2.3.1. Deformation of the Foundation Pit Retaining Structure
It can be seen from the time-history curve shown in
Figure 5 of the vertical displacement of the retaining pile top at typical positions ZTC-5, ZTC-9, ZTC-16 and ZTC-20 measuring points that the vertical displacement of the retaining pile top presents a floating trend in the excavation stage of the foundation pit. The main reason is that the foundation pit soil excavation is unloaded, and the bottom of the pit soil is uplifted and causes the pile to float. The maximum vertical displacement of the pile top of the retaining pile occurs at measuring point ZQC-16 (i.e., the position far from the station side), and the maximum vertical displacement is 2.1 mm. In the pouring stage of the bottom slab, the top of the retaining pile shows an obvious subsidence trend, mainly because the pouring of the bottom slab concrete is equivalent to the application of the load to inhibit the uplift of the foundation pit bottom, resulting in the downward settlement trend of the retaining pile.
The measured horizontal displacement data of the four direction measuring points ZQS-3, ZQS-7, ZQS-17 and ZQS-20 of the retaining pile are selected for analysis, as shown in
Figure 6. During the excavation and construction of the foundation pit in each stage, the horizontal deformation trend of the retaining pile top is toward the inner side of the foundation pit (the value toward the inner side of the foundation pit is positive, and the value toward the outer side of the foundation pit is negative), and it shows a continuous rise. The maximum horizontal displacement of the retaining pile top occurs at the ZQS-3 measuring point, which is 6.2 mm. In the floor pouring stage, the horizontal displacement of the retaining pile top has a sudden decrease trend, and the maximum change value reaches 3.5 mm. Horizontal displacement deformation gradually converges, which inhibits the drift of the retaining structure to the inside of the pit.
To further obtain the horizontal deformation law of the retaining pile in deep foundation pit excavation construction, the horizontal displacement monitoring data of the retaining pile at each time point of ZQT-4, ZQT-9, ZQT-15 and ZQT-21 in four directions and four measuring points in the southeast and northwest of the retaining pile are analyzed, as shown in
Figure 7. The deformation trend of each retaining pile measuring point position at different excavation time nodes is large in the middle and small at both ends. With the passage of time, the maximum horizontal deformation position of the retaining pile gradually moves downward along the pile body.
Comparing the pile displacement of the four measuring points at different construction times, it can be seen that the horizontal deformation of the ZQT-9 retaining pile on the south side of the foundation pit is slightly smaller than that on the north side of the ZQT-21 measuring point. The main reason is that the excavation interface of the north side of the foundation pit is large, and the contact surface between the retaining pile and the lateral active earth pressure is large during the excavation of the foundation pit, resulting in large deformation of the retaining pile on the north side. The retaining pile at measuring point ZQT-4 on the west side of the foundation pit is close to the side of the subway station, and the pile deformation is slightly smaller than that at measuring point ZQT-15 on the east side of the foundation pit. The main reason for the deformation of retaining piles is that the stiffness of subway station structure is large, and the disturbance of station structure caused by foundation pit excavation is far less than that of the stratum.
2.3.2. Deformation of the Main Body and Subsidiary Structure of the Station
(1) Deformation of the main station structure
The deformation of each measuring point of the main structure of the subway station at different construction nodes is shown in
Figure 8. During the excavation of the foundation pit from October 2018 to February 2019, the vertical deformation of adjacent subway stations was small. The main reason is that the influence of retaining pile construction and shallow soil excavation on adjacent stations is small in the early stage of foundation pit construction. During the construction period from February 2019 to May 2019, the vertical deformation of the station structure was large, and the excavation of the foundation pit had a great influence on the central position of the main structure of the station. The overall deformation trend of the station is large in the middle and small in the end. The maximum vertical deformation of the main structure of the station occurs at measuring point ZDH-7, i.e., the central position of the station. This deformation trend is consistent with the deformation trend of the numerical simulation. The maximum vertical deformation of the station is 1.43 mm.
To study the vertical deformation law of the main structure of the station in the process of foundation pit construction, the time-history data of the station vertical deformation monitoring points ZDH-3, ZDH-6 and ZDH-11 are selected for analysis, as shown in
Figure 9.
According to
Figure 9, during the construction of foundation pit retaining piles and temporary columns, the station has a slight subsidence trend. The deformation of the vertical displacement of the main structure of the station in the excavation stage is divided into three parts:
(a) When the excavation depth of the foundation pit is 3.5 and 9.5 m in excavation stages 1 and 2, respectively, the deformation of the station remains stable, and there is a slight downward trend. The soil outside the foundation pit should be squeezed inward due to the excavation and unloading of the foundation pit soil, but the soil outside the pit is squeezed due to interbracing, resulting in a slight downward movement of the vertical deformation of the station structure.
(b) In the third stage of excavation, i.e., the excavation depth from 9.5 to 14.5 m, the vertical displacement deformation of the station began to increase considerably. With the increasing excavation depth of the foundation pit, the retaining piles of the foundation pit are more exposed inside the foundation pit, while the active earth pressure outside the pit increases, and the supporting effect of interbracing weakens. The soil outside the foundation pit has an inward inclination trend, and the station has an upward displacement trend.
(c) During excavation stages 4 and 5, the vertical deformation of the station has a clear upward trend; that is, when the excavation depth of the foundation pit is greater than 14.5 m, the excavation depth of the foundation pit further increases, and the vertical deformation of the station is more pronounced.
In the stage of bottom slab pouring and structure construction, the station structure generally presents a floating trend, in which the bottom slab pouring stage fluctuates and sinks, and the maximum vertical deformation of the main structure of the station is 1.29 mm.
To study the horizontal deformation law of the main structure of the station during foundation pit construction, the time-history data of the horizontal displacement monitoring points CZH-2, CZH-5 and CZH-8 of the main structure of the station are selected for analysis, as shown in
Figure 10. The horizontal displacement of the main structure of the station shifts to the inside of the foundation pit at all stages of excavation and gradually increases. The maximum horizontal displacement deformation of the main structure of the station is 1.7 mm. Compared with the vertical displacement, the maximum horizontal displacement of the main structure of the station is 1.3 times its maximum vertical displacement. In the construction of foundation pit excavation, the horizontal displacement of the station is more sensitive than its vertical displacement. The foundation pit retaining pile plays a great role in the deformation isolation of the station. In the construction, the measurement frequency of the horizontal displacement of the station should be strengthened.
(2) Structural deformation of the entrance and exit
To obtain the vertical deformation law of the entrance and exit structure in the foundation pit construction process, the time-history data of the vertical monitoring points C-4, C-5, C-8 and C-9 at the entrance and exit are selected for analysis, as shown in
Figure 11. The vertical displacement of the entrance and exit structures has a slight downward trend in the construction stage of the foundation pit retaining structure. In the excavation stage of the foundation pit, the phenomenon of subsidence and then floating is presented, which is opposite to the deformation of the main structure of the station. The main reason is that the entrance and exit structure is close to the foundation pit and is in the position of the surface settlement trough. In the process of excavation and unloading of the foundation pit, the soil near the foundation pit is squeezed to produce downward displacement, which drives the entrance and exit structure to move downward. The cumulative deformation value of the vertical displacement of the entrance and exit in the excavation stage is 1.7 mm. In the stage of floor pouring and structure construction, the structural deformation of the entrance and exit has an obvious downward trend, and the maximum displacement reaches 2.9 mm. More attention should be given to the monitoring and measurement of the vertical deformation of the entrance and exit in the construction process.
The measured data of CH-1, CH-2, CH-3 and CH-4 at the horizontal deformation monitoring points at the entrance and exit are selected for analysis, as shown in
Figure 12. The horizontal displacement deformation trend of the entrance and exit gradually increases, which is consistent with the horizontal displacement deformation trend of the station, but the growth rate is more obvious than that of the station. The maximum horizontal displacement is 2.8 mm, which is 1.7 times the maximum horizontal displacement of the station. The horizontal displacement trend of each measuring point is biased toward the inside of the foundation pit.
2.3.3. Deformation of the Track Structure
To ensure the normal operation of subway vehicles, real-time follow-up displacement monitoring of station track structures is carried out in the process of foundation pit construction. The measured vertical displacement data of the right track structure at each measuring point at different construction time nodes are analyzed, as shown in
Figure 13. During the construction period from October 2018 to February 2019, the deformation of the track lines was small, and there was a downward trend. During the subsequent construction period, the deformation of the track line considerably increased, and the overall deformation of the line showed a trend of small deformation at both ends and large deformation in the middle, which was consistent with the deformation trend of the station. The maximum cumulative vertical displacement of the track structure was 1.24 mm.
The time-history displacement data of the right track measuring points YGD-4, YGD-7 and YGD-12 are analyzed, as shown in
Figure 14. The right track has a stable subsidence trend in the construction stage of the foundation pit retaining structure, and the subsidence error of each measuring point is small. When the vertical displacement of the track is in excavation stages 1 and 2, that is, the excavation depth of the foundation pit is 3.5 and 6.5 m, the vertical displacement of the track maintains a stable downward trend. In excavation stages 4 and 5, when the excavation depth is less than 14.5 m, the vertical displacement of the track has an obvious upward trend. In the pouring stage of the bottom slab, the cumulative displacement increases first and then decreases, and the vertical deformation of the right track is consistent with the deformation trend of the station measuring point.
Figure 15 shows that the horizontal displacement of the right track continues to increase at all stages of foundation pit excavation construction, and the horizontal displacement deformation trend of each measuring point shifts to the pit. The maximum horizontal displacement of the track is 1.4 mm.
In the process of foundation pit excavation, by extracting the vertical displacement data of the left and right tracks and subtracting the left and right rail data, the horizontal time-history changes of the left and right rails are obtained. As shown in
Figure 16 and
Figure 17, the horizontal deviation of the right rail is between −0.8 and 0.6 mm, and the maximum deviation occurs in the fourth excavation stage of the foundation pit (that is, the excavation depth is 20.5 m), which is located at the position of the YGD-8 measuring point (that is, the middle of the right rail). The horizontal deviation of the left rail is −0.4 to 0.6 mm, and the maximum horizontal deviation occurs in the fifth excavation stage of the foundation pit (that is, the excavation depth of the foundation pit is 25.5 m), which is located at the ZGD-4 measuring point (that is, the middle of the left rail).
Through the analysis of the manual monitoring data of the track distance of the left and right lines, the maximum deviation value of the track distance in the construction process is +2 mm, less than the deformation control requirements, which meets the allowable deformation control requirements of the track geometry. In the process of foundation pit construction, the deformation control of the track structure is better, and the safe operation of subway trains is not affected in the process of foundation pit construction.