Critical Obstacles in the Implementation of Value Management of Construction Projects
Previous Article in Journal
Coupling CFD Simulation and Field Experiments in Summer to Prove Feng Shui Optimizes Courtyard Wind Environments: A Case Study of Prince Kung’s Mansion in Beijing
Previous Article in Special Issue
Factors Affecting Residential End-Use Energy: Multiple Regression Analysis Based on Buildings, Households, Lifestyles, and Equipment
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Interface Management Performance Assessment Framework for Sustainable Prefabricated Construction

1
Department of Construction Management, Dalian University of Technology, Dalian 116000, China
2
School of Management Engineering, Qingdao University of Technology, Qingdao 266000, China
3
Department of Architecture and Civil Engineering, City University of Hong Kong, Hong Kong 999077, China
*
Author to whom correspondence should be addressed.
Buildings 2022, 12(5), 631; https://doi.org/10.3390/buildings12050631
Submission received: 24 March 2022 / Revised: 6 May 2022 / Accepted: 7 May 2022 / Published: 9 May 2022

Abstract

:
Prefabricated construction (PC) has been regarded as a sustainable construction method for its inherent advantages such as energy savings, emissions reductions, and cleaner and safer working environments. However, PC development has been hindered by its inherent weaknesses of fragmentation and discontinuity. Effective interface management (IM) is regarded as integral to PC project success for its appropriate management of numerous interfaces with high complexity and uncertainty among the organization, information, and logistics. Although some researchers mentioned the effectiveness of IM for PC projects, systematic assessment methods for IM performance are missing. This study aims to systematically develop a framework to assess the IM performance of PC projects to address this gap. Through a comprehensive literature review, nineteen indicators of IM performance were identified and grouped into four categories. By combining the objective weighting method of an ordered weighted averaging (OWA) operator with the set pair analysis (SPA) method of uncertainty assessment, a nineteen-indicator assessment model was developed. Finally, a case study was constructed using the proposed framework, and the feasibility and applicability of the OWA-SPA model were proved. The assessment results provided by the assessment model could guide project managers for better IM and serve as a valuable reference for researchers in the construction industry.

1. Introduction

Prefabricated construction (PC) has existed for decades [1] and aroused great interest in several countries and regions [2,3], including Japan, Germany, Malaysia, Australia, etc., because of its advantages in quality, assembly speed, cost [4], energy savings [5], emissions reductions [6], and cleaner and safer working environments [7]. In recent years, with the development and application of building information modeling (BIM), Internet of Things (IoT), and other technologies, PC has further become an important carrier of smart construction [8,9]. However, the practice of PC is still in its infancy, facing many challenges brought by the existence of geographically dispersed workplaces and having more parties involved than cast-in-situ construction [10,11]. It is critical to integrate the fragmented construction processes through proper management approaches [12].
Ideally, PC should be an organizational process with a continuity of production through a well-integrated construction organization [13]. However, the current PC processes are fragmented in a temporal–spatial distribution [14,15,16,17,18] with additional complexity introduced [19]. For example, compared to the traditional cast-in-situ methods, some of the works (e.g., manufacturing and preassembly of some building components, modules, and elements) are transferred to the factory for reassembly [18], leading to more new stakeholders (e.g., offsite manufacturers, transporters, and local authorities) being involved and the complex interactions among them [19]. The functional modules of the building are decomposed into components and assembled on site after production, which adds a lot of physical interfaces that need seamless connection and actually increases the complex interface management (IM) work. Besides, the increasing complexity challenges the efficiency of information and logistics exchange during the construction process [20]. Furthermore, the PC project may face more uncertainties under the complex construction conditions due to PC technology not being mature enough and the relevant standards and specifications not being perfect [21,22]. Consequently, the success of PC relies on the collaboration of all the participants in multiple dimensions of the project management process, such as organization, technology, information, and decision making [23].
Scholars acknowledged the complexity and fragmentation of PC projects and explored different approaches to address the issues above [24,25,26]. Among these efforts, IM—referring to the management of information, coordination, and responsibility across physical, contractual, and organizational boundaries—was introduced to the construction industry and recognized as an effective approach to realize harmonious collaboration among project organizations [27]. IM can improve the construction processes, minimize rework, and reduce the total duration by identifying and tracing the interface or changed events [28]. For temporary construction projects, the increased transparency of IM contributes to clear and definite responsibility and authority, strict control, and organizational checks and balances [29]. Previous research also proved that IM has the potential to bring cost and time benefits during the execution of adaptive reuse building projects [30]. A case study of 45 large-scale construction projects revealed that IM practices effectively mitigate the adverse impact of project complexity originating from uncertainty in scope, communication, and large numbers of stakeholders [27]. The advantages of IM in the construction industry promote its application in PC projects. The successful experience of IM in the construction industry also provides a reference for its application in prefabricated buildings. For example, the ConBIM-IM system, which combines BIM with IM [31], can not only enhance the interface information sharing and efficiency in tracking traditional construction projects but can also optimize interface information sharing during the design, manufacturing, and installation processes of PC projects and promote better coordination among all participants. Consequently, to better cope with increased levels of PC project complexity, IM was also employed and performed well in tracking coordination between project stakeholders, overall design, logistics, external influences, and assembly processes [32]. The connection between the local component and the whole of PC building is a kind of interface. Proper IM can optimize the module design of components and provide the most concise assembly scheme [33]. The standardization of the interface between components can reduce the interdependencies between the activities for installing the building components, which are executed by different subcontractors [34]. The logistics interface between factory production and on-site installation was analyzed, and it was found that improving the IM with the aid of information technology to improve the efficiency of information transmission is useful for the integration of the construction management system [35]. BIM and lean are also being employed to improve the IM of design–production interfaces to meet a fast schedule and to overcome logistical challenges in complex PC projects [36]. A sample analysis indicated the importance of early engagement of the contractor in the design process and that open communication between all stakeholders is essential to organizational IM [37]. Accordingly, scholars believe that the performance depended on how smooth the interface could be made in PC projects [32,34,37].
Above all, IM was reported to have great potential management capabilities that need to be enhanced in PC projects [32,34]. However, as a new management method, people have limited knowledge of IM, and for this reason, how IM activities are designed or executed mainly depends on the speculation about their effectiveness. In the construction industry, most interface-management-related studies are based on traditional cast-in-situ projects or undifferentiated types of construction projects. The few PC interface-management-related studies focus on methods and strategies for interface improvement and lack an in-depth examination of the influencing factors, let alone a quantitative evaluation of IM performance. Consequently, appropriate metrics and quantitative assessment methods are urgently needed for IM performance assessment to seek, prevent, or control the poor efficiency interfaces and continuously improve the IM performance in PC projects. To make up for the above research gap, this study aims to develop a framework to systematically assess the IM performance for PC. First, an assessment indicator system was established based on the influencing factors of IM performance that were identified through a literature review and expert interviews. Then, an ordered weighted averaging (OWA) operator was used to calculate the weights of the indicators. Moreover, a set pair analysis (SPA) was used to comprehensively assess the IM performance of PC management.
The remainder of this paper is organized as follows: Section 2 presents the literature review of performance assessment and IM. Section 3 elaborates the development of the IM performance assessment framework, covering framework design, the establishment of the IM performance assessment indicator system, and assessment method development. Section 4 uses a case study to demonstrate the proposed framework. Discussions are conducted in Section 5. Finally, the key findings, research contributions, and limitations are summarized in Section 6.

2. Literature Review

2.1. Interface Management (IM) in the Construction Industry

IM was first introduced by Wren in 1967 to deal with the complex inter-organizational interface issues within an aerospace and electric power pool project [38]. After a period of development, IM became mature and was widely used in manufacturing. With the introduction of manufacturing technology and information technology to the construction industry, IM is attracting more and more attention in construction [32,39]. The Construction Industry Institute (CII) defines IM as the “management of communications, relationships, and deliverables among two or more interface stakeholders (e.g., contractors, designers, and owners)” [40]. Although the connotation of IM is clear, its application in prefabrication is still unclear [41].
Interfaces exist where there are major discontinuities in technology, territory, time, or organization [42], resulting in significant breakpoints between activities within construction phases, for instance, between manufacture, inspection, delivery, warehousing, installation, and testing. Because of the large number and variety of activities, interfaces are generally considered highly complex and uncertain [39,42]. Due to the project’s complexity, nature variety, the multi-organizational composition of project teams, and lack of appropriate documentation procedures [43], it is a challenge to give a unified classification of interfaces. In the 1980s, organizational, managerial, and technical interfaces were identified by Morris, who put forward the corresponding IM method [38]. Pavitt and Gibb discussed the necessity of IM in the construction process and categorized the interface into physical interfaces, organizational interfaces, and contractual interfaces. From the perspective of supply chain management, the interface could be classified into the logistics interface, information interface, and management interface [37,44]. There exist other studies introducing social, functional, geographic, resource, and time interfaces [42,45].
Regardless of the different classifications of interfaces, many studies have been carried out to deepen the research of IM in several directions: (1) using IM to introduce effective communication strategies for construction project management [43]; (2) establishing error-free communication channels between different engineering specialties [46]; and (3) developing formal procedures for IM implementation [39,47].
Earlier publications have widely discussed the implication of IM and studied and presented some preliminary results, but the research related to PC projects is limited. No unified definition and classification of the interface exist. The effectiveness of IM for PC has not been investigated due to the lack of measurement criteria and evaluation methods. Appropriate metrics and a quantitative assessment method for IM performance measurement should be proposed to set objectives, seek the shortcomings and advantages, and determine the future courses of IM improvement actions in PC projects.

2.2. Performance Assessment for IM

Performance assessment is a process to quantify the efficiency and effectiveness of individuals’ or organizations’ past actions [48]. Generally, it refers to the comprehensive assessment of the degrees of goal achievement and the results of implementation for achieving goals through specific statistical and scientific methods [49]. IM performance assessment assists in clarifying the efficiency of IM implementation and determining whether interfaces need to be controlled and improved [50].
As IM is a complex engineering system, it is challenging to measure IM performance: (1) many factors influence IM; (2) it is difficult to quantify the performance; (3) participants on both sides of the interface often have different understandings of the same problem; and (4) the criteria of measurement are not uniform [51]. To promote the efficiency of enterprise technological innovative IM, Xu identified four main factors (interface element composition, interface element organization, interface environment, and interface agility) that have an influence on the enterprise innovative IM and constructed a model for measuring the IM performance based on the harmonious theory [52]. Du and Liang also considered the harmonious theory as one of the references for measuring IM performance; however, a more systematic index system was established, which takes into account factors such as research and development (R&D) efficiency, communication effect, organizational structure, and cultural conflict. Based on a case study, Dong analyzed the performance of the development–manufacturing interface and found the key factors (responsibility assignment factors, information transferring factors, and enterprise culture factors) that influence IM performance [53]. Considering the complexity and multi-level characteristics of the R&D–market interface, scholars determine the hierarchical structure of IM influencing factors and determine the assessment model for IM performance based on the analytic hierarchy process (AHP) [51]. In the area of aerospace, the performance of the IM (including the mechanical, environmental, command, and data handling interfaces) process implemented by NASA between the Orion Multi-Purpose Crew Vehicle (MPCV) and the Space Launch System (SLS) was investigated through a qualitative comparison of the IM practice evidence and the criteria of the System Engineering Capability Model (SECM) [54]. In recent years, some scholars have been trying to study IM performance assessment in the construction industry. Ahn et al. collected data from 45 large-scale construction projects and analyzed the effectiveness of IM using quantitative analysis methods from the perspective of dealing with project complexity [27]. Senthilkumar and Varghese assessed the effectiveness of the implementation of a design IM system through a comparative study of two design cases of a large airport [55].
In summary, the IM performance assessment research has been extensively studied in many areas (e.g., aerospace, mechanical engineering, and technology innovation management). Although the research areas are different, researchers seem to have similar views. They all consider the factors that influence IM performance from at least three aspects: technology, organization, and information. Specific assessment methods vary from study to study, including quantitative and qualitative methods, making great progress. The achievements of these researchers are of great significance to their industries. However, IM performance assessment research in the construction industry is rarely seen. The related research has not even been touched for PC projects [56]. Learning the experiences from other areas may be helpful for the IM performance assessment of PC projects.

2.3. Methods for IM Performance Assessment

An appropriate performance assessment for IM in PC should have high applicability with the characteristics of IM. The selection of method affects the objectivity and accuracy of the assessment.
Many studies [57,58] have investigated the existing methods for performance assessment and proposed new tools to address the limitations. Fayek developed a fuzzy expert system for design project performance assessment and prediction [59]. Sun developed an assessment model based on the fuzzy AHP and TOPSIS to help industrial practitioners perform performance assessments in a fuzzy environment [58]. Chao presented a data-clustering-based fuzzy model for predicting the performance of construction projects [60]. Fullerton and Wempe used structural equation modeling (SEM) to establish the relationship between different lean tools and lean production performance [61]. Considering the IM practices and the complexity of large-scale construction projects, Shen analyzed IM performance with quantitative analysis methods, such as principal component analysis and linear regression [62].
Although the research on the performance assessment method is pervasive, few of them are designed for the IM of PC. Although the methods above consider the fuzziness and complexity of performance assessment, they cannot be directly applied to IM performance assessment because the fragment-integration organization characteristics of PC make the IM of different participants, different construction processes, and entity interfaces a complex uncertainty system. Determining how to deal with the uncertainty of IM performance assessment is the motivation for this study. Although the fuzzy assessment method can deal with uncertainties to some extent [63], it has a few limitations. For example, after quantifying the indicators with the fuzzy assessment method, it is easy to ignore that different impact factors at the same performance level may have considerable differences [64]. In order to embody this difference as vividly as possible, it is necessary to accurately grasp the unity of opposites between certainties and uncertainties and make full use of the assessment information [64]. As a modern uncertainty theory that overlaps the other uncertainty theories such as probability, vague, rough, and fuzzy theory [65], set pair analysis (SPA) regards certainties and uncertainties as an integrated certain–uncertain system [66]. It takes full account of the relationship between impact factors and the performance scale to more comprehensively determine the subordinate degree of the factors to performance scale [67]. Compared to the traditional assessment methods, it can not only improve the accuracy of performance assessment by making full use of assessment information but it can also predict the trend of performance development by analyzing the relationship between factors and different scales. This advantage of the SPA model will help managers make more forward-looking decisions in the IM practices for PC.
It is also indispensable to the weight of each performance indicator in the assessment process. The rationality of the indicator weight calculation is critical to ensure the accuracy of assessment results [68]. The traditional weighting method is usually based on the direct calculation of the weights given by experts [69]. However, some experts may assign weights that deviate from reality due to subjective reasons [14]. An ordered weighted averaging (OWA) operator, an objective weighting method, can significantly reduce the adverse effects caused by extreme values of decision data and make the weights more objective and reasonable [69]. OWA has been widely used in environmental assessment [70], strategic decision [71], risk assessment [72], and performance assessment [73]. In this paper, the combination of an OWA operator and SPA is adopted to reflect all data information objectively in the assessment results.

3. Development of IM Performance Assessment Framework

This section aims to develop a framework for assessing the IM performance of PC projects. The framework development can be divided into three stages (Figure 1): (1) identify the major indicators that affect IM (Section 3.1) to establish an IM performance assessment indicator system; (2) invite experts to analyze the importance of indicators to determine their weights based on OWA operator (Section 3.2); and (3) calculate the single-indicator connection degree and synthetic connection degree based on SPA (Section 3.3).

3.1. Establishment of IM Performance Assessment Indicator System

Existing studies indicate that PC has more interfaces to be managed and that IM is more complicated and more critical than in cast-in-situ construction [74]. Although many studies [32,37,75,76] focus on the strategy of improving IM, a systematic performance analysis for IM has not been carried out. An indicator system is a prerequisite for an IM performance assessment. Therefore, this study first conducted a literature survey to identify nineteen indicators (Table 1) affecting IM performance and categorized them into four groups according to the following interfaces: the physical interface (I1), information interface (I2), relational interface (I3), and logistics interface (I4). The indicators could be revised and customized according to the characteristics of specific projects.
(1)
The physical interface refers to the actual, physical connections between two or more building components [32]. The common problems of weather-tightness, tolerance/fit, and constructability of PC projects are usually due to the failure of physical interfaces [32]. For prefabricated buildings, functional modules are decomposed into smaller components, which can meet the requirements of high-efficiency factory production [77]. However, the increase of the type and quantity of components greatly increases the complexity of the physical interfaces between components, which leads to the challenge of physical IM [34]. They challenge the design, manufacture, and construction and even the whole life cycle stage of PC projects [32]. The number and complexity of physical interfaces are largely determined by the building’s detailed design [32]. Designing standardized interfaces can reduce the complexity of the interface and promote the interoperability of different disciplines at the interface, which consequently reduces the interdependencies between the activities for installing the building components [34,78,79]. Standardization is also considered to facilitate the implementation of modular coordination as a rule for the configuration of physical interfaces [80]. Inaccurate and nonstandard design is considered to be the main factor affecting the compatibility of building components [81]. Although the interface is not mentioned here, the compatibility between components reflects the performance of the physical interface. It is a great challenge for designers to meet the requirements of physical interface performance by ensuring the accuracy of design because it is difficult to accommodate the movement and tolerance of each component and still maintain the integrity of the building [32]. Pavitt and Gibb describe the complexity of physical interfaces with an example that shows a typical physical interface between two cladding types [32]. Complexity in terms of numerous different components and the range of different interconnections between components can bring out difficulties for matching components to another [37]. Chen et al. found that the complexity of physical interfaces makes it easy to conflict when matching various components, which usually reduces constructability [76]. PC projects have strict tolerance requirements to prevent mismatching during component assembly [82], which puts forward high precision control requirements. For this reason, a dimensional and surface quality assessment of a precast concrete elements method was developed based on BIM and 3D laser scanning [83,84,85]. Besides, due to the high installation precision that is required (i.e., with small construction tolerances), risks, such as sealing joints, might come along with the assembly of prefabricated components [86]. Therefore, the accuracy of the completed working surface is the guarantee of PC projects [86]. Glass and Pepper cited practical concerns regarding ‘physical joints and interfaces’, focusing on the need for high levels of technology to ensure sufficient weatherproofing, particularly around windows [16]. Subsequently, the reliability of component interface connection technology has been one of the critical issues for PC projects [74,87].
(2)
The information interface is the basic interface among almost all kinds of interfaces. It is important for carrying the motivation, consciousness, emotion, and knowledge of both sides [88]. Unlike the physical interface, the information interface is invisible, but the transmission and interaction of information at the interface are real. Ensuring the effectiveness of information transmission and interaction at the interface is critical for the implementation of tasks. Sacks et al. emphasize the importance of exchanging information between installation and fabrication [89]. BIM is also a good example, which is committed to breaking the delay, omission, and asymmetry of information in the interface through a standardized information model [9,90]. The process design, manufacture, and construction of PC projects are located in different sites and require highly continuous information exchange among all stakeholders to achieve project success [91]. A professional information management system is recommended to be used in PC projects to manage interface-related information [4]. Transmitting and storing information in a standardized way is the basis for different stakeholders to share project information and interoperate in their information management systems [92]. The lack of information standards lowers the quality of information generated and reduces the communication efficiency and subsequent application [76]. Considering that the project information is transmitted between two or more geographically dispersed stakeholders [4], the receiving party may exaggerate or distort the subjective judgment of the information before transmitting it to other participants [93]. Therefore, managers should pay more attention to the distortion of information transmitted at the interface. Information sharing has been highly valued in the whole construction industry (both traditional construction projects and PC projects). Traditionally, the main methods for dealing with information interfaces in projects were the sharing of drawings and specifications, face-to-face meetings, oral presentations, phone conversations, and emails [27]. With the development of information technology, the information interface has been improved greatly. Advanced technologies such as RFID and BIM have been used to improve the degree of information sharing [94,95,96]. In addition to the challenges in the process of information transmission and storage, the expression defects of early design information make it difficult for manufacturers and constructors to use the design information when they receive it [97]. The lack of effective information integration processes also makes the information stored in paper and existing in the designer’s brain difficult to produce reuse value [97]. As the PC projects are difficult to change after the components are installed, the stakeholders (e.g., designers, manufactures, and constructors) of PC projects are advocated to intervene in the design stage early so that the design is oriented to manufacturing and installation at the beginning [23,37]. Meanwhile, the current information integration technology meets the high level of design information integration [90].
(3)
The relational interface refers to the interaction interface between geographically dispersed stakeholders, which can also be called the organizational interface [37]. Clarity of contract responsibility, power, and interest of contract is a formal guarantee to maintain the complex interface relationship among the designer, manufacturer, constructor, and other parties [32,35]. Direct evidence is an increase in the use and importance of contracts to govern relationships and enforcement of the terms of agreements [47]. Considering that a PC project is a typical temporary organization of geographically distributed stakeholders who have different working cultures [98], interface participants need to share a common culture. Otherwise, cultural differences may lead to a series of problems of information sharing, communication, and even cooperative attitudes, which will affect the performance of the relationship interface [99,100]. Making the goal consistent is the original intention of the contract and the beginning of a harmonious informal relationship. The existing IM-related research emphasizes that the commitment to a common goal can mitigate the complicated interaction at the interface [47]. Specifically, goal consistency is more essential for the IM of the PC projects where there are many geographically dispersed stakeholders [32,101]. Further, the cooperation attitudes of participants cannot be ignored. Some studies have found that organizations with a strong willingness to cooperate are more likely to enhance the relationship strength than those with a poor willingness [98], which can maintain better interface performance. In PC projects, participants are encouraged to participate in design and production planning through early cooperation as much as possible [2,101]. However, poor cooperation between the participants during the early stage is often caused by insufficient or inadequate communication [32]. McCarney and Gibb regards effective communication as one of the key factors affecting the IM of PC projects [101].
(4)
The logistics interface mainly exists between the manufacturing plant and the installation site, which is the key to ensure the seamless connection between the component production and site assembly/installation. However, the space constraints for storage and traffic congestion still restrict the smooth delivery of components. The lack of just-in-time (JIT) delivery was identified as a critical risk in PC projects [102]. Strengthening the research on JIT in PC projects may significantly improve the performance of the logistics interface. While ensuring on-time delivery, the quality assurance component at the logistics interface also needs to be guaranteed. Due to the large size, the prefinished components are prone to damage during transportation [103,104]. The resulting rework problems may lead to severe delays in downstream work. Further, the order and position of prefabricated components are well-organized, so the logistics interface between manufacturing and on-site installation needs to be well-tracked [102]. Recently, auto-ID technologies, such as barcode and RFID, were developed for this work [102,105,106].
Given the limited research literature on IM in PC projects, we have consulted almost all the relevant literature of PC so far to find indicators, but this still cannot guarantee comprehensiveness. Therefore, we draw lessons from the experience of some traditional construction project IM research. For the indicators that are suitable for PC projects but not yet explored in this field, they are also selected as the factors influencing the IM performance of PC projects with the approval of experts in the field. For example, “distortion of information in transmission”, which has only been verified in EPC project IM research, is also an important factor in PC projects.
Table 1. IM performance assessment indicator system of PC projects.
Table 1. IM performance assessment indicator system of PC projects.
First-Level IndicatorsSecond-Level IndicatorsSources of References
Physical interface (I1)Design standardization degree (I11)[32,34,37,78,79,80]
Design accuracy (I12)[32,37,81]
Complexity of physical interfaces (I13)[16,32,75,76,107]
Standardization degree of process interface (I14)[37,39,42]
Precision control of component manufacturing (I15)[82,84,85]
Accuracy of completed working surface (I16)[79,86]
Reliability of component interface connection technology (I17)[16,19,37,74,87]
Information interface (I2)Standardization of information transmission and storage (I21)[4,47,76,91,92]
Distortion of information in transmission (I22)[93]
Degree of information sharing (I23)[27,39,47,96,102]
Integrity and accuracy of design information (I24)[90,97]
Relational interface (I3)Clarity of contract responsibility, power, and interest (I31)[32,35,36,75]
Goal consistency (I32)[32,47,62]
Inter-organizational cultural differences (I33)[99,100,102]
Cooperation attitude of participants (I34)[16,76,98,102]
Effective communication between participants (I35)[10,32,101]
Logistics interface (I4)On-time delivery of components to the site (I41)[14,44,102,108]
Component quality assurance in transportation process (I42)[103,104,108]
Tracking of components in the transportation process (I43)[102,105,106,108]

3.2. Calculation of the Weights for the Indicators Based on OWA Operator

Ordered weighted averaging (OWA) was first introduced by Yager in 1988 [109]. This method weakens the adverse effects of extreme values by re-aggregating data sequences and differentiating the weighted data. Its essence lies in the incremental arrangement of data, and the weight is only related to its location [66]. Various OWA operators have been proposed for improving the form of data aggregation [110,111]. In this study, the classical OWA operators are improved by using a combination number as a weighting vector for data aggregation, weighting decision data by the combination number, and calculating the weight of each indicator [112]. The detailed steps for weight calculation are elaborated as follows:
(1)
The importance scores ( a 1 , a 2 , , a i , , a n ) of the indicators are sorted in descending order, and the sequence of decision data becomes B = ( b 0 , b 1 , , b i , , b n 1 ) , where b 0 b 1 b i b n 1 .
(2)
Calculate the weight of b j by the number of combinations:
w j + 1   =   C n 1 j k = 0 n 1 C n 1 k   =   C n 1 j 2 n 1 ,   j   =   0 , 1 , 2 , , n 1
where C n     1 j is the number of possible j objects from a set of n     1 objects.
(3)
The weighted vector, w , is used to weigh the decision data, B, to calculate the absolute weight, ω - i , of the indicator:
ω - i   =   j = 1 n w j · b j , w [ 0 , 1 ] , j [ 1 , n ]
(4)
Calculation of the relative weight of the indicator:
ω i   =   ω - i i = 1 m ω - i , i   =   1 , 2 , , m
The weight determination of the indicator system can be accomplished by repeating the above steps.

3.3. IM Performance Assessment Based on SPA

Set pair analysis (SPA) was proposed to describe and process the system uncertainty [68]. The core idea is to treat the problem of certainties and uncertainties as an integrated certain–uncertain system by analyzing the uncertainties of the system from three aspects: identity, discrepant, and contrary [113]. Its basic concepts are set pair and connection degree. A set pair, H(A, B), is a pair combined with two dependent sets, A and B. The connection degree is a connection number determined by the identity degree, discrepancy degree, and contrary degree for set A and B under certain circumstances [66]. Therefore, the key to SPA is to calculate the connection degree of the two sets. Suppose there are N elements in set pair H(A, B). To show its total features, S elements show the identity features, and P elements show the contrary features, such that F   =   N     S     P shows the discrepant features. Then the connection degree number ( μ ) is represented as follows:
μ   =   a   +   b α   +   c β
where a   =   S / N , b   =   F / N , and c   =   P / N denote the identity degree, discrepancy degree, and contrary degree, respectively, and 0   a ,   b ,   c   1 and a   +   b   +   c   =   1 ; and i [ 1 ,   1 ] and j   =   1 are the coefficients of discrepancy degree and contrary degree, respectively.
For the sake of understanding, the basic principle of SPA is rough, only dividing the state-space of a research object into three, which may not be directly applied to more complicated problems. Thus, it is necessary to expand Equation (4) on different levels to form a kind of multivariate connection degree [113]. The multivariate connection degree can be achieved as follows:
μ   =   a   +   b 1 α 1   +   b 2 α 2   + +   b k α k   +   c β
where b 1 ,   b 2 , ,   b k are the components of discrepancy degree, representing the grades of discrepancy degree (e.g., mild discrepancy, discrepancy, and severe discrepancy); α 1 ,   α 2 , ,   k are the coefficients of components; and, obviously, a   +   b 1   +   b 2   + +   b k   +   c   =   1 .
The connection degree describes the relationship between certainties and uncertainties. Considering the complexity of IM and the variability of the external environment, assessing IM performance based on the SPA can deal with the uncertainty of decision information more pertinently and effectively. The method has three steps as follows.

3.3.1. Determination of the Performance Measurement Scales

Before the SPA is used for quantitative assessment of the qualitative indicators, the measurement scales for each indicator’s performance are needed [114]. In general, the measurement scales are divided equally according to statistical principles [115]. However, some scholars try to further improve the scientificity of evaluation by adjusting the measurement scale of different grades. For example, Chen et al. proposed a fuzzy interval by reducing the measurement scale of high grades and expanding the measurement scale of low grades [112]. Accordingly, this paper defined four scales for the performance measurement for implementing SPA and IM performance assessment: poor, fair, good, and excellent, as summarized in Table 2. Then, the experts can assign corresponding scores according to their judgment as decision-making data in the assessment process.

3.3.2. Calculation of Single-Indicator Connection Degree

Determining the IM performance connection degree of each performance indicator is the key for SPA application. Therefore, in the process of performance assessment, the first stage is to calculate the single-indicator connection degree between each IM performance indicator and each scale of performance measurement [113]. The specific steps are described as follows:
(1)
Experts are invited to score the performance of each indicator in the 2nd level, according to Table 2. The initial performance score of the indicator can be obtained by averaging the scores from the expert group. Qualified experts shall be scholars or engineers/managers with extensive working experience in the field of PC.
(2)
The initial performance scores of each indicator are paired with different performance scales (Gk, k = 1, 2, 3, 4) and are regarded as a set pair, represented by μ ( x i j , G k ) for the second-level indicator x i j . Then, the single-indicator connection degree between Gk and x i j can be calculated in light of the following rules:
μ i j k represents the single-indicator connection degree between sample indicator x i j and Gk. The identity is considered when x i j alls in Gk ( μ i j k = 1 ); the discrepant is considered when x i j falls in the proximity of Gk ( μ i j k   =   [ 1 , 1 ] ); and the contrary is considered when x i j falls in another scale ( μ i j k = 1 ). μ i j k can be calculated as follows [113]:
μ i j 1 = { 1 ,                                       x i j s 1 1 2 ( x i j s 1 ) / ( s 2 s 1 ) ,       s 1 x i j s 2 1 ,                                     x i j s 2 μ i j 2 = { 1 2 ( s 1 x i j ) / ( s 1 s 0 ) ,      x i j s 1 1 ,                                       s 1 x i j s 2 1 2 ( x i j s 2 ) / ( s 3 s 2 ) ,      s 2 x i j s 3 1 ,                                     x i j s 3 μ i j 3 = { 1 ,                                     x i j s 1 1 2 ( s 2 x i j ) / ( s 2 s 1 ) ,      s 1 x i j s 2 1 ,                                       s 2 x i j s 3 1 2 ( x i j s 3 ) / ( s 4 s 3 ) ,      x i j s 3 μ i j 4 = { 1 ,                                     x i j s 2 1 2 ( s 3 x i j ) / ( s 3 s 2 ) ,      s 2 x i j s 3 1 ,                                       x i j s 3
where s k ( k 1 ) is the upper limit of the score interval for Gk, and s k is the lower limit of the score interval for G1.
After the calculation, the single connection degree between Gk and each IM performance indicator can be obtained. Taking the second-level indicator matrix { x 1 j j   =   1 , 2 , 3 , , m } under the first-level indicator x 1 as an example, we can obtain the connection degree ( μ 1 j k ) between each second-level indicator and Gk, as shown in Table 3.

3.3.3. Calculation of Synthetic Connection Degree

In calculating the synthetic connection degree, the criteria of the identity, discrepant, and contrary judgments of SPA should be obeyed as well. When the indicator falls in Gk, the identity is considered; when the indicator is adjacent to Gk, the discrepant is considered; and when the indicator is in the other scales, the contrary is considered.
Taking μ ( x 1 , G 1 ) for x 1 at the first level as an example, assume that the total number of second-level indicators under x 1 is m. Among those m second-level indicators, s second-level indicators fall in G1, with the corresponding weights of each indicator as c 1 , c 2 , , c s , f second-level indicators are adjacent to G1, with the corresponding weights of each indicator as d 1 , d 2 , , d f , and p second-level indicators fall in scales other than G1, with the corresponding weights of each indicator as e 1 , e 2 , , e p . Therefore, s + f + p = m . The connection degree can be calculated using Equation (7):
μ ( x 1 , G 1 )   =   h = 1 s c h   +   k = 1 f d k α k   +   l = 1 p e l β l
where α k is the single-indicator connection degree between each indicator x 1 k and G2, and β l is the single-indicator connection degree between each indicator and G3/G4. As the connection degree of the same scale is 1 and the connection degree of the different scale is −1, Equation (7) can be simplified as:
μ ( x 1 , G 1 )   =   j = 1 m ω i j μ i j k
Among the equations, ω i j is the weight of each second-level indicator under the first-level indicator x 1 , m is the number of the indicators under x 1 , and μ 1 j k is the connection degree.
Similarly, the degrees of association between x 1 and other scales (G2, G3, and G4) can be calculated according to Equation (8).
Finally, according to the principle of maximum connection degree [64], the maximum connection degree of the IM performance is as follows:
μ ( x 1 , G q )   =   max μ ( x 1 , G k ) , k   =   1 , 2 , 3 , 4
Therefore, the IM performance scale of x 1 is G q .

4. Case Study

To demonstrate the application of the proposed OWA-SPA model, a PC project is analyzed using the proposed model.

4.1. Project Background

The project is located in a megacity in South China, with five residential towers, 51–53 floors above ground and three floors underground. The completed project can accommodate 1760 households with a gross floor area of 150,000 square meters. The prefabricated components used in the project cover facades, stairs, and interior wall panels. The assembly rate is approximately 55%. The assembly of a large number and a variety of prefabricated components forms complex physical interfaces. To achieve the project objectives, seven major stakeholders from different disciplines participate in the project, e.g., client, designer, component designer, general contractor, consultant, and two manufacturers (manufacturer A and manufacturer B). The construction process is geographically fragmented. Three sites participate in the construction process. The prefabricated components are produced by those two different offsite manufacturers and transported to the construction site for installation. To ensure that the interfaces of the components produced by the two manufacturers can match seamlessly during installation and can be delivered to the site on time, a high degree of collaborative work among manufacturer A, manufacturer B, and the general contractor is the guarantee of project implementation. In addition to direct construction tasks, the flow and interaction of resources and information among the seven independent participants constitute more complex rational and information interfaces. According to the distance measurement of the three sites, the distances between the two component factories and the site are 45 km and 40 km, respectively. Due to the uncertainty of transportation conditions and high requirements of component protection, the logistics interfaces between the factory and the site are challenged.
In order to achieve the project objectives, some advanced technologies and management methods were adopted, many of which are effective for improving IM performance. For example, BIM is used in the project, and a large number of physical interface problems (more than ten interface conflicts between the ventilation ducts and the lintel and more than fifty physical interface conflicts between the precast partition seam and the electromechanical point) are found before the project construction. The standardized design method is adopted. The prefabricated component size is designed according to the principle of less specification and more combination. The physical interface between components has been designed as standardized as possible, which follows the requirements of safety, economy, and construction convenience. However, most physical interface connections still need to be performed by manual wet operation, and any change may cause large-scale rework. In the construction site, most of the installation procedures are also strictly standardized. The installation of prefabricated wall panels and stairs is broken down into several work packages that need to be strictly implemented. The finished wall column shall be checked for levelness and flatness, which provides a good interface environment for the follow-up work. Further, quick response code (QR code) technology was adopted in the delivery and transportation of components for tracking components in the process of transportation. The adoption of this technology, to a certain extent, promotes cooperation between the manufacturers and the construction site and improves the performance of the logistics interface.
It should be noted that the developers of this project rank in the top five among the real estate enterprises in China, sometimes even the first. The other participants in the project are all top enterprises in China, representing the highest level of PC in China. By assessing the IM performance of this project, some problems of PC in China can be revealed to a certain extent.

4.2. Data Collection

A group of six experts was invited to rate the importance of all indicators. The profiles of those experts are summarized in Table 4. Similar to Cong and Ma’s study (2018), the importance scores of indicators have values from 0 to 5, and the interval range is divided to determine the degree of the importance ([0, 1) = not important at all, [1, 2) = of little importance, [2, 3) = of average importance, [3, 4) = very important, [4, 5] = absolutely essential). For the sake of simplicity, all scores were taken as an integer multiple of 0.5, e.g., 1, 2.5, and 5. The second-level indicators U21, U22, U23, and U24 under U2 are used as examples to show the importance scores of these indicators, as shown in Table 5. E11, E12, E13, E14, E15, and E16 represent the six experts invited. Note that the measurement of the importance of indicators depends on the rich knowledge and experience of experts in this field. Academic professionals often have a deep understanding of the knowledge system and have experience in participating in investigation and research. Therefore, three of the six experts invited for weight determination are academic professionals. One of them has more than 20 years of experience in the field of PC research, participated in dozens of national projects, and cooperated with numerous enterprises in development projects.
In order to collect the data used for calculating the connection degree, another group of six experts were invited to assess the performance of all the second-level indicators, and their engineering practice experiences were focused. The profile of the experts is shown in Table 6.

4.3. Identification of Critical Factors and Establishment of Indicator System Based on Engineering Practice

To ensure the applicability of the indicator system to the project, four practitioners working on this residential construction project were invited to review the indicator system. This group of practitioners includes a general project manager from the client, a project manager, a site manager, and a design manager. The practitioners generally agreed with the indicator system established in this paper but made some amendments. The practitioners believed that the “distortion of information in transmission” is mainly affected by the degree of information standardization and sharing. There is no need to include this indicator in the indicator system as “standardization of information transmission and storage” (I21) and “degree of information sharing” (I23) are already included. Besides, the timeliness of information transmission is indeed an important indicator that was ignored by the original indicator system. Therefore, the “distortion of information in transmission” was replaced by “timeliness of information” (I22). “quality assurance of parts in transportation process” was considered to have little impact on the overall logistics interface of the project, mainly affecting on-site assembly work. Therefore, the indicator “quality assurance of parts in transportation process” was removed. The revised IM performance indicator system for the project is presented in Figure 2.

4.4. Application of the OWA-SPA Model

4.4.1. Calculation of Weights for Indicators

The importance score assigned by experts was used to calculate the weights of second-level indicators according to the OWA operator described in Section 3.2. The weights of all the second-level indicators are shown in Figure 2.

4.4.2. Calculation of Single-Indicator and Synthetic Connection Degrees

Based on the data collected from experts, the initial performance score of the second-level indicators was obtained by averaging the experts’ scores, as shown in Table 7. E21, E22, E23, E24, E25, and E26 represent the six invited experts.
According to the scale of performance measurement and Equation (6), the single-indicator connection degrees of IM performance indicators were calculated. Then, the scale of each IM performance indicator was determined according to the principle of maximum connection degree. The results are summarized in Table 8.
According to the weight of each indicator and the single-indicator connection degree of the IM performance indicators, the synthetic connection degree of each first-level indicator was obtained using Equation (8), shown in Table 9.

4.5. Results

As shown in Table 9, the performance of all indicators at the first level is rated as fair. Although the performance of the “physical interface” (I1) is described as “fair”, its connection degree with G2 is relatively low compared to the connection degrees of the other three interfaces. Therefore, it is necessary to look into the single-indicator connection degrees of the second-level indicators under the “physical interface” (I1). According to Table 8, two second-level indicators (I11 and I13) fall in G1 (Poor), three second-level indicators (I12, I14, and I17) fall in G2 (Fair), and the remaining two second-level indicators (I15 and I16) fall in G3 (Good). The performance of those seven indicators is relatively dispersed, resulting in the low connection degree between the “physical interface” and G2. Although the performance of “precision control of component manufacturing” (I15) and “accuracy of completed working surface” (I16) is good, the performance of the “physical interface” is still fair because of the poor performance of “design standardization degree” (I11) and “complexity of entity interfaces” (I13).
The performance of the “information interface” (I2) is rated as fair for its high connection degree with G2. However, the high connection degree with G3 should not be ignored. According to the single connection degrees shown in Table 8, all four indicators under the “information interface” show a high connection degree with G2; “timeliness of information in transmission” (I22), “degree of information sharing” (I23), and “integrity and accuracy of design information” (I24) show high connection degrees with G3. These indicate that the performance level of the “information interface” at “fair” has the possibility of moving to the next level of “good”. “standardization of information transmission and storage” (I21) shows the worst performance, which is the weak point of the information interface.
The “relational interface” (I3) is a reflection of the actual cooperative action between the participants at the interface and has a significant impact on the physical interface, information interface, and logistics interface. However, as shown in Table 9, its high connection with G2 reveals a “fair” performance level, and the low connection degree with other scales indicates a certain degree of stability. Therefore, it is unlikely to move from “fair” to “good” or “poor” for the performance of the “relational interface”. The connection degrees of subordinate indicators (I32, I33, and I35) with G2 confirm the above analysis. Nevertheless, “initiative for cooperation among participants” (I34) is highly connected with G3, which revealed the motivation of participants to strengthen cooperation. Actions must be taken to improve the performance of the “relational interface” to meet the expectations of all participants.
The “logistics interface” (I4) is also rated as “fair”, and its synthetic connection degree reveals a higher connection with G2 than other scales, indicating a certain degree of stability as well. Combined with the weights of the second-level indicators and the results of the single connection degree, “on-time delivery of component to the site” (I41) attracts more attention from experts than “tracking of components in the transportation process” (I42). However, the actual performance of the “on-time delivery of component to the site” (I41) is poorer than that of “tracking of components in the transportation process” (I42). This sharp contrast should be taken seriously.

5. Discussion

The “fair” performance levels of all the first-level indicators show that the IM of PC is not satisfactory. It is urgent to arouse people’s attention to IM for the PC project.
The IM performance of the “physical interface” is mainly reflected in the operational level. As the main influencing factor of the “physical interface”, standardization is always regarded as the most burning problem to be solved in the promotion of PC. Policies have been formulated to promote the standardization level of PC. However, in this case, standardization-related indicators (“design standardization degree” and “standardization degree of process interface”) show the poorest performance at “poor”. Moreover, the poor performance of “complexity of entity interface” indicates that interface complexity is a key barrier to the IM of PC. Precise component layering and simple interface design will be of great help to improve IM performance and even to the success of the whole project. It cannot be neglected that the “precision control of component manufacturing” is “good”, indicating that the factory manufacturing of components does improve the quality. However, the overall poor performance reveals that even if the quality of components had been improved through factory production, the PC project has not achieved good performance due to the low degree of standardization and high complexity of the interfaces.
For the “information interface”, the project under assessment has established a unified information platform and provided mobile internet terminal services in the construction. Managers and technicians can directly query project information using mobile devices, leading to a “good” performance for “timeliness of information transfer” and “integrity and accuracy of design information”. Imperfectly, the communication tools such as documents, telephones, and WeChat (similar to WhatsApp in the US, the most popular social app in China) are still important tools for information transmission in the actual construction process, resulting the performance of “standardization of information transmission and storage” staying at the “fair” level, affecting the overall performance of the “information interface”. What is more, the limited “degree of information sharing” due to participants’ protection of core knowledge is also an important factor hindering the performance improvement of the “information interface”.
The “fair” performance of the “relational interface” responds to the research hotspots in the field of cooperative relations in recent years. China has long followed the traditional construction techniques used to decompose the work into independent work packages. Participants are independent of each other and persist in pursuing the maximization of one-sided interests. However, the work tasks at the interface are neglected, and good cooperative relationships cannot be formed between participants. This construction mode divides the integration of the construction process. Despite the continuous learning of the advanced integrated delivery model, engineer procure construct (EPC), design bid (DB), and integrated project delivery (IPD) from developed western countries in recent years, it is hard to develop a stable long-term cooperative relationship among participants because of the long-term inherent sense of separation, resulting in poor performance in the distribution of interests, conflict of goals, and so on. This is confirmed by the poor performance level of indicators such as “clarity of contract responsibility, power and interest” and “conflict of goals” in the case study.
Although there are only two secondary indicators in the logistics interface, the performance is thought-provoking. Viewed from the proportion of weight, “on-time delivery of component to the site” is twice as important as “tracking of components in the transportation process”, but the performance of “on-time delivery of component to the site” is worse than “tracking of components in the transportation process”. To explain this phenomenon, the authors discussed it with experts involved in the research. For PC, component production planning needs to be decided as early as possible to ensure on-site supply. The traditional supply chain has not been completely transformed to adapt to this change. However, the adoption of QR code technology in this project made “tracking of components in the transportation process” achieve a good performance.

6. Conclusions

The IM of the PC projects is a complex, uncertain system, and IM performance is not dependent on a single source but instead on a complex system of disparate factors. In this study, a conceptual IM performance assessment framework was constructed by reviewing existing literature and using the SPA model. The assessment results provided by the framework give managers helpful guidance as they take action to improve the performance of PC projects.
This study advances previous studies as follows. First, given the insufficiency of the literature in evaluating the performance of IM, this study systematically reviewed the relevant literature on IM in PC and identified 19 factors affecting the IM performance. These factors were further grouped into four categories, which provide a better understanding of the factors affecting IM performance. Second, considering that the previous performance assessment methods cannot adequately consider the uncertainty, the SPA was introduced into this study. The SPA model can fully consider the relationship between IM performance indicators and performance level and determine the membership degree of indicators to performance level. It can not only improve the accuracy of performance assessment but can also predict the development trend of performance. Thirdly, because of the expert scoring method used in this study, subjectivity is inevitable. The OWA operator used in the assessment framework can reduce the impact of extreme values in the expert scoring process to ensure the objectivity of assessment results.
The proposed framework is a useful tool that helps project management teams to improve IM performance in different types of PC projects. It can help managers (1) identify factors that affect IM, (2) measure the influence of influencing factors on the performance of IM, (3) predict the development trend of IM performance, and (4) recognize the main issues for improvement for promoting the IM performance.
The case analysis shows an unsatisfactory IM performance level according to the fair performance of all the first-level indicators, which echoes the late development of PC in China and less application of IM. Other analyses also show that the assessment results can reflect the actual IM issues caused by the policy and project management level, verifying the feasibility and applicability of the assessment framework. Besides, the assessment model can be applied to different PC projects by modifying the indicator system in light of the characteristics of projects, reflecting the possibility of migration and application of the assessment framework.
Although the developed assessment framework can identify the problems of IM in case projects, this project does not represent all projects in China. In the future, more case samples can be used to obtain the general situation of IM practices for PC. Meanwhile, the SPA model application in this paper is not limited to IM performance assessment and can be migrated to more complex and uncertain projects.

Author Contributions

Conceptualization, S.Z. and Z.L.; methodology, S.Z.; validation, Z.L.; formal analysis, M.Y.; investigation, S.Z. and M.Y.; resources, S.Z.; data curation, M.Y.; writing—original draft, L.L.; writing—review and editing, S.Z. and L.L. All authors have read and agreed to the published version of the manuscript.

Funding

This research was funded by the National Natural Science Foundation of China, grant number 72071027, the Shandong Provincial Natural Science Foundation, grant number ZR202102220230, and the National Key Research and Development Project of the 13th Five-Year plan, grant number 2018YFC0705900.

Institutional Review Board Statement

Ethical review and approval were waived for this study, due to this study takes the construction projects as the research object, and the questionnaire survey method adopted in this study is mainly to obtain the opinions of engineers and scholars on the construction engineering issues, which does not involve any ethical issues related to humans or animals.

Informed Consent Statement

Not applicable.

Data Availability Statement

Some or all data generated or used during the study are available from the corresponding author by request. (List items).

Conflicts of Interest

The authors declare no conflict of interest.

References

  1. Agren, R.; Wing, R.D. Five moments in the history of industrialized building. Constr. Manag. Econ. 2014, 32, 7–15. [Google Scholar] [CrossRef]
  2. Pan, W.; Gibb, A.G.F.; Dainty, A.R.J.; Asce, M. Strategies for Integrating the Use of Off-Site Production Technologies in House Building. J. Constr. Eng. Manag. 2012, 138, 1331–1340. [Google Scholar] [CrossRef] [Green Version]
  3. Yuan, M.; Li, Z.; Li, X.; Li, L.; Zhang, S.; Luo, X. How to promote the sustainable development of prefabricated residential buildings in China: A tripartite evolutionary game analysis. J. Clean. Prod. 2022, 349, 131423. [Google Scholar] [CrossRef]
  4. Sacks, R.; Eastman, C.M.; Lee, G. Process model perspectives on management and engineering procedures in the precast/prestressed concrete industry. J. Constr. Eng. Manag. 2004, 130, 206–215. [Google Scholar] [CrossRef] [Green Version]
  5. Zhang, S.; Li, Z.; Ning, X.; Li, L. Gauging the impacts of urbanization on CO2 emissions from the construction industry: Evidence from China. J. Environ. Manag. 2021, 288, 112440. [Google Scholar] [CrossRef] [PubMed]
  6. Cao, X.; Li, X.; Zhu, Y.; Zhang, Z. A comparative study of environmental performance between prefabricated and traditional residential buildings in China. J. Clean. Prod. 2015, 109, 131–143. [Google Scholar] [CrossRef]
  7. Wong, P.S.P.; Zwar, C.; Gharaie, E. Examining the Drivers and States of Organizational Change for Greater Use of Prefabrication in Construction Projects. J. Constr. Eng. Manag. 2017, 143, 1–9. [Google Scholar] [CrossRef]
  8. Zhang, S.; Li, Z.; Li, T.; Yuan, M. A holistic literature review of building information modeling for prefabricated construction. J. Civ. Eng. Manag. 2021, 27, 485–499. [Google Scholar] [CrossRef]
  9. Yin, X.; Liu, H.; Chen, Y.; Al-Hussein, M. Building information modelling for off-site construction: Review and future directions. Autom. Constr. 2019, 101, 72–91. [Google Scholar] [CrossRef]
  10. Luo, L.Z.; Mao, C.; Shen, L.Y.; Li, Z.D. Risk factors affecting practitioners’ attitudes toward the implementation of an industrialized building system a case study from China. Eng. Constr. Archit. Manag. 2015, 22, 622–643. [Google Scholar] [CrossRef]
  11. Yuan, M.; Li, Z.; Li, X.; Luo, X. Managing stakeholder-associated risks and their interactions in the life cycle of prefabricated building projects: A social network analysis approach. J. Clean. Prod. 2021, 323, 129102. [Google Scholar] [CrossRef]
  12. Li, C.Z.; Xu, X.; Shen, G.Q.; Fan, C.; Li, X.; Hong, J. A model for simulating schedule risks in prefabrication housing production: A case study of six-day cycle assembly activities in Hong Kong. J. Clean. Prod. 2018, 185, 366–381. [Google Scholar] [CrossRef]
  13. Hassim, S.; Jaafar, M.S.; Sazalli, S.A.A.H. The contractor perception towers Industrialised building system risk in construction projects in Malaysia. Am. J. Appl. Sci. 2009, 6, 937–942. [Google Scholar] [CrossRef] [Green Version]
  14. Pheng, L.S.; Chuan, C.J. Just-in-time management in precast concrete construction: A survey of the readiness of main contractors in Singapore. Integr. Manuf. Syst. 2001, 12, 416–429. [Google Scholar] [CrossRef]
  15. Jonsson, H.; Rudberg, M. Classification of production systems for industrialized building: A production strategy perspective. Constr. Manag. Econ. 2014, 32, 53–69. [Google Scholar] [CrossRef]
  16. Glass, J.; Pepper, C. Perceptions of Precast Concrete Cladding in the UK Market. Archit. Eng. Des. Manag. 2005, 1, 233–246. [Google Scholar] [CrossRef]
  17. Larsson, J.; Eriksson, P.E.; Olofsson, T.; Simonsson, P. Industrialized construction in the Swedish infrastructure sector: Core elements and barriers. Constr. Manag. Econ. 2014, 32, 83–96. [Google Scholar] [CrossRef]
  18. Goodier, C.; Gibb, A. Future opportunities for offsite in the UK. Constr. Manag. Econ. 2007, 25, 585–595. [Google Scholar] [CrossRef] [Green Version]
  19. Li, L.; Li, Z.; Wu, G.; Li, X. Critical success factors for project planning and control in prefabrication housing production: A China study. Sustainability 2018, 10, 836. [Google Scholar] [CrossRef] [Green Version]
  20. Nadim, W.; Goulding, J.S. Offsite production: A model for building down barriers A European construction industry perspective. Eng. Constr. Archit. Manag. 2011, 18, 82–101. [Google Scholar] [CrossRef]
  21. Ramaji, I.J.; Memari, A.M. Extending the current model view definition standards to support multi-storey modular building projects. Archit. Eng. Des. Manag. 2018, 14, 158–176. [Google Scholar] [CrossRef]
  22. Yuan, M.; Li, Z.; Li, X.; Luo, X.; Yin, X.; Cai, J. Proposing a multifaceted model for adopting prefabricated construction technology in the construction industry. Eng. Constr. Archit. Manag. 2021. [Google Scholar] [CrossRef]
  23. Gao, S.; Low, S.P.; Nair, K. Design for manufacturing and assembly (DfMA): A preliminary study of factors influencing its adoption in Singapore. Archit. Eng. Des. Manag. 2018, 14, 440–456. [Google Scholar] [CrossRef]
  24. Ballard, G.; Harper, N.; Zabelle, T. Learning to see work flow: An application of lean concepts to precast concrete fabrication. Eng. Constr. Archit. Manag. 2003, 10, 6–14. [Google Scholar] [CrossRef]
  25. Shokri, S.; Ahn, S.; Lee, S.; Haas, C.T.; Haas, R.C.G. Current Status of Interface Management in Construction: Drivers and Effects of Systematic Interface Management. J. Constr. Eng. Manag. 2016, 142, 04015070. [Google Scholar] [CrossRef]
  26. Zhang, S.; Li, Z.; Ma, S.; Li, L.; Yuan, M. Critical Factors Influencing Interface Management of Prefabricated Building Projects: Evidence from China. Sustainability 2022, 14, 5418. [Google Scholar] [CrossRef]
  27. Ahn, S.; Shokri, S.; Lee, S.; Haas, C.T.; Haas, R.C.G. Exploratory Study on the Effectiveness of Interface-Management Practices in Dealing with Project Complexity in Large-Scale Engineering and Construction Projects. J. Manag. Eng. 2016, 33, 0401603901–0401603912. [Google Scholar] [CrossRef]
  28. Lin, Y.C. Construction network-based interface management system. Autom. Constr. 2013, 30, 228–241. [Google Scholar] [CrossRef]
  29. Chua, D.K.; Godinot, M. Use of a WBS Matrix to Improve Interface Management in Projects. J. Constr. Eng. Manag. 2006, 132, 67–79. [Google Scholar] [CrossRef]
  30. Eray, E.; Sanchez, B.; Haas, C. Usage of interface management system in adaptive reuse of buildings. Buildings 2019, 9, 105. [Google Scholar] [CrossRef] [Green Version]
  31. Lin, Y.-C. Use of Bim Approach To Enhance Construction Interface Management: A Case Study. J. Civ. Eng. Manag. 2015, 21, 201–217. [Google Scholar] [CrossRef]
  32. Pavitt, T.C.; Gibb, A.G. Interface Management within Construction: In Particular, Building Facade. J. Constr. Eng. Manag. 2003, 129, 8–15. [Google Scholar] [CrossRef]
  33. Kieran, S.; Timberlake, J. Refabricating Architecture: How Manufacturing Methodologies Are Poised to Transform Building Construction; McGraw-Hill Education: New York, NY, USA, 2003. [Google Scholar]
  34. Isaac, S.; Bock, T.; Stoliar, Y. A new approach to building design modularization. Procedia Eng. 2014, 85, 274–282. [Google Scholar] [CrossRef]
  35. Viana, D.D. Integrated Production Planning and Control Model for Engineer-To-Order Prefabricated Building Systems. Ph.D. Thesis, Universidade Federal do Rio Grande do Sul, Farroupilha, Brazil, 2015. [Google Scholar]
  36. Tillmann, P.; Viana, D.; Sargent, Z.; Tommelein, I.; Formoso, C. Bim and lean in the design-production interface of eto components in complex projects. In Proceedings of the IGLC 23—23rd Annual Conference of the International Group for Lean Construction: Global Knowledge—Global Solutions, Perth, WA, Australia, 29–31 July 2015; pp. 331–340. [Google Scholar]
  37. Pavitt, T.C.; Gibb, A.G.F. Managing Organizational Interfaces In The Cladding Supply Chain: Initial Results From Expert Interviews. In Proceedings of the 15th Annual ARCOM Conference, Liverpool, UK, 15–17 September 1999; Hughes, W., Ed.; Association of Researchers in Construction Management: Liverpool, UK, 1999; pp. 519–528. [Google Scholar]
  38. Wren, D.A. Interface and Interorganizational Coordination. Acad. Manag. J. 2018, 10, 69–81. [Google Scholar]
  39. Shokri, S.; Haas, C.T.; Haas, G.; Lee, S.H. Interface-Management Process for Managing Risks in Complex Capital Projects. J. Constr. Eng. Manag. 2015, 142, 040150691–0401506912. [Google Scholar] [CrossRef]
  40. CII (Construction Industry Institute). Interface Management Implementation Guide (IMIGe); Construction Industry Institute: Austin, TX, USA, 2014. [Google Scholar]
  41. Crumrine, T.; Nelson, R.; Cordeiro, C.; Loudermilk, M.; Malbrel, C.A. Interface Management for Subsea Sand Control Completion Systems. In Proceedings of the SPE Latin American and Caribbean Petroleum Engineering Conference, Rio de Janeiro, Brazil, 20–23 June 2005; Society of Petroleum Engineers: Rio de Janeiro, Brazil, 2005; pp. 1–11. [Google Scholar]
  42. Morris, P.W.G. Managing Project Interfaces—Key Points for Project Success. In Project Management Handbook; Cleland, D.I., King, W.R., Eds.; John Wiley & Sons, Inc: New York, NY, USA, 1983; pp. 16–55. [Google Scholar]
  43. Chan, W.T.; Chen, C.; Messner, J.I.; Chua, D.K. Interface Management for China’s Build–Operate–Transfer Projects. J. Constr. Eng. Manag. 2005, 131, 645–655. [Google Scholar] [CrossRef]
  44. Schmidt, M.; Thoroe, L.; Schumann, M. RFID and Barcode in Manufacturing Logistics: Interface Concept for Concurrent Operation. Inf. Syst. Manag. 2013, 30, 100–115. [Google Scholar] [CrossRef]
  45. Healey, P. Interfaces. In Project Management: Getting the Job Done on Time and in Budget; Butterworth-Heinemann: London, UK, 1997; pp. 267–278. ISBN 9780080943398008094339X. [Google Scholar]
  46. Siao, F.-C.; Shu, Y.-C.; Lin, Y.-C. Interface Management Practices in Taiwan Construction Project. In Proceedings of the 28th International Symposium on Automation and Robotics in Construction (ISARC 2011), Seoul, Korea, 29 June—2 July 2011; The International Association for Automation and Robotics in Construction: Seoul, Korea, 2017; pp. 947–952. [Google Scholar]
  47. Fellows, R.; Liu, A.M.M. Managing organizational interfaces in engineering construction projects: Addressing fragmentation and boundary issues across multiple interfaces. Constr. Manag. Econ. 2012, 30, 653–671. [Google Scholar] [CrossRef] [Green Version]
  48. Bititci, U.S.; Carrie, A.S.; McDevitt, L. Integrated performance measurement systems: A development guide. Int. J. Oper. Prod. Manag. 1997, 17, 522–535. [Google Scholar] [CrossRef]
  49. Pulakos, E.D.; O’Leary, R.S. Why Is Performance Management Broken? Ind. Organ. Psychol. 2011, 4, 146–164. [Google Scholar] [CrossRef]
  50. Yun, S.; Mulva, S.P.; O’Brien, W.J. A Quantitative Approach for Measuring Managerial Interfaces in the Development of a Capital Project. In Proceedings of the Construction Research Congress 2012, West Lafayette, IN, USA, 21–23 May 2012; American Society of Civil Engineers: West Lafayette, IN, USA, 2012; pp. 1410–1419. [Google Scholar]
  51. Du, Y.; Liang, Y. Research on performance assessment of R&D—Marketing Interface Management in enterprise innovation. Mod. Manag. Sci. 2007, 10, 3–6. [Google Scholar]
  52. Xu, F. A research on the evaluation of the effectiveness for enterprise technological innovative interface. In Proceedings of the 2010 3rd International Conference on Information Management, Innovation Management and Industrial Engineering, ICIII 2010, Washington, DC, USA, 26–28 November 2010; pp. 604–607. [Google Scholar]
  53. Dong, Y. A Study on the Performance Improvement of Research and Development-Manufacturing Interface Management in the Company New Product Development Process. Ph.D. Thesis, Fudan University, Shanghai, China, 2013. [Google Scholar]
  54. Jellicorse, J.J.; Rahman, S.A. Assessment of the ORION-SLS Interface Management process in achieving THE EIA 731.1 systems engineering capability model generic practices Level 3 criteria. In Proceedings of the AIAA Space 2016, Long Beach, CA, USA, 13–16 September 2016; pp. 1–16. [Google Scholar]
  55. Senthilkumar, V.; Varghese, K. Case study-based testing of design interface management system. J. Manag. Eng. 2013, 29, 279–288. [Google Scholar] [CrossRef]
  56. Fei, C.; Guoping, L.; Ni, Y. Interface Performance Reserch Approch and Appliance in Urban Sustainable Development Based on HDI. Soft Sci. 1984, 29, 6–10. [Google Scholar]
  57. Gleich, R.; Motwani, J.; Wald, A. Process benchmarking: A new tool to improve the performance of overhead areas. Benchmarking Int. J. 2008, 15, 242–256. [Google Scholar] [CrossRef]
  58. Fayek, A.R.; Sun, Z. A fuzzy expert system for design performance prediction and evaluation. Can. J. Civ. Eng. 2011, 28, 1–25. [Google Scholar] [CrossRef]
  59. Sun, C.C. A performance evaluation model by integrating fuzzy AHP and fuzzy TOPSIS methods. Expert Syst. Appl. 2010, 37, 7745–7754. [Google Scholar] [CrossRef]
  60. Chao, L.C.; Hsiao, C.S. Fuzzy model for predicting project performance based on procurement experiences. Autom. Constr. 2012, 28, 71–81. [Google Scholar] [CrossRef]
  61. Fullerton, R.R.; Wempe, W.F. Lean manufacturing, non-financial performance measures, and financial performance. Int. J. Oper. Prod. Manag. 2009, 29, 214–240. [Google Scholar] [CrossRef]
  62. Shen, W.; Choi, B.; Lee, S.; Tang, W.; Haas, C.T. How to Improve Interface Management Behaviors in EPC Projects: Roles of Formal Practices and Social Norms. J. Manag. Eng. 2018, 34, 1–12. [Google Scholar] [CrossRef]
  63. Klir, G.J.; Yuan, B. Fuzzy Sets and Fuzzy Logic: Theory and Applications; Prentice Hall: Hoboken, NJ, USA, 1996; ISBN 0-13-101171-5. [Google Scholar]
  64. Zhao, J.; Li, K.; Wang, M.; Jinghan, S. Construction Risk Assessment of Subway Construction Project Based on Set Pair Analysis. J. Civ. Eng. Manag. 2017, 34, 10–16. [Google Scholar]
  65. Garg, H.; Kumar, K. An advanced study on the similarity measures of intuitionistic fuzzy sets based on the set pair analysis theory and their application in decision making. Soft Comput. 2018, 22, 4959–4970. [Google Scholar] [CrossRef]
  66. Zhao, K.Q. Set pair and set pair analysis-a new concept and systematic analysis method. Proc. Natl. Conf. Syst. Theory Reg. Plan. 1989, 5, 87–91. [Google Scholar]
  67. Zhao, Y.; Wang, Y. On Evaluation Methodology for the Performance of Engineering Project Management Based on 5-element Set Pair Analysis. Appl. Mech. Mater. 2012, 228, 2258–2262. [Google Scholar] [CrossRef]
  68. Liu, H.T.; Tsai, Y. lin A fuzzy risk assessment approach for occupational hazards in the construction industry. Saf. Sci. 2012, 50, 1067–1078. [Google Scholar] [CrossRef]
  69. Yang, T.; Kuo, C. A hierarchical AHP/DEA methodology for the facilities layout design problem. Eur. J. Oper. Res. 2003, 147, 128–136. [Google Scholar] [CrossRef]
  70. Zhang, Y.; Shen, J.; Ding, F.; Li, Y.; He, L. Vulnerability assessment of atmospheric environment driven by human impacts. Sci. Total Environ. 2016, 571, 778–790. [Google Scholar] [CrossRef]
  71. Xu, Z.S.; Chen, J. An interactive method for fuzzy multiple attribute group decision making. Inf. Sci. 2007, 177, 248–263. [Google Scholar] [CrossRef]
  72. Chang, K.H.; Cheng, C.H. Evaluating the risk of failure using the fuzzy OWA and DEMATEL method. J. Intell. Manuf. 2011, 22, 113–129. [Google Scholar] [CrossRef]
  73. Cong, X.; Ma, L. Performance Evaluation of Public-Private Partnership Projects from the Perspective of Efficiency, Economic, Effectiveness, and Equity: A Study of Residential Renovation Projects in China. Sustainability 2018, 10, 1951. [Google Scholar] [CrossRef] [Green Version]
  74. O’Connor, J.T.; O’Brien, W.J.; Choi, J.O. Industrial Project Execution Planning: Modularization versus Stick-Built. Pract. Period. Struct. Des. Constr. 2016, 21, 1–11. [Google Scholar] [CrossRef]
  75. McCarney, M. Interface Management of Offsite Bathroom Construction: Process and People Factors. Ph.D. Thesis, Loughborough University, Leicestershire, UK, 2017. [Google Scholar]
  76. Chen, Q.; Reichard, G.; Beliveau, Y. Multiperspective Approach to Exploring Comprehensive Cause Factors for Interface Issues. J. Constr. Eng. Manag. 2008, 134, 432–441. [Google Scholar] [CrossRef]
  77. Li, L.; Li, Z.; Li, X.; Zhang, S.; Luo, X. A new framework of industrialized construction in China: Towards on-site industrialization. J. Clean. Prod. 2020, 244, 118469. [Google Scholar] [CrossRef]
  78. Gibb, A.G.F. Standardization and pre-assembly- distinguishing myth from reality using case study research. Constr. Manag. Econ. 2001, 19, 307–315. [Google Scholar] [CrossRef] [Green Version]
  79. Thuesen, C.; Hvam, L. Efficient on-site construction: Learning points from a German platform for housing. Constr. Innov. 2011, 11, 338–355. [Google Scholar] [CrossRef]
  80. Yashiro, T. Conceptual framework of the evolution and transformation of the idea of the industrialization of building in Japan. Constr. Manag. Econ. 2014, 32, 16–39. [Google Scholar] [CrossRef]
  81. Blismas, N.G.; Pendlebury, M.; Gibb, A.G.F.; Pasquire, C. Constraints to the use of Off-site production on construction projects. Archit. Eng. Des. Manag. 2005, 1, 153–162. [Google Scholar] [CrossRef] [Green Version]
  82. Gann, D.M. Construction as a manufacturing process? Similarities and differences between industrialized housing and car production in Japan. Constr. Manag. Econ. 1996, 14, 437–450. [Google Scholar] [CrossRef]
  83. Kim, M.K.; Cheng, J.C.P.; Sohn, H.; Chang, C.C. A framework for dimensional and surface quality assessment of precast concrete elements using BIM and 3D laser scanning. Autom. Constr. 2015, 49, 225–238. [Google Scholar] [CrossRef]
  84. Kim, M.K.; Wang, Q.; Park, J.W.; Cheng, J.C.P.; Sohn, H.; Chang, C.C. Automated dimensional quality assurance of full-scale precast concrete elements using laser scanning and BIM. Autom. Constr. 2016, 72, 102–114. [Google Scholar] [CrossRef]
  85. Wang, Q.; Kim, M.-K.; Cheng, J.C.P.; Sohn, H. Automated quality assessment of precast concrete elements with geometry irregularities using terrestrial laser scanning. Autom. Constr. 2016, 68, 170–182. [Google Scholar] [CrossRef]
  86. Lu, W.; Chen, K.; Xue, F.; Pan, W. Searching for an optimal level of prefabrication in construction: An analytical framework. J. Clean. Prod. 2018, 201, 236–245. [Google Scholar] [CrossRef]
  87. Liang, H.; Zhang, S.; Su, Y. Evaluating the Efficiency of Industrialization Process in Prefabricated Residential Buildings Using a Fuzzy Multicriteria Decision—Making Method. Math. Probl. E 2017, 2017, 1–12. [Google Scholar] [CrossRef] [Green Version]
  88. Xie, C. A Research on the Interface Structure of Hotel’s Customer Service System: The Theory Construction based on the Literature Reviews and Method of Focus Groups. J. Beijing Int. Stud. Univ. 2010, 17, 1–8. [Google Scholar]
  89. Sacks, R.; Akinci, B.; Ergen, E. 3D Modeling and Real-Time Monitoring in Support of Lean Production of Engineered-To-Order Precast Concrete. In Proceedings of the 11th Annual Conference of the International Group for Lean Construction, Blacksburg, VA, USA, 22–24 July 2003. [Google Scholar]
  90. Ezcan, V.; Isikdag, U.; Goulding, J.S. BIM and Off-Site Manufacturing: Recent Research and Opportunities. Pap. Present. 19th CIB World Build. Congr. Brisbane. Aust. 2013, 1, 11. [Google Scholar]
  91. Tang, X.; Chong, H.-Y.; Zhang, W. Relationship between BIM Implementation and Performance of OSM Projects. J. Manag. Eng. 2019, 35, 04019019. [Google Scholar] [CrossRef]
  92. Patlakas, P.; Livingstone, A.; Hairstans, R.; Neighbour, G. Automatic code compliance with multi-dimensional data fitting in a BIM context. Adv. Eng. Inform. 2018, 38, 216–231. [Google Scholar] [CrossRef] [Green Version]
  93. Yang, J.; Duan, J.; Chen, J.; Zhou, J. Study on Construction Management of Urban Utility Tunnel PPP Project Based on Interface Theory. Urban Roads Bridg. Flood Control 2019, 19, 151–156. [Google Scholar]
  94. Abanda, F.H.; Tah, J.H.M.; Cheung, F.K.T. BIM in off-site manufacturing for buildings. J. Build. Eng. 2017, 14, 89–102. [Google Scholar] [CrossRef] [Green Version]
  95. Zhong, R.Y.; Peng, Y.; Xue, F.; Fang, J.; Zou, W.; Luo, H.; Thomas Ng, S.; Lu, W.; Shen, G.Q.P.; Huang, G.Q. Prefabricated construction enabled by the Internet-of-Things. Autom. Constr. 2017, 76, 59–70. [Google Scholar] [CrossRef]
  96. Chen, K.; Lu, W.; Peng, Y.; Rowlinson, S.; Huang, G.Q. Bridging BIM and building: From a literature review to an integrated conceptual framework. Int. J. Proj. Manag. 2015, 33, 1405–1416. [Google Scholar] [CrossRef] [Green Version]
  97. He, Q.; Li, Y.; Peng, Y.; Zhou, S. Construction Project Management Information. In Proceedings of the Academy of Management 2008 Annual Meeting: The Questions We Ask, Anahcim, CA, USA, 8–13 August 2008; China Architecture Publishing & Meia Co., Ltd.: Beijing, China, 2011; pp. 198–199. [Google Scholar]
  98. Xue, X.; Zhang, X.; Wang, L.; Skitmore, M.; Wang, Q. Analyzing collaborative relationships among industrialized construction technology innovation organizations: A combined SNA and SEM approach. J. Clean. Prod. 2018, 173, 265–277. [Google Scholar] [CrossRef] [Green Version]
  99. Larsson, B.; Sundqvist, J.; Emmitt, S.; Larsson, B.; Sundqvist, J.; Emmitt, S. Component manufacturers ’ perceptions of managing innovation. Build. Res. Inf. 2006, 34, 37–41. [Google Scholar] [CrossRef]
  100. Li, C.Z.; Hong, J.; Xue, F.; Shen, G.Q.; Xu, X.; Luo, L. SWOT analysis and Internet of Things-enabled platform for prefabrication housing production in Hong Kong. Habitat Int. 2016, 57, 74–87. [Google Scholar] [CrossRef]
  101. McCarney, M.; Gibb, A.G.F. Interface management from an offsite construction perspective. In Proceedings of the 28th Annual Conference, Orlando, FL, USA, 3–7 December 2012; Association of Researchers in Construction Management: Edinburgh, UK, 2012; pp. 775–784. [Google Scholar]
  102. Li, C.Z.; Hong, J.; Xue, F.; Shen, G.Q.; Xu, X.; Mok, M.K. Schedule risks in prefabrication housing production in Hong Kong: A social network analysis. J. Clean. Prod. 2016, 134, 482–494. [Google Scholar] [CrossRef] [Green Version]
  103. Hwang, B.G.; Shan, M.; Looi, K.Y. Key constraints and mitigation strategies for prefabricated prefinished volumetric construction. J. Clean. Prod. 2018, 183, 183–193. [Google Scholar] [CrossRef]
  104. Bortolini, R.; Formoso, C.T.; Viana, D.D. Site logistics planning and control for engineer-to-order prefabricated building systems using BIM 4D modeling. Autom. Constr. 2019, 98, 248–264. [Google Scholar] [CrossRef]
  105. Li, X.; Shen, G.Q.; Wu, P.; Yue, T. Integrating Building Information Modeling and Prefabrication Housing Production. Autom. Constr. 2019, 100, 46–60. [Google Scholar] [CrossRef]
  106. Zhai, Y.; Chen, K.; Zhou, J.X.; Cao, J.; Lyu, Z.; Jin, X.; Shen, G.Q.P.; Lu, W.; Huang, G.Q. An Internet of Things-enabled BIM platform for modular integrated construction: A case study in Hong Kong. Adv. Eng. Inform. 2019, 42, 100997. [Google Scholar] [CrossRef]
  107. Babich, V.; Kouvelis, P. Introduction to the special issue on research at the interface of finance, operations, and risk management (iFORM): Recent contributions and future directions. Manuf. Serv. Oper. Manag. 2018, 20, 1–18. [Google Scholar] [CrossRef] [Green Version]
  108. Wang, Z.; Hu, H.; Gong, J.; Ma, X.; Xiong, W. Precast supply chain management in off-site construction: A critical literature review. J. Clean. Prod. 2019, 232, 1204–1217. [Google Scholar] [CrossRef]
  109. Yager, R.R. Families of OWA operators. Fuzzy Sets Syst. 1993, 59, 125–148. [Google Scholar] [CrossRef]
  110. Filev, D.; Yager, R.R. Analytic properties of maximum entropy OWA operators. Inf. Sci. 1995, 85, 11–27. [Google Scholar] [CrossRef]
  111. Paternain, D.; Ochoa, G.; Lizasoain, I.; Bustince, H.; Mesiar, R. Quantitative orness for lattice OWA operators. Inf. Fusion 2016, 30, 27–35. [Google Scholar] [CrossRef]
  112. Chen, W.; Zhang, S.; Wang, H.; Li, M. Decision Making of Prefabricated Building Construction Scheme Based on Vector Included Angle Cosine. J. Civ. Eng. Manag. 2017, 34, 71–76. [Google Scholar]
  113. Zou, Q.; Zhou, J.; Zhou, C.; Song, L.; Guo, J. Comprehensive flood risk assessment based on set pair analysis-variable fuzzy sets model and fuzzy AHP. Stoch. Environ. Res. Risk Assess. 2013, 27, 525–546. [Google Scholar] [CrossRef]
  114. Wang, T.; Chen, J.-S.; Wang, T.; Wang, S. Entropy weight-set pair analysis based on tracer techniques for dam leakage investigation. Nat. Hazards 2015, 76, 747–767. [Google Scholar] [CrossRef]
  115. Shen, J.; Zhang, Y.; Zhang, S. Risk Evaluation of Engineering Project Interface Based on G-COWA. J. Civ. Eng. Manag. 2016, 33, 16–21. [Google Scholar]
Figure 1. The research flow for model development.
Figure 1. The research flow for model development.
Buildings 12 00631 g001
Figure 2. Indicators factors affecting IM performance with local weights.
Figure 2. Indicators factors affecting IM performance with local weights.
Buildings 12 00631 g002
Table 2. The scales for performance measurement.
Table 2. The scales for performance measurement.
ScaleSemanticsScore Interval
G1poor[0, 5]
G2fair(5, 7]
G3good(7, 9]
G4excellent(9, 10]
Table 3. Calculation of single-indicator connection degree.
Table 3. Calculation of single-indicator connection degree.
IndicatorsG1G2G3G4
x 11 μ 111 μ 112 μ 113 μ 114
x 12 μ 121 μ 122 μ 123 μ 124
x 13 μ 131 μ 132 μ 133 μ 134
x 1 m μ 1 m 1 μ 1 m 2 μ 1 m 3 μ 1 m 4
Table 4. Profile of the experts invited to weight the indicators.
Table 4. Profile of the experts invited to weight the indicators.
Interviewee NO.PositionYears of Working Experience Related to PC
1Professor10
2Professor21
3Associate Professor7
4Senior engineer from a private developer5
5A chief manager from a private contractor8
6A senior structural engineer from a design institute7
Table 5. The importance score of U21, U22, U23, and U24.
Table 5. The importance score of U21, U22, U23, and U24.
E11E12E13E14E15E16
U2144.544.54.54.5
U2223.54444.5
U233.53.53.554.54.5
U2444.54.54.544
Table 6. Profile of the experts invited to access the performance of all the second-level indicators.
Table 6. Profile of the experts invited to access the performance of all the second-level indicators.
Interviewee NO.TitleRepresented Stakeholder in the ProjectFamiliarity with the ProjectYears of Working Experience
1Associate ProfessorConsultantFamiliar7
2Project managerClientVery familiar6
3Senior engineerMain contractorVery familiar15
4Project managerMain contractorVery familiar5
5Design managerDesign consultantVery familiar9
6Consulting engineerSupervision CompanyVery familiar4
Table 7. The initial performance scores of the IM performance indicators.
Table 7. The initial performance scores of the IM performance indicators.
E21E22E23E24E25E26Average Score
I1113.53.533.532.92
I12576.566.566.17
I134.535334.53.83
I145655.55.545.17
I15988.5898.58.50
I167.56.57.5877.57.33
I174.5766.5666.00
I215.55.5646.55.55.50
I227.576.577.577.08
I2376.575.576.56.58
I247.5776.57.577.08
I3176.56.5565.56.08
I32665.5655.55.67
I336.55.5655.565.75
I34877.5887.57.67
I355.56.555.557.55.83
I4165.5455.54.55.08
I4277.56.587.57.57.33
Table 8. The single-indicator connection degree of IM performance indicators.
Table 8. The single-indicator connection degree of IM performance indicators.
G1G2G3G4Performance Scale
I111.0000.167−1.000−1.000G1
I12−0.1671.0000.167−1.000G2
I131.0000.533−1.000−1.000G1
I140.8331.000−0.833−1.000G2
I15−1.000−0.5001.0000.500G3
I16−1.0000.6671.000−0.667G3
I170.0001.0000.000−1.000G2
I210.5001.000−0.500−1.000G2
I22−1.0000.9171.000−0.917G3
I23−0.5831.0000.583−1.000G2
I24−1.0000.9171.000−0.917G3
I31−0.0831.0000.083−1.000G2
I320.3331.000−0.333−1.000G2
I330.2501.000−0.250−1.000G2
I34−1.0000.3301.000−0.333G3
I350.1671.000−0.167−1.000G2
I410.9171.000−0.917−1.000G2
I42−1.0000.6701.000−0.667G3
Table 9. The synthetic connection degree of each first-level indicator.
Table 9. The synthetic connection degree of each first-level indicator.
G1G2G3G4Performance Scale
I10.1360.546−0.136−0.752G2
I2−0.4980.9600.498−0.960G2
I3−0.0260.9030.026−0.903G2
I40.1850.874−0.185−0.874G2
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Share and Cite

MDPI and ACS Style

Zhang, S.; Li, Z.; Li, L.; Yuan, M. Interface Management Performance Assessment Framework for Sustainable Prefabricated Construction. Buildings 2022, 12, 631. https://doi.org/10.3390/buildings12050631

AMA Style

Zhang S, Li Z, Li L, Yuan M. Interface Management Performance Assessment Framework for Sustainable Prefabricated Construction. Buildings. 2022; 12(5):631. https://doi.org/10.3390/buildings12050631

Chicago/Turabian Style

Zhang, Shengxi, Zhongfu Li, Long Li, and Mengqi Yuan. 2022. "Interface Management Performance Assessment Framework for Sustainable Prefabricated Construction" Buildings 12, no. 5: 631. https://doi.org/10.3390/buildings12050631