Next Article in Journal
Methodology for Existing Railway Reconstruction with Constrained Optimization Based on Point Cloud Data
Next Article in Special Issue
Ore Composition’s Impact on Smelting Profitability: An Optimum Pricing Index Model for Long-Term Nickel Ore Feedstock Purchasing Agreements
Previous Article in Journal
Interruption Cost Evaluation by Cognitive Workload and Task Performance in Interruption Coordination Modes for Human–Computer Interaction Tasks
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Development of a Preventive Maintenance Strategy for an Automatic Production Line Based on Group Maintenance Method

School of Mechanical and Aerospace Engineering, Jilin University, Changchun 130025, China
*
Author to whom correspondence should be addressed.
Appl. Sci. 2018, 8(10), 1781; https://doi.org/10.3390/app8101781
Submission received: 22 August 2018 / Revised: 27 September 2018 / Accepted: 28 September 2018 / Published: 30 September 2018
(This article belongs to the Special Issue Applied Engineering to Lean Manufacturing Production Systems)

Abstract

:

Featured Application

The preventive maintenance strategy developed in present study can be employed for an automatic production line in the industrial field.

Abstract

The high maintenance costs and low reliability of automatic production line are attributed to the complexity of maintenance management. In the present study, a preventive maintenance strategy for the automatic production line was developed based on the group maintenance method. The criticality of machines in the production line was evaluated, and then the machines were classified into three groups: the most critical machines, the secondary critical machines and the general machines. The general machines were performed on the breakdown maintenance. The preventive maintenance model of the most critical machines was established with the shortest shutdown time as decision objective on basis of the Delay-time theory. The maintenance model of the secondary critical machine was established based on the considering of reliability-maintenance cost. A case study on an automotive part automatic production line was carried out to verify the proposed preventive maintenance strategy based on the production line data, and the maintenance periods of the most and secondary critical machines were gained; meanwhile, the machines all satisfied the reliability requirements during the maintenance periods.

1. Introduction

An automatic production line is an important part of the manufacturing system in the modern industrial field owing to the enormous advantages of high yield, good product quality and labor cost saving [1,2,3]. However, due to the variety of machine, complex layout and structure, any machine failure may lead to the whole production line shutdown, resulting in enormous economic losses to the production enterprise. The low reliability and high maintenance costs of the production line have become an urgent problem for production enterprises to solve [4,5]. It is very important to put forward scientific maintenance strategy to guide the maintenance and management works according to the machines’ failure characteristics and operation laws of the production line.
Because the working conditions of machines in the production line are different and the machine reliability is also different from each other, if all machines in entire production line are performed on breakdown maintenance or preventive maintenance in the same maintenance period, it is difficult to meet the requirements of high reliability, high operating rate and low maintenance costs [6,7,8]. In previous literature, the group maintenance method, which meant that a group machines with similar characteristics are maintained together in order to reduce the maintenance times and maintenance costs, was considered to be suitable for the automatic production line [9,10]. Wu et al. [11] developed an optimized maintenance cost model to determine an optimal interval of condition monitoring and the degradation level after imperfect preventive repairs, which had initiated a new area for the research on cost effective maintenance strategies. Barata and Tong respectively established the maintenance optimization models for the production line using the different methods [12,13]. Rao et al. [14] developed an opportunity maintenance model for the production line to conduct preventive maintenance on several machines at the same time when one of the machines in the production line breaks down. However, it is difficult to use the opportunity maintenance strategy for the complex production line consisting of many machines. Talukder et al. [15] used a heuristic algorithm to group the machines of the production line, and then performed the maintenance to reduce maintenance costs. Arunraj et al. [16] used the Analytic Hierarchy Process (AHP) and goal planning methods to develop the maintenance strategies based on considering the machine failure rate and maintenance costs, respectively. Christer et al. [17] put forward a delay-time model to the prevent machines’ failure during the preventative maintenance period when the machines had serious deterioration. However, these previous maintenance models and maintenance strategies were often developed with single evaluation criterion such as reliability and maintenance costs, or the same maintenance model and maintenance strategy were used for all machines in the automatic production line without distinguishing the machines’ criticality.
In the present study, a preventive maintenance strategy for the automatic production line was developed based on a group maintenance method. Using the uniform design method, the machines in the production line were classified according to the influence degree of the machine failure rate on the operating rate of the production line. Then, the machines were classified into three groups: the most critical machines, the secondary critical machines and the general machines. The general machines were performed on the breakdown maintenance. The preventive maintenance models were established for the most and secondary critical machines, respectively. The preventive maintenance model of the most critical machines was established with the shortest shutdown time as a decision objective on the basis of delay-time theory, and that of a secondary critical machine was established based on consideration of reliability-maintenance cost. Finally, a case study on an automotive part automatic production line was carried out, and the preventive maintenance periods of the most and secondary critical machines were gained according to the collected data of the production line.

2. Evaluating of Machine Criticality for an Automatic Production Line

The operating rate is one of the most important performance indexes to evaluate the automatic production line, which is defined by the ratio of actual output to theoretical output in unit time. The main factors that influence the operating rate of production line are machine failure rate, mean time to repair (MTTR), buffer capacity and production line balancing rate. Because the automatic production line is often a complicated manufacturing system, it is very difficult to establish a definite analytical model between all influence factors and the operating rate. Considering the maintainability, the optimal maintenance strategy directly influenced the failure rate and repair rate of the machines; therefore, the machine failure rate was considered as the key influence factor of the operating rate in this study. The buffer capacity and balancing rate of the production line mostly depended on the design performance of production line and they were taken as the quantitative design parameters into the preventive maintenance model.
For an automatic production line with K machines (M1, M2, …, MK), the typical layout and structure are shown in Figure 1.
For the automatic production line, the preventive maintenance is to inspect the machines, and replace parts and lubrication in a certain maintenance period. The preventive maintenance will make the machine return to the state of completely new or good, as long as the parts and lubrication are correctly replaced according to the criteria. The effect of preventive maintenance on the different machine is the same. Therefore, it can be assumed that preventive maintenance has the same effect on the failure rate of each machine, and the operating rates of production line are solved by simulation for the different combinations of the machines’ failure rate. In order to ensure the simulation accuracy, many groups of combinations of the failure rate are needed, especially while the production line is comprised of a high number of machines, the simulation calculation will be very difficult and take a long time. To improve the calculation efficiency, the simulation analysis of the production line is carried out in the present study based on the uniform design method [18,19].
First of all, the range of λi value of each machine can be determined according to the machines’ failure data. The N levels were taken for each λi (N is 3–5 times the K of the machines), and then the uniform design table UN (NS) is established to combine the failure rate for each machine. Finally, the different machines’ failure rate combinations are put into the simulation model to calculate the corresponding operating rates of production line Yj, and N groups of data samples (Yj, λj1, λj2, …, λjK) (j = 1, 2, …, K) are obtained.
The failure rate of each machine in the production line doesn’t affect each other, which means that the variables λj are independent of each other. Therefore, the regression equation of operating rate Y can be expressed as:
Y = a + b 1 λ 1 + b 2 λ 2 + + b K λ K ,
where a, b1, b2, …, bK are the unknown parameters in Equation (1).
The fitting regression equation is performed by the minimal mean square error method for the N groups of samples (Yj, λj1, λj2, …, λjK) (j = 1, 2, …, N) and expressed as:
min M = E ( Y j Y j ) 2 = E ( Y j a b 1 λ j 1 b 2 λ j 2 b K λ j K ) 2 .
The partial derivation of each parameter in Equation (2) is taken, and the partial derivation is set to be zero. The following equations are gained:
{ E y j = n a + b 1 E λ j 1 + b 2 E λ j 2 + + b K E λ j K E λ j 1 y j = a E λ j 1 + b 1 E λ j 1 2 + b 2 E λ j 1 λ j 2 + + b K E λ j 1 λ j K E λ j 2 y j = a E λ j 2 + b 1 E λ j 1 λ j 2 + b 2 E λ j 2 2 + + b K E λ j 2 λ j K E λ j K y j = a E λ j K + b 1 E λ j 1 λ j K + b 2 E λ j 2 λ j K + + b K E λ j K 2 ,
where the values of a, b1, b2, …, bK can be gained by solving Equations (3) above. The value of bi indicates the effect of the machine failure rate λi on the operating rate of production line Y, and the larger the bi, the greater the effect of λi on the operating rate Y.
Finally, the criticality of machine in the production line is evaluated according to the parameter bi in Equation (3), and so the machines can be classified into three groups on the basis of the ABC (Activity Based Classification, ABC) analysis method [20,21,22]. The principle of ABC classification analysis method comes from Pareto’s principle, which classifies the top 15–20% goods occupied 65–80% value of whole system into A group, the following 30–40% goods occupied 15–20% value of whole system into B group, and the other 40–55% goods occupied 5–15% value of the whole system into C group. For the automatic production line, the most critical machines have an important effect on the operating rate of production line, so the top 20% (Upper limit of A group ratio in ABC classification method) machines were evaluated as the most critical machines (A group). The secondary critical machines have a lower influence on the operating rate of the automatic production line compared with that of the most critical machines and the production enterprises pay more attention to saving maintenance costs. Thus, the following 30% (Lower limit of B group ratio in the ABC classification method) of machines were evaluated as the secondary critical machines (B group). The other 50% of the machines were evaluated as the general machines (C group). Namely, the machines with the parameter bi at the top 20% are classified into the most critical machines and that the following 20–50% are classified into the secondary critical machines; thus, the rest of machines are classified into the general machines.
The failure of most and secondary critical machines all have a great influence on the operating rate of production line; therefore, the preventive maintenance should be carried out for them. The failure of general machines has a smaller influence on the operating rate, and the breakdown maintenance is suitable for the general machines.

3. Preventive Maintenance Modeling for Most Critical Machines Based on Delay-Time Theory

As mentioned above, the most critical machines as evaluated in Section 2 have great influence on the operating rate of the automatic production line, and they will bring enormous economic losses to production enterprises, if the downtime of the most critical machines is too long. If the preventive maintenance is carried out separately for each of the most critical machines, which causes the frequent shutdown to the production line. Therefore, based on the theory of synchronous maintenance [23], all of the most critical machines are maintained in a group in order to reduce the frequency of the preventive maintenance.
In the present study, the shortest shutdown time was regarded as the decision goal of synchronization maintenance for the most critical machines, and then the balance between the shutdown time of failure and preventive maintenance period was found, so as to minimize the total shutdown time. The relationship between the total expected value of shutdown time ED(Tm) per unit time and the preventive maintenance period Tm for the most critical machines can be expressed:
E D ( T m ) = t f E N f ( T m ) + t p T m ,
where tf is the average failure shutdown time, tp is the average preventive maintenance shutdown time, and ENf(Tm) is the expected failure number for all most critical machines in the preventive maintenance period. The tf and tp can be gained by the failure data and maintenance data of the most critical machines. Then, the Tm is gained when ED(Tm) is the shortest.
According to the delay-time theory, the machine in the production line may gradually generate the potential failure, which can’t cause machine shutdown temporarily. However, if the potential failure is not maintained in time, it will develop into failure and causes the machine to be shutdown. The time while a potential failure develops into a failure is delay-time th. On the basis of the Akaike information criterion, the delay-time th is exponential distribution [24]. Therefore, the ENf(Tm) of the most critical machines can be calculated according to the delay-time model. The key to establishing the delay-time model is to determine the probability of potential failure θ, delay-time function f(h) and the probability of potential failure that can be detected by preventive maintenance r. The maximum-likelihood method can be used to calculate the parameters in the delay-time model. Firstly, the preventive maintenance period is divided into z number of Δt intervals:
I l k = [ t k - 1 + ( l 1 ) Δ t ,   t k 1 + l Δ t ] ( l = 1 ,   2 , ,   z ) ,   t k 1 + z Δ t = t k ,
where tk−1 is the time for the (k − 1)th maintenance, and tk−1 + zΔt = tk.
Because the potential failure and its mature failure couldn’t generate at the same time, it was assumed that the potential failure and failure were independent events and each potential failure generated independently. Thus, the maximum-likelihood function is expressed:
L = k = 1 n { P r o b a b i l i t y   o f   p o t e n t i a l   f a i l u r e   n k   g e n e r a t i n g   i n   T k } l = 1 z { P r o b a b i l i t y   o f   f a i l u r e   m k l   g e n e r a t i n g   i n   I l k } ,
where n is the number of preventive maintenance, Tk is the duration time of k-th maintenance, nk is the number of potential failures detected in the k-th maintenance, and mkl is the number of failures in the l-th interval of the k-th maintenance period.
While a potential failure of machine generates at time u, the probability of the potential failure degrades to be a failure in (t, t + Δt) interval is:
p ( t ,   t + Δ t | u ) = { ( 1 r ) n k ( F ( t + Δ t u ) F ( t u ) ) ,   T k 1 < u < T k ,   k = 1 ,   2 ,   ,   n 1 F ( t + Δ t u ) F ( t u ) ,   T n 1 < u < t F ( t + Δ t u ) ,   t < u < t + Δ t 0 ,   u > t + Δ t ,
where F(th) = 1 − exp(−ηth) is the distribution function of the delay time th.
While the occurrence of potential failure obeys the Homogeneous Poisson process (HPP) and the occurrence rate is θ, the failure occurrence rate v(t) at time t is expressed:
v ( t ) = θ ( k = 1 n 1 ( 1 r ) n k ( F ( t T k 1 ) F ( t T k ) ) + F ( t T k 1 ) ) ,   ( T n 1 < t T n )
From Equation (8), it can be found that the occurrence of failure obeys the Non-homogeneous Poisson Process (NHPP). Thus, the average number of failures during the time interval I l k is:
E N f ( I l k ) = t t + Δ t v ( t ) d t = θ t t + Δ t k = 1 n 1 ( 1 r ) n k [ F ( x T k 1 ) F ( x T k ) ] d x + θ t t + Δ t F ( x T n 1 ) d x .
The probability of mkl failures generated during the I l k is:
P k l = [ E N f ( I l k ) ] m k l e E N f ( t ,   t + Δ t ) m k l ! .
Meanwhile, the probability that the potential failure that generates at time u can be detected in the Tk is expressed:
p ( T k | u ) = { ( 1 r ) k g × r × ( 1 F ( T i u ) ) ,   T g 1 < u < T g ,   g = 1 ,   2 ,   ,   k 1 r × ( 1 F ( T k u ) ) ,   T k 1 < u < T k 0 ,   u > T k .
According to Equation (11), the expected number of potential failures that are detected in the Tk can be expressed:
E N p ( T k ) = θ 0 p ( T k | u ) d u = θ l = 1 k 1 ( 1 r ) k l r T l 1 T l [ 1 F ( T k u ) ] d u + θ r T k 1 T k [ 1 F ( T k u ) ] d u .
As mentioned above, the occurrence of potential failure is assumed to obey the Homogeneous Poisson process (HPP), and, on the basis of Equation (12), the probability of the nk-th potential failure detected in the Tk is:
P k = ( E N P ( T k ) ) n k e E N P ( T k ) n k ! .
Equations (10) and (13) are taken into Equation (6) and take its natural logarithm, and then the logarithm Likelihood function is gained as follows:
ln L = k = 1 n [ n k ln E N p ( T k ) E N p ( T k ) ] + k = 1 n l = 1 z [ m k l ln E N f ( I l k ) ] k = 1 n l = 1 z [ E N f ( I l k ) ] .
The mkl and nk obtained based on the failure and maintenance data of the production line are taken into Equation (14), and the value of θ, f(th) and r can be gained by solving the maximum value of lnL. The ENf(Tm) is gained accordingly to take the θ, f(th) and r into Equation (9). Finally, the preventive maintenance period of the most critical machines can be determined by Equation (4).
According to the above model, the optimal preventive maintenance period for the most critical machines can be calculated. Meanwhile, it is necessary to ensure the reliability of the most critical machine in the preventive maintenance period that can bring the shortest shutdown time. The time between failure (TBF) of the production line is subject to Weibull distribution [17,23]:
F w ( t ) = 1 exp [ ( t / α ) β ] , t 0 .
The maximum likelihood estimation method can be used to solve the scale parameter α and shape parameter β of each machine. The cumulative failure probability of each machine can be calculated by taking the preventive maintenance period Tm into Equation (15), and then the cumulative failure probabilities are compared with experience value from the literature or specified value from enterprise to confirm.

4. Preventive Maintenance Modeling for Secondary Critical Machines Based on Reliability-Maintenance Cost

The secondary critical machines as evaluated in Section 2 have lower influence on the operating rate of the automatic production line compared with that of the most critical machines, and the production enterprises pay more attention to save maintenance costs for the secondary critical machines. Because the failures of the secondary critical machines may also lead to the shutdown of the automatic production line, it is also necessary to ensure the reliability of the secondary machines to ensure the operating rate of production line.
Firstly, the reliability model of the secondary critical machines is established to ensure the machine reliability requirement in the preventive maintenance period. In the reliability model, the failure probability of secondary critical machine needs to be lower than an upper limit. For the e secondary critical machines evaluated in Section 2, the cumulative failure probability Fm(Ts) of the m-th secondary critical machine during the preventive maintenance period Ts for the secondary critical machines is:
F m ( T s ) = 1 exp [ ( T s / α m ) β m ] ,
where αm and βm are the scale parameter and shape parameter in the Weibull distribution, respectively.
To ensure that Fm(Ts) is less than the upper limit Fmax, Ts must meet the following condition:
T s = min { T s e } = min { α m [ ln ( 1 1 F max ) ] 1 / β m } ,
where Tse is the maximum preventive maintenance period for each secondary critical machine under the reliability constraints.
Then, the maintenance cost model is established to optimize the total maintenance costs of the secondary critical machines during a production period. It is assumed that the TBF of the machine is Weibull distribution. In the preventive maintenance period of the secondary critical machines, the expected failure number of the m-th machine is [25,26]:
E N f m ( T s ) = ( T s ( α m ) ) β m ,
The total maintenance costs of machine in a production period TJ are comprised of the preventive maintenance costs and the machine failure loss, which can be expressed as [27]:
T C ( T s ) = n C o + m = 1 e n m C m + m = 1 e n m C f m ( T s e α m ) β m ,
where n is the number of preventive maintenance in the production period, C0 is the fixed cost for each preventive maintenance, nm is the number of preventive maintenance for the m-th secondary critical machine, Cm is the cost of parts replacement for the preventive maintenance of the m-th secondary critical machine, Cfm is the average cost of the breakdown maintenance for the m-th secondary critical machine.
In order to minimize the maintenance costs based on meeting the requirement of machine reliability, the multi-objective function of reliability-maintenance cost is proposed:
max T s ; min T C ( T s ) = n C 0 + m = 1 e N m C m + m = 1 e N m C f m ( T P M m α m ) β m ;      T s e T s × Y m ,   F m ( T s ) F max ;      T s e α m { ln [ 1 1 F max ] } 1 / β m ,
where Ym = [Tse/Ts], namely Ym is the integer value of Tse/Ts. TPMm is the preventive maintenance period of the m-th secondary critical machine and TPMm = Ts × Ym, Nm is the number of preventive maintenance for the m-th machine in the production period and Nm = [TJ/TPMm], n is the number of preventive maintenance in the production cycle and n = max{Nm}.
To solve the preventive maintenance model of the secondary critical machines based on the reliability-maintenance cost, the values of the parameters (C0, Cm, Cfm, Fmax, αm, βm) can be gained from the failure and maintenance data of the machines, and they are taken into Equation (16). The preventive maintenance period TPMm of each secondary machine is obtained. TPMm is an integral multiple of Ts and the closer it is to Tse, the better TPMm is. Meanwhile, the secondary critical machines are grouped for the preventive maintenance according to their TPMm, and there are as many machines as possible in each group.

5. Case Study

The preventive maintenance strategy developed in present study was used to analyze an automotive part production line located in Shandong Province, China. This production line is comprised of 20 processing machines and it operates 16 h every day. The machines and layout of the automatic production line are shown in Figure 2, and the scene of the production line is shown in Figure 3. The failure rate of each machine was gained accordingly to collect and statistically analyze the production line data including the operating data, failure data and maintenance data. The failure rates of machines in the production line are shown in Table 1.

5.1. Evaluating of Machine Criticality for the Automotive Part Production Line

In this case study, the number of uniform design factor S was equal to 20 (the number of machines in the automotive part production line) and the value of level N (N is 3–5 times S) took 70, so the uniform design table U20 (2070) was gained and used. It was assumed that the preventive maintenance had the same influence on the failure rate of each machine, namely, the failure rate of each machine uniformly reduced on the basis of current level as showed in Table 1. The 70 groups of factor levels for the machines’ failure rate are listed in Table 2.
The uniform design table was created using the DPS (Data Processing System) software (DPSv17.0, Hangzhou Ruifeng Information Technology Co., Ltd., Hangzhou, China), and 70 groups of combined schemes were gained, which were taken into the simulation model for the production line based on the Plant Simulation software (Plant Simulation 13.0, Siemens Ltd. China, Beijing, China). Then, the operating rate Y of the production line with different groups of the machine failure rates was obtained. The regression equation between the failure rate of each machine and the operating rate of production line was established using MATLAB software (MATLAB 7.0, MathWorks Inc., Natick, MA, USA). The coefficients of regression equation are shown in Table 3.
According to the coefficients of regression equation as shown in Table 3, it can be found that the coefficients of regression equation are all negative except for the constant term, that is, there is a negative correlation between the failure rate of each machine and the operating rate of the production line. The bigger the absolute value of the regression equation coefficient, the greater the influence of the machine failure rate on the operating rate of the production line. Therefore, the absolute value of the regression equation coefficient can be used as the criterion to evaluate criticality of the machines. On the basis of the ABC analysis method as mentioned in Section 2, four machines such as M02, M05, M15, and M20 were evaluated as the most critical machines and six machines such as M01, M08, M12, M16, M18, and M19 were evaluated as the secondary critical machines.

5.2. Maintenance Period of Most Critical Machines for the Automotive Part Production Line

The statistics and analysis were performed on the failure data and potential failure data of all most critical machines, and its results were taken into Equation (14); then, the delay-time function F(h), the probability of potential failure θ and the probability of potential failure detected in preventive maintenance r were gained, that is, F(th) = 1 − exp(−0.0098th), θ = 0.8012, and r = 0.4145.
The integral transformation of Equation (9) was carried out and while t = Tn−1, t + Δt = Tn−1 + Tm = Tn. The expected number of the machine failure in the preventive maintenance period Tm was expressed:
E N f ( T m ) = θ T m θ × r × ( e η T m 1 ) η × ( e η T m 1 + r ) .
Equation (21) was taken into the decision objective Equation (4):
E D ( T m ) = t f E N f ( T m ) + t p T m = t f [ θ T m θ × r × ( e η T m 1 ) η × ( e η T m 1 + r ) ] + t p T m .
On the basis of the statistics and analysis of maintenance data, the average shutdown time of automatic production line caused by the most critical machines’ failure was 2.4 h (tf = 2.4 h) and the average preventive maintenance time of the most critical machines was 1.5 h (tp = 1.5 h). Then, the parameters F(th), θ, r, tf and tp were taken into Equation (22), and the relationship between the expected shutdown time of the production line and the preventive maintenance period was obtained by MATLAB software, as shown in Figure 4.
According to Figure 4, it can be found that the shutdown time is the shortest while the preventive maintenance period Tm is 7.30 days and the value of shortest shutdown time is 0.44. Considering of the actual operation of the production enterprise and simplifying the maintenance plan, the preventive maintenance period for the most critical machines (M02, M05, M15, M20) was designated as seven days.
In order to ensure the reliability and operating rate of the automatic production line, the reliability of each machine in the production line is not less than 0.7, namely, the cumulative failure probability of each machine should be lower than 0.3 in this case study [25]. To the best of the authors’ knowledge, there is no unified standard of minimum value of machine reliability now. Thus, in this case study, we referred to the study results of reference [25]. Thus, the Weibull distribution model of each machine and reliability of each machine were calculated when the Tm was 7. The results are shown in Table 4.
It can be seen from Table 4 that the reliability of each machine in the preventive maintenance period are higher than 0.7. Therefore, while the preventive maintenance period of the most critical machine was designed as seven days, the production line had the shortest shutdown time and sufficient reliability.

5.3. Maintenance Period of Secondary Critical Machines for the Automotive Part Production Line

As mentioned in Section 5.2, the cumulative failure probability of machine should be lower than the Fmax and Fmax = 1 − 0.7 = 0.3. The value of Fmax was taken into Equation (16), and the preventive maintenance period Ts under reliability constraints was gained, which was equal to 13 days. According to Equation (18), the cumulative failure probability of each secondary critical machine Fm(Ts) during Ts period were gained. The values of Fm(Ts) for the secondary machine are shown in Table 5.
As shown in Table 5, the cumulative failure probability Fm(Ts) of each secondary critical machine is less than Fmax (Fmax = 0.3), while the preventive maintenance period Ts is 13 days. According to Equation (20), the operating rate Ym is always equal to 1 with the values listed in Table 5. Hence, the preventive maintenance period of each secondary critical machine TPMm is 13 days (TPMm = T0·Ym). Namely, six machines evaluated as the secondary critical machines (M01, M08, M12, M16, M18 and M19) were in a group for the preventive maintenance with the 13 days period.
The fixed cost C0, the average cost of the parts replacement Cm, and the average cost of the breakdown maintenance Cfm of each secondary critical machine in a preventive maintenance period were obtained from the maintenance data provide by the enterprise and shown in Table 6.
When the preventive maintenance period TS was 13 days and the production period was one year, there were about 26 periods for the preventive maintenance. The total maintenance costs could be calculated by Equation (19) and TC(Ts) = 353,306 RMB. Compare with the results in literature [12,28], it could be found that, although the number of machines and the maintenance costs were different, the average maintenance cost of each machine in the present case study was lower. The preventive maintenance strategy for the secondary critical machine in this study should reduce the maintenance cost; meanwhile, the production line reliability was ensured.

6. Conclusions

(1)
A maintenance strategy for automatic production line was developed on the basis of considering both the reliability, operating rate and maintenance cost. Furthermore, the different maintenance methods were employed according to the criticality of the machines in the production line. The maintenance strategy was practical. If this maintenance strategy was used to guide the maintenance and management work for the production enterprise, the economic efficiency and production efficiency of the automatic production line should increase obviously.
(2)
The uniform design method and simulation method were combined to establish the regression model between the failure rate of machine and the operating rate of the production line. The influence extent of the machine failure rate on the operating rate was used as the criterion to evaluate criticality of the machines. Then, the machines were classified into three groups: the most critical machines, the secondary critical machines and the general machines. The general machines were performed on the breakdown maintenance.
(3)
The preventive maintenance model for the most critical machines was built based on delay-time theory. The relation between the preventive maintenance period for the most critical machines and total shutdown time of the production line was gained. The best preventive maintenance period of the most critical machines was determined by taking the shortest total shutdown time as the decision objective.
(4)
The preventive maintenance model for the secondary critical machines was built based on the reliability-maintenance costs. The preventive maintenance period was gained according to take the parameters (C0, Cm, Cfm, Fmax, αm, βm) into the model which were determined by the statistics and analysis of failure data and maintenance data of the secondary critical machines.
(5)
A case study on an automotive part automatic production line was carried out. The results showed that the optimal preventative maintenance period for the most critical machines’ group comprised of M02, M05, M15, and M20 was seven days while the production line reliability was ensured. In addition, the secondary critical machines’ group comprised of M01, M08, M12, M16, M18, and M19 was 13 days while the average maintenance costs were lower.
(6)
This study assumed that the system would be in a new state after the maintenance, but, in fact, this assumption was difficult to achieve under the limitation of maintenance capability. Therefore, it is necessary to investigate the synchronous imperfect preventive maintenance strategy for the automatic production line in the future.

Author Contributions

Supervision and Funding Acquisition, G.L.; Writing—Original Draft Preparation, Y.L. and X.Z.; Data Curation and Analysis, C.H. and B.X.; Writing—Review and Editing, J.H. and J.C.

Funding

This research was funded by National Science and Technology Major Project of the Ministry of Science and Technology of China (2017ZX04002001) and Jilin Scientific and Technological Development Program (20170204007GX, 20180312042ZG).

Acknowledgments

The work was supported by the program for the JLU Science and Technology Innovative Research Team (JLUSTIRT).

Conflicts of Interest

The authors declare no conflict of interest.

Abbreviations

eThe number of the secondary critical machines
f(h)The delay-time function
mklThe number of failures in the l-th interval of the k-th maintenance period
nThe number of preventive maintenance in the production period
nkThe number of potential failures detected in the k-th maintenance
nmThe number of preventive maintenance for the m-th secondary critical machine
PkThe probability of the nk-th potential failure detected in the Tk
rThe probability of potential failure which can be detected by preventive maintenance
t fThe average failure shutdown time
thThe delay-time
t pThe average preventive maintenance shutdown time
uTime when a potential failure of machine generates
v(t)The failure occurrence rate at time t
zThe number of Δt intervals
C 0The fixed cost for each preventive maintenance
CfmThe average cost of the breakdown maintenance for the m-th secondary critical machine
CmThe cost of parts replacement for the preventive maintenance of the m-th secondary critical machine
ENf(Tm)The expected failure number for all most critical machines in the preventive maintenance period
E N f m ( T s ) The expected failure number of the m-th machine
F maxThe upper limit value of the cumulative failure probability
Fm(Ts)The cumulative failure probability of the m-th machine during the preventive maintenance period
I l k A Δt interval of the preventive maintenance period
TkThe duration time of k-th maintenance
TJA production period
TmThe preventive maintenance period of the most critical machines
TseThe maximum preventive maintenance period of each secondary critical machine under reliability constraints
TPMmThe preventive maintenance period of the m-th secondary critical machine
TsThe preventive maintenance period of the secondary critical machines
αmThe scale parameter in the Weibull distribution
βmThe shape parameter in the Weibull distribution
θThe occurrence rate of potential failure

References

  1. Kang, Y.-S.; Kim, H.; Lee, Y.-H. Implementation of an RFID-based sequencing-error-proofing system for automotive manufacturing logistics. Appl. Sci. 2018, 8, 109. [Google Scholar] [CrossRef]
  2. Cristalli, C.; Grabowski, D. Multivariate analysis of transient state infrared images in production line quality control systems. Appl. Sci. 2018, 8, 250. [Google Scholar] [CrossRef]
  3. Zhou, Z.; Dou, Y.; Sun, J.; Jiang, J.; Tan, Y. Sustainable production line evaluation based on evidential reasoning. Sustainability 2017, 9, 1811. [Google Scholar] [CrossRef]
  4. Vuuren, M.V.; Adan, I.J.B.F.; Resing-Sassen, S.A.E. Stochastic modeling of manufacturing systems. Oper. Res. Spektrum 2005, 27, 315–338. [Google Scholar]
  5. Doostparast, M.; Kolahan, F.; Doostparast, M. A reliability-based approach to optimize preventive maintenance scheduling for coherent systems. Reliab. Eng. Syst. Saf. 2014, 126, 98–106. [Google Scholar] [CrossRef]
  6. Wang, W. An overview of the recent advances in delay-time-based maintenance modelling. Reliab. Eng. Syst. Saf. 2012, 106, 165–178. [Google Scholar] [CrossRef]
  7. Shanmugam, R. Case studies in reliability and maintenance. J. Stat. Comput. Simul. 2003, 73, 276–277. [Google Scholar] [CrossRef]
  8. Wang, H.Z. A survey of maintenance policies of deteriorating systems. Eur. J. Oper. Res. 2007, 139, 469–489. [Google Scholar] [CrossRef]
  9. Chen, Y.M.; Li, S.B.; Jin, B.B. Determination of cycle of mitering lock overhaul based on preventive group maintenance strategy. J. Southeast Univ. 2014, 44, 436–440. [Google Scholar]
  10. Aghezzaf, E.H.; Najid, N.M. Integrated production planning and preventive maintenance in deteriorating production systems. Inf. Sci. 2008, 178, 3382–3392. [Google Scholar] [CrossRef]
  11. Wu, F.; Niknam, S.A.; Kobza, J.E. A cost effective degradation-based maintenance strategy under imperfect repair. Reliab. Eng. Syst. Saf. 2015, 144, 234–243. [Google Scholar] [CrossRef]
  12. Barata, J.; Soares, C.G.; Marseguerra, M.; Zio, E. Simulation modelling of repairable multi-component deteriorating systems for ‘on condition’ maintenance optimization. Reliab. Eng. Syst. Saf. 2002, 76, 255–264. [Google Scholar] [CrossRef]
  13. Tong, J.; Mao, D.; Xue, D. A genetic algorithm solution for a nuclear power plant risk-cost maintenance model. Nucl. Eng. Des. 2004, 229, 81–89. [Google Scholar]
  14. Rao, A.N.; Bhadury, B. Opportunistic maintenance of multi-equipment system: A case study. Qual. Reliab. Eng. Int. 2015, 16, 487–500. [Google Scholar] [CrossRef]
  15. Talukder, M.S.; Knapp, G.M. Equipment assignment to multiple overhaul blocks in series systems. J. Qual. Maint. Eng. 2002, 8, 319–330. [Google Scholar] [CrossRef]
  16. Arunraj, N.S.; Maiti, J. Risk-based maintenance policy selection using AHP and goal programming. Saf. Sci. 2010, 48, 238–247. [Google Scholar] [CrossRef]
  17. Zhao, F.; Wang, W.; Peng, R. Delay-time-based preventive maintenance modelling for a production plant: A case study in a steel mill. J. Oper. Res. Soc. 2015, 66, 2015–2024. [Google Scholar] [CrossRef]
  18. Fang, K.T.; Lin, D.J.; Winker, P.; Zhang, Y. Uniform design: Theory and application. Technometrics 2000, 42, 237–248. [Google Scholar] [CrossRef]
  19. Zheng, M.; Zhang, X.; Zhang, L.; Teng, H.; Hu, J.; Hu, M. Uniform test method optimum design for Drag-Type Modified Savonius VAWTs by CFD numerical simulation. Arab. J. Sci. Eng. 2018, 43, 4453–4461. [Google Scholar] [CrossRef]
  20. Chen, R.Q.; Ma, S.H. Production and Operations Management; Higher Education Press: Beijing, China, 1999; pp. 302–304. [Google Scholar]
  21. Moncadatorres, A.; Leuenberger, K.; Gonzenbach, R.; Luft, A.; Gassert, R. Activity classification based on inertial and barometric pressure sensors at different anatomical locations. Physiol. Meas. 2014, 35, 1245–1263. [Google Scholar] [CrossRef] [PubMed] [Green Version]
  22. Teunter, R.H.; Babai, M.Z.; Syntetos, A.A. ABC classification: Service levels and inventory costs. Prod. Oper. Manag. 2010, 19, 343–352. [Google Scholar] [CrossRef]
  23. Yuan, Y.; Fang, L.I.; Hou, C.Y.; Yang, L. Opportunistic group maintenance optimization of multi-unit system under dependence. Comput. Integr. Manuf. Syst. 2012, 18, 827–832. [Google Scholar]
  24. Baker, R.D.; Wang, W. Developing and testing the delay-time model. J. Oper. Res. Soc. 1993, 44, 361–374. [Google Scholar] [CrossRef]
  25. Das, K.; Lashkari, K.S.; Sengupta, S. Machine reliability and preventive maintenance planning for cellular manufacturing system. Eur. J. Oper. Res. 2007, 183, 162–180. [Google Scholar] [CrossRef]
  26. Kardon, B.; Fredendall, L.D. Incorporating overall probability of system failure into a preventive maintenance model for a serial system. J. Qual. Maint. Eng. 2002, 8, 331–345. [Google Scholar] [CrossRef]
  27. Nahas, N.; Nourelfath, M. Buffer allocation, machine selection and preventive maintenance optimization in unreliable production lines. In Proceedings of the 2015 IEEE International Conference on Industrial Engineering and Systems Management, Seville, Spain, 21–23 October 2015; Volume 28, pp. 1–9. [Google Scholar]
  28. Afefy, I.H. Reliability-centered maintenance methodology and application: A case study. Engineering 2010, 2, 863–873. [Google Scholar] [CrossRef]
Figure 1. The typical layout and structure of automatic production line, where Bi (i = 1, 2, …, K) is the buffer area, Li (i = 1, 2, …, K) is the corresponding buffer capacity, λi (i = 1, 2, …, K) is the machine failure rate, and it is assumed that the time between failure (TBF) of each machine is Weibull distribution.
Figure 1. The typical layout and structure of automatic production line, where Bi (i = 1, 2, …, K) is the buffer area, Li (i = 1, 2, …, K) is the corresponding buffer capacity, λi (i = 1, 2, …, K) is the machine failure rate, and it is assumed that the time between failure (TBF) of each machine is Weibull distribution.
Applsci 08 01781 g001
Figure 2. The machines and layout of an automotive part production line (CNC: Computer Numerical Control).
Figure 2. The machines and layout of an automotive part production line (CNC: Computer Numerical Control).
Applsci 08 01781 g002
Figure 3. The scene of the automotive part production line.
Figure 3. The scene of the automotive part production line.
Applsci 08 01781 g003
Figure 4. The relationship between expected shutdown time of the production line and the preventive maintenance period.
Figure 4. The relationship between expected shutdown time of the production line and the preventive maintenance period.
Applsci 08 01781 g004
Table 1. The failure rate of each machine.
Table 1. The failure rate of each machine.
MachineFailure Rate λ (1/h)
M010.0022
M020.0017
M030.0026
M040.0026
M050.0027
M060.0021
M070.0021
M080.0025
M090.0021
M100.0034
M110.0023
M120.0020
M130.0027
M140.0026
M150.0023
M160.0035
M170.0017
M180.0019
M190.0054
M200.0030
Table 2. The levels of the uniform design for the machines’ failure rate.
Table 2. The levels of the uniform design for the machines’ failure rate.
No.MachineLevels λjK (1/h)
12j 6970
1M010.00220.002180.0022 − (j − 1) × 0.000020.000840.00082
2M020.00170.001680.0017 − (j − 1) × 0.000020.000340.00032
3M030.00260.002580.0026 − (j − 1) × 0.000020.001240.00122
4M040.00260.002580.0026 − (j − 1) × 0.000020.001240.00122
5M050.00270.002680.0027 − (j − 1) × 0.000020.001340.00132
6M060.00210.002080.0021 − (j − 1) × 0.000020.000740.00072
7M070.00210.002080.0021 − (j − 1) × 0.000020.000740.00072
8M080.00250.002480.0025 − (j − 1) × 0.000020.001140.00112
9M090.00210.002080.0021 − (j − 1) × 0.000020.000740.00072
10M100.00340.003380.0034 − (j − 1) × 0.000020.002040.00202
11M110.00230.002280.0023 − (j − 1) × 0.000020.000940.00092
12M120.00200.001980.0020 − (j − 1) × 0.000020.000640.00062
13M130.00270.002680.0027 − (j − 1) × 0.000020.001340.00132
14M140.00260.002580.0026 − (j − 1) × 0.000020.001240.00122
15M150.00230.002280.0023 − (j − 1) × 0.000020.000940.00092
16M160.00350.003480.0035 − (j − 1) × 0.000020.002140.00212
17M170.00170.001680.0017 − (j − 1) × 0.000020.000340.00032
18M180.00190.001880.0019 − (j − 1) × 0.000020.000540.00052
19M190.00540.005380.0054 − (j − 1) × 0.000020.004040.00402
20M200.00300.002980.0030 − (j − 1) × 0.000020.001640.00162
Table 3. The coefficients of regression equation.
Table 3. The coefficients of regression equation.
CoefficientValueCorresponding Machine
a 0.996Constant term
b 1−1.766M01
b 2−1.897M02
b 3−1.051M03
b 4−1.129M04
b 5−3.441M05
b 6−1.231M06
b 7−0.953M07
b 8−1.551M08
b 9−0.407M09
b 10−1.060M10
b 11−1.263M11
b 12−1.848M12
b 13−0.847M13
b 14−0.914M14
b 15−2.286M15
b 16−1.405M16
b 17−1.338M17
b 18−1.437M18
b 19−1.875M19
b 20−1.977M20
Table 4. Reliability of the most critical machines during the preventive maintenance period.
Table 4. Reliability of the most critical machines during the preventive maintenance period.
MachineWeibull Distribution ModelReliability (%)
M02 F w ( t ) = 1 exp [ ( t / 393.8 ) 1.118 ] 0.783
M05 F w ( t ) = 1 exp [ ( t / 442.6 ) 1.410 ] 0.866
M15 F w ( t ) = 1 exp [ ( t / 263.7 ) 1.462 ] 0.751
M20 F w ( t ) = 1 exp [ ( t / 454.5 ) 1.784 ] 0.921
Table 5. The cumulative failure probability of secondary critical machines.
Table 5. The cumulative failure probability of secondary critical machines.
MachineTse/dayTs/dayFm(Ts)/%
M0114.5130.266
M0814.3130.269
M1213.2130.296
M1613.3130.291
M1813.3130.292
M1917.4130.218
Table 6. The maintenance cost data of each secondary critical machine.
Table 6. The maintenance cost data of each secondary critical machine.
MachineC0 (RMB)Cm (RMB)Cfm (RMB)
M0151002753470
M083702405
M123003190
M163302575
M183152640
M192903895

Share and Cite

MDPI and ACS Style

Li, G.; Li, Y.; Zhang, X.; Hou, C.; He, J.; Xu, B.; Chen, J. Development of a Preventive Maintenance Strategy for an Automatic Production Line Based on Group Maintenance Method. Appl. Sci. 2018, 8, 1781. https://doi.org/10.3390/app8101781

AMA Style

Li G, Li Y, Zhang X, Hou C, He J, Xu B, Chen J. Development of a Preventive Maintenance Strategy for an Automatic Production Line Based on Group Maintenance Method. Applied Sciences. 2018; 8(10):1781. https://doi.org/10.3390/app8101781

Chicago/Turabian Style

Li, Guofa, Yi Li, Xinge Zhang, Chao Hou, Jialong He, Binbin Xu, and Jinghao Chen. 2018. "Development of a Preventive Maintenance Strategy for an Automatic Production Line Based on Group Maintenance Method" Applied Sciences 8, no. 10: 1781. https://doi.org/10.3390/app8101781

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop