Next Article in Journal
Green Carbon Composite-Derived Polymer Resin and Waste Cotton Fibers for the Removal of Alizarin Red S Dye
Next Article in Special Issue
Two-Stage Electricity Demand Modeling Using Machine Learning Algorithms
Previous Article in Journal
Wave Energy Resource Assessment off the Coast of China around the Zhoushan Islands
Previous Article in Special Issue
An Intelligent Hybrid Heuristic Scheme for Smart Metering based Demand Side Management in Smart Homes
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Cost Analysis for a Hybrid Advanced Metering Infrastructure in Korea

Department of Electrical Engineering, Gachon University, 1342 Seongnamdaero, Sujeong-Gu, Seongnam-Si, Gyeonggi-Do 13120, Korea
*
Author to whom correspondence should be addressed.
Energies 2017, 10(9), 1308; https://doi.org/10.3390/en10091308
Submission received: 11 July 2017 / Revised: 15 August 2017 / Accepted: 28 August 2017 / Published: 1 September 2017
(This article belongs to the Special Issue From Smart Metering to Demand Side Management)

Abstract

:
Advanced metering infrastructure (AMI) refers to the electricity service infrastructure between electricity consumers and suppliers and is technically essential for the realization of a smart grid environment. To implement AMI, various communications technologies are being used based on the application environment according to the utility. However, using a single communications method can give rise to attenuation in the downtown underground distribution line section or cause higher supply costs due to decreased density in the range from farming to fishing areas. A hybrid AMI is one solution to this problem. According to an economic analysis of previous AMI deployment, the cost to install a communications network accounts on average for 45% of the total cost. Since the installation cost of a communications network is influenced by the density of the installation environment, a hybrid AMI, which allows the configuration of a flexible network using both wired and wireless communications, can be a good alternative, both technically and financially. This study conducted a simulation based on density of the installation environment and configuration of the communications network to analyze the economic effect of installing a hybrid AMI communications network. It assumed that a hybrid AMI was deployed in an overhead distribution line in a low-density area. The simulation outcomes were compared and analyzed against the power line communication (PLC)-only AMI method. The results showed that the hybrid AMI method had a 10% communications network cost reduction effect compared to the PLC-only AMI method. In addition, the analysis indicated that there was a maximum 19% cost reduction effect in communications network installation depending on the method of network installation, suggesting that the hybrid AMI was economically more effective than the PLC-only AMI method.

1. Introduction

Advanced metering infrastructure (AMI) is the electricity service infrastructure between electricity consumers and suppliers that uses two-way communications to read energy use, collect energy-use information, apply rates, and enable additional services [1,2,3,4]. The technology is essential for the realization of a smart grid environment. Currently, the provision of AMI is spreading rapidly worldwide. In Europe, by the middle of 2012, about 90 smart-metering pilot projects and country-specific rollouts were conducted. According to the European Commission, Member States aimed to supply 200 million smart meters by 2020 [5]. This indicates that more than 70% of users will be included in Smart Grid technology through the use of smart meters [6]. The United States has installed 65 million smart meters covering more than 50% of households by the end of 2015 and expects to install 90 million smart meters by 2020 [7]. As part of the national plan, China is promoting the spread of smart meters, and 150 million smart meters have been introduced by 2015 and are expected to grow steadily at an average annual rate of 8% by 2020 [5,8]. Japan has set a goal of monitoring 80% of its electricity consumption nationwide and is expected to install a smart meter in about 80 million households by 2024 [5]. According to industry reports in India, it is estimated that by 2021, 130 million smart meters with both PLC and wireless technologies will be installed [5]. In Korea, the utility company (KEPCO) is aiming for a 100% installation of smart meters in the country’s entire 21.94 million low-voltage customers by 2020 [9,10].
To implement AMI, various communications technologies are being used based on application environments according to the utility’s preference. AMI communication can be classified into the wire and wireless communication [11]. One of the popularly used wire communication methods is power line communication (PLC) [12], which has the advantages of low investment cost by using existing power line infrastructure [12,13,14]. PLC is divided into broadband PLC, using frequencies up to 30 MHz, and narrowband PLC using frequencies up to 500 kHz [5]. However, this has a disadvantage in that the bandwidth is limited and the attenuation increases as the transmission distance increases [15,16]. Wireless communication methods include WiFi-Mesh (IEEE 802.11s), ZigBee (IEEE 802.15.4), smart utility network (SUN: IEEE 802.15.4g), and TV White Space (IEEE 802.22b) [12,13,17]. The wireless communication methods have the advantages of high data throughput, fast data rate and flexible network configuration [12,15]. However, there is a disadvantage that interference caused by other wireless devices, the terrain and objects can occur [15]. This AMI communication technology is applied considering the regional characteristics and policies of each country [18]. In Europe, PLC is used as a typical communication technology, and especially narrowband PLC is widely used [19]. RF is preferred in the United States, and Pacific Gas & Electric in California and Florida Power and Light Company use RF Mesh [5,19]. Canada uses RF Mesh and ZigBee, China prefers PLC, and India uses PLC and wireless technology [19].
Utility companies tend to select a single communication technology because of the resulting cost reduction and ease of maintenance. However, the choice of a single technology can lead to unexpected adverse effects in some areas. For example, when using a power line communication (PLC) technology, the installation cost can increase in farming and fishing areas due to the decrease of customer density between spans. On the other hand, the communications performance can be degraded in downtown underground distribution line sections. In the underground distribution line sections, signal leakage to the surrounding material around the conduit through the distribution line is high, resulting in a high level of signal attenuation [20,21]. Especially, there are some study results suggesting that the communication performance is significantly lower than that of the high-voltage line, which has excellent shielding characteristics in the case of low-voltage lines [22,23,24,25,26,27].
A hybrid AMI using multiple communication technologies depending on the situations is one of the solutions to solve the problems [28]. Improving on the existing method, which limits communications between the smart meter and the data concentration unit (DCU) to one technology, a hybrid AMI is a system that is configured with either a mixed method using multiple communications technologies as supplements or a combined method using multiple communications technologies for dualization.
For successful implementation of a hybrid AMI, technical issues should be resolved and the hybrid AMI should be cost effective and economically feasible. Accordingly, a cost analysis that takes account of all the factors causing cost fluctuation must first be conducted during the initial stages of deploying the hybrid AMI.
According to analyses performed on the economics of existing AMI technologies, the communications network accounts for an average of 45% of the total installation cost [29]. Since the equipment comprising the communications network entails operation and maintenance (O&M) costs, a communications network installation plan suited to the installation environment needs to be devised during the initial stages of the undertaking from a long-term perspective. Since the installation cost of a communications network is influenced by the density of the installation environment, a hybrid AMI, which allows the configuration of a flexible network using both wired and wireless communications, can be a good alternative, both technically and financially [29].
This study conducted a cost analysis based on the density of the installation environment and the configuration of the communications network to evaluate the economic effects of installing a hybrid AMI communications network. To this end, the study deduced major cost factors of the hybrid AMI and built a cost model taking account of consumer density and wire methodology. Korea had determined to use a broadband PLC technology based on IEC 12139-1 at the initial stage of AMI deployment. Recently, adopting a hybrid AMI method has been studied to improve economics and efficiency combining wireless technology. Therefore, a PLC-only AMI method is considered as the reference model, and a hybrid AMI method with PLC and wireless communication are compared in this work. Here, ZigBee and SUN are implicitly considered as the wireless technology. In this study, the density of the installation environment was simplified into downtown and non-downtown areas, and it was assumed that hybrid AMI is deployed in the overhead distribution line in a non-downtown area, which is a low-density region. A simulation was run based on a power line communication (PLC)-only AMI method installation and a hybrid AMI method installation under the AMI deployment plan considering the situation of Korea and the proposed cost model. Based on the simulation results, a comparison was made of major cost factors and a sensitivity analysis was performed, after which the economic effects of the hybrid AMI were presented accordingly.

2. Hybrid Advanced Metering Infrastructure Cost Model

2.1. Hybrid AMI Concept

The AMI system primarily communicates through smart meters usually installed in consumer connections, and it has a hierarchical structure composed of a DCU, which collects information, and a meter data management system (MDMS), which oversees the overall consolidation and management of gathered information [30,31,32]. Improving on the existing method of limiting communications between the smart meter and the DCU to one technology, a hybrid AMI environment is a system comprised of either a mixed method that uses multiple communications in a complementary fashion or a combined method that dualizes multiple communications, depending on the environment. The communications technology between the smart meter and the DCU can be applied with various wired and wireless communications, including PLC, WiFi, ZigBee, TVWS, and SUN, and the infrastructure is structured in a way that allows changes to the communications method via repeaters and enables cell expansion. Figure 1 illustrates the structure of the hybrid AMI.

2.2. Categorization of Hybrid AMI Installation Environment

Unlike the existing communications method, it is possible to select a communications method based on the configuration of the communications network in a hybrid AMI environment. Because the configuration of a communications network is influenced by the residential environment, such as density and distance, it is necessary to categorize the installation environments to perform an effective cost analysis. According to an economic analysis on existing AMI, the average cost per consumer can vary by more than twice the value depending on consumer density [29]. In North America, Southern California Edison (51,000 m2) covered more than 20 times the area that Con Edison covered in a low-voltage consumer service area (2200 m2), leading to higher network installation and maintenance costs [29]. These results indicate that the AMI deployment cost is influenced by consumer density. This study accordingly categorized installation environments into high-density regions and low-density regions.

2.3. Hybrid AMI Cost Model

According to the guideline for conventional cost analysis, the analysis consists of three steps: the definition of the scenario, the main parameter settings, and the analysis, then additional sensitivity analysis can be performed [33,34,35]. In this study, the cost analysis model structure can be divided largely into a hybrid AMI deployment environment setup scenario and a cost setup. The hybrid AMI deployment environment setup was categorized into an overhead distribution line section and an underground distribution line section in order to apply wired and wireless communications methods according to the type of distribution line based on the area’s consumer density. Communications networks in a hybrid AMI environment are made up of a single cell containing a DCU with a communications modem and a repeater. The major cost factors for the communications network installation can be separated into costs required for equipment purchase and installation as well as the subsequent O&M cost. The main factors of each cost factor include DCU, communications modem, smart meter, and repeater. In this study, to improve the accuracy of the cost model, a formulation was made considering the type of smart meters, the architecture of communication modem connectivity, the cost change according to the number of deployment, the customer density of regions, the type of distribution lines, etc. The detailed cost model is as follows.

2.3.1. DCU

The DCU installation cost can be calculated by applying the unit price of equipment and installation based on the DCU deployment quantity, as shown in Equation (1). The average DCU quantity according to installation region, or D C U Q y , r , i , is classified into single installation methods and hybrid installation methods, and it is calculated by taking account of the average quantity of communication modems accepted per area, as observed in Equation (2). The DCU entails operational costs for using the backbone network as well as maintenance costs. The O&M cost is applied from the following year of the installation, and it can be defined as Equation (3):
D C U C y D P = ( D C U P y H W + D C U P y I n s T ) · r R , i I D C U Q y , r , i ,
D C U Q y , r , i = S M Q y , r , i / D C U y , r , i C o v e r ,
D C C y O & M = τ = 0 y 1 r R , i I ( D C U P τ O + D C U P τ M ) D C U Q τ , r , i ,

2.3.2. Smart Meter

A smart meter is a one-per consumer piece of equipment, and they have various unit prices based on any additional functions. The total deployment cost of smart meters per year can be defined using the formulas below based on the AMI deployment quantity, the deployment ratio per smart meter type, and the unit price for equipment and installation per type. Since smart meters are replaced when they break down or reach the end of their life cycle, no maintenance costs are incurred [36]:
S M C y D P = ( S M P y H W + S M P y I n s T ) · i I , r R S M Q y , i ,
S M Q y , i = g G A M I D y , r , g · S M R y , r , g , i ,

2.3.3. Communications Modem

Communications modems need to be applied with the characteristics of the overhead distribution line or the underground distribution line due to the nature of their communications method with the DCU or the repeater, and the smart meter and the communications modem need to be applicable by 1:1 or 1:N, depending on the consumer environment. The cost of installing a communications modem can be calculated by the average quantity of communications modems by type (wired or wireless) in the deployment area and the equipment cost, as defined in Equation (6):
C M C y D P = r R , j J C M Q y , r , j · ( C M P y , j H W + C M P y , j I n s T ) ,
The average quantity of communications modems within the C M Q y , r , j installation region can be estimated by the total quantity of smart meters, the ratio of the overhead distribution line to the underground distribution line, the proportion of the wired communications method to the wireless communications method, and the average quantity ratio of smart meters per communications modem, which is defined in the following equation:
C M Q y , r , j = k K , i I S M Q y , r , i · O U R y , r , k · C M R y , r , i , j T y p e / C S y , r , i , j C o v e r , w h e r e ,   { i f   ( k = 0 ) ,   C M R y , r , 0 , 0 = 1 ,   e l s e = 0 i f   ( k = 1 ) ,   o t h e r w i s e
It was assumed that the underground distribution line (k = 0) in this model was installed with only wired communications, considering the efficiency issues of the wireless communications method. Communications modems entail maintenance costs, which can be defined as the following Equation (8):
C M C y M = τ = 0 y 1 r R , i I C M Q τ , r , j · C M P τ , j M ,

2.3.4. Repeater

Repeaters are used for combining communications methods after communications attenuate due to the expansion of cell configuration following the application of a hybrid form of communications method. The installation cost of repeaters by year can be defined as Equation (9). Here, R P Q y , r , i refers to the average quantity of repeaters per area, and it can be calculated by multiplying the average quantity of repeaters per DCU in each area, or R P R y , r , i , as shown in Equation (10). Repeaters entail yearly maintenance cost, which can be defined as Equation (11) below:
R P C y D P = ( R P P y H W + R P P y I n s T ) · r R , i 0 R P Q y , r , i ,
R P Q y , r , i = D C U Q y , r , i · R P R y , r , i ,
R P C y M = τ = 0 y 1 r R , i 0 R P Q τ , r , i · R P P τ M ,

2.3.5. Hybrid AMI Cost Analysis Model

Once the installation environment is set up based on the density of the AMI deployment location as well as through the setup of the overhead distribution line and the underground distribution line, the deployment plan should be implemented based on the previously set installation environment. This is where the quantity of smart meters for the installation location is determined and the smart meter type is set up taking account of consumer characteristics. In order to install an average communications network per region, the configuration relations should be set up between the DCU, the smart meter, and the repeater, taking account of the area and the wire configuration type that was previously set. Based on the formerly set installation environment, the total cost can be estimated by applying the unit price of equipment, installation, and O&M. Figure 2 shows the hybrid AMI cost analysis model.
Each cost factor of the AMI cost model influences each another depending on the deployment plan. This study used a system dynamics-based tool, Powersim, to realize the model in order to perform an effective cost analysis. Figure 3 is an illustration of the system dynamics model structure of the AMI cost model.

3. Simulation and Discussion

3.1. Simulation Scenario

This study assumed that the hybrid AMI was deployed in the overhead distribution line within a low-density region. According to the simulation scenario setup, the classification system in reference [37] was referred to for the AMI installation environment: the high-density region and the low-density region were applied by simplifying them into the downtown area and the non-downtown area, respectively. The proportion of the downtown area to the non-downtown area was set as 6:4, as referred to in references [37,38], and the wire type was applied with the late 2012 wire ratio of 8.5:1.5 between the overhead distribution line and the underground distribution line [38]. This study chose to deploy the hybrid AMI in the overhead distribution line within a non-downtown area, and assumed based on the setup results in Section 2 that the hybrid AMI accounted for 34% of the total deployment goal. The installation plan reflects the AMI deployment plan devised by existing Korean electric companies; a 15-year cost analysis scenario was built assuming there would be approximately 1.2% new targets for installation once the deployment was completed. The following Table 1 presents the AMI deployment scenario.
In downtown areas, the PLC was set up by applying the existing AMI deployment method. The quantity of smart meters per DCU of the PLC was applied with the average referred to in reference [36], and the setup ensured no repeater was applied. In non-downtown areas, the setup involved both the PLC and the wireless in a hybrid form, in the ratio of 5:5. Considering that the maximum quantity of smart meters the hybrid AMI aims to accommodate is 500, it was assumed in this study that the quantity of smart meters per DCU was 250 on average [39]. Another assumption was that 2.5 repeaters on average were used per DCU. As for the unit price of equipment for the communications modem and the DCU, changes in unit price per deployment quantity were referred to in reference [37], and a cost curve with the target unit price of 1PU (Per Unit) was applied, as shown in Figure 4. Furthermore, the target unit price for 2 million households in reference [36] was used for installation and O&M costs.

3.2. Simulation Results and Discussion

3.2.1. Total Cost

The total AMI deployment cost amounted to 3116 billion KRW for PLC-only AMI and 2942 billion KRW for hybrid AMI. The analysis shows that as of 2030, the hybrid AMI would have a cost reduction effect of 5.6% or 174 billion KRW compared to the PLC-only AMI. Table 2 presents the total deployment cost result by deployment type.
The analysis indicated that the deployment cost item incurring the highest cost is the smart meter installation cost; it constituted about 45–48% of the total cost. Table 3 displays the results of the comparison between the total cost and smart meter cost.
Examining the cost result from the perspective of a communications network that excludes smart meters from the total deployment cost, the hybrid AMI showed a 173 billion KRW cost reduction compared to the PLC-only AMI as of 2030, which equals a 10.2% cost reduction effect. Table 4 below shows a comparison of the cost results of communications networks per deployment type, and Figure 5 presents the cost summary results per deployment type.

3.2.2. Installation and O&M Cost

Examining installation and O&M costs, Table 5 displays the installation costs as of 2030 for PLC-only AMI (900.2 billion KRW) and hybrid AMI (782.6 billion KRW), indicating a 13.1% cost decrease in hybrid AMI compared with PLC-only AMI.
Table 6 shows that the O&M costs as of 2030 are 802 billion KRW for PLC-only AMI and 745.6 billion KRW for hybrid AMI, indicating a 7% reduction of cost in hybrid AMI. The results in this subsection demonstrate that the installation cost is higher than the O&M cost. However, the cost reduction effect amounts to 117.6 billion KRW for installation cost, which is 61.2 billion KRW higher than that of O&M cost, suggesting a comparatively higher cost reduction effect. Figure 6 illustrates the comparison result of installation and O&M costs per deployment type.

3.2.3. Communications Network Cost

Examining cost by piece of equipment from the perspective of the communications network cost, it can be observed that the cost reduction effect of the DCU cost increased with the deployment of the hybrid AMI. The DCU cost for the PLC-only AMI was 885 billion KRW and the DCU + repeater cost for the hybrid AMI was 661.4 billion KRW, as presented in Table 7 and Figure 7. The analysis shows that as of 2030, the cost of the hybrid AMI decreased by 25.3% or 223.6 billion KRW in comparison to the PLC-only AMI. The DCU and repeater cost results for the hybrid AMI in Table 8 indicate that repeaters incur costs that are 6.7% of that incurred by DCUs.
The cost of a communications modem as of 2030 was estimated to be 817.1 for PLC-only AMI and 866.8 billion KRW for hybrid AMI. The hybrid AMI incurred costs that were higher by 49.7 billion KRW due to the influence of the unit price for wireless modems. This figure is equivalent to 6% of the DCU cost, which is a relatively small increase. Table 9 displays the communications modem cost results.

3.2.4. Deployment Cost per Customer

Examining the AMI deployment cost from the perspective of cost per consumer, the analysis indicates there was a 5.9% cost reduction effect based on the total cost, including smart meters, with the PLC-only AMI decreasing by 135,000 KRW and the hybrid AMI by 127,000 KRW. Based on the cost of the communications network excluding smart meters, the cost per consumer for the hybrid AMI was calculated at 66,000 KRW, which translated into a 9.6% cost reduction effect compared to the 73,000 KRW of the PLC-only AMI. The analysis shows that the cost per consumer for the hybrid AMI was equal to 53% of the average overseas AMI installation cost. Examining the cost per consumer from the perspective of the installation and O&M costs for the communications network, the analysis indicates that the installation cost was 16.3% and the O&M cost was 8.6%, suggesting a big cost reduction effect for the installation cost. Table 10 and Figure 8 below show the cost per consumer by deployment method.

3.2.5. Sensitivity Analysis for Hybrid AMI

A sensitivity analysis was performed to evaluate cost changes based on the PLC-only AMI deployment and the hybrid AMI deployment. The distribution of the modem quantity per DCU and the repeater quantity per DCU based on the configuration of the communications network was assumed a truncated normal distribution. In setting the limits to the truncated normal distribution, consideration was given to the fact that the maximum quantity accommodated by a smart meter per DCU for the PLC-only AMI was 200: therefore, the upper limit was set to 150 and the lower limit to 20 [40]. The upper limit of the number of smart meters per DCU for the hybrid AMI was set to 450 and the lower limit to 150, taking into account the target hybrid AMI deployment plan of 500 [39]. The upper and lower limits of repeaters were set to 1 and 7.5, respectively, by taking account of the average smart meter quantity accommodated per DCU in reference [36]. Table 11 presents the outcome of the sensitivity analysis setup based on the setup standard, a sensitivity analysis was performed using the Monte Carlo technique.
The results of the sensitivity analysis suggest that the hybrid AMI had a cost reduction effect in all sections, which can be seen in Figure 9. In the 5-percentile section, the PLC-only AMI showed a cost reduction of 1647.4 billion KRW and the hybrid AMI a cost reduction of 1508.5 billion KRW; in the 95-percentile section, the cost reductions were 1863.6 billion KRW and 1553.8 billion KRW, respectively.
By comparing the cost analysis results of the 95-percentile section, which was the largest cost distribution section for the hybrid AMI, and the 5-percentile section, the smallest cost distribution section for the PLC-only AMI, it became evident that the hybrid AMI had a low cost distribution of 93.6 billion KRW. Table 12 below and Figure 9 above reflect the results of the sensitivity analysis per deployment method.
The results in this subsection demonstrate that based on the AMI deployment plan, the hybrid AMI can reduce the installation cost of a communications network by as much as 19.1% compared to the PLC-only AMI. On the other hand, the analysis of the 5-percentile section of both deployment methods indicates that the hybrid AMI has a minimum 8.4% cost reduction effect compared to the PLC-only AMI. It is evident from these results that the hybrid AMI is economically more effective than the PLC-only AMI

4. Conclusions

This study conducted a simulation based on the density of the installation environment and the configuration of the communications network to analyze the economic effects of installing a hybrid AMI communications network. It was assumed that a hybrid AMI was deployed in the overhead distribution line within a low-density region, and the results were compared and analyzed against the PLC-only method. Based on the total cost, including smart meters, the results of the cost analysis show that the hybrid AMI has a 5.6% or 174 billion KRW cost reduction effect compared to the PLC-only AMI. Based on the cost of the communications network, excluding smart meters, the results show that the hybrid AMI has a cost reduction of 173 billion KRW in comparison to the PLC-only AMI, which is equivalent to a 10.2% cost reduction effect. The total cost per consumer, including smart meters, for the hybrid AMI was 127,000 KRW, which is a 5.7% decrease compared to the PLC-only AMI. From the perspective of the communications network cost, the total cost per consumer, including smart meters, for the hybrid AMI was at 66,000 KRW, a 9.6% cost cut. The installation cost and O&M cost for the deployment of the hybrid AMI reduced by 13.1% and 7%, respectively, compared to the PLC-only AMI, and the reduced costs were significant. Examining the cost per piece of equipment from the perspective of the communications network cost, the analysis shows that the DCU cost had the highest reduction effect, dropping 25.3% following the deployment of the hybrid AMI. On the contrary, the cost of communications modems increased 6% due to the influence of the modem unit price. A sensitivity analysis of both deployment methods for communications network installation was performed, and the results indicated that the decline in the cost for the hybrid AMI in each section was as high as 19.1%, which was the maximum cost reduction effect. Based on these findings, it was evident that the hybrid AMI was economically effective in Korea. While this study applied the hybrid AMI in a non-downtown area, there would be more economic gain if the application were to expand into the downtown area. In addition, if a detailed system of area classification were used and quality of service for communications network configuration were applied, it would be possible to establish an effective configuration system for the communications network and to devise a deployment plan that takes account of reading cycles and regional characteristics. Although the cost analysis is performed for Korea AMI case in this work, the proposed approach is modeled with a system dynamics tool and can be easily applied to other cases by applying the specific scenarios and parameters. Future research will involve studying an optimal implementation plan for a hybrid AMI that configures an optimal communications network with minimum cost, taking account of the technical factors of building a communications network.

Acknowledgments

This work was supported by the Korea Institute of Energy Technology Evaluation and Planning (KETEP) and the Ministry of Trade, Industry & Energy (MOTIE) of the Republic of Korea (No. 20141010501840 and No. 20151210200240).

Author Contributions

Sung-Won Park implemented the main idea, designed the experiments, and wrote technical sections of the manuscript. Sung-Yong Son organized and refined the manuscript and responded reviewers’ comments.

Conflicts of Interest

The authors declare no conflicts of interest.

Abbreviations

A M I D AMI deployment plan
C M C D P Communication modem deployment cost
C M C M Communication modem maintenance cost
C M P H W Communication modem hardware price
C M P I n s T Communication modem installation price
C M P M Communication modem maintenance price
C M R T y p e Communication type rate
C M Q Communication modem quantity
C S C o v e r Communication modem per smart meter
D C U C o v e r DCU per smart meter
D C C O & M DCU operation and maintenance cost
D C U C D P DCU deployment cost
D C U P H W DCU hardware price
D C U P I n s T DCU installation price
D C U P M DCU maintenance price
D C U P O DCU operation price
D C U Q DCU quantity
gSmart meter type coefficient
GSmart meter type range
iAMI deployment type (1 = Single, 2 = hybrid)
IAMI deployment type range (I = 1 … 2)
jCommunication method type coefficient
JCommunication method range
O U R Overhead and underground distribution line and rate
rInstallation area type coefficient
RInstallation area range
R P C D P Repeater deployment cost
R P C M Repeater maintenance cost
R P P H W Repeater hardware price
R P P I n s T Repeater installation price
R P P M Repeater maintenance price
R P Q Repeater quantity
R P R DCU per repeater
S M C H & I Smart meter deployment cost
S M P H W Smart meter hardware price
S M P I n s T Smart meter installation price
S M Q Smart meter quantity
S M R Smart meter type rate
YDeployment year

References

  1. Mohassel, R.R.; Fung, A.; Mohammadi, F.; Raahemifar, K. A Survey on Advanced Metering Infrastructure. Int. J. Electr. Power Energy Syst. 2014, 63, 473–484. [Google Scholar] [CrossRef]
  2. Borenstein, S.; Jaske, M.; Rosenfeld, A. Dynamic Pricing, Advanced Metering, and Demand Response in Electricity Markets; Technical Report, CSEM WP 105; UCEI: Berkeley, CA, USA, 2002. [Google Scholar]
  3. U.S. Department of Energy Office of Electricity Delivery and Energy Reliability. Advanced Metering Infrastructure; National Energy Technology Laboratory: Pittsburgh, PA, USA, February 2008.
  4. LeMay, M.; Nell, R.; Gross, G.; Gunter, C.A. An integrated architecture for demand response communications and control. In Proceedings of the 41st Hawaii International Conference on System Sciences, Waikoloa, HI, USA, 7–9 January 2008; pp. 68–73. [Google Scholar]
  5. Uribe-Pérez, N.; Hernandez, L.; de la Vega, D.; Angulo, I. State of the Art and Trends Review of Smart Metering in Electricity Grids. Appl. Sci. 2016, 6, 68. [Google Scholar] [CrossRef]
  6. Commission Staff Working Document. Cost-Benefit Analyses & State of Play of Smart Metering Deployment in the EU-27. Available online: http://eur-lex.europa.eu/legal-content/EN/TXT/?uri=celex% (accessed on 13 August 2017).
  7. The Edison Foundation. Electric Company Smart Meter Deployments: Foundation for A Smart Grid; Institute for Electric Innovation: Washington, DC, USA, 2016. [Google Scholar]
  8. Research and Markets. China Smart Meter Industry Report, 2016–2020. Available online: https://www.researchandmarkets.com/research/2rnpqp/china_smart_meter (accessed on 13 August 2017).
  9. Korea Smart Grid Association (KSGA). Smart Grid Technology Trends Report; KSGA: Seoul, Korea, 2012. [Google Scholar]
  10. Cho, J.H. The Next Generation Metering System Development Status for High Voltage Customer on Smart Grid. J. Electr. World 2014, 1, 46–55. [Google Scholar]
  11. Power Systems Engineering Research Center. Communication Needs and Integration Options for AMI in the Smart Grid; Wichita State University: Wichita, KS, USA, 2012. [Google Scholar]
  12. Pirak, C.; Sangsuwan, T.; Buyairaksa, S. Recent Advances in Communication Technologies for Smart Grid Application: A Review. In Proceedings of the International Electrical Engineering Congress, Chonburi, Thiland, 19–21 March 2014. [Google Scholar]
  13. Ramírez, D.F.; Céspedes, S.; Becerra, C.; Lazo, C. Performance Evaluation of Future AMI Applications in Smart Grid Neighborhood Area Networks. Communication and Computing. In Proceedings of the 2015 IEEE Colombian Conference, Popayan, Colombia, 13–15 May 2015. [Google Scholar]
  14. Amarsingh, A.A.; Latchman, H.A.; Yang, D. Narrowband Power Line Communications: Enabling the Smart Grid. IEEE Potentials 2014, 33, 16–21. [Google Scholar] [CrossRef]
  15. Sivaneasan, B.; Kumar, K.N.; So, P.L.; Gunawan, E. A hybrid PLC-WIMAX based communication system for advanced metering infrastructure. In Proceedings of the 2012 Conference on Power & Energy (IPFC), Ho Chi Minh City, Vietnam, 12–14 December 2012; pp. 386–390. [Google Scholar]
  16. Olsen, R.G. Technical considerations for wideband powerline communication-a summary. In Proceedings of the Power Engineering Society Summer Meeting, Chicago, IL, USA, 21–25 July 2002; pp. 1186–1191. [Google Scholar]
  17. Mahmood, A.; Javaid, N.; Razzaq, S. A review of wireless communications for smart gird. Renew. Sustain. Energy Rev. 2015, 41, 248–260. [Google Scholar] [CrossRef]
  18. López, G.; Morenoa, J.I.; Amarís, H.; Salazar, F. Paving the Road toward Smart Grid through Large-Scale Advanced Metering Infrastructures. Electr. Power Syst. Res. 2015, 120, 194–205. [Google Scholar] [CrossRef]
  19. Andreadou, N.; Guardiola, M.O.; Fulli, G. Telecommunication Technologies for Smart Grid Projects with Focus on Smart Metering Applications. Energies 2016, 9, 375. [Google Scholar] [CrossRef]
  20. Lazaropoulos, A.G.; Cottis, P.G. Broadband transmission via underground medium-voltage power lines—Part I: Transmission characteristics. IEEE Trans. Power Del. 2010, 25, 2414–2424. [Google Scholar] [CrossRef]
  21. Lazaropoulos, A.G.; Cottis, P.G. Broadband transmission via underground medium-voltage power lines—Part II: Capacity. IEEE Trans. Power Del. 2010, 25, 2425–2434. [Google Scholar] [CrossRef]
  22. Eom, K.H.; Shin, J.H.; Lee, S.J. An analysis of characteristics of underground power line communication channel. J. Inst. Elect. Eng. Korea (IEEK) 2011, 48, 40–45. [Google Scholar]
  23. Hyun, D.H.; Choi, I.J.; Kang, C.-S.; Lee, Y.-H. The study of the signal propagation characteristics on 22.9 kV underground distribution cable. J. Korean Inst. Inform. Tech. (KIIT) 2006, 4, 33–39. [Google Scholar]
  24. Lee, S.J.; Shin, D.H.; Kim, Y.H.; Lee, J.J.; Um, K.H. An analysis and modeling of background noise on 22.9kV underground distribution cable for medium-voltage power line communication. J. Inst. Electron. Eng. Korea (IEEK) 2010, 33, 986–987. [Google Scholar]
  25. Kim, Y.H.; Lee, J.H.; Kim, K.H.; Lee, H.B.; Kim, S.C. A study on the power line communications for smart grid access network system. In Proceedings of the KICS Summer Conference, Jeju Island, Korea, 20–22 June 2011; pp. 354–355. [Google Scholar]
  26. Baek, J.M.; Ju, S.H.; Lim, Y.H.; Choi, M.S. Design and evaluation of BPLC-based meter reading network via underground MV line. In Proceedings of the Korean Institution of Power Electronics (KIPE) Fall Conference, Seoul, Korea, 13 November 2010; pp. 304–305. [Google Scholar]
  27. Yoo, H.; Yoon, K.S.; Kang, S.; Choi, I.; Park, B.; Kim, I.H.; Kim, W. Study on Channel Characteristics and Feasibility of Narrowband Power Line Communication Over Underground Low Voltage Power Line. J.-KICS 2013, 38, 874–884. [Google Scholar] [CrossRef]
  28. Kim, Y.S.; Kwon, T.K.; Seo, H.M.; Cho, J.W. An Implementation on the Wireless AMI System Using a National Wireless Communication Technique. In Proceedings of the Korean Institute of Communications and Information Sciences, Summer Comprehensive Conference, Jeju Island, Korea, 25–27 June 2014; pp. 750–751. [Google Scholar]
  29. ValuTech Solution Inc. Analysis of AMI Deployment Plan, Technology Choice and Client Benefits; Hydro Quebec: Montreal, QC, Canada, 2011. [Google Scholar]
  30. Li, Z.; Wang, Z.; Tournier, J.C.; Peterson, W.; Li, W.; Wang, Y. A Unified Solution for Advanced Metering Infrastructure Integration with Distribution Management System. Smart Grid Communications. In Proceedings of the 2010 First IEEE International Conference, Gaithersburg, MD, USA, 4–6 October 2010; pp. 566–671. [Google Scholar]
  31. Sui, H.; Wang, H.; Lu, M.S.; Lee, W.J. An AMI system for the deregulated electricity markets. IEEE Trans. Ind. Appl. 2009, 45, 2104–2108. [Google Scholar]
  32. Petruševski, I.; Živanović, M.; Rakić, A.; Popović, I. Novel AMI Architecture for Real-Time Smart Metering. In Proceedings of the 22nd Telecommunications Forum Telfor, Belgrade, Serbia, 25–27 November 2014; pp. 664–667. [Google Scholar]
  33. Ameren Illinois. Advanced Metering Infrastructure (AMI) Cost/Benefit Analysis; Ameren: St. Louis, MO, USA, 2012. [Google Scholar]
  34. Vincenzo, G.; Ijeoma, O.; Gianluca, F.; Manuel, S.J.; Constantina, F. Guidelines for Cost Benefit Analysis of Smart Metering Deployment; Joint Research Center, Ed.; JRC Scientific and Technical Research, EU: Brussels, Belgium, 2012. [Google Scholar]
  35. Reji, K.P.; Rupendra, B.; Hem, T. AMI Rollout Strategy and Cost-Benefit Analysis for India; India Smart Grid Forum: Delhi, India, 2016; pp. 1–24. [Google Scholar]
  36. KEPCO. Middle and Long-Term Intelligent Power Metering Infrastructure (AMI) Deployment Plan; KEPCO: Naju, Korea, 2013. [Google Scholar]
  37. KEPCO. AMR Comprehensive Promotion Strategies Report; KEPCO: Naju, Korea, 2009. [Google Scholar]
  38. Gyeonggi Research Institute. Efficient Propulsion Plan. of Overhead Line Underground Project in Gyeonggi.-Do; Gyeonggi Research Institute: Suwon, Korea, 2007. [Google Scholar]
  39. KETEP. Development of AMI System Using Hybrid. and Composite Network (RFP); KETEP: Seoul, Korea, 2014. [Google Scholar]
  40. Kim, Y.S.; Oh, H.M.; Choi, S.S. A Research on the Traffic of Smart Grid Communication Network Architecture based on Smart Meters. In Proceedings of the Korean Institute of Communications and Information Sciences, Summer Comprehensive Conference, Jeju Island, Korea, 24–26 June 2015; pp. 650–651. [Google Scholar]
Figure 1. Hybrid Advanced Metering Infrastructure Structure.
Figure 1. Hybrid Advanced Metering Infrastructure Structure.
Energies 10 01308 g001
Figure 2. Hybrid AMI System Model.
Figure 2. Hybrid AMI System Model.
Energies 10 01308 g002
Figure 3. System Dynamics Modeling for Hybrid AMI.
Figure 3. System Dynamics Modeling for Hybrid AMI.
Energies 10 01308 g003
Figure 4. Communications Modem and DCU Cost Curve: (a) Communications Modem Cost Curve; (b) DCU Cost Curve.
Figure 4. Communications Modem and DCU Cost Curve: (a) Communications Modem Cost Curve; (b) DCU Cost Curve.
Energies 10 01308 g004
Figure 5. Costs by Deployment Type and Installation Item (C/N: Communication Networks).
Figure 5. Costs by Deployment Type and Installation Item (C/N: Communication Networks).
Energies 10 01308 g005
Figure 6. Comparison of Installation and O&M Cost Results per Deployment Method (P: PLC-Only, H: Hybrid).
Figure 6. Comparison of Installation and O&M Cost Results per Deployment Method (P: PLC-Only, H: Hybrid).
Energies 10 01308 g006
Figure 7. Comparison of DCU and Repeater Cost Results per Deployment Method (P: PLC-Only, H: Hybrid).
Figure 7. Comparison of DCU and Repeater Cost Results per Deployment Method (P: PLC-Only, H: Hybrid).
Energies 10 01308 g007
Figure 8. Cost per Consumer by Deployment Method.
Figure 8. Cost per Consumer by Deployment Method.
Energies 10 01308 g008
Figure 9. Sensitivity Analysis Result per Deployment Method.
Figure 9. Sensitivity Analysis Result per Deployment Method.
Energies 10 01308 g009
Table 1. AMI Deployment Scenario.
Table 1. AMI Deployment Scenario.
AMI Deployment Scenario
YearPlan (10K)Accumulation (10K)
2016200.0200.0
2017230.0430.0
2018250.0680.0
2019257.5937.5
2020250.01187.5
2021250.01437.5
2022330.01767.5
2023364.02131.5
Table 2. Total Deployment Cost Result by Deployment Type (Billion KRW).
Table 2. Total Deployment Cost Result by Deployment Type (Billion KRW).
YearAMI Deployment Scenario Cost
PLC-OnlyHybridReduction Ratio (%)
2016206.2198.23.9
2017446.6427.64.3
2018713.4681.14.5
2019994.8947.84.7
20201277.61215.34.9
20211568.81490.35.0
20221947.51847.55.1
20232370.82246.55.2
20242474.32343.15.3
20252578.82440.65.4
20262684.22539.15.4
20272790.62638.45.5
20282898.02738.65.5
20293006.32839.65.5
20303115.52941.65.6
Table 3. Comparison Results of Total Deployment Cost and Smart Meter Cost (Billion KRW).
Table 3. Comparison Results of Total Deployment Cost and Smart Meter Cost (Billion KRW).
YearDeployment Cost (Smart Meter)
Smart MeterCost Percentage
PLC-Only (%)Hybrid (%)
2016122.059.261.6
2017262.358.761.3
2018414.858.160.9
2019571.657.560.3
2020724.156.759.6
2021876.655.958.8
20221077.955.358.3
20231299.954.857.9
20241316.153.256.2
20251332.351.754.6
20261348.650.253.1
20271364.848.951.7
20281381.047.750.4
20291397.246.549.2
20301413.445.448.0
Table 4. Communications Network Cost per Deployment Type (Billion KRW).
Table 4. Communications Network Cost per Deployment Type (Billion KRW).
YearCommunications Network Deployment Cost
PLC-OnlyHybridReduction Cost Ratio (%)
201684.276.29.5
2017184.3165.310.3
2018298.6266.310.8
2019423.3376.211.1
2020553.6491.211.3
2021692.2613.711.3
2022869.6769.711.5
20231070.9946.611.6
20241158.21027.011.3
20251246.41108.311.1
20261335.71190.510.9
20271425.81273.610.7
20281517.01357.610.5
20291609.11442.410.4
20301702.11528.210.2
Table 5. Comparison of Installation Cost Result per Deployment Method (Billion KRW).
Table 5. Comparison of Installation Cost Result per Deployment Method (Billion KRW).
YearInstallation Cost
PLC-OnlyHybridReduction
CostRatio (%)
201684.276.28.09.5
2017177.1158.518.610.5
2018275.7245.030.711.1
2019375.7332.143.611.6
2020472.1415.556.612.0
2021567.7497.969.812.3
2022692.9605.487.512.6
2023830.1722.8107.312.9
2024840.2731.3108.913.0
2025850.2739.9110.313.0
2026860.2748.4111.813.0
2027870.2757.0113.213.0
2028880.2765.5114.713.0
2029890.2774.1116.113.0
2030900.2782.6117.613.1
Table 6. Comparison of O&M Cost Result per Deployment Method (Billion KRW).
Table 6. Comparison of O&M Cost Result per Deployment Method (Billion KRW).
YearO&M Cost
PLC-OnlyHybridReduction
CostRatio (%)
2016----
20177.36.70.68.2
201822.821.21.67.0
201947.544.23.36.9
202081.575.85.77.0
2021124.5115.88.77.0
2022176.7164.212.57.1
2023240.7223.816.97.0
2024318.0295.722.37.0
2025396.3368.427.97.0
2026475.5442.133.47.0
2027555.7516.639.17.0
2028636.8592.144.77.0
2029718.9668.450.57.0
2030802.0745.656.47.0
Table 7. Comparison of DCU Cost Result per Deployment Method.
Table 7. Comparison of DCU Cost Result per Deployment Method.
YearDCU Deployment Cost
PLC-OnlyHybrid (DCU+RP)Reduction
CostRatio (%)
201658.143.514.625.1
2017126.694.931.725.0
2018203.0152.250.825.0
2019283.8212.771.125.1
2020365.1273.691.525.1
2021448.8336.3112.525.1
2022558.0418.0140.025.1
2023680.2509.5170.725.1
2024708.7530.6178.125.1
2025737.5551.9185.625.2
2026766.4573.4193.025.2
2027795.7595.1200.625.2
2028825.2617.0208.225.2
2029855.0639.1215.925.3
2030885.0661.4223.625.3
Table 8. Comparison of DCU and Repeater Cost Results for Hybrid AMI.
Table 8. Comparison of DCU and Repeater Cost Results for Hybrid AMI.
YearDCU and Repeater Deployment Cost
DCURepeaterRatio (%)
201640.62.97.1
201788.76.27.0
2018142.39.97.0
2019198.913.86.9
2020255.917.76.9
2021314.621.76.9
2022391.126.96.9
2023476.732.86.9
2024496.733.96.8
2025516.835.16.8
2026537.136.36.8
2027557.637.56.7
2028578.338.76.7
2029599.239.96.7
2030620.241.26.6
Table 9. Comparison of Communications Modem Cost Results per Deployment Method.
Table 9. Comparison of Communications Modem Cost Results per Deployment Method.
YearCommunications Modem Deployment Cost
PLC-OnlyHybridReduction
CostRatio (%)
201626.232.7−6.5−24.8
201757.770.4−12.7−22.0
201895.6114.1−18.5−19.4
2019139.4163.5−24.1−17.3
2020188.4217.6−29.2−15.4
2021243.4277.4−34.0−14.0
2022311.5351.7−40.2−12.9
2023390.6437.1−46.5−11.9
2024449.5496.4−46.9−10.4
2025509.0556.4−47.4−9.3
2026569.2617.1−47.9−8.4
2027630.1678.5−48.4−7.7
2028691.8740.5−48.7−7.0
2029754.1803.3−49.2−6.5
2030817.1866.8−49.7−6.1
Table 10. Cost per Consumer by Deployment Method.
Table 10. Cost per Consumer by Deployment Method.
DivisionDeployment Cost per Consumer (KRW)
TotalCommunications
TotalInstallationO&M
PLC-Only135,00073,00039,00035,000
Hybrid127,00066,00034,00032,000
Reduction Ratio (%)5.99.616.38.6
Table 11. Sensitivity Analysis Setup.
Table 11. Sensitivity Analysis Setup.
ScenarioContentConfiguration
Smart Meter per DCURepeater per DCU
PLC-OnlyLower Limit20-
Upper Limit150-
HybridLower Limit1501
Upper Limit4507.5
Table 12. Sensitivity Analysis Result per Deployment Method.
Table 12. Sensitivity Analysis Result per Deployment Method.
ScenarioPercentile
525507595
PLC-Only16471694173717871864
Hybrid15091518152615381554

Share and Cite

MDPI and ACS Style

Park, S.-W.; Son, S.-Y. Cost Analysis for a Hybrid Advanced Metering Infrastructure in Korea. Energies 2017, 10, 1308. https://doi.org/10.3390/en10091308

AMA Style

Park S-W, Son S-Y. Cost Analysis for a Hybrid Advanced Metering Infrastructure in Korea. Energies. 2017; 10(9):1308. https://doi.org/10.3390/en10091308

Chicago/Turabian Style

Park, Sung-Won, and Sung-Yong Son. 2017. "Cost Analysis for a Hybrid Advanced Metering Infrastructure in Korea" Energies 10, no. 9: 1308. https://doi.org/10.3390/en10091308

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop