Next Article in Journal
Towards a Wireless and Low-Power Infrastructure for Representing Information Based on E-Paper Displays
Previous Article in Journal
Sustaining Regional Advantages in Manufacturing: Skill Accumulation of Rural–Urban Migrant Workers in the Coastal Area of China
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Development of a Prototype Model to Establish an Economic Earthwork Plan that Includes the Selection of a Dump Site/Borrow Pit

1
ITM Corporation, Seoul 06056, Korea
2
School of Architectural Engineering, Hongik University, Sejong 30016, Korea
*
Author to whom correspondence should be addressed.
Sustainability 2017, 9(1), 74; https://doi.org/10.3390/su9010074
Submission received: 2 December 2016 / Revised: 1 January 2017 / Accepted: 4 January 2017 / Published: 7 January 2017
(This article belongs to the Section Sustainable Engineering and Science)

Abstract

:
Earthwork in road construction projects is the major activity that accounts for about 20%–30% of the total construction cost, and the internal/external hauling plan is the key factor for determining the successful completion of the project. However, the hauling plan at the site, which includes the selection of the dump site and borrow pit, is usually determined by the site manager’s subjective and empirical discretion alone. Therefore, this study has developed a prototype model that provides the optimal internal/external hauling plan. It includes the determination of the most economical dump sites and borrow pits (location and number) among other candidate sites as well. The transshipment problem theory is incorporated into the optimized algorithm with the consideration of various factors affecting earthwork cost. Direct costs from an optimized transport based on an existing model against another from this model were compared to prove its feasibility. As a result, the reduction of earthwork cost including the dump site/borrow pits reached 4%–8%. This result implies that this prototype model would also be useful in reducing both the earthwork cost and the occurrence of exhaust gas from earthwork equipment by providing optimized transportation paths.

1. Introduction

1.1. Background and Objective

Earthwork is carried out by transferring large volumes of soil to create a balance between the existing elevation and the design elevation at the site; its cost accounts for 20%–30% of the total construction cost [1]. Hence, establishing the rational and appropriate soil hauling plan at an early stage is all the more important. However, the internal/external soil hauling plan at the site including the selection of the dump site and borrow pit is heavily dependent on site manager’s subjective and empirical discretion alone [2].
The rational hauling plan proposed in previous studies is the route with the lowest value as a result of simply multiplying the hauling distance by hauling volume [3,4,5]. The studies above are based on a transportation model in a bid to improve the transportation efficiency. The study has been developed to those on a soil hauling method that considers a number of factors (such as worker’s resource, budget, indirect cost) based on transportation theory, which further influences road construction [6,7]. The importance of the hauling plan including the dump site/borrow pit failed to be considered in such studies because they only focused on certain influential factors related to road construction [8].
When spoil cannot be accommodated internally at the site, rational determination on the dump site/borrow pit outside the site will be made after reviewing many alternatives. However, it is difficult to come up with a solution that can accommodate internal hauling as well as the hauling to the dump site or borrow pit outside the construction site from an economical standpoint. Since the earthwork is influenced by many factors including cutting, banking and hauling, the site condition of a dump site/borrow pit (location, capacity, and fees), productivity of the earthwork equipment, type of soil, etc.: These various factors must be considered in comprehensive ways for the optimized earthwork plan.
Thus, this study is aimed at developing a prototype model, based on petroleum transportation and the allocation model, that is able to come up with an optimal internal/external hauling plan that is the most economical and sustainable among other candidate sites. This model includes an optimized objective function which considers various influential factors of earthwork as aforementioned and provides the most economical internal hauling plan not only at the site, but also its destination outside the site as well as information on the location of the dump site/borrow pit, and finally, cost.

1.2. Scope of Study and Methodology

The scope of this study focuses on earthwork and the case studies are performed with the prototype model for the site requiring a dump site/borrow pit. This prototype model contains an optimized objective function considering various factors such as the hauling speed inside and outside the site, the location and capacity of dump site and borrow pit, its cost for equipment (dump truck, excavator, loader) the equipment productivity, the type of soil and the measures for an economical soil hauling plan.
Implementation procedure and the model’s method of development are as Figure 1.
An algorithm is developed by applying appropriate methodology and considering influential factors that are included in the entire process of the soil hauling plan in a bid to develop the prototype model that incorporates a hauling plan (including the selection of dump site/borrow pit) for earthwork inside and outside the site. Influential factors will include total earthwork volume, total length, productivity of equipment, recyclable earthwork volume, hauling distance and speed, which the prototype to be developed will all include. The internal and external earthwork hauling plan and dump site/borrow pit selection will be produced as an outcome of the prototype model. Moreover, the outcome of the model and road constriction will be compared to each other through the application of case studies and their verifications, thereby supporting the conclusion from the study.

2. Theoretical Review

2.1. Trend of Related Studies

Previous studies with earthwork mainly focus on how to haul the soil in an efficient and economic way. This study will address the following: (1) Optimal method considering work volume and distance; (2) optimal hauling method considering the volume to be transported outside the site considering the dump site/borrow pit; (3) optimum method based on nonlinear earthwork considering many influential factors in the process of earthwork.
The study on optimal hauling started in earnest by Mayer [3] and Easa [4,5] which focused on shortening the hauling distance at the site so as to haul excavated and banking soil over reduced distance. These studies paved the foundation to optimize the earthwork volume in various ways.
Son [9] proposed the alternative to minimize the volume for hauling by developing the mathematical model that determines the direction to haul the excavated soil from the site and Ji [10] developed the spoil hauling model that considers work sequence using a binary integer programming. Such studies seem to be proper in seeking an alternative to transport the earthwork volume in a balanced way, but are considered inappropriate in developing a hauling plan with a plural number of undetermined dump sites or borrow pits for a large road construction project.
Park [8] developed a model to determine the dump site by predicting the carbon emission of the site through network analysis from an environmental point of view. In selecting the candidate sites, distance, approach route, and land acquisition cost were considered thus, making the study more reliable.
Hassaneen [11] proposed a detailed model for assessing the energy consumption and CO2 emissions of selected hauling fleets by using an existing hauling planning program such as DynaRoad. In this research, this hauling planning program uses data on the productivity of selected haulers and the amount of materials to be hauled during cutting, filling, borrowing, and disposal operations and develops an earthwork schedule. However, this program does not focus on the selection of the most economical number and locations of borrow pits and spoil banks among multiple potential places.
Such a model is intended to reduce the carbon emission which is important to environmental conservation. Although the model is used for the site generating the spoil, the transport within the site was yet to be considered.
Moselhi [6] conducted a study to minimize the earthwork volume and developed the model for decision-making by the worker to effectively carry out the earthwork in a practical way considering various factors that may influence spoil-hauling such as a worker’s resource, budget, soil characteristics, indirect cost and equipment characteristics. The model however, has a limit in use for hauling within the site because nonlinear programming which is rather more complex was used instead of linear programming in the process of calculating many factors. Nassar [7] minimized the spoil hauling volume by applying the work sequence which is not considered in previous studies to the model, making use of linear programming. The result of using linear programming is not necessarily superior to the value from nonlinear programming, but it could produce more intuitive output in dealing with the problem as well as reduce the probability of distortion in the optimization process.
In conclusion, previous studies have shown that it is more important to establish rational and cost efficient spoil hauling plans in road constriction. Rather than focusing only on internal banking/cutting volume, it is necessary to consider both the internal and external hauling with several candidate dump sites and borrow pits and provide the information necessary for establishing the optimal hauling plan. Therefore, making a more practical hauling model applied by linear programming that considers various influential factors such as hauling speed, equipment capacity and quantity, type of soil, work efficiency and the capacity of a dump site and borrow pit must be attempted.

2.2. Transshipment Transportation Model Theory

The transportation model was developed in a bid to transport the product or service from multi suppliers to multi destinations. A prototype model was developed using a transshipment transportation model for establishing an optimized spoil hauling plan including the internal/external hauling plan and selection of the dump site/borrow pit.
A transshipment transportation model has the node between the supply source and destination such as a site entrance which is considered a phasing distribution. Figure 2 indicates the combination of the routes from the supply source (cutting site) to the destination (banking site) and a multi supply source ( S 1 , S 2 ,   ,   S m ) is linked to multi destinations ( D 1 ,   D 2 ,   ,   D n ) via interim points ( T 1 ,   T 2 ,   ) .
MinZ = DST 11 x 11 + DST 12 x 12 + DST 21 x 21 + DST 22 x 22 + DST 31 x 31 + DST 32 x 32   + DTD 11 y 11 + DTD 12 y 12 + DTD 13 y 13 + DTD 14 y 14 + DTD 21 y 21   + DTD 22 y 22 + DTD 23 y 23 + DTD 24 y 24
st .   x 11 + x 12   S 1
x 21 + x 22   S 2
x 31 + x 32   S 3
x 11 + x 21 + x 31 =   y 11 + y 12 + y 13 + y 14
x 12 + x 22 + x 32 =   y 21 + y 22 + y 23 + y 24
y 11 + y 21   D 1
y 12 + y 22   D 2
y 13 + y 23   D 3
y 14 + y 24   D 4
x i j 0   ,   y i j 0 ;   i ,   j = 1 ,   2 ,   3 ,   4
where Z is object function (hauling distance, minimum hauling volume), Si is the volume that could be supplied from supply source (m3), Dj is the volume that could be accommodated at the destination (m3). x i j is the volume from the supply source to interim point ( T 1 ,   T 2 ) (m3); y i j is the volume from interim point ( T 1 ,   T 2 ) to the destination (m3). DSTij is hauling distance from Si toTj (m), DTDij is hauling distance from Ti to Dj (m).
Equation (1) is the mathematical model of transshipment transportation and its constraint conditions are that: (1) the volume from the supply source to the interim point will be equal to or less than the maximum volume that can be supplied from the supply source; (2) the interim point serves as the passage for transportation and thus the volume from the supply source (cutting site) shall be all sent to the destination (banking site); (3) the volume required by the destination (banking site) shall be transported from the interim point and thus, the constraint condition to the destination is required. Viewing such constraint conditions, the equation which serves as a base for the spoil hauling plan was established. Using the conditional equation of transshipment transportation, the objective function classified based on the interim point was established to be the total cost of internal hauling and external hauling (including information on dump site, borrow pit). The total cost of internal and external hauling can be calculated in consideration of the data on productivity of equipment and fees for the candidate dump site/borrow pit.

3. Development of Prototype Model for Establishing Optimal Spoil Hauling Plan

3.1. Algorithm for Optimizing Earthwork Hauling Plan

Earthwork is generally divided into excavation, loading, hauling, banking, tamping and embankment laying. Earthwork hauling is then classified into no hauling, hauling by dozer, or hauling by dump truck. Figure 3 is the earthwork hauling plan algorithm showing the process of determining the internal and external hauling plan and the determination of a dump site/borrow pit. It is necessary to analyze the earthwork data for road construction. At this stage, analysis of a specific section is carried out using a drawing and the earthwork volume sheet as well as the estimate of cutting/banking volume shall be completed drawing data. When the estimate is completed, no-charge hauling is performed at the boundary after dividing the section by 20 m in accordance with the design guideline for national road construction. Afterwards, the residual cutting/banking volume shall be re-calculated for dozing and the section will be divided by 60 m considering the dozer’s work efficiency to establish ta hauling plan by a dozer. Hauling by a dozer is performed at the boundary between banking and cutting section after dividing the section by 60 m, but this volume is variable depending on the base for division. Thus, it is classified into 3 alternatives based on a base for division by 60 m as (① STA. 0 + 000–STA. 0 + 060; ② STA. 0 + 000–STA. 0 + 020, STA. 0 + 020–STA. 0 + 080; ③ STA. 0 + 000–STA. 0 + 040, STA. 0 + 040–STA. 0 + 100) and thus, the hauling optimization process is performed.
Hauling over 60 m shall be planned using the dump truck instead of the dozer. Heavy equipment used for the hauling by a dump truck includes the excavator, loader and dump truck; information necessary for each equipment operation shall be input. For optimization, the constraint condition of the equipment depending on the site condition shall also be input. Constraint conditions include capacity by equipment, minimum hourly cost considering the Q value (equipment productivity data (m3/h)), the minimum value of volume for hauling, and the limit in maximum capacity by section. After finishing such a process, optimization of the earthwork hauling plan uses the value-seeking program. Then, the objective function concludes the minimum value of total cost considering the data on the dump site/borrow pit. As a result of optimization, internal/external hauling cost and the optimal dump site/borrow pit are determined. Thus, the optimum hauling prototype model is developed through the earthwork volume algorithm.

3.2. Influential Factors and Objective Function of Optimal Process Model for Earthwork Hauling Plan

3.2.1. Influential Factors

The earthwork optimization process model includes hauling the distance by section, the equipment’s cycle time, hauling volume, travel speed, earthwork equipment’s productivity data, distance to dump site/borrow pit and fees for use. The transshipment transportation theory-based optimization objective function value was set as the total construction cost (expenses of dump truck, excavator, loader and fees using for dump site/borrow pit) in consideration of the Design Guideline for National Road Construction and the Price Information Gazette. In addition, other influencing factors, which include on-site environmental and physical conditions such as crusher, other earthwork equipment, any limited earthwork planning conditions, and weather conditions, can be added if these factors affect to estimate the earthwork costs.
The hauling volume within the site, hauling to/from the dump site/borrow pit which is considered external hauling and the determination of a dump site/borrow pit can be confirmed through the optimization mode.
Table 1 below includes influential factors included in the optimization hauling plan process model that contains the recyclable ratio of soil, volumetric conversion factor, work efficiency, equipment’s cycle time, and vehicle speed at site when loaded and when empty, which are classified as follows.

3.2.2. Objective Function

The sum of the hauling cost and fees of a dump site/borrow pit among earthwork cost is set as the objective function in this study. The objective function includes productivity of earthwork equipment (dump truck, excavator, loader) hauling distance at the site, hauling distance to dump site/borrow pit and the fees for dump site/borrow pit. Equipment productivity data includes hourly production, capacity of dump truck, volumetric conversion factor, work efficiency; a cycle time and travel speed at the site and travel time to a dump site/borrow pit are also included in an objective function. A more specific explanation is in Equations (2)–(6) [12].
Equation (2) below indicates the hourly capacity of the dump truck which is necessary to optimize the hauling plan in consideration of labor and expense of the dump truck as well as the material and hauling volume.
Q =   60   × q × f × E Cm
where Q is hourly capacity of dump truck (m3/h), q is loading capacity of dump truck in bulk (m3), f is volumetric conversion factor, E is work efficiency (dump truck: 0.9), Cm is a cycle time (m).
Equation (3) below indicates the hourly capacity of a loader. The cost of hauling by a loader is estimated in consideration of labor cost, material cost, expenses and hauling volume.
Q =   3600   × q × K × f × E Cm
where Q is loader’s hourly capacity (m3/h), q is bucket capacity (m3), K is bucket coefficient, f is volumetric conversion factor, E is work efficiency, Cm is a cycle time (s).
Equation (4) below indicates the hourly capacity of an excavator. As the equipment to haul the blasted spoil, the cost of hauling by an excavator is estimated in consideration of the labor cost, material cost, expenses and hauling volume.
Q =   3600   × q × K × f × E Cm
where Q is excavator’s hourly capacity (m3/h), q is ripper or bucket capacity (m3), K is ripper or bucker coefficient, f is volumetric conversion factor, E is work efficiency, Cm is a cycle time (s).
Based on an equation indicating the hourly capacity of equipment, the type of soil (soil, ripping rock, blasting rock), the fees for a dump site/borrow pit and the sum of direct construction cost are set as an objective function and thus, the earthwork hauling plan optimization model is developed. Using this model, the most cost efficient dump site/borrow pit and hauling route can be determined. Equation (5) is for the labor cost among the equipment expense of the dump truck for internal hauling. Labor costs in the hauling costs by dump trucks for the section can be estimated in a way by multiplying hourly labor costs of dump trucks by the hourly dump truck capacity.
SDL ( Soil ) =   SDL ÷ 60   × q × f × E ( t 1 + SHD V 1 + SHD V 2 + t 3 + t 4 + t 5 ) × Q i
where, SDL (on-Site Dump Labor cost) is hourly dump truck labor cost at site ($/h), SHD (on-Site Haul Distance) is hauling distance at the site (m), q is the capacity per load on dump truck without compaction (m3), f is volumetric conversion factor, E is work efficiency, V1 is a mean travel speed at the site when loaded (km/h), V2 is a mean travel speed at the site when empty (km/h ), t1 is loading time of dump truck (m), t3 is dumping time (m), t4 is the time between arrival at loading point and start of loading (m), t5 is the time to install and removal of the load box cover (m), Q i is earthwork volume at the section (within 60 m) (m3).
Equation (6) below is intended to estimate the labor costs of dump truck expenses for hauling spoil outside the site. The travel speed to a dump site/borrow pit (V3, V4) and hauling distance (OHD) can be input as a variable and from that, the labor cost of the dump truck expense can be obtained.
ODL ( Soil ) =   ODL ÷ 60   × q × f × E ( t 1 + OHD V 1 + OHD V 2 + OHD V 3 + OHD V 4 + t 3 + t 4 + t 5 ) × Q i
where, ODL (Off-site Dump Labor Cost) hourly labor cost of dump truck for hauling outside the site ($/h) and OHD (Off-site Haul Distance) is hauling distance outside the site (m), q is the capacity per load on dump truck without compaction (m3), f is volumetric conversion factor, E is work efficiency, V1 is a mean travel speed at the site when loaded (km/h), V2 is a mean travel speed at the site when empty (km/h), V3 is a mean travel speed outside the site when loaded (km/h), V4 is a mean travel speed outside the site when empty (km/h), t1 is loading time of dump truck (m), t3 is dumping time (m), t4 is the time between arrival at loading point and start of loading (m), t5 is the time to install and removal of the load box cover (m), Q i is earthwork volume at the section (within 60 m) (m3).
Using such equations, the objective function includes the least sum of internal and external labor costs, material costs and expenses of dump truck, loader and excavator and the fees for a dump site/borrow pit. A dump site/borrow pit shall be able to accommodate the excavated spoil or required spoil because the prototype model is developed based on a linear program. This model indicates the most economical earthwork hauling cost, hauling route by section, and designation of the dump site/borrow pit.
Figure 4 shows the objective function and influential factors used in the prototype model. The objective function is the minimal sum of internal and external labor cost, material cost and expenses of dump truck, loader and excavator and the fees for a dump site/borrow pit. As aforementioned, each of these 4 elements includes the travel speed within the site and outside the site, hourly capacity, type of soil, work volume and work efficiency. The sum of each of the 4 elements has the result value in cost and selects the optimal alternative among several other candidate dump sites/borrow pits.
The solver of company F was used in obtaining the optimum solution of this objective function. Figure 5 shows an input window such as Objective, Variables, and Constraints to drive the solver. When implementing the solver using a linear program, the value considering the cost efficiency is obtained. When the capacity is available by a candidate dump site/borrow pit, it may be set as a constraint condition. Because of the characteristic of a solver, the result of solution-seeking at the minimum cost can only be identified with the result value.

3.3. Development of Prototype Model for Earthwork Hauling Plan

To explain the Spread Sheet-based optimal prototype model, the earthwork volume optimization process is hereby introduced with this case study. At earthwork volume confirmation and division stage as the initial stage for the earthwork hauling plan prototype model, cutting and banking volume are estimated with the earthwork volume curve after dividing the entire road work by 20 m. Based on this, no-charge hauling is carried out within 20 m and then hauling by a dozer is carried out at a 60 m section.
Figure 6 (corresponding to ⓐ and ⓑ in Figure 3) shows the no-charge hauling when cutting (spoil) 48 m3 and banking 272 m3 are at the same location as ① and as ② in Figure 6, cutting 48 m3 is for no-charge hauling. When no-charge hauling is done, 224 m3 of banking only will remain at STA. 0 + 12. After applying such no-charge hauling to the entire section, the volume that still remains within 20 m shall be hauled by a dozer after dividing by 60 m.
Such a division by 60 m is in accordance with the guideline for the design practice for road construction in which division by 60 m is said to be the most effective when hauled by dozer. However, dividing by 60 m is dependent on a manager’s discretion considering the site condition and its equipment capacity. In this study, the data divided by 20 m according to earthwork volume table is divided into 3 kinds as Alt (1) STA. 0 + 000–STA. 0 + 060; (2) STA. 0 + 000–STA. 0 + 020, STA. 0 + 020–STA. 0 + 080 and (3) STA. 0 + 000–STA. 0 + 040, STA. 0 + 040–STA. 0 + 100 and then by 60 m before an optimizing earthwork hauling plan.
As ③, ④ and ⑤ in Figure 7 (corresponding to ⓒ in Figure 3), the hauling volume by dozer varies depending on an alternative for division by 60 m. When cutting and banking volume exist together within a 60 m section, hauling by a dozer is carried out.
The section is divided by 60 m and the central distance of the section is based on a central line of the length by section (ex, central distance of C1section is 0.03 km(STA. 0 + 00–STA. 0 + 06) where the central distance of F2 section is 0.09 km (STA. 0 + 06 – STA. 0 + 12). When it comes to candidate dump site 2, 0.3 km means the entrance/exit of the site is at STA. 0 + 300 and candidate dump site 2 is 1 km away from STA. 0 + 300 (entrance/exit of the sit). When it comes to candidate dump site 1, candidate dump site 1 is 0.9 km away from STA. 0 + 000.
Figure 8 (corresponding to ⓓ in Figure 3) is the earthwork volume table for developing the earthwork hauling plan optimization process model, showing soil, ripping rock, blasting rock, banking volume and the distance by section. For instance, section distance of C1 is 0.06 km with cutting volume (soil) 16 m3 and section distance of F2 is 0.06 km with banking volume 72 m3. In this Study, 2 candidate dump sites are assumed to be available and the earthwork hauling plan optimization prototype model considering hauling distance (ex, 0.6 km between C1 and F11), hauling volume, and cost is fully demonstrated.
The whole construction site is at STA. 0 + 000–STA. 0 + 660 (total length 0.6 km) and candidate dump site 1 is assumed to be 0.9 km away from STA. 0 + 00 and candidate dump site 2 is assumed to be 1 km away from STA. 0 + 30. Figure 9 below shows hauling distance by section. For instance, distance from C1 to candidate dump site 1 is 0.93 km and distance between C1 and candidate dump site 2 is 1.27 km.
Figure 10 (corresponding to ⓔ in Figure 3) is the optimization result value of Study Model which summarizes the hauling volume between sections and the sum of the construction cost (cost for excavator, dozer and dump truck, fees for dump site/borrow pit) and hauling by section. The result value of the objective function is the minimum value of the sum including expenses relating to hauling by a dump truck and fees for a dump site/borrow pit in Figure 8.
With a result value obtainable from this case study, the earthwork hauling plan by section (including C1→dump site 1, C8→F11), the hauling to dump site, and the cost for hauling by excavator, dozer and dump truck can be checked.
When it comes to candidate dump site 1, the spoil disposal cost is estimated at $4.08/m3 to $4.25/m3. Parts of section (C1, C4, C5) to dump site 1 have shorter hauling sections than dump site 2 and parts of dump site 2 (C8, C9) have shorter hauling distances than dump site 1.
As a result of seeking the solution in this case study, a hauling plan to dump site 1 is more rational in terms of cost efficiency than dump site 2. Blasting spoil in C8 is determined to use dump site 1 instead of dump site 2 which is nearer from the site, because spoil disposal cost (dump site 1: $4.08/m3, dump site 2: $4.25/m3) and dump truck cost of dump site 1 are lower than dump site 2, which is closer from the site. Yet, when the cost is similar, dump site 2 which is closer from the site is more favorable. If a situation arises where the capacity is limited, a plural number of dump sites will be designated to maximize the capacity.

4. Case Studies

Two domestic road construction sites were selected for case studies to validate the applicability of the proposed model developed in this research study. In the case study 1, the amount of filling material was larger than the one of cutting. On the other hand, in the case study 2, the amount of cutting material was larger than the one of filling. The cost of earthwork including equipment expenses and the fees for a dump site/borrow pit will be compared to the method proposed in the preexisting transportation theory.

4.1. Case Study 1

Case Study 1 is of domestic construction site A requiring spoil as much as 246,281 m3. The recycling rate considering site requirement is applied as general soil 70%, ripping rock 100% and blasting rock 100%. The total length is 5.13 km and its width is 20 m, which is the average scale among road construction projects and 5 dump sites were selected using MOLIT-provided Earth Information Sharing System [13].
Figure 11 shows 5 candidate dump sites and the locations and fees are as follows: In case of dump site 1, $5.10/m3, 8100 m away from STA. 0; dump site 2, $5.35/m3, 9500 m away from STA. 0. Dump site 3, $5.94/m3, 4800m away STA. 5 + 160; dump site 4, $5.10/m3, 10,500 m away from STA. 3 + 200. Dump site 5, $4.25/m3, 12,000 m away from STA. 3 + 200. As aforementioned in Section 3.3 optimization was carried out with 3 alternatives by applying a 60 m-division method. The average travel speed of a dump truck at a site is 20 km/h when loaded and 25 km/h when empty; beyond the site the speed is 30 km/h when loaded and 35 km/h when empty.
Figure 12 shows the result value of the optimal solution (hauling route, volume, dump site) of earthwork hauled by a section obtained by linear programming using Microsoft-Excel and Solver (Frontline System Inc., Incline Village, NV, USA) after imputing each requirement. The result value obtained from this optimized model includes: (1) Determination of dump site; (2) Equipment expense of the project (direct cost of excavator, loader and dump truck); and (3) Hauling route. As a result of seeking the solution through the Solve, candidate dump site 1 was selected among 5 candidate sites. Though the fee of dump site 1 is not the lowest, it is considered to be the most economical when considering all of the influential factors. Thus, the internal earthwork hauling result value was confirmed proving that it is rational to dispose of 262.8 m3 at C27 by transporting 60.8 m3 to F2 and 202 m3 to F26.
To verify the feasibility, the direct construction costs ($) from an earthwork optimized model and direct hauling costs from existing transportation model were compared.
Figure 13 shows the optimal solution of Alternative 1, 2 and 3 as previously introduced in Section 3.2 (direct hauling cost). For comparison purposes, 3 alternatives for section division were proposed before developing a hauling plan (by a dump truck). As a result of comparing direct hauling cost estimated by the transportation model theory (hauling distance x minimum volume) with direct cost estimated by the model developed in this study, the total cost is reduced by a minimum of 6.78% and a maximum of 8.89%. The result value of Alt 2 among 3 alternatives was most economical in establishing the hauling plan. Thus, section division according to Alt 2 (STA. 0 + 000–STA. 0 + 020, STA. 0 + 020–STA. 0 + 080, see Section 3.2 and Section 3.3) is considered to be the most cost efficient.

4.2. Case Study 2

Case study 2 is of domestic construction site B requiring spoil as much as 133,371 m3. The soil recycling rate is 80% for soil and 100% for ripping rock and blasting rock, which can be selected using the model. The total length is 8.62 km and the width is 20 m which is considered to be of average scale. In addition, 5 dump sites were selected using MOLIT-provided Earth Information Sharing System (www.tocycle.com).
Figure 14 shows 5 candidate dump sites and the locations and fees are as follows: In case of dump site 1, $14.44/m3, 4000 m away from STA. 3 + 600, dump site 2, $13.84/m3, 6000 away from STA. 8 + 620. Dump site 3, $14.44/m3, 8500 m away STA. 8 + 620, dump site 4, $13.59/m3, 3000 m away from STA. In addition, in case of dump site 5, $12.74/m3, 14,000 m away from STA. 0. The capacity of dump site 5 was limited to 90,000 m3. The travel speed at the site when loaded is 20 km and 25 km when empty; travel speed outside the site when loaded is 30 km and 35 km when empty.
Figure 15 summarizes the process of the optimal solution (hauling route, cost, dump site) of earthwork hauled by a section of a linear program using Microsoft-Excel and Solver after inputting each condition. The result value obtained through the earthwork optimization model includes the selection of dump sites and the equipment expense of the project (direct cost of excavator, loader and dump truck). As a result of seeking the solution using a Solver, an optimal value was produced from borrow pit 1, 4 and 5 among the total 5 candidates borrow pits. Thus, the spoil hauling result value was obtained and it proves that it is rational to move 122.8 m3 of soil from C1 to F3 and move 22 m3 of ripping rock from C7 to F5.
Figure 16 shows the optimal solution of Alt 1, 2 & 3 as previously introduced in Section 3.3 (direct hauling cost). Comparisons of direct hauling costs estimated from the transportation model theory (hauling distance x minimum volume) with direct cost from the model developed in this project were made. The results from the comparison show that there was a 5% decrease in the average reduction rates. Alt 3 among 3 alternatives was found to be most economical in establishing the hauling plan. Thus, it is necessary to perform earthwork according to an optimization result with Alt 3 (STA. 0 + 000–STA. 0 + 040, STA. 0 + 040–STA. 0 + 100, see Section 3.3).

5. Conclusions

This study is intended to develop the prototype model which allows for the selection of a dump site/borrow pit as well as establish the most cost efficient spoil hauling plan. To that end, the study is conducted based on a transshipment transportation theory, equipment productivity, earthwork equipment cost, hauling distance, dump site/borrow pit data, referring to existing transportation model theory. Site conditions were incorporated in consideration of “internal hauling” and “external hauling” together. What is noteworthy is, the most cost efficient dump site/borrow pit can be selected in consideration of hauling outside the construction site to and from the dump site/borrow pit, instead of just hauling inside the construction site. The data on the productivity of equipment used for hauling and unit cost were based on a Design Guideline for National Road construction, Korea Price Information Gazette and Standard Estimate of Construction Work so as to enhance the reliability of the model.
The prototype model proposed is based on linear programming and was developed by collecting site conditions over entire sections through a hauling plan optimization algorithm. As a result of applying such site data to this model, the direct cost of earthwork including equipment expenses and the fees for a dump site/borrow pit was reduced compared to the method proposed in the preexisting transportation theory. In addition, the model further obtains the optimized transportation paths which may be valuable to reduce the occurrence of exhaust gas by earthwork equipment.
Should the model including indirect costs be developed in a way of incorporating with a time schedule through the algorithm and prototype model, it would be proven even more useful. In addition, should equipment productivity and equipment cost in other countries be incorporated, it would also be more practical for overseas projects in the future as the functional formula, objective function and constraint conditions developed could help develop a program which is optimized to different site conditions. In addition, the model will be more applicable on the earthwork sites if the model considers the tunnel and bridge constructions as well.

Acknowledgments

This research was supported by a grant (11 CTIP 04) from construction Technology Innovation Program funded by Ministry of Land, Transport and Maritime Affairs of Korean government.

Author Contributions

This research study has been completed by integrating a variety of knowledge and experiences of each author. Seung Hak Lee, the first author, has developed an overall prototype model including the optimization algorithm. Jaeho Son, the second author, has reviewed and proposed various kinds of equations supporting the model. Seung Hyun Lee, the corresponding author, has designed the main process of the prototype model and supervised its development procedures. Finally, all authors were involved in all steps of this research study.

Conflicts of Interest

The authors declare no conflict of interest.

References

  1. Baek, H.; Kang, S.; Seo, J. An earthwork districting model for large construction project. J. Korean Soc. Civ. Eng. 2005, 35, 715–723. [Google Scholar] [CrossRef]
  2. Baek, K.; Kang, S.; Seo, J. Temporary haul road and bridge planning based on economic efficiency and productivity. In Proceedings of the Construction Research Congress 2016, San Juan, PR, USA, 31 May–2 June 2016.
  3. Mayer, R.H.; Stark, R.M. Earthmoving logistics. J. Constr. Div. 1981, 107, 297–312. [Google Scholar]
  4. Easa, S.M. Earthwork allocations with nonconstant unit costs. J. Constr. Eng. Manag. 1987, 113, 34–50. [Google Scholar] [CrossRef]
  5. Easa, S.M. Earthwork allocations with linear unit costs. J. Constr. Eng. Manag. 1988, 114, 641–655. [Google Scholar] [CrossRef]
  6. Moselhi, O.; Alshibani, A. Optimization of earthmoving operations in heavy civil engineering projects. J. Constr. Eng. Manag. 2009, 135, 948–954. [Google Scholar] [CrossRef]
  7. Nassar, K.; Hosny, O. Solving the least-cost route cut and fill sequencing problem using particle swarm. J. Constr. Eng. Manag. 2012, 138, 931–942. [Google Scholar] [CrossRef]
  8. Park, D.; Kang, I.; Kim, S.; Han, K. The selection of spoil-bank for reduction of carbon emission based on GIS analysis. J. Korean Soc. Geospat. Inf. Syst. 2012, 24, 3–9. [Google Scholar] [CrossRef]
  9. Son, J.; Mattila, K.; Myers, D. Determination of haul distance and direction in mass excavation. J. Constr. Eng. Manag. 2005, 131, 302–309. [Google Scholar] [CrossRef]
  10. Ji, Y.; Borrmann, A.; Rank, E.; Seipp, F.; Ruzika, S. Mathematical modeling of earthwork optimization problems. In Proceedings of the 13th International Conference on Computing in Civil and Building Engineering (ICCCBE-XIII), Nottingham, UK, 30 June–2 July 2010.
  11. Jassim, H.S.H.; Lu, W.; Olofsson, T. A practical method for assessing the energy consumption and CO2 emissions of mass haulers. Energies 2016, 9, 802. [Google Scholar] [CrossRef]
  12. Ministry of Land, Infrastructure and Transport. Earthwork. In Standard Estimate for Construction Work; Korea Institute of Civil Engineering and Building Technology: Sejong, Korea, 2015; pp. 785–796. [Google Scholar]
  13. Ministry of Land, Infrastructure and Transport. Transaction of Soil Rock Open Portal ReCYCLE System. Available online: www.tocycle.com (accessed on 26 August 2015).
Figure 1. Procedure and method of the study.
Figure 1. Procedure and method of the study.
Sustainability 09 00074 g001
Figure 2. Transshipment transportation model route.
Figure 2. Transshipment transportation model route.
Sustainability 09 00074 g002
Figure 3. Algorithm for optimizing earthwork hauling plan.
Figure 3. Algorithm for optimizing earthwork hauling plan.
Sustainability 09 00074 g003
Figure 4. Influential factors within objective function.
Figure 4. Influential factors within objective function.
Sustainability 09 00074 g004
Figure 5. Solver’s function.
Figure 5. Solver’s function.
Sustainability 09 00074 g005
Figure 6. Earthwork volume table within 20 m and hauling by dozer.
Figure 6. Earthwork volume table within 20 m and hauling by dozer.
Sustainability 09 00074 g006
Figure 7. Earthwork volume table within 60 m and hauling by dozer.
Figure 7. Earthwork volume table within 60 m and hauling by dozer.
Sustainability 09 00074 g007
Figure 8. Earthwork table of dump truck hauling model.
Figure 8. Earthwork table of dump truck hauling model.
Sustainability 09 00074 g008
Figure 9. Hauling distance by section.
Figure 9. Hauling distance by section.
Sustainability 09 00074 g009
Figure 10. Earthwork optimization result value.
Figure 10. Earthwork optimization result value.
Sustainability 09 00074 g010
Figure 11. Case Study of Domestic Road Construction on Site A.
Figure 11. Case Study of Domestic Road Construction on Site A.
Sustainability 09 00074 g011
Figure 12. Analysis of result value of Case study 1.
Figure 12. Analysis of result value of Case study 1.
Sustainability 09 00074 g012
Figure 13. Comparison of result values for Case Study 1.
Figure 13. Comparison of result values for Case Study 1.
Sustainability 09 00074 g013
Figure 14. Case Study of Domestic Road Construction on Site B.
Figure 14. Case Study of Domestic Road Construction on Site B.
Sustainability 09 00074 g014
Figure 15. Optimized result value of case study 2.
Figure 15. Optimized result value of case study 2.
Sustainability 09 00074 g015
Figure 16. Comparison of result values for Case Study 2.
Figure 16. Comparison of result values for Case Study 2.
Sustainability 09 00074 g016
Table 1. Influential factors relating to earthwork hauling plan.
Table 1. Influential factors relating to earthwork hauling plan.
FactorEquipment
F (volumetric conversion factor), E (work efficiency), Cm (one cycle time (s)), q (bucket capacity), K (bucket coefficient), t1 (time to fill bucket with spoil), t2 (Basic time such as gear change and time till following equipment arrives)Loader
F (volumetric conversion factor), E (work efficiency), Cm (one cycle time (s)), q (bucket capacity), K (bucket coefficient)Excavator
Q (loading capacity of dump truck), f (volumetric conversion factor), E (work efficiency), Cm (one cycle time (m)), Es (work efficiency of loader), n (cycle of loading machine to finish loading a dump truck), t1, t2, t3, t4, and t5 (components of one cycle time; m), hauling road and mean travel speed (V1, V2, V3, V4)Dump truck
Capacity of dump site/borrow pit, hauling distance, recyclable soil ratio Others

Share and Cite

MDPI and ACS Style

Lee, S.H.; Son, J.; Lee, S.H. Development of a Prototype Model to Establish an Economic Earthwork Plan that Includes the Selection of a Dump Site/Borrow Pit. Sustainability 2017, 9, 74. https://doi.org/10.3390/su9010074

AMA Style

Lee SH, Son J, Lee SH. Development of a Prototype Model to Establish an Economic Earthwork Plan that Includes the Selection of a Dump Site/Borrow Pit. Sustainability. 2017; 9(1):74. https://doi.org/10.3390/su9010074

Chicago/Turabian Style

Lee, Seung Hak, Jaeho Son, and Seung Hyun Lee. 2017. "Development of a Prototype Model to Establish an Economic Earthwork Plan that Includes the Selection of a Dump Site/Borrow Pit" Sustainability 9, no. 1: 74. https://doi.org/10.3390/su9010074

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop