Next Article in Journal
A Data-Driven Approach to Forecasting Heating and Cooling Energy Demand in an Office Building as an Alternative to Multi-Zone Dynamic Simulation
Next Article in Special Issue
Methodological and On-Site Applied Construction Layout Plan with Batter Boards Stake-Out Methods Comparison: A Case Study of Romania
Previous Article in Journal
Understanding the Origin and Mixing of Deep Fluids in Shallow Aquifers and Possible Implications for Crustal Deformation Studies: San Vittorino Plain, Central Apennines
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Monitoring of Time and Cost Variances of Schedule Using Simple Earned Value Method Indicators

Department of Civil Engineering and Construction Processes, Faculty of Civil Engineering and Architecture, Opole University of Technology, 45-063 Opole, Poland
*
Authors to whom correspondence should be addressed.
Appl. Sci. 2021, 11(4), 1357; https://doi.org/10.3390/app11041357
Submission received: 23 December 2020 / Revised: 24 January 2021 / Accepted: 28 January 2021 / Published: 3 February 2021

Abstract

The Planning and implementation of construction projects are difficult processes and are burdened with many risk elements. The budget spread over time, which is developed on the basis of the schedule, presents the expected distribution of costs throughout the duration of the works, which during the implementation of the project is subject to constant changes resulting from time, cost, and organizational factors. Managing construction contracts requires managers to be able to analyze on an ongoing basis the variances of production costs-from the values calculated in the offer cost estimate and assumed in the Budgeted Cost of Work Scheduled. The article attempts to analyze the emerging time and cost deviations using proprietary time variances from the schedule (T/S) and variances from planned costs (T/C) monitoring, based on simple indicators of the earned value method (EVM). An example of construction of a multi-family housing development was used to study the variances of planned and incurred costs.
Keywords: earned value method—EVM; time variances; cost variances; schedule earned value method—EVM; time variances; cost variances; schedule

Share and Cite

MDPI and ACS Style

Przywara, D.; Rak, A. Monitoring of Time and Cost Variances of Schedule Using Simple Earned Value Method Indicators. Appl. Sci. 2021, 11, 1357. https://doi.org/10.3390/app11041357

AMA Style

Przywara D, Rak A. Monitoring of Time and Cost Variances of Schedule Using Simple Earned Value Method Indicators. Applied Sciences. 2021; 11(4):1357. https://doi.org/10.3390/app11041357

Chicago/Turabian Style

Przywara, Daniel, and Adam Rak. 2021. "Monitoring of Time and Cost Variances of Schedule Using Simple Earned Value Method Indicators" Applied Sciences 11, no. 4: 1357. https://doi.org/10.3390/app11041357

APA Style

Przywara, D., & Rak, A. (2021). Monitoring of Time and Cost Variances of Schedule Using Simple Earned Value Method Indicators. Applied Sciences, 11(4), 1357. https://doi.org/10.3390/app11041357

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop