Research on the Value Improvement Model of Private Parties as “Investor–Builder” Dual-Role Entity in Major River Green Public–Private Partnership Projects
Abstract
:1. Introduction
2. Private Party Structure Analysis of SPVs Based on Single- and Dual-Role Entities
2.1. Methodology
2.2. Theoretical Model of the Impact of SPV Private Party Composition Modes on PPP Value Enhancement
2.3. The Private Party Composition Mode of SPVs
3. Model Assumption
- (1)
- Independent Entity Assumption: Each participant in the PPP project is an independent entity and belongs to different interest groups, meaning their objectives are different.
- (2)
- Information Asymmetry Assumption: This assumption, based on agency theory, postulates that there is information asymmetry between the principal and the agent at various stages of PPP project development, leading to “adverse selection” and “moral hazard”.
- (3)
- Rational Economic Actor Assumption: All participating parties are rational economic actors, and they choose compensation and effort levels to maximize their own interests.
- (4)
- Adherence to the Basic Framework of Agency Theory: It is assumed that the SPV company, as the principal, is risk-neutral, while the financing party, construction party, and operating party, as agents, are risk-averse. The utility function of the agents exhibits characteristics of constant absolute risk aversion. Assuming the agent’s cost coefficient is , where and the agent’s effort level is , where , then the agent’s effort cost for constructing the PPP project is represented as .
- (5)
- Project Completion Time Assumption: The time of project completion is denoted as , the predicted completion time as , the variable construction time as , and the construction party’s effort to reduce the variable construction period is represented by , where . Therefore, .
- (6)
- Environmental Benefit Assumption: Environmental benefits are the benefits of the project that can be perceived directly from the perspectives of citizens and the government after the implementation and completion of the project. In the context of a major river green PPP project, environmental benefits are divided into two aspects: water environmental benefits and other resource utilization environmental benefits. Other resource utilization environmental benefits mainly pertain to the content of resource utilization and reuse engineering, which is not relevant to the discussion in this paper and will not be considered here.As for water environmental benefits, they primarily include aspects such as water quality compliance, improvement in water landscapes, and the enhancement of the living environment for residents. These benefits are assessed based on a “baseline standard”, which is the minimum acceptance standard set by the government for green PPP projects. This standard includes assessment criteria for indicators such as the compliance rate of water quality within the project scope, the proportion of elimination of polluted and odorous water bodies, the percentage reduction in the COD concentration, and the percentage reduction in the total phosphorus concentration [42,43]. It is assumed that the projects discussed in this paper can meet this “baseline standard” upon acceptance. The set of standards is represented by ∆, where , and represents the basic standard for each water environmental management assessment indicator. represents the total number of assessment indicators.The weights for each indicator are denoted by , where . From the completion of construction to the end of the project’s operational period, the total environmental benefit derived from the green PPP project is calculated as
4. Establishment and Solution of PPP Project Value Improvement Model
4.1. Value Model for Single-Role Entity Scenario
4.2. Value Model for Dual-Role Entity Scenario
5. Results and Discussion
5.1. Comparison of Optimal Effort Levels of the Construction Party in Two Modes
5.2. Comparison of Enterprise Income in Two Modes
5.3. Comparison of Environmental Benefits in Two Modes
5.4. Comparison of Social Benefits in Two Modes
5.5. The Relationship between the Participating Entity’s Benefits and the Equity Participation Ratio in the Dual-Role Entity
5.6. Model Validation
6. Conclusions
Author Contributions
Funding
Data Availability Statement
Conflicts of Interest
Abbreviations
PPP | Public–private partnership |
SPV | Special Purpose Vehicle |
Contract amount | |
Net income generated per unit time after the construction project is completed | |
Profit of the project company | |
Influence coefficient of the construction party’s effort level on the major river green PPP project | |
Influence coefficient of time | |
Efficiency coefficient of reducing variable construction periods | |
Basic standard for each water environmental management assessment indicator | |
The weight for indicator i | |
Number of indicators | |
The concession period | |
Predicted completion time | |
Variable construction time | |
Influence coefficient of agent’s cost | |
The revenue generated per unit time after the construction project is completed | |
C | Construction cost |
Fixed cost | |
Variable cost | |
The management costs incurred by the professional company when participating as a shareholder in the role of the principal | |
Influence coefficient of government’s emphasis on environmental benefits | |
Social benefit | |
Agent’s effort level | |
Agent’s optimal effort level | |
Agent’s effort cost | |
k | Shareholding percentage of the professional company in SPV |
Expected profit for the construction party in Single-Role Entity Scenario | |
Expected profit for the construction party in Dual-Role Entity Scenario | |
Expected total environmental benefit in Single-Role Entity Scenario | |
Expected total environmental benefit in Dual-Role Entity Scenario | |
Social benefit in Single-Role Entity Scenario | |
Social benefit in Dual-Role Entity Scenario |
References
- Devarajan, S.; Reinikka, R. Making Services Work for Poor People; Weltbank, Ed.; World Development Report; Oxford University Press: Oxford, UK, 2003. [Google Scholar]
- Almeile, A.M.; Chipulu, M.; Ojiako, U.; Vahidi, R.; Marshall, A. Project-Focussed Literature on Public-Private Partnership (PPP) in Developing Countries: A Critical Review. Prod. Plan. Control 2022, 2022, 2123408. [Google Scholar] [CrossRef]
- Global Infrastructure Hub. Infrastructure Monitor 2022. Annual Report. Available online: https://cdn.gihub.org/umbraco/media/5171/global-infrastructure-hub_2022-infrastructure-monitor-report-plus-esg-section_fa_2203.pdf (accessed on 1 March 2023).
- Ye, T.; Geng, Z.; Zhang, Y. A Study on the Effects of Green PPP on Promoting High-Quality Regional Development. Financ. Res. 2023, 113–128. [Google Scholar]
- Musenero, L.; Baroudi, B.; Gunawan, I. Critical Issues Affecting Dispute Resolution Practice in Infrastructure Public–Private Partnerships. J. Constr. Eng. Manag. 2023, 149, 04023001. [Google Scholar] [CrossRef]
- Zhang, B.; Yin, J.; Jiang, H. Spatial–Temporal Pattern Evolution and Influencing Factors of Coupled Coordination between Carbon Emission and Economic Development along the Pearl River Basin in China. Environ. Sci. Pollut. Res. 2022, 30, 6875–6890. [Google Scholar] [CrossRef] [PubMed]
- Xu, L.; Chen, S.S. Coupling Coordination Degree between Social-Economic Development and Water Environment: A Case Study of Taihu Lake Basin, China. Ecol. Indic. 2023, 148, 110118. [Google Scholar] [CrossRef]
- Bao, F.; Martek, I.; Chen, C.; Wu, Q.; Chan, A.P.C. Critical Risks Inherent to the Transfer Phase of Public–Private Partnership Water Projects in China. J. Manag. Eng. 2022, 38, 04022006. [Google Scholar] [CrossRef]
- Zhang, S.; Xu, Z. Governance for Principal–Principal Relationship in Infrastructure Public–Private Partnerships: A Case Study in China. J. Manag. Eng. 2022, 38, 05022005. [Google Scholar] [CrossRef]
- Bennett, J.; Iossa, E. Building and Managing Facilities for Public Services. J. Public Econ. 2006, 90, 2143–2160. [Google Scholar] [CrossRef]
- Wang, X.; Wang, S.; Gao, Y. Optimal Equity Structure of PPP Projects When Private-Sector Shareholders’ “Investor-Contractor” Dual Roles Is Considered. Constr. Manag. Econ. 2023, 41, 910–925. [Google Scholar] [CrossRef]
- Park, A.; Chang, C.-Y. Impacts of Construction Events on the Project Equity Value of the Channel Tunnel Project. Constr. Manag. Econ. 2013, 31, 223–237. [Google Scholar] [CrossRef]
- Chang, Z. Public–Private Partnerships in China: A Case of the Beijing No.4 Metro Line. Transp. Policy 2013, 30, 153–160. [Google Scholar] [CrossRef]
- Chileshe, N.; Kavishe, N. Human Capacity Building Strategies for Improving PPP Implementation in Tanzanian Construction Projects. Built Environ. Proj. Asset Manag. 2022, 12, 906–923. [Google Scholar] [CrossRef]
- Shi, L.; He, Y.; Onishi, M. Effect of the Internal Agency Problem on Risk-Sharing Incentive Contracts in Public–Private Partnership Projects. J. Constr. Eng. Manag. 2023, 149, 04023126. [Google Scholar] [CrossRef]
- Iossa, E.; Martimort, D. Risk Allocation and the Costs and Benefits of Public–private Partnerships. RAND J Econ. 2012, 43, 442–474. [Google Scholar] [CrossRef]
- Zuo, T.; Zhao, L. A Comparison on Profit of BOT Project under Two Kinds of Shareholders’ Structure. Forecasting 2007, 1, 76–80. [Google Scholar]
- Askar, M.M.; Gab-Allah, A.A. Problems Facing Parties Involved in Build, Operate, and Transport Projects in Egypt. J. Manag. Eng. 2002, 18, 173–178. [Google Scholar] [CrossRef]
- Demirel, H.Ç.; Leendertse, W.; Volker, L.; Hertogh, M. Flexibility in PPP Contracts—Dealing with Potential Change in the Pre-Contract Phase of a Construction Project. Constr. Manag. Econ. 2017, 35, 196–206. [Google Scholar] [CrossRef]
- Wang, L.; Zuo, C.; Li, C. Has PPP Improved the Output Efficiency of Infrastructure. Financ. Res. 2019, 1, 90–102. [Google Scholar]
- Bao, F.; Chen, C.; Martek, I.; Chan, A.P.; Jiang, W. Factors Underpinning the Successful Return of Public–Private Partnership Projects to Public Authority: Assessing the Critical Success Factors of the Transfer Phase of Chinese Water Projects. J. Infrastruct. Syst. 2023, 29, 04023015. [Google Scholar] [CrossRef]
- Xue, Y.; Wang, G. Analyzing the Evolution of Cooperation among Different Parties in River Water Environment Comprehensive Treatment Public-Private Partnership Projects of China. J. Clean. Prod. 2020, 270, 121118. [Google Scholar] [CrossRef]
- Jin, H.; Liu, S.; Sun, J.; Liu, C. Determining Concession Periods and Minimum Revenue Guarantees in Public-Private-Partnership Agreements. Eur. J. Oper. Res. 2021, 291, 512–524. [Google Scholar] [CrossRef]
- Shi, L.; He, Y.; Onishi, M.; Kobayashi, K. Double Moral Hazard and Risk-Sharing in Construction Projects. IEEE Trans. Eng. Manag. 2021, 68, 1919–1929. [Google Scholar] [CrossRef]
- Jin, H.; Liu, C. Incorporating Social Benefits in Concession Price Negotiation for Public–Private Partnership Contracts. J. Leg. Aff. Disput. Resolut. Eng. Constr. 2023, 15, 04522040. [Google Scholar] [CrossRef]
- Liu, B.; Ji, J.; Chen, J.; Qi, M.; Li, S.; Tang, L.; Zhang, K. Quantitative VfM Evaluation of Urban Rail Transit PPP Projects Considering Social Benefit. Res. Transp. Bus. Manag. 2023, 49, 101015. [Google Scholar] [CrossRef]
- Lu, P.; Qian, L.; Chu, Z.; Xu, X. Role of Opportunism and Trust in Construction Projects: Empirical Evidence from China. J. Manag. Eng. 2016, 32, 05015007. [Google Scholar] [CrossRef]
- Dewulf, G.; Garvin, M.J. Responsive Governance in PPP Projects to Manage Uncertainty. Constr. Manag. Econ. 2020, 38, 383–397. [Google Scholar] [CrossRef]
- Brogaard, L. Business Value in Public-Private Partnerships: The Positive Impact of Trust and Task-Relevant Competencies on Business Outcomes in PPPs. Int. Public Manag. J. 2019, 22, 617–642. [Google Scholar] [CrossRef]
- Zhen, H.U.; Lu, W.; Management, S.O. The Relationship among Government Shareholding, Trust and Project Performance in PPP Projects. Constr. Econ. 2019, 40, 33–38. [Google Scholar]
- Yin, Y.; Zhao, H.; Yan, L.; Zheng, J. A Theoretical Integration Study on Public Project Contract Governance and Relational Governance. Sci. Technol. Prog. Policy 2011, 28, 1–4. [Google Scholar]
- Maurya, D.; Srivastava, A.K. Managing Partner Opportunism in Public–Private Partnerships: The Dynamics of Governance Adaptation. Public Manag. Rev. 2019, 21, 1420–1442. [Google Scholar] [CrossRef]
- Ying-Hong, S.; Fang, W.; Xin-Yue, C. The Relationship between Stakeholders’ Trust and Cooperation Efficiency in PPP. East China Econ. Manag. 2019, 33, 148–155. [Google Scholar]
- Fleta-Asín, J.; Muñoz, F.; Rosell-Martínez, J. Public-Private Partnerships: Determinants of the Type of Governance Structure. Public Manag. Rev. 2020, 22, 1489–1514. [Google Scholar] [CrossRef]
- Li, Y.; He, N.; Zhang, Y.; Li, H.; Zhang, C. Optimization of Capital Structure for Urban Water PPP Projects Using Mezzanine Financing: Sustainable Perspective. J. Constr. Eng. Manag. 2023, 149, 04023059. [Google Scholar] [CrossRef]
- Zhang, X.; Liu, J. Incentive Mechanism and Value-Added in PPP Projects Considering Financial Institutions’ Early Intervention. J. Constr. Eng. Manag. 2022, 148, 04022001. [Google Scholar] [CrossRef]
- Winata, L.E.; Gultom, Y.M.L. The Effects of Governance on Performance: The Case of Public–Private Partnership (PPP) Toll Roads in Indonesia. Int. J. Constr. Manag. 2023, 2023, 2219937. [Google Scholar] [CrossRef]
- Chen, B. Optimal Capital Structure of Government-Subsidized Private Participation in Infrastructure Projects. Eng. Econ. 2020, 65, 321–338. [Google Scholar] [CrossRef]
- Zhang, D. A Study on the Relationship between Capital Structure and Value Stability of PPP Projects. Master’s Thesis, Chongqing University, Chongqing, China, 2019. [Google Scholar]
- Kivleniece, I.; Quelin, B.V. Creating and Capturing Value in Public-Private Ties: A Private Actor’s Perspective. Acad. Manag. Rev. 2012, 37, 272–299. [Google Scholar] [CrossRef]
- Wei, X.; Han, L. The Optimal Contract for Green PPP Project Portfolios: A Welfare Perspective for Economic and Environmental Effects. Financ. Res. 2022, 50, 60–78. [Google Scholar]
- National Development and Reform Commission of China; Ministry of Housing and Urban-Rural Development. 14th Five-Year Plan for the Development of Urban Sewage Treatment and Resource Utilization. Available online: https://www.ndrc.gov.cn/xwdt/tzgg/202106/P020210615582638801329.pdf (accessed on 1 June 2021).
- Li, H.; Li, W.; Wang, L.; Lv, L. Public Satisfaction Evaluation of Urban Water Environment Treatment Public-Private Partnership Project: A Case Study from China. Int. J. Build. Pathol. Adapt. 2020, 39, 407–432. [Google Scholar] [CrossRef]
- Liu, J.; Liu, J.; Ruan, L. Revenue Structure of the Dual-Role as Investor-Contractors in PPP Project. Nankai Bus. Rev. Int. 2020, 11, 283–298. [Google Scholar] [CrossRef]
- Liu, J.; Gao, R.; Cheah, C.Y.J.; Luo, J. Incentive Mechanism for Inhibiting Investors’ Opportunistic Behavior in PPP Projects. Int. J. Proj. Manag. 2016, 34, 1102–1111. [Google Scholar] [CrossRef]
- He, Y.; Shi, L.; Li, Z. The combined effect of marginal social and private benefit on the socially optimal equity structure of PPP projects. Constr. Manag. Econ. 2021, 39, 807–823. [Google Scholar] [CrossRef]
- Ministry of Finance of China. Guidelines for PPP Project Contracts. 2014. Available online: https://www.gov.cn/xinwen/2015-01/19/content_2806400.htm (accessed on 19 January 2015).
- Lucko, G.; Rojas, E.M. Research Validation: Challenges and Opportunities in the Construction Domain. J. Constr. Eng. Manag. 2010, 136, 127–135. [Google Scholar] [CrossRef]
- Sargent, R.G. Verification and Validation of Simulation Models. J. Simul. 2013, 7, 12–24. [Google Scholar] [CrossRef]
- European Commission. Resource Book on PPP Case Studies. (2004-07). Available online: http://ec.europa.eu/regional_policy/sources/docgener/guides/pppresourcebook.pdf (accessed on 1 June 2004).
Type | Mode | Private Party | Investment Elements | Key Elements | Examples |
---|---|---|---|---|---|
Single-Role Entity Scenario | I | Pure financial institutions | Funds | 1. During the financing phase, the SPV company acts as both the principal and the agent. 2. During the construction and operation phases, the SPV company acts as the principal, while the construction contractor and operator act as the agents. | Guizhou’s Guanshan Lake Environmental Improvement PPP project, with a total investment of CNY 1.135 billion and a 32-year cooperation period. The winning private party was the Guizhou Public and Social Capital Cooperation Industrial Investment Fund. |
Dual-Role Entity Scenario | II | Construction contractors | Funds + Knowledge | 1. During the construction phase, the SPV company acts as both the principal and the agent. 2. During the financing and operation phases, the SPV company acts as the principal, while financial institutions and operators act as the agents. 3. Construction companies are responsible for project construction, ensuring quality, progress, and safety to mitigate construction risks. | Yunnan’s Underground Comprehensive Pipe Gallery Project PPP project, with a total investment of CNY 6.759 billion and a 20-year project period. The winning private party was Yunnan Construction Group Co., Ltd. |
III | Operators | Funds + Knowledge | 1. During the operation phase, the SPV company acts as both the principal and the agent. 2. During the financing phase, the SPV company acts as the principal, while financial institutions act as the agents. 3. Typically used for complex comprehensive operation and management projects, favorable for project operation and risk avoidance. | Anhui’s Chizhou Main Urban Area Sewage Treatment and Municipal Drainage Facility Purchase Service PPP project, with a total investment of CNY 2.054 billion and a 26-year cooperation period. The winning private party was Shenzhen Water (Group) Co., Ltd. | |
IV | Construction contractors and operators | Funds + Knowledge | 1. During both the construction and operation phases, the SPV company acts as both the principal and the agent. 2. During the financing phase, the SPV company acts as the principal, while financial institutions act as the agents. | Yunnan’s Kunming Guandu District River Comprehensive Management Project PPP project, with a total investment of CNY 1.555 billion and a 15-year project period. The winning private party was a consortium formed by Shenzhen TIEHAN Ecological Environment Co., Ltd.; China Railway Shanghai Engineering Bureau Group Co., Ltd.; and China Municipal Engineering South Design & Research Institute Co., Ltd. China Railway Shanghai Engineering Bureau Group Co., Ltd., and China Municipal Engineering South Design & Research Institute Co., Ltd. are responsible for the construction process, while Shenzhen TIEHAN Ecological Environment Co., Ltd. oversees both construction and operation. | |
V | Financial institutions and construction contractors | Funds + Knowledge | 1. During the financing and construction phases, the SPV company acts as both the principal and the agent. 2. During the operation phase, the SPV company acts as the principal, while operators act as the agents. | Shandong’s Rizhao Kuishan Comprehensive Passenger Transport Terminal and Supporting Project, with a total investment of CNY 1.634 billion and a 12-year project period. The winning private party was a consortium formed by China Construction Eighth Engineering Division Corp. Ltd. and GF Xinde Investment Management Co., Ltd. | |
VI | Financial institutions, construction contractors, and operators | Funds + Knowledge | Throughout the entire PPP project operation, the SPV company acts as both the principal and the agent. | Hohhot City Urban Rail Transit Line 1 Phase I Project, with a total investment of CNY 15.584 billion and a 30-year project period. The winning private party is a consortium formed by China Railway Corporation and Shenzhen Taiping Investment Co., Ltd. Shenzhen Taiping Investment Co., Ltd. is responsible for financing, while China Railway Corporation handles both construction and operation. |
Parameter | Assigned Value | Value Basis |
---|---|---|
Contract amount | Reference case, simplified unit value (trillion/billion, etc.) | |
Influence coefficient of the construction party’s effort level on the major river green PPP project | Hypothetical base value | |
Influence coefficient of time | Hypothetical base value | |
Efficiency coefficient of reducing variable construction periods | Hypothetical base value | |
Basic standard for each water environmental management assessment indicator | Refers to the “14th Five-Year Plan for the Development of Urban Sewage Treatment and Resource Utilization” by the National Development and Reform Commission of China | |
The weight for each indicator | Reference case | |
Quantity of indicators | Reference case | |
The concession period | Reference case, simplified unit value (year/month, etc.) | |
Predicted completion time | Reference case, simplified unit value (year/month, etc.) | |
Variable construction time | Reference case, simplified unit value (year/month, etc.) | |
Influence coefficient of agent’s cost | Hypothetical base value | |
The revenue generated per unit time after the construction project is completed | Reference case, simplified unit value (trillion/billion, etc.) | |
Fixed cost | Reference case, simplified unit value (trillion/billion, etc.) | |
The management costs incurred by the professional company when participating as a shareholder in the role of the principal | Reference case, simplified unit value (trillion/billion, etc.) | |
Influence coefficient of government’s emphasis on environmental benefits | Hypothetical base value | |
Social benefit | Hypothetical base value |
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |
© 2023 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/).
Share and Cite
Zhang, J.; Feng, J.; Zhang, K.; Han, X. Research on the Value Improvement Model of Private Parties as “Investor–Builder” Dual-Role Entity in Major River Green Public–Private Partnership Projects. Buildings 2023, 13, 2881. https://doi.org/10.3390/buildings13112881
Zhang J, Feng J, Zhang K, Han X. Research on the Value Improvement Model of Private Parties as “Investor–Builder” Dual-Role Entity in Major River Green Public–Private Partnership Projects. Buildings. 2023; 13(11):2881. https://doi.org/10.3390/buildings13112881
Chicago/Turabian StyleZhang, Jianyi, Jingchun Feng, Ke Zhang, and Xun Han. 2023. "Research on the Value Improvement Model of Private Parties as “Investor–Builder” Dual-Role Entity in Major River Green Public–Private Partnership Projects" Buildings 13, no. 11: 2881. https://doi.org/10.3390/buildings13112881
APA StyleZhang, J., Feng, J., Zhang, K., & Han, X. (2023). Research on the Value Improvement Model of Private Parties as “Investor–Builder” Dual-Role Entity in Major River Green Public–Private Partnership Projects. Buildings, 13(11), 2881. https://doi.org/10.3390/buildings13112881