A Scientometric Analysis of Studies on Risk Management in Construction Projects
Abstract
:1. Introduction
- Reveal the most productive countries, authors, and journals in the field.
- Analyse the main research topics and their relationships.
- Determine the key research areas in construction risk management.
- Suggest the future research direction in the field.
2. Methodology
2.1. Selection of Database
2.2. Identification of Literature
3. Results and Discussions
3.1. Annual Publication Trend of Risk Management in Construction Projects
3.2. Most Productive Countries
3.3. Most Productive Authors
3.4. Most Productive Journals
3.5. Main Research Topics and Their Relationships
3.6. Key Research Areas
3.6.1. Cluster 1
- Process in Risk Management
- b.
- Risk Analytical Models and Techniques
- c.
- Sources of Risk and Uncertainty
3.6.2. Cluster 2
- Effective Knowledge-Based Systems for Improved Risk Management
3.6.3. Cluster 3
- Risk Contingency in Construction Contracts
3.6.4. Cluster 4
- Risk-Integrated Project Planning and Scheduling
3.6.5. Cluster 5
- Stakeholder Management
4. Future Research Directions
5. Conclusions
Author Contributions
Funding
Conflicts of Interest
References
- Project Management Institute. A Guide to the Project Management Body of Knowledge: PMBOK®Guide, 6th ed.; Project Management Institute: Newton Square, PA, USA, 2017. [Google Scholar]
- Ward, S.; Chapman, C. Transforming project risk management into project uncertainty management. Int. J. Proj. Manag. 2003, 21, 97–105. [Google Scholar] [CrossRef]
- Francis, R.; Armstrong, A. Ethics as a risk management strategy: The Australian experience. J. Bus. Ethics 2003, 45, 375–385. [Google Scholar] [CrossRef]
- Chatterjee, K.; Zavadskas, E.K.; Tamošaitienė, J.; Adhikary, K.; Kar, S. A hybrid MCDM technique for risk management in construction projects. Symmetry 2018, 10, 46. [Google Scholar] [CrossRef]
- Mustafa, M.A.; Al-Bahar, J.F. Project risk assessment using the analytic hierarchy process. IEEE Trans. Eng. Manag. 1991, 38, 46–52. [Google Scholar] [CrossRef]
- Wang, W.; Guo, H.; Li, X.; Tang, S.; Li, Y.; Xie, L.; Lv, Z. BIM Information Integration Based VR Modeling in Digital Twins in Industry 5.0. J. Ind. Inf. Integr. 2022, 28, 100351. [Google Scholar] [CrossRef]
- Cobo, M.J.; López-Herrera, A.G.; Herrera-Viedma, E.; Herrera, F. Science mapping software tools: Review, analysis, and cooperative study among tools. J. Am. Soc. Inf. Sci. Technol. 2011, 62, 1382–1402. [Google Scholar] [CrossRef]
- Hosseini, M.R.; Martek, I.; Zavadskas, E.K.; Aibinu, A.A.; Arashpour, M.; Chileshe, N. Critical evaluation of off-site construction research: A Scientometric analysis. Autom. Constr. 2018, 87, 235–247. [Google Scholar] [CrossRef]
- Chellappandi, P.; Vijayakumar, C. Bibliometrics, Scientometrics, Webometrics/Cybermetrics, Informetrics and Altmetrics—An Emerging Field in Library and Information Science Research. Shanlax Int. J. Educ. 2018, 7, 5–8. [Google Scholar]
- Hood, W.W.; Wilson, C.S. The literature of bibliometrics, scientometrics, and informetrics. Scientometrics 2001, 52, 291–314. [Google Scholar] [CrossRef]
- Börner, K. Mapping science. Sci. Technol. 2009, 54, 447–461. [Google Scholar]
- Liu, J.-W.; Huang, L.-C. Detecting and visualizing emerging trends and transient patterns in fuel cell scientific literature. In Proceedings of the 2008 4th International Conference on Wireless Communications, Networking and Mobile Computing, Dalian, China, 12–17 October 2008; pp. 1–4. [Google Scholar]
- Zhao, X.; Zuo, J.; Wu, G.; Huang, C. A bibliometric review of green building research 2000–2016. Archit. Sci. Rev. 2019, 62, 74–88. [Google Scholar] [CrossRef]
- Meho, L.I.; Rogers, Y. Citation counting, citation ranking, and h-index of human-computer interaction researchers: A comparison of Scopus and Web of Science. J. Am. Soc. Inf. Sci. Technol. 2008, 59, 1711–1726. [Google Scholar] [CrossRef] [Green Version]
- Bakalbassi, N.; Bauer, K.; Glover, J.; Wang, L. Three options for citation tracking: Google Scholar, Scopus and Web of Science. Biomed. Digit. Libr. 2006, 3, 7. [Google Scholar] [CrossRef]
- Ghaleb, H.; Alhajlah, H.H.; Bin Abdullah, A.A.; Kassem, M.A.; Al-Sharafi, M.A. A Scientometric Analysis and Systematic Literature Review for Construction Project Complexity. Buildings 2022, 12, 482. [Google Scholar] [CrossRef]
- Gnaedinger, J. Attitude and Communication in the Management of Underground Construction Projects. Undergr. Space 1979, 4, 85–89. [Google Scholar]
- Finch, W.; Postula, F. Risk Evaluation of Alternative Energy Sources; General Atomic Co.: San Diego, CA, USA, 1983. [Google Scholar]
- Perry, J.; Hayes, R. Construction projects-know the risks. Chart. Mech. Eng. 1985, 32, 42–45. [Google Scholar]
- Niwa, K. A knowledge-based human computer cooperative system for ill-structured management domains. IEEE Trans. Syst. Man Cybern. 1986, 16, 335–342. [Google Scholar] [CrossRef]
- Kangari, R. Application of expert systems to construction management decision-making and risk analysis. In Proceedings of the Expert Systems in Civil Engineering, Seattle, WA, USA, 8 April 1986; pp. 78–86. [Google Scholar]
- Ashley, D.B.; Perng, Y.-H. An intelligent construction risk identification system. In Proceedings of the Sixth International Symposium on Offshore Mechanics and Arctic Engineering, Houston, TX, USA, 1–6 March 1987; ASME: New York, NY, USA, 1987. [Google Scholar]
- Kangari, R.; Boyer, L.T. Knoledge-Based Systems and Fuzzy Sets in Risk Management. Comput.-Aided Civ. Infrastruct. Eng. 1987, 2, 273–283. [Google Scholar] [CrossRef]
- Ashley, D.B.; Stokes, S.; Perng, Y. Combining multiple expert assessments for construction risk identification. In Proceedings of the 7th International Conference on Offshore Mechanics and Arctic Engineering, Houston, TX, USA, 7 February 1988; pp. 183–192. [Google Scholar]
- Niwa, K. Human-computer cooperative systems: Conceptual basis, sample system evaluation, and R&D directions. In Proceedings of the American Society of Mechanical Engineers Manufacturing International-88, Atlanta, GA, USA, 17–20 April 1988; p. 87. [Google Scholar]
- Al-Bahar, J.F.; Crandall, K.C. Systematic risk management approach for construction projects. J. Constr. Eng. Manag. 1990, 116, 533–546. [Google Scholar] [CrossRef]
- Osei-Kyei, R.; Chan, A.P. Review of studies on the Critical Success Factors for Public–Private Partnership (PPP) projects from 1990 to 2013. Int. J. Proj. Manag. 2015, 33, 1335–1346. [Google Scholar] [CrossRef]
- Osei-Kyei, R.; Wuni, I.Y.; Xia, B.; Minh, T.T. Research trend on retirement village development for the elderly: A scientometric analysis. J. Aging Environ. 2020, 34, 402–416. [Google Scholar] [CrossRef]
- Chen, J.; Su, Y.; Si, H.; Chen, J. Managerial areas of construction and demolition waste: A scientometric review. Int. J. Environ. Res. Public Health 2018, 15, 2350. [Google Scholar] [CrossRef] [PubMed]
- Cui, T.; Zhang, J. Bibliometric and review of the research on circular economy through the evolution of Chinese public policy. Scientometrics 2018, 116, 1013–1037. [Google Scholar] [CrossRef]
- Su, H.-N.; Lee, P.-C. Mapping knowledge structure by keyword co-occurrence: A first look at journal papers in Technology Foresight. Scientometrics 2010, 85, 65–79. [Google Scholar] [CrossRef]
- Van Eck, N.; Waltman, L. VOSviewer Manual; Manual for VOSviewer Version 1.6. 11.; Universiteit Leiden: Leiden, The Netherlands, 2019. [Google Scholar]
- Antwi-Afari, P.; Ng, S.T.; Hossain, M.U. A Review of the Circularity Gap in the Construction Industry through Scientometric Analysis. J. Clean. Prod. 2021, 298, 126870. [Google Scholar] [CrossRef]
- Bing, L.; Akintoye, A.; Edwards, P.J.; Hardcastle, C. The allocation of risk in PPP/PFI construction projects in the UK. Int. J. Proj. Manag. 2005, 23, 25–35. [Google Scholar] [CrossRef]
- Hatamleh, M.T.; Moynihan, G.P.; Batson, R.G.; Alzarrad, A.; Ogunrinde, O. Risk assessment and ranking in the developing countries’ construction industry: The case of Jordan. Eng. Constr. Archit. Manag. 2021. [Google Scholar] [CrossRef]
- Nasirzadeh, F.; Khanzadi, M.; Rezaie, M. Dynamic modeling of the quantitative risk allocation in construction projects. Int. J. Proj. Manag. 2014, 32, 442–451. [Google Scholar] [CrossRef]
- Yamaguchi, H.; Uher, T.E.; Runeson, G. RISK allocation in PFI projects. In Proceedings of the 17th ARCOM Annual Conference, Salford, UK, 5–7 September 2001; University of Salford: Salford, UK, 2001. [Google Scholar]
- Zaghloul, R.S. Risk Allocation in Contracts: How to Improve the Process. Ph.D. Thesis, University of Calgary, Calgary, AB, Canada, 2005. [Google Scholar]
- Tian, Z.; Chen, Q.; Zhang, T. A method for assessing the crossed risk of construction safety. Saf. Sci. 2022, 146, 105531. [Google Scholar] [CrossRef]
- Wu, J.; Xu, S.; Zhou, R.; Qin, Y. Scenario analysis of mine water inrush hazard using Bayesian networks. Saf. Sci. 2016, 89, 231–239. [Google Scholar] [CrossRef]
- Abbasnezhad, K.; Ansari, R.; Mahdikhani, M. Schedule Risk Assessments Using a Precedence Network: An Object-Oriented Bayesian Approach. Iran. J. Sci. Technol. Trans. Civ. Eng. 2020, 46, 1737–1753. [Google Scholar] [CrossRef]
- Sadeh, H.; Mirarchi, C.; Pavan, A. Integrated approach to construction risk management: Cost implications. J. Constr. Eng. Manag. 2021, 147, 04021113. [Google Scholar] [CrossRef]
- Gurgun, A.P.; Koc, K. The role of contract incompleteness factors in project disputes: A hybrid fuzzy multi-criteria decision approach. Eng. Constr. Archit. Manag. 2022. [Google Scholar] [CrossRef]
- Koc, K.; Pelin Gurgun, A. Assessment of Readability Risks in Contracts Causing Conflicts in Construction Projects. J. Constr. Eng. Manag. 2021, 147, 04021041. [Google Scholar] [CrossRef]
- Koulinas, G.K.; Xanthopoulos, A.S.; Sidas, K.A.; Koulouriotis, D.E. Risks Ranking in a Desalination Plant Construction Project with a Hybrid AHP, Risk Matrix, and Simulation-Based Approach. Water Resour. Manag. 2021, 35, 3221–3233. [Google Scholar] [CrossRef]
- Qazi, A.; Shamayleh, A.; El-Sayegh, S.; Formaneck, S. Prioritizing risks in sustainable construction projects using a risk matrix-based Monte Carlo Simulation approach. Sustain. Cities Soc. 2021, 65, 102576. [Google Scholar] [CrossRef]
- Saaty, T.L. Fundamentals of Decision Making and Priority Theory with the Analytic Hierarchy Process; RWS Publications: Pittsburgh, PA, USA, 1994. [Google Scholar]
- Partovi, F.Y.; Burton, J.; Banerjee, A. Application of analytical hierarchy process in operations management. Int. J. Oper. Prod. Manag. 1990, 10, 5–19. [Google Scholar] [CrossRef]
- De Marco, A.; Narbaev, T. Factors of Schedule and Cost Performance of Tunnel Construction Megaprojects. Open Civ. Eng. J. 2021, 15, 38–49. [Google Scholar] [CrossRef]
- Afzal, F.; Yunfei, S.; Nazir, M.; Bhatti, S.M. A review of artificial intelligence based risk assessment methods for capturing complexity-risk interdependencies: Cost overrun in construction projects. Int. J. Manag. Proj. Bus. 2019, 14, 300–328. [Google Scholar] [CrossRef]
- Membah, J.; Asa, E. Estimating cost for transportation tunnel projects: A systematic literature review. Int. J. Constr. Manag. 2015, 15, 196–218. [Google Scholar] [CrossRef]
- Cross, R. Managing for knowledge: Managing for growth. Knowl. Manag. 1998, 1, 9–13. [Google Scholar]
- Brookes, N.; Morton, S.; Dainty, A.; Burns, N. Social processes, patterns and practices and project knowledge management: A theoretical framework and an empirical investigation. Int. J. Proj. Manag. 2006, 24, 474–482. [Google Scholar] [CrossRef]
- Egbu, C.O.; Robinson, H.S. Construction as a knowledge-based industry. Knowl. Manag. Constr. 2005, 4, 31–49. [Google Scholar]
- Lipa, M.J.; O’Donnell, K.; Greene, A. Knowledge as the Currency of Managing Risk: A Novel Framework to Unite Quality Risk Management and Knowledge Management. J. Valid. Technol. (JVT) 2020, 26. [Google Scholar] [CrossRef]
- Ramnarine, E.; O’Donnell, K. Demonstrating Pharmaceutical Quality System Effectiveness and Driving Continual Improvement: Evidence-Based Risk Reduction. PDA J. Pharm. Sci. Technol. 2018, 72, 338–345. [Google Scholar] [CrossRef]
- Ozturk, G.B.; Yitmen, I. Conceptual model of building information modelling usage for knowledge management in construction projects. IOP Conf. Ser. Mater. Sci. Eng. 2019, 471, 022043. [Google Scholar] [CrossRef]
- Project Management Institute. Practice Standard for Project Risk Management; Project Management Institute: Newton Square, PA, USA, 2009. [Google Scholar]
- Hoseini, E.; Van Veen, P.; Bosch-Rekveldt, M.; Hertogh, M. Cost performance and cost contingency during project execution: Comparing client and contractor perspectives. J. Manag. Eng. 2020, 36, 05020006. [Google Scholar] [CrossRef]
- De Marco, A.; Rafele, C.; Thaheem, M.J. Dynamic management of risk contingency in complex design-build projects. J. Constr. Eng. Manag. 2016, 142, 04015080. [Google Scholar] [CrossRef]
- Narbaev, T.; De Marco, A. Cost estimate at completion methods in construction projects. In Proceedings of the 2011 2nd International Conference on Construction and Project Management, Singapore, 16–18 September 2011; pp. 32–36. [Google Scholar]
- Rzempała, J.; Borkowski, D.; Rzempała, A.P. Risk Identification in Cogeneration (Combined Heat and Power) Projects: A Polish Case Study. Energies 2021, 15, 42. [Google Scholar] [CrossRef]
- Al Nasseri, H.A.; Widen, K.; Aulin, R. A taxonomy of planning and scheduling methods to support their more efficient use in construction project management. J. Eng. Des. Technol. 2016, 14, 580–601. [Google Scholar] [CrossRef]
- Dobrovolschi, O. Risk Assessment in the Planning of Development Projects. 2019. Available online: https://stc.fs.cvut.cz/pdf19/9542.pdf (accessed on 23 August 2022).
- Srinivasan, N.; Dhivya, S. An empirical study on stakeholder management in construction projects. Mater. Today Proc. 2020, 21, 60–62. [Google Scholar] [CrossRef]
- Nasirzadeh, F.; Khanzadi, M.; Rezaei, M. System dynamics approach for quantitative risk allocation. Int. J. Ind. Eng. Prod. Res. 2013, 24, 237–246. [Google Scholar]
- Pipattanapiwong, J. Development of Multi-Party Risk and Uncertainty Management Process for an Infrastructure Project. Ph.D. Thesis, Kochi University of Technology, Kochi, Japan, 2004. [Google Scholar]
- Yang, R.J.; Jayasuriya, S.; Gunarathna, C.; Arashpour, M.; Xue, X.; Zhang, G. The evolution of stakeholder management practices in Australian mega construction projects. Eng. Constr. Archit. Manag. 2018, 25, 690–706. [Google Scholar] [CrossRef]
- Yaseen, Z.M.; Ali, Z.H.; Salih, S.Q.; Al-Ansari, N. Prediction of risk delay in construction projects using a hybrid artificial intelligence model. Sustainability 2020, 12, 1514. [Google Scholar] [CrossRef]
- Pan, Y.; Zhang, L. Roles of artificial intelligence in construction engineering and management: A critical review and future trends. Autom. Constr. 2021, 122, 103517. [Google Scholar] [CrossRef]
- Pinheiro, M.; Ivandic, I.; Razzouk, D. The economic impact of mental disorders and mental health problems in the workplace. In Mental Health Economics; Springer: Singapore, 2017; pp. 415–430. [Google Scholar]
- Kalakoski, V.; Selinheimo, S.; Valtonen, T.; Turunen, J.; Käpykangas, S.; Ylisassi, H.; Toivio, P.; Järnefelt, H.; Hannonen, H.; Paajanen, T. Effects of a cognitive ergonomics workplace intervention (CogErg) on cognitive strain and well-being: A cluster-randomized controlled trial. A study protocol. BMC Psychol. 2020, 8, 1–16. [Google Scholar] [CrossRef] [PubMed]
- Couffe, C.; Michael, G.A. Failures due to interruptions or distractions: A review and a new framework. Am. J. Psychol. 2017, 130, 163–181. [Google Scholar] [CrossRef] [Green Version]
- Jahncke, H.; Hygge, S.; Halin, N.; Green, A.M.; Dimberg, K. Open-plan office noise: Cognitive performance and restoration. J. Environ. Psychol. 2011, 31, 373–382. [Google Scholar] [CrossRef]
Country | Cluster | Degree of Centrality | Documents | Citations | Total Link Strength |
---|---|---|---|---|---|
United Kingdom | 4 | 24 | 149 | 3759 | 76 |
Australia | 5 | 22 | 117 | 3168 | 95 |
United States | 1 | 20 | 281 | 5212 | 83 |
China | 8 | 17 | 301 | 2798 | 79 |
Hong Kong | 7 | 12 | 44 | 1731 | 38 |
Iran | 5 | 10 | 72 | 1052 | 30 |
Malaysia | 4 | 9 | 60 | 610 | 18 |
Saudi Arabia | 3 | 9 | 18 | 276 | 19 |
Turkey | 2 | 9 | 49 | 1351 | 14 |
Canada | 7 | 8 | 61 | 879 | 14 |
Egypt | 3 | 8 | 28 | 344 | 20 |
South Korea | 1 | 8 | 65 | 1451 | 24 |
France | 2 | 7 | 17 | 214 | 7 |
South Africa | 3 | 7 | 31 | 150 | 10 |
United Arab Emirates | 4 | 7 | 15 | 256 | 11 |
Ghana | 3 | 6 | 10 | 143 | 13 |
Qatar | 3 | 6 | 10 | 75 | 10 |
Russian Federation | 2 | 6 | 29 | 182 | 8 |
Singapore | 8 | 6 | 32 | 1184 | 23 |
Spain | 6 | 6 | 11 | 293 | 9 |
Viet Nam | 1 | 6 | 13 | 353 | 10 |
India | 4 | 5 | 57 | 402 | 5 |
New Zealand | 7 | 5 | 16 | 151 | 10 |
Pakistan | 2 | 5 | 12 | 171 | 5 |
Taiwan | 1 | 5 | 31 | 883 | 6 |
Netherlands | 6 | 4 | 15 | 132 | 4 |
Sweden | 2 | 4 | 15 | 228 | 6 |
Iraq | 2 | 3 | 11 | 25 | 5 |
Poland | 1 | 3 | 39 | 437 | 6 |
Germany | 4 | 2 | 12 | 79 | 2 |
Greece | 5 | 2 | 11 | 164 | 3 |
Indonesia | 1 | 2 | 36 | 177 | 2 |
Portugal | 6 | 1 | 10 | 249 | 1 |
Norway | 9 | 0 | 15 | 246 | 0 |
Author | Cluster | No. of Publications | Degree of Centrality | Citations | Total Link Strength |
---|---|---|---|---|---|
Dikmen I. | 2 | 19 | 3 | 723 | 18 |
Wang Y. | 1 | 17 | 4 | 71 | 4 |
Birgonul M.T. | 2 | 17 | 3 | 688 | 18 |
Han S.H. | 7 | 16 | 2 | 603 | 13 |
Fayek A.R. | 16 | 13 | 0 | 370 | 0 |
Zou P.X.W. | 1 | 11 | 2 | 411 | 2 |
Zhang J. | 1 | 10 | 6 | 48 | 7 |
Liu M. | 1 | 10 | 4 | 69 | 6 |
Wang J. | 1 | 10 | 4 | 67 | 4 |
Li H. | 1 | 10 | 3 | 75 | 3 |
Deng X. | 4 | 9 | 3 | 204 | 13 |
Kim D.Y. | 7 | 9 | 2 | 382 | 13 |
Kim H. | 7 | 9 | 2 | 383 | 12 |
Tah J.H.M. | 2 | 9 | 2 | 801 | 4 |
Zhao X. | 4 | 8 | 4 | 272 | 15 |
Breysse D. | 6 | 8 | 2 | 87 | 12 |
Taillandier F. | 6 | 8 | 2 | 89 | 11 |
Zhang H. | 1 | 8 | 2 | 54 | 2 |
Chileshe N. | 14 | 8 | 0 | 194 | 0 |
El-Adaway I.H. | 15 | 8 | 0 | 71 | 0 |
Li X. | 3 | 7 | 2 | 110 | 2 |
Liao P.-C. | 3 | 7 | 2 | 25 | 4 |
Heravi G. | 18 | 7 | 0 | 51 | 0 |
Adafin J. | 5 | 6 | 2 | 49 | 12 |
Mehdizadeh R. | 6 | 6 | 2 | 92 | 9 |
Rotimi J.O.B. | 5 | 6 | 2 | 49 | 12 |
Wilkinson S. | 5 | 6 | 2 | 49 | 12 |
Zhang L. | 1 | 6 | 2 | 6 | 2 |
Liu R. | 1 | 6 | 1 | 16 | 1 |
Molenaar K.R. | 11 | 6 | 1 | 201 | 2 |
Nasirzadeh F. | 10 | 6 | 1 | 148 | 3 |
Ardeshir A. | 13 | 6 | 0 | 233 | 0 |
Gunduz M. | 17 | 6 | 0 | 244 | 0 |
Latief Y. | 19 | 6 | 0 | 27 | 0 |
Wang H. | 25 | 6 | 0 | 82 | 0 |
Chang T. | 4 | 5 | 3 | 98 | 12 |
Hwang B.-G. | 4 | 5 | 3 | 138 | 11 |
Feng Y. | 1 | 5 | 2 | 69 | 2 |
Liu J. | 1 | 5 | 2 | 38 | 2 |
Sacks R. | 2 | 5 | 2 | 374 | 2 |
Wang T. | 3 | 5 | 2 | 36 | 3 |
Dey P.K. | 8 | 5 | 1 | 249 | 2 |
Gurgun A.P. | 9 | 5 | 1 | 11 | 4 |
Khanzadi M. | 10 | 5 | 1 | 139 | 3 |
Koc K. | 9 | 5 | 1 | 8 | 4 |
Ogunlana S.O. | 8 | 5 | 1 | 374 | 2 |
Tran D.Q. | 11 | 5 | 1 | 61 | 2 |
Wang C. | 3 | 5 | 1 | 28 | 1 |
Adeleke A.Q. | 12 | 5 | 0 | 15 | 0 |
Li C. | 20 | 5 | 0 | 41 | 0 |
Love P.E.D. | 21 | 5 | 0 | 201 | 0 |
Shen G.Q. | 22 | 5 | 0 | 201 | 0 |
Smith S.D. | 23 | 5 | 0 | 336 | 0 |
Song X. | 24 | 5 | 0 | 17 | 0 |
Öztaş A. | 26 | 5 | 0 | 181 | 0 |
Source | Documents | Citations | Total Link Strength |
---|---|---|---|
Journal of Construction Engineering and Management | 116 | 5498 | 229 |
Engineering, Construction and Architectural Management | 55 | 1172 | 81 |
IOP Conference Series: Materials Science and Engineering | 46 | 174 | 17 |
Construction Management and Economics | 43 | 2476 | 118 |
Safety Science | 42 | 1954 | 73 |
Journal of Management in Engineering | 37 | 1139 | 72 |
Advanced Materials Research | 34 | 35 | 5 |
Applied Mechanics and Materials | 28 | 52 | 2 |
Automation In Construction | 27 | 1156 | 107 |
International Journal of Construction Management | 26 | 354 | 51 |
Proceedings, Annual Conference-Canadian Society for Civil Engineering | 24 | 19 | 2 |
Journal of Civil Engineering and Management | 23 | 761 | 71 |
Procedia Engineering | 23 | 306 | 28 |
KSCE Journal of Civil Engineering | 21 | 220 | 49 |
Proceedings of the International Conference on Industrial Engineering and Operations Management | 19 | 28 | 12 |
Journal of Engineering, Design and Technology | 17 | 206 | 36 |
Cost Engineering (Morgantown, West Virginia) | 14 | 183 | 9 |
International Journal of Civil Engineering and Technology | 14 | 70 | 8 |
AACE International Transactions | 11 | 24 | 0 |
MATEC Web of Conferences | 11 | 28 | 2 |
ASCE-ASME Journal of Risk and Uncertainty in Engineering Systems, Part A: Civil Engineering | 10 | 30 | 15 |
Construction Innovation | 10 | 99 | 16 |
Geotechnical Special Publication | 10 | 28 | 0 |
Journal of Professional Issues in Engineering Education and Practice | 10 | 277 | 15 |
Keyword | Clusters | Occurrences | Total Link Strength |
---|---|---|---|
Risk Management | 2 | 378 | 417 |
Construction Industry | 2 | 166 | 213 |
Construction Project Management | 4 | 160 | 235 |
Construction Project | 1 | 148 | 166 |
Risk Assessment | 1 | 126 | 125 |
Risks | 3 | 109 | 127 |
Risk Analysis | 1 | 78 | 105 |
Fuzzy Set Theory | 1 | 56 | 82 |
Risk Identification | 1 | 36 | 41 |
Monte Carlo Simulation | 3 | 35 | 53 |
Safety | 2 | 32 | 51 |
Construction Safety | 1 | 30 | 16 |
Uncertainty | 3 | 29 | 47 |
Analytic Hierarchy Process | 1 | 27 | 38 |
Scheduling | 4 | 27 | 52 |
International Construction | 2 | 25 | 31 |
Risk Factors | 1 | 23 | 40 |
Decision Making | 4 | 22 | 35 |
BIM | 2 | 21 | 21 |
Risk Evaluation | 1 | 19 | 18 |
Simulation | 3 | 19 | 29 |
Contingency | 3 | 17 | 29 |
Contracts | 2 | 17 | 30 |
Cost | 3 | 16 | 31 |
Procurement | 5 | 16 | 19 |
Management | 3 | 15 | 25 |
China | 2 | 13 | 19 |
Factor Analysis | 5 | 12 | 19 |
Bayesian Network | 1 | 11 | 11 |
Contract Management | 2 | 11 | 16 |
Project Performance | 4 | 11 | 17 |
Risk Allocation | 5 | 11 | 13 |
Collaboration | 5 | 10 | 12 |
Construction Planning | 4 | 10 | 21 |
Knowledge Management | 1 | 10 | 14 |
Machine Learning | 1 | 10 | 10 |
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations. |
© 2022 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/).
Share and Cite
Osei-Kyei, R.; Narbaev, T.; Ampratwum, G. A Scientometric Analysis of Studies on Risk Management in Construction Projects. Buildings 2022, 12, 1342. https://doi.org/10.3390/buildings12091342
Osei-Kyei R, Narbaev T, Ampratwum G. A Scientometric Analysis of Studies on Risk Management in Construction Projects. Buildings. 2022; 12(9):1342. https://doi.org/10.3390/buildings12091342
Chicago/Turabian StyleOsei-Kyei, Robert, Timur Narbaev, and Godslove Ampratwum. 2022. "A Scientometric Analysis of Studies on Risk Management in Construction Projects" Buildings 12, no. 9: 1342. https://doi.org/10.3390/buildings12091342
APA StyleOsei-Kyei, R., Narbaev, T., & Ampratwum, G. (2022). A Scientometric Analysis of Studies on Risk Management in Construction Projects. Buildings, 12(9), 1342. https://doi.org/10.3390/buildings12091342