Next Article in Journal
A Methodology for the Enhancement of the Energy Flexibility and Contingency Response of a Building through Predictive Control of Passive and Active Storage
Previous Article in Journal
Challenges and Opportunities for End-of-Life Coal Mine Sites: Black-to-Green Energy Approach
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

A Comparative Analysis of Economics of PMSG and SCSG Floating Offshore Wind Farms

1
Department of Electrical Engineering, Changwon National University, Changwon 51140, Korea
2
Department of Naval Architecture and Ocean Engineering, University of Ulsan, Ulsan 44610, Korea
*
Author to whom correspondence should be addressed.
Energies 2021, 14(5), 1386; https://doi.org/10.3390/en14051386
Submission received: 20 January 2021 / Revised: 18 February 2021 / Accepted: 23 February 2021 / Published: 3 March 2021
(This article belongs to the Section C: Energy Economics and Policy)

Abstract

:
The biggest obstacle to using a permanent magnet synchronous generator (PMSG) for a floating offshore wind turbine (FOWT) is the weight. A superconducting synchronous generator (SCSG) can be an alternative to this problem. In this paper, first, the weight and volume of a 10 MW class PMSG and SCSG for a large floating offshore wind farm (FOWF) were compared. Reflecting this, the economic feasibility of a 200 MW class FOWF based on a semi-submersible platform was compared and analyzed. The levelized cost of energy (LCOE) was used to compare the economics of the two types of FOWF, and the LCOE of the SCSG type FOWF was 6 (USD/MWh) more expensive than that of the PMSG type FOWF. However, if the superconducting wire price is reduced by 40% compared to the current price, the economic feasibility of the SCSG type FOWF can be secured. Considering only the weight, the SCSG type FOWF is far superior to the PMSG type FOWF. With the trend of falling superconducting wire prices and improving critical current, the SCSG type FOWF is expected to become a definite alternative to large-capacity wind farms, and the economic feasibility is expected within the next five years.

Graphical Abstract

1. Introduction

Wind power has now become the world’s fastest-growing source of renewable energy. According to the US Department of Energy, wind energy is expected to contribute to a significant portion of the U.S. electricity supply over the next 20 years [1]. Currently, the development of offshore wind technology, which has many advantages over the onshore wind, is actively progressing, and accordingly, the installed capacity is continuously increasing. However, if the support of the wind turbine is fixed to the seafloor, installation becomes difficult when the water depth is more than 50 m. Floating offshore wind turbine (FOWT) systems are no longer limited to maximum depth constraint (50 m) because they can be deployed in deep-sea areas with high wind energy utilization potential [2]. In terms of the design of a FOWT, as the weight of the wind generator increases, the size of the platform increases, and the total construction cost also increases. Therefore, in order to reduce the capital expenditure (CAPEX), an effective design technology that can reduce the volume and weight of the entire platform is required. The permanent magnet synchronous generator (PMSG) is most often used for MW class wind power generation because of its high efficiency [3,4,5,6,7]. However, the development and installation of wind turbines of 10 MW or more suffer from the high weight of the wind generator. As an alternative to solving these problems, a superconducting synchronous generator (SCSG) has been proposed. The high magnetic field strength generated by the superconducting coil is expected to provide a lighter and more compact direct-drive design than those implemented in copper coils, permanent magnets, and magnetic iron [8]. In the case of a superconducting generator, the EcoSwing project was carried out in Europe until 2019 [9]. In this project, a full-scale 3.6 MW direct-drive SCSG was designed, manufactured, and tested.
The SCSG has the advantages of having a small volume, lightweight, and high efficiency compared to the conventional PMSG type generators. However, compared to the conventional generator, the SCSG has a cost issue because it includes a superconducting wire and a cooling system, and a superconducting wind turbine is almost twice the price of a conventional wind turbine. To prove the suitability of FOWT, it is necessary to compare the economic feasibility of the PMSG and SCSG types FOWTs. Regarding the economic analysis of wind turbines using various types of generators, reference [10] estimated the CAPEX of a 10 MW direct-drive wind turbine using only an SCSG, without comparing it to the PMSG type. Reference [11] also presented a model related to design cost and scaling that can be used when developing an SCSG, but they did not compare with the PMSG method. Reference [12] aimed to develop a methodology for determining the economic feasibility of a floating offshore wind farm (FOWF) but did not compare different types of generators. Reference [13] conducted a study comparing 12 MW class PMSG type and SCSG type wind turbine, but an economic analysis was not conducted including the floating structures. In order to appeal to the economic feasibility of a large-scale FOWF, it is necessary to compare the economic feasibility of the SCSG type FOWF with other existing generator types.
This paper compared the economic feasibility of FOWFs consisting of two types of generators. In order to compare economic feasibility, the structure of generators of the PMSG and SCSG types was investigated, and the scaling equation was studied to scale up the capacity to 10 MW. The levelized cost of energy (LCOE) has been calculated taking into account the different types of generators, which means a measure from an economic point of view used to compare the lifetime costs of electricity production. Depending on the type of FOWT, there are differences in the CAPEX and operating costs, so we analyzed and compared the economic feasibility of each floater type. For the PMSG and SCSG types FOWTs, the cost of the FOWT was calculated by considering the difference in the weight and volume of the turbine. Moreover, the economic feasibility of a FOWF was analyzed based on the composition of the wind farm. The nacelle mass of the 10 MW class PMSG type FOWT is 542.6 tons and that of the SCSG type FOWT is 335.0 tons. The reduction in nacelle mass has reduced the cost of wind turbine-related items including transportation and installation, mooring systems, and infrastructures. The LCOE of the PMSG type FOWF was calculated as 206.78 (USD/MWh) and that of the SCSG type FOWT was calculated as 212.88 (USD/MWh), due to the reduction in turbine weight. Looking at the trend of superconducting wire prices over the past five years, the price is falling rapidly. Considering this trend of the price decline, it is possible to cut the price by 40% in the near future. Then, the LCOE of the SCSG type FOWT is expected to be 205.56 (USD/MWh), securing the economic feasibility. The lighter weight makes it possible to operate the wind turbine more safely, and the design, transport, and installation of the tower that can support the nacelle become easier. Therefore, we are confident that the SCSG can be an effective alternative to large-scale FOWFs.

2. A 10 MW Class FOWT System

2.1. The FOWF Platforms

The current FOWF in operation is Hywind Scotland 30 MW, the world’s first FOWF [14]. It consists of 6 MW class wind turbines using the spar-buoy concept. Moreover, WindFloat Atlantic, the world’s first semi-submersible FOWF is fully operated with a total installed capacity of 25 MW using an 8.4 MW wind turbine [15]. In addition to this, the construction of the 88 MW Hywind Tampen using the Siemens Gamesa 8 MW turbine with a spar-buoy floating system began in October 2020 [16], and a 10 MW FOWT is still under development.
In this paper, we reviewed several platform types to design a 10 MW FOWT system. The FOWT systems are generally classified into spar-buoy, semi-submersible, and tension leg platforms (TLP) [17,18,19,20], as shown in Figure 1. As a characteristic of each FOWT system, the spar-buoy has a very large cylindrical buoy, and the semi-submersible is a structure that secures the necessary stability by combining the main principles of spar-buoy + TLP. The TLP consists of a semi-submersible in a highly buoyant structure, and several tensioned mooring lines are attached to the structure and anchored to the seabed to increase buoyancy and stability [20].
The 10 MW FOWT platform is being developed at the University of Ulsan as part of a joint research project in Korea based on the National Renewable Energy Laboratory (NREL) 5 MW floating concept [21,22,23,24]. Analysis by type showed that the spar-buoy had greater nacelle acceleration, load on wind turbines, and platform pitch than the semi-submersible and TLP, and mooring tension of the TLP was greater than that of the semi-submersible and spar-buoy. The semi-submersible was analyzed to be the most stable than the spar-buoy and TLP. Based on these findings, the semi-submersible type was selected as the platform type of a 10 MW FOWT.
Table 1 shows the specifications of the PMSG and SCSG designed with semi-submersible FOWT. The mass of the PMSG FOWT excluding the blade was calculated by referring to 10 MW of International Energy Agency (IEA) fixed offshore wind turbine [25]. The blade mass of the PMSG FOWT was calculated as the same value as the SCSG FOWT, and the mass of the SCSG FOWT was calculated through a joint research project [21].

2.2. Characteristic Comparison of the PMSG and SCSG Applied to 10 MW Class Wind Turbines

The larger the unit capacity of a wind turbine has more advantages, but as its weight increases, it is very difficult to install and maintain a tall tower capable of supporting a huge nacelle. Moreover, it is more difficult to install and operate at sea, not on land. In addition, as mass is added, the total cost also increases, limiting commercial viability. The SCSG has caught the attention of researchers as a solution to this problem. The SCSG can overcome the limitations of conventional PMSG through its lightweight and compact volume. At the same length, superconducting wires can acquire more magnetic fields than copper wires, making them more compact, which leads to easy transportation, reduced installation and maintenance costs. Figure 2 shows the size comparison of the PMSG and SCSG of the same capacity.
By applying the SCSG, it is possible to design nacelles and supporting structures that can be safely operated by reducing the weight, and in the case of the FOWT, the size of the platform is reduced, which affects the reduction of CAPEX. In addition, rare earth requirements increase significantly with increasing the PMSG capacity, which leads to economic dependence on countries that exclusively own these resources. This problem can be reduced by using the SCSG. High-capacity wind turbines tend to use gearless types due to gearbox maintenance issues. The 10 MW gearless type generator uses a synchronous generator, so it is much larger and heavier than a geared type generator. Therefore, in the event of a breakdown of a large and heavy generator, it takes more time to repair, and due to the weight of the generator, there are few cranes that can lift a 10 MW PMSG. The SCSG requires a cooling system to maintain cryogenic temperatures, resulting in additional Operation & Maintenance (O&M) costs for the cooling system compared to the PMSG, which does not require a low-temperature cooler. In order to compare the PMSG and SCSG in terms of cost, we calculated the generator manufacturing cost. In the case of the PMSG, since the price of the generator calculated by the scaling equation is different from the price trend of the large-capacity generator, it was corrected through literature review. The total cost of 10 MW class PMSG was estimated at USD 7 million, and that of the SCSG was calculated taking into account the price of the SCSG components [26]. The SCSG’s rotor consists of 10 modules and includes four coils per module. Table 2 shows the price of one rotor module.
The price of the SCSG, taking into account all components, the stator, and 10 rotor modules, is given in Table 3. Comparing the price of the two generators, the PMSG price is 7.0 (MUSD) and the SCSG price is 14.2 (MUSD), respectively.
The weights of the PMSG and SCSG were 323 tons and 120 tons, respectively. The SCSG weight was close to one-third of the PMSG weight, but the price doubled as shown in Figure 3.
The big difference in price between the PMSG and SCSG is due to the price of superconducting wire. Figure 4 shows the ratio of the SCSG generator components to cost. The 10 MW class SCSG was designed with superconducting wires from two companies in consideration of economy and performance. The superconducting wire was composed of 4182 m from company A and 5662 m from B. The average price of a superconducting wire applied to the 10 MW SCSG is USD 76.6 per meter. Therefore, the total price of the superconducting wire applied to the 10 MW SCSG design is USD 0.68 million, accounting for about 55% of the price of one rotor module and 50% of the total price of the SCSG. For this reason, the SCSG still has an obstacle to commercialize in terms of price.

2.3. Economic Feasibility Study of the PMSG Type FOWF and the SCSG Type FOWF

To analyze the economic feasibility of a FOWF with different types of generators, the LCOE of each FOWF was calculated. The LCOE is a measure of the average net present cost of electricity generation for a generating plant over its lifetime [27]. The LCOE is calculated as the ratio of all the discounted costs over the lifetime of an electricity generating plant divided by the discounted sum of the actual amount of energy delivered [28].
The LCOE was calculated as follows:
L C O E = I C C × F C R A E P + A O E
where
  • FCR = fixed charge rate (1/year)
  • ICC = initial capital cost (USD)
  • AEP = net annual energy production (kWh/year)
  • AOE = annual operating expenses = (LLC + O&M + LRC)/AEP
  • LLC = land lease cost
  • O&M = levelized operating and management cost
  • LRC = levelized replacement/overhaul cost
The PMSG and SCSG type FOWTs were scaled up based on the NREL 5 MW OC4 wind turbine considering the floating type. The 10 MW FOWT has an aerodynamic rotor diameter of 178.2 m and a rated rotational speed of 9.69 rpm. Both types of generators were considered direct-driven. The specifications of a 10 MW class FOWT are shown in Table 4.
The FOWF has a capacity of 200 MW and is located 58 km from the coast. Components of the FOWF include FOWT, converter station, and submarine cables. Considering the distance to the shore, the transmission system was chosen as an High Voltage Direct Current (HVDC) system. Collection and transmission systems voltage levels were chosen as 66 kV and 154 kV, respectively, taking into account the cable rating as shown in Figure 5.
The offshore wind farm topologies include a radial topology, a single-sided ring, a double-sided ring, and a star topology [29]. Topologies for the offshore wind farm collection system are proposed by previous researches [29,30,31]. The number of components of a FOWF depends on the topology. In this study, a radial configuration that is economical and easy to install was selected. To analyze the economic feasibility of a 10 MW class wind turbine, the cost was calculated based on the scaling equation studied in [32,33]. The platform of the FOWT for economic analysis is a semi-submersible type. For economic analysis, turbine capital cost (TCC), balance of station cost (BOS), initial capital cost (ICC), levelized replacement cost (LRC), land lease cost (LLC), operation and maintenance cost (O&M), capacity factor (CF), annual energy production (AEP), fixed-charge rate (FCR), the rotor diameter of the wind turbine (DWT), and the capacity of the wind turbine (CWT) were considered. The wind turbine components and the cost formulas for calculating the TCC are shown in Table 5. The cost formulas were referenced the NREL wind turbine design cost and scaling model, and the 10 MW wind turbine data were used to calculate the TCC by the scaling equation.
The CAPEX for wind turbines includes the TCC and BOS. The BOS of a wind turbine represents the total cost excluding turbine cost. The BOS was calculated including the substructure components based on a 10 MW wind turbine design [33]. The cost formulas for calculating the BOS are shown in Table 6.
Table 7 shows the items required for the calculation of the LCOE. Among the items, the ICC is the initial cost, and the LRC, the LLC, and the O&M are the factors of the annual cost. The CF is the average output power divided by the maximum power, and the AEP is the annual energy production. The FCR is covered by construction financing, financing fees, debt, equity returns, depreciation, income tax, property tax and insurance.
A contingency cost formula was defined considering the FOWT price is USD 4.9 million per MW due to the early stage domestic manufacturing technology of the FOWT. Due to the cooling system, the SCSG type FOWT adds 20% and 15% of the LRC and O&M costs, respectively [34]. In addition, the capacity factor of the FOWT was calculated as 44.3% through the Weibull distribution analysis based on the wind condition data measured at the sea of Ulsan, Korea [35]. The expansion from the floating system to the wind farm includes collection systems, converter stations, and transmission systems. Each element price was investigated to calculate including the components of the wind farm as shown in Table 8. The price of the dynamic submarine cable used in the FOWT was calculated taking into account the price 30–50% higher than the fixed type [36].
To calculate the operating expenditure (OPEX) of the FOWF, the items related to the operation and maintenance of wind turbines and cables were considered as shown in Table 9.
The O&M cost of the wind turbine was calculated based on the cost equation in the NREL report [39]. Assuming that the water depth is appropriate, the O&M cost of the semi-submersible type FOWT can be calculated as Equation (2).
y = 4.5907ln(x) + 48.827
where, x is the water depth and y is the O&M cost.
The collection cable loss cost was calculated as Equation (3) based on the AC cable [40].
C i n , l o s s = C E × 8760 × 10 5 × k = 1 N i n 3 ( C F · P F e e d e r , k 3 V i n p f ) 2 R i n · l i n , k
where, Cin,loss is the collection cable loss cost, CE is the energy generation cost per kWh, N i n is the number of collection system cable feeders, CF is the capacity factor, PFeeder,k is the sum of the rated capacity of the wind turbine installed at the kth feeder, V i n is the internal network voltage level, pf is the power factor, Rin is the resistance per unit length of the collection system cable, and lin,k is the kth collection system feeder cable length.
The cable O&M cost was calculated as Equation (4).
C m , t = C r e p a i r × ( k = 1 N i n λ i n l i n , k + λ e x l e x N e x )
where, Cm,t is the cable O&M cost, Crepair is the repair cost in case of one failure of cable, λ i n   a n d   λ e x are the annual failure rate per unit length of the collection system and transmission system cable, l e x is the transmission cable length, and N e x is the number of transmission system cable lines.
The cost of energy not supplied was calculated as Equations (5) and (6).
C E N S = C E × 10 5 × ( k = 1 N m C F · P F e e d e r , k U i n , k + C F · P O W F U e x )
U = 8760 × λ μ × l
where CENS is the cost of energy not supplied, P O W F is the capacity of the wind farm, and U i n , k and U e x are the collection system and the transmission system cable repair rates.

3. Study Results and Discussions

3.1. The CAPEX of the PMSG and SCSG Type FOWFs

To analyze the economic feasibility of the 200 MW class FOWF, it is necessary to calculate the CAPEX of the FOWT constituting the wind farm. The CAPEX of the PMSG and SCSG type FOWTs can be estimated based on the cost scaling formulas [32,33], as shown in Table 10. In the case of the SCSG type FOWT, the cost scaling was performed considering that the nacelle mass was close to that of the 6 MW conventional PMSG type wind turbine due to the reduction of top head weight. Items including nacelle cover, mooring system, and substructure were scaled to 6 MW. Transportation and installation cost was calculated as 20% of the fixed offshore wind turbine [41].
The 10 MW PMSG type FOWT was calculated as 49 (MUSD), and the 10 MW SCSG type FOWT was calculated as 50 (MUSD). Including the calculated FOWT, the CAPEX of the 200 MW class wind farm consisting of 20 turbines of 10 MW wind turbine was calculated based on the cost formulas of the FOWF components as shown in Table 11.
Except for the FOWT, the wind farm component prices were the same for the PMSG type and the SCSG type, but because the price of the SCSG type FOWT is slightly higher, the total cost of the 200 MW class FOWF was about 20 (MUSD) higher for the SCSG type than the PMSG type.

3.2. The OPEX of the PMSG and SCSG Type FOWFs

The OPEX of the PMSG and SCSG types FOWFs can be estimated based on the OPEX cost scaling formulas. Cost data is required for price calculation, which is shown in Table 12. The OPEX of the 200 MW class FOWF was calculated by the wind turbine O&M equation shown in Table 7 and Equations (2)–(6), and calculation results are shown in Table 13.

3.3. Comparison Results of Economic Analysis of the PMSG and SCSG Type FOWFs

The CAPEX of the PMSG and SCSG type FOWTs were compared, as shown in Figure 6. In the case of the TCC, the SCSG type FOWT was about 1.1 (MUSD/MW) higher than that of the PMSG type FOWT. In the case of the BOS, 0.57 (MUSD/MW) was saved due to the reduction of the top head weight of the SCSG type. However, the total CAPEX of the SCSG was about 0.54 (MUSD/MW) higher than that of the PMSG.
When comparing the OPEX, the SCSG type FOWT adds additional replacement cost and maintenance cost for the cooling system. Therefore, the SCSG type FOWT was about 1.1 (MUSD/MW·year) higher than the PMSG type FOWT in total OPEX, as shown in Figure 7.
A comparison study of the PMSG type FOWF and the SCSG type FOWF was conducted to evaluate the economic feasibility of a large-scale FOWF, and the results are shown in Table 14. The LCOE of the FOWF was calculated and compared by reflecting the components of the FOWF.
To determine the possibility of securing the economic feasibility of the SCSG type FOWF, the cost trend of superconducting wire, which has a great influence on the economy, was reviewed. Superconducting wire prices have fallen from USD 150/kA m in 2014 to USD 83/kA m in 2019 (kA m: the price of a 1 m wire with a critical current of 1 kA), as shown in Table 15 [42,43]. The drop in superconducting wire prices is due to an increase in critical current. According to SuNAM, the critical current for a 10 mm superconducting wire was 355 A in 2012, but now it is 616 A, an increase of 74% as shown in Figure 8, which has become a factor that could reduce the cost of the wire to 55.33%. Therefore, it is expected that the price will reach 40% lower than the current price within the next five years, and based on this, the LCOE was calculated by applying 40% of the wire cost to confirm the economic feasibility of the 10 MW generator. As a result, the LCOE of the SCSG type FOWF was 1.2 (USD/MWh) lower than the PMSG type FOWF as shown in Table 16.
Economic feasibility evaluation reflecting the financial assumption was performed to confirm whether the PMSG type FOWF and the SCSG type FOWF can earn profits during the operation period. The financial assumptions for the evaluation of the economic feasibility were considered the domestic Renewable energy supply certification (REC) system. The REC weight was calculated considering the distance, which is over 15 km from the coast. The financial assumptions required for the economic feasibility study are shown in Table 17.
The evaluation results of the economic feasibility are shown in Table 18. As a result of the evaluation of the economic feasibility reflecting financial assumption, Net Present Values (NPVs) of the PMSG and SCSG types FOWFs after tax were calculated as USD 607,455 and USD 468,810, respectively. Moreover, Internal Rate of Return (IRRs) of the PMSG and SCSG types FOWFs after tax were calculated as 5.98% and 5.34%, respectively. NPV of the PMSG type FOWF has a positive value from 15 years, and NPV of the SCSG type FOWF has a positive value from 16 years. Because the low operating cost of the PMSG type FOWF has caused NPV to reverse SCSG type FOWF from 10 years, the IRR of the PMSG type FOWF was higher than the SCSG type FOWF. It is worth investing in both FOWF projects because both IRR results are higher than the standard IRR of 4.5%.
The LCOE calculation results of the PMSG type FOWF and the SCSG type FOWF were 206.78 (USD/MWh) and 212.88 (USD/MWh), respectively. According to calculation results, the PMSG and SCSG type FOWFs have a lower LCOE than that of Hywind Scotland wind farm in Scotland, UK operated by Hywind (Scotland) Limited, which has a range of 241.52~277.75 (USD/MWh) [46]. However, the LCOE of the SCSG type FOWF was still more expensive than that of the PMSG type FOWF. Looking at the trend of superconducting wire prices over the past five years, the price is falling rapidly. Considering the trend of the price decline, the LCOE of the SCSG type FOWF can reach 205.56 (USD/MWh) and the economic feasibility is expected within the next five years.

4. Conclusions

In this paper, the economic value of the PMSG and SCSG type FOWFs were analyzed and compared. The structure of the 10 MW class FOWT was designed through a joint research project in Korea. The platform for the 10 MW class FOWT was chosen as semi-submersible and expanded on the basis of the NREL floating concept. The PMSG and SCSG were compared in terms of weight, volume, operation, and cost to find the difference between the two generators applied to large wind turbines. In terms of weight, the SCSG type has been shown to be far more advantageous for the design of large wind farms. Because the SCSG is light, it is advantageous in terms of operation and maintenance but has the disadvantage of requiring additional consideration for maintenance of the cooling system.
To compare the two types of FOWF economically, the CAPEX and OPEX of a 10 MW class FOWT were calculated through a cost scaling equation. LCOE is calculated to compare the economics of the PMSG type FOWF and the SCSG type FOWF. As calculated, the SCSG type FOWF was 6.1 (USD/MWh) more expensive for LCOE than the PMSG type FOWF. When the cost of the superconducting wire of a 10 MW generator is reduced by 40%, the LCOE of the SCSG type FOWF is lowered by 1.2 (USD/MWh) than the PMSG type FOWF. In addition, during the operating period, we conducted an economic evaluation that reflects financial assumptions so that the PMSG type FOWF and the SCSG type FOWF can generate profits. After tax, the IRR calculation results for the PMSG type FOWF and the SCSG type FOWF were 5.98% and 5.34%, respectively. These results are higher than the standard IRR of 4.5%, confirming that it is worth investing in the 200 MW PMSG type FOWF project and SCSG type FOWF project with a 40% reduction in the cost of the superconducting wire. Considering the performance improvement and price decline of superconducting wires, the economic feasibility of the SCSG type FOWF is expected to be secured in the near future.

Author Contributions

Methodology, investigation, formal analysis, writing—original draft preparation, G.-E.J.; validation, G.-E.J., M.-C.D., and H.S.; formal analysis, data curation, G.-E.J. and H.-J.S.; writing—review and editing, M.-C.D.; project administration, H.-J.S.; supervision, M.P. All authors have read and agreed to the published version of the manuscript.

Funding

This research was supported by Korea Electric Power Corporation. (Grant number: R18XA03). This work was supported by the Korea Institute of Energy Technology Evaluation and Planning (KETEP) grant funded by the Korea government(MOTIE). (Grant number: 20203010020050).

Institutional Review Board Statement

Not applicable.

Informed Consent Statement

Not applicable.

Data Availability Statement

Not applicable.

Conflicts of Interest

The authors declare no conflict of interest.

Abbreviations

PMSGPermanent magnet synchronous generator
SCSGSuperconducting synchronous generator
FOWTFloating offshore wind turbine
FOWFFloating offshore wind farm
LCOELevelized cost of energy
CAPEXCapital expenditures
OPEXOperating expenditures
FCRFixed charge rate
ICCInitial capital cost
AEPAnnual energy production
AOEAnnual operating expenses
LLCLand lease cost
O&MLevelized operating and management cost
LRCLevelized replacement/overhaul cost
TCCTurbine capital cost
BOSBalance of station cost
DWTRotor diameter of wind turbine
CWTCapacity of the wind turbine
SMPSystem marginal cost
RECRenewable energy certificate

References

  1. Amano, R.S. Review of Wind Turbine Research in 21st Century. J. Energy Resour. Technol. 2017, 5, 1–8. [Google Scholar] [CrossRef]
  2. Leimeister, M.; Kolios, A.; Collu, M. Critical review of floating support structures for offshore wind farm deployment. In Proceedings of the 15th Deep Sea Offshore Wind R&D Conference, Trondheim, Norway, 17–19 January 2018. [Google Scholar]
  3. Sindhya, K.; Manninen, A.; Miettinen, K.; Pippuri, J. Design of a Permanent Magnet Synchronous Generator Using Interactive Multiobjective Optimization. IEEE Trans. Ind. Electron. 2017, 64, 9776–9783. [Google Scholar] [CrossRef]
  4. Dehghan, S.M.; Mohamadian, M.; Varjani, A.Y. A new variable-speed wind energy conversion system using permanent-magnet synchronous generator and Z-source inverter. IEEE Trans. Energy Convers. 2009, 24, 714–724. [Google Scholar] [CrossRef]
  5. Nakano, M.; Kometani, H. A study on eddy-current losses in rotors of surface permanent-magnet synchronous machines. IEEE Trans. Ind. Appl. 2006, 42, 429–435. [Google Scholar] [CrossRef]
  6. Wei, Q.; Liyan, Q.; Ronald, G.H. Control of IPM synchronous generator for maximum wind power generation considering magnetic saturation. IEEE Trans. Ind. Appl. 2009, 45, 1095–1105. [Google Scholar]
  7. Scott, S.R.; Polikarpova, M.; Röyttä, P.; Alexandrova, J.; Pyrhönen, J.; Nerg, J.; Mikkola, A.; Backman, J. Direct-drive permanent magnet generators for high-power wind turbines: Benefits and limiting factors. IET Renew. Power Gener. 2012, 6, 1–8. [Google Scholar] [CrossRef]
  8. Kalsi, S.S.; Weeber, K.; Takesue, H.; Lewis, C.; Neumueller, H.W.; Blaughe, R.D. Development status of rotating machines employing superconducting field windings. Proc. IEEE 2004, 92, 1688–1704. [Google Scholar] [CrossRef]
  9. Winkler, T. The EcoSwing Project. In Proceedings of the IOP Conference Series: Materials Science and Engineering, 27th International Cryogenics Engineering Conference and International Cryogenic Materials Conference (ICEC-ICMC 2018), Oxford, UK, 3–7 September 2018. [Google Scholar]
  10. Hamid, N.A.; Suparin, M.F.; Gokila, T.; Ewe, L.S. Design Cost and Scaling Model of Superconducting Wind Turbine Generator for Electricity Generation. Appl. Mech. Mater. 2014, 564, 758–763. [Google Scholar] [CrossRef]
  11. Abrahamsen, A.B.; Dong, L.; Magnusson, N.; Thomas, A.; Azar, Z.; Stehouwer, E.; Hendriks, B.; Zinderen, G.J.V.; Deng, F.; Chen, Z.; et al. Comparison of Levelized Cost of Energy of Superconducting Direct Drive Generators for a 10-MW Offshore Wind Turbine. IEEE Trans. Appl. Supercond. 2018, 28, 1–5. [Google Scholar] [CrossRef]
  12. Santos, L.C. Economic feasibility of floating offshore wind farm. Energy 2016, 112, 868–882. [Google Scholar] [CrossRef]
  13. Technical Issue of 10MW Class Superconducting Wind Power Generator. Available online: http://www.see.eng.osaka-u.ac.jp/seeqb/seeqb/ALCAconf/PM/04(Minwon%20Park).pdf (accessed on 15 February 2021).
  14. Hywind Scotland-Equinor.com. Available online: https://www.equinor.com/en/what-we-do/floating-wind/hywind-scotland.html (accessed on 14 January 2021).
  15. World’s First Semi-Submersible Floating Wind Farm Now Online. Available online: https://www.oedigital.com/news/480465-world-s-first-semi-submersible-floating-wind-farm-now-online (accessed on 18 January 2021).
  16. Hywind Tampen-floating Wind Power Project-Equinor.com. Available online: https://www.equinor.com/en/what-we-do/hywind-tampen.html (accessed on 14 January 2021).
  17. Stehly, T.; Beiter, P.; Duffy, P. 2019 Cost of Wind Energy Review; Technical Report No. NREL/TP-5000-78471; National Renewable Energy Laboratory (NREL): Golden, CO, USA, December 2020. [Google Scholar]
  18. Taboada, J.V. Comparative Analysis Review on Floating Offshore Wind Foundations (FOWF). In Proceedings of the 54th Naval Engineering and Maritime Industry Congress, Ferrol, Spain, 14–16 October 2015. [Google Scholar]
  19. The Crown Estate–UK Market Potential and Technology Assessment for Floating Offshore Wind Power: An Assessment of the Commercialization Potential of the Floating Offshore Wind Industry. Available online: http://pelastar.com/wp-content/uploads/2015/04/uk-floating-offshore-wind-power-report.pdf (accessed on 17 February 2021).
  20. Deep Water: The Next Step for Offshore Wind Energy. A report by the European Wind Energy Association. Available online: https://www.researchgate.net/publication/257553940_Deep_Water_The_next_step_for_offshore_wind_energy_A_report_by_the_European_Wind_Energy_Association (accessed on 17 February 2021).
  21. Park, M.; Sung, H.J.; Go, B.S.; Lee, S.J.; Shin, H.K.; Kim, H.; Kim, H.M.; Shin, H.S.; Kim, S.H.; Yu, I.K. An Innovative Wind Project on the Development of HTS Magnet, Test Facility, Offshore Floating System, and Network Connection Technologies for 10 MW Class Wind Power System Fully Sponsored by KEPCO. In Proceedings of the IEEE CSC & ESAS Superconductivity News Forum (global edition), Seattle, DC, USA, 28–5 October–November 2019. [Google Scholar]
  22. Jonkman, J. Definition of the Floating System for Phase IV of OC3 (No. NREL/TP-500-47535); National Renewable Energy Lab. (NREL): Golden, CO, USA, 2010. [Google Scholar]
  23. Robertson, A.; Jonkman, J.; Masciola, M.; Song, H. Definition of the Semisubmersible Floating System for Phase II of OC4 (No. NREL/TP-5000-60601); National Renewable Energy Lab. (NREL): Golden, CO, USA, 2014. [Google Scholar]
  24. Ahn, H.; Shin, H. Experimental and Numerical Analysis of a 10 MW Floating Offshore Wind Turbine in Regular Waves. Energies 2020, 10, 2608. [Google Scholar] [CrossRef]
  25. Bortolotti, P.; Tarr´es, H.C.; Dykes, K.; Merz, K.; Sethuraman, L.; Verelst, D.; Zahle, F. IEA Wind TCP Task 37: Systems Engineering in Wind Energy-WP2.1 Reference Wind Turbines; International Energy Agency (IEA): Paris, France, 2019. [Google Scholar]
  26. Moghadam, F.K.; Nejad, A.R. Evaluation of PMSG-based drivetrain technologies for 10-MW floating offshore wind turbines: Pros and cons in a life cycle perspective. Wind Energy 2020, 23, 1542–1563. [Google Scholar] [CrossRef]
  27. Levelized Cost of Energy–Wikipedia. Available online: http://en.wikipedia.org/wiki/Levelizedcostofenergy (accessed on 9 January 2021).
  28. Lai, C.S.; McCulloch, M.D. Levelized cost of electricity for solar photovoltaic and electrical energy storage. Appl. Energy 2017, 190, 191–203. [Google Scholar] [CrossRef]
  29. Gil, M.D.P. Design, Operation and Control of Novel Electrical Concepts for Offshore Wind Power Plants. Ph.D. Thesis, Universitat Politècnica de Catalunya, Barcelona, Spain, April 2014. [Google Scholar]
  30. Mogstad, A.B.; Molinas, M. Power collection and integration on the electric grid from offshore wind parks. In Proceedings of the Nordic Workshop on Power and Industrial Electronics (NORPIE), Espoo, Finland, 9–11 June 2008. [Google Scholar]
  31. Franken, B.; Breder, H.; Dahlgren, M.; Nielsen, E. Collection grid topologies for off-shore wind parks. In Proceedings of the CIRED 2005-18th International Conference and Exhibition on Electricity Distribution, Turin, Italy, 6–9 June 2005. [Google Scholar]
  32. Chung, T.; Moon, S.; Rim, C. A Study on the Estimation Model of Cost of Energy for Wind Turbines. New Renew. Energy 2012, 8, 4. [Google Scholar]
  33. Heidari, S. Economic Modelling of Floating Offshore Wind Power. Master’s Thesis, Mälardalen University, Västerås and Eskilstuna, Sweden, 2017. [Google Scholar]
  34. Kim, J.Y. A economic feasibility of HTS cable by estimating the life-cycle cost. In Proceedings of the KIEE Conference, Busan, Korea, 14–16 July 2004. [Google Scholar]
  35. Yu, Y.J.; Shin, H.K. Motion Performances of 5-MW Floating Offshore Wind Turbine under Combined Environmental Conditions in the East Sea, Korea. In Proceedings of the European Energy Research Alliance (EERA) DeepWind’2019, Trondheim, Norway, 16 January 2019. [Google Scholar]
  36. D3.1 Review of the State of the Art of Dynamic Cable System Design. Available online: https://corewind.eu/wp-content/uploads/files/publications/COREWIND-D3.1-Review-of-the-state-of-the-art-of-dynamic-cable-system-design.pdf (accessed on 15 January 2021).
  37. Collin, A.J.; Nambiar, A.J.; Bould, D.; Whitby, B.; Moonem, M.A.; Schenkman, B.; Atcitty, S.; Chainho, P.; Kiprakis, A.E. Electrical components for marine renewable energy: A Techno-Economic Review. Energies 2017, 12, 1973. [Google Scholar] [CrossRef] [Green Version]
  38. Hur, D. Economic Considerations Underlying the Adoption of HVDC and HVAC for the Connection of an Offshore Wind Farm in Korea. JEET 2012, 7, 154–162. [Google Scholar] [CrossRef] [Green Version]
  39. Beiter, P.; Stehly, T. A Spatial-Economic Cost-Reduction Pathway Analysis for U.S. Offshore Wind Energy Development from 2015–2030; (No. NREL/TP-6A20-66579); National Renewable Energy Lab. (NREL): Golden, CO, USA, 2016. [Google Scholar]
  40. Won, J.N. A Study on Siting of HVAC Offshore Substation for Wind Power Plant using Submarine Cable Cost Model. Trans. Korean Inst. Electr. Eng. 2013, 62, 451–456. [Google Scholar] [CrossRef] [Green Version]
  41. James, R.; Ros, M.C. Floating Offshore Wind: Market and Technology Review; Carbon Trust: London, UK, 2015. [Google Scholar]
  42. Moon, S.H. HTS Development and Industrialization at SuNAM, Supercond. Nano & Advanced Materials. In Proceedings of the 1st Workshop on Accelerator Magnets in HTS, Hamburg, Germany, 21–23 May 2014. [Google Scholar]
  43. Convenor, M.N.; Hayakawa, N. Common Characteristics and Emerging Test Techniques for High Temperature Superconducting Power Equipment; (Working Group D1.38); CIGRE: Brochure, France, 2015. [Google Scholar]
  44. SuNAM Co., Ltd.’s Second-Generation High-Temperature Superconducting Long Wire Manufacturing Technology Status and Commercialization Prospects. Available online: https://www.ceramist.or.kr/upload/pdf/ceramist-2012-15-6-16.pdf (accessed on 17 February 2021).
  45. Ha, H.; Kim, G.; Noh, H.; Lee, J.; Moon, S.; Oh, S.S. Fabrication of 1 m long multi layered superconducting coated conductor with high engineering critical current density. IOP Publ. Supercond. Sci. Technol. 2020, 33. [Google Scholar] [CrossRef]
  46. Realizing Floating Offshore Wind. Available online: https://www.eksportkreditt.no/wp-content/uploads/2020/03/Flytende-havvind-for-%C3%A5-dekarbonisere-norsk-sokkel-hva-skal-til.pdf (accessed on 17 February 2021).
Figure 1. Three major types of floating offshore wind turbine (FOWT).
Figure 1. Three major types of floating offshore wind turbine (FOWT).
Energies 14 01386 g001
Figure 2. Comparison of the size of the permanent magnet synchronous generator (PMSG) and superconducting synchronous generator (SCSG) [14].
Figure 2. Comparison of the size of the permanent magnet synchronous generator (PMSG) and superconducting synchronous generator (SCSG) [14].
Energies 14 01386 g002
Figure 3. Comparison of the PMSG and SCSG; (a) weight of the PMSG and SCSG and (b) cost of the PMSG and SCSG.
Figure 3. Comparison of the PMSG and SCSG; (a) weight of the PMSG and SCSG and (b) cost of the PMSG and SCSG.
Energies 14 01386 g003
Figure 4. Cost ratio of the SCSG and the rotor module; (a) cost ratio of components in the generator and (b) cost ratio of components in the rotor modules.
Figure 4. Cost ratio of the SCSG and the rotor module; (a) cost ratio of components in the generator and (b) cost ratio of components in the rotor modules.
Energies 14 01386 g004
Figure 5. Configuration of the 200 MW monopolar HVDC system for the FOWF.
Figure 5. Configuration of the 200 MW monopolar HVDC system for the FOWF.
Energies 14 01386 g005
Figure 6. The CAPEX of the PMSG and SCSG type FOWTs.
Figure 6. The CAPEX of the PMSG and SCSG type FOWTs.
Energies 14 01386 g006
Figure 7. The OPEX of the PMSG and SCSG type FOWTs.
Figure 7. The OPEX of the PMSG and SCSG type FOWTs.
Energies 14 01386 g007
Figure 8. The critical current trend of the superconducting wire [44,45].
Figure 8. The critical current trend of the superconducting wire [44,45].
Energies 14 01386 g008
Table 1. Data of the 10 MW class FOWT for the platform design.
Table 1. Data of the 10 MW class FOWT for the platform design.
ItemsPMSG Type 10 MW SCSG Type 10 MW
Rated power [MW]1010
Blade radius [m]89.189.1
Cut-in wind speed [m/s]43
Rated wind speed [m/s]1111.3
Cut-out wind speed [m/s]2525
Single blade mass [kg]32,51232,512
Nacelle mass [kg]542,600335,000
Tower mass [kg]628,442610,084
Table 2. Cost of one rotor module for 10 MW class SCSG.
Table 2. Cost of one rotor module for 10 MW class SCSG.
Main PartComponents/RemarkQuantityCost (USD)
Rotor module (1 module)Cryostat162,730
Bobbin12386,400
Current lead21000
Current feedthrough terminal2692
Terminal joint2300
FRP supporter810,702
Radiation shield14000
Vacuum pump14000
Temperature sensor2011,800
Hall sensor (low temperature)46400
Vacuum sensor and Monitor11500
Current feed through31050
Superconducting wire9844375,259
MLI4302,946
Others (Nitrogen, tools, and accessories)463,820
Total cost 1,232,599
Table 3. Cost for the 10 MW class SCSG.
Table 3. Cost for the 10 MW class SCSG.
Main PartMaterialWeight/UnitCost (USD)
Rotor body (Back iron)35PN25010,600 kg110,770
Rotor modules (rotor poles)HTS module10 modules12,325,986
Stator coilsCopper25,900 kg414,400
Stator body35PN25040,800 kg426,360
CryocoolerStirling cryocooler 854,511
Torque disk 3500 kg45,500
Generator cover 13,500 kg15,337
Total cost 14,192,863
Table 4. Specifications of the 10 MW class FOWT.
Table 4. Specifications of the 10 MW class FOWT.
ItemsValue
Rated power [MW]10
Rated wind speed [m/s]11.3
Rotation speed [rpm]9.69
Blade length [m]89.1
Rotor diameter [m]178.2
Hub height [m]120
Tower height [m]102.5
Mass density of air [kg/m3]1.225
Table 5. Cost formulas for turbine capital cost (TCC) of the FOWT [32].
Table 5. Cost formulas for turbine capital cost (TCC) of the FOWT [32].
ComponentsMass FormulasCost Formulas
RotorBlades- ( 0.4019 D WT 3 955.24 + 2.7445 D WT 2.5025 ) ( 1 0.28 )
Hub- h u b   m a s s × 4.25
Pitch bearing 0.954 × t o t a l   t h r e e   b l a d e   m a s s + 491.31 2.28 × ( 0.2106 × D WT 2.6578 )
Pitch system ( T o t a l   p i t c h   b e a r i n g   m a s s × 1.328 ) + 555
Spinner, Nose cone 18.5 × D WT 520.5 N o s e   c o n e   m a s s × 5.57
Drive train, NacelleLow-speed shaft 0.0142 × D WT 2.888 0.01 × D WT 2.887
Bearings D WT × 8 / 600 0.033 × 0.0092 × D WT 2.5 2 × b e a r i n g   m a s s × 17.6
Mech brakeBrake coupling cost/10 ( 1.9894 × C W T   [ k W ] 0.1141 )
Generator- C W T   [ k W ] × 219.33
Variable speed electronics- 79 × C W T × 1000
Yaw drive and Bearing 1.6 × ( 0.0009 × D WT 3.314 ) 2 × ( 0.0399 × D WT 2.964 )
Main frame 1.228 × D WT 1.953 627.28 × D WT 0.85
Platforms and Railings 0.125 × m a i n f r a m e   m a s s m a s s × 8.7
Electrical connections- 40 × C W T × 1000
Hydraulic and cooling system 0.08 × C W T × 1000 12 × C W T × 1000
Nacelle cover 11.537 × C W T × 1000 + 3849.7 ( n a c e l l e   c o s t / 10 )
Control, safety system, condition monitoring- 55 , 000
Tower 0.3973 × s w e p t   a r e a × h u b   h e i g h t 1414 T o w e r   m a s s × 1.50
Marinization- 13.5 %   o f   t u r b i n e   a n d   t o w e r   c o s t s
Table 6. Cost formulas for the balance of station cost (BOS) of the FOWTs [32,33].
Table 6. Cost formulas for the balance of station cost (BOS) of the FOWTs [32,33].
ComponentsPMSG Type FOWTSCSG Type FOWT
Contingency1,269,583 × C W T 1,269,583 × C W T
Insurance during construction43,858 × C W T 43,858 × C W T
Transport and installation272,140 × C W T 137,446 × C W T
Electrical interconnection490,520 × C W T 490,520 × C W T
Mooring system65,787 × C W T 39,473 × C W T
Substructure1,051,115 × C W T 630,669 × C W T
Project development173,124 × C W T 173,124 × C W T
Port and staging equipment20,000 × C W T 12,000 × C W T
Personal access equipment 60 , 000 × n u m b e r   o f   t u r b i n e 60 , 000 × n u m b e r   o f   t u r b i n e
Surety bond I C C × 0.03 I C C × 0.03
Table 7. Cost formulas for levelized cost of energy (LCOE) calculation of the wind turbine [32,34].
Table 7. Cost formulas for levelized cost of energy (LCOE) calculation of the wind turbine [32,34].
ItemsCost FormulasRemark
ICC T C C + B O S -
LRC 17 × C W T × 1000 The SCSG is added by 20% due to the cost of replacing the cooling system
LLC;
offshore bottom lease cost
0.00108 × A E P -
O&M 4.5907 ln ( x ) + 48.827
(x: water depth [m])
The SCSG is added by 15% due to the cooling system O&M cost
CF44.3%Selected by Weibull distribution analysis
AEP 365 × 24 × C F × C W T × 1000 -
FCR10.4%-
Table 8. Cost formulas for the FOWF components [37,38].
Table 8. Cost formulas for the FOWF components [37,38].
ClassificationsComponentsCost Formulas
Collection systemAC cable 1 , 070 , 000 × c o l l e c t i o n   s y s t e m   c a b l e   l e n g t h   p e r   k m
Collection cable installation cost 330 , 000 × c o l l e c t i o n   s y s t e m   c a b l e   l e n g t h   p e r   k m
Converter stationConverter station 130 , 000 × w i n d   f a r m   r a t i n g × 2 × 10 6
Transmission systemHVDC cable 620 , 000 × t r a n s m i s s i o n   s y s t e m   c a b l e   l e n g t h   p e r   k m
Transmission cable installation cost 494 , 000 × t r a n s m i s s i o n   s y s t e m   c a b l e   l e n g t h   p e r   k m
Table 9. Items used to calculate the operating expenditure (OPEX) of the FOWF.
Table 9. Items used to calculate the operating expenditure (OPEX) of the FOWF.
ClassificationsItems
Wind turbineWind turbine O&M cost
Wind farmCollection cable loss cost
Cable O&M cost
Energy not supplied cost
Table 10. The capital expenditure (CAPEX) of the 10 MW class PMSG and SCSG types FOWTs (unit: USD).
Table 10. The capital expenditure (CAPEX) of the 10 MW class PMSG and SCSG types FOWTs (unit: USD).
ComponentsPMSG Type FOWT CostSCSG Type FOWT Cost
RotorBlades2,047,1372,047,137
Hub340,000340,000
Pitch mechanism and bearing461,164461,164
Spinner, Nose cone15,46315,463
Drive train, NacelleLow speed shaft315,044315,044
Bearings321,641174,240
Mech brake19,89419,894
Generator7,017,18914,192,863
Variable speed electronics790,000790,000
Yaw drive and Bearing318,361318,361
Main frame51,37351,373
Platforms and Railings33,23933,239
Electrical connections400,000400,000
Hydraulic and cooling system120,000120,000
Nacelle cover115,41773,072
Control, safety system, condition monitoring55,00055,000
Tower942,663915,126
Marinization145,425145,425
TCC14,034,89720,755,943
Contingency12,695,82512,695,825
Insurance during construction438,583438,583
Transport and installation2,721,4001,374,464
Electrical interconnection4,905,2054,905,205
Mooring system657,875394,725
Substructure10,511,1516,306,691
Project development1,731,2491,731,249
Port and staging equipment200,000120,000
Personal access equipment60,00060,000
Surety bond930,0001,500,000
BOS35,271,28829,526,742
ICC49,306,18550,282,685
Table 11. CAPEX of the 200 MW class PMSG and SCSG types FOWFs (unit: USD).
Table 11. CAPEX of the 200 MW class PMSG and SCSG types FOWFs (unit: USD).
ClassificationsComponentsPMSG Type FOWF CostSCSG Type FOWF Cost
Wind turbineFOWTs (20 turbines)986,123,7061,005,653,704
Collection systemAC cable31,244,00031,244,000
Collection cable installation cost9,636,0009,636,000
Converter stationConverter station52,000,00052,000,000
Transmission systemHVDC cable143,840,000143,840,000
Transmission cable installation cost114,608,000114,608,000
Total cost 1,337,451,7061,356,981,704
Table 12. Data for calculating the OPEX of the FOWF.
Table 12. Data for calculating the OPEX of the FOWF.
ClassificationsItemsValue
Wind farmCapacity of the wind farm (MW)200
Voltage level of the collection system (kV)66
Voltage level of the transmission system (kV)154
Power factor0.95
Collection system cableCable installation cost (Cin) (MUSD/km)0.48
AC resistance (Ω/km)0.067
Failure rate (times/year·km)0.000705
Repair rate (times/year)6.083
Transmission system cableCable installation cost (Cex) (MUSD/km)0.61
Failure rate (times/year·km)0.0011
Repair rate (times/year)6.404
Energy generation cost (USD/kWh)0.073
Cable repair cost (MUSD/km)0.65
Table 13. OPEX of the PMSG and SCSG types FOWFs (unit: USD/year).
Table 13. OPEX of the PMSG and SCSG types FOWFs (unit: USD/year).
ItemsPMSG Type FOWF CostSCSG Type FOWF Cost
Wind turbine O&M cost13,493,45515,517,473
Collection cable loss cost626,187626,187
Cable O&M cost551,877551,877
Energy not supplied cost2,485,0202,485,020
Total cost17,156,53919,180,557
Table 14. The LCOE of the PMSG and SCSG type FOWFs.
Table 14. The LCOE of the PMSG and SCSG type FOWFs.
ItemsPMSG Type FOWFSCSG Type FOWF
Wind farm capacity (MW)200200
TCC (USD/MW)1,403,4902,075,594
BOS (USD/MW)3,527,1292,952,674
CAPEX (USD/MW)6,687,2596,784,909
OPEX (USD/MW)85,78395,903
FCR (%)10.410.4
AEP (MWh)776,136776,136
CF (%)44.344.3
LCOE (USD/MWh)206.78212.88
Table 15. The trend of the superconducting wire cost.
Table 15. The trend of the superconducting wire cost.
Years20142019Reduced Rate
Superconducting wire cost at 77 K150 (USD/kA m)83 (USD/kA m)55.33%
Table 16. The LCOE considering a 40% reduction in the superconducting wire cost of a 10 MW generator.
Table 16. The LCOE considering a 40% reduction in the superconducting wire cost of a 10 MW generator.
ItemsPMSG Type FOWFSCSG Type FOWF
Wind farm capacity (MW)200200
TCC (USD/MW)1,403,4901,721,544
BOS (USD/MW)3,527,1292,952,674
CAPEX (USD/MW)6,687,2596,511,897
OPEX (USD/MW)85,78395,903
FCR (%)10.410.4
AEP (MWh)776,136776,136
CF (%)44.344.3
LCOE (USD/MWh)206.78205.56
Table 17. The financial assumption for the evaluation of economic feasibility of the 200 MW class SCSG type FOWF.
Table 17. The financial assumption for the evaluation of economic feasibility of the 200 MW class SCSG type FOWF.
ParametersValue
SMP (USD/MWh)80
REC (USD/MW)48
REC weight3.26
Loan rate (%)70
Loan repayment period (year)10
Loan interest (%)2.5
Inflation rate (%)1.45
Depreciation (year)10
Corporation tax (%)22
Discount rate (%)4.5
Installation period (year)3
Operation period (year)25
Table 18. Evaluation results of economic feasibility of the 200 MW class PMSG and SCSG type FOWFs.
Table 18. Evaluation results of economic feasibility of the 200 MW class PMSG and SCSG type FOWFs.
PMSG Type FOWFSCSG Type FOWF
1st Year15th Year25th Year1st Year16th Year25th Year
AEP (MWh)-776,136776,136-776,136776,136
Energy price (USD/MWh)-252291-229241
Revenue (USD)-195,840226,164-177,822187,120
Operation cost (USD)-20,10023,213-22,79725,951
ICC (USD)1,339,573--1,286,172--
Loan balance (USD)937,701--900,320--
Loan interest (USD)23,443--22,508--
Loan payment (USD)23,443--22,508--
Corporate tax (USD)-250,374289,141-263,779296,890
After-tax cash flow (USD)−23,443137,077158,302-22,508120,920125,712
NPV (USD)−960,1343453607,455-921,85937,504468,810
IRR (%)--5.98--5.34
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Share and Cite

MDPI and ACS Style

Jung, G.-E.; Sung, H.-J.; Dinh, M.-C.; Park, M.; Shin, H. A Comparative Analysis of Economics of PMSG and SCSG Floating Offshore Wind Farms. Energies 2021, 14, 1386. https://doi.org/10.3390/en14051386

AMA Style

Jung G-E, Sung H-J, Dinh M-C, Park M, Shin H. A Comparative Analysis of Economics of PMSG and SCSG Floating Offshore Wind Farms. Energies. 2021; 14(5):1386. https://doi.org/10.3390/en14051386

Chicago/Turabian Style

Jung, Ga-Eun, Hae-Jin Sung, Minh-Chau Dinh, Minwon Park, and Hyunkyoung Shin. 2021. "A Comparative Analysis of Economics of PMSG and SCSG Floating Offshore Wind Farms" Energies 14, no. 5: 1386. https://doi.org/10.3390/en14051386

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop