Previous Article in Journal
Prediction of Electrical Resistivity of Concrete Containing Electric Arc Furnace Slag as Fine Aggregate Using Gene Expression Programming Method
Previous Article in Special Issue
Urban Polycentricity and Architectural Heritage: A PROMETHEE-Based Multicriteria Approach
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Life-Cycle Maintenance Cost Model for Concrete Bridges Using Markovian Deterioration Curves

by
Kleopatra Petroutsatou
1,
Theodora Vagdatli
1,*,
Nikolaos Louloudakis
1 and
Panagiotis Panetsos
2
1
Department of Civil Engineering, Aristotle University of Thessaloniki, Campus, GR 541 24 Thessaloniki, Greece
2
EGNATIA ODOS SA, GR 570 01 Thermi, Greece
*
Author to whom correspondence should be addressed.
Buildings 2025, 15(5), 807; https://doi.org/10.3390/buildings15050807 (registering DOI)
Submission received: 30 January 2025 / Revised: 25 February 2025 / Accepted: 28 February 2025 / Published: 2 March 2025

Abstract

:
Long-term deterioration of concrete bridges is a natural process that requires prudent maintenance actions throughout the bridge’s life-cycle. Nowadays, there is an ongoing effort to simulate such processes into practical models. One primary element for the model’s accuracy is the datasets used for its development. The gap between underestimated or overestimated and actual values could be narrowed by utilizing real-world datasets on bridge deterioration and rehabilitation obtained from systematic inspections over time in similar environments. Therefore, the present study aims to develop an empirical probabilistic model for precisely predicting the bridge’s future performance and suitably implementing maintenance strategies that facilitate sustainable management during bridge service life based on real data. Actual records of 72 concrete bridges from motorways in Northern Greece were collected, documenting different detected defect types, condition states, and associated maintenance costs over time. Two discrete-time Markov-chain models for the bridge’s superstructure and substructure were produced, allowing for the prediction of maintenance costs that align with the given structural condition throughout its operational life. A Chi-square test demonstrated the model’s applicability to similar datasets. This enables bridge managers to obtain a comprehensive overview of the bridge’s longitudinal performance and maintenance expenditures and adopt economically sustainable solutions for the bridge’s management.

1. Introduction

Transport infrastructure projects indisputably contribute to countries’ economies and development. In particular, bridges are vital links in the transportation network and the overall development of a nation’s economic activities. Nevertheless, a significant portion of the ageing bridges deteriorate steadily, owing to combined degradation factors, such as increased traffic volumes, extreme weather conditions, etc. [1,2]. Hence, precise deterioration prediction as well as thorough maintenance planning should be constantly prioritized to keep the bridges in an acceptable condition throughout their service life.
The gradual degradation process of bridge systems integrates various uncertainties deriving from material, damage mechanisms, climate, as well as design and maintenance risk parameters [3,4]. An accurate deterioration model is a fundamental management tool since it lays the foundation for the successful upcoming maintenance and cost estimation modules [5]. Compared to the deterministic models that export single point values for the future performance of bridge elements, the probabilistic methods are regarded as more suitable for capturing the inherent uncertainties of condition data, resulting in the development of more reliable infrastructure performance models [4,6,7]. Among the probabilistic methods used for infrastructure assets’ performance modeling, the Markov-chain models are considered the most adopted method [8]. Owing to its stochastic nature, the inherent uncertainty and randomness of the bridge’s performance can be captured adequately. For this reason, many existing bridge management systems (BMSs), including Pontis and BRIDGIT, have adopted the Markov-chain process to accurately model the bridge’s progressive deterioration [9,10,11].
Maintenance planning is a crucial aspect of infrastructure asset management that demands investigation from multiple perspectives, such as economic, engineering, environmental, etc. [12]. Due to bridge’s constructability and inspection issues as well as their exposure to intense climate conditions, bridges’ life-cycle economic expenses can be significantly high [13]. Moreover, the investigation of the most beneficial maintenance interventions remains a challenging issue for project managers because it is subject to multiple conflicting objectives, such as restricted maintenance and inspection budgets or optimization of bridge performance [14].
Bridge managers regularly undertake repair actions, either time-based or condition-based, to maintain the structure’s optimal performance. However, it is claimed that, in some cases, rehabilitation decisions lead to unnecessary over-safety levels and redundant consumption of financial resources. On top of that, the budgetary allocations are usually restricted, and administrative authorities should be quite cautious regarding the prioritization of projects requiring rehabilitation actions. To eliminate such instances, the concept is to restore the serviceability and safety of bridge assets up to sufficient levels over the life-cycle of the system with the limited available funds. The selection of the most cost-effective solution by forecasting bridge performance based on inspection data is a current issue that needs to be addressed.
The collection of on-site inspection datasets significantly impacts the accuracy of subsequent asset deterioration prediction models [15]. However, due to confidential issues and sensitivity in cost data provision by management companies, the extant papers of the literature body rarely deal with life-cycle maintenance cost analysis based on real datasets. The present study aims to address this issue by collecting and processing actual condition and cost datasets from 72 concrete bridges that serve the Greek road network. Therefore, the objective of the present study is to investigate the probabilistic deterioration of bridge components based on real inspection condition data and estimate the expected life-cycle maintenance costs based on actual rehabilitation actions for capturing the comprehensive bridge behavior and promoting long-term sustainable solutions against short-term ones.

2. Systematic Literature Review

Longitudinal degradation and maintenance of concrete bridge assets stimulates the great concern of project managers and stakeholders due to various social, economic, and political implications that arise. Primarily, a systematic literature review (SLR) was conducted to holistically investigate the current state in the field of bridge life-cycle deterioration and maintenance activities. The SLR was performed via the Web of Science (WoS) Core Collection bibliographic database for the timespan between 2000 and 2025. The SLR focused exclusively on studies with real-world deterioration and cost datasets that address life-cycle deterioration and maintenance using probabilistic parametric models. Initially, 59 peer-reviewed papers were extracted from the WoS database, while the final eligible papers were seven (7) after applying specific exclusion criteria that excluded papers relevant to (i) seismic loads and life-cycle costs; (ii) bridge maintenance optimization; (iii) other construction materials than concrete, such as timber and masonry bridges; (iv) life-cycle costs of materials; (v) deterioration models without cost estimation; (vi) deterministic approaches (e.g., parametric regressions, machine learning models, etc.).
An overview of the key descriptive attributes of the literature on bridge life-cycle maintenance cost estimation reviewed in this study is presented in Table 1. More precisely, Shim and Lee [16] conducted a Monte-Carlo simulation to develop a probabilistic analysis for annual maintenance costs for bridge decks by utilizing a dataset comprising 53 bridge decks from the state of Wyoming. Van Noortwijk and Klatter [17] proposed a probabilistic model to calculate expected maintenance or repair costs based on the lifetime data fitted to a Weibull distribution. Vagdatli et al. [4] developed a probabilistic model for bridge life-cycle maintenance cost estimation using a Dynamic Bayesian Network. A first-order Markov-chain model formulated by a dataset of 60 bridges in Greece was implemented to demonstrate the performance and expected maintenance costs of expansion joints over their service life. Later on, Vagdatli et al. [7] introduced a Dynamic Bayesian Network to estimate the life-cycle costs of bridges, based on the actual records of 78 concrete bridges in Northern Greece. For demonstrating purposes, a semi-Markovian process and survival analysis were applied to assess the deterioration progress and expected annual maintenance costs of expansion joints throughout their 10-year lifespan.
Furthermore, Yianni et al. [18] utilized a Petri-Net modeling approach to integrate a system encompassing deterioration, inspection, and maintenance modules for investigating the behavior of railway bridge main girders over 100 years. The study used real-world data from 4434 bridges in the UK, collected during inspections from 1998 to 2014. Gadiraju et al. [19] presented a deep reinforcement learning model for enhancing bridge maintenance schedules in Nebraska state by using a dataset of 15,350 bridges from the Nebraska NBI. Three different bridge components—the deck, superstructure, and substructure—shared the same transition probability matrices, obtained through Markovian computations, to demonstrate bridge deterioration and cumulative maintenance costs over 20 years. Lee et al. [20] suggested updating the deterioration state of prestressed concrete bridges through Bayesian inference to estimate maintenance costs based on the bridge’s current structural condition. A dataset of 84 Korean bridges between 1995 and 2018 was used to incorporate existing information in the proposed model.
Evidently, the majority of existing studies in the extant literature body concerning the probabilistic bridge life-cycle maintenance costs focus on the bridge’s deck system elements. Additionally, large datasets usually have not been performed under the same specifications, such as the consistent pricelists, construction standards, and administrative authorities, rendering it challenging to extract homogeneous results from them. Therefore, the present study aims to introduce a data-driven probabilistic model for life-cycle deterioration prediction and maintenance cost analysis for bridge superstructure and substructure components based on homogeneous datasets collected from 72 concrete bridges in Northern Greece.

3. Methodology

The process for the proposed framework development involves the following steps: (a) data collection and processing; (b) prediction of bridge components longitudinal deterioration; and (c) life-cycle maintenance cost analysis with real datasets. A general flowchart of the developed methodology is illustrated in Figure 1, while a detailed explanation of each step is provided in the following sections.

3.1. Markovian Stochastic Model

The Markov-chain approach is regarded as the most common stochastic procedure utilized for the deterioration prediction and asset management of infrastructure projects, such as bridges and pavements [21,22]. Markov chains are probabilistic methods that can be parameterized by empirical transition probabilities calculation between discrete states [23].
The classic Markovian model follows three assumptions [24]: (a) the process is discrete in time; (b) the behavior of the studied system is represented by a finite state space, known as condition states (CS), { S i = S 1 ,   S 2 , S N } , which are discrete random variables; and (c) the model satisfies the “Markov property”. The latter theorem indicates that the conditional probability, P i j , of a given future condition state j depends only on the current state i and not on previous ones, known as the first-order Markov process [25]. In general, for a given sequence of time points t , the conditional probabilities follow the subsequent rule:
P i j = p r o b [ X t + 1 = j | X t = i ]
The Markov-chain process consists of three main elements [25]: the condition probability vector, the time step of the process, and the transition matrix:
a. 
The condition probability vector is a row vector presenting the condition of bridge components utilizing the probabilities of stating in each condition state, C R = { a 1 ; a 2 ; , a n } . The sum of all a i is equal to one, with all the elements being positive values. For instance, the initial condition vector for any new rehabilitated bridge is represented with the following form:
C R ( 0 ) = { 1 ; 0 ; 0 ; , 0 }
a. 
The time step is the time interval among two consecutive states. Typically, this step is identical with the frequency of real data collection.
b. 
The Transition Probability Matrix (TPM), usually denoted as P , describes the bridge’s deterioration over time. A typical TPM is shown in Equation (3) along with its restrictions described in Equations (4) and (5):
P = p 11 p 12 p 1 n p 21 p 22 p 2 n p n 1 p n 2 p n n
0 p i j 1 ,   for   all   i   and   j ,   where   i , j = 0,1 , 2 . . . , n
j I p i j = 1       i I
Each component p i j represents the transition probabilities from one condition state i at time t to another condition state j at time t + 1 . In cases where the nature deterioration of the presented system is examined and maintenance actions are not considered, only the upper diagonal of the TPM receive values, where i < j . Therefore, the general form of Equation (3) is converted into Equation (6):
P = p 11 p 12 p 1 n 0 0 p 2 n 0 0 1
Once the TPM is formulated, the predicted condition vector of the next state is estimated by multiplying the current state by the TPM. In the case of time-homogeneous Markov-chain models, which is the case in the present study, the transition rates are exponentially distributed, remain constant throughout all the analysis years, and are applied to any t to t + 1 transition [26], as presented in Equation (7).
A t = A t 1 × P = A 0 P t
where A t is the state vector at any time t ; A 0 is the state vector at time t = 0 .
Ultimately, the overall expected bridge component deterioration can be estimated by Equation (8):
C R t = C R 0 × P i j t × C R
where P i j t is the TPM an any given time t ; C R is the bridge’s condition vector that remains constant C R = 9,8 , 7,6 ,   1 ; and C R 0 is the initial condition vector, which, in the present study, equals to C R 0 = { 1 ,   0 ,   0 ,   ,   0 } , since it is considered that the bridges degraded from an intact level and for a period of 100 years.

3.2. Transition Probability Matrix Computation

The reliability of a Markov-chain model is highly related to the accuracy of the computed transition probabilities [15]. Two techniques are the most commonly used for estimating the matrix’s transition probabilities: collection of historical real data or experts’ judgement [25]. Ιt is acknowledged that the calculation of the transition probabilities is ideally accomplished by using the bridge’s available condition data derived from uniform time intervals over a long time period [27]. In the case of on-site data collection, the most appropriate processing method is the maximum likelihood estimator for the deterioration probabilities P i j calculation [28], as depicted in Equation (9):
P i j = N i j N i
where P i j = the element in row i and column j of TPM; N i j = the portion of assets shifting from one condition state i into another worse j during one time step; N i = the total portion of assets was in state i before any transition take place.
Thus, the TPMs of the present study were calculated by using actual values concerning the condition of the bridge’s components to simulate more realistic deterioration outcomes. The real inspection data of 72 concrete bridges serving the Greek motorways were collected over a period of 15 to 25 years, covering bridge operation from 1999 to 2024.
Since the Markov-chain process relies only on two consecutive years to calculate the TMP, only nine transition probabilities are necessary, each for every condition state. However, in the present study, a set of transition probabilities is available for each pair of successive years, owing to the longitudinal data collected. As observed, these values are not uniformly distributed. Hence, the average value of the computed transition probabilities was calculated for each CS over the entire analysis period. As can be seen in Equations (10) and (11), transition probabilities outside the valid range should be excluded, while the final transition probabilities, p i i v a l i d , represent the average of the valid values for each condition state. This approach allows for fully utilizing the available dataset and ensures a more thorough data analysis and a more informed decision-making process.
P R i = p i i ¯ s i p i i ¯ + s i         i [ 9 ,   8 ,   7 ,   1 ]
p i i v a l i d = p i i ¯         p i i P R i
where P R i is the valid range of transition probabilities for each state i ; p i i represents the computed transition probabilities throughout all the years of the inspection dataset for each state i ; p i i ¯ and s i are the average value and standard deviation of p i i values, respectively; p i i v a l i d represents the final transition probabilities for each state i removing invalid values.

3.3. Validation Process of Markovian Stochastic Model

Ultimately, the Markovian models should be validated for ensuring their applicability in the light of new datasets from similar environments. In this study, quantitative validation methods were utilized to compare the predicted stochastic models with observed datasets. For this reason, the collected datasets, analyzed in Section 3.4, were divided into two distinct datasets, the training and the validation dataset; specifically, 80% of the data were utilized to train the Markovian models, and 20% was used to validate them for generalization purposes.
The Chi-square goodness-of-fit test was conducted using appropriate statistical packages in the Python 3.8.3 version programming language. According to classical binary testing theory [29], two hypothesis tests, the null hypothesis ( H 0 ) and the alternative hypothesis ( H 1 ), should be checked for determining the model’s accuracy:
H0: 
The predicted conditions are not significantly different from the observed conditions.
H1: 
The predicted conditions are significantly different from the observed conditions.
For accepting the H 0 hypothesis, the probability of the estimated Chi-square ( p v a l u e ) should be greater than a given chosen significance level ( a ).

3.4. Data Collection

The main key aspects considered in the present study are summarized below:
a. 
Bridge and Component type selection: The Markovian model was calibrated using actual datasets collected from 72 existing concrete bridges serving the Greek national road network in Northern Greece. The dataset is grouped into three categories: (a) bridges with pier height greater than 15 m, (b) overpasses, and (c) underpasses. Among the bridge’s components, the superstructure and substructure were regarded as the most critical ones; hence, they were selected for the deterioration and life-cycle analysis. Table A1 and Table A2 in Appendix A display the main structural information of the collected datasets along with the indicative condition states for superstructure and substructure observed during the bridge’s service life.
b. 
Analysis period: The real dataset was collected over a 25-year time period from bridges operating from 1999 to 2024. The bridge performance model was calculated based on actual data collected from its initial operation and projected for 100 years of its total lifespan. Since all the available data were used, a comprehensive insight into the bridge components’ deterioration can be obtained and illustrated in the formulated TPM.
c. 
Defect identification: Based on detailed visual inspections, the different types of bridges’ defects and the percentage of material defects for the superstructure and substructure elements were detected. More precisely, the most common registered damages for the collected bridges account for staining, efflorescence, cracks, spalling, exposed reinforcement and reinforcement corrosion.
d. 
Condition States: The number and ranking of CSs were adopted by the National Bridge Inventory (NBI) and are illustrated in Table 2. The classification of the bridge’s components into the individual CSs was conducted based on the aforementioned identified damages. Since there were no data on the last condition states, a by-6 TPM was considered representative of the studied case and was developed for the suggested Markov-chain probabilistic models. To obtain a complete and consistent dataset that would serve as an adequate basis for the deterioration model prediction, the data were screened to filter out any records with incomplete data.
e. 
Time step: A one-year time cycle was adopted to resemble the annual data collection regarding the bridge condition.
f. 
Maintenance improvements: For the initial phase of the model, only the data accounting for the natural deterioration of the bridge’s components was considered. Consequently, any bridge component that demonstrated an improvement in the condition value compared to the previous year was not considered; hence, all the elements under the main diagonal of TPM are equal to zero, as defined in Equation (6). In the second step of this research, where maintenance improvements take place, the TPM is modified to incorporate any possible maintenance action.

3.5. Maintenance Policies and Related Costs

In ageing systems, assets are either repaired preventively at scheduled time intervals or replaced correctively in case of failure based on emerging needs [30]. Figure 2 indicates all the possible cases of failure rates, ( f i , i = 1,2 , , N ), and repair rates, ( r i , i = 1,2 , , N ), that might occur in degraded systems, indicated by red and blue colors arrows, respectively. Assuming that the current time step is t and the time interval among two consecutive steps is Δ t , then the transition probabilities between the examined states for natural decay or preventive maintenance are shown in Table 3 and Table 4, respectively.
More precisely, it is clarified that in the present study, the only feasible failure transition occurs between two successive CSs, as depicted with continuous arrows in Figure 2 and calculated with relative probabilities in Table 3. Moreover, Table 4 presents all the possible solutions for imperfect and perfect maintenance actions. Various maintenance strategies, M z = { M 1 , M 2 , , M Z } , can be applicable for retaining the bridge performance at its optimum level. The appropriate maintenance actions can be determined based on the developed Markov-chain prediction of bridge components performance and according to the CSs; hence, a condition-based maintenance model is constructed. For all the maintenance works identified as necessary for improving the bridge’s condition state, the actual procurement and real costs were collected and used in the analysis calculations. The full specification of the implemented maintenance actions along with their associated actual costs and the CSs applied to are summarized in Table 5. These activities are combined suitably according to the detected damage each time for completing one full maintenance activity for each CS.
The uncertainties related to structural and external causes lead to structural bridge failures that are distributed as random events with time-dependent probabilities of occurrence. Therefore, the expected monetary value concept is applied to the proposed life-cycle maintenance model for bridge components computation. The expected life-cycle maintenance costs are estimated by using Equation (12), without taking into account the time value of money:
E C M t = s = 1 S 1 P m , s ( t ) × c m , s + s = S S P f , s ( t ) × c f , s
where s = the current condition state; S = the overall number of condition states of bridge’s components; P m , s ( t ) = the probability of a preventive maintenance action m occurring at a given time t in states s = { 1,2 , ,   N 1 } ; P f , s ( t ) = the probability of corrective maintenance action f occurring at a given time t in the final failure state s = N ; c m , s = the undiscounted unit cost related to the preventive maintenance action in states s = { 1,2 , ,   N 1 } ; c f , s = the undiscounted unit cost related to the corrective maintenance strategy in the final failure state.

4. Deterioration and Maintenance Prediction Using Markov-Chain Model

The entire calculation of the TPMs for the bridge’s superstructure and substructure components was fulfilled via Excel spreadsheets by using the training dataset and applying Equations (3)–(11) as analyzed in Section 3.1 and Section 3.2. Eventually, Equations (13) and (14) depict the transition probabilities of remaining to the same CS or transiting to the next CS after one-year step for the bridge’s superstructure and substructure, respectively.
P s u p = 0.844 0.156 0 0 0 0 0 0.931 0.069 0 0 0 0 0 0.972 0.028 0 0 0 0 0 0.90 0.10 0 0 0 0 0 0.91 0.09 0 0 0 0 0 1
Equation (13) Transition Probability Matrix for a one-year time step of superstructure.
P s u b = 0.854 0.146 0 0 0 0 0 0.908 0.092 0 0 0 0 0 0.984 0.016 0 0 0 0 0 0.687 0.313 0 0 0 0 0 0.94 0.06 0 0 0 0 0 1
Equation (14) Transition Probability Matrix for a one-year time step of substructure.
Considering the exported TPMs as uniform for the entire analysis period, the deterioration prediction results under natural decay emerged for each time step t , as shown in Figure 3 and Figure 4, while the expected CRs for the bridge’s components were calculated via Equation (8) and are presented in Figure 5 and Table A3 and Table A4 in Appendix B. A perfect condition probability vector was considered as an initial vector for the year 0 when the bridge initiated its operation. Afterwards, the bridge’s degradation commences with approximately the 55% to be in the State “8” by the tenth year for the superstructure component. Roughly the same percentage is shifted to the State “7” in the thirtieth year of the analysis. After the fiftieth year of the bridge’s life-cycle, the highest proportion of the cumulative percentage of transition probabilities is detected in the lower CSs from “6” to “4”. Finally, at the end of the time period, 75% of superstructures reach the lower examined state of “4” (Figure 3). Regarding the deterioration of the bridge’s substructure, a percentage of 60% reaches the “4” CS at the 100th year of the analysis period, indicating, as expected, a slower deterioration compared to the superstructure component (Figure 4).
Moreover, the crucial issue of the execution time of maintenance actions throughout the bridge’s service life should be addressed. The managing authority of bridges under consideration has set the State “5” as a condition threshold to ensure smooth operations and user safety (Figure 5). Hence, by comparing the exported results of Figure 3 and Figure 4 with the specified condition threshold, useful policy recommendations regarding the extent and the time of major maintenance actions can be derived. For instance, for both superstructure and substructure, the peak of the deterioration curves for State “5” occur during the sixth decade of bridge service life, with approximately 17% of the bridge fleet falling into this condition. However, State “4” roughly starts between the 15th and 20th years of the analysis period with an upward trend until the end of the analysis period. Consequently, the exported deterioration curves can serve as a consulting tool for bridge managers in order to obtain an overall sight of bridge degradation and to examine and prioritize suitable maintenance actions under budget constraints each time.
The results of the statistical goodness-of-fit test for superstructure and substructure deterioration curves are summarized in Table 6. For this study, the significance level was set at a = 0.05 . As can be seen, the null hypothesis H 0 is confirmed for both training and validation datasets, since p v a l u e > a = 0.05 . Therefore, it can be inferred that the Markovian models can effectively predict the condition of bridge’s superstructure and substructure within an acceptable range of differences.
Additionally, the deterioration curves for the bridge’s superstructure and substructure exported from the present study were compared with the corresponding ones found by widely known and reputable agencies that adhere to FHWA practices, such as those in Nebraska and New York [31,32]. As observed in Figure 6, slight differences have appeared between the Greece and Nebraska models, exhibiting similar deterioration trends for the bridge’s superstructure (Figure 6a) and substructure (Figure 6b). Also, New York’s deterioration curve decreases at the same rate as the other two models, despite its initial deterioration state being State 7 for superstructure.
Subsequently, the maintenance costs were estimated based on the aforementioned longitudinal transition probabilities over a 100-year period of the bridge’s service life. It is mentioned that for the model’s demonstrative purposes and taking into account the most commonly implemented maintenance strategy whereby the system returns to its initial state from any worse state, the repair rates with the continuous arrows of Figure 2 are considered with a 100% probability of occurrence. The maintenance actions shown in Table 5 were employed for restoring the bridge asset to its initial condition. Considering the quantities of the damaged areas of either the bridge’s superstructure or substructure and by applying appropriate multiplications with the unit costs of maintenance works of Table 5, the final repair prices were converted to / m 2 and are illustrated in Figure 7 as representative costs for each CS and each of the group of studied deteriorated bridges.
It is stated that the derived unit costs for substructure components appeared notable differences among the studied categories and their classification into three sub-categories was deemed necessary. Primarily, the difference in actual costs for the bridge and underpass substructure components is due to the types of prerequisite auxiliary works applied for the implementation of the maintenance works. Bridges with piers > 15 m typically utilize the types of M 1 and M 2 , whereas underpasses make use of the M 3 type according to Table 5. Furthermore, it is clarified that the classification of the bridge into condition states is based on the severity and intensity of any given damage, rather than the extent of deterioration. Thus, considering the extent of the occurred damage, the cost outcomes might be slightly different from the ones derived from this study.
Ultimately, the obtained transition probabilities for each CS (Figure 3 and Figure 4) were multiplied by the actual unit maintenance costs corresponding to each CS (Figure 7) to yield the expected costs of superstructure and substructure components over the bridge’s lifetime. Figure 8, Figure 9, Figure 10 and Figure 11 provide a comprehensive overview of the expected maintenance costs throughout a 100-year bridge life-cycle. By knowing the expected maintenance costs in each year of the bridge’s remaining service life and comparing them through the formulation of different maintenance alternatives, the project managers can have a solid base for planning future expenditures in a more cost-effective way. More precisely, as expected, the cost trend aligns with the corresponding condition states. As can be seen in the cumulative cost diagram of Figure 8, if the maintenance of the superstructure is performed in the first half of the analysis period, the costs are reduced by half compared to those incurred during the second fifty-year life. Accordingly, in the case of the bridge’s substructure (Figure 9, Figure 10 and Figure 11), the costs of the first fifty years were estimated at two-thirds of the costs of the second half of the life-cycle. This can be explained by the fact that the superstructure deteriorates faster than the bridge’s substructure. As a result, by the end of the analysis period, a greater proportion of the bridge’s superstructure is classified in state “4” compared to the substructure. Consequently, restoring the superstructure to its initial condition will incur higher costs.

5. Conclusions

Bridge management actions are an incremental part of its smooth and seamless operation during its service life. These repair actions must be delivered within the bounds of available resources. For promoting feasible solutions, bridge managers should conduct life-cycle modeling procedures, which encompasses the overall expenditures of the asset. Due to various uncertain factors that impact the bridge’s operation, the probabilistic methods are considered more suitable for accurately modeling bridge performance. Therefore, the main goal of the current study is to develop a data-driven performance and maintenance cost model for the bridge’s life-cycle, to provide insights into the field of overall bridge management under uncertain circumstances, as well as highlight the significance of the usage of actual inspection and cost datasets in the accuracy of such models.
There are three primary steps in the entire process. Firstly, actual datasets regarding the bridge’s defects, condition states, as well as maintenance actions and costs were collected for further processing from 72 concrete bridges serving the Greek national highways. Secondly, considering the detected defects and the corresponding bridge’s conditions states, two discrete-time Markov-chain models were developed for the performance prediction of superstructure and substructure components over a 100-year period, with a one-year time step. Finally, the unit costs for restoring both examined bridge components to their initial condition were calculated, which allowed for the estimation of expected life-cycle maintenance costs. Ultimately, the probabilistic performance curves of the superstructure and substructure, along with the predicted life-cycle maintenance costs presented in this study, can assist asset managers in promoting more sustainable rehabilitation strategies, both structurally and economically. Since these costs have been projected over 100 years, they offer a comprehensive overview of the bridge’s total life-cycle expenses. This assessment highlights cost-effective solutions, enabling experts to eliminate unnecessary early maintenance actions and prevent severe damages that could be devastating in both economic and safety terms. Consequently, the exported deterioration curves and maintenance costs of the current study can serve as a baseline for implementing management policies for bridges constructed and operated under the same or similar conditions, such as similar construction specifications, geographical areas, and administrative authorities for ensuring reliable results. Additionally, several maintenance scenarios can be investigated using the exported life-cycle costs to identify the most optimal scenario while considering financial and safety constraints.
A practical limitation of this study is that the sample bridges have been in service for up to twenty-five years. As a result, the data collected only reflect the initial years of the bridges’ operation life. Therefore, future research will focus on implementing updating methods, such as Bayesian methods, that update the model in the light of new datasets, for even more realistic results. Moreover, with the passage of an even longer bridge lifespan that will allow for the collection of a sufficient volume of condition and maintenance datasets, non-homogeneous techniques, such as semi-Markov models, can be applied to capture the temporal variability of bridge degradation. Furthermore, bridge constitutes a multi-component system with different deterioration rates among its components. Hence, it would be fruitful to investigate more bridge components, such as bearings, deck etc., for exporting representative empirical probabilistic curves for each deterioration type.

Author Contributions

Conceptualization, K.P. and T.V.; methodology, K.P., T.V. and N.L.; formal analysis, T.V. and N.L.; validation, K.P. and P.P., investigation, T.V. and N.L.; resources, P.P.; data curation, T.V. and N.L.; writing—original draft, T.V.; writing—review and editing, K.P.; visualization, T.V. and N.L.; supervision, K.P. All authors have read and agreed to the published version of the manuscript.

Funding

This research received no external funding.

Data Availability Statement

The data presented in this study are available on request from the corresponding author due to privacy restrictions.

Conflicts of Interest

The authors declare no conflicts of interest.

Appendix A

Table A1. Overview of structural information of actual datasets used in the analysis.
Table A1. Overview of structural information of actual datasets used in the analysis.
Serial NumberBridge’s IDConstruction YearSpan Number and
Arrangement (m)
Superstructure
Material
101.07Β.08200936.30/37.50 × 7/36.30Prestressed
concrete
201.08.07Β200936.30/37.50 × 6/36.30
304.08Β.09200760/8 × 100/60
404.09.08Β200760/8 × 100/60
507.31.3220013 × 34.50/3 × 42.00/2 × 34.50/22.75
607.32.31200122.75/34.50/3 × 43.50/34.50
706.42.43200019.40/19.05
801.43199932.01/31.71
904.43199927.58/26.78
1004.24.24A200227.85/27.85/27.85
1104.24A.24200227.85/27.85/27.85
1209.24.24A200129.62/30.76/29.62
1309.24A.24200129.62/30.76/29.62
1402.24A.25200219.67/20.66/19.67
1502.25.24A200219.67/20.66/19.67
1605.24A.25200127.1/27.9/27.1
1705.25.24A200127.1/27.9/27.1
1809.24A.25200225.0/25.0
1909.25.24A200225.0/25.0
2012.24A.25200119.67/20.66/19.67
2112.25.24A200119.67/20.66/19.67
2216.24A.25200235.00/45.00/35.00
2316.25.24A200235.00/45.00/35.00
2418.24A.25200138.0/47.0 × 2/38.0
2518.25.24A200138.0/47.0 × 2/38.0
Reinforced
concrete
5004.24A.25200310.5
5104.25.24A200310.5
5206.24A.25200310.5
5306.25.24A200310.5
5407.24A.25200013
5507.25.24A200013
5608.24A.25200310.5
5708.25.24A200310.5
5810.24A.25200010.5
5910.25.24A200010.5
6011.24A.25200010.5
6111.25.24A200010.5
6213.24A.25200010.5
6313.25.24A200010.5
6414.24A.25200214.00
6514.25.24A200214.00
6615.24A.25200010.5
6815.25.24A200010.5
6917.24A.25200010.5
7017.25.24A200010.5
7119.24A.25200110.5
7219.25.24A200110.5
Table A2. Indicative actual condition states of bridge superstructure and substructure over time.
Table A2. Indicative actual condition states of bridge superstructure and substructure over time.
Serial NumberBridge’s ID5th Year10th Year15th Year20th Year25th Year
101.07Β.088/97/66/5-/--/-
201.08.07Β8/97/66/5-/--/-
304.08Β.097/97/85/6-/--/-
404.09.08Β7/97/85/6-/--/-
507.31.328/98/88/77/7-/-
607.32.318/98/88/77/7-/-
706.42.439/98/88/77/67/5
801.438/87/87/66/46/4
904.439/98/87/77/76/7
1004.24.24A9/99/98/88/8-/-
1104.24A.249/99/98/88/8-/-
1209.24.24A7/87/77/77/7-/-
1309.24A.247/87/77/77/7-/-
1402.24A.257/87/77/77/7-/-
1502.25.24A7/87/77/77/7-/-
1605.24A.259/99/98/87/87/8
1705.25.24A9/99/98/87/87/8
1809.24A.258/98/87/76/7-/-
1909.25.24A8/98/87/76/7-/-
2012.24A.258/88/87/77/76/7
2112.25.24A8/88/87/77/76/7
2216.24A.258/98/88/87/7-/-
2316.25.24A8/98/88/87/7-/-
2418.24A.258/88/88/88/87/7
2518.25.24A8/88/88/88/87/7
5004.24A.259/99/88/88/7-/-
5104.25.24A9/99/88/88/7-/-
5206.24A.259/98/88/88/7-/-
5306.25.24A9/98/88/88/7-/-
5407.24A.259/98/88/88/87/7
5507.25.24A9/98/88/88/87/7
5608.24A.259/98/88/87/7-/-
5708.25.24A9/98/88/87/7-/-
5810.24A.258/88/88/87/77/7
5910.25.24A8/88/88/87/77/7
6011.24A.258/88/88/88/87/8
6111.25.24A8/88/88/88/87/8
6213.24A.259/98/88/88/87/7
6313.25.24A9/98/88/88/87/7
6414.24A.259/99/88/88/8-/-
6514.25.24A9/99/88/87/8-/-
6615.24A.258/88/88/87/87/8
6815.25.24A8/88/88/88/87/8
6917.24A.259/99/98/88/87/8
7017.25.24A9/99/98/88/87/8
7119.24A.259/99/99/98/8-/-
7219.25.24A9/99/99/98/8-/-
Data size72/7272/7272/7264/6435/35

Appendix B

Table A3 and Table A4 present the CR data points exported via the Markov-chain models for superstructure and substructure deterioration, respectively.
Table A3. CR data points of superstructure for a single bridge in 100 years.
Table A3. CR data points of superstructure for a single bridge in 100 years.
Superstructure
YearsCondition RatingYearsCondition RatingYearsCondition RatingYearsCondition Rating
09000266935525756784933
18844276885535717794910
28701286840545679804886
38571296809555641814864
48450306736565603824841
58339316687575567834820
68237326639585531844798
78141336591595495854778
88051346543605460864757
97967356496615426874738
107887366449625392884718
117812376402635359894699
127740386356645326904681
137671396310655295914663
147605406265665263924646
157542416220675233934629
167480426175685202944612
177421436131695173954596
187363446088705144964580
197306456044715116974564
207250466002725088984549
217196475959735061994535
2271424859187450341004520
237090495876755008
247037505836764983
256986515796774958
Table A4. CR data points of substructure for a single bridge in 100 years.
Table A4. CR data points of substructure for a single bridge in 100 years.
Substructure
YearsCondition RatingYearsCondition RatingYearsCondition RatingYearsCondition Rating
09000266909525993785347
18854276865535964795326
28716286822545935805306
38586296781555907815286
48463306741565879825266
58347316700575851835246
68238326661585824845227
78135336623595797855208
88038346585605770865190
97947356548615744875171
107860366512625718885153
117779376476635692895135
127701386440645667905118
137628396406655642915100
147558406371665618925083
157491416337675593935066
167427426304685569945050
177366436271695546955033
187308446239705522965017
197252456206715499975002
207198466175725477984986
217146476143735454994971
2270954861137454321004955
237047496082755410
246999506052765389
256953516022775368

References

  1. Abdelkader, E.M.; Zayed, T.; Marzouk, M. A Computerized Hybrid Bayesian-Based Approach for Modelling the Deterioration of Concrete Bridge Decks. Struct. Infrastruct. Eng. 2019, 15, 1178–1199. [Google Scholar] [CrossRef]
  2. Zanini, M.A.; Faleschini, F.; Pellegrino, C. Cost Analysis for Maintenance and Seismic Retrofit of Existing Bridges. Struct. Infrastruct. Eng. 2016, 12, 1411–1427. [Google Scholar] [CrossRef]
  3. Biondini, F.; Frangopol, D.M. Life-Cycle Performance of Deteriorating Structural Systems under Uncertainty: Review. J. Struct. Eng. 2016, 142, F4016001. [Google Scholar] [CrossRef]
  4. Vagdatli, T.; Petroutsatou, K.; Panetsos, P.; Barmpa, Z.; Fragkakis, N. Bayesian Pre-Estimation of Bridge Life-Cycle Costs. In Proceedings of the 8th International Symposium on Life-Cycle Engineering, IALCCE 2023, Milan, Italy, 2–6 July 2023; Biondini, F., Frangopol, D.M., Eds.; Taylor & Francis: Milano, Italy, 2023. [Google Scholar]
  5. Callow, D.; Lee, J.; Blumenstein, M.; Guan, H.; Loo, Y.C. Development of Hybrid Optimisation Method for Artificial Intelligence Based Bridge Deterioration Model—Feasibility Study. Autom. Constr. 2013, 31, 83–91. [Google Scholar] [CrossRef]
  6. Barone, G.; Frangopol, D.M. Life-Cycle Maintenance of Deteriorating Structures by Multi-Objective Optimization Involving Reliability, Risk, Availability, Hazard and Cost. Struct. Saf. 2014, 48, 40–50. [Google Scholar] [CrossRef]
  7. Vagdatli, T.; Petroutsatou, K.; Panetsos, P.; Barmpa, Z.; Fragkakis, N. Probabilistic Pre-Estimation of Life-Cycle Costs of Road Bridges Using Dynamic Bayesian Networks. Struct. Infrastruct. Eng. 2024, 1–20. [Google Scholar] [CrossRef]
  8. Yamany, M.S.; Abraham, D.M.; Labi, S. Comparative Analysis of Markovian Methodologies for Modeling Infrastructure System Performance. J. Infrastruct. Syst. 2021, 27, 1–13. [Google Scholar] [CrossRef]
  9. Bocchini, P.; Saydam, D.; Frangopol, D.M. Efficient, Accurate, and Simple Markov Chain Model for the Life-Cycle Analysis of Bridge Groups. Struct. Saf. 2013, 40, 51–64. [Google Scholar] [CrossRef]
  10. Li, L.; Lu, Y.; Peng, M. Deterioration Model for Reinforced Concrete Bridge Girders Based on Survival Analysis. Mathematics 2022, 10, 4436. [Google Scholar] [CrossRef]
  11. O’Connor, A.J.; Sheils, E.; Breysse, D.; Schoefs, F. Markovian Bridge Maintenance Planning Incorporating Corrosion Initiation and Nonlinear Deterioration. J. Bridge Eng. 2013, 18, 189–199. [Google Scholar] [CrossRef]
  12. Vagdatli, T.; Petroutsatou, K. Modelling Approaches of Life Cycle Cost–Benefit Analysis of Road Infrastructure: A Critical Review and Future Directions. Buildings 2023, 13, 94. [Google Scholar] [CrossRef]
  13. Yang, D.Y.; Frangopol, D.M. Probabilistic Optimization Framework for Inspection/Repair Planning of Fatigue-Critical Details Using Dynamic Bayesian Networks. Comput. Struct. 2018, 198, 40–50. [Google Scholar] [CrossRef]
  14. Gong, C.; Frangopol, D.M. Condition-Based Multiobjective Maintenance Decision Making for Highway Bridges Considering Risk Perceptions. J. Struct. Eng. 2020, 146. [Google Scholar] [CrossRef]
  15. Collins, J.; Weidner, J. Comparison of Markovian-Based Bridge Deterioration Model Approaches. J. Bridge Eng. 2023, 28, 1–13. [Google Scholar] [CrossRef]
  16. Shim, H.S.; Lee, S.H. Developing a Probable Cost Analysis Model for Comparing Bridge Deck Rehabilitation Methods. KSCE J. Civ. Eng. 2015, 20, 68–76. [Google Scholar] [CrossRef]
  17. Van Noortwijk, J.M.; Klatter, H.E. The Use of Lifetime Distributions in Bridge Maintenance and Replacement Modelling. Comput. Struct. 2004, 82, 1091–1099. [Google Scholar] [CrossRef]
  18. Yianni, P.C.; Rama, D.; Neves, L.C.; Andrews, J.D.; Castlo, D. A Petri-Net-Based Modelling Approach to Railway Bridge Asset Management. Struct. Infrastruct. Eng. 2017, 13, 287–297. [Google Scholar] [CrossRef]
  19. Gadiraju, D.S.; Muthiah, S.R.; Khazanchi, D. A Deep Reinforcement Learning Based Approach for Bridge Health Maintenance. In Proceedings of the 2023 International Conference on Computational Science and Computational Intelligence (CSCI), Las Vegas, NV, USA, 13–15 December 2023; pp. 43–48. [Google Scholar] [CrossRef]
  20. Lee, J.H.; Choi, Y.; Ann, H.; Jin, S.Y.; Lee, S.-J.; Kong, J.S. Maintenance Cost Estimation in PSCI Girder Bridges Using Updating Probabilistic Deterioration Model. Sustainability 2019, 11, 6593. [Google Scholar] [CrossRef]
  21. Moscoso, Y.F.M.; Rincón, L.F.; Leiva-Maldonado, S.L.; Campos e Matos, J.A.S.C. Bridge Deterioration Models for Different Superstructure Types Using Markov Chains and Two-Step Cluster Analysis. Struct. Infrastruct. Eng. 2022, 20, 791–801. [Google Scholar] [CrossRef]
  22. Alimoradi, S.; Golroo, A.; Asgharzadeh, S.M. Development of Pavement Roughness Master Curves Using Markov Chain. Int. J. Pavement Eng. 2022, 23, 453–463. [Google Scholar] [CrossRef]
  23. Shamshad, A.; Bawadi, M.A.; Wan Hussin, W.M.A.; Majid, T.A.; Sanusi, S.A.M. First and Second Order Markov Chain Models for Synthetic Generation of Wind Speed Time Series. Energy 2005, 30, 693–708. [Google Scholar] [CrossRef]
  24. Lethanh, N.; Hackl, J.; Adey, B.T. Determination of Markov Transition Probabilities to Be Used in Bridge Management from Mechanistic-Empirical Models. J. Bridge Eng. 2017, 22. [Google Scholar] [CrossRef]
  25. Pérez-Acebo, H.; Mindra, N.; Railean, A.; Rojí, E. Rigid Pavement Performance Models by Means of Markov Chains with Half-Year Step Time. Int. J. Pavement Eng. 2019, 20, 830–843. [Google Scholar] [CrossRef]
  26. Alonso-Solorzano, Á.; Pérez-Acebo, H.; Findley, D.J.; Gonzalo-Orden, H. Transition Probability Matrices for Pavement Deterioration Modelling with Variable Duty Cycle Times. Int. J. Pavement Eng. 2023, 24. [Google Scholar] [CrossRef]
  27. Mizutani, D.; Lethanh, N.; Adey, B.T.; Kaito, K. Improving the Estimation of Markov Transition Probabilities Using Mechanistic-Empirical Models. Front. Built Environ. 2017, 3. [Google Scholar] [CrossRef]
  28. Mašović, S.; Hajdin, R. Modelling of Bridge Elements Deterioration for Serbian Bridge Inventory. Struct. Infrastruct. Eng. 2014, 10, 976–987. [Google Scholar] [CrossRef]
  29. Ling, Y.; Mahadevan, S. Quantitative Model Validation Techniques: New Insights. Reliab. Eng. Syst. Saf. 2013, 111, 217–231. [Google Scholar] [CrossRef]
  30. van den Boomen, M.; Schoenmaker, R.; Wolfert, A.R.M. A Life Cycle Costing Approach for Discounting in Age and Interval Replacement Optimisation Models for Civil Infrastructure Assets. Struct. Infrastruct. Eng. 2018, 14, 1–13. [Google Scholar] [CrossRef]
  31. Morcous, G.; Hatami, A. Developing Deterioration Models for Nebraska Bridges; Nebraska Transportation Center: Lincoln, NE, USA, 2011. [Google Scholar]
  32. Agrawal, A.K.; Kawaguchi, A.; Chen, Z. Deterioration Rates of Typical Bridge Elements in New York. J. Bridge Eng. 2010, 15, 419–429. [Google Scholar] [CrossRef]
Figure 1. General flowchart of the proposed Markovian deterioration and life-cycle maintenance.
Figure 1. General flowchart of the proposed Markovian deterioration and life-cycle maintenance.
Buildings 15 00807 g001
Figure 2. Possible transitions for the discrete-time Markov-chain model.
Figure 2. Possible transitions for the discrete-time Markov-chain model.
Buildings 15 00807 g002
Figure 3. Exported probabilistic deterioration curves of bridge superstructure in 100 years.
Figure 3. Exported probabilistic deterioration curves of bridge superstructure in 100 years.
Buildings 15 00807 g003
Figure 4. Exported probabilistic deterioration curves of bridge substructure in 100 years.
Figure 4. Exported probabilistic deterioration curves of bridge substructure in 100 years.
Buildings 15 00807 g004
Figure 5. CR deterioration for a single bridge in 100 years.
Figure 5. CR deterioration for a single bridge in 100 years.
Buildings 15 00807 g005
Figure 6. Greek exported empirical versus international deterioration curves for bridge (a) superstructure and (b) substructure.
Figure 6. Greek exported empirical versus international deterioration curves for bridge (a) superstructure and (b) substructure.
Buildings 15 00807 g006
Figure 7. Actual maintenance costs ( / m 2 ) for bridge’s (a) superstructure and (b) substructure.
Figure 7. Actual maintenance costs ( / m 2 ) for bridge’s (a) superstructure and (b) substructure.
Buildings 15 00807 g007
Figure 8. (a): Expected annual maintenance costs; (b) cumulative annual maintenance costs ( / m 2 ) for bridge’s superstructure.
Figure 8. (a): Expected annual maintenance costs; (b) cumulative annual maintenance costs ( / m 2 ) for bridge’s superstructure.
Buildings 15 00807 g008
Figure 9. (a): Expected annual maintenance costs; (b) cumulative annual maintenance costs ( / m 2 ) for bridge’s substructure.
Figure 9. (a): Expected annual maintenance costs; (b) cumulative annual maintenance costs ( / m 2 ) for bridge’s substructure.
Buildings 15 00807 g009
Figure 10. (a): Expected annual maintenance costs; (b) cumulative annual maintenance costs ( / m 2 ) for overpasses’ substructure.
Figure 10. (a): Expected annual maintenance costs; (b) cumulative annual maintenance costs ( / m 2 ) for overpasses’ substructure.
Buildings 15 00807 g010
Figure 11. (a): Expected annual maintenance costs; (b) cumulative annual maintenance costs ( / m 2 ) for underpasses’ substructure.
Figure 11. (a): Expected annual maintenance costs; (b) cumulative annual maintenance costs ( / m 2 ) for underpasses’ substructure.
Buildings 15 00807 g011
Table 1. Overview of the probabilistic studies on bridge maintenance cost estimation.
Table 1. Overview of the probabilistic studies on bridge maintenance cost estimation.
SourcesBridge ComponentsData SizeApplied
Probabilistic Methods
SuperstructureSubstructureWhole Bridge
Shim and Lee (2015) [16] 53Monte-Carlo simulation
Van Noortwijk & Klatter (2004) [17] N/AWeibull distribution
Vagdatli et al. (2023) [4] 60Dynamic Bayesian Network
Vagdatli et al. (2024) [7] 78Dynamic Bayesian Network
Yianni et al. (2017) [18] 4434Petri-net model
Gadiraju et al. (2023) [19] 15,350Markov-chain model
Lee et al. (2019) [20] 84Bayesian updating
Table 2. Definition of bridge condition states according to NBI classification.
Table 2. Definition of bridge condition states according to NBI classification.
NBI ScaleConditionDescription
9ExcellentNew condition; no remarkable deficiencies
8Very goodNo repair needed
7GoodSome minor problems, minor maintenance needed
6SatisfactorySome minor deterioration, major maintenance needed
5FairMinor section loss, cracking, spalling, or scouring for minor rehabilitation; minor rehabilitation needed
4PoorAdvanced section loss, deterioration, spalling, or scouring; major rehabilitation needed
3SeriousSection loss, deterioration, spalling, or scouring that have seriously affected the primary structural components
2CriticalAdvanced deterioration of primary structural elements for urgent rehabilitation; bridge may be closed until corrective action is taken
1Imminent
failure
Major deterioration or loss of section; bridge may be closed to traffic, but corrective action can put it back to light service
Table 3. General form of transition probabilities among condition states for natural decay.
Table 3. General form of transition probabilities among condition states for natural decay.
t t + Δ t
12
1 e ( f 1 + f 4 + f 5 ) Δ t f 1 ( 1 e f 1 + f 4 + f 5 Δ t ) / ( f 1 + f 4 + f 5 )
20 e ( f 2 + f 6 ) Δ t
N 1 00
N 00
N 1 N
1 f 4 ( 1 e f 1 + f 4 + f 5 Δ t ) / ( f 1 + f 4 + f 5 ) f 5 ( 1 e f 1 + f 4 + f 5 Δ t ) / ( f 1 + f 4 + f 5 )
20 e ( f 2 + f 6 ) Δ t
N 1 e ( f 3 ) Δ t 1 e f 3 Δ t
N 01
Table 4. General form of transition probabilities among condition states with repair actions.
Table 4. General form of transition probabilities among condition states with repair actions.
t t + Δ t
12
1 e ( f 1 + f 4 + f 5 ) Δ t f 1 ( 1 e f 1 + f 4 + f 5 Δ t ) / ( f 1 + f 4 + f 5 )
2 r 1 ( 1 e r 1 + f 2 + f 6 Δ t ) / ( r 1 + f 2 + f 6 ) e ( f 2 + f 6 + r 1 ) Δ t
N 1 r 2 ( 1 e r 2 + r 6 + f 3 Δ t ) / ( r 2 + r 6 + f 3 ) r 6 ( 1 e r 2 + r 6 + f 3 Δ t ) / ( r 2 + r 6 + f 3 )
N r 3 ( 1 e r 3 + r 4 + r 5 Δ t ) / ( r 3 + r 4 + r 5 ) r 5 ( 1 e r 3 + r 4 + r 5 Δ t ) / ( r 3 + r 4 + r 5 )
N 1 N
1 f 4 ( 1 e f 1 + f 4 + f 5 Δ t ) / ( f 1 + f 4 + f 5 ) f 5 ( 1 e f 1 + f 4 + f 5 Δ t ) / ( f 1 + f 4 + f 5 )
2 f 2 ( 1 e f 2 + f 6 + r 1 Δ t ) / ( f 2 + f 6 + r 1 ) f 6 ( 1 e f 2 + f 6 + r 1 Δ t ) / ( f 2 + f 6 + r 1 )
N 1 e ( f 3 + r 6 + r 2 ) Δ t f 3 ( 1 e f 3 + r 6 + r 2 Δ t ) / ( f 3 + r 6 + r 2 )
N r 3 ( 1 e r 3 + r 4 + r 5 Δ t ) / ( r 3 + r 4 + r 5 ) e ( r 3 + r 4 + r 5 ) Δ t
Table 5. Maintenance actions and cost estimation breakdown.
Table 5. Maintenance actions and cost estimation breakdown.
Maintenance Works
Category
Applied
Condition State
Maintenance
Action
SymbolActual Unit Costs *
Prerequisite
auxiliary works
8, 7, 6, 5, 4Supply of a special under bridge inspection platform vehicle for inspection or maintenance of the bridge underside at heights > 15 m M 1 550   / u n i t
Use of a special motorized work platform for inspection or maintenance of the underside of bridges at heights > 15 m M 2 1100   / u n i t
High-grade tubular iron scaffolding M 3 9   / m 2
Minor works8, 7Protective coating for concrete surfaces, siloxane/silane based, permeable to water vapor and impermeable to water and CO2, according to ELOT EN M 4 14.4   / m 2
7, 6, 5Application of high-pressure water jetting on concrete surfaces M 5 3.60   / m 2
6, 5, 4Corrosion inhibitor application on reinforced concrete elements M 6 13.3   / m 2
Major works6, 5, 4Coating concrete surface with a cement-based sealer to extract existing moisture and protect the concrete from water M 7 6   / m 2
6, 5, 4High-strength, non-shrinking thixotropic repair mortar in an average thickness of 5 cm M 8 45.6   / m 3
5, 4Filling of small width cracks (0.3–3.00 mm) in concrete structures by injection of epoxy resin M 9 20.6   / m
5, 4Application of very high-pressure water jetting on surfaces of reinforced or prestressed concrete to expose reinforcing bars M 10 400   / m 3
* Current market prices in 2024.
Table 6. Chi-square goodness of fit results for superstructure and substructure deterioration models.
Table 6. Chi-square goodness of fit results for superstructure and substructure deterioration models.
Superstructure Markovian Deterioration Model
Training DatasetValidation Dataset
Degree of freedom2525
Significance level ( a )0.050.05
p v a l u e of Chi-square test0.4870.356
Substructure Markovian deterioration model
Training datasetValidation dataset
Degree of freedom2525
Significance level ( a )0.050.05
p v a l u e of Chi-square test0.6510.508
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Petroutsatou, K.; Vagdatli, T.; Louloudakis, N.; Panetsos, P. Life-Cycle Maintenance Cost Model for Concrete Bridges Using Markovian Deterioration Curves. Buildings 2025, 15, 807. https://doi.org/10.3390/buildings15050807

AMA Style

Petroutsatou K, Vagdatli T, Louloudakis N, Panetsos P. Life-Cycle Maintenance Cost Model for Concrete Bridges Using Markovian Deterioration Curves. Buildings. 2025; 15(5):807. https://doi.org/10.3390/buildings15050807

Chicago/Turabian Style

Petroutsatou, Kleopatra, Theodora Vagdatli, Nikolaos Louloudakis, and Panagiotis Panetsos. 2025. "Life-Cycle Maintenance Cost Model for Concrete Bridges Using Markovian Deterioration Curves" Buildings 15, no. 5: 807. https://doi.org/10.3390/buildings15050807

APA Style

Petroutsatou, K., Vagdatli, T., Louloudakis, N., & Panetsos, P. (2025). Life-Cycle Maintenance Cost Model for Concrete Bridges Using Markovian Deterioration Curves. Buildings, 15(5), 807. https://doi.org/10.3390/buildings15050807

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop