderate importance (moderate preference)
5Strong importance (strong preference)
7Very strong importance (very strong preference)
9Extreme importance (extreme preference)
2, 4, 6, 8Intermediate values
Table 2. Pairwise comparison of the alternatives.
Table 2. Pairwise comparison of the alternatives.
AlternativesCharacteristics of the BreakwaterComplexity of the ConstructionDecrease in Wave HeightWave Energy DissipationProtection of Coastal StructureEnvironmental ImpactsSocial Impacts
A1no breakwaterno breakwater constructionnonenonenonen/an/a
A2made of large stone elements, connected to the shore (length 100 m, crest height −2.0 m and width
6.0 m, the crest altitude on the beach side is higher
−1.5 m for beach protection, max. depth is—6.5 m, volume 2150 m3)
simpler and cheaper than the construction of the breakwater in alternative A4 and A5 because it is possible to construct it by filling the material from the shore—without offshore construction equipmentav. by 17%,
max. by 23%
high, energy is dissipated very close to the structureprovides protection for natural beach material, protects the structure from scouringprovides a significant area near the coastline for new bio habitatsome negative impacts during extreme ebb phases, due to reduced water depth and unappealing sea bed where swimmers enter the water
A3made of large stone elements, connected to the shore (4.0 m wider than A2, length 110 m, crest height −2.0 m, the crest altitude on the beach side is higher −1.5 m for beach protection, max. depth is—7.5 m, volume 2870 m3)simpler and cheaper than the construction of the breakwater in alternative A4 and A5 because it is possible to construct it by filling the material from the shore—without offshore construction equipment, more material is needed than in A2av. by 18%,
max. by 28%
high, energy is dissipated close to the structureprovides protection for natural beach material, protects the structure from scouring, slightly better than A2provides a significant area near the coastline for new bio habitat, better than A2, A4, A5some negative impacts during extreme ebb phases, due to reduced water depth and unappealing sea bed where swimmers enter the water (similar to A2)
A4made of large stone elements, with a trapezoidal cross-section detached from shore (length 110 m, crest height
−2.0 m and width 6.0 m, the axis is at an average depth of −5.0 m, volume 3200 m3)
complex and more expensive than A2 and A3 because of the distance of the breakwater from shore and need for offshore construction equipmentav. by 15%,
max. by 28%
high, energy is dissipated far from the structureprovides protection for natural beach material, does not protect the structure from scouring, similar to A5, worse than A2provides a significant area far from the coastline for new bio habitat, similar to A2, A5insignificant impact during extreme ebb phases for potential boat approach
A5made of large stone elements, with trapezoidal cross-section detached from shore (length 125 m, crest height −2.0 m and width 6.0 m, the breakwater axis is at an average depth of −6.0 m, volume of material
4100 m3)
complex and more expensive than A2 and A3 because of the distance of the breakwater from shore and need for offshore construction equipment, more material is needed than in A4av. by 17%,
max. by 33%
high, energy is dissipated very far from the structureprovides protection for natural beach material, does not protect the structure from scouring similar to A4 and worse than A2provides a significant area far from the coastline for new bio habitat, similar to A2 and A4insignificant impact during extreme ebb phases for potential boat approach
Table 3. Pairwise comparison of alternatives.
Table 3. Pairwise comparison of alternatives.
T1A2A3A4A5T2A2A3A4A5T3A2A3A4A5
A2 −4−3−6A2 −3−5−7A2 −277
A3 3−3A3 −3−5A3 88
A4 −4A4 −3A4 1
A5 A5 A5
EC1A2A3A4A5EC2A2A3A4A5
A2 155A2 357
A3 55A3 35
A4 1A4 3
A5 A5
ENA2A3A4A5
A2 −311
A3 33
A4 1
A5
SA2A3A4A5
A2 1−3−3
A3 −3−3
A4 1
A5
Table 4. Result of AHP application on 5 different criteria scenarios.
Table 4. Result of AHP application on 5 different criteria scenarios.
RankScenario
S1S2S3S4S5
1A3
(0.334)
A3
(0.369)
A3
(0.333)
A3
(0.326)
A3
(0.345)
2A2
(0.272)
A2
(0.262)
A2
(0.262)
A5
(0.249)
A2
(0.303)
3A5
(0.219)
A5
(0.203)
A5
(0.241)
A2
(0.244)
A5
(0.196)
4A4
(0.175)
A4
(0.167)
A4
(0.163)
A4
(0.181)
A4
(0.157)
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Share and Cite

MDPI and ACS Style

Karleuša, B.; Krvavica, N.; Ružić, I. Selection of Appropriate Coastal Protection Structure Using AHP Method. Environ. Sci. Proc. 2020, 2, 4. https://doi.org/10.3390/environsciproc2020002004

AMA Style

Karleuša B, Krvavica N, Ružić I. Selection of Appropriate Coastal Protection Structure Using AHP Method. Environmental Sciences Proceedings. 2020; 2(1):4. https://doi.org/10.3390/environsciproc2020002004

Chicago/Turabian Style

Karleuša, Barbara, Nino Krvavica, and Igor Ružić. 2020. "Selection of Appropriate Coastal Protection Structure Using AHP Method" Environmental Sciences Proceedings 2, no. 1: 4. https://doi.org/10.3390/environsciproc2020002004

APA Style

Karleuša, B., Krvavica, N., & Ružić, I. (2020). Selection of Appropriate Coastal Protection Structure Using AHP Method. Environmental Sciences Proceedings, 2(1), 4. https://doi.org/10.3390/environsciproc2020002004

Article Metrics

Back to TopTop