Next Article in Journal
Testing Smart Grid Scenarios with Small Volume Testbed and Flexible Power Inverter
Previous Article in Journal
Hysteresis Control in Pump-Controlled Systems—A Way to Reduce Mode-Switch Oscillations in Closed and Open Circuits
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Cost and Emissions Reduction in CO2 Capture Plant Dependent on Heat Exchanger Type and Different Process Configurations: Optimum Temperature Approach Analysis

by
Solomon Aforkoghene Aromada
1,*,
Nils Henrik Eldrup
2 and
Lars Erik Øi
1
1
Department of Process, Energy and Environmental Technology, University of South-Eastern Norway, Kjølnes Ring 56, 3918 Porsgrunn, Norway
2
SINTEF Tel-Tek, SINTEF Industri, Forskningsparken, Hydrovegen 67, 3936 Porsgrunn, Norway
*
Author to whom correspondence should be addressed.
Energies 2022, 15(2), 425; https://doi.org/10.3390/en15020425
Submission received: 28 November 2021 / Revised: 24 December 2021 / Accepted: 28 December 2021 / Published: 7 January 2022

Abstract

:
The performance of a plate heat exchanger (PHE), in comparison with the conventional shell and tube types, through a trade-off analysis of energy cost and capital cost resulting from different temperature approaches in the cross-exchanger of a solvent-based CO2 capture process, was evaluated. The aim was to examine the cost reduction and CO2 emission reduction potentials of the different heat exchangers. Each specific heat exchanger type was assumed for the cross-exchanger, the lean amine cooler and the cooler to cool the direct contact cooler’s circulation water. The study was conducted for flue gases from a natural-gas combined-cycle power plant and the Brevik cement plant in Norway. The standard and the lean vapour compression CO2 absorption configurations were used for the study. The PHE outperformed the fixed tube sheet shell and tube heat exchanger (FTS-STHX) and the other STHXs economically and in emissions reduction. The optimal minimum temperature approach for the PHE cases based on CO2 avoided cost were achieved at 4 °C to 7 °C. This is where the energy consumption and indirect emissions are relatively low. The lean vapour compression CO2 capture process with optimum PHE achieved a 16% reduction in CO2 avoided cost in the cement plant process. When the available excess heat for the production of steam for 50% CO2 capture was considered together with the optimum PHE case of the lean vapour compression process, a cost reduction of about 34% was estimated. That is compared to a standard capture process with FTS-STHX without consideration of the excess heat. This highlights the importance of the waste heat at the Norcem cement plant. This study recommends the use of plate heat exchangers for the cross-heat exchanger (at 4–7 °C), lean amine cooler and the DCC unit’s circulation water cooler. To achieve the best possible CO2 capture process economically and in respect of emissions reduction, it is imperative to perform energy cost and capital cost trade-off analysis based on different minimum temperature approaches.

1. Introduction

Climate change caused by global warming is the greatest environmental challenge to our world today [1]. The Intergovernmental Panel on Climate Change (IPCC) asserted unequivocally that the blame is mostly on humans [2]. Thus, humans need to intervene to mitigate climate change [3], which motivated the Paris Agreement. Carbon capture and storage (CCS), which includes transport, is widely recognised as a promising measure to mitigate CO2 emissions associated with the combustion of fossil fuels in power plants, cement plants and other process industries [4]. A number of carbon capture technologies and techniques have already been recognised: the absorption of CO2 into solvents followed by desorption [5], the separation of CO2 from exhaust gas by means of membrane [5], the adsorption of CO2 on solid adsorbents [6], the separation of CO2 from flue gas through cryogenic means [5] and the direct injection of exhaust gas into naturally occurring gas hydrate reservoirs so CO2 forms hydrate mainly with pore water [7]. Mechanisms of CO2 hydrate formation and stabilisation are described in [8,9,10].
Solvent-based CO2 capture technologies, especially the monoethanolamine (MEA) process, are the most mature option and are ready for industrial deployment [3,11]. The key challenge is still the high cost of its industrial deployment. CO2 capture and compression processes account for 80% of this cost, while the CO2 transport and storage processes each account for 10% of the cost [4,12]. Consequently, there is a necessity to investigate cost reduction possibilities, particularly in the CO2 capture process.
Several research efforts have been devoted to reducing the cost of the energy required. These include improved process configuration designs through flowsheet modifications [13] and the development of improved solvents and blends of solvents [14,15,16]. Recently, the recovery of waste heat to provide heat for desorption to reduce the cost of the heat demand has been studied [17,18]. Another essential aspect which needs to be given attention is the process units that make up the CO2 capture process. It is therefore important to seek cost reduction possibilities in the most important or expensive equipment units of the process. The lean/rich heat exchanger, which is also often called the cross-exchanger, is one of the important cost centres of the process. If any of the shell and tube heat exchanger types are used as the lean/rich heat exchanger, the lean/rich heat exchanger can account for 12–33% of the total plant cost (TPC) depending on the process scope [3,14,19,20,21].
Most of the CO2 absorption and desorption technoeconomic studies broadly specify shell and tube heat exchangers (STHXs). Nevertheless, references [3,19,20,22,23] have advocated for the plate heat exchanger (PHE) to replace the conventional STHX in CO2 capture processes to reduce cost. We have shown that the specific type of heat exchanger employed in the carbon capture process has a significant influence on the capture cost [3]. However, besides the preliminary results we presented at the 61st International Conference of Scandinavian Simulation Society (SIMS 2020) [20], we did not find any work in the literature where a comprehensive cost optimisation of the lean/rich heat exchanger in a CO2 absorption and desorption process using different types of heat exchangers, based on the minimum temperature approach ( Δ T m i n ) or logarithmic mean temperature difference (LMTD) was conducted, which is needed to identify cost reduction potential. This work therefore seeks to perform a trade-off analysis between energy and different heat exchangers’ costs based on optimal Δ T m i n . This is to examine how much of the carbon capture or avoided cost can be saved or reduced through finding the optimum Δ T m i n . Conducting this study with only one specific type of heat exchanger is not comprehensive enough or sufficient to draw a conclusion on the impact of Δ T m i n on the cost of carbon capture and actual CO2 emissions reduction.
This study is based on initial cost estimates. The initial cost estimation of heat exchangers in solvent-based CO2 capture plants is based on the required heat exchanger area. This is evaluated from the heat duty, overall heat transfer coefficient (U) and the logarithmic mean temperature difference (LMTD). The LMTD is calculated based on Δ T m i n at the cold and hot sides of a heat exchanger. In some studies, the LMTD is approximated to the Δ T m i n [14,23] since it is merely slightly higher than the Δ T m i n . Therefore, for a given thermal load, it is the Δ T m i n that determines the size of the heat transfer area needed in the lean/rich heat exchanger [19]. According to reference [11], the heat exchanger surface area needed in a lean/rich heat exchanger doubles if the Δ T m i n of 5 °C is applied instead of 10 °C. In addition, Δ T m i n also determines the amount of heat that can be recovered from the regenerated lean amine by the rich amine stream. Eimer [23] calculated that 7% more heat and 7% less heat would be recovered if a Δ T m i n of 5 °C and 15 °C, respectively, are used instead of 10 °C. Therefore, a cost reduction study focused on a lean/rich heat exchanger using different heat exchangers, as was completed in [3], is incomplete without studying the influence of Δ T m i n .
There are arguments about the influence of Δ T m i n on cost saving potential. According to [24], reference [25] argued that a reduction in reboiler heat consumption through a reduction in the Δ T m i n in a lean/rich heat exchanger is not significant. Arguments for higher Δ T m i n suggest that this lowers the cost of a heat exchanger required, as found in [11]. Different researchers have applied different Δ T m i n in their studies. References [26,27] specified 5 °C in their work. Reference [11] conducted their study using both 5 °C and 10 °C and emphasised that the Δ T m i n is an important parameter to optimise in the solvent-based CO2 capture process. Reference [28] used 8.5 °C, while reference [22] applied 11 °C and claimed it to be close to the optimum. Reference [29] performed their study with 15 °C. In their study, Alhajaj et al. [4] specified 20 °C to greatly reduced the influence of the lean/rich heat exchanger on the plant’s capital cost, while 10 °C is most commonly used [14,30,31].
For comprehensiveness, the fixed tube sheet shell and tube heat exchanger (FTS-STHX), U-tube shell and tube heat exchanger (UT-STHX), floating head shell and tube heat exchanger (FH-STHX) and the gasketed-plate heat exchanger (PHE) were selected for this study. The FTS-STHX is probably the most common type found in the process industry [32]; thus, in this study, it was selected as the base case scenario for the lean/rich heat exchanger. In addition, 10 °C was also specified as the base case Δ T m i n since it is most common in the literature. The impact of available excess heat from the cement plant on cost optimum Δ T m i n was also studied. How the Δ T m i n affects the actual amount of CO2 emissions reduction was investigated.

Objectives

This study was a trade-off analysis of energy cost and the cost of different but the most common types of heat exchangers that can be applied as a lean/rich heat exchanger in a CO2 absorption and desorption process. The aim was to evaluate the cost optimum Δ T m i n in terms of the commercial metric known as CO2 capture cost (CCC) and CO2 avoided cost (CAC), which considers CO2 emissions in operation of the capture plant. The specific objectives in this study were:
  • To evaluate the economic (cost reduction) and environmental (emissions reduction) implications of selecting a shell and tube type or a plate heat exchanger based on optimal cost, through trade-off analysis of energy and heat exchanger costs with respect to Δ T m i n .
  • To give a comprehensive assessment of the influence of Δ T m i n . on heat recovery in a lean/rich exchanger, on the heat exchange area of a lean/rich heat exchanger and heat duties of a reboiler and lean amine cooler.
  • To evaluate the impact of available excess heat from the cement plant on cost optimum Δ T m i n . Since the Norcem AS cement plant at Brevik in Norway was used as a case study, steam produced from the excess or waste heat was assumed to cover 50% CO2 capture steam requirement.
  • To perform sensitivity analysis of steam cost and total plant cost on the economic performance of the capture processes at different Δ T m i n .

2. Methodology

2.1. Scope of Analysis

All the cost estimates in this work are initial cost estimates. The cost optimisation in the study also refers purely to finding the minimum cost through trade-off analysis of energy consumption costs and the cost of a lean/rich heat exchanger resulting from varying Δ T m i n . The optimum Δ T m i n is the one that gives the minimum cost.
Since the most common Δ T m i n in the literature is between 5 °C and 15 °C, the trade-off analysis is conducted for a range of 5 °C to 20 °C. In the case of the PHE, the Δ T m i n range was extended to 3 °C to determine the optimum cost.
Detailed mechanical engineering design and optimisation are not necessary in initial cost estimation. Thus, details such as tube length and tube diameter are outside the scope of this work. In each case, a specific type of heat exchanger, for example, in the case of the fixed tube sheet shell and tube heat exchanger (FTS-STHX), only an FTS-STHX was used as the lean/rich heat exchanger, as the lean MEA cooler and as cooler for cooling the direct contact cooling (DCC) unit circulation water stream. The condenser, condensate cooler and intercoolers were specified as UT-STHX in all cases.
The cost metrics of CO2 capture cost and CO2 avoided cost were used. However, CO2 avoided cost was only estimated for the cement plant’s flue gas treatment processes. The capture cost is a mere commercial metric, but the avoided cost considers actual climate change or CO2 emission implications in operation of the plant.
The cost estimates were based on Nth-of-a-kind (NOAK) plants. These are chemical plants that have been commercially built after the technology has been successfully adopted and experience has been gained from first-of-a-kind (FOAK) plants.
Energy provision for the plant was assumed to be from the combustion of natural gas. Thus, the CO2 emissions that result from energy (steam) production were accounted for as 0.00018 tCO2/kWh (thermal) [33]. Meanwhile, for electricity, it was four times this value for steam by assuming 25% efficiency in the conversion of steam to electricity [34,35,36].
For comprehensiveness, 90% CO2 absorption from flue gas of two different industrial processes with different flow rates and CO2 concentrations were considered. They were exhaust gas from a 400 MW combined-cycle (NGCC) power plant in Mongstad near Bergen and flue gas from the Norcem AS cement plant at Brevik both in Norway [37,38].
Two process configurations were also studied: the standard and the lean vapour compression (LVC) CO2 absorption and desorption models. The schematic descriptions of the two processes are presented in Figure 1 and Figure 2. How they were implemented in the simulation, that is, the process flow diagrams (PFDs), are attached in Appendix A as Figure A1, Figure A2, Figure A3 and Figure A4. The process only includes the flue gas fan and the direct contact cooler (DCC) precooling section, the absorption–desorption process and the CO2 compression section. For simplicity, the water wash section shown in Figure 1 is not included. The compression section was modelled as was shown in [39]. The compression was carried out in four stages with intercoolers and separators. A CO2 pump was used to pump the supercritical CO2 from the final pressure of 76 bar to 110 bar. CO2 transport and storage were not necessary in this work. CO2 transport and storage estimates are available in [40,41,42]. Location factor was assumed as 1 since it was not important in this study.

2.2. Process Simulations

A 30 wt% monoethanolamine (MEA) process simulation for 90% CO2 capture from the two flue gases was performed in Aspen HYSYS Version 12. The lean amine stream entered the top of the absorber at 40 °C and at 1.013 bar. The reflux ratio in the desorber was 0.3. The first process for CO2 capture concerned exhaust gas from a natural gas combined-cycle (NGCC) power plant in Mongstad, close to Bergen in Norway. The second capture process concerned flue gas from Norcem Cement plant in Brevik in Norway.
The NGCC power plant exhaust gas and the cement plant’s flue gas specifications are given in Table 1 and Table 2, respectively. The simulation strategy was the same as in our previous works [34,35,37]. The absorber in the NGCC case was simulated with 17 packing stages (1 m per packing stage) with Murphree efficiencies of 11–21% from the bottom to top, as was carried out in [31,35]. The cement plant’s case absorption column was simulated with 29 packing stages (0.6 m per packing stage) with a constant Murphree efficiency of 15% based on [24]. Thus, the cement plant’s case absorption total packing height was 17.4 m. In both cases, the desorption column was simulated with 10 packing stages (1 m per packing stage) each and a constant Murphree efficiency of 50%. The desorber was maintained at 2 bar, and the reboiler temperature was specified as 120 °C. The minimum temperature approach of the lean/rich heat exchanger was 10 °C in the base case.
The DCC section and compression section of both processes were modelled in the same way. The flue gas fan raised the flue gas pressure from 1.01 bar to 1.21 bar to cover for the pressure drop in the absorber. Each of the compression stages had a pressure ratio of 2.8. The inlet pressure of the first stage was at 1.5 bar, and the final compression pressure was 75.9 bar. With the aid of the intercoolers, the temperature of the CO2 stream was maintained at the supercritical temperature of 31 °C. The CO2 streams, each having a purity of 99.74%, were then pressurised to 110 bar, as carried out by [39].

2.3. Equipment Dimensioning and Assumptions

The equipment sizing was based on the mass and energy balances from the process simulations. The approach was the same as that used in [3,20,36,43].
The absorption and desorption columns were dimensioned based on superficial gas velocity using the Souders–Brown equation with a k-factor of 0.15 m/s [44]. Structured packing was selected as advocated by [22] to reduce operating cost by reducing the pressure drop. A shell tangent-to-tangent height (TT) of 40 m was specified for both systems’ absorption columns to account for the water wash section, even though its details were not included in the study. The desorption columns’ shell tangent-to-tangent heights were also specified as 25 m.
The flue gas fans, pumps and compressors in both processes were sized based on their duties in kW and flow rates in m3/h, except the pumps in l/s. The values were obtained directly from the simulation.
The separators were dimensioned as vertical vessels; the vessel diameter was calculated using the Souders–Brown equation with a k-factor of 0.101 m/s [44,45]. A corrosion allowance of 0.001 m, joint efficiency of 80%, stress of 2.15 × 108 Pa, and a tangent-to-tangent to diameter ration of 3, i.e., TT = 3Do [35,45] were specified. The direct contact cooler (DCC) unit was dimensioned in similar manner, with the shell tangent-to-tangent height specified to be 15 m and a 4 m packing height.
The reboiler, coolers and condenser were sized based on the required heat exchange area, as carried out for the main heat exchangers in the next section. All the cooling water inlet and outlet temperatures were specified to 15 °C and 25 °C, respectively, and were controlled using adjust functions. The overall heat transfer coefficients of 1200 W/m2·K and 1000 W/m2·K [35] were specified for the U-tube kettle-type reboiler and condenser (UT-STHX)m respectively. Meanwhile, 800 W/m2·K [35] and 1600 W/m2·K were used for the coolers with STHXs and PHE, respectively. The conditions of steam supplied to the reboiler were 145 °C and 4 bar, while it exited at 130 °C and 3.92 bar.

2.4. Basis for Heat Exchange Equipment Sizing and Assumptions

Initial cost estimation of heat exchangers is mainly based on the required heat exchange area. This is the surface area needed to effectively recover a reasonable amount of heat from the returning lean amine stream from the desorber to heat up the rich amine stream. The estimation of the required heat exchange area is relatively simple compared to columns and vessels during initial cost estimation. This is simply completed using Equation (1):
Q ˙ L R H X = U S T H X · A S T H X · Δ T L M T D
Q ˙ L R H X = U P H E · A P H E · Δ T L M T D
where Q ˙ L R H X is the thermal load, and U is the overall heat transfer coefficient. “A” refers to the required heat exchange area, and Δ T L M T D is the log mean temperature difference (LMTD). Subscript “STHX” stands for shell and tube heat exchanger type, while subscript “PHE” represents the plate heat exchanger. Since the LMTD is only slightly higher than the minimum temperature approach ( Δ T m i n ), some studies simply assume LMTD Δ T m i n [14,23]. In this study, LMTD is calculated as shown in Equation (3).
LMTD = ( T h o t , o u t T C o l d , i n ) ( T h o t , i n T C o l d , o u t ) l n ( T h o t , o u t T C o l d , i n ) ( T h o t , i n T C o l d , o u t ) .
where T h o t , i n and T h o t , o u t are the temperature of the returning lean amine stream at the hot side and cold side, respectively. The temperature of the cold stream, rich amine at the cold side and hot side are represented with T C o l d , i n and T C o l d , o u t , respectively.
In the literature, constant overall heat transfer coefficients are typically used in techno-economic studies (initial cost estimates) of carbon capture processes [46]. The following values can be found for the overall heat transfer coefficients, U for the lean/rich heat exchanger in an MEA CO2 capture process with a shell and tube heat exchanger (STHX): 500 W/m2·K [24], 550 W/m2·K [47], 710 W/m2·K [48], 732 W/m2·K [14] and 760.8 W/m2·K [4]. The U-value in [14] is used this work. If we assume LMTD = Δ T m i n , as done in [14,23], Equation (1) becomes:
A S T H X = ( Q ˙ L R H X 732 ) · ( 1 Δ T m i n ) m 2 A S T H X = 00137 Q ˙ L R H X · ( 1 Δ T m i n ) m 2
or
A S T H X · Δ T m i n =   0.00137 Q ˙ L R H X   K · m 2
The overall heat transfer coefficient of the plate heat exchanger is much higher than that of the shell and tube heat exchangers. Thus, they exhibit an order of magnitude higher surface area per unit volume in comparison with the STHXs. The overall heat transfer coefficient for the PHE is 2–4 times of the STHXs [32,49,50]. Based on that, a conservative overall heat transfer coefficient of 1500 W/m2·K was assumed in this work. Therefore, Equations (4) and (5) for the PHE become:
A P H E = 0.00067 Q ˙ L R H X · ( 1 Δ T m i n ) m 2 ·
or
A P H E · Δ T m i n = 0.00067 Q ˙ L R H X   K · m 2
Equations (5) and (7) simply indicate that the required heat transfer surface area is directly proportional to the thermal load and inversely proportional to the minimum temperature approach ( Δ T m i n ) . The inverse relationship between the required heat exchange area and the minimum temperature approach ( Δ T m i n ) shows that decreasing Δ T m i n implies increasing the required heat exchange surface area, and thus, an increase in capital cost. On the other hand, the lower the Δ T m i n , the higher the Q ˙ L R H X . An increase in Q ˙ L R H X implies a decrease in the reboiler heat demand for desorption, which in turn means lower energy costs.

2.5. Capital Cost Estimation Method and Assumptions

The capital cost (CAPEX) in this work was estimated with the Enhanced Detailed Factor (EDF) method, which follows a bottom-up approach. The comprehensive details can be found in [31,35]. Here, the CAPEX is the total plant cost (TPC), which is the sum of all equipment installed costs. Since the work involved iterative simulations and cost estimation, it was implemented according to the Iterative Detailed Factor (IDF) Scheme as documented in [36]. It falls under Class 4 of the AACE International (Association for the Advancement of Cost Engineering) for concept screening and feasibility studies. Therefore, the accuracy of the TPC is expected to be ±30.
Equipment cost data were obtained from the most recent Aspen In-Plant Cost Estimator, i.e., Version 12, with a cost period of the first quarter of 2019. The capital cost year was 2020; thus, the cost estimates were escalated to 2020 using the Norwegian Statistisk Sentralbyrå (SSB) [51] industrial construction price index. Stainless steel was specified for almost all the main plant equipment because of corrosion. The flue gas fan and casing of the compressor were assumed to be constructed from carbon steel. The main assumptions for the estimation of the capital cost are summarised in Table 3.

2.6. Annual Operating and Maintenance Costs Estimation and Assumptions

The operating and maintenance costs in this work were divided into variable operating costs (VOCs) and fixed operating costs (FOCs). The economic assumptions utilised for the VOCs and FOCs are tabulated in Table 4.

2.7. CO2 Capture Cost and CO2 Avoided Cost Estimation

The main cost metrics in this work were CO2 capture cost and CO2 avoided cost. Levelised cost or levelised cost of electricity (LCOE) for power plants’ cost estimates is another important cost metric, but it was not used in this work. The estimation of CO2 avoided cost was only performed for the CO2 capture process for the cement flue gas. This accounts for CO2 emissions during the production of the electricity and steam needed for desorption. According to the U.S. Energy Information Administration [33], for each kWh of steam produced from natural gas, 0.18 kg of CO2 is emitted. That means, for every kWh of electricity consumed, 0.64 kg of CO2 is emitted. This is the basis for CO2 avoided cost estimation in this work, to account for the actual CO2 emissions reduction. The annualised capital cost, annualised factor, total annual cost (TAC) and CO2 capture cost were estimated using Equations (8)–(11), respectively. Symbol n is the number of operational years, and r is the discount rate. The CO2 avoided cost in this work was estimated with Equation (12), which is equivalent to (13), as was also carried out in several studies in the literature [29,52,54,55]. The cost of transport and storage were not included. This is because transport and storage costs depend on the mode of transport, distance and specific characteristics of the storage site. When the transport and storage costs are included to account for the entire CCS chain, Equation (14) is used.
A n n u a l i z e d   C A P E X   ( y r ) = c a p i t a l   c o s t   ( T P C ) A n n u a l i z e d   f a c t o r
Equation (8) is applied to compute the annualised factor.
A n n u a l i z e d   f a c t o r =   i = 1 n [ 1 ( 1 + r ) n ]
T A C   ( y r ) = A n n u a l i z e d   C A P E X   ( y r ) + A n n u a l   V O C   ( y r ) + A n n u a l   F O C   ( y r )
C O 2   c a p t u r e   c o s t   ( t C O 2 ) = T A C   ( y r ) M a s s   o f   C O 2   a n n u a l   c a p t u r e d   ( t C O 2 y r )  
C O 2   a v o i d d e d / a b a t e d   c o s t   ( t C O 2 )   =   T A C   ( y r ) M a s s   o f   a n n u a l   C O 2   c a p t u r e d     ( t C O 2 y r )     M a s s   o f   a n n u a l   C O 2   e m i t t e d   i n   e n e r g y   p r o d u c t i o n     ( t C O 2 y r )
C O 2   a v o i d e d   c o s t   ( t C O 2 )   =   ( C O P ) P C C     ( C O P ) r e f ( S p e c i f i c   e m i s s i o n s ) r e f       ( S p e c i f i c   e m i s s i o n s ) P C C
C O 2   a v o i d e d   c o s t   ( t C O 2 ) = ( C O P ) C C S ( C O P ) r e f ( S p e c i f i c   e m i s s i o n s ) r e f   ( S p e c i f i c   e m i s s i o n s ) C C S

3. Results and Discussion

3.1. Base Case Simulation Results and Discussion

The results obtained in the base case process simulations of this work are compared with those found in the literature in Table 5 and Table 6. The references in Table 5 and Table 6 are simulations of CO2 capture processes from an NGCC power plant and a cement plant’s flue gases, respectively. In addition, they are all 30% MEA solvent CO2 capture processes. The CO2 concentrations in the flue gases are provided.
In the NGCC power plant’s case, the rich loading in this work is only about 0.02–0.03 more than the references [28,30,56]. The lean loading of the references is not available to ascertain their cyclic capacity. The reboiler specific heat consumption calculated in this work is 4.8% less than the results published in [30,56]. The absorber packing heights have great influence on the reboiler heat requirement, and they vary from one study to another, as can be seen in Table 5. The result calculated in this work is almost the same as the simulation result of [28]. The Δ T m i n are, however, different; reference [28] used 8.5 °C, while 10 °C was specified in this work. Reboiler specific heat requirements of 3.66 GJ/tCO2 and 3.70 GJ/tCO2 were calculated for Δ T m i n of 8 °C and 9 °C, respectively, in this work. The agreement of the results of this work with the references is good.
In the cement plant flue gas CO2 capture process, the specific reboiler heat consumption calculated is 0.7% to 3.4% higher than the references [14,57]. The agreement in the cement process is also good.

3.2. Base Case Capital Cost Analysis

The estimates of total plant cost (TPC) of the different plant scenarios are presented and compared in Table 7. These results are only for the base cases with Δ T m i n of 10 °C. Here and in all other parts of this paper, the FTS-STHX case with Δ T m i n of 10 °C is the reference case. The heat exchanger areas used for the heat exchanger purchase costs in this work were estimated based on Equations (1)–(7). In each case, the same type of heat exchanger was specified for the lean/rich heat exchanger, lean MEA cooler and DCC cooler functions, while the UT-STHX was specified for the condenser and condensate cooler.
The estimates of the standard CO2 capture processes for the cases of the STHXs systems are close to results in the literature. Manzolini et al. [58] estimated a TPC of an MEA-based standard CO2 capture plant from an NGCC power plant to be EUR 163.2 million in 2015. Li et al. [59] estimated a TPC of USD 132.6 million (2013) for an MEA-based post-combustion CO2 capture from a 650 MWe advanced pulverised coal (APC) power plant. The cost is expected to be lower due to the higher partial pressure of CO2 in an APC power plant exhaust gas. This is in addition to the fact that even the estimated TPCs of similar plants are expected to differ due to the different capital cost estimation methods and underlying assumptions, as well as different plant-specific characteristics [35]. They also used a Δ T m i n of 15 °C, which will cause a significant reduction in the capital cost due to a reduction in the cost of the cross-exchanger. It is challenging to make a direct comparison of cost estimates from different studies [35,41,52].
A TPC of EUR 76 million (cost year of 2014) was estimated by [52] for a representative size of a European cement plant with a clinker annual production capacity of 1 metric ton. This study used the Norcem As cement plant in Brevik as a case study, which has an annual cement production of around 1.2 million tons [60].
The results in Table 7 indicate that 14% and 17% can be saved if PHE is specified for the cross-exchanger, lean MEA cooler and DCC cooler functions in the NGCC power plant and cement plant standard CO2 capture processes, respectively. If the lean vapour compression (LVC) configuration is implemented, in both industrial processes, a 10% cost reduction in TPC will be achieved if the PHE is used instead of the FTS-STHX.

3.3. Capital Cost Distribution

It is important to establish the capital cost contributions of the different functional operational units, to show why attention needs to be given to the cost reduction of lean/rich heat exchangers. This is a common practice when the EDF method is employed for the capital cost estimation of a process plant [35]. It helps during the process development because the process engineer can see the effect of their choices very quickly. In addition, it becomes easier to communicate between the cost estimator and the process developer on which equipment needs to be cost optimised [35].
Figure 3 and Figure 4 present the capital cost distribution of the CO2 capture plant for the NGCC power plant’s exhaust gas and the cement plant’s flue gas, respectively. If any of the three shell and tube heat exchanger types are employed as the lean/rich heat exchanger, then the lean/rich heat exchanger becomes the second- and third-highest contributing equipment to the total plant cost in the standard cases of the cement plant and NGCC power plant capture processes, respectively. The cross-exchanger contributes 16% or 17% if FTS-STHX or FH-STHX, respectively, is selected for its function in the two standard CO2 capture and compression processes. Nwaoha et al. [14] showed that broadly specified STHX calculated the cross-exchanger contribution in an MEA capture process from a cement plant flue gas to be 17%, which is the same value estimated for the FH-STHX case in this study. This study applied the same overall heat transfer coefficient as [14]. The lean vapour compression configuration reduced the lean/rich heat exchanger’s contribution to 10% in both FTS-STHX and FH-STHX cases and in both the NGCC power plant and the cement flue gas treatment processes. This is because of a reduction in steam requirement by the reboiler due to the extra stripping vapour supplied to the desorber in this case. If PHE is used instead of any of the STHXs, the cross-exchanger will only contribute 5% and 3% to the TPC in both standard and lean vapour compression CO2 capture plant configurations, respectively, in two different industrial processes.
Since the same type of heat exchanger was specified for the cross-exchanger, lean MEA cooler and DCC cooler functions, in the NGCC power plant’s case, the total plant cost will decline by 14% and 9% for the standard configuration and the lean vapour compression configuration, respectively, in comparison with the reference case (FTS-STHX). In the cement plant’s case, the reduction in TPC is 17% and 10%, respectively. These results for the base cases show a significant cost reduction in the TPC.
In the NGCC power plant cases, the absorber contributes the highest amount to the TPC. That is, 42–44% and 31–34% in the standard model and the lean vapour compression configuration, respectively. Meanwhile, in the cement plant’s cases, the contributions are 14–17% and 13–14% in the standard model and the lean vapour compression configuration, respectively. This is low due to the relatively lower volume flow of flue gas and higher CO2 partial pressure due to the higher CO2 concentration in this case compared to the power plant’s case. The absorber dimensioning results for both systems are presented in Table 8. In the case of the NGCC power plant, the absorber was split up into three units since for diameters greater than 10 m, concrete columns are a better choice, and stainless steel was specified in this study [46].

3.4. Impact of Minimum Temperature Approach on Heat Recovery and on the Required Heat Exchanger Surface Area

The minimum temperature approach of the lean/rich heat exchanger of a solvent-based CO2 absorption and desorption process determines how much heat can be recovered by the rich stream from the lean stream flowing from the desorber. This is shown in Table 9, where the heat recoveries at the Δ T m i n of 5 °C, 15 °C and 20 °C are compared with the heat recovery of the base case Δ T m i n of 10 °C. The results obtained are compared with the results also calculated for a 400 MW NGCC power plant exhaust gas in the book of Dag Eimer [23]. Negative values represent relative less heat recovery, while positive values show how much more heat is recovered compared to Δ T m i n of 10 °C.
Even though the estimated amount of heat recovery in the base case Δ T m i n in [23] is 6% less than the result in this work, both works calculated 7% more heat recovery at Δ T m i n of 5 °C compared to the reference process at Δ T m i n of 10 °C for the NGCC system. The heat recovery is higher in this work because the cold rich stream enters the cross-heat exchanger at 46 °C, while 50 °C was assumed by [23]. At Δ T m i n of 15 °C, 8% less heat recovery was obtained in this work in the CO2 capture from the NGCC power plant’s exhaust gas, while [23] also calculated this value to be 7%. In this work, in the NGCC system, if Δ T m i n of 20 °C is specified, the heat recovery will decrease by 16%.
No work was found to compare the heat recovery results for the cement system. However, the heat recovery at Δ T m i n of 5 °C is about 10% higher than at Δ T m i n of 10 °C in the CO2 absorption and desorption in the cement plant scenario. At Δ T m i n of 15 °C and 20 °C, heat recovery decreases by approximately 9% and 20%, respectively.
The comprehensive results of heat duties of the cross-exchanger, reboiler and lean MEA coolers at the different Δ T m i n are presented in Table 10, Table 11, Table 12 and Table 13 for the NGCC exhaust gas cleaning process and cement plant flue gas purification systems. These four tables also show the resulting heat exchange surface area required in the lean/rich heat exchanger for a Δ T m i n range of 5–20 °C for the STHXs and a Δ T m i n range of 3–20 °C for the PHE. The relative increase and decrease in the heat transfer area needed in the lean/rich heat exchanger for both the STHXs and PHE are also computed and presented in Table 9, Table 10, Table 11 and Table 12.
In the NGCC power plant standard CO2 capture process, if a Δ T m i n of 5 °C is specified in the lean/rich heat exchanger instead of 10 °C, the required heat exchange area becomes 76% larger if any of the STHXs are employed as the lean/rich heat exchanger. If the PHE is used, then the calculated surface area becomes 95% larger at 5 °C instead of 10 °C. According to Karimi et al. [11] and Eimer [23], the required heat exchanger area doubles if a Δ T m i n of 5 °C is used instead of 10 °C. The analysis of Eimer [23] is based on the same 400 MW NGCC process as was completed in this work. The work of [11] regards a 90% CO2 absorption and desorption from a 150 MW bituminous coal power plant’s exhaust gas. In the NGCC system, especially for the PHE case, the results of this work are close to two times the heat transfer area required if Δ T m i n of 5 °C is used instead of the reference Δ T m i n of 10 °C. The difference is simply due to the overall heat transfer coefficients used. In this work, an overall coefficient (U-value) of 732 W/m2·K [14] was used to estimate the required heat transfer area for the STHXs. Eimer [23] used 1250 W/m2·K, which is considerably higher than the U-values in CO2 capture studies such as [14,24,31,47]. Since the analysis of Karimi et al. [11] was based on data from [61,62], the overall heat transfer coefficient used for the STHX surface calculation should be considerably higher than the U-value in this work and in [14,24,31,47].
In the cement plant standard CO2 capture process, decreasing the Δ T m i n from 10 °C to 5 °C resulted in a 97% and 100% increase in the heat exchanger area needed for the cases of STHXs and PHE, respectively.
In the lean vapour compression cases, using Δ T m i n of 5 °C instead of 10 °C caused the heat exchanger area to increase by 128% for both the STHXs and PHE in the NGCC power plant CO2 capture process. Meanwhile, in the case of the cement plant, the increase is 138% and 139% for the STHXs and PHE, respectively.
The number of heat exchanger units required are significantly fewer if the PHE is selected for the CO2 capture operations instead of the STHX. These also lead to a lower area or volume requirement as well as less capital cost, as also shown in Figure 2 and Figure 3. The reboiler duty increases by 1–2 MW with an increase of 1 °C of Δ T m i n of the lean/rich heat exchanger. The duty of the lean MEA cooler also increases at approximately 2–3 MW for every 1 °C increase in the Δ T m i n of the lean/rich heat exchanger. The specific heat demand by the reboiler increases mainly between 0.03–0.04 GJ/tCO2 with each 1 °C increase in the Δ T m i n of the lean/rich heat exchanger. Table 14 provides a summary of comparison between the standard and the lean vapour compression configuration CO2 capture processes.
The results in this section show that the Δ T m i n of the lean/rich heat exchanger has significant influence on important economic variables in a CO2 absorption and desorption process. An increase in the reboiler duty implies an increase in the amount of steam needed. The amount of cooling water needed also increases with increase in the lean amine duty. As the reboiler and lean MEA cooler duties increases with an increase in the Δ T m i n of the lean/rich heat exchanger, the corresponding required heat transfer area also increases; therefore, to arrive at the minimum cost of the process, a trade-off analysis is required using Equations (8)–(11) and (13), as also stated by [11]. In this work, Equation (10) is mostly used for the trade-off analysis, which also depends on Equations (8) and (9).

3.5. Base Case Variable Operating Cost (VOC)

The varying heat duties in the reboiler and in the lean MEA cooler with varying Δ T m i n of the lean/rich heat exchanger in Table 10, Table 11, Table 12 and Table 13 have variable operating cost implications. An increase in reboiler heat consumption implies an increase in energy (steam) cost. Meanwhile, changes in the duty of the lean MEA cooler mean changes in both the amount of cooling water needed and electrical energy consumption for pumping of water, as the situation demands. Figure 4 shows that these variables which are influenced by the Δ T m i n of the lean/rich heat exchanger are the most important variable cost drivers in both the NGCC power plant and cement plant flue gas CO2 capture systems. At a Δ T m i n of 10 °C, they account for 82% and 84% of the variable costs in the NGCC standard and lean vapour compression processes, respectively. Meanwhile, the energy cost accounts for 82% and 81% of the variable cost in the standard configuration and the lean vapour compression process, respectively, in the cement plant systems.
Since the PHEs have small channels, the pressure drop is higher than for the STHXs. Higher pumping duties by the rich pump and lean pump are incurred by the PHE system [3]. The allowable pressure drops in the tubes of the STHXs is between 0.5 and 0.7 bar [62]. According to [63,64], the allowable pressure drop is 1 bar. To account for the higher pumping pressure in the PHE system, the outlet pressure of the rich pump and lean pump were made 1 bar higher than when any STHX was selected for the lean/rich heat exchanger function.
Figure 5 shows the electricity consumption cost in both the STHX and the PHE systems for the NGCC power plant lean vapour compression. Figure 5 also shows that the two energy (steam and electricity) consumption costs slightly increase with an increase in the Δ T m i n of the lean/rich heat exchanger. The cost of electricity consumption of the PHE system is about EUR 70,000 more than those of the processes with STHXs as the lean/rich heat exchanger.

3.6. Base Case CO2 Capture Cost

Estimates of CO2 capture cost for all the base cases in this study are presented in Table 15. These values are in line with the literature results. According to reference [31], CO2 capture costs for post-combustion CO2 capture processes are in the range of EUR 50/tCO2 to EUR 128/tCO2. A decade ago, reference [65] reported a range of EUR 60/tCO2 to EUR 90/tCO2 for the power industry. Meanwhile, a range of USD 48/tCO2 to USD 111/tCO2 (i.e., EUR 41/tCO2 to EUR 95/tCO2) was reported by [35] specifically for post-combustion CO2 capture from NGCC power plant’s exhaust gas.
In their study, Roussanaly et al. [66] estimated a CO2 capture cost of EUR 63.2/tCO2 (cost year of 2014) for a solvent-based CO2 capture from a cement plant’s flue gas. For the cost year of 2016, Ali et al. [31] estimated the capture cost for a similar cement flue gas CO2 capture system to be EUR 62.5/tCO2. These literature capture costs are close to the capture cost in this work for the STHXs systems, though the cost years are different.
These results revealed that using the PHE in a standard post-combustion CO2 capture process will lead to 4.4% reduction in carbon capture cost. A CO2 capture cost reduction of approximately 3% will be achieved if the lean vapour compression is implemented instead. These are significant cost reductions, since over 1 million tons of CO2 and over 630,000 CO2 are captured in the NGCC system and the cement system, respectively.
The costs based on actual CO2 emissions reduction (CO2 avoided cost) from the cement plant were also estimated for the FTS-STHX, FH-STHX and PHE capture scenarios. They are EUR 87.5/tCO2, EUR 87.7/tCO2 and EUR 73.7/tCO2, respectively, for the cement flue gas’ standard of CO2 capture process. For the lean vapour recompression cement flue gas process, the costs are EUR 77.4/tCO2, EUR 77.6/tCO2 and EUR 75.2/tCO2 for the FTS-STHX, FH-STHX and PHE capture systems, respectively. The CO2 avoided cost values reported in the literature for the MEA capture systems ranges widely from EUR 75/tCO2 to EUR 170/tCO2. A CO2 avoided cost of EUR 95.2/tCO2 was estimated by [67], while reference [68] estimated EUR 81.9/tCO2. Li et al. [29] reported an avoided cost of EUR 86.4/tCO2. A CO2 avoided cost of EUR 83/tCO2 was estimated by [66]. For a closely related system, EUR 80/tCO2 was recently estimated by [52].
The analysis of CO2 actual emissions reduction is given in Figure 6. Steam and electricity are assumed to be generated from natural gas with CO2 emissions of 0.18 kg of CO2 emitted per kWh (thermal). The lean vapour compression (LVC) has better CO2 emissions reduction performance due to the reduction in reboiler heat consumption from 3.89 GJ/tCO2 to equivalent heat (reboiler heat and compressor work) of 3.28 GJ/tCO2 (see Table 11 and Table 13).

3.7. Cost Optimum Temperature Approach—CO2 Capture Cost Analysis

The results of the trade-off analysis between energy cost and capital cost at different Δ T m i n based on CO2 capture cost are presented in Figure 7, Figure 8, Figure 9 and Figure 10. This is to investigate cost reduction potential and assess if significant cost reduction can be achieved through energy cost and heat exchanger cost trade-off analysis. To make the result comprehensive, the analysis was performed for two different flue gasses of two different industrial processes with different flue gas flow rates and different CO2 compositions, as stated earlier. Two different CO2 capture configurations, the conventional or standard process and the lean vapour recompression configurations were also used for this study. In the four figures, the left vertical axis represents the values of the STHXs, while the right vertical axis is for the PHE.
In the CO2 absorption from the NGCC power plant flue gas cases, the cost optimum a Δ T m i n of 12 °C was estimated for both the FTS-STHX and UT-STHX processes in the standard process. The cost optimum Δ T m i n for the FH-STHX and PHE are 14 °C and 6 °C, respectively. In the lean vapour compression configuration, all the STHXs have the same cost optimum Δ T m i n of 9 °C, while the PHE optimum is 5 °C.
These results revealed the significance of both the lean/rich heat exchanger function and the specific type of heat exchanger selected for the lean/rich heat exchanger on the cost of the capture process. The more expensive a specific heat exchanger type is, the higher the Δ T m i n that will achieve the cost optimum capture cost. Additionally, the less expensive the heat exchanger is, the lower the Δ T m i n that will give the cost optimum CO2 capture cost. While the cost savings at the optimum Δ T m i n is marginal in terms of CO2 capture cost in this work, the absolute value is significant, especially in the NGCC power plant capture system where over one million tons of CO2 is captured annually. In the standard process for the NGCC power plant capture system, an annual total cost saving of EUR 165,000/year to EUR 311,000/year was estimated depending on the specific heat exchanger type. Meanwhile, in the lean vapour compression process, the FTS-STHX and FH-STHX could only achieve EUR 97,000 and EUR 74,000, respectively, in CO2 capture cost at the optimum Δ T m i n . This is because all the STHXs cases’ optimum Δ T m i n was only one degree (1 °C) from the base case Δ T m i n . The UT-STHX case which also had its optimum at 9 °C achieved a cost saving of EUR 171,510. However, the lean vapour compression process with PHE achieved a cost reduction of EUR 819,530 at the cost optimum Δ T m i n .
In the cement plant standard capture processes, the cost optimum trade-off of both the FTS-STHX and the UT-STHX was 13 °C, while it was 7 °C for the PHE. In the lean vapour compression capture process, 10 °C, which is the base case Δ T m i n , remained the cost optimum for the two STHXs. The cost optimum Δ T m i n for the PHE system of lean vapour compression was 5 °C. The cost reduction in the two STHX processes based on standard capture configuration was marginal. However, the capture cost optimum Δ T m i n achieved EUR 253,570 and EUR 483,700 in the standard and lean vapour compression CO2 capture processes, respectively.
A general observation is that as the Δ T m i n decreases from 10 °C to 5 °C, the resulting increase in the heat exchanger area makes the capital cost dominate, causing the capture cost to rise steeply in the cases of all the STHXs in both capture configurations. In the standard process, above a Δ T m i n of 14 °C, the capture cost begins to increase steeply, indicating the dominance of steam cost, especially in the cement plant capture system. In the lean vapour compression systems, the impact of moving from one Δ T m i n to the next is more significant. The energy cost and heat exchanger cost trade-off trends of the standard CO2 capture system for both the NGCC power plant and cement plant capture systems are similar, likewise in the lean vapour compression configuration capture process for industrial capture processes.

3.8. Analysis of Cost Reduction Based on CO2 Capture Cost

A more appropriate way to present performance may not be in absolute values but in percentages. Therefore, the cost reduction potential of the systems was assessed on percentage basis. However, in comparisons here and in subsequent sections where cost saving potentials are reported, all comparison is made with the reference case. The reference case is the case of using FTS-STHX as the lean/rich heat exchanger with a “ Δ T m i n of 10 °C”, and for the lean MEA cooler and DCC cooler. This means all other Δ T m i n trade-off analyses of the FTS-STHX are compared with FTS-STHX of Δ T m i n of 10 °C to show if there is cost reduction potential at other Δ T m i n with the same heat exchanger type. All Δ T m i n trade-off analyses of the other specific types of heat exchanger cases were also all compared with the reference case, FTS-STHX of Δ T m i n of 10 °C. The results are presented in Figure 11 and Figure 12 using curves to concisely give overviews of the performance of utilising each specific type of heat exchanger at different Δ T m i n as well as the impact of choosing the lean vapour compression CO2 capture process.
In the NGCC power plant standard CO2 capture system, despite the significant energy demand reduction in the LVC process, the standard PHE system dominated over the lean vapour compression processes of the FTS-STHX and FH-STHX at Δ T m i n of 5 °C and 6 °C. It also competes with the lean vapour compression process of the UT-STHX at 5 °C. The cost optimum Δ T m i n (5 °C) of the PHE standard process achieved 4.7% cost reduction, while it was 9.6% for the lean vapour compression PHE process. This implies the lean vapour compression doubles the performance of the cost optimum PHE over the reference case. All the STHXs cases achieved significant cost reduction at all Δ T m i n in the lean vapour compression CO2 capture process.
In the cement plant flue gas treatment, the PHE system reached cost savings of 5% and 11.6% in the standard and lean vapour compression CO2 capture configurations, respectively. In both industrial flue gases treatments, the most robust FH-STHX process was not economically viable at all Δ T m i n in the standard capture processes. The FTS-STHX process could only realise very marginal cost savings between Δ T m i n of 11 °C (0.04%) and 14 °C (0.2%), with a maximum of 0.3% at the optimum Δ T m i n of 12 °C, in the NGCC power plant standard capture process. The standard UT-STHX process only achieved a maximum of 1%. The results revealed that while the lean vapour compression process achieves very good cost reduction for all specific types of heat exchanger studied, using the PHE as the lean/rich heat exchanger, lean MEA cooler and as cooler for the DCC circulation water dominates as the best choice for CO2 capture cost reduction, irrespective of its higher pumping cost requirement. With PHE, we can take advantage of the considerable energy reduction at lower Δ T m i n . Since steam is usually the major cost driver, operating at lower Δ T m i n between 4 °C and 7 °C and using PHE will provide the possibility of significant cost reductions.

3.9. Cost Optimum Temperature Approach—CO2 Avoided Cost Analysis

The previous section only considered economic viability without taking into account climate change implications. The actual CO2 emission reductions are not considered in CO2 capture cost estimation. This section deals with the cost of actual CO2 emissions reduction. It is pertinent to re-emphasise that the CO2 avoided cost in this study does not include CO2 transport and storage cost as in [29,52,54,55].
The results of the cost of actual CO2 emission reductions are presented in Figure 13 and Figure 14 for the standard and lean vapour compression CO2 capture processes from the cement plant’s flue gas, respectively. The red dot represents where the optimum CO2 capture cost was achieved. It is used to make a comparison with optimum CO2 capture cost and the optimum CO2 avoidance cost, that is when the actual CO2 emissions reduction is considered.
In the standard CO2 capture process, the optimum CO2 avoided cost was evaluated to be at Δ T m i n of 10 °C and 4 °C in the FTS-STHX and PHE scenarios, respectively. Meanwhile, in CO2 capture cost estimation, the cost optimum Δ T m i n is 13 °C and 7 °C in the cases of the FTS-STHX and PHE, respectively. In the LVC CO2 capture process, a Δ T m i n of 4 °C was also estimated as the cost optimum CO2 avoided cost, while it was 7 °C in the case of the FTS-STHX. The CO2 capture cost optimum Δ T m i n in the LVC process were 10 °C and 5 °C in the cases of the FTS-STHX and PHE, respectively.
The Δ T m i n in the lean/rich heat exchanger has a significant impact on the steam consumption in the reboiler, as shown in Table 10, Table 11, Table 12 and Table 13 as well as in Figure 6. Thus, the higher the Δ T m i n , the higher the steam requirement, which also implies the higher the indirect CO2 emissions due to production of steam by combustion of natural gas. The actual CO2 emissions reduction achieved by using an STHX as the lean/rich heat exchanger is a bit higher than if the PHE is applied. This is because of the higher electrical energy consumption in the case of the PHE compared to the STHX. It is due to the higher pumping duties by the rich pump and lean pump to pump the lean and rich amine streams through the small channels of the PHE. However, considering the cost optimum Δ T m i n of 4 °C in the case of using the PHE in both CO2 capture processes compared to the case of the FTS-STHX, the PHE absolutely dominates in performance economically and in CO2 emissions reduction efficiency. If the PHE is selected, its cost optimum Δ T m i n or even if 5 °C is specified for the lean/rich heat exchanger, it will achieve about 1.2% and 1.0% more CO2 emissions reduction more than its counterpart in the standard CO2 capture process and in the LVC CO2 capture configuration, respectively.
The optimum CO2 avoided costs of the PHE cases are EUR 82/tCO2 and EUR 73/tCO2 in the cases of the standard and LVC CO2 capture processes, respectively. The actual CO2 emissions estimated are approximately 65% and 68%, respectively. For the FTS-STHX cases, the estimated optimum CO2 avoided costs are EUR 88/tCO2 and EUR 77/tCO2 in the standard and LVC capture processes, respectively. The actual CO2 emissions reduced were estimated to be around 64% and 67%, respectively.
The results reveal the significance of performing cost optimisation of the lean/rich heat exchanger based on Δ T m i n trade-off analysis between energy cost and capital cost (especially heat exchanger cost). This work is therefore more complete than our previous work [3] where the conventional Δ T m i n of 10 °C was specified for all the specific heat exchanger types. It also emphasises the importance of this study.
Another important observation is that even though the electricity consumption of the lean vapour compression CO2 capture process is higher than that of the standard process, the significant reduction in steam consumption meant it achieved better actual CO2 emissions reduction and less CO2 avoided costs. Therefore, the lean vapour compression configuration gives a more economic and a more environmentally friendly outcome.

3.10. Analysis of Cost Savings Based on CO2 Avoided Cost Analysis

In this section, the CO2 avoided cost at different Δ T m i n of the lean/rich heat exchanger using the PHE and FTS-STHX are compared with that of the reference case (FTS-STHX with Δ T m i n of 10 °C). The results are presented in Figure 15. Since the cost optimum Δ T m i n of the FTS-STHX case in the standard capture process is 10 °C, no cost reduction is achieved at other Δ T m i n . However, the cost reduction achieved by the two PHE cases and the lean vapour compression capture process with FTS-STHX is higher here (CO2 avoided cost) compared to the CO2 capture cost estimates. The optimum CO2 avoided cost in the PHE cases achieved about 6% and 16.2% cost reduction in the standard and lean vapour compression CO2 capture processes, respectively. The lean vapour compression case with FTS-STHX CO2 avoided cost optimum achieved 12% cost reduction, compared to a 7.7% reduction in ordinary capture cost. This is due to the reduction in the amount of steam consumption when emissions reduction is considered. These cost reductions also indicate that the Δ T m i n of the lean/rich heat exchanger is an important process parameter to optimise [11].

3.11. Cost Optimum Minimum Temperature Approach—Excess (or Waste) Heat Implication

The available waste or excess heat at the Norcem AS cement plant in Brevik can cover for the production of steam for 50% CO2 capture. How this advantage affects the cost optimum Δ T m i n , emissions reduction and cost reduction potential was studied. The results are presented in Figure 16, Figure 17 and Figure 18. The PHE avoided cost optimum Δ T m i n in both the standard and lean vapour compression CO2 capture processes are 7 °C and 5 °C, respectively. The CO2 avoided costs at these optimum Δ T m i n are EUR 60/tCO2 and EUR 58/tCO2, respectively. Meanwhile, for the FTS-STHX cases, this is 13 °C and 10 °C in the standard and lean vapour compressions CO2 capture processes. The optimum CO2 capture cost of the PHE case in the standard capture process coincides with the avoided cost. This also occurred for the FTS-STHX case in the lean vapour compression capture process. The cost reduction performances of the two heat exchanger types in both the standard and lean vapour compression CO2 capture systems are presented in Figure 18. Even though the lean vapour compression is very effective in the reduction in energy consumption, the cost reduction in steam supply from waste heat to cover 50% CO2 capture in a 90% capture process shows the standard capture process with PHE as the lean/rich heat exchanger performing better than the lean vapour compression capture process with FTS-STHX at Δ T m i n less than 10 °C. The lean vapour compression process with FTS-STHX only outperformed the standard process with PHE with an average of 0.5% between 14 °C and 18 °C. These results, like the previous ones, also highlight that the PHE is a better choice economically and in emission reduction compared to the STHXs. This is because at their individual best costs (optimal cost), the PHE case achieved the least cost and a higher CO2 emissions reduction.
The cost reduction impact of having steam supply that is sufficient for up to 50% CO2 capture and its impact on the actual CO2 emissions reduction compared with a reference case (the original base case) of a standard CO2 capture having FTS-STHX with Δ T m i n of 10 °C are presented in Table 16. Table 16 is a summary of all the 90% CO2 capture from the cement plant’s flue gas based on CO2 avoided cost. The results indicate that if the lean vapour compression configuration is implemented with PHE as the lean MEA cooler, DCC circulation water cooler and as the lean/rich heat exchanger with a Δ T m i n of 5 °C, and steam can be successfully provided for up to 50% capture, then 10.4% more CO2 emissions reduction can be achieved compared to the reference case (base case). It is important to remember here that the base case is a standard CO2 capture process which has FTS-STHX as the lean MEA cooler, DCC circulation water cooler and as the lean/rich heat exchanger with a Δ T m i n of 10 °C, with steam supply only from natural gas combustion. When the available excess heat which can provide steam for up to 50% CO2 capture at Brevik was considered, the optimum PHE case of the lean vapour compression CO2 capture system achieved a 34% reduction in CO2 avoidance cost. It is important to note that this is in comparison with the base case without considering steam supply from excess heat. However, without excess heat, the lean vapour compression process with the optimised minimum temperature approach still achieved a 16.4% saving in CO2 avoided cost compared to the reference case.
In this study, steam supply has the greatest impact on cost reduction followed by the implementation of lean vapour compression process configuration. However, if the steam from the excess heat for 50% CO2 capture is available, then the cost reduction impact of selecting the PHE even in the standard capture process is greater than that of using FTS-STHX in the lean vapour compression process for a Δ T m i n less than 10 °C. If we must take advantage of less steam consumption and less indirect CO2 emissions which a lower Δ T m i n of 4–7 °C offers, then PHE is the best choice.

3.12. Sensitivity Analysis

This study is about the trade-off between energy and capital costs. Therefore, a sensitivity analysis of these two cost parameters on the overall capture cost and the CO2 avoided cost was conducted. Since the unit prices of energy can fluctuate widely, a probable range of ±50% was assumed for the steam cost [3,31]. The capital cost estimates in this work study fall under the “study estimate” (factored estimate). Thus, the probable accuracy is ±30%. However, a probable range of +30%/−15% was assumed, as was assumed in [52]. The NGCC power plant standard CO2 capture process and the cement plant LVC CO2 capture system were selected for the sensitivity analysis. The analysis is based on CO2 capture cost and CO2 avoided cost in the cases of the NGCC power plant and cement plant CO2 capture processes, respectively.
The results of the sensitivity analysis were estimated by comparing the performance of different processes, with each having a specific heat exchanger type at different Δ T m i n with the corresponding result of the FTS-STHX case with a Δ T m i n of 10 °C. This means, for example, in the case of a 50% increase in steam cost, the resulting estimates of both the PHE and FTS-STHX at the different Δ T m i n from the 50% increased steam cost are compared with a reference case, which is FTS-STHX, having a Δ T m i n of 10 °C with a 50% increase in steam cost. Therefore, the performance of the corresponding reference case, that is, a Δ T m i n of 10 °C will be zero (0) in all cases, makes for better comparison between the PHE case and FTS-STHX case when costs increase or decrease. This gives a better answer to the question, of “how better would the performance be if instead of having the reference case when changes occur in the cost of steam or capital cost”, the system has any other Δ T m i n or PHE is used. Then, what is the performance of the PHE system at different Δ T m i n . compared to the reference?
The results of the sensitivity analysis for ±50% changes in steam cost are presented in Figure 19 and Figure 20 for the NGCC power plant and the cement plant’s CO2 capture processes, respectively. In the NGCC power plant CO2 capture process, if there is an increase of 50% in steam cost, the performance of the FTS-STHX will be from 0 to −2.6%. That implies that more cost will be incurred if the design is for FTS-STHX with a Δ T m i n other than 10 °C. The PHE system performed better than the FTS-STHX with its cost optimum at a Δ T m i n of 6 °C (4.3%). However, the cost reduction achieved is lower than the in the original case. It continues to decline as the Δ T m i n increases until reaching 19 °C, where no savings can be made, but more cost would be incurred. Meanwhile, a 50% decline in steam cost resulted in cost savings for the FTS-STHX with the optimum at 17 °C, which achieved merely 1.6% cost reduction. The PHE system achieved a higher cost reduction compared to the original PHE case with the optimum at 8 °C (5.3%).
In the CO2 avoided cost estimates for the cement plant’s CO2 capture plant, a 50% rise in the steam cost resulted in a higher cost reduction in the FTS-STHX between 5 and 9 °C compared to the original case. More costs will be incurred at all Δ T m i n greater than 10 °C, and at all Δ T m i n (except 10 °C—reference case) if the steam cost reduces by 50%. In the PHE case, a 50% increase in steam cost will only make the PHE perform better between 3 and 6 °C, after which its performance becomes lesser than the original PHE case. The cost reduction ends at 12 °C, but at 16 °C if there is a 50% decline in the cost of steam. The performance of the PHE case with a 50% reduction in the cost of steam becomes better than the original PHE case and the case of +50% at 8 °C. The performance also increases with an increase in the Δ T m i n of the lean/rich heat exchanger.
The results of the sensitivity analysis of the capital cost are presented in Figure 21 and Figure 22 for both the NGCC power plant and the cement plant’s CO2 capture processes, respectively. The results are opposite to those of changes in the cost of steam in the NGCC power plant CO2 capture cost. The optimum Δ T m i n moved from 6 to 8 °C (5.4%) and from 6 to 5 °C (4.4%) in the cases of a +30% increase and −15% decrease, respectively, in the PHE cases. In the FTS-STHX cases, the optimum Δ T m i n moved from 12 to 14 °C (0.6%) and it remained 12 °C (0.2%) if the capital cost rose by +30% and declined by −15%, respectively. In the cement plant’s case, a ±30% change in the capital cost achieved their optimum at the same 4 °C as the original case for the PHE. The performance of the 30% increase scenario is slightly higher than the original PHE case at 4 °C (5.5%). This performance continued to slightly increase as the Δ T m i n of the lean/rich heat exchanger increased. The case of a −15% decrease in capital cost displayed a similar trend but in the opposite fashion. The performance is slightly lower than the original PHE case. The results for the FTS-STHX follow almost the same trend in the opposite way to the case of changes in steam cost. In the case of −15%, 7 °C is the optimum with 0.8% cost reduction.

3.13. Comparison of Optimum Δ T m i n Results with Literature

A lot of literature may not be available on an extensive trade-off analysis between energy cost and capital cost at different Δ T m i n in a post-combustion CO2 capture process. However, a review of some of the literature is given here. The work of Tobiesen et al. [25] indicated that reducing the Δ T m i n does not have a significant effect on the steam consumption in the reboiler. This is not the case in our work and some other works reviewed here. They stated that 15 °C may be a reasonable Δ T m i n for a CO2 capture plant based on new technology. Their final proposition is that the ratio between the cost of energy consumption and capital cost is anticipated to increase; hence, a Δ T m i n of 10 °C or less is conceivably reasonable.
In a CCP project, Choi et al. [22] specified 11 °C for their lean/rich heat exchanger Δ T m i n and claimed that this is close to the cost optimum value. They also suggested that to reduce cost, the PHE should replace the STHX, and that it could probably result in a lower cost optimum Δ T m i n . The results from this study affirm the latter. Besides reduction in the capital cost, which is achieved by the PHE, the cost optimum Δ T m i n based on both CO2 capture cost and CO2 avoided cost is also reduced to between 4 and 7 °C, instead of the higher Δ T m i n obtained as cost optimum in the cases of the STHXs.
Li et al. [59] investigated an 85% CO2 capture from the exhaust gas from a 650 MW coal-fired power plant. They estimated an optimum CO2 avoided cost for a standard MEA capture process to be 5–7 °C. The exact type of heat exchanger was not mentioned. It is important to state the specific type of heat exchanger to ensure a proper and transparent comparison with other studies [3]. The benefit from reduction in energy consumption at the lower Δ T m i n was more significant compared to the increase in capital cost due to the high increase in the heat exchanger area. They concluded that due to the difficulty of manufacturing the heat exchanger to meet the requirement of such large area, the Δ T m i n range of 5–10 °C will achieve the optimum process in avoided cost. In this study, the optimum CO2 avoided costs estimated for the cement flue gas CO2 capture plant was within 4–7 °C for the PHE capture scenarios and 7–10 °C in the FTS-STHX capture scenarios.
For a 90% MEA-based standard CO2 capture process, Schach et al. [55] conducted a trade-off analysis based on an LMTD and on a standardise CO2 avoided cost. Their cost optimum was an LMTD of 7.5 °C. They proposed an advanced MEA-based CO2 capture configuration which include inter-cooling of the absorber, a conventional rich-split process and desorber inter-heating. For this process, they estimated an optimum LMTD of 8 °C. The type of heat exchanger was also not stated.
Karimi et al. [11] investigated seven different configurations for 90% CO2 capture from the flue gas of a 150 MW bituminous coal power plant. They were evaluated for a Δ T m i n of 5 °C and 10 °C using CO2 capture cost and CO2 avoided cost metrics. In all the configurations, a Δ T m i n of 10 °C achieved the lesser CO2 capture cost and CO2 avoided cost, except in the multi-pressure configuration where 5 °C achieved a marginal reduction of USD 0.01/tCO2 in CO2 avoided cost with a Δ T m i n of 5 °C.
Some other studies of an MEA-based post-combustion CO2 capture system can be found in [20,35,36,43,69]. These studies were all carried out using the U-tube and the fixed tube sheet shell and tube heat exchangers in an 85% MEA-based CO2 capture from the NGCC power plant exhaust gas. Kallevik [36] estimated the cost optimum for the UT-STHX to be 10–14 °C in a standard CO2 capture process. In a lean vapour compression CO2 capture process, Øi et al. [69] estimated the cost optimum to be 12 °C. Meanwhile, Aromada and Øi [43] estimated a Δ T m i n of 13 °C as the cost optimum in an LVC process. These studies made several simplification assumptions that excluded some important parameters, and the process scope did not include CO2 compression. In a study conducted for 5 °C, 10 °C, 15 °C and 20 °C where FTS-STHX was used as the lean/rich heat exchanger in CO2 capture from NGCC power plant flue gas, Aromada et al. [35] estimated the cost optimum Δ T m i n with different capital cost estimation methods to be 15 °C. Preliminary results of this work for different heat exchangers used as the lean/rich heat exchanger for CO2 capture from a cement plant flue gas without the compression section also estimated the cost optimum Δ T m i n for the UT-STHX, FTS-STHX and FH-STHX to be 15 °C [20]. The cost optimum Δ T m i n . if PHE is selected was evaluated to be 5 °C. The investigation was also carried out for for 5 °C, 10 °C, 15 °C and 20 °C only. Ali et al. [31] estimated 10 °C as a cost optimum using the UT-STHX as the lean/rich heat exchanger in a standard CO2 capture process from cement plant flue gas.
In the NGCC power plant CO2 capture process in this work, the optimum CO2 capture costs were achieved at a Δ T m i n of 12 °C in the cases of FTS-STHX and UT-STHX. For the FH-STHX and PHE, this was 14 °C and 6 °C, respectively. Meanwhile, 9 °C and 5 °C were the optimum CO2 capture costs for all the STHXs and the PHE, respectively, in the lean vapour compression process configuration.
In the cement plant capture system, FTS-STHX and UT-STHX cases achieved their capture cost optimum at a Δ T m i n of 13 °C and 10 °C in the standard and lean vapour compression processes, respectively. Meanwhile, this was 7 °C and 5 °C, respectively, in the PHE case.
In avoided cost estimates for the cement plant capture process, a Δ T m i n of 4 °C was estimated as cost optimum in both the standard and lean vapour compression capture processes. Meanwhile, the two STHX achieved their optimum CO2 avoided costs at 10 °C and 7 °C in the standard and lean vapour compression CO2 capture processes, respectively.
To select PHE instead of the STHXs will result in capital cost reduction, lower energy cost and higher emissions reduction, since a lower Δ T m i n results in lower steam consumption. It is therefore desirable to operate at a lower Δ T m i n . Larger capital costs at lower a Δ T m i n cancel out the OPEX advantage in the cases of the more expensive heat exchangers (STHXs). Higher-cost optimum Δ T m i n implies that the capital cost dominates the system, and a lower-cost optimum Δ T m i n indicates that energy cost dominates. While the results agree with some of the studies reviewed, to only consider energy reduction of a process only can cause a conclusion which would not evince the best possible solution to be made. Therefore, it is imperative to perform a trade-off analysis between energy cost and capital cost at different Δ T m i n for every innovative solvent-based capture system if the best possible CO2 capture process economically and in respect of emissions reduction is to be achieved.

3.14. Uncertainties

Since the Δ T m i n has significant impact on the size of the heat exchanger used as a lean/rich heat exchanger, more energy will be required for pumping both the lean and rich streams through the lean/rich heat exchanger as the Δ T m i n reduces. This was not accounted for in this study, and it may have some impact, but the effect may be negligible on the outcomes. The mass of CO2 emitted annually from the Norcem AS cement plant in Brevik is estimated to be about 800,000 tons/year. In this study, the emissions based on the data used for the simulations is of 708,142 tons/year.

4. Conclusions

This study was conducted to evaluate the performance of the plate heat exchanger in comparison with the conventional shell and tube types through a trade-off between energy cost and capital cost resulting from different minimum temperature approaches of the cross-heat exchanger in a solvent-based CO2 capture process. The following conclusions can be drawn:
  • To achieve the best possible CO2 capture process economically and in respect of emissions reduction, it is imperative to perform energy cost and capital cost trade-off analysis based on different Δ T m i n .
  • The CO2 capture cost optimum temperature approach for the standard process based on a natural gas power plant capture process was calculated to 12 °C for the STHXs and 6 °C for the PHE. For the cement-based process with higher CO2 inlet concentration, the CO2 capture cost optimum approach temperatures were slightly higher: 13 °C and 7 °C, respectively.
  • A lean vapour compression configuration was calculated to be more cost optimal. The optimum temperature was calculated to be slightly lower, 9 °C and 5 °C and 10 °C and 5 °C for the STHXs and PHE scenarios, respectively, compared to the standard process.
  • The plate heat exchanger outperformed the shell and tube heat exchanger types economically and in emissions reduction.
  • With the plate heat exchanger, the impact of the highly increased cost of heat exchanger, which makes a lower Δ T m i n . such as 5–7 °C not desirable due to the resulting higher CO2 capture cost or avoided cost, is minimised using the plate heat exchangers for the cross-heat exchanger, amine cooler and for the DCC circulation water cooler functions.
  • The optimum cost, i.e., CO2 capture cost or CO2 avoided cost, if the plate heat exchangers are used is achieved between 4 °C and 7 °C. This is where steam consumption and indirect CO2 emissions from an energy production process for the capture plant’s operation are relatively low.
  • The lean vapour compression CO2 capture configuration with the optimum PHE as the lean/rich heat exchanger and PHE as the lean amine cooler and the cooler for the DCC unit’s circulation water in the cement plant process achieved 16.4% cost reduction.
  • If the excess heat at the Brevik cement plant that can be utilised for steam supply for 50% CO2 capture is considered, the optimum PHE lean vapour compression process will achieve about 34% cost reduction relative to the ordinary standard case with FTS-STHX without steam supply from the available excess heat at the plant. This emphasises the impact of the uncommon excess heat at the Brevik cement plant.
  • In the standard capture process from a 400 MWe natural gas combined-cycle power plant exhaust gas, 7% more heat recovery can be achieved in the lean/rich heat exchanger if the Δ T m i n is 5 °C instead of 10 °C, while there would be 8% and 16% less heat recovery if it was 15 °C and 20 °C, respectively.
  • In the cement plant capture system, 10% extra recovery of heat would be realised if the Δ T m i n is 5 °C is used, or −9% and −20% if 15 °C and 20 °C, respectively, are used instead of the conventional 10 °C.
Therefore, this study recommends the use of plate heat exchangers for the cross-heat exchanger, lean amine cooler and DCC cooler functions in a post-combustion CO2 capture process.

Author Contributions

Conceptualisation, methodology, investigation, formal analysis, writing—original draft preparation, writing—review and editing, S.A.A.; methodology, supervision, writing—review and editing, N.H.E.; supervision, resources, writing—review and editing, L.E.Ø. All authors have read and agreed to the published version of the manuscript.

Funding

This research received no external funding.

Institutional Review Board Statement

Not applicable.

Informed Consent Statement

Not applicable.

Data Availability Statement

Not applicable.

Conflicts of Interest

The authors declare no conflict of interest.

Appendix A

Figure A1. Aspen HYSYS simulations process flow diagram of the NGCC power plant standard CO2 capture process.
Figure A1. Aspen HYSYS simulations process flow diagram of the NGCC power plant standard CO2 capture process.
Energies 15 00425 g0a1
Figure A2. Aspen HYSYS simulations process flow diagram of the NGCC power plant LVC CO2 capture process.
Figure A2. Aspen HYSYS simulations process flow diagram of the NGCC power plant LVC CO2 capture process.
Energies 15 00425 g0a2
Figure A3. Aspen HYSYS simulations process flow diagram of the cement plant standard CO2 capture process.
Figure A3. Aspen HYSYS simulations process flow diagram of the cement plant standard CO2 capture process.
Energies 15 00425 g0a3
Figure A4. Aspen HYSYS simulations process flow diagram of the cement plant LVC CO2 capture process.
Figure A4. Aspen HYSYS simulations process flow diagram of the cement plant LVC CO2 capture process.
Energies 15 00425 g0a4

References

  1. Jacobson, M.Z. Review of solutions to global warming, air pollution, and energy security. Energy Environ. Sci. 2009, 2, 148–173. [Google Scholar] [CrossRef]
  2. Kerr, R.A. Global warming is changing the world. Science 2007, 316, 188–190. [Google Scholar] [CrossRef] [Green Version]
  3. Aromada, S.A.; Eldrup, N.H.; Normann, F.; Øi, L.E. Techno-Economic Assessment of Different Heat Exchangers for CO2 Capture. Energies 2020, 13, 6315. [Google Scholar] [CrossRef]
  4. Alhajaj, A.; Mac, D.N.; Shah, N. A techno-economic analysis of post-combustion CO2 capture and compression applied to a combined cycle gas turbine: Part II. Identifying the cost-optimal control and design variables. Int. J. Greenh. Gas Control 2016, 52, 331–343. [Google Scholar] [CrossRef]
  5. Singh, J.; Dhar, D.W. Overview of carbon capture technology: Microalgal biorefinery concept and state-of-the-art. Front. Mar. Sci. 2019, 6, 29. [Google Scholar] [CrossRef] [Green Version]
  6. Lam, M.K.; Lee, K.T.; Mohamed, A.R. Mohamed, Current status and challenges on microalgae-based carbon capture. Int. J. Greenh. Gas Control 2012, 10, 456–469. [Google Scholar] [CrossRef]
  7. Hassanpouryouzband, A.; Joonaki, E.; Farahani, M.V.; Takeya, S.; Ruppel, C.; Yang, J.; English, N.J.; Schicks, J.M.; Edlmann, K.; Mehrabian, H.; et al. Gas hydrates in sustainable chemistry. Chem. Soc. Rev. 2020, 49, 5225–5309. [Google Scholar] [CrossRef]
  8. Kvamme, B.; Aromada, S.A.; Saeidi, N. Heterogeneous and homogeneous hydrate nucleation in CO2/water systems. J. Cryst. Growth 2019, 522, 160–174. [Google Scholar] [CrossRef]
  9. Aromada, S.A.; Kvamme, B.; Wei, N.; Saeidi, N. Enthalpies of hydrate formation and dissociation from residual thermodynamics. Energies 2019, 12, 4726. [Google Scholar] [CrossRef] [Green Version]
  10. Aromada, S.A.; Kvamme, B. Impacts of CO2 and H2 S on the risk of hydrate formation during pipeline transport of natural gas. Front. Chem. Sci. Eng. 2019, 13, 616–627. [Google Scholar] [CrossRef]
  11. Karimi, M.; Hillestad, M.; Svendsen, H.F. Capital costs and energy considerations of different alternative stripper configurations for post combustion CO2 capture. Chem. Eng. Res. Des. 2011, 89, 1229–1236. [Google Scholar] [CrossRef]
  12. Metz, B.; Davidson, O.; De Coninck, H.C.; Loos, M.; Meyer, L. IPCC Special Report on Carbon Dioxide Capture and Storage; Cambridge University Press: Cambridge, UK, 2005. [Google Scholar]
  13. Cousins, A.; Wardhaugh, L.; Feron, P. A survey of process flow sheet modifications for energy efficient CO2 capture from flue gases using chemical absorption. Int. J. Greenh. Gas Control. 2011, 5, 605–619. [Google Scholar] [CrossRef]
  14. Nwaoha, C.; Beaulieu, M.; Tontiwachwuthikul, P.; Gibson, M.D. Techno-economic analysis of CO2 capture from a 1.2 million MTPA cement plant using AMP-PZ-MEA blend. Int. J. Greenh. Gas Control 2018, 78, 400–412. [Google Scholar]
  15. Wu, X.; Yu, Y.; Qin, Z.; Zhang, Z. The advances of post-combustion CO2 capture with chemical solvents: Review and guidelines. Energy Procedia 2014, 63, 1339–1346. [Google Scholar] [CrossRef] [Green Version]
  16. Borhani, T.N.; Wang, M. Role of solvents in CO2 capture processes: The review of selection and design methods. Renew. Sustain. Energy Rev. 2019, 114, 109299. [Google Scholar] [CrossRef]
  17. Ali, H.; Eldrup, N.H.; Normann, F.; Andersson, V.; Skagestad, R.; Mathisen, A.; Øi, L.E. Cost estimation of heat recovery networks for utilization of industrial excess heat for carbon dioxide absorption. Int. J. Greenh. Gas Control 2018, 74, 219–228. [Google Scholar] [CrossRef]
  18. Viklund, S.B.; Karlsson, M. Industrial excess heat use: Systems analysis and CO2 emissions reduction. Appl. Energy 2015, 152, 189–197. [Google Scholar] [CrossRef] [Green Version]
  19. Lin, Y.-J.; Rochelle, G.T. Heat Transfer Enhancement and Optimization of Lean/Rich Solvent Cross Exchanger for Amine Scrubbing. Energy Procedia 2017, 114, 1890–1903. [Google Scholar] [CrossRef]
  20. Aromada, S.A.; Eldrup, N.H.; Normann, F.; Øi, L.E. Simulation and Cost Optimization of different Heat Exchangers for CO2 Capture. In Proceedings of the 61st International Conference of Scandinavian Simulation, Virtual Conference, Oulu, Finland, 22–24 September 2020. [Google Scholar]
  21. Aromada, S.A.; Eldrup, N.H.; Øi, L.E. Simulation-based Cost Optimization tool for CO2 Absorption processes: Iterative Detailed Factor (IDF) Scheme. In Proceedings of the 1st SIMS EUROSIM Conference 2021, Virtual Conference, Finland Linköping Electronic Conference Proceedings, Oulu, Finland, 21–23 September 2021. [Google Scholar]
  22. Choi, G.N.; Chu, R.; Degen, B.; Wen, H.; Richen, P.L.; Chinn, D. CO2 removal from power plant flue gas–cost efficient design and integration study. Carbon Dioxide Capture Storage Deep Geol. Form. 2005, 1, 99–116. [Google Scholar]
  23. Eimer, D. Gas Treating: Absorption Theory and Practice; John Wiley and Sons: Hoboken, NJ, USA, 2014. [Google Scholar]
  24. Øi, L.E. Removal of CO2 from Exhaust Gas. Ph.D. Thesis, Telemark University College, Porsgrunn, Norway, 2012. [Google Scholar]
  25. Tobiesen, F.A.; Svendsen, H.F.; Hoff, K.A. Desorber energy consumption amine based absorption plants. Int. J. Green Energy 2005, 2, 201–215. [Google Scholar] [CrossRef]
  26. Hopkinson, D.; Luebke, D.; Li, Z.; Chen, S. Solvent optimization of conventional absorption processes for CO2 capture from postcombustion flue gases. Ind. Eng. Chem. Res. 2014, 53, 7149–7156. [Google Scholar] [CrossRef]
  27. Choi, J.; Cho, H.; Yun, S.; Jang, M.-G.; Oh, S.-Y.; Binns, M.; Kim, J.-K. Process design and optimization of MEA-based CO2 capture processes for non-power industries. Energy 2019, 185, 971–980. [Google Scholar] [CrossRef]
  28. Amrollahi, Z.; Ystad, P.A.M.; Ertesvåg, I.S.; Bolland, O. Optimized process configurations of post-combustion CO2 capture for natural-gas-fired power plant–Power plant efficiency analysis. Int. J. Greenh. Gas Control 2012, 8, 1–11. [Google Scholar] [CrossRef]
  29. Li, K.; Yu, H.; Yan, S.; Feron, P.; Wardhaugh, L.; Tade, M. Technoeconomic assessment of an advanced aqueous ammonia-based postcombustion capture process integrated with a 650-MW coal-fired power station. Environ. Sci. Technol. 2016, 50, 10746–10755. [Google Scholar] [CrossRef]
  30. Sipöcz, N.; Tobiesen, A.; Assadi, M. Integrated modelling and simulation of a 400 MW NGCC power plant with CO2 capture. Energy Procedia 2011, 4, 1941–1948. [Google Scholar] [CrossRef] [Green Version]
  31. Ali, H.; Eldrup, N.H.; Normann, F.; Skagestad, R.; Øi, L.E. Cost Estimation of CO2 Absorption Plants for CO2 Mitigation–Method and Assumptions. Int. J. Greenh. Gas Control. 2019, 88, 10–23. [Google Scholar] [CrossRef]
  32. Peters, M.S.; Timmerhaus, K.D.; West, R.E. Plant Design and Economics for Chemical Engineers, 5th ed.; McGraw-Hill Companies, Inc.: Singapore, 2004. [Google Scholar]
  33. EIA, U.S. Frequently Asked Questions (FAQS): How Much Carbon Dioxide Is Produced When Different Fuels Are Burned? Available online: https://www.eia.gov/tools/faqs/faq.php?id=73&t=11 (accessed on 8 September 2021).
  34. Aromada, S.A.; Øi, L. Simulation of improved absorption configurations for CO2 capture. In Proceedings of the 56th Conference on Simulation and Modelling (SIMS 56), Linköping University, Linköping, Sweden, 7–9 October 2015; Linköping University Electronic Press: Linköping, Sweden, 2015. [Google Scholar]
  35. Aromada, S.A.; Eldrup, N.H.; Øi, L.E. Capital cost estimation of CO2 capture plant using Enhanced Detailed Factor (EDF) method: Installation factors and plant construction characteristic factors. Int. J. Greenh. Gas Control 2021, 110, 103394. [Google Scholar] [CrossRef]
  36. Kallevik, O.B. Cost Estimation of CO2 Removal in HYSYS. Master’s Thesis, Høgskolen i Telemark, Porsgrunn, Norway, 2010. [Google Scholar]
  37. Øi, L.E. Aspen HYSYS simulation of CO2 removal by amine absorption from a gas based power plant. In Proceedings of the 48th Scandinavian Conference on Simulation and Modeling (SIMS 2007), Göteborg (Särö), Sweden, 30–31 October 2007; Linköping University Electronic Press: Linköping, Sweden, 2007. Available online: https://ep.liu.se/en/conference-article.aspx?series=ecp&issue=27&Article_No=8 (accessed on 28 November 2021).
  38. Onarheim, K.; Garðarsdòttir, S.Ò.; Mathisen, A.; Nord, L.O.; Berstad, D. Industrial Implementation of Carbon Capture in Nordic Industry Sectors; Nordic CCS Competence Centre NORDICCS: 2015. Available online: https://www.sintef.no/globalassets/sintef-energi/nordiccs/d4.2.1501-d18-co2-capture-cases.pdf (accessed on 28 November 2021).
  39. Ahn, H.; Luberti, M.; Liu, Z.; Brandani, S. Process configuration studies of the amine capture process for coal-fired power plants. Int. J. Greenh. Gas Control 2013, 16, 29–40. [Google Scholar] [CrossRef] [Green Version]
  40. Andersson, V.; Franck, P.Ÿ.; Berntsson, T. Techno-economic analysis of excess heat driven post-combustion CCS at an oil refinery. Int. J. Greenh. Gas Control 2016, 45, 130–138. [Google Scholar] [CrossRef]
  41. Rubin, E.S.; Zhai, H. The cost of carbon capture and storage for natural gas combined cycle power plants. Environ. Sci. Technol. 2012, 46, 3076–3084. [Google Scholar] [CrossRef] [PubMed]
  42. Tel-Tek. Carbon Capture and Storage in the Skagerrak/Kattegat Region; In Chalmers University of Technology, University of Oslo, Gothenburg University, Tel-Tek: 2012. Available online: https://www.diva-portal.org/smash/get/diva2:487798/FULLTEXT01.pdf (accessed on 28 November 2021).
  43. Aromada, S.A.; Øi, L.E. Energy and economic analysis of improved absorption configurations for CO2 capture. Energy Procedia 2017, 114, 1342–1351. [Google Scholar] [CrossRef]
  44. Yu, F.C.-L. Process Design for Chemical Engineers Supplement; Amazon CreateSpace: Scotts Valley, CA, USA, 2014. [Google Scholar]
  45. CheGuide. Vapor Liquid Separator: A Guide for Chemical Engineers Working in Process Industry. 2017. Available online: https://cheguide.com/vapor_liquid_separator.html (accessed on 8 August 2021).
  46. van der Spek, M.; Roussanaly, S.; Rubin, E.S. Best practices and recent advances in CCS cost engineering and economic analysis. Int. J. Greenh. Gas Control 2019, 83, 91–104. [Google Scholar] [CrossRef]
  47. Kvamsdal, H.M.; Mejdell, T.; Steineke, F.; Weydahl, T.; Aspelund, A.; aHoff, K.A.; Skouras, S.; Barrio, M. Tjeldbergodden Power/Methanol-CO2 Reduction Efforts SP 2: CO2 Capture and Transport, TR A6062; SINTEF Energy Research: Trondheim, Norway, 2005. [Google Scholar]
  48. Mores, P.; Rodríguez, N.; Scenna, N.; Mussati, S. CO2 capture in power plants: Minimization of the investment and operating cost of the post-combustion process using MEA aqueous solution. Int. J. Greenh. Gas Control 2012, 10, 148–163. [Google Scholar] [CrossRef]
  49. Kaelin, J. Plate and Frame Heat Exchangers Explained: Thermaxx Jackets. 2015. Available online: https://www.thermaxxjackets.com/plate-and-frame-heat-exchangers-explained/ (accessed on 26 August 2020).
  50. Kesco, B.H. Heat Exchangers; Course Material for Queens University (CHEE 470-Fall 2008); Queen’s University: Kingston, ON, Canada, 2008. [Google Scholar]
  51. SSB. Industrial Cost Index. Norwegian Statistisk Sentralbyrå. Available online: https://www.ssb.no/en (accessed on 25 January 2021).
  52. Gardarsdottir, S.O.; De Lena, E.; Romano, M.; Roussanaly, S.; Voldsund, M.; Pérez-Calvo, J.-F.; Berstad, D.; Fu, C.; Anantharaman, R.; Sutter, D.; et al. Comparison of technologies for CO2 capture from cement production—Part 2: Cost analysis. Energies 2019, 12, 542. [Google Scholar] [CrossRef] [Green Version]
  53. Luo, M. Process Modelling, Simulation and Optimisation of Natural Gas Combined Cycle Power Plant Integrated with Carbon Capture, Compression and Transport. Ph.D. Thesis, University of Hull, Yorkshire, UK, 2016. [Google Scholar]
  54. Naims, H. Economics of carbon dioxide capture and utilization—A supply and demand perspective. Environ. Sci. Pollut. Res. 2016, 23, 22226–22241. [Google Scholar] [CrossRef] [PubMed] [Green Version]
  55. Schach, M.-O.; Schneider, R.; Schramm, H.; Repke, J.-U. Techno-economic analysis of postcombustion processes for the capture of carbon dioxide from power plant flue gas. Ind. Eng. Chem. Res. 2010, 49, 2363–2370. [Google Scholar] [CrossRef]
  56. Ali, U.; Font-Palma, C.; Akram, M.; Agbonghae, E.O.; Ingham, D.B.; Pourkashanian, M. Comparative potential of natural gas, coal and biomass fired power plant with post-combustion CO2 capture and compression. Int. J. Greenh. Gas Control 2017, 63, 184–193. [Google Scholar] [CrossRef]
  57. Voldsund, M.; Gardarsdottir, S.O.; De Lena, E.; Pérez-Calvo, J.-F.; Jamali, A.; Berstad, D.; Fu, C.; Romano, M.; Roussanaly, S.; Anantharaman, R.; et al. Comparison of technologies for CO2 capture from cement production—Part 1: Technical evaluation. Energies 2019, 12, 559. [Google Scholar] [CrossRef] [Green Version]
  58. Manzolini, G.; Fernandez, E.S.; Rezvani, S.; Macchi, E.; Goetheer, E.; Vlugt, T. Economic assessment of novel amine based CO2 capture technologies integrated in power plants based on European Benchmarking Task Force methodology. Appl. Energy 2015, 138, 546–558. [Google Scholar] [CrossRef]
  59. Li, K.; Leigh, W.; Feron, P.; Yu, H.; Tade, M. Systematic study of aqueous monoethanolamine (MEA)-based CO2 capture process: Techno-economic assessment of the MEA process and its improvements. Appl. Energy 2016, 165, 648–659. [Google Scholar] [CrossRef]
  60. Norcem Cement AS Brevik. Carbon Capture and Storage (CCS). Available online: https://www.norcem.no/en/CCS (accessed on 30 September 2021).
  61. Turton, R.; Bailie, R.C.; Whiting, W.B.; Shaeiwitz, J.A. Analysis, Synthesis and Design of Chemical Processes, 5th ed.; Prentice Hall: Boston, MA, USA, 2018. [Google Scholar]
  62. Sinnott, R.; Towler, G. Chemical Engineering Design; Butterworth-Heinemann: Oxford, UK, 2009; ISBN 978-0-7506–8551-1. [Google Scholar]
  63. Park, K. Optimization of Partial CO2 Capture. Master’s Thesis, University College of Southeast, Porsgrunn, Norway, 2016. [Google Scholar]
  64. Haslego, C.; Polley, G. Designing plate-and-frame heat exchangers. Chem. Eng. Prog. 2002, 98, 32–37. [Google Scholar]
  65. Carbon Capture and Storage Association. Affordability, CCS: Keeping the Lights on without Costing the Earth, 2011–2020. Available online: http://www.ccsassociation.org/whyccs/affordability/ (accessed on 5 July 2020).
  66. Roussanaly, S.; Fu, C.; Voldsund, M.; Anantharaman, R.; Spinelli, M.; Romano, M. Techno-economic analysis of MEA CO2 capture from a cement kiln–impact of steam supply scenario. Energy Procedia 2017, 114, 6229–6239. [Google Scholar] [CrossRef] [Green Version]
  67. Ramezan, M.; Skone, T.J.; Nsakala, N.Y.; Liljedahl, G.N.; Gearhart, L.E.; Hestermann, R.; Rederstorff, B.; DOE/NETL. Carbon Dioxide Capture from Existing Coal-Fired Power Station; Department of Energy, National Energy Technology Laboratory: Albany, OR, USA, 2007.
  68. Singh, D.; Croiset, E.; Douglas, P.; Douglas, M. Techno-economic study of CO2 capture from an existing coal-fired power plant: MEA scrubbing vs. O2/CO2 recycle combustion. Energy Convers. Manag. 2003, 44, 3073–3091. [Google Scholar] [CrossRef]
  69. Øi, L.E.; Bråthen, T.; Berg, C.; Brekne, S.K.; Flatin, M.; Johnsen, R.; Moen, I.G.; Thomassen, E. Optimization of configurations for amine based CO2 absorption using Aspen HYSYS. Energy Procedia 2014, 51, 224–233. [Google Scholar] [CrossRef] [Green Version]
Figure 1. Standard CO2 capture process [3].
Figure 1. Standard CO2 capture process [3].
Energies 15 00425 g001
Figure 2. Lean vapour compression (LVC) configuration CO2 capture process (modified from [3]). (the red line is to highlight the additional equipment).
Figure 2. Lean vapour compression (LVC) configuration CO2 capture process (modified from [3]). (the red line is to highlight the additional equipment).
Energies 15 00425 g002
Figure 3. Capital cost distribution of 90% CO2 standard capture plant and lean vapour compression plant for the 400 MW NGCC power plant’s exhaust gas.
Figure 3. Capital cost distribution of 90% CO2 standard capture plant and lean vapour compression plant for the 400 MW NGCC power plant’s exhaust gas.
Energies 15 00425 g003
Figure 4. Capital cost distribution of 90% CO2 standard capture plant and lean vapour compression plant for cement plant’s flue gas.
Figure 4. Capital cost distribution of 90% CO2 standard capture plant and lean vapour compression plant for cement plant’s flue gas.
Energies 15 00425 g004
Figure 5. Energy consumption cost as a function of Δ T m i n of the lean/rich heat exchanger.
Figure 5. Energy consumption cost as a function of Δ T m i n of the lean/rich heat exchanger.
Energies 15 00425 g005
Figure 6. Annual CO2 emissions reduction analysis.
Figure 6. Annual CO2 emissions reduction analysis.
Energies 15 00425 g006
Figure 7. Energy and heat exchanger costs trade-off analysis at different Δ T m i n for different heat exchanger types in a standard CO2 capture from NGCC power plant exhaust gas.
Figure 7. Energy and heat exchanger costs trade-off analysis at different Δ T m i n for different heat exchanger types in a standard CO2 capture from NGCC power plant exhaust gas.
Energies 15 00425 g007
Figure 8. Energy and heat exchanger costs trade-off analysis at different Δ T m i n for different heat exchanger types in an LVC CO2 capture from NGCC power plant exhaust gas.
Figure 8. Energy and heat exchanger costs trade-off analysis at different Δ T m i n for different heat exchanger types in an LVC CO2 capture from NGCC power plant exhaust gas.
Energies 15 00425 g008
Figure 9. Energy and heat exchanger costs trade-off analysis at different Δ T m i n for different heat exchanger types in a standard CO2 capture from cement flue gas.
Figure 9. Energy and heat exchanger costs trade-off analysis at different Δ T m i n for different heat exchanger types in a standard CO2 capture from cement flue gas.
Energies 15 00425 g009
Figure 10. Energy and heat exchanger costs trade-off analysis at different Δ T m i n for different heat exchanger types in an LVC CO2 capture from cement flue gas.
Figure 10. Energy and heat exchanger costs trade-off analysis at different Δ T m i n for different heat exchanger types in an LVC CO2 capture from cement flue gas.
Energies 15 00425 g010
Figure 11. Cost reduction analysis at different Δ T m i n for different heat exchanger types compared with FTS–STHX of Δ T m i n = 10 °C in the NGCC power plant capture process.
Figure 11. Cost reduction analysis at different Δ T m i n for different heat exchanger types compared with FTS–STHX of Δ T m i n = 10 °C in the NGCC power plant capture process.
Energies 15 00425 g011
Figure 12. Cost reduction analysis at different Δ T m i n for different heat exchanger types compared with FTS–STHX of Δ T m i n = 10 °C in the cement plant capture process..
Figure 12. Cost reduction analysis at different Δ T m i n for different heat exchanger types compared with FTS–STHX of Δ T m i n = 10 °C in the cement plant capture process..
Energies 15 00425 g012
Figure 13. Energy and heat exchanger costs trade-off analysis at different Δ T m i n for different heat exchanger types in a standard CO2 capture from cement flue gas with consideration of actual CO2 emissions reduction (red dot is the Δ T m i n where optimum CO2 capture cost is achieved, which can be different from the CO2 avoided cost optimum the Δ T m i n ).
Figure 13. Energy and heat exchanger costs trade-off analysis at different Δ T m i n for different heat exchanger types in a standard CO2 capture from cement flue gas with consideration of actual CO2 emissions reduction (red dot is the Δ T m i n where optimum CO2 capture cost is achieved, which can be different from the CO2 avoided cost optimum the Δ T m i n ).
Energies 15 00425 g013
Figure 14. Energy and heat exchanger costs trade-off analysis at different Δ T m i n for different heat exchanger types in an LVC CO2 capture from cement flue gas with consideration of actual CO2 emissions reduction (red dot is the Δ T m i n where optimum CO2 capture cost is achieved, which can be different from the CO2 avoided cost optimum the Δ T m i n ).
Figure 14. Energy and heat exchanger costs trade-off analysis at different Δ T m i n for different heat exchanger types in an LVC CO2 capture from cement flue gas with consideration of actual CO2 emissions reduction (red dot is the Δ T m i n where optimum CO2 capture cost is achieved, which can be different from the CO2 avoided cost optimum the Δ T m i n ).
Energies 15 00425 g014
Figure 15. Cost reduction analysis at different Δ T m i n for different heat exchanger types compared with FTS–STHX of Δ T m i n = 10 °C.
Figure 15. Cost reduction analysis at different Δ T m i n for different heat exchanger types compared with FTS–STHX of Δ T m i n = 10 °C.
Energies 15 00425 g015
Figure 16. Energy and heat exchanger costs trade-off analysis at different Δ T m i n for different heat exchanger types in a standard CO2 capture from cement flue gas (red dot is the Δ T m i n where optimum CO2 capture cost is achieved, which can be different from the CO2 avoided cost optimum the Δ T m i n ).
Figure 16. Energy and heat exchanger costs trade-off analysis at different Δ T m i n for different heat exchanger types in a standard CO2 capture from cement flue gas (red dot is the Δ T m i n where optimum CO2 capture cost is achieved, which can be different from the CO2 avoided cost optimum the Δ T m i n ).
Energies 15 00425 g016
Figure 17. Energy and heat exchanger costs trade-off analyses at different Δ T m i n for different heat exchanger types in a standard CO2 capture from cement flue gas (red dot is the Δ T m i n where optimum CO2 capture cost is achieved which can be different from the CO2 avoided cost optimum the Δ T m i n ).
Figure 17. Energy and heat exchanger costs trade-off analyses at different Δ T m i n for different heat exchanger types in a standard CO2 capture from cement flue gas (red dot is the Δ T m i n where optimum CO2 capture cost is achieved which can be different from the CO2 avoided cost optimum the Δ T m i n ).
Energies 15 00425 g017
Figure 18. Cost reduction analysis at different Δ T m i n for different heat exchanger types compared with FTS–STHX of Δ T m i n = 10 °C, in waste heat utilisation scenario.
Figure 18. Cost reduction analysis at different Δ T m i n for different heat exchanger types compared with FTS–STHX of Δ T m i n = 10 °C, in waste heat utilisation scenario.
Energies 15 00425 g018
Figure 19. Sensitivity analysis of steam cost on the energy and heat exchanger costs trade–off analyses at different Δ T m i n for different heat exchanger types in a standard CO2 capture from cement flue gas.
Figure 19. Sensitivity analysis of steam cost on the energy and heat exchanger costs trade–off analyses at different Δ T m i n for different heat exchanger types in a standard CO2 capture from cement flue gas.
Energies 15 00425 g019
Figure 20. Sensitivity analysis of steam cost on the energy and heat exchanger costs trade–off analyses at different Δ T m i n for different heat exchanger types in a standard CO2 capture from cement flue gas.
Figure 20. Sensitivity analysis of steam cost on the energy and heat exchanger costs trade–off analyses at different Δ T m i n for different heat exchanger types in a standard CO2 capture from cement flue gas.
Energies 15 00425 g020
Figure 21. Sensitivity analysis of TPC on the energy and heat exchanger costs trade–off analyses at different Δ T m i n for different heat exchanger types in a standard CO2 capture from cement flue gas.
Figure 21. Sensitivity analysis of TPC on the energy and heat exchanger costs trade–off analyses at different Δ T m i n for different heat exchanger types in a standard CO2 capture from cement flue gas.
Energies 15 00425 g021
Figure 22. Sensitivity analysis of TPC on the energy and heat exchanger costs trade–off analyses at different Δ T m i n for different heat exchanger types in a standard CO2 capture from cement flue gas.
Figure 22. Sensitivity analysis of TPC on the energy and heat exchanger costs trade–off analyses at different Δ T m i n for different heat exchanger types in a standard CO2 capture from cement flue gas.
Energies 15 00425 g022
Table 1. NGCC power plant exhaust gas specification.
Table 1. NGCC power plant exhaust gas specification.
ParameterValueReference
CO2 mole%3.75[37]
H2O mole%6.71[37]
N2 mole%89.54Calculated
Molar flow rate, kmol/h85,000[37]
Flue gas temperature, °C80[35]
Flue gas pressure, kPa110[35]
Temperature of flue gas into absorber, °C40[34]
Pressure of flue gas into absorber, kPa121[31]
Table 2. The cement plant flue gas specification.
Table 2. The cement plant flue gas specification.
ParameterValueReference
String 1
CO2 mole%22[38]
O27[38]
H2O mole%9[38]
N2 mole%62[38]
Molar flow rate, kmol/h5785[38]
Flue gas temperature, °C80[3]
Flue gas pressure, kPa101.3[3]
Temperature of flue gas into absorber, °C40[31]
Pressure of flue gas into absorber, kPa121[31]
String 2
CO2 mole%13[38]
O27[38]
H2O mole%10[38]
N2 mole%70[38]
Molar flow rate, kmol/h5682[38]
Flue gas temperature, °C80[3]
Flue gas pressure, kPa101.3[3]
Temperature of flue gas into absorber, °C40[31]
Pressure of flue gas into absorber, kPa121[31]
Table 3. Capital cost assumptions.
Table 3. Capital cost assumptions.
DescriptionValueReference
Capital cost methodEDF method[35]
CAPEXTotal plant cost (TPC)[35]
Capital cost year2020, 1st quarterAssumed
Equipment Cost data year2019, 1st quarter(AspenTech-A.I.C.E)
Cost currencyEuro (EUR)Assumed
Plant locationRotterdamDefault
Project life25 years[3]
Plant construction period3 years[52]
Discount rate7.50%[3]
Annual maintenance4% of TPC[3]
FOAK or NOAKNOAK[35]
Material conversion factor (SS to CS)1.75 welded; 1.30 machined[35]
Table 4. Economic assumptions for estimating the operating costs.
Table 4. Economic assumptions for estimating the operating costs.
DescriptionUnitValue/UnitReference
Annual operation Hours8000[43]
Steam (natural gas)EUR/ton 15.51 *[52]
Steam (excess/waste heat)EUR/ton 5.21 *[52]
ElectricityEUR/kWh0.058[52]
Process WaterEUR/m36.65[52]
Cooling WaterEUR/m30.022Assumed
Solvent (MEA)EUR/ton 1450[53]
MaintenanceEUR 4% of TPC[43]
EngineerEUR 150,000 (1 engineer)[31]
OperatorsEUR 77,000 (× 20 operators) **[52]
* Converted to EUR/ton from [52], ** Number of staff [52].
Table 5. Comparison of NGCC power plant’s exhaust gas process simulation results with literature.
Table 5. Comparison of NGCC power plant’s exhaust gas process simulation results with literature.
CO2 Capture RateCO2 ConcentrationΔTminLean LoadingRich LoadingAbsorber Packing HeightReboiler Specific Heat
Unit%mol%°C mGJ/tCO2
This work (NGCC)903.75100.260.50173.73
Amrollahi et al. [28]903.808.5n.a.0.47133.74
Ali et al. [56]904.16n.a.n.a.0.48n.a.3.93
Sipöcz et al. [30]904.2010n.a.0.4726.9 *3.93
* Not defined if it is packing height or shell tangent-tangent height. n.a. = not available.
Table 6. Comparison of the cement plant’s flue gas process simulation results with literature.
Table 6. Comparison of the cement plant’s flue gas process simulation results with literature.
CO2 Capture RateCO2 ConcentrationΔTminLean LoadingRich LoadingAbsorber Packing HeightReboiler Specific Heat
Unit%mol%°C mGJ/tCO2
This work (cement)9018n.a.0.260.4817.4 (29 stages)3.89
Voldsund et al. [57]9022n.a.0.220.50n.a.3.76
Voldsund et al. [57] 9018n.a.0.220.50n.a.3.80
Nwaoha et al. [14]9011.5 vol%100.320.5022 (36 stages)3.86
n.a.= not available.
Table 7. Comparison of the base cases’ total plant costs (TPCs) of the different plant scenarios (reference: FTS-STHX).
Table 7. Comparison of the base cases’ total plant costs (TPCs) of the different plant scenarios (reference: FTS-STHX).
NGCC Power Plant CO2 Capture ProcessesCement Plant CO2 Capture Processes
StandardLVCStandardLVC
EUR (Millions)%EUR (Millions)%EUR (Millions)%EUR (Millions)%
FTS-STHX172.40177.9078.8085.10
FH-STHX174.51178.9179.3185.71
UT-STHX167.8−3174.0−2 ---
PHE147.5−14160.7−1065.2−1776.8−10
Negative percentage indicates cost reduction and positive percentage implies increase in TPC. Comparisons were made with the FTS-STHX in both the NGCC power plant and cement plant processes.
Table 8. Absorber dimensioning data.
Table 8. Absorber dimensioning data.
Absorber
UnitNGCC ProcessCement Plant Process
Number of units-31
Shell tangent-to-tangent heightm4040
Diameter (overall)m16.326.50
Diameter per unitm9.436.50
Stages-2917
Packing heightm17.417
Packing type-Structured packing (MellaPak 250Y)Structured packing (MellaPak 250Y)
Table 9. Comparison of heat recovery in the lean/rich heat exchanger of the standard CO2 capture processes.
Table 9. Comparison of heat recovery in the lean/rich heat exchanger of the standard CO2 capture processes.
ΔTminThis Work (NGCC)This Work (Cement)Eimer [23]-NGCC
°C%%%
57107
10Reference (Base case)
15−8−9−7
20−16−20-
Table 10. The influence of the lean/rich heat exchanger ΔTmin on the thermal load and area of the required heat exchangers (400 MW NGCC power plant standard CO2 capture process).
Table 10. The influence of the lean/rich heat exchanger ΔTmin on the thermal load and area of the required heat exchangers (400 MW NGCC power plant standard CO2 capture process).
ΔTminSpecific Reboiler HeatHX Thermal LoadReboiler Duty Lean MEA CoolerSTHXPHE
Total HX AreaΔHX AreaNo. of UnitsTotal HX AreaΔHX AreaNo. of Units
°CGJ/tCO2MWMWMWm2% m2%
33.5217312321---29,296 18118
43.5417112423---24,107 13115
53.571681252537,543 763820,101 9313
63.601661262732,721 533317,149 6511
73.631641283028,794 352914,886 439
83.661621293226,156 232712,953 248
93.701601303423,485 102411,598 117
103.731571313621,331 02210,421 07
113.761551333919,170 −10209361−106
123.801521344217,273 −19188365−206
133.841501354415,539 −27167536−285
143.891471374714,090 −34156863−345
153.931451385012,856 −40136253−404
163.981421405311,771 −45125699−454
174.021391415610,879 −49115261−504
184.061371435810,033 −53114873−533
194.11134145619326 −56104537−563
204.15132146648681 −5994221−593
Average HX area of STHX per unit, m2 973
Average HX area of PHE per unit, m2 1553
Overall heat transfer coefficient (U) of STHX per unit, kW/m2·K0.73[14]
Overall heat transfer coefficient (U) of PHE per unit, kW/m2·K1.50Based on [50]
Table 11. The influence of the lean/rich heat exchanger ΔTmin on the thermal load and area of the required heat exchangers (cement plant standard CO2 capture process).
Table 11. The influence of the lean/rich heat exchanger ΔTmin on the thermal load and area of the required heat exchangers (cement plant standard CO2 capture process).
ΔTmin Specific Reboiler HeatHX Thermal LoadReboiler Duty Lean MEA Cooler DutySTHXPHE
Total HX AreaΔHX AreaNo. of UnitsTotal HX AreaΔHX AreaNo. of Units
°CGJ/tCO2MWMWMWm2% m2%
33.6594.480.935.8--- 17,13021011
43.6893.081.637.3---13,5661469
53.7191.682.338.722,178972311,0651007
63.7590.183.140.419,11770209342696
73.7888.583.942.016,55847178028455
83.8286.984.743.814,32527156935265
93.8585.485.645.312,76013136193124
103.8983.186.247.711,266012551904
113.9282.387.348.610,187−10114924−113
123.9780.788.150.39181−19104439−203
134.0178.989.052.28257−2794007−273
144.0577.190.154.17457−3483606−353
154.1075.391.156.06772−4073278−412
164.1573.692.157.86185−4572996−462
174.1971.893.359.75658−5062754−502
184.2470.094.361.55210−5462532−542
194.2868.295.463.44803−5752332−582
204.3366.596.565.24442−6152158−612
Average HX area of STHX per unit, m2 945
Average HX area of PHE per unit, m2 1477
Overall heat transfer coefficient (U) of STHX per unit, kW/m2·K0.73[14]
Overall heat transfer coefficient (U) of PHE per unit, kW/m2·K1.50Based on [50]
Table 12. The influence of the lean/rich heat exchanger ΔTmin on the thermal load and area of the required heat exchangers (400 MW NGCC power plant lean vapour compression CO2 capture process).
Table 12. The influence of the lean/rich heat exchanger ΔTmin on the thermal load and area of the required heat exchangers (400 MW NGCC power plant lean vapour compression CO2 capture process).
ΔTminSpecific Reboiler HeatEquivalent Heat HX Thermal LoadReboiler Duty Lean MEA Cooler DutySTHXPHE
Total HX AreaΔHX AreaNo. of UnitsTotal HX AreaΔHX AreaNo. of Units
°CGJ/tCO2GJ/tCO2MWMWMWm2% m2%
32.763.11115.997.018.3-- -24,69728215
42.793.14114.398.119.9---19,05919512
52.833.18112.099.622.330,4431283114,7711289
62.873.23109.6100.924.724,575842511,926848
72.923.27107.2102.327.120,47853219935546
82.963.32104.9103.829.417,46131188472316
93.003.36102.9105.531.515,06513167345145
103.053.40100.7106.833.613,342014646604
113.093.4598.2108.436.411,796−12125744−114
123.143.4995.8110.138.810,539−21115123−214
133.183.5493.6111.841.19497−29104613−293
143.223.5791.3113.543.48601−3694179−353
153.273.6389.0115.145.77828−4183769−423
163.323.6886.7116.548.27148−4683472−463
173.383.7384.5118.550.76549−5173182−512
183.423.7782.1119.952.86025−5572929−552
193.473.8279.9121.655.15557−5862705−582
203.523.8777.8123.457.45139−6162497−612
Average HX area of STHX per unit, m2 957
Average HX area of PHE per unit, m2 1515
Overall heat transfer coefficient (U) of STHX per unit, kW/m2·K0.73[14]
Overall heat transfer coefficient (U) of PHE per unit, kW/m2·K1.50Based on [50]
Average compressor (specific) duty, MW (GJ/tCO2)3.10 (0.09)
Table 13. The influence of the lean/rich heat exchanger ΔTmin on the thermal load and area of the required heat exchangers (cement plant lean vapour recompression CO2 capture process).
Table 13. The influence of the lean/rich heat exchanger ΔTmin on the thermal load and area of the required heat exchangers (cement plant lean vapour recompression CO2 capture process).
ΔTminSpecific Reboiler HeatEquivalent Heat HX Thermal LoadReboiler Duty Lean MEA Cooler DutySTHXPHE
Total HX AreaΔHX AreaNo. of UnitsTotal HX AreaΔHX AreaNo. of Units
°CGJ/tCO2GJ/tCO2MWMWMWm2% m2%
32.673.0057.059.221.6---12,1763018
42.713.0455.759.922.9---91212006
52.743.0654.460.724.114,9061381572671395
62.783.1153.161.625.611,95891125842924
72.823.1551.762.527.0993759104841593
82.863.1850.363.528.484153494096353
92.903.2349.064.329.872341683492152
102.953.2847.265.331.7625907303802
112.983.3146.466.132.65608−1062730−102
123.033.3645.367.033.45024−2062430−202
133.073.4043.267.935.64431−2952176−282
143.123.4542.068.937.13991−3641942−362
153.163.4940.669.938.53606−4241755−422
163.203.5339.370.939.83272−4841592−481
173.253.5838.071.941.22976−5231448−521
183.293.6236.772.942.52715−5731321−571
193.343.6735.474.043.92480−6031219−601
Average HX area of STHX per unit, m2 938
Average HX area of PHE per unit, m2 1393
Overall heat transfer coefficient (U) of STHX per unit, kW/m2·K0.73[14]
Overall heat transfer coefficient (U) of PHE per unit, kW/m2·K1.50Based on [50]
Average compressor (specific) duty, MW (GJ/tCO2)1.81 (0.08)
Table 14. Summary of energy performances of the standard and the LVC capture processes.
Table 14. Summary of energy performances of the standard and the LVC capture processes.
Specific Reboiler DutyEquivalent Heat
ConfigurationEnergy SavingConfigurationEnergy Saving
Standard LVCStandard LVC
°CGJ/tCO2GJ/tCO2%GJ/tCO2GJ/tCO2%
NGCC power plant53.892.95323.893.2819
NGCC power plant103.733.05223.733.4010
Cement plant53.712.74353.713.0621
Cement plant103.572.83263.573.1812
Table 15. Comparison of the base cases’ CO2 capture cost of the different plant scenarios (reference: FTS-STHX).
Table 15. Comparison of the base cases’ CO2 capture cost of the different plant scenarios (reference: FTS-STHX).
NGCC Power Plant CO2 Capture ProcessesCement Plant CO2 Capture Processes
StandardLVCStandardLVC
EUR/tCO2%EUR/tCO2%EUR/tCO2%EUR/tCO2%
FTS-STHX73.40.069.40.062.10.057.30.0
FH-STHX73.60.269.60.262.20.257.40.2
UT-STHX72.8−0.868.9−0.7
PHE70.2−4.467.2−3.259.4−4.455.6−3.0
Negative percentage indicates cost reduction and positive percentage implies increase in CO2 capture cost.
Table 16. CO2 avoided cost and emissions reduction performances of FTS-STHX and PHE with and without available waste heat for 50% CO2 capture from Brevik cement plant’s flue gas.
Table 16. CO2 avoided cost and emissions reduction performances of FTS-STHX and PHE with and without available waste heat for 50% CO2 capture from Brevik cement plant’s flue gas.
Δ T m i n Reboiler HeatEquivalent HeatCapital Cost (TPC)CO2 Avoided CostCost Reduction CO2 Emissions Reduction
°CGJ/tCO2GJ/tCO2MEUR EUR /tCO2%%
Standard process
Reference/optimum FTS-STHX103.893.8978.887.5064.1
PHE103.893.8965.284.53.463.7
Optimum PHE 43.683.6870.682.45.864.9
FTS-STHX (+Excess heat)103.893.8978.863.827.173.9
Optimum FTS-STHX (+Excess heat)134.014.0175.063.527.573.6
Optimum PHE (+Excess heat)73.783.7867.060.231.273.9
Lean vapour compression (LVC)
FTS-STHX102.953.2885.177.411.566.7
PHE102.953.2876.875.214.166.6
Optimum FTS-STHX 72.823.1589.377.012.067.3
Optimum PHE 42.713.0480.873.116.467.7
FTS-STHX (+Excess heat)/optimum102.953.2885.160.530.874.1
Optimum PHE (+Excess heat)52.743.0679.657.933.874.5
Compressor work for the LVC is 0.082 GJ/tCO2
Capital cost of steam production from excess heat is not included in the main capture plant TPC, but it is rather included in the steam cost.
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Share and Cite

MDPI and ACS Style

Aromada, S.A.; Eldrup, N.H.; Øi, L.E. Cost and Emissions Reduction in CO2 Capture Plant Dependent on Heat Exchanger Type and Different Process Configurations: Optimum Temperature Approach Analysis. Energies 2022, 15, 425. https://doi.org/10.3390/en15020425

AMA Style

Aromada SA, Eldrup NH, Øi LE. Cost and Emissions Reduction in CO2 Capture Plant Dependent on Heat Exchanger Type and Different Process Configurations: Optimum Temperature Approach Analysis. Energies. 2022; 15(2):425. https://doi.org/10.3390/en15020425

Chicago/Turabian Style

Aromada, Solomon Aforkoghene, Nils Henrik Eldrup, and Lars Erik Øi. 2022. "Cost and Emissions Reduction in CO2 Capture Plant Dependent on Heat Exchanger Type and Different Process Configurations: Optimum Temperature Approach Analysis" Energies 15, no. 2: 425. https://doi.org/10.3390/en15020425

APA Style

Aromada, S. A., Eldrup, N. H., & Øi, L. E. (2022). Cost and Emissions Reduction in CO2 Capture Plant Dependent on Heat Exchanger Type and Different Process Configurations: Optimum Temperature Approach Analysis. Energies, 15(2), 425. https://doi.org/10.3390/en15020425

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop