Generation Expansion Planning with Energy Storage Systems Considering Renewable Energy Generation Profiles and Full-Year Hourly Power Balance Constraints
Abstract
:1. Introduction
1.1. Motivation
1.2. Literature Review
1.3. Our Contribution
2. Methodology
2.1. Problem Statement
- The model is deterministic.
- Adequacy of generation capacity can be ensured by exceeded capacity results from reliability constraints.
- The objective of this problem is to create a generation expansion plan that has minimum total electricity cost. Total electricity cost consists of average and levelized investment costs, fuel costs, fixed operation and maintenance costs, and variable operation and maintenance costs.
- The given planning horizon is divided into monthly timeslots.
- The power system is modelled as a conventional system as shown in Figure 1. Only generation and total system load are considered. Transmission elements are neglected.
- The initial generation system prior to the given planning horizon is required.
- Renewable energy penetration is already planned for a whole planning horizon.
- A set of candidate units for generation expansion are given with different technologies, fuels, sizes, and heat rates.
- Operational and short-term characteristics, e.g., ramp rates, minimum up and down times, synchronization and desynchronization time, etc., are neglected in this optimization.
- Only generation system reliability is considered. Transmission system reliability is neglected.
- The individual hourly output power of each generation unit is considered to accurately represent power generation profile of intermittent renewable energy resources. For example, non-dispatchable solar generation units generate varied output power, which changes hourly according to sunlight.
- Electricity demand is represented with a full-year hourly load curve.
- Generation expansion decisions will be made from reliability criteria and hourly power balance criteria.
- The generation units selected from the set of candidates during each timeslot.
- The hourly electricity production of each generation unit in each timeslot.
- The hourly charged and discharged electricity of each ESS unit.
2.2. Mathematical Formulation
2.2.1. Objective Function
2.2.2. Constraints
Reliability Constraint
Hourly Energy Balance Constraint
Energy Storage System Operating Constraint
Fuel Mix Ratio Constraint
CO2 Emissions Constraint
Power Generation Upper Bound and Lower Bound
2.3. Simplification Process
2.3.1. The Concept of Simplification
- Separate each month into multiple timeslots within the planning horizon to reduce the number of variables in a single calculation. By doing this, multiple MILP models will be used instead of a single multi-period MILP. Thus, multiple problems need to be iteratively solved and the optimal solution of the previous timeslot will be used as the initial condition of the next.
- Separate generation expansion decisions from the MILP model. By doing this, the MILP model will be reduced to a linear programming model. Reliability constraints can also be removed from the linear programming model. However, a reliability index still needs to be calculated separately for generation expansion decisions. The remaining linear programming model in each specific month m of year y will be used for unit commitment problem and energy dispatch, which provides decision-making indices that will be subsequently used for generation expansion decisions.
- Generation expansion decisions shall be made by comparing candidate generation units’ levelized average cost of electricity. With objective function shown in (1), adding generation units with the cheapest levelized average cost, considering the aforementioned constraints, still leads to near-optimal solutions for generation expansion planning, even if a full-scale optimization model is not used.
2.3.2. A Slack Generation Unit
- Availability: always available
- Generating capacity: larger than peak demand of considered timeslot
- Unit cost: much more than the most expensive unit
- Fuel type and CO2 emissions: unspecified fuel type, no emission factor
2.3.3. Simplified Model
2.3.4. LOLE Calculation with ESS
2.3.5. Candidate Generation Capacity Selection
- the system reserve margin is lower than the planning criteria, or
- system LOLE is higher than the planning criteria, or
- there is no optimal solution provided by linear programming, (in this case the slack generation units will be dispatched, instead).
3. Case Study and Simulation Results
3.1. Planning Constraints
- Planning horizon: 2013–2030
- Existing generation system as of December 2012 used as initial power generation system.
- Consider reserve margin as reliability criteria. Reserve margin of the system shall not fall below 16%
- Renewable energy source penetration in this plan is set in advance according to Thailand’s alternative energy development plan: AEDP 2012-2021 [34].
- Average CO2 emission limited to 0.5 kgCO2/kWh within planning horizon.
- Fuel used in electricity generation classified into ten types:
- Bituminous
- Diesel
- Bunker oil
- Import coal
- Natural gas
- Import hydro
- Lignite
- Import HVDE
- Nuclear
- Renewable
- Maximum fuel mix ratio in 2030 of natural gas is 70% and bituminous is 13%
3.2. System Demand
3.3. Fuel Cost
3.4. Generation System
3.4.1. Generation Units in Generation Expansion Planning
3.4.2. Generation Unit Modeling
- Renewable energy generation units with generation profiles:
- 2.
- Peak cutting generation units:
- 3.
- Dispatchable generation units:
- 4.
- Energy storage systems:
3.5. Result and Discussion
3.5.1. Verification of the Results from the Proposed Method
3.5.2. Generation Expansion Planning with Uncertainty
3.5.3. Generation Expansion Planning with ESS
3.5.4. Computational Cost
4. Conclusions
Author Contributions
Funding
Conflicts of Interest
Nomenclature
Indices | |
f | fuel type |
h | hour in considering month |
i | State of capacity outage Oi |
j | existing generation unit and ESS in current planning horizon |
k | new generation unit added into current planning horizon |
m | month in planning horizon |
s | ESS type |
y | year in planning horizon |
Parameters | |
Cinvj,k | investment capital cost of generation unit k which use fuel type f (THB/MW) |
Cf,k | fixed cost per MW of candidate generation unit k which use fuel type f (THB/MW) |
Crates,j | c-rate of ESS type s unit j (MW/MWh) |
DFf,j | dependable factor of generation unit j of fuel type f (%) |
ef,j,y | variable cost of electricity generated from generation unit j of fuel type f in year y (THB/MWh) |
EFf | emission factor of fuel type f (kgCO2/Btu) |
Es,j,y,m,h | stored energy in ESS type s unit j at hour h month m year y (MWh) |
FCf,y | fuel cost of fuel type f in year y (THB/Btu) |
FOMCf,k | Fixed operation and maintenance cost of generation unit k which use fuel type f (THB/MW/year) |
FORf,j,y,m | forced outage rate of generation unit j which use fuel type f of month m of year y (%) |
Hm | number of hours in month m, i.e., 744 h in January, 720 h in April |
HRf,j | heat rate of generation unit j that use fuel type f (Btu/MWh) |
LDCy,m | Load duration of month m of year y |
LOLE | loss of load expectation (day/year) |
LTf,k | lifetime of new generation unit k which use fuel type f (year) |
Ly,m,h | load of hour h in month m of year y (MW) |
Nf,y,m | number of existing generation unit of fuel type f in month m of year y |
Ns,y,m | number of existing ESS unit of type s in month m of year y |
Nf,y,m | number of new generation unit of fuel type f added in the system in month m of year y |
Oi | Outage capacity i (MW) |
Pchs,j,max | maximum internal power input (charge state) of ESS of type s unit j (MW) |
Pchs,j,min | minimum internal power input (charge state) of ESS of type s unit j (MW) |
Pdchs,j,max | maximum internal power output (discharge state) of ESS of type s unit j (MW) |
Pdchs,j,min | minimum internal power output (discharge state) of ESS of type s unit j (MW) |
Pf,j,max | maximum power output of generation unit j that use fuel type f (MW) |
Pf,j,min | minimum power output of generation unit j that use fuel type f (MW) |
pi | individual probability of outage capacity state i |
PLy,m | peak load of month m of year y (MW) |
PSchs,j,max | maximum system power input (charge state) of ESS unit j (MW) |
PSdchs,j,max | maximum system power output (discharge state) of ESS unit j (MW) |
r | discount rate (%) |
RM | reserve margin (%) |
SOCmax,s,j | maximum state of charge of ESS type s unit j (%) |
SOCmin,s,j | minimum state of charge of ESS type s unit j (%) |
tLDC(Oi) | duration of the load loss due to the outage capacity Oi (hr) in load duration curve (LDC) |
tLDC’(Oi) | duration of the load loss due to the outage capacity Oi (hr) in modified load duration curve (LDC’) |
VOMCf,j | variable operation and maintenance cost of generation unit j of fuel type f (THB/MWh) |
δf,y,m | fuel ratio of fuel type f in year y (%) |
εy,m | maximum average CO2 emission of year y (kgCO2/MWh) |
ηch,s,j | charging efficiency of ESS type s unit j (%) |
ηdch,s,j | discharging efficiency of ESS type s unit j (%) |
Variable | |
ICf,k,y,m | Installed capacity of candidate generation unit k which use fuel type f commissioned in month m of year y (MW) |
Pchs,j,y,m,h | Self-power absorbed by ESS type s unit j in hour h of month m of year y (MW) |
Pdchs,j,y,m,h | Self-power supplied by ESS type s unit j in hour h of month m of year y (MW) |
Pf,j,y,m,h | Power generated by generation unit j which use fuel type f in hour h of month m of year y (MW) |
Appendix A
Fuel Type | Number (Unit) | Total Capacity (MW) | Lifetime (Years) | Heat Rate (Btu/kWh) |
---|---|---|---|---|
bituminous | 8 | 2376.00 | 25–30 | 8300–9100 |
diesel | 1 | 4.40 | 25 | 10,400 |
oil | 2 | 320.00 | 21–30 | 8300–10,400 |
import coal | - | - | - | - |
import HVDC | 1 | 300.00 | 25 | - |
import hydro | 5 | 2104.60 | 25–50 | - |
Lignite | 10 | 2180.00 | 30–39 | 10,600–11,500 |
natural gas | 65 | 21,796.30 | 20–31 | 6800–10,300 |
nuclear | - | - | - | - |
renewable | N/A | 4684.10 | 21–50 | - |
PHS | 1 | 500.00 | 50 | - |
Fuel Type | Total Cap. (MW) | Lifetime (Years) |
---|---|---|
hydro | 2967.98 | 25–50 |
solar | 303.03 | 25 |
wind | 249.90 | 25 |
biomass | 1028.60 | 21–25 |
biogas | 110.20 | 25 |
waste | 22.40 | 25 |
geothermal | 2.00 | 25 |
Year | Bituminous | Diesel | Oil | Import Coal | Import Hydro | Lignite | Natural Gas | PHS |
---|---|---|---|---|---|---|---|---|
2013 | 1186.00 | |||||||
2014 | 3436.90 −1052.00 | |||||||
2015 | 982.00 | 3056.90 −1175.10 | ||||||
2016 | 270.00 | 491.00 | 1370.80 −478.20 | |||||
2017 | 270.00 | 900.00 −494.00 | 500.00 | |||||
2018 | 659.00 | 720.90 −680.50 | ||||||
2019 | 800.00 | −5.00 | 1220.00 | 724.80 −180.00 | ||||
2020 | 90.00 −1521.00 | |||||||
2021 | 300.00 | 1080.90 −200.00 | ||||||
2022 | 300.00 | 1084.80 −150.00 | ||||||
2023 | 300.00 | 1980.00 −2863.00 | ||||||
2024 | −270.00 | 300.00 | 1980.90 −360.00 | |||||
2025 | −90.00 | 300.00 | 1084.8 −2330.00 | |||||
2026 | 300.00 | 1080.00 | ||||||
2027 | 300.00 | 1980.90 −2617.00 | ||||||
2028 | 250.00 | 300.00 | 1804.80 −1289.00 | |||||
2029 | 250.00 | 300.00 | −270.00 | 900.00 | ||||
2030 | 250.00 | 300.00 −126.00 | −270.00 | 0.90 |
Year | Small Hydro | Solar | Wind | Biomass | Biogas | Waste |
---|---|---|---|---|---|---|
2013 | 19.20 | 375.80 | 14.00 | 574.50 | - | 56.00 |
2014 | 0.50 | 181.10 | 263.60 | 206.80 | 1.20 | 12.80 |
2015 | 51.80 | 191.10 | 302.90 | 180.50 | 2.30 | 22.80 |
2016 | 5.20 | 130.10 | 163.10 | 175.30 | 2.30 | 32.80 |
2017 | 22.00 | 130.10 | 163.10 | 175.30 | 2.30 | 41.80 |
2018 | 23.60 | 130.00 | 7.40 | 184.50 | 2.40 | 41.80 |
2019 | 3.50 | 151.00 | 117.80 | 179.80 | 2.40 | 41.80 |
2020 | 4.70 | 151.00 | 8.20 | 234.00 −8.00 | 2.50 | 41.90 |
2021 | 1.50 | 201.00 | 8.60 | 186.00 | 2.50 | 41.90 |
2022 | 1.30 | 220.10 | 9.00 | 53.70 | 2.50 | 1.90 |
2023 | 3.50 | 220.10 | 19.50 | 32.80 | 2.60 | 1.90 |
2024 | 2.20 | 220.10 | 9.90 | 38.60 −49.80 | 2.60 | 1.90 |
2025 | 3.30 | 220.00 | 10.40 | 21.20 −56.00 | 2.60 | 2.00 |
2026 | 1.00 | 221.00 | 11.00 | 16.80 −5.00 | 2.70 | 2.00 |
2027 | 12.00 | 220.10 | 61.50 | 16.90 −7.00 | 2.70 | 2.00 |
2028 | 17.30 | 221.00 | 12.10 | 14.40 −103.00 | 2.80 | 2.00 |
2029 | 1.00 | 223.00 | 22.70 | 14.50 | 2.80 | 2.00 |
2030 | 1.00 | 230.00 | 43.30 | 14.70 −20.00 | 2.80 | 2.10 |
References
- Nie, S.; Huang, Z.C.; Huang, G.H.; Yu, L.; Liu, J. Optimization of electric power systems with cost minimization and environmental-impact mitigation under multiple uncertainties. Appl. Energy 2018, 221, 249–267. [Google Scholar] [CrossRef]
- Koltsaklis, N.E.; Dagoumas, A.S. State-of-the-art generation expansion planning: A review. Appl. Energy 2018, 230, 563–589. [Google Scholar] [CrossRef]
- Oree, V.; Sayed Hassen, S.Z.; Fleming, P.J. Generation expansion planning optimisation with renewable energy integration: A review. Renew. Sustain. Energy Rev. 2017, 69, 790–803. [Google Scholar] [CrossRef]
- Saber, H.; Moeini-Aghtaie, M.; Ehsan, M. Developing a multi-objective framework for expansion planning studies of distributed energy storage systems (DESSs). Energy 2018, 157, 1079–1089. [Google Scholar] [CrossRef]
- Massé, P.; Gibrat, R. Application of linear programming to investments in the electric power industry. Manag. Sci. 1957, 3, 149–166. [Google Scholar] [CrossRef]
- Heuberger, C.F.; Rubin, E.S.; Staffell, I.; Shah, N.; Mac Dowell, N. Power capacity expansion planning considering endogenous technology cost learning. Appl. Energy 2017, 204, 831–845. [Google Scholar] [CrossRef]
- Koltsaklis, N.E.; Dagoumas, A.S.; Kopanos, G.M.; Pistikopoulos, E.N.; Georgiadis, M.C. A spatial multi-period long-term energy planning model: A case study of the Greek power system. Appl. Energy 2014, 115, 456–482. [Google Scholar] [CrossRef]
- Quiroga, D.; Sauma, E.; Pozo, D. Power system expansion planning under global and local emission mitigation policies. Appl. Energy 2019, 239, 1250–1264. [Google Scholar] [CrossRef]
- Zhang, N.; Hu, Z.; Shen, B.; He, G.; Zheng, Y. An integrated source-grid-load planning model at the macro level: Case study for China’s power sector. Energy 2017, 126, 231–246. [Google Scholar] [CrossRef]
- Hemmati, R.; Saboori, H.; Jirdehi, M.A. Multistage generation expansion planning incorporating large scale energy storage systems and environmental pollution. Renew. Energy 2016, 97, 636–645. [Google Scholar] [CrossRef]
- Alizadeh, B.; Jadid, S. A dynamic model for coordination of generation and transmission expansion planning in power systems. Int. J. Electr. Power Energy Syst. 2015, 65, 408–418. [Google Scholar] [CrossRef]
- Booth, R.R. Optimal generation planning considering uncertainty. IEEE Trans. Power Appar. Syst. 1972, PAS-91, 70–77. [Google Scholar] [CrossRef]
- Su, C.T.; Lii, G.R.; Chen, J.J. Long-term generation expansion planning employing dynamic programming and fuzzy techniques. In Proceedings of the IEEE International Conference on Industrial Technology, Goa, India, 19–22 January 2000; pp. 644–649. [Google Scholar] [CrossRef]
- Neshat, N.; Amin-Naseri, M.R. Cleaner power generation through market-driven generation expansion planning: An agent-based hybrid framework of game theory and Particle Swarm Optimization. J. Clean. Prod. 2015, 105, 206–217. [Google Scholar] [CrossRef]
- Gupta, N.; Khosravy, M.; Patel, N.; Senjyu, T. A Bi-Level Evolutionary Optimization for Coordinated Transmission Expansion Planning. IEEE Access 2018, 6, 48455–48477. [Google Scholar] [CrossRef]
- Gupta, N.; Shekhar, R.; Kalra, P.K. Computationally efficient composite transmission expansion planning: A Pareto optimal approach for techno-economic solution. Int. J. Electr. Power Energy Syst. 2014, 63, 917–926. [Google Scholar] [CrossRef]
- Gacitua, L.; Gallegos, P.; Henriquez-Auba, R.; Lorca; Negrete-Pincetic, M.; Olivares, D.; Valenzuela, A.; Wenzel, G. A comprehensive review on expansion planning: Models and tools for energy policy analysis. Renew. Sustain. Energy Rev. 2018, 98, 346–360. [Google Scholar] [CrossRef]
- Korea Power Exchange. The 7th Basic Plan for Long-term Electricity Supply and Demand (2015–2019). Available online: https://www.kpx.or.kr/eng/selectBbsNttView.do?key=328&bbsNo=199&nttNo=14547 (accessed on 31 August 2021).
- Energy Policy and Planning Office. Summary of Thailand Power Development plan (PDP2010: Revision 3). Available online: https://www.erc.or.th/ERCWeb2/Upload/Document/PDP2010-Rev3-Cab19Jun2012-E.pdf (accessed on 31 August 2021).
- Park, H.; Baldick, R. Multi-year stochastic generation capacity expansion planning under environmental energy policy. Appl. Energy 2016, 183, 737–745. [Google Scholar] [CrossRef]
- Afful-Dadzie, A.; Afful-Dadzie, E.; Awudu, I.; Banuro, J.K. Power generation capacity planning under budget constraint in developing countries. Appl. Energy 2017, 188, 71–82. [Google Scholar] [CrossRef]
- Guerra, O.J.; Tejada, D.A.; Reklaitis, G.V. An optimization framework for the integrated planning of generation and transmission expansion in interconnected power systems. Appl. Energy 2016, 170, 1–21. [Google Scholar] [CrossRef]
- Koltsaklis, N.E.; Georgiadis, M.C. A multi-period, multi-regional generation expansion planning model incorporating unit commitment constraints. Appl. Energy 2015, 158, 310–331. [Google Scholar] [CrossRef]
- Wierzbowski, M.; Lyzwa, W.; Musial, I. MILP model for long-term energy mix planning with consideration of power system reserves. Appl. Energy 2016, 169, 93–111. [Google Scholar] [CrossRef] [Green Version]
- Belderbos, A.; Delarue, E. Accounting for flexibility in power system planning with renewables. Int. J. Electr. Power Energy Syst. 2015, 71, 33–41. [Google Scholar] [CrossRef] [Green Version]
- Chen, X.; Lv, J.; McElroy, M.B.; Han, X.; Nielsen, C.P.; Wen, J. Power system capacity expansion under higher penetration of renewables considering flexibility constraints and low carbon policies. IEEE Trans. Power Syst. 2018, 33, 6240–6253. [Google Scholar] [CrossRef]
- Opathella, C.; Elkasrawy, A.; Adel Mohamed, A.; Venkatesh, B. MILP formulation for generation and storage asset sizing and sitting for reliability constrained system planning. Int. J. Electr. Power Energy Syst. 2020, 116, 105529. [Google Scholar] [CrossRef]
- Billinton, R.; Allan, R. Reliability Evaluation of Power Systems; Pitman Advanced Publishing Program: London, UK, 1984; ISBN 0273084852. [Google Scholar]
- Aghaei, J.; Akbari, M.A.; Roosta, A.; Baharvandi, A. Multiobjective generation expansion planning considering power system adequacy. Electr. Power Syst. Res. 2013, 102, 8–19. [Google Scholar] [CrossRef]
- Pudjianto, D.; Aunedi, M.; Djapic, P.; Strbac, G. Whole-Systems assessment of the value of energy storage in low-carbon electricity systems. IEEE Trans. Smart Grid 2014, 5, 1098–1109. [Google Scholar] [CrossRef]
- Hemmati, R.; Saboori, H.; Siano, P. Coordinated short-term scheduling and long-term expansion planning in microgrids incorporating renewable energy resources and energy storage systems. Energy 2017, 134, 699–708. [Google Scholar] [CrossRef]
- Choi, J.; Park, W.K.; Lee, I.W. Economic dispatch of multiple energy storage systems under different characteristics. Energy Procedia 2017, 141, 216–221. [Google Scholar] [CrossRef]
- Xiong, P.; Singh, C. Optimal planning of storage in power systems integrated with wind power generation. IEEE Trans. Sustain. Energy 2016, 7, 232–240. [Google Scholar] [CrossRef]
- Sutabutr, T. Alternative Energy Development Plan (2012–2021). Available online: http://www.sert.nu.ac.th/IIRE/FP_V7N1(1).pdf (accessed on 28 August 2021).
- Ministry of Energy Thailand: Thailand’s Power Development Plan (PDP) 2018 Rev. 1. Available online: https://policy.asiapacificenergy.org/node/4347/portal (accessed on 31 August 2021).
- Electricity Generating Authority of Thailand Lamtakong Jolabha Vadhana Power Plant. Available online: https://www.egat.co.th/en/information/power-plants-and-dams?view=article&id=46 (accessed on 28 August 2021).
- BMZ Energy Storage System Data Sheet—ESS 7.0/9.0. Available online: https://d3g1qce46u5dao.cloudfront.net/data_sheet/170622_bmz_ess_70_datasheet_en_v032017.pdf (accessed on 28 August 2021).
Capacity Outage (MW) | Capacity Available (MW) | State Probability |
---|---|---|
O1 | Installed capacity—O1 | p1 |
O2 | Installed capacity—O2 | p2 |
Oi | Installed capacity—Oi | pi |
ON | Installed capacity—ON | pN |
Generation Unit | Fuel Type | Capacity (MW) | Lifetime (years) | Heat Rate (Btu/kWh) | Remark |
---|---|---|---|---|---|
Coal fired thermal | Bituminous | 800 | 30 | 8650 | Unlimited |
Combined cycle | Natural gas | 900 | 25 | 6800 | Unlimited |
Nuclear | Nuclear | 1000 | 60 | 10,950 | Unlimited |
Parameters | % of Forecasted Load (Associated Probability) | |||
---|---|---|---|---|
97% (0.25) | 100% (0.5) | 103% (0.25) | ||
% of solar power generation (associated probability) | 90% (0.25) | 0.0625 | 0.125 | 0.0625 |
100% (0.5) | 0.125 | 0.25 | 0.125 | |
110% (0.25) | 0.0625 | 0.125 | 0.0625 |
Type | C-Rate (MW/MWh) | Charging Efficiency (%) | Discharging Efficiency (%) | Minimum State of Charge (%) | Maximum State of Charge (%) |
---|---|---|---|---|---|
PHS | 0.125 | 86.6% | 86.6% | 0.0% | 100.0% |
BESS | 1 | 97.5% | 97.5% | 10.0% | 90.0% |
Year | Results for Section 3.5.1 | Results for Section 3.5.2 | ||
---|---|---|---|---|
Case 1 | Case 2 (w/Forecasted) | Case 2 Min | Case 2 Max | |
2015 | (4) NG 900 MW | |||
2021 | (1) NG 900 MW | (4) NG 900 MW | ||
2022 | (6) Coal 800 MW (6) NG 900 MW | (4) NG 900 MW | ||
2023 | (1) NG 900 MW | (3) Coal 800 MW (3) NG 900 MW (4) NG 900 MW | (3) Coal 800 MW (3) NG 900 MW (4) NG 900 MW | (3) Coal 800 MW (3) NG 900 MW (4) NG 900 MW |
2024 | (6) NG 900 MW | |||
2025 | (6) Coal 800 MW (6) NG 900 MW | (4) NG 900 MW | (4) NG 900 MW | (4) NG 900 MW (4) NG 900 MW |
2026 | (6) Nuclear 1000 MW (6) NG 900 MW | (3) Nuclear 1000 MW (4) Coal 800 MW | (3) Nuclear 1000 MW (4) NG 900 MW | (4) Nuclear 1000 MW |
2027 | (6) Nuclear 1000 MW | (3) Nuclear 1000 MW (4) NG 900 MW | (3) Nuclear 1000 MW (4) Coal 800 MW | (3) Nuclear 1000 MW (4) Coal 800 MW (4) NG 900 MW |
2028 | (1) Coal 800 MW | (3) Coal 800 MW (4) NG 900 MW | (4) NG 900 MW | (3) Coal 800 MW (4) NG 900 MW |
2029 | (6) NG 900 MW | |||
2030 | (1) NG 900 MW | (3) NG 900 MW (4) NG 900 MW | (3) Coal 800 MW (4) NG 900 MW | (3) NG 900 MW (4) NG 900 MW |
Total | 11,600 MW | 11,600 MW | 9800 MW | 13,400 MW |
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations. |
© 2021 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/).
Share and Cite
Diewvilai, R.; Audomvongseree, K. Generation Expansion Planning with Energy Storage Systems Considering Renewable Energy Generation Profiles and Full-Year Hourly Power Balance Constraints. Energies 2021, 14, 5733. https://doi.org/10.3390/en14185733
Diewvilai R, Audomvongseree K. Generation Expansion Planning with Energy Storage Systems Considering Renewable Energy Generation Profiles and Full-Year Hourly Power Balance Constraints. Energies. 2021; 14(18):5733. https://doi.org/10.3390/en14185733
Chicago/Turabian StyleDiewvilai, Radhanon, and Kulyos Audomvongseree. 2021. "Generation Expansion Planning with Energy Storage Systems Considering Renewable Energy Generation Profiles and Full-Year Hourly Power Balance Constraints" Energies 14, no. 18: 5733. https://doi.org/10.3390/en14185733