Next Article in Journal
Assessment of Hydropower Potential in Wastewater Systems and Application in a Lowland Country, Lithuania
Next Article in Special Issue
Planning of Flexible Generators and Energy Storages under High Penetration of Renewable Power in Taiwan Power System
Previous Article in Journal
Continuous Line Loss Calculation Method for Distribution Network Considering Collected Data of Different Densities
Previous Article in Special Issue
A Framework for Reliability Assessment in Expansion Planning of Power Distribution Systems
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Optimal Preventive Maintenance Planning for Electric Power Distribution Systems Using Failure Rates and Game Theory

by
Noppada Teera-achariyakul
and
Dulpichet Rerkpreedapong
*
Department of Electrical Engineering, Faculty of Engineering, Kasetsart University, Bangkok 10900, Thailand
*
Author to whom correspondence should be addressed.
Energies 2022, 15(14), 5172; https://doi.org/10.3390/en15145172
Submission received: 24 June 2022 / Revised: 13 July 2022 / Accepted: 15 July 2022 / Published: 17 July 2022
(This article belongs to the Special Issue Power Systems Flexibility, Reliability, and Resilience)

Abstract

:
Current electric utilities must achieve reliability enhancement of considerable distribution feeders with an economical budget. Thus, optimal preventive maintenance planning is required to balance the benefits and costs of maintenance programs. In this research, the proposed method determines the time-varying failure rate of each feeder to evaluate the likelihood of future interruptions. Meanwhile, the consequences of feeder interruptions are estimated using interruption energy rates, customer-minutes of interruption, and total kVA of service areas. Then, the risk is assessed and later treated as an opportunity for mitigating the customer interruption costs by planned preventive maintenance tasks. Subsequently, cooperative game theory is exploited in the proposed method to locate a decent balance between the benefits of reliability enhancement and the costs required for preventive maintenance programs. The effectiveness of the proposed method is illustrated through case studies of large power distribution networks of 12 service regions, including 3558 medium-voltage distribution feeders. The preventive maintenance plans resulting from the proposed method present the best compromise of benefits and costs compared with the conventional approach that requires a pre-specified maintenance budget.

1. Introduction

In most parts of the world, power distribution networks are still overhead feeders, prone to being affected by various outage causes, such as tree contact, animal contact, and equipment failure [1,2,3]. As a result, reliability concerns have been a critical issue among electric utilities for several decades. In a competitive environment, electric utilities are challenged to achieve reliability improvement of power distribution systems with tight maintenance budgets. Therefore, cost-effective preventive maintenance must be planned to mitigate power interruptions by fully exploiting data and information available in organizations.
A number of electric utilities prioritize their feeders so that the critical feeders receive appropriate and cost-effective maintenance [4,5,6]. To achieve this objective successfully, the available resources must be optimally allocated [7]. In [5,6,8,9,10,11], the reliability-centered maintenance (RCM) technique was employed to select cost-effective preventive maintenance tasks for electric power systems.
Several risk-based approaches for maintenance planning were well adopted in a wide range of power systems, for instance, hydroelectric power plants [12], generation units in combined heat and power systems [13], and power distribution systems [14]. In addition, ref. [15] explored long-term risk-based maintenance optimization for power distribution systems under hurricane hazards. In [16], a short-term maintenance strategy was successfully implemented based on a risk-cost analysis of power transmission and transformer equipment.
Most research works [4,5,6,8,9,10,11,17] employed failure rates assumed to be invariant with time in risk studies because of their simplicity and availability. However, such an assumption may sacrifice some helpful information for risk assessment, for example, a trend of failure rates [18,19,20]. Instead, the time-varying failure rate can be beneficial to the risk assessment since its trend, either increasing or decreasing, indicates the likelihood of future power interruptions [18,21]. This is very important since the effectiveness of preventive maintenance planning depends on the accuracy of risk assessment.
In [17,22,23,24,25], optimal preventive maintenance planning was conducted for power distribution systems under pre-specified maintenance budgets. In fact, policymakers often question the assigned budgets about a reasonable balance between utility investment and customer interruption costs. Admittedly, a larger budget will allow more reliability improvement in power distribution systems, but it will lessen profitability for utilities. As a result, finding the right figure for the budget can be problematic because an optimal balance of benefits between utilities and customers needs to be sought.
In multi-objective optimization, it is difficult to pick one optimal solution that can improve one objective without worsening the others. Recently, the cooperative game theory approach has been applied in various areas because it can effectively find a balanced solution with much less computational effort [26]. Some applications of game theory for solving power system problems can be found in [27]. Examples of recent studies are on allocating the transmission losses [28,29], allocating the small power producer losses [30], allocating unit start-up costs of generators [31], constructing prosumer coalitions for energy cost savings [32], maintenance planning [33], and applications in distribution system expansion planning, including distributed generation [34].
This research proposed a methodology for the preventive maintenance planning of power distribution systems using the time-varying failure rate and cooperative game theory. The concept of the method is described as follows.
First, the risk likelihood and consequences are determined to perform the risk assessment for individual distribution feeders. The time-varying failure rates, calculated from the three-year interruption record data based on the Weibull distribution, are exploited to indicate the likelihood of future interruptions. Subsequently, the consequences are evaluated using the interruption energy rates, customer-minutes of interruption, and total kVA of service areas. Accordingly, the risk of feeder interruptions can be assessed and later considered as an opportunity for mitigating customer interruption costs by appropriate preventive maintenance.
Secondly, preventive maintenance tasks corresponding to interruption causes are listed for each feeder. Then, the cost of each task can be estimated. Later, the benefit–cost ratio (BCR) of individual tasks is calculated to illustrate the cost-effectiveness. As a result, all maintenance tasks can be ranked according to their BCR. This step is essential because the tasks sorted by their BCR will simplify the problem formulation for optimal maintenance planning.
Lastly, the method employs cooperative game theory to locate the budget amount, resulting in an optimal balance between costs and benefits of preventive maintenance. Then, the list of selected tasks can be obtained accordingly.
To demonstrate the practicability and effectiveness of the proposed method, extensive overhead distribution networks of 12 service regions covering all provincial areas of Thailand [4,35] are used as case studies. The networks consist of 3558 medium-voltage distribution feeders with a total length of 318,349 circuit kilometers. The first case study illustrates that the proposed method can successfully find the preventive maintenance plan resulting in the optimal balance between costs and benefits. The second case study highlights the accuracy of the presented method by revealing the reduced accuracy of maintenance planning that neglects the time-varying failure rates.
This paper is organized as follows: Section 2 carefully describes the risk assessment; in Section 3, the benefit–cost evaluation of preventive maintenance tasks is illustrated; Section 4 explains the cooperative game theory exploited in the method; then, the results and discussion are illustrated in Section 5; and, finally, Section 6 provides the conclusions.

2. Risk Assessment

The risk assessment is the process to identify and evaluate hazards that deteriorate the distribution system reliability. This section is divided into three subsections to explain the presented concept. In the first subsection, power interruption causes are identified. The second part analyzes the time-varying failure rates of distribution feeders. The last subsection presents the evaluation of customer interruption costs.

2.1. Causes of Power Interruptions

As the overhead distribution feeders are exposed, they are vulnerable to damage from a variety of external factors. In addition, most overhead distribution feeders in Thailand are over 30 years old, so equipment failures due to aging and material degradation are likely to occur. The most common causes of power interruptions found in outage event records from 2004 to 2019 [36] are equipment failure, tree contact, and animal contact. Table 1 shows customer-minutes of interruption categorized by their causes regarding the overhead distribution systems in 2019 as calculated from [36]. According to the Pareto principle (80/20 rule), which states that 80% of consequences come from 20% of the causes, the most influential causes in Table 1 are equipment failure, tree contact, and animal contact, all resulting in over 80% of the total customer-minutes of interruption. Consequently, this research focuses solely on maintenance tasks that prevent outages caused by equipment failure, tree contact, and animal contact.

2.2. Feeder Failure Rates

The failure rate is one of the vital parameters describing the reliability characteristics of components or systems. It expresses the frequency with which a component or system fails. Superior to a constant or average failure rate [37], the time-varying failure rate can illustrate its trend that can be exploited for preventive maintenance planning. After excluding all feeders with no interruptions, this research determines the time-varying failure rates of 3112 distribution feeders with 3-year (2017–2019) interruption data based on the Weibull distribution. The Anderson–Darling test showed that 2654 feeders, approximately 75% of the total feeders, accepted the hypothesis, as categorized by the 12 service regions in Table 2.
The Weibull distribution is commonly used in a two-parameter version, including scale parameter α and shape parameter β. Both parameters are positive numbers [38]. From the statistics of power interruptions during the period 2017–2019, the data were analyzed to find parameters α and β. Then, the time-varying failure rate λ(t) of each feeder is determined by Equation (1) [38], where t is defined as the amount of time that the feeder continuously supplies its customers. Accordingly, every time the feeder is back in service after the last interruption, t is reset to 0.
λ ( t ) = β t β 1 α β
From Equation (1), it can be observed that the failure rate decreases with t if the power of t is negative (i.e., if β < 1). On the other hand, if β > 1, the failure rate increases with t. In the case of β = 1, the failure rate is constant with t.
In Figure 1 and Figure 2, t 1 is the time when the maintenance planning is performed, usually by the end of each year. Additionally, λ ( t 1 ) , the failure rate at t = t 1 , implies the frequency with which the feeder fails currently. From a planning point of view, it needs to look ahead at least one year and consider a change in the failure rate. Hence, λ ( t 2 ) , the failure rate at t = t 2 , where t 2 is one year after t 1 , presents the anticipated frequency. As a result, the failure rate tendency index kλ defined by Equation (2) can be used to predict how the risk likelihood will change in the following year.
k λ = λ ( t 2 ) λ ( t 1 )
Figure 1 shows the increasing failure rate, resulting in a kλ value greater than 1. It implies that the reliability will deteriorate if maintenance plans are not upgraded. In Figure 2, the decreasing failure rate leads to kλ being less than 1. This indicates that the reliability is likely to increase, although maintenance plans are not revised [38].
The calculation of kλ is performed for all feeders accepting the Weibull distribution hypothesis. It is found that 1509 feeders have increasing failure rates (kλ > 1) and 720 feeders have decreasing failure rates (kλ < 1). However, the other 425 feeders have almost constant failure rates (kλ ≈ 1). As a result, the number of feeders in different types of failure rate tendencies are shown in Table 3. In addition, kλ = 1 is assumed for the 458 feeders rejecting the hypothesis.

2.3. Evaluation of Customer Interruption Costs

This subsection explains the concept of evaluating the impacts of power interruptions. The customer-minutes of interruption CMI is a quantity indicating the effects of power interruptions in terms of the number of affected customers and interruption duration in minutes. Although CMI is a rational index to express the reliability impacts, it is preferable to convert this index into the customer interruption costs, which is more understandable from an economic perspective.
First, the CMI in each zone of a feeder due to three influential causes (equipment failure, tree contact, and animal contact) can be calculated by Equation (3) [39].
C M I z , f c = i = 1 N c C z i c   ×   d i c
where
  • C M I z , f c is the customer-minutes of interruption in zone z of feeder f due to cause c;
  • C z i c is the number of customers in zone z affected by incident i due to cause c;
  • d i c is the interruption duration of incident i due to cause c (minutes);
  • N c is the number of interruptions due to cause c.
Subsequently, the outage rate of customers (THB/customer-minute) is proposed to assess the impacts on customers when experiencing a power interruption. This value depends on customer loads and interruption energy rates of customers in different zones (industrial, metropolitan, urban, suburban, and rural) as presented in Table 4. Accordingly, the outage rate of customers in each zone of a feeder can be calculated by Equation (4).
O z , f = k V A z , f × P F × U F C z , f × I E R z 60
where
  • O z , f is the outage rate of customers in zone z of feeder f;
  • k V A z , f is the installed kVA in zone z of feeder f;
  • PF is the power factor;
  • UF is the utilization factor;
  • C z , f is the number of customers in zone z of feeder f;
  • I E R z is the interruption energy rate of customers in zone z (THB/kWh) as presented in Table 4 (Exchange rate: THB 1 = USD 0.028).
Then, the customer interruption cost can be obtained by multiplying the CMI by the outage rate of the customers. Where N z is the number of zones, the customer interruption cost of feeder f due to cause c, C I C f c , is evaluated by using Equation (5).
C I C f c = z = 1 N z C M I z , f c   ×   O z , f

3. Benefit–Cost Evaluation of Preventive Maintenance Tasks

This section illustrates the cost–benefit evaluation of preventive maintenance tasks. As the three influential causes, including equipment failure, tree contact, and animal contact, were identified previously, corresponding preventive maintenance tasks must be carefully planned for reliability enhancement. In this research, the patrol and condition-based maintenance, tree trimming, and installation of animal guards are selected accordingly. This section is divided into three subsections. The first and the second subsections explain the evaluation of benefits and costs of preventive maintenance tasks, respectively. The third part describes the benefit/cost analysis.

3.1. Benefits of Preventive Maintenance Tasks

Preventive maintenance can help to reduce the risk of power interruptions and lessen customer interruption costs. When the preventive maintenance benefits are evaluated in monetary terms, it is easier to understand and helpful for economic analysis. To achieve this objective, it requires the maintenance effectiveness of each maintenance task. In this research, the effectiveness factors of preventive maintenance tasks are obtained from the field surveys. Hundreds of engineers, technicians, maintenance crews, patrolmen, and skilled operators answered the questionnaires based on maintenance records, interruption records, and field experience. In addition, the survey conclusions were confirmed by the results of the maintenance model in [40]. Associated with the statistical comparison of before and after performing each task, the effectiveness factors of preventive maintenance tasks to prevent power interruptions due to equipment failure η e , tree contact η p , and animal contact η a are 0.05, 0.70, and 0.30, respectively.
The proposed method uses the effectiveness factor of maintenance tasks preventing power interruptions due to cause c, η c , and the failure rate tendency index, k λ , f , to assess the opportunity for the corresponding maintenance task to mitigate the interruptions due to cause c in the following year. Thus, the benefits of preventive maintenance tasks corresponding to cause c for feeder f or b p m f c can be described by Equation (6).
b p m f c   =   k λ , f   ×   η c   ×   C I C f c

3.2. Costs of Preventive Maintenance

For each feeder, the costs of planned preventive maintenance tasks can be estimated from the historical costs. Alternatively, the unit cost per kilometer of these preventive maintenance tasks can be adopted to estimate the costs. Such information can be found in the yearly maintenance budget plans [41] and the actual maintenance expenses recorded in one fiscal year. In this study, the maintenance cost per feeder kilometer for patrol and condition-based maintenance, m e , is approximately THB 160 per kilometer. The unit costs of tree trimming, m p , and installing animal guards, m a , are approximately THB 3200 and 1200 per kilometer, respectively.
Then, the costs of preventive maintenance tasks corresponding to cause c for feeder f or c p m f c can be estimated from the unit cost per kilometer, m c , multiplied by the length of feeder f, L f , as expressed by Equation (7).
c p m f c   =   L f   ×   m c

3.3. Benefit/Cost Analysis of Maintenance Tasks

Benefit/cost analysis of preventive maintenance tasks is an approach for evaluating the cost-effectiveness of maintenance tasks by comparing the benefits with the costs in terms of the benefit/cost ratio, BCR. Hence, the BCR of preventive maintenance tasks corresponding to cause c for feeder f or B C R f c can be given by Equation (8) [5]:
B C R f c = b p m f c c p m f c
From the analysis of 3112 distribution feeders, 7587 or H preventive maintenance tasks were initially suggested, as shown in Table 5. Then, the B C R f c value of each task was evaluated and all were sorted in descending order. According to the BCR ranking, accumulating b p m f c and c p m f c of each task in a one-by-one fashion from j = 1 to H will generate BPMj and CPMj as members of the datasets BPM and CPM, respectively, in Table 6. While BPMj and CPMj are defined as the benefit and cost of maintenance strategy j, the method of cooperative game theory examines strategies for j = 1 to H to determine the optimal preventive maintenance program, as explained in the next section.

4. Cooperative Game Theory

For multi-objective optimization, it is difficult to pick one optimal solution that can improve one objective without worsening the others. According to game theory, optimization seeks to find a solution that results in a Pareto optimum and satisfies the requirements of all players. As investigated by previous research [42], the game theory approach is an effective technique to find the best compromise answer with lower computing time than combinatorial optimization.
In this work, cooperative game theory was employed to search for the most effective preventive maintenance program that resulted in a decent balance between the preventive maintenance costs and the benefits of reliability enhancement. The objectives to be optimized are modeled as game players i = (1…P), where P is the number of players. Thus, this optimization has two players, which are BPM and CPM, called P 1 and P 2 , respectively.
Each player has decisions d = (1…D), where D is the number of decisions. In addition, decision d has a strategy set s = { s d , 1 , , s d , j , , s d , H d } that presents all strategies available to play. The number of strategies H d may or may not be equal for each decision, as shown in Figure 3.
Subsequently, a combination of strategies played by each decision creates a scenario, S k . Additionally, the number of all possible combinations, K, can be determined by Equation (9) [26].
K = d = 1 D H d
In this research, the decisions represent the 12 service regions, so H d is the total number of preventive maintenance tasks for service region d. According to the number of preventive maintenance tasks for each service region in Table 5, the number of possible scenarios K as calculated by Equation (9) is up to 2.56 × 1033. By constructing datasets for game-playing strategies, consistent with Table 6, this large number can be significantly reduced to only 7575 game scenarios. The number of game scenarios or matches, M, can be calculated by Equation (10), where D is the number of decisions, i.e., 12.
M = d = 1 D H d   D
Scenario S k as a set of strategies played by service regions r = (1…R) creates a particular function value for player i, F i ( S k ) . Therefore, the function values for players P 1 and P 2 resulting from S k can be determined by Equations (11) and (12), respectively.
F 1 ( S k )   =   r = 1 R B P M r , k r
F 2 ( S k )   =   r = 1 R C P M r , k r
where
  • F 1 ( S k ) is the function value for player 1 in scenario S k ;
  • F 2 ( S k ) is the function value for player 2 in scenario S k ;
  • S k is a set of strategies s r , k r played by service regions r = (1…R);
  • R is the number of service regions;
  • B P M r , k r is the regional benefit of preventive maintenance tasks in strategy s r , k r ;
  • C P M r , k r is the regional cost of preventive maintenance tasks in strategy s r , k r .
If function values for players are not in the same unit, they can be normalized to a per-unit value using the sigmoid function. The normalized value is defined as a utility value that presents a player’s profit for a considered scenario. For player i, a profit in scenario S k , u i ( S k ) can be evaluated from the utility function shown in Equation (13) [42].
u i ( S k )   =   1 1 + e ε [ F i ( S k )     F i ( S 0 ) ]
The adjustment multiplier for the sigmoid function, ε, should be a near-zero value. If the objective of player i is maximized, ε must be a positive value. On the other hand, if the objective is minimized, ε must be a negative value. However, they must have the same magnitude value for all players involved [26]. At the beginning of the game, the base scenario has been defined as the collection of the first strategies from all individual service regions as S 0 = { s 1 , 1 ,   s 2 , 1 ,   ,   s r , 1 ,   ,   s R , 1 } . As a result, the utility function of each player in the base scenario produces u i ( S 0 ) = 0 .5 by using Equation (13). For each successive match, service region r is allowed to shift its strategy step by step from j = 2 to H r , as shown in Table 7, where S r ( j ) is the scenario in which service region r plays its strategy j, while the other service regions use their strategies given in S 0 .
The global utility is a value that represents the outcome of the cooperation among players. The global utility in scenario S k , u G ( S k ) is the summation of individual profits of all players divided by the number of players, P, as expressed by Equation (14) [42].
u G ( S k )   =   i = 1 P u i ( S k ) P
In Table 7, the best strategy for service region r, s r , B r , can be found when its global utility u G ( S r ( j ) ) is maximized. Accordingly, the best scenario, S B , is the collection of the best strategies for all individual service regions, i.e., S B = { s 1 , B 1 ,   s 2 , B 2 ,   ,   s r , B r ,   ,   s R , B R } as summarized in the last row of Table 7. Then, the global utility value of the best scenario, u G ( S B ) , can be calculated by Equation (15) [42].
u G ( S B )   =   i = 1 P u i ( S B ) P
Finally, the optimal balance between the benefits and costs of preventive maintenance tasks resulting from the best scenario S B produces the function values of players 1 and 2, as expressed in Equations (16) and (17), respectively.
F 1 ( S B )   =   r = 1 R B P M r , B r
F 2 ( S B )   =   r = 1 R C P M r , B r
where
  • F 1 ( S B ) is the function value of player 1 in the best scenario S B ;
  • F 2 ( S B ) is the function value of player 2 in the best scenario S B ;
  • S B is the collection of the best strategies for all individual service regions;
  • R is the number of service regions;
  • B P M r , B r is the regional benefit of preventive maintenance tasks in strategy s r , B r ;
  • C P M r , B r is the regional cost of preventive maintenance tasks in strategy s r , B r .
The flowcharts, as shown in Figure 4 and Figure 5, summarize the proposed approach.

5. Results and Discussions

Two situations were stipulated for optimal preventive maintenance planning to investigate the effectiveness of the proposed methodology. In the first situation, called BCR prioritization, the cost-effective preventive maintenance tasks were selected according to their benefit-per-cost ratios under pre-specified different maintenance budgets. In the other situation, the proposed method was employed to find the most appropriate preventive maintenance tasks that balanced the benefits and costs.
According to the BCR prioritization, preventive maintenance plans can be achieved when a maintenance budget is assigned. This technique cost-effectively spends the budget to reach the most benefits of preventive maintenance. When the budget amount is varied with a step of THB 100 million (MB) from 100 MB to 700 MB, the most cost-effective plan for each amount is obtained as its CPM and BPM are plotted in Figure 6. However, one remaining question for the management is how much the budget should be specified to achieve a decent balance between the costs and benefits.
To answer the question above, the proposed method extended from the BCR prioritization exploits cooperative game theory to locate the budget amount, resulting in an optimally balanced solution. It can be found where the global utility plotted against CPM reaches the maximum, as shown in Figure 6. In this case, the maximum global utility value or the global utility value of the best scenario u G ( S B ) is 0.51074848, and the total cost of the preventive maintenance plan equals 201.85 MB. To highlight the results, three comparable plans (budget ≤ 100 MB, 200 MB, and 300 MB) of the BCR prioritization are selected to illustrate their global utility values against the proposed method in Table 8. In addition, the benefits, B P M r , costs, C P M r , and the number of selected tasks, B r , by service region are also compared among those plans in Table 9.
According to Table 9, when the budget rises from 100 MB to 300 MB, or triples, the benefit BPM increases by only 25.16% ((1130.87–903.54)/903.54). Such a result shows that an increase in preventive maintenance budgets may not offer worthy reliability improvement. On the other hand, the plan with the budget of 100 MB results in the highest BCR, but the increased reliability may be unsatisfactory for the customers. Consequently, the plan resulting from the proposed method, which is located by the maximum global utility, is the optimally balanced solution.
After the budget amount of the preventive maintenance plan is obtained, the percentage of allocated CPM for each service region is shown in Figure 7. The results show a wide range of variation in CPM among all regions because individual regions have different degrees of risks to mitigate. As presented in the risk assessment section, the time-varying failure rates of feeders can illustrate the likelihood of future interruptions. The proposed method utilizes the failure rate tendency index kλ as introduced in Equation (2) to describe a change in the failure rate at one year ahead. To be more explicit, kλ > 1 presents the increasing failure rate, and kλ < 1 indicates the decreasing failure rate. In the case of kλ = 1, the failure rate does not change with time or is constant.
Assuming the failure rate is constant when it is really not eases the failure rate computation. Yet, it may sacrifice some helpful information for risk assessment, such as the likelihood of future interruptions. To clarify this statement, the failure rates of all feeders are assumed constant (kλ = 1). Then, the proposed method is employed to reproduce the new results for kλ = 1 to compare with the previous results in Figure 7. The comparison of CPM by service region shows differences between both cases, which imply the reduced accuracy of preventive maintenance planning when the time-varying failure rates are disregarded. For instance, CPM is excessively allocated to service region 3, while service region 10 should have received more expenditure. Similar to Figure 7, the numbers of selected preventive maintenance tasks by service region are compared in percentage terms in Figure 8. The differences between both cases are consistent with those presented in Figure 7. In addition, the number of tasks by service region does not necessarily depend on the allocated CPM because the costs of individual preventive maintenance tasks can be widely different due to a variety of circuit lengths and unit costs of various preventive maintenance activities.

6. Conclusions

This research presents a methodology of optimal preventive maintenance planning for power distribution systems using the time-varying failure rates and cooperative game theory. For each feeder, the time-varying failure rate was determined, and its trend was analyzed to assess the likelihood of future interruptions. Meanwhile, the risk consequences were estimated using the interruption energy rates, customer-minutes of interruption, and total kVA of service areas. Then, the assessed risk of feeder interruptions was considered as an opportunity for mitigating the customer interruption costs by proper preventive maintenance tasks. Thus, it was defined as the benefits of preventive maintenance tasks. Subsequently, the BCR of each task was calculated so that all tasks could be ranked according to their BCR in descending order.
According to the BCR prioritization, the most cost-effective plan can be obtained by gathering the top-ranked tasks as many as possible under a given budget. However, a challenge for the management is how much the budget should be specified to achieve a decent balance between the costs and benefits. In this research, the proposed method extended from the BCR prioritization exploits cooperative game theory to set the budget amount that results in an optimally balanced solution.
To illustrate its practicability and effectiveness, the proposed method was applied to the extensive distribution networks of the 12 service regions covering all provincial areas of Thailand. The time-varying failure rates were computed from three-year historical outage records for more than three thousand overhead distribution feeders. Then, the costs and benefits of preventive maintenance tasks corresponding to the outage causes were evaluated.
The BCR prioritization was performed by varying the budget from 100 MB to 700 MB. The most cost-effective plan for each amount was obtained, as its CPM and BPM were plotted in Figure 6. However, those results could not show how well the CPM and BPM were balanced. On the other hand, the proposed method successfully located the best-balanced solution where the global utility value was maximum. This global utility value was compared with those resulting from the BCR prioritization to confirm the results.
In the proposed method, cooperative game theory was directly applied to the strategies obtained from the ranked maintenance tasks. This problem formulation substantially reduced the search space or the number of scenarios, so it required less computational effort to explore the optimal result.
Furthermore, the case study assuming all the failure rates were constant (kλ = 1) was conducted to illustrate the other contribution of the proposed method. By comparing the allocated CPM by service region for kλ = 1 with the proposed method using the time-varying failure rates, the differences between both cases implied the reduced accuracy of preventive maintenance planning that neglects the time-varying failure rates.
The highlighted results discussed above have strengthened the contributions of the proposed method in aspects of practicability and effectiveness for preventive maintenance planning. Moreover, the presented method fully exploits utilities’ available information to reach the best decision making with light computational effort. Therefore, this method appeals to current electric utilities that strive to achieve efficient investment and become data-driven organizations.

Author Contributions

Conceptualization, D.R.; methodology, N.T.-a. and D.R.; software, N.T.-a.; validation, D.R.; formal analysis, N.T.-a.; investigation, N.T.-a. and D.R.; resources, D.R.; data curation, N.T.-a.; writing—original draft preparation, N.T.-a.; writing—review and editing, D.R.; visualization, N.T.-a. All authors have read and agreed to the published version of the manuscript.

Funding

This research received no external funding.

Institutional Review Board Statement

Not applicable.

Informed Consent Statement

Not applicable.

Data Availability Statement

Not applicable.

Conflicts of Interest

The authors declare no conflict of interest.

References

  1. Xu, L.; Chow, M.; Timmis, J.; Taylor, L.S. Power Distribution Outage Cause Identification With Imbalanced Data Using Artificial Immune Recognition System (AIRS) Algorithm. IEEE Trans. Power Syst. 2007, 22, 198–204. [Google Scholar] [CrossRef] [Green Version]
  2. Zhang, X.; Gockenbach, E. Component Reliability Modeling of Distribution Systems Based on the Evaluation of Failure Statistics. IEEE Trans. Dielectr. Electr. Insul. 2007, 14, 1183–1191. [Google Scholar] [CrossRef]
  3. Hyland, M.; Hofmann, A.; Doyle, T.; Lee, J.Y. Evaluation of Data Submitted in APPA’s 2018 Distribution System Reliability & Operations Survey; DOKUMEN: Richmond, VA, USA, 2019. [Google Scholar]
  4. Teera-achariyakul, N.; Rerkpreedapong, D. A Method of Cost-effective Preventive Maintenance Planning for Power Distribution Systems using Cooperative Game Theory. In Proceedings of the 2019 IEEE PES GTD Grand International Conference and Exposition Asia (GTD Asia), Bangkok, Thailand, 19–23 March 2019; pp. 23–28. [Google Scholar]
  5. Duangta, N.; Teera-achariyakul, N.; Rerkpreedapong, D. Prioritization of Maintenance Tasks on Electrical Distribution Systems Using RCM method and Criticality Factors. In Proceedings of the 14th GMSARN International Conference on Smart Energy, Enviroment, and Development for sustainable GMS, Luang Prabang, Laos, 27–29 November 2019. [Google Scholar]
  6. Teera-achariyakul, N.; Rerkpreedapong, D. Optimal Allocation of Maintenance Resources and Reliability Benchmarking of Electric Power Utilities. In Proceedings of the 8th GMSARN International Conference 2013 on Green Growth in GMS: Energy, Environment and Social Issues, Mandalay, Myanmar, 18–20 December 2013. [Google Scholar]
  7. Dehghanian, P.; Fotuhi-Firuzabad, M.; Bagheri-Shouraki, S.; Kazemi, A.A.R. Critical Component Identification in Reliability Centered Asset Management of Power Distribution Systems Via Fuzzy AHP. IEEE Syst. J. 2012, 6, 593–602. [Google Scholar] [CrossRef]
  8. Walliyamethee, N.; Hongesombut, K. Maintenance Scheduling of Distribution Reclosers Using RCM Techniques. In Proceedings of the 2019 IEEE PES Asia-Pacific Power and Energy Engineering Conference (APPEEC), Macao, China, 1–4 December 2019; pp. 1–5. [Google Scholar]
  9. Chaengakson, K.; Rerkpreedapong, D.; Hongesombut, K. Reliability Improvement Opportunity for 115-kV Overhead Transmission Lines Using RCM Method. In Proceedings of the 2019 IEEE PES GTD Grand International Conference and Exposition Asia (GTD Asia), Bangkok, Thailand, 19–23 March 2019; pp. 808–812. [Google Scholar]
  10. Vilayphonh, O.; Premrudeepreechacharn, S.; Ngamsanroaj, K. Reliability Centered Maintenance for Electrical Distribution System of Phontong Substation in Vientiane Capital. In Proceedings of the 2017 6th International Youth Conference on Energy (IYCE), Budapest, Hungary, 21–24 June 2017; pp. 1–6. [Google Scholar]
  11. Lazecký, D.; Král, V.; Rusek, S.; Goňo, R. Software Solution Design for Application of Reliability Centered Maintenance in Preventive Maintenance Plan. In Proceedings of the 2017 18th International Scientific Conference on Electric Power Engineering (EPE), Kouty nad Desnou, Czech Republic, 17–19 May 2017; pp. 1–4. [Google Scholar]
  12. Özcan, E.; Yumuşak, R.; Eren, T. Risk Based Maintenance in the Hydroelectric Power Plants. Energies 2019, 12, 1502. [Google Scholar] [CrossRef] [Green Version]
  13. Sadeghian, O.; Mohammadpour Shotorbani, A.; Mohammadi-Ivatloo, B.; Sadiq, R.; Hewage, K. Risk-averse maintenance scheduling of generation units in combined heat and power systems with demand response. Reliab. Eng. Syst. Saf. 2021, 216, 107960. [Google Scholar] [CrossRef]
  14. Yeddanapudi, S.R.K.; Li, Y.; McCalley, J.D.; Chowdhury, A.A.; Jewell, W.T. Risk-Based Allocation of Distribution System Maintenance Resources. IEEE Trans. Power Syst. 2008, 23, 287–295. [Google Scholar] [CrossRef]
  15. Salman, A.M.; Li, Y.; Bastidas-Arteaga, E. Maintenance optimization for power distribution systems subjected to hurricane hazard, timber decay and climate change. Reliab. Eng. Syst. Saf. 2017, 168, 136–149. [Google Scholar] [CrossRef] [Green Version]
  16. Yang, H.; Zhang, Z.; Yin, X.; Han, J.; Wang, Y.; Chen, G. A Novel Short-Term Maintenance Strategy for Power Transmission and Transformation Equipment Based on Risk-Cost-Analysis. Energies 2017, 10, 1865. [Google Scholar] [CrossRef] [Green Version]
  17. Aravinthan, V.; Jewell, W. Optimized Maintenance Scheduling for Budget-Constrained Distribution Utility. IEEE Trans. Smart Grid 2013, 4, 2328–2338. [Google Scholar] [CrossRef]
  18. Moradkhani, A.; Haghifam, M.R.; Mohammadzadeh, M. Failure rate modelling of electric distribution overhead lines considering preventive maintenance. IET Gener. Transm. Distrib. 2014, 8, 1028–1038. [Google Scholar] [CrossRef]
  19. Peng, W.; Billinton, R. Reliability cost/worth assessment of distribution systems incorporating time-varying weather conditions and restoration resources. IEEE Trans. Power Deliv. 2002, 17, 260–265. [Google Scholar] [CrossRef]
  20. Bowles, J.B. Commentary-caution: Constant failure-rate models may be hazardous to your design. IEEE Trans. Reliab. 2002, 51, 375–377. [Google Scholar] [CrossRef]
  21. Chu, C.M.; Moon, J.F.; Lee, H.T.; Kim, J.C. Extraction of Time-varying Failure Rates on power distribution system equipment considering failure modes and regional effects. Int. J. Electr. Power Energy Syst. 2010, 32, 721–727. [Google Scholar] [CrossRef]
  22. Phoothong, N.; Vanittanakom, P.; Teera-achariyakul, N.; Rerkpreedapong, D. Optimal Preventive Maintenance Budget Setting for Electric Power Distribution Utilities. In Proceedings of the 2008 5th International Conference on Electrical Engineering/Electronics, Computer, Telecommunications and Information Technology, Krabi, Thailand, 14–17 May 2008; pp. 957–960. [Google Scholar]
  23. Singh, I.; Popova, E.; Kee, E. Optimal Preventive Maintenance Policy Under a Budget Constraint. Int. Conf. Nucl. Eng. Proc. 2008, 48140, 13–18. [Google Scholar] [CrossRef] [Green Version]
  24. Enjavimadar, M.; Rastegar, M. Optimal reliability-centered maintenance strategy based on the failure modes and effect analysis in power distribution systems. Electr. Power Syst. Res. 2022, 203, 107647. [Google Scholar] [CrossRef]
  25. Dao, C.D.; Zuo, M.J. Optimal selective maintenance for multi-state systems in variable loading conditions. Reliab. Eng. Syst. Saf. 2017, 166, 171–180. [Google Scholar] [CrossRef]
  26. Jeromin, I.; Balzer, G. Game Theoretical Approach for Maintenance Planning of Large Networks. In Proceedings of the 2011 IEEE Trondheim PowerTech, Trondheim, Norway, 19–23 June 2011; pp. 1–5. [Google Scholar]
  27. Navon, A.; Ben Yosef, G.; Machlev, R.; Shapira, S.; Roy Chowdhury, N.; Belikov, J.; Orda, A.; Levron, Y. Applications of Game Theory to Design and Operation of Modern Power Systems: A Comprehensive Review. Energies 2020, 13, 3982. [Google Scholar] [CrossRef]
  28. Tan, X.H.; Lie, T.T. Allocation of Transmission Loss Cost Using Cooperative Game Theory in the Context of Open Transmission Access. In Proceedings of the 2001 IEEE Power Engineering Society Winter Meeting, Conference Proceedings (Cat. No.01CH37194), Columbus, OH, USA, 28 January–1 February 2001; Volume 1213, pp. 1215–1219. [Google Scholar]
  29. Shih-Chieh, H.; Hsin-Min, W. Allocation of Transmission Losses Based on Cooperative Game Theory and Current Injection Models. In Proceedings of the 2002 IEEE International Conference on Industrial Technology, IEEE ICIT ’02., Bangkok, Thailand, 11–14 December 2002; Volume 852, pp. 850–853. [Google Scholar]
  30. Heng, S.; Noohawm, O.; Rerkpreedapong, D. SPP Loss Allocation by Cooperative Games. In Proceedings of the GMSARN International Journal (ISSN: 19059094), Mandalay, Myanmar, 18–20 December 2013; pp. 13–18. [Google Scholar]
  31. Zhaoyang, H.; Lin, C.; Deqiang, G.; Chattopadhyay, D. Allocation of unit start-up costs using Cooperative game theory. IEEE Trans. Power Syst. 2006, 21, 653–662. [Google Scholar] [CrossRef]
  32. Han, L.; Morstyn, T.; McCulloch, M. Constructing Prosumer Coalitions for Energy Cost Savings Using Cooperative Game Theory. In Proceedings of the 2018 Power Systems Computation Conference (PSCC), Dublin, Ireland, 11–15 June 2018; pp. 1–7. [Google Scholar]
  33. Pourahmadi, F.; Fotuhi-Firuzabad, M.; Dehghanian, P. Application of Game Theory in Reliability-Centered Maintenance of Electric Power Systems. IEEE Trans. Ind. Appl. 2017, 53, 936–946. [Google Scholar] [CrossRef]
  34. Li, R.; Ma, H.; Wang, F.; Wang, Y.; Liu, Y.; Li, Z. Game Optimization Theory and Application in Distribution System Expansion Planning, Including Distributed Generation. Energies 2013, 6, 1101–1124. [Google Scholar] [CrossRef]
  35. PEA Thailand. PEA Annual Report 2019; Provincial Electricity Authority (PEA): Bangkok, Thailand, 2019. [Google Scholar]
  36. PEA Thailand. PEA Interruptions Database JF.3 Year 2004–2019; Provincial Electricity Authority (PEA): Bangkok, Thailand, 2019. [Google Scholar]
  37. Zuo, X.; Yu, X.; Yue, Y.; Yin, F.; Zhu, C. Reliability Study of Parameter Uncertainty Based on Time-Varying Failure Rates with an Application to Subsea Oil and Gas Production Emergency Shutdown Systems. Processes 2021, 9, 2214. [Google Scholar] [CrossRef]
  38. Robert, R. Reliability Analysis for Asset Management of Electric Power Grids; IEEE Press: Hoboken, NJ, USA, 2019; 528p. [Google Scholar]
  39. IEEE Std. 1366-2012; IEEE Guide for Electric Power Distribution Reliability Indices. (Revision of IEEE Std. 1366-2003); IEEE Press: Hoboken, NJ, USA, 2012; pp. 1–43. [CrossRef]
  40. Final Report on Reliability Target Setting Methodology Study; Kasetsart University: Bangkok, Thailand, 2013.
  41. PEA Strategic Plan 2014–2023; Provincial Electricity Authority (PEA): Bangkok, Thailand, 2016.
  42. Orths, A.; Schmitt, A.; Styczynski, Z.A.; Verstege, J. Multi-criteria optimization methods for planning and operation of electrical energy systems. Electr. Eng. 2001, 83, 251–258. [Google Scholar] [CrossRef]
Figure 1. Increasing failure rate, kλ > 1.
Figure 1. Increasing failure rate, kλ > 1.
Energies 15 05172 g001
Figure 2. Decreasing failure rate, kλ < 1.
Figure 2. Decreasing failure rate, kλ < 1.
Energies 15 05172 g002
Figure 3. Strategies in each decision.
Figure 3. Strategies in each decision.
Energies 15 05172 g003
Figure 4. Flowchart for constructing the datasets for game-playing strategies.
Figure 4. Flowchart for constructing the datasets for game-playing strategies.
Energies 15 05172 g004
Figure 5. Optimal preventive maintenance planning using cooperative game theory.
Figure 5. Optimal preventive maintenance planning using cooperative game theory.
Energies 15 05172 g005
Figure 6. The benefits and costs of preventive maintenance plans.
Figure 6. The benefits and costs of preventive maintenance plans.
Energies 15 05172 g006
Figure 7. The percentage of allocated preventive maintenance budget by service region.
Figure 7. The percentage of allocated preventive maintenance budget by service region.
Energies 15 05172 g007
Figure 8. The percentage of the number of selected preventive maintenance tasks by service region.
Figure 8. The percentage of the number of selected preventive maintenance tasks by service region.
Energies 15 05172 g008
Table 1. Causes of power interruptions and customer-minutes of interruption.
Table 1. Causes of power interruptions and customer-minutes of interruption.
RankCause of InterruptionsCustomer-Minutes of Interruption%
1Equipment failure499,322,37233.34
2Tree contact463,909,70830.97
3Animal contact299,530,44920.00
4Environment91,440,1326.10
5Vehicle53,221,5373.55
6Foreign object31,161,0962.08
7Others21,693,7921.45
8Human20,407,6681.36
9Natural disaster16,073,3291.07
10Overload1,069,2610.07
Total1,497,829,344100.00
Table 2. Results of the Anderson–Darling test categorized by 12 service regions.
Table 2. Results of the Anderson–Darling test categorized by 12 service regions.
Service
Region
Number of
Feeders
Accepted
A.D. Test
Rejected
A.D. Test
No Event
12582141826
2257226823
3198177129
42571892939
5253213328
62502002129
75333886184
845427576103
93892585675
102211565213
112862035825
122021553512
Total35582654458446
Table 3. Number of feeders with different types of failure rate tendencies in each service region.
Table 3. Number of feeders with different types of failure rate tendencies in each service region.
Service Regionkλ < 1kλ > 1kλ ≈ 1Total
16310348214
21319617226
32913711177
45810130189
52115537213
65012426200
716313392388
89812354275
95917029258
10775623156
115311535203
12369623155
Total72015094252654
Table 4. Interruption energy rate of customers in different zones of each service region.
Table 4. Interruption energy rate of customers in different zones of each service region.
Service
Region
Zones
IndustrialMetropolitanUrbanSuburbanRural
1125.1265.5272.65103.0794.25
2154.5480.9289.74127.30116.40
3*71.5679.35112.57102.93
4*48.2653.5275.9269.42
5*45.2550.1771.1865.09
6121.4263.5870.50100.0291.45
779.8341.8046.3565.7660.13
877.6440.6645.0863.9658.48
9104.3454.6360.5985.9578.59
10110.6157.9264.2391.1283.32
11*44.8049.6870.4764.44
12105.1655.0761.0786.6379.21
* No industrial zone in service regions.
Table 5. Number of preventive maintenance tasks categorized by maintenance type.
Table 5. Number of preventive maintenance tasks categorized by maintenance type.
Service
Region
Patrol and Condition-Based MaintenanceTree TrimmingInstalling
Animal Guards
Total
1200204201605
2213222220655
3169176168513
4126107109342
5224246230700
6137132140409
7311303311925
8294302293889
9263249260772
10184182182548
11237221243701
12176176176528
Total2534252025337587
Table 6. BPMj and CPMj generated for strategy j from j = 1 to H.
Table 6. BPMj and CPMj generated for strategy j from j = 1 to H.
BCR RankingbpmcpmStrategy No.BPMCPM
1 b p m 1 c p m 1 1 B P M 1     =   b p m 1 C P M 1     =   c p m 1
2 b p m 2 c p m 2 2 B P M 2   =   b p m 2   +   B P M 1 C P M 2   =   c p m 2   +   C P M 1
3 b p m 3 c p m 3 3 B P M 3   =   b p m 3   +   B P M 2 C P M 3   =   c p m 3   +   C P M 2
j b p m j c p m j j B P M j   =   b p m j   +   B P M j 1 C P M j   =   c p m j   +   C P M j 1
H b p m H c p m H H B P M H   =   b p m H   +   B P M H 1 C P M H   =   c p m H   +   C P M H 1
Table 7. Game scenarios and global utilities.
Table 7. Game scenarios and global utilities.
MatchScenarioService RegionsUtility Values of PlayersGlobal Utilities
12rR u 1 ( S k ) u i ( S k ) u p ( S k ) u G ( S k )
Base S 0 s 1 , 1 s 2 , 1 s r , 1 s R , 1 0.50.50.50.50.50.5
1 S 1 ( 2 ) s 1 , 2 s 2 , 1 s r , 1 s R , 1 u 1 ( S 1 ( 2 ) ) u i ( S 1 ( 2 ) ) u p ( S 1 ( 2 ) ) u G ( S 1 ( 2 ) )
2 S 1 ( 3 ) s 1 , 3 s 2 , 1 s r , 1 s R , 1 u 1 ( S 1 ( 3 ) ) u i ( S 1 ( 3 ) ) u p ( S 1 ( 3 ) ) u G ( S 1 ( 3 ) )
S 1 ( j ) s 1 , j s 2 , 1 s r , 1 s R , 1 u 1 ( S 1 ( j ) ) u i ( S 1 ( j ) ) u p ( S 1 ( j ) ) u G ( S 1 ( j ) )
S 1 ( H 1 ) s 1 , H 1 s 2 , 1 s r , 1 s R , 1 u 1 ( S 1 ( H 1 ) ) u i ( S 1 ( H 1 ) ) u p ( S 1 ( H 1 ) ) u G ( S 1 ( H 1 ) )
S 2 ( 2 ) s 1 , 1 s 2 , 2 s r , 1 s R , 1 u 1 ( S 2 ( 2 ) ) u i ( S 2 ( 2 ) ) u p ( S 2 ( 2 ) ) u G ( S 2 ( 2 ) )
S 2 ( 3 ) s 1 , 1 s 2 , 3 s r , 1 s R , 1 u 1 ( S 2 ( 3 ) ) u i ( S 2 ( 3 ) ) u p ( S 2 ( 3 ) ) u G ( S 2 ( 3 ) )
S 2 ( j ) s 1 , 1 s 2 , j s r , 1 s R , 1 u 1 ( S 2 ( j ) ) u i ( S 2 ( j ) ) u p ( S 2 ( j ) ) u G ( S 2 ( j ) )
S 2 ( H 2 ) s 1 , 1 s 2 , H 2 s r , 1 s R , 1 u 1 ( S 2 ( H 2 ) ) u i ( S 2 ( H 2 ) ) u p ( S 2 ( H 2 ) ) u G ( S 2 ( H 2 ) )
S r ( 2 ) s 1 , 1 s 2 , 1 s r , 2 s R , 1 u 1 ( S r ( 2 ) ) u i ( S r ( 2 ) ) u p ( S r ( 2 ) ) u G ( S r ( 2 ) )
S r ( 3 ) s 1 , 1 s 2 , 1 s r , 3 s R , 1 u 1 ( S r ( 3 ) ) u i ( S r ( 3 ) ) u p ( S r ( 3 ) ) u G ( S r ( 3 ) )
S r ( j ) s 1 , 1 s 2 , 1 s r , j s R , 1 u 1 ( S r ( j ) ) u i ( S r ( j ) ) u p ( S r ( j ) ) u G ( S r ( j ) )
S r ( H r ) s 1 , 1 s 2 , 1 s r , H r s R , 1 u 1 ( S r ( H r ) ) u i ( S r ( H r ) ) u p ( S r ( H r ) ) u G ( S r ( H r ) )
S R ( 2 ) s 1 , 1 s 2 , 1 s r , 1 s R , 2 u 1 ( S R ( 2 ) ) u i ( S R ( 2 ) ) u p ( S R ( 2 ) ) u G ( S R ( 2 ) )
S R ( 3 ) s 1 , 1 s 2 , 1 s r , 1 s R , 3 u 1 ( S R ( 3 ) ) u i ( S R ( 3 ) ) u p ( S R ( 3 ) ) u G ( S R ( 3 ) )
S R ( j ) s 1 , 1 s 2 , 1 s r , 1 s R , j u 1 ( S R ( j ) ) u i ( S R ( j ) ) u p ( S R ( j ) ) u G ( S R ( j ) )
.
S R ( H R ) s 1 , 1 s 2 , 1 s r , 1 s R , H R u 1 ( S R ( H R ) ) u i ( S R ( H R ) ) u p ( S R ( H R ) ) u G ( S R ( H R ) )
Best S B s 1 , B 1 s 2 , B 2 s r , B r s R , B R u 1 ( S B ) u i ( S B ) u p ( S B ) u G ( S B )
Table 8. Comparisons of results between BCR prioritization and the proposed method.
Table 8. Comparisons of results between BCR prioritization and the proposed method.
ApproachBest Strategies by Service RegionUtility ValuesGlobal Utility
123456789101112 u 1 ( S k ) u 2 ( S k ) u G ( S k )
BCR prioritization
CPM ≤ 100 MB s 1 , 310 s 2 , 50 s 3 , 117 s 4 , 102 s 5 , 131 s 6 , 158 s 7 , 62 s 8 , 526 s 9 , 325 s 10 , 234 s 11 , 250 s 12 , 220 0.5225970.4974900.510044
CPM ≤ 200 MB s 1 , 383 s 2 , 72 s 3 , 181 s 4 , 172 s 5 , 213 s 6 , 203 s 7 , 126 s 8 , 621 s 9 , 411 s 10 , 358 s 11 , 323 s 12 , 301 0.5264930.4950010.510747
CPM ≤ 300 MB s 1 , 461 s 2 , 116 s 3 , 264 s 4 , 229 s 5 , 328 s 6 , 264 s 7 , 203 s 8 , 699 s 9 , 492 s 10 , 430 s 11 , 413 s 12 , 363 0.5282420.4925030.510372
Proposed method
Best scenario s 1 , 384 s 2 , 72 s 3 , 182 s 4 , 173 s 5 , 219 s 6 , 206 s 7 , 131 s 8 , 626 s 9 , 414 s 10 , 363 s 11 , 327 s 12 , 307 0.5265430.4949540.510748
Table 9. Preventive maintenance plans obtained from the BCR prioritization and the proposed method.
Table 9. Preventive maintenance plans obtained from the BCR prioritization and the proposed method.
Service
Region
Budget ≤ 100 MBBudget ≤ 200 MBBudget ≤ 300 MBBest Scenario
BPM r CPM r B r BPM r CPM r B r BPM r CPM r B r BPM r CPM r B r
1120.7717.10310131.7823.91383141.1137.21461131.7823.91384
21.200.17501.860.64723.853.611161.860.6472
328.774.0411742.9313.5418151.6125.8526442.9313.54182
418.353.2410233.6313.1517238.9021.5122933.6413.16173
523.094.2113142.4316.5121353.8033.0132842.7716.85219
646.375.2815855.0611.1320361.6420.1526455.2911.36206
70.590.11620.980.351261.481.022031.010.38131
8233.0817.60526247.0926.42621251.8733.58699247.2926.63626
984.016.2232593.6412.6041197.1117.3449293.6712.62414
10131.3220.00234171.5944.35358180.3456.64430172.1144.86363
1144.315.6825049.078.8532352.4613.5741349.389.15327
12171.6816.34220190.7428.52301196.7036.41363190.9828.75307
Total903.5499.9924851060.80199.9733641130.87299.9042621062.71201.853404
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Share and Cite

MDPI and ACS Style

Teera-achariyakul, N.; Rerkpreedapong, D. Optimal Preventive Maintenance Planning for Electric Power Distribution Systems Using Failure Rates and Game Theory. Energies 2022, 15, 5172. https://doi.org/10.3390/en15145172

AMA Style

Teera-achariyakul N, Rerkpreedapong D. Optimal Preventive Maintenance Planning for Electric Power Distribution Systems Using Failure Rates and Game Theory. Energies. 2022; 15(14):5172. https://doi.org/10.3390/en15145172

Chicago/Turabian Style

Teera-achariyakul, Noppada, and Dulpichet Rerkpreedapong. 2022. "Optimal Preventive Maintenance Planning for Electric Power Distribution Systems Using Failure Rates and Game Theory" Energies 15, no. 14: 5172. https://doi.org/10.3390/en15145172

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop