Next Article in Journal
Optimal Design of Mix Proportion of Hot-Mix Epoxy Asphalt Mixture for Steel Bridge Decks and Its Anti-Slip Performance
Next Article in Special Issue
Critical Factors Influencing Early Contract Termination in Public Design–Build Projects in Developing and Emerging Economies
Previous Article in Journal
Tuned-Mass-Damper-Inerter Performance Evaluation and Optimal Design for Transmission Line under Harmonic Excitation
Previous Article in Special Issue
Dynamic Network Analysis of the Risks of Mega Infrastructure Projects from a Sustainable Development Perspective
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Effective Use of Tower Cranes over Time in the Selected Construction Process

1
Department of Technology, Mechanization and Construction Management, Faculty of Civil Engineering, Brno University of Technology, 602 00 Brno, Czech Republic
2
Department of Building Technology, Faculty of Civil Engineering, Slovak University of Technology in Bratislava, 810 05 Bratislava, Slovakia
*
Author to whom correspondence should be addressed.
Buildings 2022, 12(4), 436; https://doi.org/10.3390/buildings12040436
Submission received: 17 January 2022 / Revised: 19 March 2022 / Accepted: 23 March 2022 / Published: 2 April 2022
(This article belongs to the Special Issue Construction Scheduling, Quality and Risk Management)

Abstract

The quality of preparations carried out before building work commences has a significant impact on the smooth running and overall financial costs of a construction project. The use of construction machinery, which is crucial with regard to the efficiency of the construction process, plays an important role. In building construction, the machines in question are mainly tower cranes. The paper presents a new method for assessing the utilisation of tower cranes over time during the construction of reinforced concrete monolithic structures. The method, which contributes to the efficient utilisation of such cranes, is based on a mathematical simulation model that predicts the work cycles of a tower crane during a work shift when work is being performed on individual construction sub-processes. Construction sub-processes are analysed in detail with regard to the service provided to them by a tower crane. Data can also be obtained from binding construction schedules and boundary conditions, which in every case are for a specific executed construction project. The simulation model of the work of tower cranes has been developed for use in software applications. The created application expands the possibilities of smart construction site design in a digital environment and can also be used directly from an internet browser.
Keywords: pre-construction phase; tower crane; tower crane design; smart construction site pre-construction phase; tower crane; tower crane design; smart construction site

Share and Cite

MDPI and ACS Style

Motyčka, V.; Gašparík, J.; Přibyl, O.; Štěrba, M.; Hořínková, D.; Kantová, R. Effective Use of Tower Cranes over Time in the Selected Construction Process. Buildings 2022, 12, 436. https://doi.org/10.3390/buildings12040436

AMA Style

Motyčka V, Gašparík J, Přibyl O, Štěrba M, Hořínková D, Kantová R. Effective Use of Tower Cranes over Time in the Selected Construction Process. Buildings. 2022; 12(4):436. https://doi.org/10.3390/buildings12040436

Chicago/Turabian Style

Motyčka, Vít, Jozef Gašparík, Oto Přibyl, Martin Štěrba, Dita Hořínková, and Radka Kantová. 2022. "Effective Use of Tower Cranes over Time in the Selected Construction Process" Buildings 12, no. 4: 436. https://doi.org/10.3390/buildings12040436

APA Style

Motyčka, V., Gašparík, J., Přibyl, O., Štěrba, M., Hořínková, D., & Kantová, R. (2022). Effective Use of Tower Cranes over Time in the Selected Construction Process. Buildings, 12(4), 436. https://doi.org/10.3390/buildings12040436