Next Article in Journal
Shear Bearing Capacity of Steel-Fiber-Reinforced Concrete Shear Wall under Low-Cycle Repeated Loading Based on the Softened Strut-and-Tie Model
Previous Article in Journal
Experimental Study on Crack Width of HRB600 Grade High-Strength Steel Bar Reinforced Concrete Beams
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Development of an Algorithm for Crane Trajectory Distance Calculation for Erection of Precast Concrete Members

Department of Architectural Engineering, Kyung-Hee University, 1732, Deogyeong-daero, Giheung-gu, Yongin-si 17104, Gyeonggi-do, Republic of Korea
*
Author to whom correspondence should be addressed.
Buildings 2024, 14(1), 11; https://doi.org/10.3390/buildings14010011
Submission received: 4 October 2023 / Revised: 1 December 2023 / Accepted: 18 December 2023 / Published: 20 December 2023
(This article belongs to the Section Construction Management, and Computers & Digitization)

Abstract

:
Reducing the construction time for large logistics buildings can result in reduced construction management costs and economic gains from early operation. A large logistics building with a heavy load and long spans was constructed as a precast concrete (PC) structure, which required the use of a sizable crane to lift heavy PC members. A basic analytical approach was employed to resolve potential errors in the planning of PC member erection and to build a systematic erection plan. Calculation techniques for the trajectory distance that use the crane location were applied to select an erection plan that minimizes crane work. A crane trajectory distance calculation algorithm for sustainable PC member erection in large logistics buildings with heavy loads and long spans has been developed. The developed model aids in creating simulation and optimization models to ensure the minimal usage of cranes in the future and in determining the cost, construction time, CO2 emissions, and energy use for each erection plan.

1. Introduction

Large logistics buildings must be quickly constructed in order to recover their investment costs. Thus, it is crucial to consider the economic advantages of early operation and to reduce construction management costs (labor, equipment, and other expenses) [1,2]. Precast concrete (PC) structures are considered particularly beneficial over reinforced concrete (RC) structures in terms of construction time [3,4,5,6,7]. Furthermore, given that large logistics buildings have high floor heights and long spans, columns and beams in the range of 5–10 m must be installed [8]. However, construction requires a considerable amount of temporary work [9,10,11,12]. Accordingly, the capital-intensive PC technique is beneficial because equipment and material costs are reduced and labor costs are increased [13,14,15]. The PC method is preferred because of the shortening of the construction time [3,4,5,13], quality assurance [14,15], and cost savings [15,16,17], and it has been extensively researched [18,19].
A large crane is required to lift heavy PC members, and PC members are installed inside the crane’s working radius following a review of crane specifications and designs [20,21]. Mobile cranes are the most commonly utilized; they are a shared resource among on-site resources due to their considerable mobility and weight, and they are involved in all types of lifting operations [22,23,24]. Prior to commencing work, a thorough lifting plan should be devised, especially given the complexities of lifting heavy objects [25,26]. Lifting for PC construction is conventionally performed in accordance with a production schedule based on the field manager’s experience. Furthermore, issues such as procurement delays in factory production at the site and reproduction due to inaccurate PC member details often lead to delivery delays for PC members [27].
When simulation techniques are expanded, it is vital to systematically undertake PC erection by establishing regulations and estimating the distance between a crane and a member on a construction site. Hence, a distance calculation method that simply and rapidly calculates the trajectory distance based on the crane position must be devised to select a plan that minimizes crane work among erection plans. In particular, two objective functions must be derived: (1) a function that can derive the farthest member from the crane to the installation member and (2) a function that can derive the crane position with the smallest movement of the crane boom. Therefore, the objective of this study was to develop a crane trajectory distance calculation algorithm for erecting sustainable PC members in large logistics buildings with heavy loads and long spans. Cranes utilized on construction sites are classified as fixed cranes or mobile cranes based on the weight of the materials. The three types of mobile cranes are hydraulic truck, crawler, and tower cranes. The scope of this study was confined to crawler cranes, which are mostly utilized for the PC erection of large logistics buildings with heavy loads and long spans.
This study was conducted based on the following steps:
(1)
Investigate potential methods for PC member erection and select a method that is suited to the field.
(2)
Analyze issues encountered throughout the process of PC member erection in the actual field.
(3)
Develop an algorithm for calculating the path of a moving crane.
(4)
Analyze the lifting range of cranes applicable to the field and the process of crane movement for liftable PC members.
(5)
Calculate the trajectory distance using simulation.
(6)
Compare and assess the cost, construction time, CO2 emissions, and energy consumption of the actual plan and the simulation-calculated plan.

2. Preliminary Studies

2.1. Literature Review

Numerous algorithms and methods have been developed to automate the crane-work-planning process to improve the productivity and efficiency of crane operations [28]. Some of the crane-related research topics include crane and feed position optimization [29,30,31], crane type selection [32,33,34], lift sequence simulation [35,36,37,38], three-dimensional (3D) visualization of crane work to detect potential collisions [23,34,39], and crane lift path planning [26,40,41,42,43].
These studies can be divided into three categories: (1) optimization of the crane location and material supply location according to the selected crane type, (2) the crane load and the distance between the crane boom and the structure, and (3) the crane movement path.
First, research on optimizing the crane location and material supply location according to the selected crane type was reviewed. To optimize the crane and material location, several studies have determined the appropriate crane type based on a variety of project factors [30,32,33,34]. These factors included the required operating clearance, construction height, soil foundation, duration, and site accessibility. Furthermore, in a recent study, the effect of wind was examined on the crane body as an additional factor when selecting the crane type [44]. The crane and material delivery locations can be optimized according to the type of crane selected. A genetic-algorithm-based model was developed to investigate the optimal feeding position of a tower crane in which the hook travel time was considered [29]. A more complex method for optimizing the tower crane set position and feed position for high-rise buildings has also been proposed using mixed-integer linear programming [45].
The crane load and the distance between the crane boom and the structure were reviewed. Al-Hussein et al. [46] suggested a technique for selecting a workable crane based on independent 2D designs by evaluating whether the crane load and the distance between the crane and the building component match the basic requirements. The optimal crane was selected based on several constraints, including the minimum clearance with the building, crane operating radius, and crane load. Hasan et al. [47] computed the crane leg pressure at various horizontal swing angles and ensured safety by monitoring the leg pressure during crane operation. Moselhi et al. [48] developed a mobile crane selection and positioning system to establish a 3D model based on the coordinates and sizes of hoists and obstacles. The system selects the optimal crane by simulating the position and probable collisions of the mobile cranes in a virtual environment. Based on previous studies, they suggested a systematic method for selecting a mobile crane.
Third, in the research on the crane movement path, Lei et al. [42] proposed a general method for verifying a mobile-crane-lifting binary (yes/no) path. They considered site constraints by calculating the minimum and maximum crane lift radii based on capacity and crane configuration. Reddy and Varghese [49] developed a tool that identifies a lift pathway that satisfies planning requirements by applying two heuristic searches. Chang et al. [50] developed a method for automatically and efficiently planning an installation path using a crane. The two proposed methods composed the crane installation space by including the crane load capacity and environmental obstacles and obtained a collision-free path in the constructed space using the probabilistic road map (PRM) method. Therefore, various studies have been conducted to increase the productivity and efficiency of crane work. However, there has been no research to systematically perform the erection of PC members by calculating the trajectory distance for a PC construction case site. In other words, research on arranging a crawler crane to calculate the trajectory distance of a crane boom and to plan a path has not been conducted.

2.2. PC Member Erection Method Using a Crane

The crane position was determined by the working radius because the PC members were installed within the working radius of the crane. Given that the crane is moved after all members within the working radius are installed, the position of the crane is determined by the erection plane. In general, there are three types of PC member erection. Floor-by-floor erection is a method of installing PC members on the next floor after installing all PC columns, girders, and slabs on each floor. There are no problems with the structural stability of the building because joint concrete is poured on each floor [51]. Most pin-joint PC frames are erected in this manner [52]. Second, cascading erection is a method for stacking PC members in a stepwise manner within the range of the crane boom. This is applied when the construction time for each floor is insufficient [53]. Third, section-by-section erection is easier than other erection methods for securing the efficiency of equipment operation and workspace by constructing PC members in a specific section on all floors [54,55]. In this study, cascading erection, as shown in Figure 1, was adopted to reduce the construction time.

3. Actual Erection Case Analysis

The case project was conducted on four floors above the ground. The second to fourth floors are PC structures, the core is a reinforced concrete structure, and the roof is a steel frame structure. Thus, the bottom floors of the second through fourth floors of the PC structure were targeted. The site conditions must be analyzed to efficiently erect PC members. Figure 2 shows the second-floor plan of the case site and an overview of the site conditions. When erecting PC members, the movement line of the mobile crane and the PC-member-carrying line are important. The northeast and southeast sides of the site are adjacent to other sites, and the northwest site and access road are +63.80 m and +56.03 m in elevation (EL), respectively, with a difference of 7.8 m. Therefore, entry into the site is impossible. Moreover, the main entrance can be positioned on the southernmost side on the southwest side of the site, ruling out the vehicle access limit section.
Additionally, Table 1 shows the analysis of PC members in the field to perform installation simulation. The PC members of the site were analyzed to simulate their erection. In this study, PC columns and PC beams were targeted, whereas PC slabs were excluded. As a result of aggregation based on the member list of the case site, 1004 columns and 1284 beams were obtained. When the dimensions of PC columns and beams were analyzed, the PC columns were found to be 0.8–1.7 m wide, 0.8–1.0 m high, 9.2 m long, and 5.9–15.6 m3 in volume. In contrast, the PC beams are 0.5–1.3 m wide, 1.0–2.6 m high, 11.0–23.0 m long, and 11.0–34.8 m3 in volume. If the unit weight of reinforced concrete is 2.4 ton/m3, then the weight is 14.2–37.4 t for the column and 26.4–83.6 t for the beam.
Erection was performed according to the plan of the actual site. Figure 3 shows the monthly processes. As is shown in Figure 3a, the PC column member on the east side was erected on the first day of construction. Subsequently, as is shown in Figure 3b,c, the PC members of the first and second floors were sequentially erected by prioritizing the construction of each floor. Three cranes erected PC columns on the first floor and some girders and slabs on the second floor. The core, which is an RC structure, was combined with PC columns and beams for joining. This implies that the core was constructed according to the erection plan for the PC columns and beams. As is shown in Figure 3d, cascade installation was applied, and it took 172 calendar days to erect all PC components (Lee et al., 2020). Figure 3e,f show the working conditions after eight and ten months, respectively. As is shown in these figures, PC and RC core erection was completed on all floors, and the steel frame was erected and finished on the fourth floor. Thus, PC members were erected without any specific rules in the actual field. This is due to the fact that the PC members were procured by reflecting the production schedule available at the factory during PC member erection planning.

4. Algorithm for Crane-Moving-Path Calculation for the Sustainable Erection of PC Members

Before erecting the PC members, the operator is not required to reposition the mobile crane [56], thereby reducing space collisions between the crane and the building via a crane-moving plan. Crane movement planning requires a number of complex decisions while adhering to a wide range of criteria and constraints. Thus, these decisions are usually time-consuming and are largely dependent on experience. However, currently, given that the fourth industrial revolution has commenced and construction sites are increasingly robotized, a PC member erection plan should be systematically established by setting rules and calculating the distance between the crane and members. Figure 4 shows the algorithm for calculating the crane-moving path.
(1)
Definition of PC member position
Using the floor-by-floor method at the case site is difficult when PC is used. Given that PC erection is conducted inside the building at the case site, a crane can only be erected at a distance. Therefore, PC erection was performed in a cascade manner. If the building is not large, PC members can be produced on-site at a specified location within the crane rotation radius. However, if the building is large, as in the case of this study, it should be produced in a place where erection can be easily performed. For a large-scale PC structure with a large floor area, a construction plan should be prepared in line with a safe workflow that considers crane productivity. As is shown in Figure 5a, PC erection was planned with three 550 t mobile cranes at the case site. Consequently, it is necessary to prepare a plan to enable erection within the working radii of these cranes. For each 550 t crane, a working radius of up to 74 m can be used by applying a 54 m jib and 36 m boom. Each zone (A–C) is divided into three areas. A zoning plan was established with the areas distributed considering the construction efficiency. The crane moved by erecting the members from the top to the bottom in each zone. Sample ⓐ is selected for crane A in Figure 5a, while the positions of the PC column, crane, and trailer on the first floor are defined in Figure 5b. With the position coordinates of the crane defined as (0, 0, 0), the position coordinates of each PC column can be defined as listed in Table 2. The position coordinates of the trailer are defined as (0, −33, 0).
(2)
Calculation of the crane rotation distance
The crane rotation distance can be divided into the horizontal (Figure 6a) and vertical (Figure 6b) rotation distances of the crane. They are determined by calculating each distance and adding them. Hence, the horizontal rotation of the crane indicates movement from ⓐ to ⓑ in Figure 6a, and the vertical rotation of the crane indicates movement from ⓑ to ⓒ in Figure 6b. To calculate the horizontal rotation distance, the crane position coordinates are defined as (0, 0, 0), the position coordinates of the column member are defined as (xci, yci, zci), the position coordinates of the trailer are defined as (xt, yt, zt), and the horizontal rotation distance is defined as r(θi). The horizontal rotation angle of the boom is calculated using Equation (1) with the relative coordinate values of the erected member whose origin corresponds to the position coordinates of the crane. Hence, the horizontal rotation angle can be calculated using the distance between the crane and the erected member. The crane horizontal distance can be calculated using the distance from the crane to the trailer and the horizontal rotation angle of the boom, as shown in Equation (2).
θ i = π arctan x i 0 y i 0 ,
r θ i = l t r a i l e r × θ i ,
  • Mci = column member position coordinates;
  • xci = x-coordinate of the erected column member;
  • yci = y-coordinate of the erected column member;
  • zci = z-coordinate of the erected column member;
  • C = crane position coordinates;
  • T = trailer position coordinates;
  • xt = x-coordinate of the trailer;
  • yt = y-coordinate of the trailer;
  • zt = z-coordinate of the trailer;
  • θi = horizontal rotation angle (rad);
  • r(θi) = horizontal rotation distance;
  • ltrailer = distance from crane to trailer;
  • i = number of ith erected members at the crane position (1, …, n).
Figure 6. Calculation of the crane horizontal and vertical rotation distances (in the order of 1, 2, and 3): (a) crane horizontal rotation distances, (b) crane vertical rotation distances.
Figure 6. Calculation of the crane horizontal and vertical rotation distances (in the order of 1, 2, and 3): (a) crane horizontal rotation distances, (b) crane vertical rotation distances.
Buildings 14 00011 g006
Using Equations (1)–(3), the horizontal rotation angle of the boom is calculated, and the horizontal rotation distance of the crane is derived. The horizontal distances of n-members can be sequentially calculated. The algorithm steps are shown in Algorithm 1.
Algorithm 1 Calculating crane vertical rotation distances
Input:  C ( 0 , 0 , 0 ) ,   M c i ( x i , y i , z i ) , T ( x t , y t , z t ) , B t ( x b t , y b t , z b t )
Output:  r θ 1 ,  r θ 2 , …,   r θ n
1int  i
2for  M c i M c  do
3if i ≤ n then
4 θ i = π arctan x i 0 y i 0   then
5 r ( θ i ) = l t r a i l e r × θ i  then
6else break
7end if
8end for
9return  r θ i
The head position of the boom must be defined to calculate the horizontal rotational distance. As is shown in Equation (3), the position of the boom head is defined as (xbt, ybt, zbt), the position of the horizontally rotated boom is defined as (xb′t, yb′t, zb′t), the position of the vertically rotated boom is defined as (xb′c, yb′c, zb′c), and the vertical rotation distance is defined as r(ψi). Furthermore, the linear distance during vertical rotation is defined as A, and the boom length is defined as LB. As in Equation (4), the x- and y-coordinates of the trailer and boom are the same, while the x- and y-coordinates of the column member and horizontally rotated boom are the same. Therefore, the boom length during horizontal and vertical rotation is constant, and the horizontal distance from the crane to the boom head is also constant.
B t = x b t y b t z b t ,   B t = x b t y b t z b t ,   B c = x b c y b c z b c .
x t = x b t ,   y t = y b t ,   x c i = x b c ,   y c i = y b c ,
  • Bt = boom head position coordinates;
  • xbt = boom head x-coordinate;
  • ybt = boom head y-coordinate;
  • zbt = boom head z-coordinate;
  • B′t = position coordinates of the horizontally rotated boom;
  • xb′t= x-coordinate of the horizontally rotated boom;
  • yb′t= y-coordinate of the horizontally rotated boom;
  • zb′t= z-coordinate of the horizontally rotated boom;
  • B′c = position coordinates of the vertically rotated boom;
  • xb′c = x-coordinate of the vertically rotated boom;
  • yb′c = y-coordinate of the vertically rotated boom;
  • zb′c = z-coordinate of the vertically rotated boom;
  • xt = x-coordinate of the trailer;
  • yt = y-coordinate of the trailer;
  • xci = x-coordinate of the erected column member;
  • yci = y-coordinate of the erected column member;
  • i = number of ith erected members at the crane position (1, …, n).
The distance from the crane to the erected member can be calculated using the x- and y-coordinates of the erected member. According to the Pythagorean theorem, the z-coordinate of the vertically rotated boom can be calculated using the boom length and horizontal distance to the boom head. Moreover, the linear distance during vertical rotation can be calculated using the z-coordinate of the boom and the distance from the crane to the erected member. The vertical rotation angle of the boom is calculated using Equation (5) with the boom length and linear distance during vertical rotation. The crane vertical distance can be calculated, as is shown in Equation (6), using the boom length and vertical rotation angle. Finally, the boom trajectory distance Dt can be calculated as the sum of the horizontal and vertical rotation distances, as shown in Equation (7).
φ i = 2 × arcsin A / 2 L B .
r φ i = L B × φ i .
D t = i = 1 n ( r ( θ i ) + r φ i ) ,
  • LB = boom length;
  • A = linear distance during vertical rotation;
  • φi = vertical rotation angle of the boom (radian);
  • r(φi) = vertical rotation distance;
  • Dt = boom trajectory distance;
  • i = number of ith erected members at the crane position (1, …, n).
Using Equations (6)–(10), the distance from the crane to the installation member and the z-coordinate of the vertically rotated boom are calculated. Then, the vertical rotation angle of the boom is calculated, and the vertical rotation distance of the crane is derived. The vertical distances of n members can be sequentially calculated. The algorithm steps are shown in Algorithm 2.
Algorithm 2 Calculating crane horizontal rotation distances
Input:  C ( 0 , 0 , 0 ) ,   M c i ( x i , y i , z i ) T ( x t , y t , z t ) B t ( x b t , y b t , z b t )
Output:   r φ 1 , r φ 2 , …, r φ n
1int  i
2for  M c i M c  do
3if i ≤ n then
4 l c m c i = { ( x c i ) 2 + ( y c i ) 2 }    then
5 z b c = ( L B ) 2 ( y b t ) 2    then
6 A = [ y b t l c m c i ] 2 + ( z b t z b c ) 2   then
7 φ i = 2 arcsin A / 2 L B    then
8 r φ i = L B × φ i    then
9else break
10end if
11end for
12return  r φ i
  • lcmci = distance from the crane to member to be erected;
  • xci = x-coordinate of column member to be erected;
  • yci = y-coordinate of column member to be erected;
  • zb′c = z-coordinate of the vertically rotated boom;
  • LB = boom length;
  • ybt = y-coordinate of the boom head.
(3)
Development of the objective function
PC members are installed in descending order of the straight-line distance from the crane to the member. Among the currently installed members, the member with the farthest distance from the crane must be selected. The member with the longest distance from the coordinates of the installation member to the position coordinates of the crane must be selected. Therefore, the objective function in Equation (8) can be derived to derive the farthest member from the crane to the installation member. And the movement of the member is calculated as the sum of the horizontal rotation distance and the vertical rotation distance of the crane boom, and this value must be the smallest in order to increase the crane’s efficiency. Therefore, the objective function in Equation (9) can be derived to derive the crane position with the smallest movement of the crane boom. And the crane position that satisfies Equations (8) and (9) must be derived.
M a x i m i z e   f ( D s ) = D s = ( x i C ( x ) ) 2 + ( y i C ( y ) ) 2 + ( z i C ( z ) ) 2 .
M i n i m i z e   f D t r i = i = 1 n ( r ( θ i ) + r φ i ) ,
  • f ( D s ) = total function equation of the linear distance from the crane to the erected member;
  • Ds = total linear distance from the crane to the erected member;
  • xi = x-coordinate of the erected member;
  • yi = y-coordinate of the erected member;
  • zi = z-coordinate of the erected member;
  • C(x) = x-coordinate of the crane;
  • C(y) = y-coordinate of the crane;
  • C(z) = z-coordinate of the crane;
  • r(φi) = vertical rotation distance;
  • f D t r i = boom trajectory distance function equation;
  • Dt = boom trajectory distance;
  • i = number of ith erected members at the crane position (1, …, n).
(4)
Erection simulation
PC member erection was simulated in accordance with the site design drawing and erection schedule to verify whether it is actually applicable to the field. The assumptions for the simulation are as follows:
Members are erected at the crane location to the maximum extent.
The trajectory distance is large where the linear distance from the crane is greater.
The trajectory distance is large where the linear distance from the crane is small.
(5)
Satisfying cost and energy use?
A PC erection plan is established when the cost and energy use satisfy the target values. However, if they do not satisfy the target values, the simulation must be repeated by recalculating the vertical and horizontal rotation distances of the crane.
(6)
Application to the site
The PC member erection simulation was completed via iterative work using this algorithm. If modification is necessary due to changes in site conditions during construction, then it can be performed by using the relevant methods for each step.

5. Simulation of a Crane-Moving Path

5.1. Crane Lifting Range Analysis

Before starting the PC member erection simulation based on the analyzed site design drawing and established erection schedule, it is necessary to accurately analyze the lifting range of the applied crane. The 550 t crawler crane adopted in this study is defined by the boom and jib, as shown in Figure A1a, and the working radius is set as shown in Figure A1b. The working radius of a 550 t crawler crane can be analyzed using this information. The boom starts at a horizontal length of 1.7 m. Given that the boom length is 36 m and the maximum angle is 86°, a value of 2.51 m is derived by calculating the horizontal length at the maximum angle of the boom using Equation (10). Moreover, given that the jib length is 54 m and the maximum angle is 71°, 17.58 m is derived when the horizontal length is calculated at the maximum angle of the jib using Equation (11). Hence, as the boom is located at a horizontal length of 1.7 m, and the horizontal lengths of the boom and jib are 2.51 m and 17.58 m, respectively, the horizontal length is 21.79 m when the maximum angle of the 36 m boom is reached, as shown in Equation (12). Hence, the minimum operating distance of the crane is 21.79 m, and the crane can erect members located at 21.79 m or more.
Horizontal length of boom = 36 m × cos 86 = 2.51 m.
horizontal length of jib = 54 m × cos 71 = 17.58 m.
Total horizontal length = 1.7 + 2.51 + 17.58 = 21.79 m.
The boom starts at a horizontal length of 1.7 m. As the boom length is 36 m and the minimum angle is 65°, a length of 15.21 m is derived by calculating the horizontal length at the minimum angle of the boom, as shown in Equation (13). Moreover, given that the jib length is 54 m and the minimum angle is 15°, a length of 52.16 m is derived by calculating the horizontal length at the minimum angle of the jib, as shown in Equation (14). Hence, as the boom is located at a horizontal length of 1.7 m and the horizontal lengths of the boom and jib are 15.21 m and 52.16 m, respectively, the horizontal length is 69.07 m when the minimum angle of 36 m boom is reached, as shown in Equation (15). Consequently, the maximum operation distance of the crane is 69.07 m, and the crane can erect members located at 69.07 m or less.
Horizontal length of boom = 36 m × cos 65 = 15.21 m.
Horizontal length of jib = 54 m × cos 15 = 52.16 m.
Total horizontal length = 1.7 + 15.21 + 52.16 = 69.07 m.
The liftable columns are analyzed based on the working radius of the crane, as illustrated in Figure 7. Thus, columns of 21.76 m or more and 69.07 m or less are derived based on the boom head of the crane. This confirms that the assumption regarding the definition of the column position is incorrect, as is shown in Table 1, which was set at the beginning of the study. For example, the coordinates of C9 in Figure 6b and Table 1 are (11, 0, 10), which is a column located at a horizontal distance of 11 m. As this column is not located at 21.76 m or more and 69.07 m or less, it cannot be erected with the crawler crane used in this study. The crane-moving process analyzed in Figure 7 is shown in Figure 8. First, a crane is installed 55 m from the members to be erected; second, the members are erected in a cascade manner. The members are installed via the sequential movement of the crane, which moves by 11 m each time. Finally, the erection of the PC members is completed by positioning the crane at 22 m, considering the crane lifting distance. In other words, the crane position coordinates (0, 0, 0) are newly redefined as the crane moves by 11 m.

5.2. PC Member Erection Sequence Algorithm

An algorithm for the PC member erection sequence was developed to perform the simulations, as shown in Figure 9. This algorithm can be applied to all of the PC columns and beam members. The erection of one member is defined as one simulation. This implies that the number of simulations increased with the number of members.
(1)
Calculating the distance from the crane to each member
The distance from the crane to each member is calculated using the defined position coordinates of the crane and member using the following equation (Equation (16)):
D s = ( x i C ( x ) ) 2 + ( y i C ( y ) ) 2 + ( z i C ( z ) ) 2 ,
  • Ds = total linear distance from the crane to the erected member;
  • xi = x-coordinate of the erected member;
  • yi = y-coordinate of the erected member;
  • zi = z-coordinate of the erected member;
  • C(x) = x-coordinate of the crane;
  • C(y) = y-coordinate of the crane;
  • C(z) = z-coordinate of the crane;
  • i = number of ith erected members at the crane position (1, …, n).
(2)
Selection of the farthest member
To reduce interference with the erected members during the erection of PC members, PC members are erected in descending order of the linear distance from the crane to the member. Consequently, the member with the largest distance is selected from among the currently erected members.
(3)
Are there members with greater distances?
The erection simulation is performed if the selected member has the largest distance from the crane among the non-erected members. However, if there is a member whose distance from the crane is greater than that of the selected member, then that member should be selected.
(4)
Simulation of the ith member
Erection simulations are performed using the selected members. If there are members at the same distance, then they must be erected in descending order of angle from the trailer to the member. This is to reduce the interference of the members to be erected with the already-erected members. If Equations (16) and (17) are in conflict with each other, Equation (17) is prioritized. A simulation is performed for the total number of members and then sequentially according to the distance. When all of the members are erected, the member installation sequence algorithm is completed.
M i n i m i z e   f ( θ ) = θ i = arctan x t x i y t y i .

5.3. Simulation Results

Before starting the simulation, the position of the trailer was selected as (0, −33, 92). To reflect the position of the trailer, the head of the boom was positioned 33 m from the crane, and the lifting of the PC members began at this position. This position was calculated as 92 m in height due to the 97.74 m length of the boom. The trajectory distance of each column member can be calculated using Equations (1)–(7) based on the coordinate values (see Table 1) of the PC member position definition on sample ⓐ in Figure 6b as shown Table 3. The horizontal rotation angle is calculated using Equation (1), and the horizontal rotation distance is calculated using Equation (2). Moreover, the vertical rotation angle is calculated using Equations (4) and (5), and the vertical rotation distance is calculated using Equation (6). Finally, the total trajectory distance of the boom can be calculated using Equation (7). For example, the horizontal rotation angle of C1 among the column members is 153°, and the horizontal trajectory distance at this angle is 88 m. The vertical rotation angle of this member is 0.09°, and the vertical trajectory distance is 9 m. Hence, the total trajectory distance is 97 m. However, according to the liftable PC column analysis results in Figure 7, only columns at 21.76 m or more and 69.07 m or less can be lifted. Hence, not all values derived from Table 2 can be applied. Therefore, only C3, C4, C7, C8, C11, and C12 can be lifted at the crane position.
Based on the aforementioned analysis results, Figure 10, Figure 11 and Figure 12 show the calculation of the trajectory distance of the column members for the crane path from the first to the third floor. The trajectory distance of each member complies with the rules of the crane-moving process for PC member erection shown in Figure 8, and the total trajectory distance is determined to be 183,575 m. The location with the farthest linear distance from the crane is expected to show the largest trajectory distance. However, it is observed that the trajectory distance is not large even if the linear distance from the crane is large. The location with the largest trajectory distance corresponds to that with the largest horizontal movement, where it shows the same x-coordinate as the trailer. Furthermore, the trajectory distance is not the smallest when the linear distance is the smallest. Among the members that can be lifted by the crane, the member at the position where the horizontal movement is smallest shows the smallest value. The trajectory distance can be easily calculated because it shows a consistent pattern based on the crane movement. This is due to the fact that the members are positioned at distances of 11 or 18 m due to the characteristics of large logistics buildings.
The crane is removed by sequentially erecting its members. However, as the last members of the second and third floors are not required to be erected in a cascade manner, as is shown in Figure 11 and Figure 12, they can be simultaneously erected without moving the crane. However, additional y-column members must be installed on the opposite side of Zone B. Thus, their erection must be completed by moving them. Moreover, given that the third floor is the last floor of the PC structure, PC members can be erected without considering the connection with other floors, as shown in Figure 12.
The average unit erection time for each PC member at the case site is 40 min, 15 min, and 10 min for columns, beams, and slabs, respectively. The number of members for columns, beams, and slabs is 850, 1371, and 4032, respectively. Furthermore, the actual erection time is 210 calendar days, and the rotation distance of the crane is 20 m/min. After excluding the time required to fix the position of the members, the actual and simulated durations required for PC member erection are 172 and 158 days, respectively. Thus, a 13.99% reduction in the construction period is possible.
With respect to the cost comparison, labor, material, and equipment costs are summed [57] using Equations (18) and (19). Labor, material, and equipment costs are calculated using Equations (20)–(22). The actual cost of PC member erection in Table 4 denotes the results of the calculation using the actual input quantity. The simulation-calculated cost in Table 5 shows the results of the calculation reflecting the actual cost. With respect to the unit price of the labor cost, the amount from the “Construction Industry Wage Survey Report (Market Wage Unit Price) applied to the first half of 2022” was applied. Material and equipment costs were calculated based on the unit price applied in the field. Hence, the actual cost was USD 6,221,704, and the simulation-calculated cost was USD 5,710,335. Therefore, when applying the model developed in this study, the cost can be reduced by 8.33% when compared to the actual construction cost. In terms of equipment cost, the actual and simulation-calculated costs accounted for 89% and 90%, respectively, showing the highest proportions of construction costs as shown Table 4 and Table 5. This implies that the daily rent for the crane accounted for the highest percentage. Therefore, to reduce construction costs, the minimum rental period should be applied by deriving accurate dates when the crane is used before starting construction.
C t = C d + C i ,
C d = C l + C m + C e ,
  • Ct = total cost of the boom trajectory;
  • Cd = direct cost of the boom trajectory;
  • Ci = indirect cost of the boom trajectory;
  • Cl = labor cost of the boom trajectory;
  • Cm = material cost of the boom trajectory;
  • Ce = equipment cost of the boom trajectory.
C l = i = 1 n ( Q c i × C c u l ) + j = 1 m ( Q b i × C b u l ) + k = 1 l ( Q s i × C s u l ) .
C m = i = 1 n ( Q c i × C c u m ) + i = 1 m ( Q b i × C b u m ) + i = 1 l ( Q s i × C s u m ) .
C e = i = 1 n ( Q c i × C c u e ) + j = 1 m ( Q b i × C b u e ) + k = 1 l ( Q s i × C s u e ) .
  • Cl = labor cost of the boom trajectory;
  • Cm = material cost of the boom trajectory;
  • Ce = equipment cost of the boom trajectory;
  • Qci = quantity of the ith columns;
  • Ccul = unit labor cost for column erection;
  • Qbi = number of ith beams;
  • Cbul = unit labor cost for beam erection;
  • Qsi = number of ith slabs;
  • Csul = unit labor cost for slab erection;
  • Ccum = unit material cost for column erection;
  • Cbum = unit material cost for beam erection;
  • Csum = unit material cost for slab erection;
  • Ccue = unit equipment cost for column erection;
  • Cbue = unit equipment cost for beam erection;
  • Csue = unit equipment cost for slab erection;
  • i = number of erected ith columns (1, …, n);
  • j = number of erected ith beam members (1, …, m);
  • k = number of erected ith slab members (1, …, l).
Table 4. Actual costs for erection of PC members.
Table 4. Actual costs for erection of PC members.
ItemUnitQuantityUnit Price (USD)Amount (USD)
Labor costEquipment operatorDay17222939,388
Common laborDay51615479,464
Material costDieselL12,9001.8325,437
Equipment feeCrane (550 ton)Day43013,0005,590,000
Indirect cost487,415
Total6,221,704
Table 5. Simulation-calculated costs for the erection of PC members.
Table 5. Simulation-calculated costs for the erection of PC members.
ItemUnitQuantityUnit Price (USD)Amount (USD)
Labor costEquipment operatorDay15822936,182
Common laborDay47415472,996
Material costDieselL10,2751.8318,803
Equipment feeCrane (550 ton)Day39513,0005,135,000
Indirect cost447,353
Total5,710,335
CO2 emissions were calculated, as shown in Table 6, using the labor, material, and equipment costs and the indirect cost calculated in Table 4 and Table 5. The CO2 emissions corresponding to the direct cost were calculated using the actual input labor, oil, and electricity use. Furthermore, the CO2 emissions corresponding to indirect costs were calculated using the actual input lighting, heating use, and environmental conservation. Consequently, when the model developed in this study is applied, 25.99% of CO2 emissions can be reduced when compared to actual construction. Equations (23)–(26) show that the total CO2 emissions can be derived by multiplying the number of PC members by the unit CO2 emission of each item. In terms of oil use, the actual and simulation-calculated plans accounted for 99% and 98%, respectively, indicating high CO2 emissions.
C E t = C E c + C E b + C E s .
C E c = i = 1 n Q c i × C E u l + C E u o + C E u e l + C E u l h + C E u e c .
C E b = i = 1 m Q b i × C E u l + C E u o + C E u e l + C E u l h + C E u e c .
C E s = i = 1 l Q s i × C E u l + C E u o + C E u e l + C E u l h + C E u e c .
  • CEt = total CO2 emissions;
  • CEc = CO2 emissions of the column;
  • CEb = CO2 emissions of the beam;
  • CEs = CO2 emissions of the slab;
  • Qci = number of ith columns;
  • CEul = unit CO2 emissions of labor;
  • CEuo = unit CO2 emissions of oil;
  • CEuel = unit CO2 emissions of electricity;
  • CEulh = unit CO2 emissions of lighting and heating;
  • CEuec = unit CO2 emissions of environmental conservation;
  • Qbi = number of ith beams;
  • Qsi = number of ith slabs;
  • i = number of erected ith columns (1, …, n);
  • j = number of erected ith beams (1, …, m);
  • k = number of erected ith slabs (1, …, l).
Table 6. Comparison of actual and simulation-calculated CO2 emissions (unit: kg).
Table 6. Comparison of actual and simulation-calculated CO2 emissions (unit: kg).
ItemActualSimulation Calculated
Labor372341
Oil use73,00453,965
Electricity use427307
Lighting and heating use197153
Environmental conservation11083
Total74,11054,850
Energy consumption was calculated, as shown in Table 7, using the oil and electricity consumption presented in Table 4 and Table 5. The electrical energy consumption was calculated using Equation (27), and the actual diesel input was converted into the SI base unit for energy. For the capacity of the 550 t crane, 397 kW was applied, and for the energy conversion value of diesel, 41,090/m3 was applied. Hence, the simulation-calculated plan for member erection can reduce energy consumption by 26.01%. In terms of oil use, the actual and simulated plans accounted for more than 99%, indicating high energy consumption.
E = 1000 × P × t
  • E = energy consumption;
  • P = power (kW);
  • t = time (s).
Table 7. Comparison of actual energy consumption and simulation-calculated energy consumption (unit: MJ).
Table 7. Comparison of actual energy consumption and simulation-calculated energy consumption (unit: MJ).
ItemActualSimulation Calculated
Oil use570,317421,583
Electricity use21241951
Total572,441523,534
The simulation-calculated plan shows a reduction effect in terms of construction time, cost, CO2 emissions, and energy use when compared with the actual plan. These ratios are not the same because the constituent items and composition ratios differ. Furthermore, CO2 emissions and energy consumption were reduced by 25.99% and 26.01%, respectively, indicating high reduction rates. Therefore, the minimization of the crane usage rate at a site has a considerable effect on preventing environmental pollution.

6. Conclusions

In this study, the time required for each activity in the construction process was analyzed to investigate the developed productivity analysis method. The analysis results were then compared with those of the current construction method in terms of time and cost. The conclusions obtained in this study are as follows:
The existing algorithm is widely applied in the construction field and depends only on labor experience. Hence, the method and order of specific crane work are determined right before the work. However, this study proposed a mathematical model for calculating the trajectory distance so that crane work can be planned and simulated in advance. In other words, it solved the problem of crane work being based on experience.
By calculating the trajectory distance of the column members, it was confirmed that the trajectory distance for each member complied with the rules of the crane-moving process for PC member erection assumed in this study. A total trajectory distance of 183,575 m was derived from this calculation. In this study, the farthest linear distance from the crane was expected to show the largest trajectory distance. However, it was confirmed that the trajectory distance was not large, even when the linear distance from the crane was large. The location with the largest trajectory distance corresponded to that with the largest horizontal movement, which had the same x-coordinate as the trailer.
By calculating the trajectory distance, it was observed that the smallest trajectory distance was not derived when the linear distance from the crane was the smallest. Among the members that can be lifted by the crane, the member with the intermediate distance showed the smallest value. This is due to the fact that as the linear distance from the crane decreases, the vertical rotation distance increases, and therefore, the smallest value was not observed.
A consistent pattern of the trajectory distance, according to crane movement, can be derived, thereby making the calculation easier. The reason for showing a certain pattern was that the column members had distances of 11 or 18 m because of the characteristics of a large logistics building.
Actual and simulated plans were compared by applying them to a case site. The simulation-calculated plan showed reductions of 13.99% in the construction period, 8.33% in cost, 25.99% in CO2 emissions, and 26.01% in energy consumption when compared to the actual plan. Furthermore, CO2 emissions and energy use showed high reduction rates, suggesting that the minimization of the crane usage rate at the site had a considerable effect on preventing environmental pollution.
In this study, rules for the location of cranes and members were established, and equations for calculating the distance between cranes and members were derived and simulated. This can be used as basic data for research on PC erection. However, in the case of general building construction, PC members or materials are not arranged at equal intervals, so it must be calculated differently from the trajectory distance method applied in this study. In other words, it is difficult to apply the equations and algorithms provided in this study. Therefore, a method for integrating this simulation into the field for crane operators or construction managers in the future and a framework that can be applied to various construction sites should also be presented.
In addition, through this study, the problem of crane work being based only on experience at the construction site was solved, and the developed model can streamline the construction process, reduce time and cost, and enhance productivity. Additional research can be conducted to verify the efficiency of the developed model via trajectory distance calculations based on various scenarios across a variety of fields. The cost, construction time, CO2 emissions, and energy consumption can be easily calculated using the developed model. Furthermore, the shortest distance according to field conditions can be optimized by developing simulation and optimization models in the future. They can be automatically calculated using the developed model, and the shortest distance can be automatically derived based on the calculated data. Furthermore, errors due to human calculation can also be prevented. Additionally, in this study, the boom and jib of the crane were not distinguished, and the energy and cost required to move the trailer were not investigated in detail. Therefore, additional research should be conducted in the future by clearly defining the rotational distances of the boom and jib of the crane and collecting data on the movement of the trailer.

Author Contributions

Conceptualization, S.K.; methodology, S.K. and J.L.; validation, J.L.; formal analysis, S.K. and J.L.; investigation, J.O. and J.L.; data curation, J.L.; writing—original draft preparation, J.L.; writing—review and editing, S.K. and J.L.; visualization, J.O. and J.L.; supervision, S.K. and J.L.; project administration, S.K. and J.L.; funding acquisition, J.L. All authors have read and agreed to the published version of the manuscript.

Funding

This work was supported by the National Research Foundation of Korea (NRF) grant funded by the Korean Government (MOE) (No. 2021R1C1C2094527).

Data Availability Statement

The data presented in this study are available on request from the corresponding author. The data are not publicly available due to privacy.

Conflicts of Interest

The authors declare no conflict of interest.

Appendix A

Figure A1. Crane-moving process for PC member erection.
Figure A1. Crane-moving process for PC member erection.
Buildings 14 00011 g0a1

References

  1. Lim, J.; Kim, D.Y. Integrated management model of production and yard stock for in-situ precast concrete production. J. Asian Archit. Build. Eng. 2021, 23, 1–17. [Google Scholar] [CrossRef]
  2. Kang, S.M.; Kim, O.J. Domestic and Foreign Present Situation Analysis of a PC Method; Daelim Technology Research Institute Architecture (Spring): Seoul, Republic of Korea, 2006; pp. 28–37. [Google Scholar]
  3. Badir, Y.F.; Kadir, M.R.A.; Hashim, A.H. Industrialized building systems construction in Malaysia. J. Archit. Eng. 2002, 8, 19–23. [Google Scholar] [CrossRef]
  4. Chan, W.T.; Hu, H. Constraint programming approach to precast production scheduling. J. Constr. Eng. Manag. 2002, 128, 513–521. [Google Scholar] [CrossRef]
  5. Eastman, C.M.; Sacks, R. Relative productivity in the AEC industries in the United States for on-site and off-site activities. J. Constr. Eng. Manag. 2008, 134, 517–526. [Google Scholar] [CrossRef]
  6. Kwon, H.; Jeon, S.; Lee, J.; Jeong, K. Development of a simulation model for supply chain management of precast concrete. Korean J. Constr. Eng. Manag. 2021, 22, 86–98. [Google Scholar] [CrossRef]
  7. Lee, S.; Cha, H. A study on plans for diffusion & revitalization, and developing key performance indicator for OSC based PC structure apartment housing. Korean J. Constr. Eng. Manag. 2021, 22, 98–105. [Google Scholar] [CrossRef]
  8. Lim, J.; Son, C.B.; Kim, S. Scenario-based 4-D dynamic simulation model for in-situ production and yard stock of precast concrete members. J. Asian Arch. Build. Eng. 2023, 22, 2320–2334. [Google Scholar] [CrossRef]
  9. Kim, W.; Lee, D. Wall Structure Combination and Ramen Structure PC Combination Method. J. Korea Inst. Build. Constr. 2002, 2, 84–88. [Google Scholar]
  10. Shin, D.W.; Kim, C.D. A typological study on performance defects of PC apartment housing. J. Archit. Inst. Korea 1993, 10, 123–130. [Google Scholar]
  11. An, S.H.; Lee, U.K.; Kang, K.I. A study on the proposal about the improvement of PC in construction industry. J. Archit. Inst. Korea 2004, 20, 135–142. [Google Scholar]
  12. Jin, E.; Park, S.; Chae, M.; Han, S. Decision making model for application of manufacturing production system in construction project. In Proceedings of the 2004 Autumn Annual Conference of Korea Institute Construction Engineering and Management, Seoul, Korea, 22 October 2004; pp. 515–520. [Google Scholar]
  13. Kim, M.; Yoon, I.; Kim, N.; Park, M.; Ahn, C.; Jung, M. A study on virtual environment platform for autonomous tower crane. Korean J. Constr. Eng. Manag. 2022, 23, 3–14. [Google Scholar] [CrossRef]
  14. Kale, S.; Arditi, D. Diffusion of ISO 9000 certification in the precast concrete industry. Constr. Manag. Econ. 2006, 24, 485–495. [Google Scholar] [CrossRef]
  15. Polat, G. Factors affecting the use of precast concrete systems in the United States. J. Constr. Eng. Manag. 2008, 134, 169–178. [Google Scholar] [CrossRef]
  16. Yee, A.A.; Eng, H.D. Structural and economic benefits of precast/prestressed concrete construction. PCI J. 2001, 46, 34–42. [Google Scholar] [CrossRef]
  17. Yun, W.G.; Shin, E.Y.; Kang, T.K. Analysis of Factors for Improvement of Economic Feasibility of Construction Cost to Spread Application of OSC Construction Method for Apartment Housing. Korean J. Constr. Eng. Manag. 2021, 22, 55–63. [Google Scholar] [CrossRef]
  18. Kang, H.J. A Study of Ship Design Process Optimization in a Concurrent Engineering Environment. Master’s Thesis, Seoul National University, Seoul, Republic of Korea, 2008. [Google Scholar]
  19. Lim, J.; Kim, S. Evaluation of CO2 emission reduction effect using in-situ production of precast concrete components. J. Asian Archit. Build. Eng. 2020, 19, 176–186. [Google Scholar] [CrossRef]
  20. Lim, J.; Kim, J.J. Dynamic optimization model for estimating in-situ production quantity of PC members to minimize environmental loads. Sustainability 2020, 12, 8202. [Google Scholar] [CrossRef]
  21. Lim, J.; Kim, S.; Kim, J.J. Dynamic simulation model for estimating in-situ production quantity of PC members. Int. J. Civ. Eng. 2020, 18, 935–950. [Google Scholar] [CrossRef]
  22. Guo, H.; Zhou, Y.; Pan, Z.; Zhang, Z.; Yu, Y.; Li, Y. Automated selection and localization of mobile cranes in construction planning. Buildings 2022, 12, 580. [Google Scholar] [CrossRef]
  23. Kang, S.; Miranda, E. Planning and visualization for automated robotic crane erection processes in construction. Autom. Constr. 2006, 15, 398–414. [Google Scholar] [CrossRef]
  24. Lacey, A.W.; Chen, W.; Hao, H.; Bi, K. Structural response of modular buildings–An overview. J. Build. Eng. 2018, 16, 45–56. [Google Scholar] [CrossRef]
  25. Jang, J.Y.; Cho, K.W.; Koo, C.; Lee, C.; Kim, T. Importance and Performance Analysis on Factors of PC Component Allocation and Loading Planning. Korean J. Constr. Eng. Manag. 2022, 22, 53–62. [Google Scholar] [CrossRef]
  26. Olearczyk, J.; Al-Hussein, M.; Bouferguene, A.; Telyas, A. 3D-modeling for crane selection and logistics for modular construction on-site assembly. In Computing in Civil Engineering; American Society of Civil Engineers: Reston, VA, USA, 2012; pp. 445–452. [Google Scholar] [CrossRef]
  27. Lim, J.; Park, K.; Son, S.; Kim, S. Cost reduction effects of in-situ PC production for heavily loaded long-span buildings. J. Asian Archit. Build. Eng. 2020, 19, 242–253. [Google Scholar] [CrossRef]
  28. Lei, Z.; Han, S.; Bouferguène, A.; Taghaddos, H.; Hermann, U.; Al-Hussein, M. Algorithm for mobile crane walking path planning in congested industrial plants. J. Constr. Eng. Manag. 2015, 141, 05014016. [Google Scholar] [CrossRef]
  29. Tam, C.M.; Tong, T.K.L.; Chan, W.K.W. Genetic algorithm for optimizing supply locations around tower crane. J. Constr. Eng. Manag. 2001, 127, 315–321. [Google Scholar] [CrossRef]
  30. Al-Hussein, M.; Alkass, S.; Moselhi, O. Optimization algorithm for selection and on site location of mobile cranes. J. Constr. Eng. Manag. 2005, 131, 579–590. [Google Scholar] [CrossRef]
  31. Safouhi, H.; Mouattamid, M.; Hermann, U.; Hendi, A. An algorithm for the calculation of feasible mobile crane position areas. Autom. Constr. 2011, 20, 360–367. [Google Scholar] [CrossRef]
  32. Hanna, A.S.; Lotfallah, W.B. A fuzzy logic approach to the selection of cranes. Autom. Constr. 1999, 8, 597–608. [Google Scholar] [CrossRef]
  33. Sawhney, A.; Mund, A. Adaptive probabilistic neural network-based crane type selection system. J. Constr. Eng. Manag. 2002, 128, 265–273. [Google Scholar] [CrossRef]
  34. Wu, D.; Lin, Y.; Wang, X.; Wang, X.; Gao, S. Algorithm of crane selection for heavy lifts. J. Comput. Civ. Eng. 2011, 25, 57–65. [Google Scholar] [CrossRef]
  35. Al-Hussein, M.; Athar Niaz, M.A.; Yu, H.; Kim, H. Integrating 3D visualization and simulation for tower crane operations on construction sites. Autom. Constr. 2006, 15, 554–562. [Google Scholar] [CrossRef]
  36. Lin, Y.; Wu, D.; Wang, X.; Wang, X.; Gao, S. Statics-based simulation approach for two-crane lift. J. Constr. Eng. Manag. 2012, 138, 1139–1149. [Google Scholar] [CrossRef]
  37. Taghaddos, H.; AbouRizk, S.; Mohamed, Y.; Hermann, U. Simulation-based auction protocol for resource scheduling problems. J. Constr. Eng. Manag. 2012, 138, 31–42. [Google Scholar] [CrossRef]
  38. Taghaddos, H.; Hermann, U.; AbouRizk, S.; Mohamed, Y. Simulation-based multiagent approach for scheduling modular construction. J. Comput. Civ. Eng. 2014, 28, 263–274. [Google Scholar] [CrossRef]
  39. Al-Bahnassi, H.; Hammad, A. Near real-time motion planning and simulation of cranes in construction: Framework and system architecture. J. Comput. Civ. Eng. 2012, 26, 54–63. [Google Scholar] [CrossRef]
  40. Sivakumar, P.L.; Varghese, K.; Babu, N.R. Automated path planning of cooperative crane lifts using heuristic search. J. Comput. Civ. Eng. 2003, 17, 197–207. [Google Scholar] [CrossRef]
  41. Zhang, C.; Hammad, A. Multiagent approach for real-time collision avoidance and path replanning for cranes. J. Comput. Civ. Eng. 2012, 26, 782–794. [Google Scholar] [CrossRef]
  42. Lei, Z.; Taghaddos, H.; Hermann, U.; Al-Hussein, M. A methodology for mobile crane lift path checking in heavy industrial projects. Autom. Constr. 2013, 31, 41–53. [Google Scholar] [CrossRef]
  43. Lei, Z.; Taghaddos, H.; Olearczyk, J.; Al-Hussein, M.; Hermann, U. Automated method for checking crane paths for heavy lifts in industrial projects. J. Constr. Eng. Manag. 2013, 139, 04013011. [Google Scholar] [CrossRef]
  44. Hasan, S.; Zaman, H.; Han, S.; Al-Hussein, M.; Su, Y. Integrated building information model to identify possible crane instability caused by strong winds. In Proceedings of the Construction Research Congress, West Lafayette, Indiana, 21–23 May 2012; American Society of Civil Engineers: Reston, VA, USA, 2012; pp. 1281–1290. [Google Scholar] [CrossRef]
  45. Huang, C.; Wong, C.K.; Tam, C.M. Optimization of tower crane and material supply locations in a high-rise building site by mixed-integer linear programming. Autom. Constr. 2011, 20, 571–580. [Google Scholar] [CrossRef]
  46. Al-Hussein, M.; Alkass, S.; Moselhi, O. An algorithm for mobile crane selection and location on construction sites. Constr. Innov. 2001, 1, 91–105. [Google Scholar] [CrossRef]
  47. Hasan, S.; Al-Hussein, M.; Hermann, U.H.; Safouhi, H. Interactive and dynamic integrated module for mobile cranes supporting system design. J. Constr. Eng. Manag. 2010, 136, 179–186. [Google Scholar] [CrossRef]
  48. Moselhi, O.; Alkass, S.; Al-Hussein, M. Innovative 3D-modelling for selecting and locating mobile cranes. Eng. Constr. Archit. Manag. 2004, 11, 373–380. [Google Scholar] [CrossRef]
  49. Reddy, H.R.; Varghese, K. Automated path planning for mobile crane lifts. Comput. Aid. Civ. Infrastruct. Eng. 2002, 17, 439–448. [Google Scholar] [CrossRef]
  50. Chang, Y.; Hung, W.; Kang, S. A fast path planning method for single and dual crane erections. Autom. Constr. 2012, 22, 468–480. [Google Scholar] [CrossRef]
  51. Son, S.; Lim, J.Y.; Kim, S.K. Erection simulation of steel connected precast concrete components for long span and heavy loaded logistics buildings. In Proceedings of the 3rd World Congress on Civil, Structural, and Environmental Engineering, CSEE, Budapest, Hungary, 8–10 April 2018. [Google Scholar] [CrossRef]
  52. Lee, H.-H.; Kim, K.-H.; Son, S.; Park, K.; Kim, S. Time reduction effects of steel connected precast concrete components for heavily loaded long-span buildings. J. Civ. Eng. Manag. 2020, 26, 160–174. [Google Scholar] [CrossRef]
  53. Nawy, E.G. Concrete Construction Engineering Handbook; CRC Press: Boca Raton, FL, USA, 2008. [Google Scholar] [CrossRef]
  54. Lim, C.Y.; Joo, J.K.; Lee, G.J.; Kim, S.K. In-situ production analysis of composite precast concrete members of green frame. J. Korea Inst. Build. Constr. 2011, 11, 501–514. [Google Scholar] [CrossRef]
  55. Kim, S.H.; Choi, E.G.; Kim, S.K.; Lee, S.H. A case study of the improvement of the structural work of a logistics facility by using PC member. J. Korea Inst. Build. Constr. 2010, 10, 127–135. [Google Scholar] [CrossRef]
  56. Park, S.; Kim, T.W.; Son, B. Quantitative Analysis of Construction Site Layout: A Usability Evaluation Study. Korea J. Constr. Eng. Manag. 2022, 23, 34–42. [Google Scholar] [CrossRef]
  57. Lee, J.H.; Tae, Y.H.; Baek, S.H.; Kim, K. A study of improvements in the standards of cost estimate for the new excellent technology in construction. Korea J. Constr. Eng. Manag. 2022, 23, 65–76. [Google Scholar] [CrossRef]
Figure 1. Erection of PC members using crane.
Figure 1. Erection of PC members using crane.
Buildings 14 00011 g001
Figure 2. Site condition analysis.
Figure 2. Site condition analysis.
Buildings 14 00011 g002
Figure 3. Actual erection process of case project: (a) D + 1, (b) D + 35, (c) D + 70, (d) D + 105, (e) D + 140, (f) D + 172.
Figure 3. Actual erection process of case project: (a) D + 1, (b) D + 35, (c) D + 70, (d) D + 105, (e) D + 140, (f) D + 172.
Buildings 14 00011 g003
Figure 4. Algorithm for crane-moving path calculation.
Figure 4. Algorithm for crane-moving path calculation.
Buildings 14 00011 g004
Figure 5. Crane location plan: (a) crane path, (b) PC member position definition on sample ⓐ.
Figure 5. Crane location plan: (a) crane path, (b) PC member position definition on sample ⓐ.
Buildings 14 00011 g005
Figure 7. Liftable PC column analysis.
Figure 7. Liftable PC column analysis.
Buildings 14 00011 g007
Figure 8. Crane-moving process for erection of PC members.
Figure 8. Crane-moving process for erection of PC members.
Buildings 14 00011 g008
Figure 9. Sequence algorithm for member erection.
Figure 9. Sequence algorithm for member erection.
Buildings 14 00011 g009
Figure 10. Trajectory distance on the first floor.
Figure 10. Trajectory distance on the first floor.
Buildings 14 00011 g010
Figure 11. Trajectory distance on the second floor.
Figure 11. Trajectory distance on the second floor.
Buildings 14 00011 g011
Figure 12. Trajectory distance on the third floor.
Figure 12. Trajectory distance on the third floor.
Buildings 14 00011 g012
Table 1. The shape details of PC members.
Table 1. The shape details of PC members.
PC TypeWidth (m)Length (m)Height (m)Volume (m3)Weight (ton)
Column0.8–1.70.8~1.09.25.9~15.614.2~37.4
Beam0.5~1.31.0~1.31.0–2.611.0–34.826.4~83.6
Table 2. Definition of position coordinates of the PC column.
Table 2. Definition of position coordinates of the PC column.
ClassificationC1C2C3C4C5C6C7C8C9C10C11C12
x-coordinate112233441122334411223344
y-coordinate22222222111111110000
z-coordinate101010101010101010101010
Table 3. Calculation of trajectory distance of column member.
Table 3. Calculation of trajectory distance of column member.
ClassificationUnitC1C2C3C4C5C6C7C8C9C10C11C12
Horizontal rotation angleDegree15313512411713511710810490909090
Horizontal rotation distancem887871677867626052525252
Vertical rotation angleDegree0.090.020.070.180.180.090.020.140.230.120.000.12
Vertical rotation distancem927181892142311012
Total trajectory distance of the boomm978078859676647375635264
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Kim, S.; Oh, J.; Lim, J. Development of an Algorithm for Crane Trajectory Distance Calculation for Erection of Precast Concrete Members. Buildings 2024, 14, 11. https://doi.org/10.3390/buildings14010011

AMA Style

Kim S, Oh J, Lim J. Development of an Algorithm for Crane Trajectory Distance Calculation for Erection of Precast Concrete Members. Buildings. 2024; 14(1):11. https://doi.org/10.3390/buildings14010011

Chicago/Turabian Style

Kim, Sunkuk, Jinhyuk Oh, and Jeeyoung Lim. 2024. "Development of an Algorithm for Crane Trajectory Distance Calculation for Erection of Precast Concrete Members" Buildings 14, no. 1: 11. https://doi.org/10.3390/buildings14010011

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop