A base case (BC) and five different scenarios changing the presence of DG and EVs were considered (see
Table 3). In this case, the BC scenario does not take into account DG and represents a traditional radial distribution network. In the BC scenario, the load is fed through the main grid. In scenario EV1, the DG units are still disconnected; nonetheless, there are 6 EVs connected to the grid. In scenario EV2, the DG units remain disconnected, but there are 18 EVs in the network. The second base case scenario is denoted as BC DG. In this case, the DG units are connected to the grid; therefore, the load is fed by the DG units and the main grid. In scenario EV1 DG, the DG units are connected to the grid, and there are also 6 EVs. Finally, in scenario EV2 DG, the DG units are connected to the grid, and there are 18 EVs. In the tests carried out, 6 electric vehicle charging stations (EVCS) were incorporated and distributed as illustrated in
Figure 5. In all cases, 100 kW level 3 battery chargers were considered.
Regarding the protection coordination scheme, the network is protected with 15 DOCRs, which are labeled with numbers ranging from 1 to 15 preceded by the letter R as indicated in
Figure 5. The settings and characteristics of the DOCRs used in this study are presented in
Table 4 and were taken from [
44].
Table 4 indicates the transformation ratio of the current transformers
, as well as the pickup current
and dial
of each relay. Regarding the dial, one setting is considered for the scenarios without DG and another one for the scenarios with DG. The test system was implemented and simulated in DigSILENT PowerFactory. To evaluate the protection scheme, five three-phase faults at lines DL-1, DL-2, DL-3, DL-4, and DL-5 were considered. Calculations and tests were performed according to the recommendations of the IEEE Standard 242, which is widely used for overcurrent protection coordination. This paper considers a CTI of 0.3 s for comparative purposes. For the operation time of the DOCRs, the IEC normal inverse curve with constants A and B of 0.14 and 0.02, respectively, was considered.
The results section is divided in two subsections. Initially, short-circuit levels are evaluated at each bus of the test system and their variations are compared considering the scenarios described in
Table 3. Then, the coordination of the protection scheme is evaluated using the settings and characteristics proposed in [
44] by means of the constraints and indexes indicated in
Section 5. To this end, a fault in the protected element is performed to compare the operating times of the main relays with the backup relays.
6.1. Modifications in Short-Circuit Currents
To evaluate the impact of the incorporation of EVs in the proposed network, an analysis of the short-circuit levels considering the main buses of the network was carried out. Faults in all buses were performed for each of the scenarios presented in
Table 3. The results are presented in
Figure 6. It can be seen that the incorporation of EVs increases the short-circuit levels. In scenarios EV1 and EV2, where DG is disconnected, there is an increase in short-circuit levels at all buses compared to the base case (BC). Note that of this group of scenarios, EV2 presents the highest short-circuit levels. When considering DG connected to the grid (scenarios EV1 DG and EV2 DG), there is also an increase in short-circuit levels at all buses compared to the corresponding base case with DG (scenario BC DG). Note that scenario EV2 DG presents the highest short-circuit levels. Note that the highest increments in short-circuit levels take place when DG is connected to the network. Finally, it was observed that Bus 1 PCC features the highest magnitudes of short-circuit, which is due to its proximity to the main grid.
The percentage change in short-circuit levels was measured in order to have a numerical reference of the modifications. For this purpose, the short-circuit levels of BC and BC DG scenarios were defined as the base data. The percentages presented in
Figure 7 and
Figure 8 indicate the increment in short-circuit levels of the scenarios that consider the incorporation of EVs with respect to the base case.
Figure 7 shows the results of the scenarios without DG, while
Figure 7 presents the results of the scenarios that consider DG in the network. Note that in none of the analyzed scenarios, the short-circuit levels are reduced; in all cases, they increase with respect to the base case.
From
Figure 7, it can be seen that EVs impose a considerable increase in short-circuit levels when there is no DG connected to the network. Scenario EV1, which considers 5 EVs, presents a smaller increase in short-circuit levels compared to scenario EV2, which considers 15 EVs. Note that Bus 1 PCC presents the lowest short-circuit percentage increase in both scenarios: 19% in EV1 and 40 % in EV2. This is due to the high short-circuit level of the bus, which is related to its proximity to the main grid. Buses 3 and 5 present the highest short-circuit percentage increase: 71% for scenario EV1 and 193 % scenario EV2. According to these results, it can be inferred that the most affected protections are those at Buses 3 and 5, due to their large short-circuit level variations.
From
Figure 8, it can be seen that there is also an increment in the short-circuit levels when DG is connected to the network; nonetheless, such an increment is lower than that of the previous case illustrated in
Figure 7. In scenario EV1 DG, which considers 5 EVs, there is a smaller increase compared to scenario EV2 DG that considers 15 EVs. As in the previous case (without DG), Bus 1 PCC has the lowest percentage increase in short-circuit levels: 11% in scenario EV1 GD and 26% in scenario EV2 DG. Furthermore, Buses 3 and 5 present the highest increment in short-circuit levels: 40% and 110% in scenarios EV1 DG and EV2 DG, respectively. According to these results, it can be seen that the protections that may have the greatest impact are those at Buses 3 and 5 due to their large short-circuit level variations.
Comparing the results of the scenarios with and without GD, it can be concluded that the latter presents the greatest variations in short-circuit levels when incorporating EVs. This suggests that there will be a greater impact on the protection schemes in those systems that have their DG units disconnected from the main grid.
6.2. Effects on the Protection Coordination Scheme
After the assessment of the short-circuit levels developed in the previous section, the evaluation of the protection coordination scheme is carried out. In order to evaluate the existing DOCR scheme in the network, and for comparative purposes, five three-phase faults are considered in lines DL-1, DL-2, DL-3, DL-4 and DL-5. Once the faults are executed, the performance of the existing scheme is evaluated using the equations, constraints and indexes presented in
Section 4. Initially, the performance of the scheme is globally evaluated, using Equations (
1), (
2), (
8) and (
10); subsequently, the performance of the scheme is particularly evaluated, measuring the performance of each protection, using Equations (
2) and (
9). Finally, the results obtained from the evaluations performed with the equations, constraints and indexes presented in
Section 4 are contrasted against the analysis of the traditional coordination curves.
The results to generally evaluate the DOCR protection scheme of the network are presented in
Table 5,
Table 6 and
Table 7.
Table 5 and
Table 6 present the operation time
T, given by Equation (
1), and the number of violations
V of Equation (
2) for scenarios considering the DG, disconnected and connected, respectively.
Table 7 presents the
and
indices for all scenarios.
From
Table 5, it can be observed that in the BC scenario, there are no coordination problems since the number of violations of Equation (
2) is zero; furthermore, the total operating time of the protections is the shortest one. With the connection of 5 EVs (scenario EV1), there are coordination problems since two violations of Equation (
2) appear and the operation time also increases to 11.65 s. With respect to scenario EV2, which considers 15 EVs, the coordination problems increase since there are three violations of Equation (
2).
In
Table 6, it can be seen that in the BC DG scenario, there are no coordination problems since there are no violations of Equation (
2), and the total operating time of the protections is the shortest one. With scenario EV1, there are no coordination problems; nonetheless, the total operating time increases to 18.36 s. In scenario EV2 DG, there are coordination problems represented in two violations of Equation (
2), and the operation time also increases.
Table 7 shows the
and
indices described in described in
Section 4 for all scenarios. The negative sign of the
index indicates that there was a reduction in the operating speed of the DOCR scheme in all scenarios. This evidences that the increase in EVs in the network affects the performance of the DOCR scheme. From the
index, it can also be identified that the impact is greater in scenarios without DG.
According to the sign of the index, there is a reduction in the , which indicates that the protection coordination is affected. The index shows that the increase in EVs in the network affects the performance of the DOCR scheme. It can also be concluded from the index that the scenarios with DG show a lower impact on the protection coordination (smaller changes of the ) than those scenarios without DG.
After the evaluation of the general indexes of the DOCR scheme, the particular evaluation of each of the relays is carried out. The results of this evaluation are presented in
Table 8 and
Table 9.
Using the general indices, it can be concluded that the increase in EVs in the network has a negative impact on the protection coordination scheme. It can also be concluded that in scenarios with DG, the impact is slightly lower. This shows that the impact of EVs on protection coordination schemes can be higher in networks with low short-circuit levels. These analyses are in agreement with those initially performed on the short-circuit levels presented in
Section 6.2.
After the evaluation of the general indexes, the particular evaluation of each relay of the protection coordination scheme is carried out. The results are presented in
Table 8 and
Table 9. In
Table 8, the
index is presented. This index allows to evaluate the operating speed of each relay. From the
index, it can be identified that in all scenarios, the operating speed of R6 and R12 are negatively impacted since the index has a value greater than 1; the other relays have a positive or very similar impact on the operating speed.
In
Table 9, the selectivity of each one of the protections is evaluated in the applicable cases according to the recommendations and analysis proposed in [
42,
43,
44].
Table 9 indicates the cases where selectivity is lost. Selectivity is evaluated using Equation (
2). In the
column, the relay on the right is the main relay, and the relay on the left is the backup. From the selectivity results, it can be seen that in scenarios BC, BC DG and EV1 DG, there is no coordination problem. In scenario EV1, selectivity is lost in two cases: the first one when the main relay is R3 and the backup relay is R1; and the second one when the main relay is R6 and the backup relay is R7. In scenario EV2 DG, selectivity is lost in two cases: when the main relay is R3 and the backup is R1; and when the main relay is R4 and the backup is R15. In scenario EV2, selectivity is lost in three cases: when the main relay is R3 and the backup is R1; when the main relay is R2 and the secondary is R4; and when the main relay is R6 and the secondary is R8. From the selectivity analysis of each relay, it can also be concluded that the impact of EVs is lower in scenarios with DG connected to the network.
Once the selectivity is analyzed by verifying compliance with Equation (
2), some of the cases are validated using the coordination curves. The first case to be analyzed is when there is a fault on line DL-4. In this case, relay R3 is the main relay and R1 is the backup relay. In the BC scenario, R3 does not see the fault current because the contributions to this current come from the main network; consequently, in this scenario, it is not necessary to verify the coordination of these relays. Therefore, when analyzing scenarios EV1 and EV2, there are selectivity problems. In scenario BC DG, it is necessary to coordinate relays R3 and R1 (see
Figure 9) and there is no problem with selectivity. In scenario EV1 DG, there is also no problem with selectivity (see
Figure 10), while in scenario EV2 DG, selectivity is lost (see
Figure 11) because the
is lower than 0.3 s.
The second case to be analyzed is when there is a fault on line DL-3. In this case, relay R6 is the main relay and R7 is the backup relay. In the BC scenario relays, R6 and R7 present selectivity as in the other scenarios (see
Figure 12). In scenario EV1, selectivity is lost because the CTI is lower than 0.3 s (see
Figure 13).
The third case to be analyzed is when there is a fault on line DL-5. In this case, relay R2 is the main relay, and R4 is the backup relay. In the BC scenario, relays R2 and R4 present selectivity (see
Figure 14), as in the other scenarios; nonetheless, in scenario EV2, selectivity is lost (see
Figure 15) because the CTI is lower than 0.3 s.