5.1. Crane Lifting Range Analysis
Before starting the PC member erection simulation based on the analyzed site design drawing and established erection schedule, it is necessary to accurately analyze the lifting range of the applied crane. The 550 t crawler crane adopted in this study is defined by the boom and jib, as shown in
Figure A1a, and the working radius is set as shown in
Figure A1b. The working radius of a 550 t crawler crane can be analyzed using this information. The boom starts at a horizontal length of 1.7 m. Given that the boom length is 36 m and the maximum angle is 86°, a value of 2.51 m is derived by calculating the horizontal length at the maximum angle of the boom using Equation (10). Moreover, given that the jib length is 54 m and the maximum angle is 71°, 17.58 m is derived when the horizontal length is calculated at the maximum angle of the jib using Equation (11). Hence, as the boom is located at a horizontal length of 1.7 m, and the horizontal lengths of the boom and jib are 2.51 m and 17.58 m, respectively, the horizontal length is 21.79 m when the maximum angle of the 36 m boom is reached, as shown in Equation (12). Hence, the minimum operating distance of the crane is 21.79 m, and the crane can erect members located at 21.79 m or more.
The boom starts at a horizontal length of 1.7 m. As the boom length is 36 m and the minimum angle is 65°, a length of 15.21 m is derived by calculating the horizontal length at the minimum angle of the boom, as shown in Equation (13). Moreover, given that the jib length is 54 m and the minimum angle is 15°, a length of 52.16 m is derived by calculating the horizontal length at the minimum angle of the jib, as shown in Equation (14). Hence, as the boom is located at a horizontal length of 1.7 m and the horizontal lengths of the boom and jib are 15.21 m and 52.16 m, respectively, the horizontal length is 69.07 m when the minimum angle of 36 m boom is reached, as shown in Equation (15). Consequently, the maximum operation distance of the crane is 69.07 m, and the crane can erect members located at 69.07 m or less.
The liftable columns are analyzed based on the working radius of the crane, as illustrated in
Figure 7. Thus, columns of 21.76 m or more and 69.07 m or less are derived based on the boom head of the crane. This confirms that the assumption regarding the definition of the column position is incorrect, as is shown in
Table 1, which was set at the beginning of the study. For example, the coordinates of C9 in
Figure 6b and
Table 1 are (11, 0, 10), which is a column located at a horizontal distance of 11 m. As this column is not located at 21.76 m or more and 69.07 m or less, it cannot be erected with the crawler crane used in this study. The crane-moving process analyzed in
Figure 7 is shown in
Figure 8. First, a crane is installed 55 m from the members to be erected; second, the members are erected in a cascade manner. The members are installed via the sequential movement of the crane, which moves by 11 m each time. Finally, the erection of the PC members is completed by positioning the crane at 22 m, considering the crane lifting distance. In other words, the crane position coordinates (0, 0, 0) are newly redefined as the crane moves by 11 m.
5.3. Simulation Results
Before starting the simulation, the position of the trailer was selected as (0, −33, 92). To reflect the position of the trailer, the head of the boom was positioned 33 m from the crane, and the lifting of the PC members began at this position. This position was calculated as 92 m in height due to the 97.74 m length of the boom. The trajectory distance of each column member can be calculated using Equations (1)–(7) based on the coordinate values (see
Table 1) of the PC member position definition on sample ⓐ in
Figure 6b as shown
Table 3. The horizontal rotation angle is calculated using Equation (1), and the horizontal rotation distance is calculated using Equation (2). Moreover, the vertical rotation angle is calculated using Equations (4) and (5), and the vertical rotation distance is calculated using Equation (6). Finally, the total trajectory distance of the boom can be calculated using Equation (7). For example, the horizontal rotation angle of C1 among the column members is 153°, and the horizontal trajectory distance at this angle is 88 m. The vertical rotation angle of this member is 0.09°, and the vertical trajectory distance is 9 m. Hence, the total trajectory distance is 97 m. However, according to the liftable PC column analysis results in
Figure 7, only columns at 21.76 m or more and 69.07 m or less can be lifted. Hence, not all values derived from
Table 2 can be applied. Therefore, only C3, C4, C7, C8, C11, and C12 can be lifted at the crane position.
Based on the aforementioned analysis results,
Figure 10,
Figure 11 and
Figure 12 show the calculation of the trajectory distance of the column members for the crane path from the first to the third floor. The trajectory distance of each member complies with the rules of the crane-moving process for PC member erection shown in
Figure 8, and the total trajectory distance is determined to be 183,575 m. The location with the farthest linear distance from the crane is expected to show the largest trajectory distance. However, it is observed that the trajectory distance is not large even if the linear distance from the crane is large. The location with the largest trajectory distance corresponds to that with the largest horizontal movement, where it shows the same x-coordinate as the trailer. Furthermore, the trajectory distance is not the smallest when the linear distance is the smallest. Among the members that can be lifted by the crane, the member at the position where the horizontal movement is smallest shows the smallest value. The trajectory distance can be easily calculated because it shows a consistent pattern based on the crane movement. This is due to the fact that the members are positioned at distances of 11 or 18 m due to the characteristics of large logistics buildings.
The crane is removed by sequentially erecting its members. However, as the last members of the second and third floors are not required to be erected in a cascade manner, as is shown in
Figure 11 and
Figure 12, they can be simultaneously erected without moving the crane. However, additional y-column members must be installed on the opposite side of Zone B. Thus, their erection must be completed by moving them. Moreover, given that the third floor is the last floor of the PC structure, PC members can be erected without considering the connection with other floors, as shown in
Figure 12.
The average unit erection time for each PC member at the case site is 40 min, 15 min, and 10 min for columns, beams, and slabs, respectively. The number of members for columns, beams, and slabs is 850, 1371, and 4032, respectively. Furthermore, the actual erection time is 210 calendar days, and the rotation distance of the crane is 20 m/min. After excluding the time required to fix the position of the members, the actual and simulated durations required for PC member erection are 172 and 158 days, respectively. Thus, a 13.99% reduction in the construction period is possible.
With respect to the cost comparison, labor, material, and equipment costs are summed [
57] using Equations (18) and (19). Labor, material, and equipment costs are calculated using Equations (20)–(22). The actual cost of PC member erection in
Table 4 denotes the results of the calculation using the actual input quantity. The simulation-calculated cost in
Table 5 shows the results of the calculation reflecting the actual cost. With respect to the unit price of the labor cost, the amount from the “Construction Industry Wage Survey Report (Market Wage Unit Price) applied to the first half of 2022” was applied. Material and equipment costs were calculated based on the unit price applied in the field. Hence, the actual cost was USD 6,221,704, and the simulation-calculated cost was USD 5,710,335. Therefore, when applying the model developed in this study, the cost can be reduced by 8.33% when compared to the actual construction cost. In terms of equipment cost, the actual and simulation-calculated costs accounted for 89% and 90%, respectively, showing the highest proportions of construction costs as shown
Table 4 and
Table 5. This implies that the daily rent for the crane accounted for the highest percentage. Therefore, to reduce construction costs, the minimum rental period should be applied by deriving accurate dates when the crane is used before starting construction.
Ct = total cost of the boom trajectory;
Cd = direct cost of the boom trajectory;
Ci = indirect cost of the boom trajectory;
Cl = labor cost of the boom trajectory;
Cm = material cost of the boom trajectory;
Ce = equipment cost of the boom trajectory.
Cl = labor cost of the boom trajectory;
Cm = material cost of the boom trajectory;
Ce = equipment cost of the boom trajectory;
Qci = quantity of the ith columns;
Ccul = unit labor cost for column erection;
Qbi = number of ith beams;
Cbul = unit labor cost for beam erection;
Qsi = number of ith slabs;
Csul = unit labor cost for slab erection;
Ccum = unit material cost for column erection;
Cbum = unit material cost for beam erection;
Csum = unit material cost for slab erection;
Ccue = unit equipment cost for column erection;
Cbue = unit equipment cost for beam erection;
Csue = unit equipment cost for slab erection;
i = number of erected ith columns (1, …, n);
j = number of erected ith beam members (1, …, m);
k = number of erected ith slab members (1, …, l).
Table 4.
Actual costs for erection of PC members.
Table 4.
Actual costs for erection of PC members.
Item | Unit | Quantity | Unit Price (USD) | Amount (USD) |
---|
Labor cost | Equipment operator | Day | 172 | 229 | 39,388 |
Common labor | Day | 516 | 154 | 79,464 |
Material cost | Diesel | L | 12,900 | 1.83 | 25,437 |
Equipment fee | Crane (550 ton) | Day | 430 | 13,000 | 5,590,000 |
Indirect cost | 487,415 |
Total | 6,221,704 |
Table 5.
Simulation-calculated costs for the erection of PC members.
Table 5.
Simulation-calculated costs for the erection of PC members.
Item | Unit | Quantity | Unit Price (USD) | Amount (USD) |
---|
Labor cost | Equipment operator | Day | 158 | 229 | 36,182 |
Common labor | Day | 474 | 154 | 72,996 |
Material cost | Diesel | L | 10,275 | 1.83 | 18,803 |
Equipment fee | Crane (550 ton) | Day | 395 | 13,000 | 5,135,000 |
Indirect cost | 447,353 |
Total | 5,710,335 |
CO
2 emissions were calculated, as shown in
Table 6, using the labor, material, and equipment costs and the indirect cost calculated in
Table 4 and
Table 5. The CO
2 emissions corresponding to the direct cost were calculated using the actual input labor, oil, and electricity use. Furthermore, the CO
2 emissions corresponding to indirect costs were calculated using the actual input lighting, heating use, and environmental conservation. Consequently, when the model developed in this study is applied, 25.99% of CO
2 emissions can be reduced when compared to actual construction. Equations (23)–(26) show that the total CO
2 emissions can be derived by multiplying the number of PC members by the unit CO
2 emission of each item. In terms of oil use, the actual and simulation-calculated plans accounted for 99% and 98%, respectively, indicating high CO
2 emissions.
CEt = total CO2 emissions;
CEc = CO2 emissions of the column;
CEb = CO2 emissions of the beam;
CEs = CO2 emissions of the slab;
Qci = number of ith columns;
CEul = unit CO2 emissions of labor;
CEuo = unit CO2 emissions of oil;
CEuel = unit CO2 emissions of electricity;
CEulh = unit CO2 emissions of lighting and heating;
CEuec = unit CO2 emissions of environmental conservation;
Qbi = number of ith beams;
Qsi = number of ith slabs;
i = number of erected ith columns (1, …, n);
j = number of erected ith beams (1, …, m);
k = number of erected ith slabs (1, …, l).
Table 6.
Comparison of actual and simulation-calculated CO2 emissions (unit: kg).
Table 6.
Comparison of actual and simulation-calculated CO2 emissions (unit: kg).
Item | Actual | Simulation Calculated |
---|
Labor | 372 | 341 |
Oil use | 73,004 | 53,965 |
Electricity use | 427 | 307 |
Lighting and heating use | 197 | 153 |
Environmental conservation | 110 | 83 |
Total | 74,110 | 54,850 |
Energy consumption was calculated, as shown in
Table 7, using the oil and electricity consumption presented in
Table 4 and
Table 5. The electrical energy consumption was calculated using Equation (27), and the actual diesel input was converted into the SI base unit for energy. For the capacity of the 550 t crane, 397 kW was applied, and for the energy conversion value of diesel, 41,090/m
3 was applied. Hence, the simulation-calculated plan for member erection can reduce energy consumption by 26.01%. In terms of oil use, the actual and simulated plans accounted for more than 99%, indicating high energy consumption.
E = energy consumption;
P = power (kW);
t = time (s).
Table 7.
Comparison of actual energy consumption and simulation-calculated energy consumption (unit: MJ).
Table 7.
Comparison of actual energy consumption and simulation-calculated energy consumption (unit: MJ).
Item | Actual | Simulation Calculated |
---|
Oil use | 570,317 | 421,583 |
Electricity use | 2124 | 1951 |
Total | 572,441 | 523,534 |
The simulation-calculated plan shows a reduction effect in terms of construction time, cost, CO2 emissions, and energy use when compared with the actual plan. These ratios are not the same because the constituent items and composition ratios differ. Furthermore, CO2 emissions and energy consumption were reduced by 25.99% and 26.01%, respectively, indicating high reduction rates. Therefore, the minimization of the crane usage rate at a site has a considerable effect on preventing environmental pollution.