1. Introduction
To decrease the use of fossil fuels and CO
2 emissions, the past decade has seen a rapid increase in the deployment of renewable distributed generation (DG). This growth, however, introduces difficulties for managing active distribution networks (ADN). On one hand, the mismatch between DG distribution and demand can cause reverse power flow and worsen voltage issues, potentially leading to the simultaneous need for DG curtailment and load shedding within a system. On the other hand, the unpredictable and variable nature of renewable energy means that errors in forecasting DG outputs are unavoidable, compounding the challenges of maintaining real-time power balance in ADNs [
1].
Accommodating the growing demand and generation of power will necessitate significant investment in reinforcing networks and replacing aging assets, a process that is both expensive and time-intensive. As an alternative, leveraging the flexibility of DG, demand response, and network devices offers a strategy to manage network constraints in real-time, presenting a potentially more efficient and cost-effective approach [
2,
3].
Soft open points (SOPs) power electronic devices typically installed at the normally open junctions of electrical distribution networks and offer precise and flexible control over the power and voltage within these systems. With their superior real-time power management capabilities, SOPs have proven to be effective in addressing the various challenges associated with distribution networks [
4]. These devices, integral to distribution-level power electronics, were developed and named the Siemens multifunctional power link (SIPLINK) by Siemens AG in Germany in 2001 [
5]. However, the name SOP was first mentioned in reference [
6], highlighting their role in replacing normally open points within distribution networks.
The core component of an SOP consists of two voltage source converters (VSCs) connected back-to-back [
7,
8]. By substituting the mechanical switch at a normally open point with an SOP, it becomes possible to maintain continuous power transfer between two busbars. Consequently, SOPs are valued for their ability to facilitate flexible interconnections, making them the optimal choice for addressing imbalances between generation and power demand, thereby enhancing the energy efficiency of ADNs [
6,
9].
The SOP device has been utilized to reduce losses and balance loads, with strategies developed for local voltage control to address distribution system fluctuations and optimization methods incorporating SOPs and energy storage to minimize losses and voltage deviations [
10,
11]. Robust optimization techniques have been proposed to manage PV output uncertainties and exploit SOPs’ benefits fully, including strategies to lower operational losses, correct three-phase imbalances, and a dual-time-scale optimization approach for multi-terminal SOPs to simultaneously reduce system loss and voltage imbalance [
12,
13,
14]. Reference [
15] found that SOPs supported the economical operation of ADN, with network performance enhancements achieved by integrating SOP usage and network reconfiguration strategies. Moreover, reference [
16] introduced a coordinated scheduling method for ADNs, leveraging SOP and Plug-in Electric Vehicles (PEVs) across multiple timescales. It optimizes operational efficiency and handles uncertainties through advanced programming techniques, demonstrated an effective performance on modified IEEE and real distribution systems and showcased significant operational improvements.
Research has underscored SOPs’ pivotal role in enhancing ADN operations. The coordination of SOPs with Volt–Ampere Reactive (VAR) regulation methods has successfully mitigated voltage violations through a convex programming strategy detailed in [
17]. These strategies predominantly depend on predictive data, neglecting the uncertainties of PV outputs. Given these uncertainties, relying solely on deterministic SOP operation strategies might exacerbate voltage instability issues. To refine SOP control strategies for optimal effectiveness, reference [
18] integrated a chance-constrained optimization model to ideally allocate SOPs, DG, and capacitor banks. Reference [
19] introduced a data-driven stochastic optimization to devise optimal SOP strategies for the least favorable probabilities. Moreover, a two-stage stochastic optimization model for a hybrid wind farm with hydrogen and energy storage systems is introduced in [
20], demonstrating better performance when compared to Monte Carlo and deterministic approaches in handling uncertainties. For the optimal operation of integrated energy systems, a distributionally robust approach is proposed in [
21] to address uncertainties arising from renewable energy resources, load demand, and energy prices. Despite the indeterminacy of scenario probabilities, the forecasted outcomes within these scenarios are fixed, making scenario selection crucial to the method’s success. The necessity to analyze a broad array of scenarios also significantly increases the computational workload.
The strategies in the above-mentioned documents have had great contributions to the optimal operation of ADNs with the existence of SOPs. However, the majority of works have focused on a single objective such as power losses, power curtailments, social welfare, and voltage deviations. Therefore, this paper considers multiple optimization objectives including power transmission losses, voltage deviations, operation costs of distributed battery energy storage systems (BESSs) and SOPs, as well as utility power purchase objective.
The rest of the document is structured in the following way:
Section 2 explains the models, distribution networks, BESS operation model, PV curtailment model, as well as loss model of SOPs with energy storage system.
Section 3 lays out the main problem that this paper addresses, starting with a clear-cut, certain scenario before moving on to a sturdier, uncertainty-ready model. After that,
Section 4 provides simulation case study to show how this all works in a real-world example, with discussion of the results of simulations based on this case study. The paper ends with the conclusions in
Section 5.
4. Numerical Results
To validate the proposed optimal operation strategy for ADN with an SOP, a 21-bus distribution system is adopted in a case study, as shown in
Figure 2. The 10-kV distribution network contains six PV plants and a BESS installed at buses 3, 7, 9, 12, 16, and 20, respectively. Additionally, buses 20 and 14 are connected via an SOP, which is integrated with a BESS to provide power support for the system. The system operates at a rated voltage of 11 kV, with a maximum branch flow capacity of 10 MVA. To ensure stability and efficiency within the network, the bus voltage levels are regulated to remain within a permissible range: the upper limit is set at 1.05 per unit (p.u.), and the lower limit is established at 0.95 p.u. This framework ensures that voltage levels at various buses within the network are maintained within a narrow window, promoting reliable and efficient power distribution.
PV sources and BESS units are integrated at designated nodes within the network, specifically at nodes [3, 7, 9, 13, 16, 20]. An SOP connection is established between nodes 14 and 20, with the relevant capacities detailed in
Table 1. The maximum power outputs for the BESS units are set to
MW, and their minimum power outputs are defined inversely to their maximums,
MW. The BESS integrated within the SOP is configured to a maximum and minimum output of 1 MW and −1 MW, respectively.
The system’s power factor is maintained at 0.95. Line characteristics, including resistance and reactance, are specified as
. The loss coefficient of SOP, denoted as
, is set at 0.02. As shown in
Figure 3, total PV generation varies from zero to 5.5 MW, and the peak generation appears from
to
. Load demand varies from 3.8 to 6.5 MW, and its peak demand occurs at
to
.
Economic parameters for the PV sources and BESS, including those integrated with SOP, are outlined with cost coefficients S/kWh2, and the utility price is set at 0.5 CNY/kWh. The simulation framework is implemented using MATLAB 2022b/CVX, and optimization problems are solved with Gurobi 10.0.0.
4.1. Simulation Results of ADN without SOP
This section examines the optimal operation of an ADN in the absence of an SOP. The dynamics of power and energy within the battery energy storage system (BESS) are depicted in
Figure 4. Specifically,
Figure 4a illustrates that the power output of the BESS varies between −0.8 MW and 0.7 MW. This is indicative of the charging phase, occurring from 8:00 to 17:00, during which the BESS absorbs energy, and the discharging phase, happening outside these hours, where the BESS releases energy. While charging, the BESS injects negative reactive power to regulate the nodal voltage within safe range. Conversely, during discharging, it supplies positive reactive power to the grid, ensuring the nodal voltage does not dip below acceptable levels. Additionally,
Figure 4b demonstrates the state of charge (SoC) of the BESS over a 24 h cycle, confirming that the SoC remains consistently within the strategically designed range of 20% to 80%. Furthermore, the output power of each BESS vary from each other since the operation costs of BESS are different. Meanwhile, the reactive power outputs of the BESS are from −20 to 120 kVar to support system voltages, and the reactive power output of BESS at bus 3 is the highest during the peak hours (from 18:00 to 22:00). This is because the load demand of this branch is much higher than other branches and BESSs at this branch would generate more reactive power to support bus voltages.
Figure 5 presents the power outputs of photovoltaic (PV) sources, the power at the point of common coupling (PCC), and the nodal voltages of the network. As depicted in
Figure 5a, from 6:00 a.m. to 7:00 p.m.—corresponding to daylight hours—PV sources contribute active power to the grid, with values ranging from 0 to 1.1 MW, and each PV generate power according to its capacity from 0.6 MW to 1.2 MW. Notably, peak power outputs of PV sources occur between 12:00 p.m. and 2:00 p.m. During these daylight hours, PV sources also produce negative reactive power, thereby aiding in maintaining nodal voltages within the standard operational range. The reactive power generated by the PV sources fluctuates between −40 kVar and 0 kVar. However, the outputs of reactive power are different, which is caused by the power outputs constraints, power flow constraints, and load demand distribution in the system.
Figure 5b illustrates that the active power at the PCC varies from 3.4 MW to 3.8 MW, while the reactive power remains approximately constant at 0.3 MVar, as indicated by the blue curve. Furthermore,
Figure 5c confirms that nodal voltages at buses equipped with BESS are consistently within the acceptable range of 0.95 to 1.05 per unit (p.u.), ensuring stable operation within the network. Voltage constraints are satisfied because the PV, BESS and upper grid provide reactive power as well as PV active power curtailments. The curtailed power of PV sources are shown in
Figure 5d, where it can be seen that the maximal curtailed power of PV reaches 85 kW during the peak time. The minimal curtailed power is still higher than 40 kW.
4.2. Simulation Results of ADN with SOP
This section examines the optimal operation of an active distribution network (ADN) with an SOP. The power outputs of a distributed BESS and SOP are shown in
Figure 6. In
Figure 6a, power outputs in the distributed BESS vary from −0.4 MW to 0.3 MW, and reactive power outputs are from 10 kVar to 110 kVar. With an SOP, the power outputs of BESS 1, 2, 3, 5 are close to each other; however, the power outputs of BESS 4 and BESS 6 installed at buses 14 and 20 are opposite during peak hours. This is because during the peak hours, load demand is transferred from bus 14 to bus 20. To conclude, the outputs of BESS are decided not only by operation costs but also by operation constraints of SOP.
Specially, the power outputs of the SOP and the BESS in an SOP are shown in
Figure 6b, varying from −0.25 MW to 0.25 MW. Reactive power of the SOP stays close to −0.3 MVar, and reactive power of the BESS in an SOP is 0.5 MVar. Accordingly, the SoC of the distributed BESS varies in a small range, from 45% to 58%, since the variation in the distributed BESS is small, as shown in
Figure 6c. The SoC of the SOP BESS is depicted in
Figure 6d, demonstrating a fluctuation range from 45% to 55%. This variation is attributed to the smooth fluctuations in the power output of the BESS, which directly influences the SoC of the SOP.
Compared with BESS power outputs without an SOP, shown in
Figure 4 and
Figure 6, the fluctuation BESS power output when an SOP is adopted is smaller than that without an SOP since the SOP transfers power between two different branches efficiently.
Additionally, PV power outputs are shown in
Figure 7a, where their outputs vary from 0 to 1.2 MW; meanwhile, reactive power varies from zero to 30 kVar to support nodal voltages, and the curtailed power is decreased to about 5 kW, a large amount power decrease when compared with the power curtailment without an SOP, shown by
Figure 6d. This means that PV power generation with an SOP is higher than PV generation without an SOP; in other words, the installation of an SOP increases the penetration of PV sources.
As seen in
Figure 7c, utility power varies from 0 to 5.5 MW when an SOP is installed, and reactive power varies from 0.25 to 0 MVar. From 8:00 to 18:00, PV generation is shared by loads and BESS; therefore, it is indicated that load demand is locally balanced with the help of an SOP. Moreover, nodal voltages are still in the normal range of 0.98 to 1.01 p.u., as shown in
Figure 7d.
The SOP plays a pivotal role in enhancing the operational flexibility and efficiency of the distribution network, as validated by the results shown in
Figure 4,
Figure 5,
Figure 6 and
Figure 7. It smooths BESS power outputs and reduces PV power curtailments. Compared to
Figure 5d and
Figure 7b, the reduction in PV power curtailments is over 90% in general while still satisfying the operational constraints.
5. Conclusions
This paper introduces a sophisticated mixed-integer convex optimization framework specifically engineered for orchestrating the scheduling of SOPs seamlessly integrated with energy storage (ES) systems in ADNs that largely incorporate photovoltaic (PV) sources. The model is designed to eliminate any risk of constraint violations, ensuring a seamless operation. To further enhance the operational efficiency and sustainability of these networks, a comprehensive stochastic optimization strategy is proposed. This strategy is aimed at amplifying the utility and efficiency of SOPs while simultaneously aiming for a substantial reduction in system power losses, minimizing SOP-related power losses, curtailing voltage deviations, reducing the need for PV power curtailment, lowering the operational costs associated with BESS, and decreasing the necessity for utility power purchases.
To accommodate the inherent uncertainties associated with PV generation and load demand, the model employs advanced Monte Carlo simulation techniques coupled with k-means clustering technologies, providing a solution on robust optimization. Detailed simulation cases conducted on a structured 21-bus distribution network offer compelling evidence of the model’s superior performance, with an over 90% percent reduction in PV power curtailment. The connection of SOPs into the network significantly minimizes the curtailments typically faced by PV sources and effectively dampens the power fluctuations experienced by BESS, showcasing a marked improvement over scenarios devoid of SOP integration. Moreover, the model ensures strict adherence to a set of critical operational constraints, including nodal voltage levels, precise power outputs, stringent energy balance requirements, and fluid power flow dynamics, highlighting its comprehensive capability to enhance the resilience, efficiency, and reliability of ADNs with renewable energy sources.