Research on the Initial Launching Technology of Subway Shield Tunneling in Complex Terrain and Numerical Simulation of Soil Deformation
Abstract
1. Introduction
2. Project Overview
2.1. Alignment Overview
- Left line: Starting/ending mileage ZDK17 + 464.160~ZDK18 + 658.895, short chainage 2.513 m, and a total length of 1192.222 m.
- Right line: Starting/ending mileage YDK17 + 464.986~YDK18 + 658.895, short chainage 0.084 m, and a total length of 1193.825 m.
- Left line: Starting/ending mileage ZDK18 + 658.895~ZDK19 + 669.658.
- Right line: Starting/ending mileage YDK18 + 658.895~YDK19 + 669.658.
2.2. Engineering Hydrogeology
2.3. Surrounding Environment
3. Analysis of Construction Difficulties and Key Points
3.1. Narrow Shield Launching Space
3.2. Shield Machine Passing Through Surrounding Buildings/Structures
- (1)
- Underpassing: improper operation during underpassing may cause settlement/cracking of adjacent buildings and ground settlement.
- (2)
- Overpassing: inadequate parameter control during overpassing may increase soil disturbance leading to soil chamber pressure loss and ground collapse.
- (3)
- Side passing: when passing pile foundations laterally, the lateral pressure from the tunneling may cause pile deformation, endangering bridge/building structures.
4. Shield Launch and Tunneling Technology
4.1. Pre-Tunneling Preparations
4.2. Tunneling Parameter Design
4.3. Construction Transportation
- (1)
- The construction transportation during the right line launch phase consists of three main parts, as follows: horizontal transportation inside the tunnel, transverse passage shifting transportation, and vertical transportation through the shaft.Horizontal Transportation Inside the Tunnel: a single track with 43 kg/m steel rails is laid inside the tunnel for transporting muck, segments, and other materials. The shield machine uses small muck buckets for muck removal, with horizontal transportation carried out by a 1-set marshalling train composed of a 45 t traction locomotive, one flatbed car for segment transportation, and one flatbed car for general cargo, as shown in Figure 1.
- (2)
- Shifting Transportation in the Transverse Passage: during the right line launch phase, materials and muck required for shield tunneling are connected to the ground via the muck shaft and the No. 1 transverse passage. Since the muck shaft is located outside the main tunnel alignment, direct vertical transportation at the muck shaft is infeasible. Therefore, lifting devices and transportation devices must be installed within the No. 1 transverse passage to ensure material/muck transportation, as shown in Figure 2.
- (3)
- Vertical Transportation: a 16 t gantry crane is installed above the muck shaft to transport materials required for shield tunneling, and to dump the muck into the muck pit.
4.4. Segment Installation
4.5. Synchronous and Secondary Grouting
- (1)
- Synchronous GroutingCement mortar is used as a synchronous grouting material. P.O 42.5 ordinary Portland cement is employed to enhance the corrosion resistance of the grout stone body. This ensures the segments are encapsulated within a corrosion-resistant grout matrix to mitigate groundwater corrosion of the segment concrete. Based on previous similar tunnel projects, the synchronous grouting mix proportion is determined as shown in Table 3.Synchronous grouting is conducted simultaneously with shield tunneling using four pipelines (four injection points) symmetrically injected by A-fluid piston pumps and B-fluid screw pumps.To ensure effective filling of the annular gap while preventing segment deformation/damage from grouting, the grouting pressure is set at 0.2~0.6 MPa based on calculations and experience. For full-face rock strata, the grouting volume is 1~1.1 times the theoretical volume of the annular gap, resulting in a per-ring (1.5 m) grouting volume Q = 4.31~4.74 m3. The actual grouting volume is adjusted according to the settlement monitoring data measured during tunneling. The synchronous grouting rate must match the tunneling speed, with the average grouting rate determined by completing the grouting volume for one 1.5 m ring within the time taken for shield advancement. A dual-parameter control criteria is adopted, that is, grouting is deemed compliant when both the grouting pressures reach the set value and the grouting volume exceeds 90% of the design value.
4.6. Shield Alignment Control and Adjustment
- (1)
- Control of the shield direction. The shield attitude is monitored using a millimeter measurement system and a manual measurement as an auxiliary. This system is equipped with guidance, automatic positioning, excavation program software, and a display. This can dynamically display at all times, the deviation and the trend of the shield’s current position from the designed tunnel axis in the shield machine’s main control room. Based on this, the excavation direction of the shield machine is adjusted to keep it within the allowable deviation range. As the rear reference point of the shield guidance system moves forward with the shield advancement, precise positioning must be carried out through a manual measurement. To ensure the accuracy and reliability of the advancement direction, a manual measurement is conducted twice a week to verify the measurement data of the automatic guidance system, and to recheck the position and attitude of the shield machine. This ensures the correct excavation direction of the shield.The shield’s excavation direction is controlled by operating the shield’s thrust cylinders in different zones. When advancing on an uphill section, the thrust of the lower cylinders of the shield is appropriately increased; when advancing on a downhill section, the thrust of the upper cylinders is appropriately increased; when advancing on a left-turn curve, the thrust of the right cylinders is appropriately increased; when advancing on a right-turn curve, the thrust of the left cylinders is appropriately increased; when advancing on a straight and level section, the thrust of all cylinders should be kept as consistent as possible i.e., the same.
- (2)
- Adjustment and correction of the shield’s excavation attitude. The shield’s attitude is adjusted and deviations are corrected by operating the thrust cylinders in the different zones. For sharp curves and slope change sections, if necessary, the shield’s overcutting tools can be used for local overcutting to correct the deviation. When the rolling exceeds the limit, the shield will automatically alarm. At this time, the shield’s cutterhead should be reversed to correct the rolling deviation.
4.7. Portal Sealing
5. Numerical Simulation Analysis of Soil Layer Deformation
5.1. Model Establishment
5.2. Construction Stages
5.3. Analysis of Soil Layer Deformation Model
6. Conclusions
- Tailored Shield Parameters: for three working conditions (contact reinforcement zone, entry reinforcement zone, and exit reinforcement zone) shield tunneling parameters were specifically designed to control any environmental disturbances within acceptable limits.
- Multi-Modal Transportation: three transportation methods (in-tunnel horizontal transport, cross-passage transfer transport, and vertical transport) ensured efficient segment delivery and muck disposal in spatially constrained environments.
- Grouting Optimization: post-reinforcement synchronous grouting using cement mortar (P.O42.5 cement) effectively mitigated groundwater erosion of the concrete segments, enhancing construction safety.
- Soil Reinforcement Efficacy: numerical modeling revealed that soil reinforcement significantly reduced surface deformation. The maximum settlement decreased from 2.33 mm (unreinforced) to 0.782 mm (reinforced), a reduction of 1.548 mm, while the maximum uplift decreased from 2.03 mm to 1.87 mm (a reduction of 0.16 mm). These results validate the effectiveness of soil reinforcement for minimizing ground deformation.
Author Contributions
Funding
Data Availability Statement
Conflicts of Interest
References
- Lijie, J.; Yixin, W.; Yanming, S.; Hang, Y.; Lianhui, J. Design and analysis of tool changing robot for shield machine in narrow space. J. Railw. Sci. Eng. 2023, 20, 3081–3092. [Google Scholar]
- Zihao, Z.; Shuying, W.; Jiazheng, Z.; Zhunlin, N.; Tongming, Q. Automatic identification method of improved state of shield dreg soil based on laser scanning technology. J. Cent. South Univ. (Sci. Technol.) 2023, 54, 3975–3986. [Google Scholar]
- Huilong, W.; Chuanwei, L.; Liyan, L.; Qiang, Z. Application of automatic monitoring and early warning technology in subway shield engineering. Constr. Technol. 2023, 52, 85–90. [Google Scholar]
- Xian, L.; Zhenkun, G.; Pengli, W.; Hong, C. Study on the influence of channel opening on mechanical behavior of super large diameter shield railway station structure and structural optimization. China Civ. Eng. J. 2021, 54, 114–122. [Google Scholar]
- Li, Z.D. Research on key technology of multi-shield receiving in narrow oblique cross channel. Tunn. Constr. 2021, 41 (Suppl. S1), 458–463. [Google Scholar]
- Haisheng, L. Study on the Force Characteristics and Safety of Embedded Steel Plates for Shield Lateral Launching. Mod. Urban Rail Transit 2023, 9, 63–67. [Google Scholar] [CrossRef]
- Weining, L.; Yanfeng, S.; Furong, L. Prediction and Analysis of Environmental Impact Caused by Station Construction of Beijing Metro Fuba Line. China Civ. Eng. J. 2000, 4, 47–50. [Google Scholar] [CrossRef]
- Huang, R.Q.; Qi, G.Q. Study on the environmental impact of subway tunnel construction using shield tunneling method. Chin. J. Rock Mech. Eng. 2003, (Suppl. S1), 2464–2468. [Google Scholar]
- Zhan, Y.M. Study on the separation technology of narrow space shield in deep tunnel—Taking Dong Hao Yong test section of deep tunnel drainage system in Guangzhou as an example. Ind. Constr. 2023, 53 (Suppl. S2), 487–490. [Google Scholar]
- Chen, S.; Huang, X.; Yang, J.; Xiao, Z. Key technologies for the initiation of four large diameter mud shield bidirectional split shafts in coastal shafts: A case study of Fuzhou Binhai Express Line tunnel section. Tunn. Constr. 2022, 42 (Suppl. S2), 449–457. [Google Scholar]
- Zhong, Z.Q. Construction technique of earth pressure balance shield construction in narrow space: A case study of shield tunnel of Singapore Metro C715 project. Tunn. Constr. 2020, 40, 1197–1202. [Google Scholar]
- Xingwei, B.; Bocun, Z.; Feiming, W.; Peng, D.; Ziyang, Q. Study on the construction technology of shield construction under the condition of narrow space. Tunn. Constr. 2018, 38 (Suppl. S2), 292–297. [Google Scholar]
- Junqi, R.; Pengju, X.; Congyu, G.; Hongzhi, L. Study on the construction technology of mud-water shield split-off in water-rich sand pebble formation. Water Resour. Hydropower Eng. 2022, 53 (Suppl. S2), 180–187. [Google Scholar]
- Xiong, D.D.; Chen, X.L. Application of sludge pumping technology in the initiation of separate body of earth pressure balancing shield machine. Urban Mass Transit 2021, 24, 102–107. [Google Scholar]
- GB 50446-2017; Code for Construction of Shield Tunneling Method. Ministry of Housing and Urban–Rural Development of the People’s Republic of China: Beijing, China; State Administration for Market Regulation: Beijing, China, 2017.
Buildings/Structures | Starting/Ending Mileage | Relationship with Shield Section |
---|---|---|
Metro Line 11 Section Tunnel | YDK17 + 465~YDK17 + 480 ZDK17 + 472~ZDK17 + 508 | Overpasses (with a clear tunnel spacing of approximately 2.773 m) |
Sima Yong Box Culvert | YDK17 + 465~YDK17 + 492 ZDK17 + 464~ZDK17 + 542 | Underpasses (vertical spacing of 15.15 m) |
Guangzhou Children’s Palace Gymnasium & Swimming Pool | ZDK17 + 578~ZDK17 + 615 | Passes by (approximately 0.181 m from the left tunnel) |
Dongfeng West Viaduct Widening Project No. 1 Pedestrian Overpass | YDK17 + 713~YDK17 + 760 ZDK17 + 672~ZDK17 + 774 | Passes by (3.8 m from the right tunnel) |
Renmin Road Viaduct Project (North Section) | YDK17 + 858~YDK17 + 868 ZDK17 + 865~ZDK17 + 869 | Passes by (1.45 m from left tunnel, 1.96 m from right tunnel) |
Renmin North Road-Dongfeng West Road Pedestrian Overpass | YDK17 + 900~YDK18 + 000 ZDK17 + 912~ZDK17 + 980 | Passes by (pile foundation is 3.732 m from the crown of the right tunnel) |
Jintongtai Building | YDK18 + 200~YDK18 + 240 | Passes by (4.44 m from the right tunnel) |
Guangzhou Municipal People’s Hospital Outpatient Building | YDK18 + 256~YDK18 + 290 | Passes by (3.399 m from the right tunnel) |
Dongfeng Middle Road-Panfu Interchange | YDK18 + 193~YDK18 + 471 ZDK18 + 193~ZDK18 + 471 | Underpasses and passes by (pile foundation is 0.46 m from the crown of the left tunnel) |
No. 9 Civil Air Defense Project | ZDK18 + 364.329 YDK18 + 361.365 | Overpasses (vertical clear distance of 1.116 m) |
Jiefang North Road Viaduct Project No. 1 Pedestrian Overpass | YDK18 + 600~YDK18 + 650 ZDK18 + 591~ZDK18 + 640 | Passes by (7.662 m from the right tunnel) |
Buildings/Structures | Starting/Ending Mileage | Relationship with Shield Section |
Jiefang North Road Viaduct | YDK18 + 651~YDK18 + 665 ZDK18 + 650~ZDK18 + 661 | Passes by (1.55 m from left tunnel, 1.5 m from right tunnel) |
Metro Line 2 | Underpasses (clear spacing from tunnel structure edge is 2.987 m) | |
Guangzhou Municipal People’s Congress Standing Committee Office Building | Passes by (clear distance of 4 m from right tunnel) | |
Guangdong Building | Passes by (clear distance of 18 m from right tunnel) | |
Jiaye Building | Passes by (clear distance of 6 m from right tunnel) | |
Guangdong Environmental Protection Building | Passes by (clear distance of 6 m from right tunnel) |
Working Condition | Parameter | Design Value |
---|---|---|
Approaching Reinforcement Zone | Advance Speed | 10~20 mm/min |
Thrust Force | 600~700 t | |
Cutter Head Torque | 2000~2500 kN·m | |
Earth Pressure | 0 | |
Muck Volume | 0 | |
Grouting Volume | 0 | |
Entering Reinforcement Zone | Advance Speed | 10~20 mm/min |
Thrust Force | 600~700 t | |
Cutter Head Torque | 2000~2500 kN·m | |
Earth Pressure | 0~1.5 bar | |
Muck Volume | 61.8~63.1 m3 | |
Grouting Volume | 10~20 mm/min | |
Exiting Reinforcement Zone | Advance Speed | 10~20 mm/min |
Thrust Force | 700~900 t | |
Cutter Head Torque | 2000~2500 kN·m | |
Earth Pressure | 1.5~1.8 bar | |
Muck Volume | 61.8~63.1 m3 | |
Grouting Volume | 5.6~7.8 m3 |
Cement (kg) | Fly Ash (kg) | Bentonite (kg) | Sand (kg) | Water (kg) |
---|---|---|---|---|
80~200 | 241~380 | 50~60 | 600~780 | 460~600 |
Material Name | Young’s Modulus (MPa) | Poisson’s Ratio | Unit Weight (kN/m3) | Cohesion (kPa) | Internal Friction Angle (°) |
---|---|---|---|---|---|
Artificial Fill | 18 | 0.4 | 17.5 | 17.5 | 22 |
Silt Sand | 23 | 0.35 | 18 | 4 | 30 |
Medium Coarse Sand | 70 | 0.35 | 19 | 8 | 34 |
Silt | 4 | 0.33 | 15.5 | 14 | 12 |
Silty Clay 11 | 13 | 0.3 | 18 | 30 | 22 |
2 Silty Clay 2 | 13 | 0.3 | 19 | 33 | 24 |
3 Silty Clay | 25 | 0.3 | 19 | 55 | 26 |
Fully Weathered Clayey Siltstone | 17 | 0.3 | 18 | 35 | 25 |
Material Name | Young’s Modulus (MPa) | Poisson’s Ratio | Unit Weight (kN/m3) | Cohesion (kPa) | Internal Friction Angle (°) |
Strongly Weathered Coarse Sandstone | 60 | 0.28 | 20 | 50 | 30 |
Strongly Weathered Clayey Siltstone | 70 | 0.3 | 20 | 40 | 28 |
Moderately Weathered Coarse Sandstone | 80 | 0.25 | 23 | 120 | 37 |
Moderately Weathered Clayey Siltstone | 30 | 0.25 | 20 | 70 | 30 |
Slightly Weathered Clayey Siltstone | 50 | 0.28 | 21 | 110 | 33 |
Concrete | 35,500 | 0.2 | 25 | ||
Shield Shell | 208,000 | 0.2 | 78 |
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |
© 2025 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/).
Share and Cite
Wang, J.; Li, H.; Li, X.; Nong, X.; Liu, C.; Yang, T. Research on the Initial Launching Technology of Subway Shield Tunneling in Complex Terrain and Numerical Simulation of Soil Deformation. Buildings 2025, 15, 2222. https://doi.org/10.3390/buildings15132222
Wang J, Li H, Li X, Nong X, Liu C, Yang T. Research on the Initial Launching Technology of Subway Shield Tunneling in Complex Terrain and Numerical Simulation of Soil Deformation. Buildings. 2025; 15(13):2222. https://doi.org/10.3390/buildings15132222
Chicago/Turabian StyleWang, Jiangka, Hui Li, Xujie Li, Xingzhong Nong, Chen Liu, and Tao Yang. 2025. "Research on the Initial Launching Technology of Subway Shield Tunneling in Complex Terrain and Numerical Simulation of Soil Deformation" Buildings 15, no. 13: 2222. https://doi.org/10.3390/buildings15132222
APA StyleWang, J., Li, H., Li, X., Nong, X., Liu, C., & Yang, T. (2025). Research on the Initial Launching Technology of Subway Shield Tunneling in Complex Terrain and Numerical Simulation of Soil Deformation. Buildings, 15(13), 2222. https://doi.org/10.3390/buildings15132222