Next Article in Journal
Effect of Rotational Speed Variation on the Flow Characteristics in the Rotor-Stator System Cavity
Previous Article in Journal
Pressure Loss in Ducts by Dissipative Splitter Silencers: Comparative Study of Standardized, Numerical and Experimental Results
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Conceptual Solution Decision Based on Rough Sets and Shapley Value for Product-Service System: Customer Value-Economic Objective Trade-Off Perspective

1
School of Design and Architecture, Zhejiang University of Technology, Hangzhou 310023, China
2
College of Mechanical Engineering, Zhejiang University of Technology, Hangzhou 310023, China
*
Author to whom correspondence should be addressed.
Appl. Sci. 2021, 11(22), 11001; https://doi.org/10.3390/app112211001
Submission received: 8 October 2021 / Revised: 14 November 2021 / Accepted: 18 November 2021 / Published: 20 November 2021

Abstract

:
The product service system (PSS), as a design concept for integrated products and services, needs to be evaluated in the early design stage to maximize the value for stakeholders of the PSS concept, which is a crucial task for enterprises. However, existing methods focus on the ranking and value assessment of PSS evaluation criteria (e.g., quality, sustainability, cost), ignoring the needs conflict between customer value and economic objectives in PSS design, resulting in decision results that are not applicable to industrial enterprises. Furthermore, the influence of weight preference and uncertain information on solution evaluation is seldom considered when calculating the weight of each criterion. To fill this gap, integrating rough sets and the Shapley value decision approach for product-service system design considering customer value-economic objective trade-off is proposed, which mainly includes two parts: firstly, the best worst method (BWM) and the entropy weight method are integrated to obtain the comprehensive weight of evaluation criteria in the customer value and economic objectives; secondly, the Shapley value method in the coalition game is used to solve the optimal expectation allocation of the two objectives, so as to select the solution closest to the allocation, i.e., the optimal solution. In addition, rough set techniques are used to capture and integrate subjective assessment information originating from DMs under uncertainty. Finally, a case study of the electric forklift design is illustrated to verify the proposed decision model. The decision results show that this approach is more reliable through sensitivity and comparison analysis, and provide a valuable recommendation for enterprises to consider product service in forklift design.

1. Introduction

The product service system (PSS) is a design approach that combines products with services, which is widely adopted in the transformation of manufacturing enterprises to enhance product competitiveness [1,2]. By considering the multidimensional nature of PSS design, the PSS has the potential to create synergies between user needs and corporate profits that cannot be obtained by focusing only on the service performance (e.g., sustainability, serviceability) or more traditional objectives (e.g., time, quality) in product development [3]. Furthermore, PSS provides customers with integrated solutions of products and services, and provides personalized services according to different user needs, so as to improve customer satisfaction [4]. The PSS design cycle comprises a large number of design factors and data [5], which can be used to identify customer requirements and evaluate PSS conceptual solutions. However, excessive focus on customer demands may lead to designs that are too expensive to be implemented as actual industrial products. For example, there are conflicting needs between users’ service performance of the product and the product lifecycle cost of the enterprises, which may increase the burdens for enterprises to improve the serviceability of PSS design. For this reason, to satisfy the customer service needs of the product in the PSS design and not exceed the economic capacity of the enterprise, PSS concept trade-off decisions need to be made to ensure the feasibility of downstream activities of PSS design. This research aims to find the optimal trade-off between the economic needs of the company and customer value (CV), so as to solve the optimal ratio between CV and economic objectives of PSS design is still one of the most significant questions needing to be answered.
The early-stage evaluation of PSS conceptual solutions involves a conventional multiple-criteria decision analysis problem [6,7], which includes conventional objectives such as quality, time, cost and performance, and PSS service characteristics. Therefore, the evaluation of PSS designs differs from conventional product evaluations. To select the optimal PSS solution, it is necessary to have accurate evaluation criteria weights and holistically consider the value of each PSS conceptual solution across all criteria. A plethora of weighting models have been used to calculate evaluation criteria weights, such as the analytical network process (ANP) [8], analytic hierarchy process (AHP) [9], and quality function deployment (QFD) [10]. These methods are based on the matrix construction method, and the decision-makers (DMs) can make subjective judgment among the criteria to obtain the subjective weight of these criteria [1]. However, because pairwise comparisons by DMs are necessary to determine the priority of each evaluation criterion, the weightings will contain uncertainties, owing to subjective factors such as the knowledge, skill, and ability of the DMs. Accordingly, attempts have been made to minimize subjectivity, using subjective weighting models, such as the entropy weight method (EWM) [11] and CRITIC method [12]. However, because objective and subjective weighting methods ultimately rely on the evaluation data provided by DMs, their evaluation data inherently contain some ambiguity and subjectivity, which will affect the accuracy of the final decision. Rough sets are often used to capture assessment information from multiple DMs, as they can characterize the uncertainty of the assessment information using interval boundaries, without adopting auxiliary data or membership functions [13,14]. This helps to ensure the objectivity of the decision-making process.
However, aggregating the assessments for the conceptual PSS solution remains a major challenge. During the design of a PSS, each PSS design (solution) is evaluated by numerous stakeholders based on various factors, including functionality, environmental, and social factors. The resulting assessment data will then be adopted to model the PSS evaluation process and determine the optimal solution [15]. Bertoni [16] constructed a five-step iterative process to support decision making in PSS design, which matches CV with sustainability to ensure customer satisfaction and meet performance requirements. Liu et al. [17] used a refined QFD tool to convert customer requirements into engineering characteristics and ranked these characteristics by importance. Owing to the increasing complexity of PSS evaluation challenges, several multiple-criteria decision models have been adopted to extract the overall value of PSS conceptual solutions, such as the technique for order of preference by similarity to ideal solution (TOPSIS) [14,18], višekriterijumska optimizacija i kompromisno rešenje (VIKOR) [19,20], and the preference ranking organization method for enrichment evaluation (PROMETHEE) [21]. For instance, Wang and Durugbo [22] adopted the fuzzy AHP and fuzzy technique for order of preference by similarity to ideal solution (TOPSIS) to evaluate PSS designs and analyze the benefit and operational risks in converting a product-focused business into a service-oriented operation. Qi et al. [23] proposed a modified rough vlsekriterijumska optimizacija i kompromisno resenje (VIKOR) model to reconcile the effects of objective design and subjective preferences on conceptual solution evaluations, thereby enhancing the objectivity of the design concept evaluation. Furthermore, it can be determined that the aforementioned method can transform multiple evaluation criteria into a single objective, as well as calculate the comprehensive utility of the solution using this objective. However, the disparity between CV and economic interests is rarely discussed in previous studies [15]. In most cases, CV is simply considered an ordinary design requirement (such as weight, price, or power) when assessing the optimality of a conceptual solution. Considering the competing relationship between customer needs and economic goals, one needs to weigh the design benefit conflicts between product economics and customer needs, and to satisfy product service quality as much as possible while reducing the burden of service transformation in the enterprise, which further promotes our research motivation.
To address this issue, this study focuses on balancing the effects of CV and economic requirements on the overall design of a PSS, by considering this process as a cooperative game. It is well-understood that the balancing problem implies that it is impossible for a PSS decision to maximally satisfy all requirements, as the relative importance of CV and economic objectives must be considered to form a balanced solution. Therefore, the multi-objective balancing process resembles cooperative game theory [11,24], which attempts to obtain an optimal compromise by balancing the interests of all design objectives [25]. Moreover, the utility functions used in cooperative game theory are suitable for the incomplete and fuzzy nature of the early PSS design phase, as they do not require precise inputs and outputs.
Inspired by this idea, a conceptual scheme decision approach integrating rough sets and Shapley value for product-service system considering CV-economic objective trade-off is proposed. Compared with previous decision-making methods for PSS design, the main contributions of this study are summarized as follows:
(1)
The best worst method (BWM) and entropy weight method are integrated to consider the personal preference and objective weight of the evaluation criteria, and to realize the accurate calculation of the weight.
(2)
The Shapley value method is proposed to weigh the requirement conflict between the CV and economic objectives, and then the optimal expectation ratio for the two objectives is solved to determine the scheme with optimal overall interests.
(3)
The rough set technique is introduced to integrate the subjective evaluations from multi-DMs and transform the evaluation data into interval values for the construction and calculation of the criteria weights and game utility functions without additional auxiliary information.
The remaining sections in this paper are as follows. Section 2 reviews the PSS design evaluation. Section 3 describes the integrated BWM and Shapley value method for PSS design decision framework. Section 4 takes the electric forklift design as a case study to verify the proposed approach and present discussions. Section 5 draws conclusions and presents future work.

2. Research on PSS Design Evaluation

When a manufacturer initially transitions from a product-focused approach to PSS, they are more likely to encounter design issues or accidents owing to a lack of service design knowledge. Simultaneously, various feasible PSS concepts are usually generated during the early design stage [12], and the selection of design concepts directly affects the service performance of the PSS concepts. Therefore, how to evaluate and rank the PSS design concepts and provide a most suitable design for the detailed design is still a critical issue in the scientific field of PSS.
Previously, Qu et al. [26] conducted a systematic review of the PSS literature, and analyzed PSS evaluation methodologies from the perspectives of CV and sustainability and their trade-offs. Geng and Chu [27] proposed an importance-performance analysis (IPA) method based on Kano’s model to evaluate the importance of CV; in addition, they employed vague sets to handle the uncertainty of PSS evaluations. Presently, studies on PSS concept evaluation generally focus on two areas: (1) PSS criteria weighting based on customer requirements, and (2) the objective aggregation of PSS assessment information. Because PSS concept evaluation is a multiple-criteria decision analysis problem, accurate criteria weights are crucial for the efficacy of this process. Accordingly, various weighting methods have been proposed to obtain accurate criteria weights. For instance, Lee et al. [28] used a combination of ANP and niche theory to quantify customer perceptions of value throughout the customer experience cycle, as well as facilitate the selection of PSS concepts. To help designers to select optimal PSS designs, Chen et al. [29] presented a method that adopts the decision-making trial and evaluation laboratory (DEMATEL) model to determine influence weights between design attributes, including the VIKOR method to determine the gap between a conceptual solution and the ideal solution. The aforementioned methods (including ANP and DEMATEL) all rely on the construction of several judgment matrices and a large number of pair-wise comparisons. Consequently, with several criteria, these methods often fail to obtain accurate and objective criteria weights. On this basis, BWM, a new multi-criteria decision-making method, was proposed by Professor Rezaei [30], based on the idea of pairwise comparison to complete the calculation of criteria weight. Additionally, the advantage of BWM is to construct a structured comparison method rather than any two criteria pairwise comparison [31]. However, because the aforementioned subjective weighting methods consider subjective judgments of the DM, it is inevitable that the resulting criteria weightings will be strongly biased by the personal preferences of the DM. Hence, the entropy weight method (EWM) was implemented in our research to correct the subjective weightings of each criterion, and to construct a comprehensive weighting function that ensures objectivity in the evaluation of PSS conceptual solutions.
In the early stages of PSS development, quantitative data on customer needs and values are usually unavailable, and the uncertainty in decision analysis data often triggers invalid or inaccurate evaluations. In several studies, fuzzy models have been adopted to improve the accuracy of decision analysis, such as intuitionistic fuzzy sets, fuzzy set theory, and rough set theory have been proposed to capture uncertainty evaluation information. Fuzzy analysis does not require quantitative input from DMs, but can obtain initial evaluation information by predetermined membership function, and transform it into scheme evaluation data. For instance, Chen et al. [32] used fuzzy random variables to address uncertainties in PSS concept evaluation data, and ranked PSS conceptual solutions using the information axiom (i.e., minimize information content). Liu et al. [33] used intuitionistic fuzzy number operators and DEMATEL to evaluate the hesitancy of expert PSS judgments and derive all interdependencies between co-creative value propositions (CVPs), respectively. They then validated their method using a smart fridge service system. Ma et al. [34] proposed a concept evaluation model based on the fuzzy morphological matrix, and developed a fuzzy multi-objective optimization model to select the design concept with maximum customer satisfaction. After that, determining membership and non-membership in fuzzy sets and intuitionistic fuzzy sets remains a critical challenge [14]. For this issue, rough set technology can integrate the original evaluation data from various DMs, and does not require a predetermined membership function or auxiliary information. In addition, a rough-Z-number-based DEMATEL was proposed by Zhu et al. [35] to address uncertainties in stakeholder evaluations and determine the risk prioritization of sustainable value propositions. To improve the delivery performance of PSSs, Song et al. [12] proposed a method that adopts rough sets to perform fuzzy processing on a priori information, which then ranks evaluation criteria using the best worst method (BWM) and criteria importance through the inter-criteria correlation (CRITIC) method. Obviously, rough number in rough set is an objective mathematical model, which can integrate the original individual judgment of each DM from group experts.
Based on Table 1, we compare our proposed approach with the pertinent literature for PSS design decisions in Table 1. Additionally, previous studies in this area have widely focused on the calculation of criteria weights for assessing the value of PSS concepts. This has resulted in the selection of PSS conceptual solutions that are relatively unsuitable for the needs of both manufacturers and customers. There are few studies that quantitatively assess the conflict of interest between customer demand and economics objectives with respect to enterprises for PSS design, and some do not even consider the uncertainty of assessments come from stakeholders’ subjective judgments. The intent of this study is to fill this gap, and the coalitional game is adopted to reconcile the conflicting between customer demand and economics objectives for PSS design under uncertainty. In this study, a Shapley value is obtained to represent a stable coalition condition in which all objectives will not unilaterally leave this coalition to improve their own benefits—please refer to [11,25].

3. Methodology

Figure 1 shows a PSS concept decision trade-off model based on rough sets and the Shapley value method, which is used to select the optimal concept to trade-off CV-economic expectations for enterprise. The proposed decision analysis framework comprises two parts. In the first part, BWM and EWM are adopted to calculate subjective and objective weights to satisfy CV and economic PSS evaluation criteria, which are then used to construct a comprehensive weighting function and rank the criteria and their importance. In the second part, CV and economic criteria are considered players in constructing a cooperative game comprising players, strategies, and utility. The Shapley value model is adopted to calculate the contribution of each player to the product’s overall gain (optimal utility allocation), and the solution whose allocation of utilities is closest to the Shapley value is considered the optimal solution. The aforementioned procedure enables the criteria weighting process to balance CV and economic objectives via the creation of importance ratios during the design phase. This will prevent an excessive focus on PSS performance without considering cost, which would be detrimental to its competitiveness.

3.1. Acquisition of Conceptual Solutions and PSS Evaluation Criteria for CV

The systematic approach presented by Beitz [37] was adopted to perform requirement analysis, extract the overall function of the products, and decompose this function into energy, material, and signal flows, to ultimately obtain subfunctions for the principal solution. Among them, sub-function t (αtF) can be realized by multiple principle solutions, and the principle solution in each sub-function are selected to be combined into a conceptual scheme. Then, to obtain a structure that satisfies the aforementioned subfunctions and CV requirements, and construct the product morphology matrix shown in Table 2, the product knowledge database was searched according to customer demands (Table 3). A total of α = 1 F t PS combinations can then be created, where t denotes the number of principal solutions. Subsequently, to eliminate unfeasible solutions, Pugh’s table [38] was used to screen the solutions according to the basic configuration and designed purpose of the product.
To evaluate the customer satisfaction for a candidate PSS design, one must determine whether the conceptual solution will provide the services demanded by the customer, and whether the customer will obtain reliable service quality from the product. Therefore, PSS evaluation is a conventional multiple-criteria problem that includes customer demands such as environmental, cost, and sustainability demands [39]. Based on previous studies on PSS evaluation [12,40], the performance elements of a PSS can be defined as the lowest level performance requirements of a system, which are obtained by decomposing a system to its most basic elements. These system performance requirements can then be adopted by the product and service designer to convert CVs into specific design criteria. According to the service quality tool (SERVQUAL) model [41] and CV hierarchy theory [42,43], the CVs of a PSS can be divided into six: reliability, environmental, flexibility, social, and economic values. These CVs can be converted into ten PSS design criteria, as presented in Table 3. Therefore, to ensure that the PSS in the conceptual solution provides an adequate level of service quality with minimal product design costs, it is necessary to analyze the disparity between the PS value and economic requirements during the design of the PSS.

3.2. Calculation of Evaluation Criteria Weights Based on Rough BWM and Entropy Weight Method

In this section, the rough BWM and EWM methods are adopted simultaneously to compute the comprehensive weights of the CV and economic criteria. This approach circumvents the weakness of objective weight calculations (i.e., weights that do not consider DM preferences), and also reduces the uncertainty triggered by subjective preferences. In addition, the preference evaluation for criteria is evaluated by the DM using the so-called 9-point scale [34,44], which is defined as follows: 1, very low (VL); 3, low (L); 5, moderate (M); 7, high (H); 9, very high (VH); and 2, 4, 6, 8, intermediate values between the two adjacent judgments.

3.2.1. Calculation of Subjective Weights of Evaluation Criteria Using Rough BWM

Step 1. Let the set of CV evaluation criteria be {a1, a2, …, an}. The importance of each criterion is assessed via expert questionnaires [45], and the results of this assessment are adopted to identify the best criterion cB and worst criterion cW.
Step 2. Based on the 9-point scale, by determining the preference of the optimal criterion over other criterions, a best-to-others vector HkB = (hkB1, hkB2, …, hkBn) is constructed. Similarly, the preference of other criteria for the worst criterion is evaluated, and an others-to-worst vector HkW = (hk1W, hk2W, …, hknW) is constructed, where hkWj represents the preference of DM k (1 ≤ km) for other criteria j (1 ≤ jn) compared to the worst criterion.
Step 3. Rough comparison vectors are constructed for all of the DMs [10,38]. Suppose that RkB1 = {h1B1, h2B1 …, hmB1}, where any preference assessment relative to Criterion 1 is hphkB1, XRkB1. The lower ( A p r ¯ h p ) and upper ( A p r ¯ h p ) approximations can then be defined as:
A p r ¯ ( h p ) = { X R k B 1 / R k B 1 ( X ) h p } A p r ¯ ( h p ) = { X R k B 1 / R k B 1 ( X ) h p }
Then, based on Equation (2), the rough number RN(hp) is defined by its lower limit ( L i m ¯ h p ) and the upper limit ( L i m ¯ h p ), respectively.
L i m ¯ ( h p ) = 1 Q L R B i ( X ) | Y A p r ¯ ( h p ) L i m ¯ ( h p ) = 1 Q U R B i ( X ) | Y A p r ¯ ( h p ) R N ( h p ) = [ L i m ¯ ( h p ) , L i m ¯ ( h p ) ]
Equations (1) and (2) are used to construct rough comparison vectors, RN(hBj) and RN(hjW), for criterion j, as expressed in Equation (3).
R N ( h B j ) = { [ h B j 1 ¯ , h B j 1 ¯ ] , [ h B j 2 ¯ , h B j 2 ¯ ] , , [ h B j m ¯ , h B j m ¯ ] } R N ( h j W ) = { [ h j W 1 ¯ , h j W 1 ¯ ] , [ h j W 2 ¯ , h j W 2 ¯ ] , , [ h j W m ¯ , h j W m ¯ ] }
Subsequently, the averages of the rough series can be expressed as rough numbers of the comparison vectors. The rough numbers, R N ¯ (hBj) and R N ¯ (hjW), defined by Equation (4), can be transformed as follows: R N ¯ (hBj) = {[   h B 1 ¯ ,   h B 1 ¯ ], [ h B 2 ¯ ,   h B 2 ¯ ], …, [ h B n ¯ ,   h B n ¯ ]}, R N ¯ (hjW) = {[   h 1 W ¯ ,   h 1 W ¯ ], [ h 2 W ¯ ,   h 2 W ¯ ], …, [ h n W ¯ ,   h n W ¯ ]}.
R N ¯ ( h B j ) = [ h B j ¯ , h B j ¯ ] = 1 m k = 1 m [ h B j k ¯ , h B j k ¯ ] R N ¯ ( h j W ) = [ h j W ¯ , h j W ¯ ] = 1 m k = 1 m [ h j W k ¯ , h j W k ¯ ]
where h B j k ¯ and h B j k ¯ represent the upper and lower boundaries of the rough number R N ¯ (hBj), respectively, while h j W k ¯ and h j W k ¯ denote the upper and lower bounds of the rough number R N ¯ (hjW), respectively.
Step 4. A nonlinear min-max mathematical programming problem is constructed, as expressed in Equation (5). This is used to evaluate the rough weight of each criterion, RN(wj). In addition, d([x],[y]) represents the degree of separation between the RN(x) and RN(y) rough sets [46], while [wB] and [wW] denote the weights of the best and worst criteria, respectively, as expressed in Equation (6).
min max j d ( [ w B ] [ w j ] ,   [ h B j ] ) , d ( [ w j ] [ w W ] ,   [ h j W ] ) ; s . t . j = 1 n w j ¯ 1 ,   for   all   j . j = 1 n w j ¯ 1 ,   for   all   j . w j ¯ w j ¯ 0 ,   for   all   j .
d ( [ x ] , [ y ] ) = ( x ¯ y ¯ ) 2 + ( x ¯ y ¯ ) 2
Based on the rules of arithmetic operations with rough numbers and the characteristics of min-max programming problems [13], to obtain the optimal weights wj = [w1*, w2*, …, wn*] and goals constraint ξ, an improved mathematical model was proposed by Rezaei [47], and the objective function was customized as follows:
min ζ ; s . t . w B ¯ h B j ¯ w j ¯ ζ ,   w B ¯ h B j ¯ w j ¯ ζ ,   for   all   j . w j ¯ h j W ¯ w W ¯ ζ ,   w j ¯ h j W ¯ w W ¯ ζ ,   for   all   j . j = 1 n w j ¯ 1 ,   j = 1 n w j ¯ 1 ,   for   all   j w j ¯ w j ¯ 0 ,   for   all   j .
where ξ denotes the goals constraint, and {[ w 1 ¯ , w 1 ¯ ], [ w 2 ¯ , w 2 ¯ ], …, [ w n ¯ , w n ¯ ]} represent the optimal rough weights of criteria.
The Lingo18 software is used to solve the aforementioned linear programming problem, while Equation (8) is adopted to normalize the rough weights of the evaluation criteria and calculate their crisp weights (wj, where wj ∈ [0,1).
w j = ( 1 α ) w j ¯ + α w j ¯

3.2.2. Calculation of Objective Weights of Evaluation Criteria Using the Entropy Weight Method

The entropy weight method describes the uncertainty of evaluation information in objectively analyzing the importance of the evaluation criteria [38,48]. To address biases in the subjective weighting solutions, an initial evaluation matrix for solution values is first constructed using the evaluation criteria. The EWM is then adopted to calculate the objective weight of each evaluation criterion.
Step 1. The CV evaluation criteria are first divided into quantitative and qualitative criteria. Then, the DM k evaluates the solution, and the evaluations of all DMs are gathered to construct the initial evaluation matrix IEM = (xij)K×n, where 1 ≤ iK. In particular, qualitative criteria are evaluated using a 9-point scale. For quantitative criteria, each DM suggests an appropriate value according to his own perception and experience. For example, based on the criterion E1 in our case, the value judgments of CS1 are assigned by four DMs, which are 1.75 (t), 1.80 (t), 1.50 (t), and 1.75 (t), respectively.
Step 2. Equations (1) and (2) are used to convert the evaluation data of the DMs into rough numbers and construct the rough value matrix (RVM) of the solutions, RVM = (x’ij)K×n. This matrix is adopted to compute objective evaluation data for the criteria weights.
Step 3. The RVM of the solutions in terms of CV criteria is first constructed, and then normalized using Equation (8). Subsequently, the rough values of the solutions in terms of cost criteria are converted into utility values to produce the normalized rough value matrix NRM = (fij)K×n, which is adopted in subsequent dimensionless entropy weight and criteria effect calculations, as expressed in Equation (9).
r i j = [ r i j L , r i j U ] = f i j L / i ( f i j U ) 2 , h i j U / i ( f i j L ) 2 ,   j benefit   criterion 1 / f i j U / i ( 1 / f i j L ) 2 , 1 / f i j L / i ( 1 / f i j U ) 2 ,   j cost   criterion
where fijL and fijU denote the lower and upper bounds of the rough number of criteria j in solution i, respectively.
Step 4. The information entropy ej of each evaluation criterion is calculated based on the normalized RVM. ej represents a measure of the uncertainty of the solution values for each criterion j; the higher the value of ej, the more consistent the data for an evaluation criterion, and the lower its weight. The formulas for calculating ej are expressed in Equations (10) and (11):
e j = λ ( 1 ln K i = 1 K g i j ln g i j ) + ( 1 λ ) ( 1 ln K i = 1 K z i j ln z i j )
g i j = r i j L + r i j U / 2 i = 1 K r i j L + r i j U / 2 , z i j = 1 r i j U r i j L K i = 1 K r i j U r i j L
where λ (0 < λ < 1) is the balancing coefficient for the median of the rough number and uncertainty of DM evaluations. In this study, λ was set to 0.5 in all ej calculations.
Finally, Equation (12) is adopted to compute the entropy weight of each evaluation criterion using their information entropy, thus generating their objective weights.
e w j = 1 e j / j = 1 l 1 e j
Based on Equation (13), the normalized comprehensive weight function cwj is constructed by integrating the subjective weight and objective entropy weight of each criterion in the aforementioned Section 3.2.1 and Section 3.2.2, and to ensure the stability of the ranking results of schemes.
c w j = w j e w j / j = 1 l w j e w j

3.3. Decision of the Optimal Solution Based on the Coalitional Game Model

Within the context of this study, the coalitional game model is a multi-objective cooperative game model that is used to analyze design preferences and internal relationships in CV and economic objectives. In this section, the coalitional game model will be used to analyze the coalitional utility of CV and economic objectives in different solutions. The Shapley value will then be adopted to obtain a fair allocation of utilities, to ensure that none of the players (objectives) will try to leave the coalition. Furthermore, the Shapley value of each objective is a fair payoff, which considers the interactions between all objectives in calculating the optimal payoff that maximizes coalitional utility. The Shapley values were obtained via the following procedure:
Step 1. Construction of the coalition game: Firstly, one must define the players, strategies, and utility of the coalition game model. The model is expressed as G = {Pc; Sc; Uc}, c ∈ P, E, while the CV and economic objectives are projected as players Pp and PE, respectively. The strategy of Pp is Sp(CSi) = {P1(CSi), …, PM(CSi)}, where M denotes the number of CV criteria, respectively. Similarly, the strategy of PE is SE(CSi) = {P1(CSi), …, PN(CSi)}, where N denotes the number of economic criteria. Because each conceptual solution corresponds to the strategy sets of a pair of players, S = (SP(CSi), SE(CSi)), if one selects some strategy set such as CSi, the player utilities are UP(SP(CSi), SE(CSi)), and UE(SP(CSi), SE(CSi)). Therefore, once a strategy has been determined for one player, the strategy of the other player is also determined. However, because the solution values of PP and PE in each evaluation criterion are different, any change in the strategy of Pp will inevitably affect the designed expectation of PE, thereby changing the overall designed expectation of the solution. The conflict of interest between Pp and PE must be balanced by selecting the strategy set that best satisfies the design expectations of both players, i.e., the optimal conceptual solution.
Step 2. Calculation of player utilities: Given that each strategy set (SP(CSi), SE(CSi)) corresponds to a conceptual solution, the player utilities reflect the expected value of each solution for a given strategy. Because each solution represents an attempt by the designer to balance the design requirements of the PSS, the evaluations of the solutions will exhibit conflicts or dependencies with each other, and the utility of one player will inevitably influence that of the other. The objective of the coalitional game is to determine the optimal allocation of utilities to CV and economic objectives, despite their mutual antagonism, to maximize the overall utility of the solution. After the strategy (CSi) has been determined, it is necessary to consider the effects of the evaluation criteria (which have different weights) on player utility under the selected strategy set, and then objectively compute the utility of each player. First, the criteria weights (Equation (8)) are adopted to transform the solution’s normalized rough values in CV and economic objectives into crisp values r’ij (α = 0.5). The weights are then applied to obtain the actual utilities of the players. To ensure that the utilities are expressed in a consistent, comparable and intuitive manner, the actual utilities of each player are averaged by their number of criteria. Finally, the relative average of all criteria relative to the average utility is considered the utility of the CV and economic objectives, as expressed in Equations (14) and (15).
a v e J j c = 1 K i = 1 K c w j c r j c ( C S i ) ,   c P ,   E
U P S P ( C S i ) ,   S E ( C S i ) = 1 M × j p = 1 M c w j p r j p ( C S i ) a v e J j p   U E S P ( C S i ) ,   S E ( C S i ) = 1 N × j E = 1 N c w j E r j E ( C S i ) a v e J j E  
where ave(Ji) represents the average of all solution values in the criterion j, jp and jE denote the CV and economic objective, while rj(CSi) is the crisp value of the criterion j in solution i.
Based on the utility function, the normalized rough values of each solution are adopted to obtain the CV and economic utilities of the various conceptual solutions. These utilities are then used to construct the utility matrix presented in Table 4.
Step 3. Finding the optimal allocation of utilities: in a coalitional game, the players cooperate to maximize the utility of the coalition and their personal utility, as well as obtain a practical allocation of utilities (i.e., Shapley values). In the current context, the CV and economic objectives form a coalition N that attempts to maximize coalitional utility, where N = {P, E}. Three possible non-empty coalitions c exist: {P}, {E}, and {P, E}. To ensure that all players gain utility by cooperating with each other, instead of abandoning the coalition to form single coalitions (such as {P} or {E}), a pessimistic standard [25,49] was adapted to define the characteristic function that calculates the coalitional utility v({c}) of each player, as expressed in Equation (16). This approach ensures that coalitional utility is maximized if the players cooperate with each other, regardless of the strategy adopted by the coalition {c}.
a v c = min max 1 i K U c S P ( C S i ) , S E ( C S i )
where c represents the players P and E.
The coalition {P, E}, which exists if the players are cooperating, has the characteristic function v({P, E}) = min{UP + UE}. Therefore, coalitional utility is maximized if the CV and economic players (P and E) cooperate with each other. This also implies that the coalition will still maximize the utility of each player despite their conflicting interests. The Shapley value is defined as φ(v) = (φ1(v), φ2(v), ..., φL(v)), and it is the optimal allocation of player utilities that will optimize the overall utility of the coalition. Because L is 2, φ(v) = (φP(v), φE(v)). In other words, the Shapley value balances the interests of the solution’s CV and economic objectives to provide the optimal allocation of utilities that maximizes coalitional and player utility in a competitive environment, as expressed in Equation (17). In addition, the Shapley value can be regarded as the expectation of each player’s utility in the overall coalition utility, thereby reflecting the importance degree of different players on the overall interest. The Shapley value is proportional to the contribution of a player to the designed value of the solution, as well as the influence of the player on the coalition’s overall utility.
ϕ c v = S :   c S S ! d 1 S ! d ! × v S c v S
where S is an arbitrary subset of coalition N that does not contain c, |S| is the number of players included in S, v = (S∪{c}) represents the coalition utility when S and the game player c cooperate, and d represents the number of players.
Step 4. Ranking solutions based on their Shapley values: Equation (18) is adopted to compute the optimal expected ratio of the players, (φP(v), φE(v)). The deviation function [50] is then used to compute the deviation of all solutions from this ratio. The solution with the smallest deviation is the design that maximizes the overall utility of the PSS; hence, it is the optimal solution. φP(v) and φE(v) represent the optimal balance between CV and economic objectives, respectively, and they ensure that the CV requirements will be satisfied with minimal losses in economic value. This will provide a fresh perspective for designers and enterprises, as it was impossible to evaluate the product-service value and cost during the early design phase. Moreover, the relative importance between the intrinsic service value and economic objectives of the scheme can be mined without auxiliary functions or parameters because the Shapley values were computed from the evaluation data of the initial solutions. Hence, this approach improves the objectivity of the decision.
D C S i = U P C S i ϕ P v 2 + U E C S i ϕ E v 2
where UE(Schj) and UT(Schj) are the economic and technical utilities of solution j, D(CSi) represents the deviation of solution i from the optimal distribution of utilities, and φ(v) = (φP(v), φE(v)).

4. Case Study

Owing to the rapid growth of small warehouse logistics, electric forklift buyers have become increasingly demanding in terms of their service requirements. For example, electric forklifts are now required to support online purchasing, online maintenance, and delayed scrapping, and this has intensified the competitiveness amongst forklift manufacturers [51,52]. To obtain a warehouse logistics solution that satisfies all CV and economic objectives in the initial design phase, forklift manufacturers must evaluate the CV and economic value of their warehouse logistics solutions within the design phase, and then select an optimal conceptual solution. Therefore, a case study of electric forklift PSS concept design is employed to verify the proposed decision model.

4.1. Determination of Evaluation Criteria for CV and Economic Value in the Electric Forklift PSS

The overall function of an electric forklift is to move goods using electrical power. According to its energy, material, and information flows, this function can be further decomposed into moving goods, turning wheels, increasing height, braking, changing directions, and operating the vehicle. The principal solutions that satisfy the aforementioned functions were obtained by searching through the product knowledgebase; these solutions were then adopted to construct the morphological matrix of an electric forklift, as presented in Table 5.
Six research students from our group were asked to screen the principal solutions by using a Pugh table to qualitatively ascertain the initial principal solution combinations. Accordingly, the principal solutions that were clearly impractical were eliminated (the screening process will not be described in further detail, and interested readers can refer to [44]). Finally, a total of six candidate concept schemes were selected, with the names CS1 (A1B3C1D3E1F2G1); CS2 (A1B3C1D1E1F2G2), CS3 (A2B3C1D3E2F3G1), CS4 (A1B1C1D3E1F1G1), CS5 (A3B3C1D3E2F3G1), and CS6 (A1B3C1D3E2F3G2), respectively. In addition, SM and SC in Figure 2 denote the service modules in the electric forklift PSS and the corresponding sub-items, respectively, as shown in Table A1.
The technical, operational, and design characteristics of warehouse logistics systems were used to determine their economic requirements. Accordingly, eight evaluation criteria were formed, which include E1 (rated lifting capacity), E2 (maximum driving speed), E3 (maximum lifting height), E4 (motor power), E5 (production cost), E6 (maintenance cost), E7 (safety), and E8 (forklift weight). The specific definitions and categories of these criteria are presented in Table 6. Here, it should be noted that economic value in the context of CV pertains to the customer’s user experience or psychological expectations, while cost-related economic objectives are related to product costs due to design-related activities such as structural optimization, manufacturing, and assembly.

4.2. Calculation of Criteria Weights Integrating Rough BWM and Entropy Weight Method

4.2.1. Calculation of Subjective Weights of CV and Economic Criteria for Warehouse Logistics System

Step 1. Consistent with previous studies [53], four experts were invited to determine the best and worst criteria. The selected experts possess skills and experience in the design and development of warehouse logistics PSSs, and they include one forklift designer, one service engineer, one manufacturing engineer, and one PSS researcher. The best and worst CV criteria were P1 and P5, while the best and worst economic criteria were E7 and E8, respectively.
Step 2. The four DMs were asked to compare each criterion to cB and cW on a 9-point scale. Then, the best-to-others vector and the others-to-worst vector were obtained through comparison between criteria, as shown in Equations (19) and (20). Among them, hkWW = 1 and hkBB = 1.
PSS   criteria : 1 2 3 4 5 6 7 8 9 10 H B P = DM 1 DM 2 DM 3 DM 4 1 2 6 6 9 6 8 4 2 4 1 3 3 6 9 5 5 6 2 6 1 2 2 7 9 2 5 2 5 6 1 2 3 6 9 5 3 3 5 3 , 1 2 3 4 5 6 7 8 9 10 H W P = 9 6 6 3 1 4 4 3 7 3 9 6 6 3 1 7 4 7 4 3 9 4 7 6 1 6 3 5 4 3 9 6 6 3 1 4 6 6 4 6
Economic   criteria : 1 2 3 4 5 6 7 8 H B E = DM 1 DM 2 DM 3 DM 4 3 4 1 4 3 4 1 9 3 1 2 5 2 8 1 9 1 5 1 3 3 4 1 9 1 4 2 2 4 2 1 9 , 1 2 3 4 5 6 7 8 H W E = 6 9 7 4 7 1 9 1 8 4 8 6 6 5 9 1 7 4 6 3 6 9 9 1 9 5 7 7 5 7 9 1
Step 3. The rough comparison vector for the CV and economic objectives were calculated by Equations (1) and (2). Taking the results of the best criterion P1 to P2 as an example, the result was {2,3,2,2}, RN(hPB2) = {[2,2.75], [2.33,3.5], [2,2.75], [2.75,4]}, and the average rough set was R N ¯ (hPB2) = [(2 + 2.333 + 2 + 2.75)/4, (2.75 + 3.5 + 2.75 + 4)/4] = [2.271,3.250]. Then, the rough sets of other evaluation criteria were integrated to construct the rough comparison vector, as shown in Table 7.
Step 4. By constructing the rough comparison vector, a programming problem was constructed according to Equations (6) and (7). LINGO 16.0 was used to solve this problem, and the rough weight vectors for criteria are described in Table 8. Next, the crisp weight was obtained by using Equation (8).

4.2.2. Calculation of Objective Weights of CV and Economic Criteria for the Electric Forklifts PSS

Step 1. The four DMs evaluated the CV of the PSS solutions according to the aforementioned evaluation criteria. Qualitative criteria were assessed by a 9-point scale, where a score of 9 represents the value of the solution that is most consistent with the criteria, and a score of 1 indicates that the value of the solution is the least consistent. In addition, considering the limitation of paper length, this study took the CS1 as an example to construct the initial evaluation matrix of electric forklift, as shown in Table 8. Additionally, other evaluation matrixes were used for the remaining schemes in Appendix A, as shown in Table A2, Table A3, Table A4, Table A5 and Table A6.
Step 2. To provide objective information on the value of each solution, rough numbers were generated using the data in the initial evaluation matrix. Taking the sequence of the criterion E1 for CS1 as an example, the sequence was [1.75, 1.80, 1.50, 1.75], L i m ¯ 1.75 = (1.75 + 1.5 + 1.75)/3 = 1.667, L i m ¯ 1.75 = (1.75 + 1.8 + 1.75)/3 = 1.767, L i m ¯ 1.8 = (1.75 + 1.8 + 1.5 + 1.75)/4 = 1.7, L i m ¯ 1.8 = (1.8)/1 = 1.8, L i m ¯ 1.5 = (1.5)/1 = 1.5, L i m ¯ 1.5 = (1.75 + 1.8 + 1.5 + 1.75)/4 = 1.7. Based on Equations (1) and (2), the rough value of CS1 with respect to the criterion E1 was calculated as RN(E11) = RN(E41) = RN(1.75) = [1.667,1.767], RN(E21) = RN(1.8) = [1.7,1.8], RN(E31) = RN(1.5) = [1.5,1.7]. The average rough set was [(1.667 + 1.7 + 1.5 + 1.667)/4, (1.767 + 1.8 + 1.7 + 1.767)/4] = [1.633, 1.758]. The previous step was then repeated to obtain RVMs for the CV and economic objectives, as expressed in Equations (21) and (22).
Ρ V Μ P = C S 1 C S 2 C S 3 C S 4 C S 5 C S 6 P 1 P 2 P 3 P 4 P 5 P 6 P 7 P 8 P 9 P 10 [ [ 4.208 , 6.708 ] [ 3.250 , 3.750 ] [ 5.104 , 6.354 ] [ 4.750 , 7.250 ] [ 5.583 , 6.833 ] [ 5.625 , 6.667 ] [ 3.363 , 4.775 ] [ 3.563 , 4.896 ] [ 6.063 , 6.438 ] [ 2.583 , 3.417 ] [ 6.500 , 7.500 ] [ 6.750 , 8.250 ] [ 4.750 , 6.250 ] [ 4.688 , 6.750 ] [ 5.250 , 5.750 ] [ 2.875 , 5.292 ] [ 5.104 , 6.354 ] [ 5.333 , 6.750 ] [ 3.250 , 3.750 ] [ 4.250 , 4.750 ] [ 5.583 , 6.417 ] [ 4.167 , 5.833 ] [ 5.750 , 6.729 ] [ 5.646 , 6.368 ] [ 5.250 , 5.750 ] [ 4.271 , 5.250 ] [ 4.250 , 4.750 ] [ 3.646 , 4.896 ] [ 5.250 , 6.667 ] [ 3.958 , 6.042 ] [ 4.813 , 6.771 ] [ 3.750 , 5.250 ] [ 4.625 , 6.292 ] [ 5.563 , 5.938 ] [ 6.688 , 7.813 ] [ 5.250 , 6.667 ] [ 4.333 , 5.750 ] [ 4.500 , 5.500 ] [ 5.583 , 6.417 ] [ 2.958 , 5.042 ] [ 5.104 , 6.354 ] [ 7.000 , 7.000 ] [ 5.167 , 6.833 ] [ 3.750 , 5.250 ] [ 6.000 , 7.250 ] [ 4.750 , 5.729 ] [ 4.708 , 7.125 ] [ 7.063 , 7.438 ] [ 5.563 , 5.938 ] [ 5.646 , 6.896 ] [ 5.688 , 6.813 ] [ 6.104 , 7.354 ] [ 4.333 , 5.750 ] [ 5.271 , 6.250 ] [ 4.542 , 6.500 ] [ 4.125 , 4.875 ] [ 6.250 , 6.750 ] [ 3.208 , 4.250 ] [ 7.250 , 8.667 ] [ 5.750 , 7.250 ] ]
R V M E = C S 1 C S 2 C S 3 C S 4 C S 5 C S 6 E 1 E 2 E 3 E 4 E 5 E 6 E 7 E 8 [ [ 1.663 , 1.758 ] [ 1.922 , 2.443 ] [ 2.526 , 2.839 ] [ 1.693 , 2.214 ] [ 3.031 , 3.219 ] [ 2.042 , 2.458 ] [ 13.188 , 14.313 ] [ 14.813 , 17.729 ] [ 13.438 , 16.063 ] [ 10.375 , 12.625 ] [ 16.646 , 19.563 ] [ 15.500 , 18.979 ] [ 3375 , 3865 ] [ 3563 , 3938 ] [ 3031 , 3219 ] [ 3792 , 4208 ] [ 4781 , 4969 ] [ 3552 , 4177 ] [ 4.500 , 5.500 ] [ 6.271 , 7.250 ] [ 6.271 , 7.250 ] [ 3.750 , 4.729 ] [ 7.583 , 8.417 ] [ 7.000 , 8.521 ] [ 11181 , 13260 ] [ 11192 , 13025 ] [ 11608 , 15025 ] [ 10358 , 12808 ] [ 16200 , 18550 ] [ 15050 , 17400 ] [ 3.292 , 5.708 ] [ 3.750 , 5.250 ] [ 5.104 , 6.354 ] [ 4.333 , 5.750 ] [ 6.563 , 6.938 ] [ 6.750 , 8.250 ] [ 6.250 , 6.750 ] [ 4.750 , 6.250 ] [ 5.750 , 7.250 ] [ 5.125 , 5.875 ] [ 4.542 , 6.500 ] [ 5.000 , 6.521 ] [ 3.516 , 3.609 ] [ 3.656 , 4.594 ] [ 4.583 , 5.417 ] [ 3.115 , 4.156 ] [ 5.792 , 6.208 ] [ 4.052 , 4.677 ] ]
Step 3. The CV and economic RVMs of the PSSs were normalized using Equation (9). The solution values relative to P10, E5, E6, and E8 were then converted into utility values to obtain the normalized rough value matrices associated with the CV and economic value, NRMp and NRME, as expressed in Equations (23) and (24).
N R M P = C S 1 C S 2 C S 3 C S 4 C S 5 C S 6 P 1 P 2 P 3 P 4 P 5 P 6 P 7 P 8 P 9 P 10 [ [ 0.270 , 0.568 ] [ 0.208 , 0.317 ] [ 0.327 , 0.538 ] [ 0.305 , 0.613 ] [ 0.358 , 0.578 ] [ 0.361 , 0.564 ] [ 0.225 , 0.383 ] [ 0.238 , 0.393 ] [ 0.405 , 0.517 ] [ 0.173 , 0.274 ] [ 0.434 , 0.602 ] [ 0.451 , 0.662 ] [ 0.312 , 0.538 ] [ 0.308 , 0.581 ] [ 0.345 , 0.495 ] [ 0.189 , 0.456 ] [ 0.355 , 0.547 ] [ 0.350 , 0.581 ] [ 0.231 , 0.315 ] [ 0.302 , 0.398 ] [ 0.397 , 0.538 ] [ 0.296 , 0.489 ] [ 0.409 , 0.565 ] [ 0.402 , 0.534 ] [ 0.383 , 0.524 ] [ 0.311 , 0.478 ] [ 0.310 , 0.433 ] [ 0.266 , 0.446 ] [ 0.383 , 0.608 ] [ 0.289 , 0.551 ] [ 0.302 , 0.532 ] [ 0.235 , 0.413 ] [ 0.290 , 0.495 ] [ 0.349 , 0.467 ] [ 0.420 , 0.614 ] [ 0.330 , 0.524 ] [ 0.293 , 0.463 ] [ 0.304 , 0.443 ] [ 0.377 , 0.517 ] [ 0.200 , 0.406 ] [ 0.345 , 0.512 ] [ 0.473 , 0.564 ] [ 0.317 , 0.522 ] [ 0.230 , 0.401 ] [ 0.368 , 0.554 ] [ 0.291 , 0.438 ] [ 0.289 , 0.544 ] [ 0.433 , 0.568 ] [ 0.348 , 0.444 ] [ 0.353 , 0.515 ] [ 0.356 , 0.509 ] [ 0.382 , 0.550 ] [ 0.271 , 0.430 ] [ 0.330 , 0.467 ] [ 0.291 , 0.526 ] [ 0.388 , 0.579 ] [ 0.280 , 0.382 ] [ 0.445 , 0.744 ] [ 0.218 , 0.329 ] [ 0.261 , 0.415 ] ]
N R M E = C S 1 C S 2 C S 3 C S 4 C S 5 C S 6 E 1 E 2 E 3 E 4 E 5 E 6 E 7 E 8 [ [ 0.282 , 0.323 ] [ 0.310 , 0.451 ] [ 0.408 , 0.524 ] [ 0.273 , 0.409 ] [ 0.489 , 0.594 ] [ 0.330 , 0.454 ] [ 0.322 , 0.413 ] [ 0.361 , 0.512 ] [ 0.328 , 0.464 ] [ 0.253 , 0.365 ] [ 0.406 , 0.565 ] [ 0.378 , 0.548 ] [ 0.336 , 0.424 ] [ 0.355 , 0.432 ] [ 0.302 , 0.353 ] [ 0.378 , 0.462 ] [ 0.477 , 0.545 ] [ 0.354 , 0.458 ] [ 0.259 , 0.371 ] [ 0.361 , 0.489 ] [ 0.361 , 0.489 ] [ 0.216 , 0.319 ] [ 0.437 , 0.568 ] [ 0.403 , 0.575 ] [ 0.373 , 0.531 ] [ 0.379 , 0.531 ] [ 0.329 , 0.512 ] [ 0.386 , 0.574 ] [ 0.266 , 0.367 ] [ 0.284 , 0.395 ] [ 0.320 , 0.766 ] [ 0.348 , 0.672 ] [ 0.287 , 0.494 ] [ 0.317 , 0.582 ] [ 0.263 , 0.384 ] [ 0.221 , 0.373 ] [ 0.390 , 0.523 ] [ 0.297 , 0.484 ] [ 0.359 , 0.562 ] [ 0.320 , 0.455 ] [ 0.284 , 0.504 ] [ 0.312 , 0.505 ] [ 0.440 , 0.530 ] [ 0.345 , 0.510 ] [ 0.293 , 0.407 ] [ 0.382 , 0.599 ] [ 0.256 , 0.322 ] [ 0.339 , 0.460 ] ]
Step 4. Based on the normalized rough value matrices (Equations (23) and (24)), Equations (10)–(12) were used to compute the objective weights of the CV and economic criteria, with λ = 0.5. The results are presented in Table 9.

4.2.3. Calculation of Comprehensive Weights of Evaluation Criteria

Equation (13) was used to calculate comprehensive criteria weights (cwj) based on the subjective and objective criteria weights from steps (1) and (2). The obtained results are presented in Table 9. In the design of electric forklifts, the CV criteria that are most important for experts include reliability (P1), digital controlling and smartness (P2), and total cost for PSS (P10). The most important economic criteria are maximum driving speed (E2), maximum lifting height (E3), and maintenance cost (E6).

4.3. Determination of the Optimal Solution Based on the Coalitional Game Model

Step 1. The strategy sets of six conceptual solutions for warehouse logistics systems were obtained, which include (SP(CS1), SE(CS1))–(SP(CS6), SE(CS6)). The interactions between CV and economic objectives are illustrated in Figure 3, and it is shown that the criteria weights of each objective will affect utility. Hence, the criteria weights were considered in utility calculations.
Step 2. The normalized rough values of the warehouse logistics system solutions (Equations (23) and (24)) were converted into crisp values. Equations (14) and (15) were then adopted to calculate the utilities of the CV and economic objectives in each strategy set. The calculated utilities of the electric forklift solutions are presented in Table 10.
Step 3. Based on Table 11, a min-max representation model (Equation (16)) was used to define the characteristic function for each possible coalition. This gave v({P}) = 0.901 and v({E}) = 0.959. The coalitional utility associated with the players cooperating with each other was calculated using a pessimistic criterion, i.e., v P ,   E = min c = 1 2 U c . This gave a coalitional utility of v({P,E}) = 1.9. Concurrently, the Shapley value method (Equation (17)) was used to allocate the utility of each game player—that is, the optimal design expectation for CV and economy objective, thereby obtaining φ(v) = (φP(v), φE(v)) = (0.923, 0.982).
Step 4. The deviation function (Equation (17)) was used to determine the conceptual solution closest to the Shapley value, and satisfied expectations relative to CV and economic utilities while maximizing overall utility. The deviations of the solutions from φ(v) were: D(CS1) = 0.031, D(CS2) = 0.065, D(CS3) = 0.104, D(CS4) = 0.033, D(CS5) = 0.154, and D(CS6) = 0.186. Therefore, the ranking of the electric forklift solutions was CS1 > CS4 > CS2 > CS3 > CS5 > CS6, and CS1 is the optimal solution. The CV and economic utilities of CS1 were (UP, UE) = (0.946, 1.004), as presented in Figure 4.
The results in Figure 4 indicate that the CV and economic utilities of each strategy are related to each other by mutualistic and antagonistic relationships. Therefore, it is impossible to optimize the overall utility of a solution by solely focusing on CV or economic objectives, as it is important balance the interests of both players. By adopting the Shapley value to obtain the ratio of importance between CV and economic objectives in the design of a warehouse logistics system, it becomes possible to ensure that the utility of the grand coalition is always greater than that of any single coalition (i.e., φP(v) > v({P}) and φE(v) > v({E})). This also circumvents the limitation of decreasing system performance by excessively considering economic objectives. The optimal solution, CS1, can provide the required level of system performance (φP(v) = 0.946) without significantly compromising the economic value (φE(v) = 0.982). Although CS2 is better in terms of economic value (φE(v) = 1.043), it will decrease CV (φP(v) = 0.901), and therefore fail to satisfy the customers’ design expectations.

4.4. Sensitivity and Comparison Analysis

To better verify the reliability of the proposed decision model, this section will perform the sensitivity analysis of game utility and compare with the rough TOPSIS.

4.4.1. Sensitivity Analysis

When calculating utility, it is important to convert the normalized rough values into crisp values. This conversion requires the introduction of a risk propensity indicator, α. If the DMs exhibit a more optimistic attitude to the results, a larger α value (α > 0.5) should be selected; if the DMs exhibit a more pessimistic attitude to the result, a smaller α (α < 0.5) value should be selected; if the DMs maintain a practical and moderate attitude, o.5 should be selected as the α value. The CV and economic utilities associated with seven values of α were calculated, as presented in Figure 5. The utilities increase with increasing α and the changes in CV and economic utilities with α are substantially similar. Neither of these trends exhibits any significant fluctuation. Based on these behaviors, it can be deduced that the comprehensive criteria weights obtained by combining rough BWM and EWM values can eliminate uncertainties due to design preferences while ensuring stability in the calculation of CV and economic utilities.
The ranking of warehouse logistic system solutions for each α value is presented in Table 11. By comparing the sensitivity results, when DMs exhibit a strong negative attitude to risk propensity (α= 0, 0.1, 0.3), CS4 is the optimal solution. In this case, the DMs can tolerate higher costs to improve PS (i.e., UP > φP(v), UE < φE(v)) and minimize risk-induced design uncertainties in the decision-making process. When DMs exhibit a positive risk profile or weaker negative attitude (α = 0.5, 0.7, 0.9, 1), CS1 has a maximum priority. Because the DMs have adopted an optimistic view toward the solution values, they will believe that it is possible to ensure adequate service quality while prioritizing economic value (UP > φP(v), UE < φE(v)). Therefore, the proposed decision-making framework can be flexibly used by enterprises or researchers, which enables the framework to adapt to different market conditions and guarantees that the selected warehouse logistics system solution will always maximize the overall design value.

4.4.2. Comparison with Rough-TOPSIS Method

It is widely known that TOPSIS is a classical multi-objective ranking method [49,54], which can be used to obtain the optimal scheme closest to the ideal solution. However, before determining the ideal utility reference, the weights of the CV and the economy objectives need to be set, followed by the analysis of the decision results. To this end, PE and PT are given five weight value groups: (WP, WE) ∈ {(0.1, 0.9), (0.3, 0.7), (0.5, 0.5), (0.7, 0.3), (0.9, 0.1)}. By weighting the game utility in Table 10, the positive utility reference (WUc*) and negative-ideal utility reference (WUc0) for the CV and economic objectives can be determined, respectively, as shown in Table 12.
After that, based on different weight distributions of CV and economic objectives, the distance between each positive ideal (disi*) and negative ideal reference (disi0) is determined based on Equations (25) and (26).
d i s i * = c = 1 2 ( W c U i c W U c * ) 2 ,   c P ,   E
d i s i 0 = c = 1 2 ( W c U i c W U c 0 ) 2 ,   c P ,   E
where disi0 is the distance between Uc and the negative ideal solution WU0 in CSi; disj* is the distance between Uc(Schi) and the positive ideal solution WU* in CSi; Ujc = (UP(SP(CS1), SE(CS1)), UE(SP(CS1), SE(CS1))).
Finally, based on Equation (27), the scheme with the minimum distance between the game utility and the positive ideal solution is obtained, which is the comprehensive optimal scheme.
C i * = d i s i 0 / d i s i 0 + d i s i * ,   i 1 , 2 , , K
where Cj* represents the relative closeness index between the scheme i and positive ideal reference, and the greater the Cj* value, the better the comprehensive value of the scheme.
Under different weighting groups, the relative closeness values of each scheme can be calculated by Equations (25)–(27) and the optimal decision option can be analyzed. Then, the decision results obtained by the two methods are given in Table 13.
To explore the influence law of game utility under each weight combination for the CV and economic objectives, game utility is analyzed based on the comparison of decision results in Table 13, as illustrated in Figure 6. It is demonstrated that if the weight of the CV objectives is equal to or smaller than 0.5 (wp = 0.1, 0.3, 0.5), the optimal solution will be CS5, which prioritizes CV. If the weight of the CV objectives is greater than 0.5 (wp = 0.7, 0.9), the optimal solution will be CS6, which prioritizes design expectations associated with economic objectives. If the rough TOPSIS-2 decision analysis method is adopted, the ideal utility references for (wP, wE) = (0.3, 0.7) are (WUP*, WUE*) = (0.333, 0.730) and (WUP0, WUE0) = (0.270, 0.671), respectively. The solution closest to the ideal utility reference is CS5, and its distribution of utilities is (UP, UE) = (1.070, 1.029). If the combination of weights is altered, the ideal utility reference (Table 13) will also change, thereby causing the optimal decision to change. Upon further analysis, it was determined that TOPSIS focuses on the distance between a solution and the ideal reference, rather than balancing conflicts in interest. Therefore, the quality of the final decision depends on the weighting of the objectives. In the rough TOPSIS-3 and TOPSIS-4 results, the two best solutions are very similar to each other, as they have relative closeness values of 0.813/0.759 and 0.811/0.880, respectively. This will make it difficult for the designer to differentiate the priority of the solutions, which will trigger fluctuations in the decision-making process. Based on the analysis above, it can be deduced that the antagonism between CV and economic utilities makes it difficult to accurately determine their relative importance, especially if one tries to maximize one type of utility or the other without considering its effects on the overall design. Consequently, the proposed decision analysis model adopts Shapley values to balance the interests of both players in this cooperative game, to select an optimal solution that satisfies both players.
Hence, TOPSIS can transform a multi-objective decision problem into a single-objective evaluation using relative closeness index and obtain the distance-optimal solution. However, this method cannot consider the interaction between CV and economic objectives in the design process, especially, when there is a conflicting relationship between the two objectives. Then, the influence of their own interests on the overall design expectation needs to be fully considered in order to avoid unstable decision results. This study constructs a comprehensive weight model integrating entropy weight and BWM method, which can ensure the objectivity of the program value acquisition process. Simultaneously, Shapley is used to fairly weigh the contribution of CV and economic objectives to obtain a fair objective benefit ratio. Furthermore, the proposed decision method focuses only on objectives’ game utilities derived from the initial scheme value data without other auxiliary mathematical models, which can reduce the objectivity of the decision results for design concept under uncertainty.

5. Conclusions and Future Work

This study proposed a design concept decision approach based on rough sets and the Shapley value for PSS, which can determine the optimal solution to satisfy users and the needs of enterprises by weighing the conflicting interests between the CV and economic objectives. First, EWM and BWM were used to obtain the comprehensive weights of the evaluation criteria for both sets of objectives. The rough set technique was then applied to these weights to objectively acquire the initial value of each solution. Second, a multi-objective utility function was constructed based on the solution values, and the Shapley value was used to obtain the optimal allocation of utilities to the CV and economic objectives of the product. The solution closest to this ratio is thus the optimal PSS solution. Finally, a case study of electric forklift PSS concept design is adopted to demonstrate the effectiveness of the proposed method.
Compared with other decision models for PSS design, the objectives of this research are shown in three parts: (1) constructing customer value and economic objectives as important factors for enterprises and users, assisting designers to develop the comprehensive optimal PSS with a higher applicability in industrial enterprises; (2) performing the combination of the Shapley value method and the comprehensive weighting model to quantify explains the interaction between CV and economic objectives on each other from raw evaluation data during the early design phase; and (3) using coalition game theory to weigh the marginal utility of each game player in the overall design expectation, so as to form a stable and fair design expectation distribution in the game process of multi-objective conflict of interest, which can reduce the risk of subsequent design.
The comprehensive weighting method developed in this study is an effective way to holistically aggregate personal preferences and subjective weights. Unlike other subjective weighting methods (such as AHP), the rough BWM only needs to make 2j-3 pairwise comparisons, and then the structured comparison method simplifies the data and calculation process, and makes the results more reliable. Considering the subjective judgment of decision makers on the value proposition of PSS design, the rough set technique is used to quantify subjective judgments without requiring auxiliary parameters and to obtain PSS design value information in the form of interval values. Specifically, compared with other decision models such as TOPSIS, the main purpose of our proposed game decision model is to measure the “equilibrium solution” between customer value and the economic cost to the enterprises of satisfying customer service needs, in a way that supports the evaluation and ranking of PSS concepts through numerical models at early design stage. In addition, the game process does not require complex mathematical formulas, which can avoid the introduction of unnecessary subjective parameters and the change in decision results (Figure 6).
Despite its advantages, the decision approach for product PSS design still has the following limitations. (1) Because the accuracy of the utility calculations depends on the reliability of the solution value data, it is difficult to adapt this approach to novel products without well-defined design attributes or performance data. (2) Because the calculation of Shapley values will become increasingly complex as the number of players in the game increases, the proposed decision analysis model is only suitable for decision problems that have a small number of players. Future research will develop a more comprehensive evaluation model that incorporates more uncertainties and validation techniques into the decision framework. For instance, (1) the trust and risk attitudes of the DMs could be combined to reduce the impact of evaluation data from low-trust DMs on the decision-making process, as well as to create a metric that can be adopted to ascertain the consistency of the evaluation data. (2) The virtualization software or 3D printing could be used to validate product design solutions, thus increasing the availability of data for assessing the feasibility of PSS conceptual solutions during the early design phase.

Author Contributions

Conceptualization, L.J. and D.F.; Writing—original draft, D.F.; Investigation, X.F.; Writing—review and editing, L.J.; Funding acquisition, S.J. and X.F. All authors have read and agreed to the published version of the manuscript.

Funding

This research was funded by the National Natural Science Foundation of China [under grant numbers 52105282 and U1610112], the Project funded by China Postdoctoral Science Foundation [2021M702893], and the Zhejiang Provincial Natural Science Foundation of China [under grant number LY20E050020].

Acknowledgments

The authors acknowledge the anonymous Editor and reviewers for valuable comments and suggestions.

Conflicts of Interest

The authors declare no conflict of interest.

Appendix A

Table A1. Service module of the electric storage and handling system of electric forklift PSS.
Table A1. Service module of the electric storage and handling system of electric forklift PSS.
ItemsService ModuleSub-ItemsService Components
SM1Guidance and trainingSC1.1Performance parameter library
SC1.2Equipment selection specification
SC1.3Operation specification
SC1.4System price composition
SC1.5Instructor
SC1.6Training processes and specifications
SC1.7Remote communication platform
SC1.8Customer experience platform
SC1.9Typical problem processing database
SM2Spare parts supplySC2.1Spare parts sales platform
SC2.2Spare parts performance database
SC2.3Supply of spare parts information base
SM3Routine maintenanceSC3.1Maintenance knowledge database
SC3.2Maintenance record information database
SC3.3Maintenance price composition
SC3.4Maintenance tools
SC3.5Maintenance staff
SC3.6Maintenance flow and specifications
SM4TroubleshootingSC4.1Equipment troubleshooting device
SC4.2Equipment troubleshooting platform
SC4.3Fault information knowledge base
SC4.4Troubleshooting staff
SC4.5Troubleshooting tools
SM5Delivery distributionSC5.1System sales platform
SC5.2Logistics and distribution system
SC5.3Financial payment system
SM6Field serviceSC6.1Field service appointment platform
SC6.2Field service price composition
SC6.3Field service knowledge base
SC6.4Field service staff
SC6.5Field service flow and specifications
SC6.6Service tools
SM7Factory serviceSC7.1Factory service appointment platform
SC7.2Factory service knowledge base
SC7.3Factory service staff
SC7.4Factory service equipment
SC7.5Factory service progress information exchange platform
SM8Scrap recyclingSC8.1Recycling knowledge database
SC8.2Recycling price composition
SC8.3Recycling tools
SC8.4Recycling staff
SC8.5Recycling process and specifications
Table A2. Initial evaluation matrix of the electric forklift PSS concept (taking the CS2 as an example).
Table A2. Initial evaluation matrix of the electric forklift PSS concept (taking the CS2 as an example).
(a) Scheme Value Assessment of Evaluation Criteria on the PSS Design
Evaluation CriteriaEvaluation Value Assigned by Four DMs
DM1DM2DM3DM4
P1 4 3 3 4
P2 6 4 4 3
P3 7 8 4 4
P4 5 5 4 3
P5 6 4 4 5
P6 4 6 3 5
P7 4 6 4 6
P8 5 4 6 3
P9 5 6 6 8
P10 4 4 4 6
(b) Scheme Value Assessment of Evaluation Criteria on the Economy
Evaluation CriteriaEvaluation Value Assigned by Four DMs
DM1DM2DM3DM4
E1 (t)2.252.751.52.25
E2 (km/h)16201613
E3 (mm)3000400040004000
E4 (kw)6864
E5 (yuan)14,40012,00012,00014,400
E6 6 6 7 5
E7 4 6 7 5
E8 (t) 4.5 5 3 4
Table A3. Initial evaluation matrix of the electric forklift PSS concept (taking the CS3 as an example).
Table A3. Initial evaluation matrix of the electric forklift PSS concept (taking the CS3 as an example).
(a) Scheme Value Assessment of Evaluation Criteria on the PSS Design
Evaluation CriteriaEvaluation Value Assigned by Four DMs
DM1DM2DM3DM4
P1 7 4 6 6
P2 7 6 6 6
P3 6 5 6 5
P4 6 5 6 7
P5 5 4 4 5
P6 7 6 3 6
P7 7 6 5 6
P8 7 8 6 5
P9 7 7 4 7
P10 7 6 6 7
(b) Scheme Value Assessment of Evaluation Criteria on the Economy
Evaluation CriteriaEvaluation Value Assigned by Four DMs
DM1DM2DM3DM4
E1 (t)2.752.7532.25
E2 (km/h)13132013
E3 (mm)3000350030003000
E4 (kw)6786
E5 (yuan)16,80010,00014,40012,000
E6 6 7 6 4
E7 7 8 5 6
E8 (t) 5 5 6 4
Table A4. Initial evaluation matrix of the electric forklift PSS concept (taking the CS4 as an example).
Table A4. Initial evaluation matrix of the electric forklift PSS concept (taking the CS4 as an example).
(a) Scheme Value Assessment of Evaluation Criteria on the PSS Design
Evaluation CriteriaEvaluation Value Assigned by Four DMs
DM1DM2DM3DM4
P1 5 8 8 3
P2 4 3 3 2
P3 7 4 3 2
P4 5 7 3 5
P5 6 3 4 4
P6 5 6 6 6
P7 6 2 3 5
P8 5 4 6 6
P9 5 7 8 7
P10 5 3 3 4
(b) Scheme Value Assessment of Evaluation Criteria on the Economy
Evaluation CriteriaEvaluation Value Assigned by Four DMs
DM1DM2DM3DM4
E1 (t)1.751.51.752.75
E2 (km/h)16101010
E3 (mm)4000400045003500
E4 (kw)4444
E5 (yuan)12,00014,40010,0009600
E6 5 4 4 3
E7 5 5 5 7
E8 (t) 3.5 2.5 3.5 5
Table A5. Initial evaluation matrix of the electric forklift PSS concept (taking the CS5 as an example).
Table A5. Initial evaluation matrix of the electric forklift PSS concept (taking the CS5 as an example).
(a) Scheme Value Assessment of Evaluation Criteria on the PSS Design
Evaluation CriteriaEvaluation Value Assigned by Four DMs
DM1DM2DM3DM4
P1 8 6 5 6
P2 8 8 6 6
P3 6 7 6 4
P4 7 5 7 6
P5 7 6 4 7
P6 8 8 5 8
P7 7 4 6 6
P8 8 3 6 7
P9 7 4 4 5
P10 8 9 6 9
(b) Scheme Value Assessment of Evaluation Criteria on the Economy
Evaluation CriteriaEvaluation Value Assigned by Four DMs
DM1DM2DM3DM4
E1 (t)33.533
E2 (km/h)13202020
E3 (mm)4500500050005000
E4 (kw)7988
E5 (yuan)16,80019,20014,40019,200
E6 7 7 7 6
E7 8 4 6 6
E8 (t) 5.5 6.5 6 6
Table A6. Initial evaluation matrix of the electric forklift PSS concept (taking the CS5 as an example).
Table A6. Initial evaluation matrix of the electric forklift PSS concept (taking the CS5 as an example).
(a) Scheme Value Assessment of Evaluation Criteria on the PSS Design
Evaluation CriteriaEvaluation Value Assigned by Four DMs
DM1DM2DM3DM4
P1 7 7 6 5
P2 7 9 8 6
P3 5 5 8 6
P4 6 6 8 5
P5 7 3 6 4
P6 7 4 6 7
P7 7 7 7 7
P8 7 7 7 8
P9 7 5 5 6
P10 7 6 8 5
(b) Scheme Value Assessment of Evaluation Criteria on the Economy
Evaluation CriteriaEvaluation Value Assigned by Four DMs
DM1DM2DM3DM4
E1 (t)2.252.251.752.75
E2 (km/h)13201616
E3 (mm)4000400045003000
E4 (kw)6997
E5 (yuan)14,40014,40019,20016,800
E66385
E77577
E8 (t)4.54.53.55

References

  1. Martin, M.; Heiska, M.; Björklund, A. Environmental assessment of a product-service system for renting electric-powered tools. J. Clean. Prod. 2021, 281, 125245. [Google Scholar] [CrossRef]
  2. Haber, N.; Fargnoli, M. Design for product-service systems: A procedure to enhance functional integration of product-service offerings. Int. J. Prod. Dev. 2017, 22, 135–164. [Google Scholar] [CrossRef]
  3. Bertoni, M.; Rondini, A.; Pezzotta, G. A systematic review of value metrics for PSS design. Procedia CIRP 2017, 64, 289–294. [Google Scholar] [CrossRef]
  4. Fargnoli, M.; Costantino, F.; Di Gravio, G.; Tronci, M. Product service-systems implementation: A customized framework to enhance sustainability and customer satisfaction. J. Clean. Prod. 2018, 188, 387–401. [Google Scholar] [CrossRef]
  5. Kimita, K.; Sakao, T.; Shimomura, Y. A failure analysis method for designing highly reliable product-service systems. Res. Eng. Des. 2018, 29, 143–160. [Google Scholar] [CrossRef]
  6. Sundin, E.; Lindahl, M.; Ijomah, W. Product design for product/service systems: Design experiences from Swedish industry. J. Manuf. Technol. Mana. 2009, 20, 723–753. [Google Scholar] [CrossRef]
  7. Song, W.; Sakao, T. A customization-oriented framework for design of sustainable product/service system. J. Clean. Prod. 2017, 140, 1672–1685. [Google Scholar] [CrossRef] [Green Version]
  8. Saaty, T.L. Decision Making with Dependence and Feedback: The Analytic Network Process; RWS Publications: Pittsburgh, PA, USA, 1996; Volume 4922, No. 2. [Google Scholar]
  9. Cao, G.; Sun, Y.; Tan, R.; Zhang, J.; Liu, W. A function-oriented biologically analogical approach for constructing the design concept of smart product in Industry 4.0. Adv. Eng. Inform. 2021, 49, 101352. [Google Scholar] [CrossRef]
  10. Fang, H.; Li, J.; Song, W. A New Method for Quality Function Deployment Based on Rough Cloud Model Theory. IEEE Trans. Eng. Manag. 2020, 58, 5751–5768. [Google Scholar] [CrossRef]
  11. Jing, L.; Jiang, S.; Li, J.; Peng, X.; Ma, J. A cooperative game theory based user-centered medical device design decision approach under uncertainty. Adv. Eng. Inform. 2021, 47, 101204. [Google Scholar] [CrossRef]
  12. Song, W.; Niu, Z.; Zheng, P. Design concept evaluation of smart product-service systems considering sustainability: An integrated method. Comput. Ind. Eng. 2021, 159, 107485. [Google Scholar] [CrossRef]
  13. Pamučar, D.; Gigović, L.; Bajić, Z.; Janošević, M. Location selection for wind farms using GIS multi-criteria hybrid model: An approach based on fuzzy and rough numbers. Sustainability 2017, 9, 1315. [Google Scholar] [CrossRef] [Green Version]
  14. Zhu, G.N.; Hu, J.; Ren, H. A fuzzy rough number-based AHP-TOPSIS for design concept evaluation under uncertain environments. Appl. Soft Comput. 2020, 91, 106228. [Google Scholar] [CrossRef]
  15. Vasantha, G.V.A.; Roy, R.; Lelah, A.; Brissaud, D. A review of product–service systems design methodologies. J. Eng. Des. 2012, 23, 635–659. [Google Scholar] [CrossRef]
  16. Bertoni, M. Multi-criteria decision making for sustainability and value assessment in early PSS design. Sustainability 2019, 11, 1952. [Google Scholar] [CrossRef] [Green Version]
  17. Liu, C.; Jia, G.; Kong, J. Requirement-oriented engineering characteristic identification for a sustainable product–service system: A multi-method approach. Sustainability 2020, 12, 8880. [Google Scholar] [CrossRef]
  18. Hwang, C.L.; Yoon, K. Multiple Attribute Decision Making: Methods and Applications; Springer: New York, NY, USA, 1981. [Google Scholar]
  19. Opricovic, S. Multicriteria optimization of civil engineering systems. Fac. Civ. Eng. Belgrade 1998, 2, 5–21. [Google Scholar]
  20. Tiwari, V.; Jain, P.K.; Tandon, P. Product design concept evaluation using rough sets and VIKOR method. Adv. Eng. Inform. 2016, 30, 16–25. [Google Scholar] [CrossRef]
  21. Kilic, H.S.; Zaim, S.; Delen, D. Selecting “The Best” ERP system for SMEs using a combination of ANP and PROMETHEE methods. Expert Syst. Appl. 2015, 42, 2343–2352. [Google Scholar] [CrossRef]
  22. Wang, X.; Durugbo, C. Analysing network uncertainty for industrial product-service delivery: A hybrid fuzzy approach. Expert Syst. Appl. 2013, 40, 4621–4636. [Google Scholar] [CrossRef]
  23. Qi, J.; Hu, J.; Peng, Y. Modified rough VIKOR based design concept evaluation method compatible with objective design and subjective preference factors. Appl. Soft Comput. 2021, 107, 107414. [Google Scholar] [CrossRef]
  24. Vincent, T.L. Game theory as a design tool. J. Mech. Des. 1983, 105, 165–170. [Google Scholar] [CrossRef]
  25. Huo, Y.L.; Hu, X.B.; Chen, B.Y.; Fan, R.G. A Product Conceptual Design Method Based on Evolutionary Game. Machines 2019, 7, 18. [Google Scholar] [CrossRef] [Green Version]
  26. Qu, M.; Yu, S.; Chen, D.; Chu, J.; Tian, B. State-of-the-art of design, evaluation, and operation methodologies in product service systems. Comput. Ind. 2016, 77, 1–14. [Google Scholar] [CrossRef]
  27. Geng, X.; Chu, X. A new importance–performance analysis approach for customer satisfaction evaluation supporting PSS design. Expert Syst. Appl. 2012, 39, 1492–1502. [Google Scholar] [CrossRef]
  28. Lee, S.; Geum, Y.; Lee, S.; Park, Y. Evaluating new concepts of PSS based on the customer value: Application of ANP and niche theory. Expert Syst. Appl. 2015, 42, 4556–4566. [Google Scholar] [CrossRef]
  29. Chen, T.L.; Chen, C.C.; Chuang, Y.C.; Liou, J.J. A Hybrid MADM Model for Product Design Evaluation and Improvement. Sustainability 2020, 12, 6743. [Google Scholar] [CrossRef]
  30. Rezaei, J. Best-worst multi-criteria decision-making method. Omega 2015, 53, 49–57. [Google Scholar] [CrossRef]
  31. Guo, S.; Zhao, H. Fuzzy best-worst multi-criteria decision-making method and its applications. Knowl.-Based Syst. 2017, 121, 23–31. [Google Scholar] [CrossRef]
  32. Chen, D.; Chu, X.; Sun, X.; Li, Y. A new product service system concept evaluation approach based on Information Axiom in a fuzzy-stochastic environment. Int. J. Comput. Integr. Manuf. 2015, 28, 1123–1141. [Google Scholar] [CrossRef]
  33. Liu, Z.; Ming, X.; Song, W. A framework integrating interval-valued hesitant fuzzy DEMATEL method to capture and evaluate co-creative value propositions for smart PSS. J. Clean. Prod. 2019, 215, 611–625. [Google Scholar] [CrossRef]
  34. Ma, H.; Chu, X.; Xue, D.; Chen, D. A systematic decision making approach for product conceptual design based on fuzzy morphological matrix. Expert Syst. Appl. 2017, 81, 444–456. [Google Scholar] [CrossRef]
  35. Zhu, G.N.; Hu, J. A rough-Z-number-based DEMATEL to evaluate the co-creative sustainable value propositions for smart product-service systems. Int. J. Intell. Syst. 2021, 36, 3645–3679. [Google Scholar] [CrossRef]
  36. Fargnoli, M.; Haber, N. A practical ANP-QFD methodology for dealing with requirements’ inner dependency in PSS development. Comput. Ind. Eng. 2019, 127, 536–548. [Google Scholar] [CrossRef]
  37. Beitz, W.; Pahl, G.; Grote, K. Engineering Design: A Systematic Approach; Springer: London, UK, 1996; Volume 21, p. 71. [Google Scholar]
  38. Jing, L.; Yao, J.; Gao, F.; Li, J.; Peng, X.; Jiang, S. A rough set-based interval-valued intuitionistic fuzzy conceptual design decision approach with considering diverse customer preference distribution. Adv. Eng. Inform. 2021, 48, 101284. [Google Scholar] [CrossRef]
  39. Jiang, S.; Feng, D.; Lu, C.; Li, J.; Chai, H. Research on the construction of the spiral evolutionary design methodology for a product service system based on existing products. Proc. Inst. Mech. Eng. Part B J. Eng. Manuf. 2020, 234, 825–839. [Google Scholar] [CrossRef]
  40. Liu, Z.; Ming, X.; Song, W.; Qiu, S.; Qu, Y. A perspective on value co-creation-oriented framework for smart product-service system. Procedia Cirp 2018, 73, 155–160. [Google Scholar] [CrossRef]
  41. Parasuraman, A.; Zeithaml, V.A.; Berry, L.L. A conceptual model of service quality and its implications for future research. J. Mark. 1985, 49, 41–50. [Google Scholar] [CrossRef]
  42. Woodruff, R.B. Customer value: The next source for competitive advantage. J. Acad. Market. Sci. 1997, 25, 139–153. [Google Scholar] [CrossRef]
  43. Akhmedova, A.; Mas-Machuca, M.; Marimon, F. Value co-creation in the sharing economy: The role of quality of service provided by peer. J. Clean. Prod. 2020, 266, 121736. [Google Scholar] [CrossRef]
  44. Jiang, S.; Jing, L.; Peng, X.; Chai, H.; Li, J. Conceptual design conceptual scheme optimization based on integrated design objectives. Concurr. Eng. 2018, 26, 231–250. [Google Scholar] [CrossRef]
  45. Tian, Z.; Wang, J.; Zhang, H. An integrated approach for failure mode and effects analysis based on fuzzy best-worst, relative entropy, and VIKOR methods. Appl. Soft Comput. 2018, 72, 636–646. [Google Scholar] [CrossRef]
  46. Xu, Z.S.; Sun, Z.D. Priority method for a kind of multi-attribute decision-making problems. J. Manag. Sci. China 2002, 5, 35–39. [Google Scholar]
  47. Stević, Ž.; Pamučar, D.; Kazimieras Zavadskas, E.; Ćirović, G.; Prentkovskis, O. The selection of wagons for the internal transport of a logistics company: A novel approach based on rough BWM and rough SAW methods. Symmetry 2017, 9, 264. [Google Scholar] [CrossRef] [Green Version]
  48. Shannon, C.E. A mathematical theory of communication. Bell Syst. Tech. J. 1948, 27, 379–423. [Google Scholar] [CrossRef] [Green Version]
  49. Jing, L.; Zhan, Y.; Li, Q.; Peng, X.; Li, J.; Gao, F.; Jiang, S. An integrated product conceptual scheme decision approach based on Shapley value method and fuzzy logic for economic-technical objectives trade-off under uncertainty. Comput. Ind. Eng. 2021, 156, 107281. [Google Scholar] [CrossRef]
  50. Chen, N.; Xu, Z.; Xia, M. The ELECTRE I multi-criteria decision-making method based on hesitant fuzzy sets. Int. J. Inf. Tech. Decis. 2015, 14, 621–657. [Google Scholar] [CrossRef]
  51. You, Z.; Wang, L.; Han, Y.; Zare, F. System design and energy management for a fuel cell/battery hybrid forklift. Energies 2018, 11, 3440. [Google Scholar] [CrossRef] [Green Version]
  52. Jiang, Z.; Xiao, B. Electric Power Steering System Control Strategy Based on Robust H Control for Electric Forklift. Math. Probl. Eng. 2018, 2018, 7614304. [Google Scholar] [CrossRef]
  53. Li, J.; Fang, H.; Song, W. Sustainability evaluation via variable precision rough set approach: A photovoltaic module supplier case study. J. Clean. Prod. 2018, 192, 751–765. [Google Scholar] [CrossRef]
  54. Ma, J.F.; Harstvedt, J.D.; Jaradat, R.; Smith, B. Sustainability driven multi-criteria project portfolio selection under uncertain decision-making environment. Comput. Ind. Eng. 2020, 140, 106236. [Google Scholar] [CrossRef]
Figure 1. Framework of the proposed decision model.
Figure 1. Framework of the proposed decision model.
Applsci 11 11001 g001
Figure 2. Schematic diagram of the electric forklift PSS concept.
Figure 2. Schematic diagram of the electric forklift PSS concept.
Applsci 11 11001 g002
Figure 3. Impact relationship between evaluation objectives.
Figure 3. Impact relationship between evaluation objectives.
Applsci 11 11001 g003
Figure 4. Game utility of CV and economic objective under different solutions and Shapley value.
Figure 4. Game utility of CV and economic objective under different solutions and Shapley value.
Applsci 11 11001 g004
Figure 5. Sensitivity analysis of scheme decision process based on α value.
Figure 5. Sensitivity analysis of scheme decision process based on α value.
Applsci 11 11001 g005
Figure 6. Comparison of game utility results of two decision methods.
Figure 6. Comparison of game utility results of two decision methods.
Applsci 11 11001 g006
Table 1. Comparison with related literature involving PSS design decisions.
Table 1. Comparison with related literature involving PSS design decisions.
AuthorEvaluation-Related FactorsCase Study
Objective WeightsSubjective WeightsInteractivityUncertainty
Kimita et al. [5] Cleaning machine
Song et al. [12] Washing machine
Bertoni. [16] Electrical load carrier
Wang and Durugbo. [22] Stainless steel manufacturer
Huo et al. [25] Fixed winch hoist
Geng and Chu. [27] Metering pumps
Lee et al. [28] Car’s rental service
Chen et al. [32] Crane machine
Liu et al. [33] Fridge-service system
Fargnoli and Haber. [36] Medical imaging equipment
Proposed methodElectric forklift
Table 2. Morphology matrix of sub-functions.
Table 2. Morphology matrix of sub-functions.
Sub-FunctionPrinciple Solution (PS)
1 μ t
SF1PS11 PS1μ PS1t
SFαPSα1 PSαμ PSαt
SFFPSF1 PS PSFt
Table 3. Description of the PSS evaluation criteria for CV (Modified from Song et al. [12]).
Table 3. Description of the PSS evaluation criteria for CV (Modified from Song et al. [12]).
CVDescriptionEvaluation Criteria
LabelCriterionCategory
Reliable ValueSecurity, service efficiency, the ability to proactively provide services, and the prevention and correction of errors.P1Product system reliabilityBenefit
P2Digital controlling and smartnessBenefit
Environmental ValueThe effects on the environment (including product scrap, recycling, environmental grade, etc.)P3Beneficial effects on the environmentBenefit
P4Product operating conditionsBenefit
Flexible ValueCustom design, customer participation and feedbackP5Interactive customizationBenefit
P6Plan communication and modificationBenefit
Social ValuePositive social image (including product quality, user experience and personnel performance, etc.)P7Community feelingBenefit
P8Convenience and safetyBenefit
Economic ValueCost and resource utilization of product system design (including maintenance, hardware restoration, delivery, etc.)P9Ability to improve the product durabilityBenefit
P10Total cost for PSSCost
Table 4. Game utility matrix of scheme under each strategy combination.
Table 4. Game utility matrix of scheme under each strategy combination.
Game UtilityConceptual Scheme
CS1CS2...CSi
UP(SP, SE)UP(SP(CS1), SE(CS1))UP(SP(CS2), SE(CS2))...UP(SP(CSi), SE(CSi))
UE(SP, SE)UE(SP(CS1), SE(CS1))UE(SP(CS2), SE(CS2))...UE(SP(CSi), SE(CSi))
Table 5. Morphology matrix of electric forklifts.
Table 5. Morphology matrix of electric forklifts.
Sub-FunctionPrinciple Solution
1234
ACarrying the goodsSecondary gantrySecondary fully free gantryThree-stage fully free gantry
BDriving wheelMechanical driveFluid driveHydraulic drive
CConvert electricityAC MOTORDC MOTOR
DHoisting heightChain wheelBelt wheelHydraulicGear
EBrake modeManual hydraulicElectro hydraulic
FSteering modeMechanical manual steeringManual hydraulic steeringElectro hydraulic steering
GOperating handleVertical handleSide handling handle
Table 6. Description of evaluation criteria in the economic objective of warehouse logistics system.
Table 6. Description of evaluation criteria in the economic objective of warehouse logistics system.
LabelCriterionDescriptionCategory
E1Rated lifting capacityThe maximum mass allowed for forklift loads when the center of gravity is within the standard load center distance of the forklift truckBenefit
E2Maximum driving speedThe maximum steady speed of the forklift truck when the fork carries the rated load at maximum speedBenefit
E3Maximum lifting heightThe height that the forklift can lift when it is on level ground and the fork carries the rated lifting weightBenefit
E4Motor powerThe maximum power that the motor can run normally when the forklift is on the level ground and running stably after startingBenefit
E5Production costThe total cost of the forklift after design, processing and assembly, including materials, supplies, research and development, etcCost
E6Maintenance costsThe expenses for regular inspection, maintenance and replacement of vulnerable parts of the forkliftCost
E7SafetyThe reliability of forklift design and the ability to protect the driver and cargo during operation and operationBenefit
E8Forklift weightThe total weight of all parts of a forklift truck when it is not loadedCost
Table 7. The results of R N ¯ (hBj), R N ¯ (hjW) and weight wj of the criteria in CV and economic objective.
Table 7. The results of R N ¯ (hBj), R N ¯ (hjW) and weight wj of the criteria in CV and economic objective.
(a) The Subjective Weights of Criteria in the CV Objective
Criteria R N ¯ ( h P Bj ) R N ¯ ( h P jW ) RN(wPj)wPj
P1[1,1][9,9][0.289,0.289]0.266
P2[2.271,3.250][5.104,6.354][0.100,0.100]0.092
P3[2.708,4.375][6.271,7.250][0.123,0.146]0.124
P4[6.271,7.250][3.333,4.750][0.060,0.060]0.055
P5[9,9][1,1][0.025,0.025]0.023
P6[3.625,5.292][4.479,6.000][0.091,0.100]0.088
P7[4.229,6.313][3.646,4.896][0.063,0.073]0.062
P8[2.813,4.771][4.229,6.188][0.096,0.122]0.100
P9[1.875,3.000][4.333,5.750][0.085,0.171]0.118
P10[4.000,5.521][3.479,5.000][0.066,0.093]0.073
(b) The Subjective Weights of Criteria in the Economic Objective
CriteriaRN(hEBj)RN(hEjW)RN(wEj)wEj
E1[1.333,2.500][6.750,8.250][0.056,0.061]0.059
E2[2.625,4.292][4.458,6.750][0.186,0.186]0.188
E3[1.250,1.750][6.583,7.417][0.225,0.225]0.228
E4[2.750,4.250][3.958,6.042][0.146,0.165]0.157
E5[2.583,3.417][5.583,6.417][0.020,0.020]0.020
E6[3.292,5.792][3.458,7.375][0.050,0.050]0.051
E7[1,1][9,9][0.278,0.278]0.281
E8[9,9][1,1][0.016,0.016]0.016
Table 8. Initial evaluation matrix of the electric forklift PSS concept (taking the CS1 as an example).
Table 8. Initial evaluation matrix of the electric forklift PSS concept (taking the CS1 as an example).
(a) Scheme Value Assessment of Criteria in the CV Objective
Evaluation CriteriaEvaluation Value Assigned by Four DMs
DM1DM2DM3DM4
P1 6 6 2 8
P2 6 3 4 3
P3 6 7 4 5
P4 4 4 3 3
P5 5 6 4 6
P6 5 8 4 6
P7 5 7 4 4
P8 6 8 6 4
P9 6 5 6 6
P10 6 4 4 8
(b) Scheme Value Assessment of Criteria in the Economic Objective
Evaluation CriteriaEvaluation Value Assigned by Four DMs
DM1DM2DM3DM4
E1 (t)1.751.801.501.75
E2 (km/h)13131613
E3 (mm)3500400040003000
E4 (kw)4664
E5 (¥)14,400960012,00012,500
E6 6 2 5 2
E7 6 7 7 6
E8 (t)3.753.53.53.5
Table 9. Comprehensive weight of evaluation criteria with respect to CV and economic.
Table 9. Comprehensive weight of evaluation criteria with respect to CV and economic.
CV CriteriaewjwjcwjEconomic Criteriaewjwjcwj
P10.1080.2660.287E10.1540.0590.097
P20.2700.0920.249E20.0860.1880.172
P30.0420.1240.052E30.0690.2280.167
P40.1060.0550.058E40.1800.1570.301
P50.0450.0230.010E50.0920.0200.020
P60.0560.0880.049E60.2620.0510.142
P70.0790.0620.049E70.0260.2810.078
P80.0660.1000.066E80.1320.0160.023
P90.0240.1180.028
P100.2050.0730.150
Table 10. Game utility matrix of warehouse logistics system under each strategy combination.
Table 10. Game utility matrix of warehouse logistics system under each strategy combination.
Game UtilityConceptual Scheme
CS1CS2CS3CS4CS5CS6
UP(SP, SE)0.9460.9011.0270.9461.0701.110
UE(SP, SE)1.0041.0430.9880.9591.0290.977
Table 11. The sorting results of the scheme under different α values.
Table 11. The sorting results of the scheme under different α values.
α valueSorting ResultsThe Optimal Scheme(UP, UE)(φP(v), φE(v))
α = 0CS4 > CS1 > CS2 > CS3 > CS5 > CS6CS4(0.898,0.940)(0.895,0.944)
α = 0.1CS4 > CS1 > CS2 > CS3 > CS5 > CS6CS4(0.910,0.945)(0.902,0.953)
α = 0.3CS4 > CS1 > CS2 > CS3 > CS5 > CS6CS4(0.930,0.952)(0.914,0.968)
α = 0.5CS1 > CS4 > CS2 > CS3 > CS5 > CS6CS1(0.946,1.004)(0.923,0.982)
α = 0.7CS1 > CS4 > CS2 > CS3 > CS5 > CS6CS1(0.953,1.001)(0.931,0.994)
α = 0.9CS1 > CS4 > CS2 > CS3 > CS5 > CS6CS1(0.958,0.998)(0.938,1.004)
α = 1CS1 > CS4 > CS2 > CS3 > CS5 > CS6CS1(0.961,0.997)(0.941,1.009)
Table 12. Positive and negative ideal reference vectors of the utility.
Table 12. Positive and negative ideal reference vectors of the utility.
Utility ReferenceUtility Function Uc(SE, ST)
UPUEUPUEUPUEUPUEUPUE
(WP, WE) = (0.1, 0.9)(WP, WE) = (0.3, 0.7)(WP, WE) = (0.5, 0.5)(WP, WE) = (0.7, 0.3)(WP, WE) = (0.9, 0.1)
WUc*0.1110.9390.3330.7300.5550.5220.7770.3130.9990.104
WUc00.0900.8630.2700.6710.4500.4800.6300.2880.8110.096
Table 13. The optimal scheme for two decision methods.
Table 13. The optimal scheme for two decision methods.
Decision MethodOptimal SchemeGame Utility
UE(SE, ST)UT(SE, ST)
Rough TOPSIS-1 (WP,WE) = (0.1,0.9)CS51.0701.029
Rough TOPSIS-2 (WP,WE) = (0.3,0.7)CS51.0701.029
Rough TOPSIS-3 (WP,WE) = (0.5,0.5)CS51.0701.029
Rough TOPSIS-4 (WP,WE) = (0.7,0.3)CS61.1100.977
Rough TOPSIS-5 (WP,WE) = (0.9,0.1)CS61.1100.977
Weighted Shapley value methodCS109461.004
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Share and Cite

MDPI and ACS Style

Feng, D.; Fu, X.; Jiang, S.; Jing, L. Conceptual Solution Decision Based on Rough Sets and Shapley Value for Product-Service System: Customer Value-Economic Objective Trade-Off Perspective. Appl. Sci. 2021, 11, 11001. https://doi.org/10.3390/app112211001

AMA Style

Feng D, Fu X, Jiang S, Jing L. Conceptual Solution Decision Based on Rough Sets and Shapley Value for Product-Service System: Customer Value-Economic Objective Trade-Off Perspective. Applied Sciences. 2021; 11(22):11001. https://doi.org/10.3390/app112211001

Chicago/Turabian Style

Feng, Di, Xiaoyun Fu, Shaofei Jiang, and Liting Jing. 2021. "Conceptual Solution Decision Based on Rough Sets and Shapley Value for Product-Service System: Customer Value-Economic Objective Trade-Off Perspective" Applied Sciences 11, no. 22: 11001. https://doi.org/10.3390/app112211001

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop